JPH04161617A - Underground external wall - Google Patents

Underground external wall

Info

Publication number
JPH04161617A
JPH04161617A JP2287348A JP28734890A JPH04161617A JP H04161617 A JPH04161617 A JP H04161617A JP 2287348 A JP2287348 A JP 2287348A JP 28734890 A JP28734890 A JP 28734890A JP H04161617 A JPH04161617 A JP H04161617A
Authority
JP
Japan
Prior art keywords
wall
underground
concrete
shaped steel
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2287348A
Other languages
Japanese (ja)
Inventor
Yoshihiro Fujita
佳広 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2287348A priority Critical patent/JPH04161617A/en
Publication of JPH04161617A publication Critical patent/JPH04161617A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To economically form an underground external wall by providing shear connectors in a soil column piles and integrating a reinforcing concrete wall with a sheath wall. CONSTITUTION:First of all, cement slurry is poured while digging the underground to be mixed with dug sediment. Before they are hardened, an H-shaped steel is built in and stabilized after their hardening. In the next step, the ground within the lot is dug, and in the half way or after the digging, a soil part, which becomes an external form along the back face of the inner side flange 2 of the H-shaped steel, is cut, and an L shaped stud bolt 3 is welded and fixed on the surface of the flange 2. In the next step, the reinforcing bars 5 and inner form of the sheath wall 4 are assembled, and concrete is placed in the underground beam, and concrete is placed while integrating the sheath wall 4 with the H-shaped steel.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、仮設山留壁を本設に組み込んだ地下外壁に関
する。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to an underground external wall in which a temporary retaining wall is permanently installed.

(従来の技術) 従来のソイル柱列杭は、仮設の山留壁として使用してお
り、本設に組み込むことはなかった。
(Conventional technology) Conventional soil column piles were used as temporary retaining walls and were not incorporated into permanent construction.

フィル柱列杭は、地中に穴を掘りながらセメントスラリ
ーを注入し、掘削土砂と混合し、この土砂が硬化する前
にH形鋼や鋼管等を建込んで杭としたものである。
Fill column piles are made by injecting cement slurry into the ground while digging a hole, mixing it with the excavated soil, and before the soil hardens, H-beams, steel pipes, etc. are erected to form the pile.

(発明が解決しようとする課題) 叙述ソイル柱列杭は仮設の山留壁として利用するたけて
あった。
(Problems to be Solved by the Invention) The prescriptive soil column piles were intended to be used as temporary retaining walls.

山留費用も工事費の中で比較的高額な値を占めることが
多く、また本設の地下外壁は必要な土庄を受ける壁とし
て設計するため、重複して土圧を受ける壁を2種類構築
することとなっていた。
Mountain retaining costs often account for a relatively high amount of construction costs, and since the main underground outer wall is designed to receive the necessary soil support, two types of walls were constructed to receive redundant earth pressure. It was supposed to be done.

本発明は上記事情に鑑みてなされたものであって、その
目的はソイル柱列杭を効率よく利用した経済的な地下外
壁を提供することにある。
The present invention has been made in view of the above circumstances, and its purpose is to provide an economical underground exterior wall that efficiently utilizes soil columns and piles.

(課題を解決するための手段) 上記目的を達成するために本発明の地下外壁は、フィル
柱列杭にシャーコネクタを設け、鉄筋コンクリート壁と
一体化して本設の土留壁を構成することを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the underground external wall of the present invention is characterized in that shear connectors are provided on the fill column row piles and integrated with the reinforced concrete wall to constitute a permanent earth retaining wall. shall be.

(作 用) 柱列杭に設けたシャーコネクタを介して鉄筋コンクリー
ト壁と柱列杭とを一体に構成して、本設の土留壁(地下
外壁)を構成する。
(Function) The reinforced concrete wall and the column piles are integrated via shear connectors installed on the column piles to form the permanent earth retaining wall (underground outer wall).

この土留壁はソイル柱列杭と鉄筋コンクリート璧との合
成壁になる。
This earth retaining wall will be a composite wall of soil column piles and reinforced concrete walls.

合成土留壁に作用する土圧はシャーコネクタに引張りと
剪断を生じさせるように働く。したがって、ソイル柱列
杭は常に土庄による曲げに抵抗するように作用している
Earth pressure acting on the composite earth retaining wall acts to create tension and shear on the shear connector. Therefore, the soil column piles always act to resist bending due to the tonosho.

このように構成した合成土留壁をそのまま本設地下外壁
として使用する。
The synthetic earth retaining wall constructed in this way will be used as it is as the permanent underground outer wall.

(実 施 例) 以下、本発明の好適な実施例について図面を参照にして
詳細に説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

本実施例は基本的には、フィル柱列杭にシャーコネクタ
を設け、鉄筋コンクリート壁と一体化して本設の土留壁
が構成される。ソイル柱列杭としては、H形鋼や鋼管等
が使用される。またシャーコネクタとしては、L形等の
スタッドボルト、コ字状等に折曲された鉄筋1丁字形状
の鉄板(CT材)等が用いられる。さらにシャーコネク
タの配置密度は、土圧応力によって決定されるとともに
、H形鋼や鋼管は、錆の発生を断面欠損として考慮して
成る。
Basically, in this embodiment, shear connectors are provided on the fill column piles and integrated with the reinforced concrete wall to form the permanent earth retaining wall. H-beam steel, steel pipes, etc. are used as soil column piles. Further, as the shear connector, an L-shaped stud bolt or the like, a steel plate (CT material) in the shape of a single reinforcing bar bent in a U-shape, etc. are used. Furthermore, the arrangement density of shear connectors is determined by earth pressure stress, and H-shaped steel and steel pipes are constructed by taking into account the occurrence of rust as a cross-sectional defect.

第1図は、先ずソイル柱列杭を説明するもので、地中に
穴を掘りながらセメントスラリーを注入し、掘削土砂と
セメントスラリーを混合する。
Fig. 1 first explains soil column piles, in which cement slurry is injected while digging a hole in the ground, and the excavated earth and sand are mixed with the cement slurry.

次に、セメントスラリーと掘削土砂か硬化しないうちに
H形鋼1を建込む。セメントスラリーが硬化して建込ん
だH形鋼1は安定する。
Next, the H-beam 1 is erected before the cement slurry and excavated soil harden. The cement slurry hardens and the built H-beam 1 becomes stable.

その後、敷地内を掘削し、必要によっては切梁を架ける
か、掘削途中で、又は掘削後にH形鋼1の内側のフラン
ジ2背面に沿って外型枠となるフィル部分を切削する。
Thereafter, the site is excavated, and if necessary, a strut is installed, or a fill portion that will become the outer formwork is cut along the back surface of the flange 2 inside the H-section steel 1 during or after the excavation.

併せてフランジ2の表面にL形のスタッドボルト3を溶
接固定する。
At the same time, an L-shaped stud bolt 3 is welded and fixed to the surface of the flange 2.

掘削終了後、スタッドボルト3のほか土留壁4の鉄筋5
および内型枠を組み、地中梁のコンクリートを打設し、
土留壁4もH形鋼1と合成しながらそのコンクリートを
打ち込み構築している。
After the excavation is completed, in addition to the stud bolts 3, the reinforcing bars 5 of the retaining wall 4 are
erected the inner formwork and poured concrete for the underground beams,
The earth retaining wall 4 is also constructed by pouring concrete while combining it with the H-shaped steel 1.

脱型後、第2図に示すようにH形鋼1との合成による土
留壁4が完成する。
After demolding, the earth retaining wall 4 is completed by combining with the H-section steel 1 as shown in FIG.

この土留壁4を本設地下外壁として使用するものである
This earth retaining wall 4 is used as a permanent underground outer wall.

スタッドボルト3はL型の異形棒鋼スタッドで、横向き
溶接のため、D16以下を使用し、土留壁4のコンクリ
ート壁厚は200關程度である。
The stud bolt 3 is an L-shaped deformed steel bar stud, and because it is horizontally welded, D16 or less is used, and the concrete wall thickness of the earth retaining wall 4 is about 200 mm.

また、H形鋼1についても湿潤状態の中におかれるので
、錆の発生を断面欠損として考慮する必要があり、更に
仮設杭を前提とするH形鋼ではなく、本設の地下外壁用
H形鋼として新材を使用する。
In addition, since the H-beam 1 is also placed in a wet condition, it is necessary to consider the occurrence of rust as a cross-sectional loss. Use new material as the shape steel.

スタッドボルト3の使用本数、すなわち配置密度はスタ
ッドボルトをL形とし、引張りによるコンクリートのコ
ーン破壊を防止している。
The number of stud bolts 3 used, that is, the arrangement density, is such that the stud bolts are L-shaped to prevent cone breakage of concrete due to tension.

土留壁4は一般の合成梁と異なり、荷重方向が反対にな
るため、コンクリートとH形鋼との緊結材であるスタッ
ドに引張り剪断を生じさせる。
The earth retaining wall 4 is different from a general composite beam in that the load direction is opposite, so that tensile shear is generated in the stud, which is a binding material between the concrete and the H-section steel.

それ故に、スタッド本数は合成梁の規準とは別に土圧応
力を基にして決定している。
Therefore, the number of studs is determined based on the earth pressure stress, in addition to the standards for composite beams.

(効 果) 以上詳細に説明したように、本発明の地下外壁によれば
、ソイル柱列杭と鉄筋コンクリート壁との合成による土
留壁を形成するので、壁が二重にならず、また杭による
土圧への抵抗を得て壁厚や鉄筋径を小さくできる。
(Effects) As explained in detail above, according to the underground external wall of the present invention, the soil retaining wall is formed by combining the soil column piles and the reinforced concrete wall, so the wall does not become double, and By providing resistance to earth pressure, wall thickness and reinforcing bar diameter can be reduced.

この事は工期を短縮し、使用敷地の有効面積を狭くする
ことなく、経済面でも極めて有用である。
This shortens the construction period and does not reduce the effective area of the site, which is extremely useful from an economic standpoint.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の好適実施例を示す斜視図、第2図はそ
の平面図である。 1・・・フィル柱列杭(H形鋼) 2・・・フランジ
FIG. 1 is a perspective view showing a preferred embodiment of the present invention, and FIG. 2 is a plan view thereof. 1... Fill column pile (H-shaped steel) 2... Flange

Claims (1)

【特許請求の範囲】[Claims] ソイル柱列杭にシャーコネクタを設け、鉄筋コンクリー
ト壁と一体化して本設の土留壁を構成することを特徴と
する地下外壁。
An underground exterior wall characterized by installing shear connectors on soil column piles and integrating them with a reinforced concrete wall to form a permanent earth retaining wall.
JP2287348A 1990-10-26 1990-10-26 Underground external wall Pending JPH04161617A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2287348A JPH04161617A (en) 1990-10-26 1990-10-26 Underground external wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2287348A JPH04161617A (en) 1990-10-26 1990-10-26 Underground external wall

Publications (1)

Publication Number Publication Date
JPH04161617A true JPH04161617A (en) 1992-06-05

Family

ID=17716207

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2287348A Pending JPH04161617A (en) 1990-10-26 1990-10-26 Underground external wall

Country Status (1)

Country Link
JP (1) JPH04161617A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199909A (en) * 2015-04-09 2016-12-01 株式会社 南組 Raising structure, and molding method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5829922A (en) * 1981-08-14 1983-02-22 Takenaka Komuten Co Ltd Constructing method for underground outer wall

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5829922A (en) * 1981-08-14 1983-02-22 Takenaka Komuten Co Ltd Constructing method for underground outer wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199909A (en) * 2015-04-09 2016-12-01 株式会社 南組 Raising structure, and molding method thereof

Similar Documents

Publication Publication Date Title
JP2007154413A (en) Soldier pile type earth retaining anchor type retaining wall and its construction method
JP2000265484A (en) CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
JP2000352296A (en) Method o constructing passage just under underground structure
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
KR102277470B1 (en) Basement Composite Wall Using Retaing Wall And Method for Constructing the Same
KR20080059951A (en) Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor
JPH04161617A (en) Underground external wall
JP2605479B2 (en) Structure with eccentricity measures
JPS63280153A (en) Underground inverted lining method
JP3063673B2 (en) Foundation structure of building with soil cement pillar row retaining wall tied to frame
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JP2907807B1 (en) Tunnel construction method
JPS61102911A (en) Steel cell
JPS6286242A (en) Reverse casting consttructin method
KR20030085264A (en) soil sheathing method of rahmaen frame using prestress support and bracket and bracket thereof
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JPH04185816A (en) Construction of beam in underground wall
KR101650312B1 (en) Concrete retaining wall and method for manufacturing the same
JPH11181807A (en) Construction method for underground story
JP3232487B2 (en) Construction method of column base and column base structure
JP2002115324A (en) Column base unit, column integrated column base fixing foundation structure using the column base unit, and construction method therefor
JPS62129420A (en) Reinforcing method for tank foundation ground
KR20230052741A (en) Precast inner mould and precast structure using the same
JPH05118047A (en) Constructing method for foundation structure
JPH11172689A (en) Anchoring method of leg section of steel-framed column