JPH04153415A - Earth carrying out device in pneumatic caisson method - Google Patents

Earth carrying out device in pneumatic caisson method

Info

Publication number
JPH04153415A
JPH04153415A JP27866290A JP27866290A JPH04153415A JP H04153415 A JPH04153415 A JP H04153415A JP 27866290 A JP27866290 A JP 27866290A JP 27866290 A JP27866290 A JP 27866290A JP H04153415 A JPH04153415 A JP H04153415A
Authority
JP
Japan
Prior art keywords
earth
sand
bucket
carrying
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27866290A
Other languages
Japanese (ja)
Other versions
JPH068541B2 (en
Inventor
Yoshitake Sawa
澤 祥剛
Takeshi Yoshioka
武 吉岡
Masafumi Kiyama
木山 雅文
Kazuo Ando
一男 安藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OOMOTOGUMI KK
Original Assignee
OOMOTOGUMI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OOMOTOGUMI KK filed Critical OOMOTOGUMI KK
Priority to JP27866290A priority Critical patent/JPH068541B2/en
Publication of JPH04153415A publication Critical patent/JPH04153415A/en
Publication of JPH068541B2 publication Critical patent/JPH068541B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To promote carrying-out efficiency by loading an empty earth carrying-out bucket suspended and brought in a workshop on a running truck, moving it horizontally right under earth reloading bucket stood by in a riser, opening bottom covers to load earth, and carrying out it to the ground. CONSTITUTION:An earth reloading bucket 27 unloaded by opening bottom covers 28 and 28' with a hinge is suspended to a specific position by a lifting device 21 provided to the upper part of a hollow and cylindrical riser 18 connected to a workshop 9. After that, an earth carrying-out bucket 14 is hung on a rail 14 fixed to the lower surface of a ceiling slab 10 of the workshop 9, it is loaded on a running truck 44 capable of moving horizontally, and it is horizontally moved right under the earth reloading bucket 27 suspended to a specific position in a riser 18 to stop. A suspended chain 26 of the lifting device 21 is drawn out to open the bottom covers 28 and 28' of the reloading bucket 27, earth is reloading to the carrying-out bucket 14 to move the running truck 44, and it is carried out to the ground through the riser 13 and a lock device 12.

Description

【発明の詳細な説明】[Detailed description of the invention]

〈産業上の利用分野〉 この発明は、ニューマチックケーソン工法における掘削
土砂の(煎出装置に関するものである。 〈従来の技術と技術課題〉 従来、ニューマチックケーソン工法における掘削土砂の
搬出は第5図に示すように、掘削機(図示しない)によ
り掘削された土砂を土砂搬出用バケツlに積込み、この
土砂搬出用バケツ1を、作業室2と外部とをに部に設け
られたロック装置3を介して連通ずる中空円筒状の立管
4内を、クレーン等により垂直方向に吊り」二げること
により、掘削土砂を大気中に搬出していた。 この時、1個のバケツにより土砂を搬出したのでは掘削
機による土砂積込みに時間を要し、土砂の1般出能率が
悪いため、2個の土砂搬出用バケツ1.1゛ を用い、
一方の土砂搬出用バケツ1が立管4内を通って吊り上げ
られ、大気中に土砂が搬出され、空になった土砂搬出用
バケッ1が再びロンク装置3、立管4内を通って作業室
2内に戻ってくる間、他方の土砂搬出用バケッ1゛には
、作業室2内において掘削機により土砂を積込み、掘削
土砂の積み込み、搬出作業を2個のバヶッ1.1゛を用
いて交互に行うことにより、掘削土砂の1般出能率を増
大するようにしている。 しかしながら、2個のバケッ1.1“を用いる場合、作
業室2内に作業員5を配置して、人力にて土砂(般出用
バケツの吊り」二げ用のワイヤーロープ6を付は替えな
ければならず、潜函本体7の沈設深度が深くなるにした
がって、作業室2内の気圧も高くなるため、作業員5の
作業室2内における作業時間を短縮させなければならず
、作業能率が低下する欠点があった。 この発明は前記の欠点を解消し、掘削土砂の搬出能率が
高く、作業室内に作業員を配置することなく、掘削土砂
を搬出する装置を提供することを目的とする。 く課題を解決するための手段〉 前記の従来技術が有していた技術課題を解決するため、
この発明のニューマヂノクケーソン工法における土砂搬
出装置は、 掘削機により掘削、積み込まれた土砂を蝶番付された底
蓋28.28′ を開くことにより放荷するようにした
土砂積替用バケッ27を、作業室9と連通し、」1端が
鏡板1Gによって閉塞された中空円筒状の立管18の上
部に取りつけられた揚重装置21により、立管18内の
所定の位置まで吊り上げて、バケツ支持部材40によっ
て土砂積替用バケツ27を支持させて待機させ、クレー
ン等により吊り上げられる土砂搬出用バヶッ14が、作
業室9の天井スラブ10の下面に固設されたレール41
に懸架され、走行装置43により水平移動ができるよう
にした走行台車44に装架されて、前記立管18内の所
定の位置まで吊り上げられたt砂積替用バケッ27の直
下まで水平移動して停止した後、揚重装置21の吊りチ
ェーン26を繰り出して土砂積替用バケッ27の蝶番付
された底蓋28.28゛を開くことにより、土砂を土砂
積替用バケッ27がら土砂搬出用バヶッ14に積み替え
て、走行台車44を水平移動し、土砂搬出用バケツ14
を立管13、ロック装置12を介して大気中に搬出する
ようにしたものである。 〈実施例〉 以下、この発明の一実施例を添イ;(図面に基づいて詳
細に説明する。 第1〜2図において、潜函本体8の作業室9の天井スラ
ブ10には開口部11が設けられ、作業室9と外部とを
上部に設はられたロック装置12を介して連通ずる中空
円筒状の立管13が、前記開口部11を覆うように気密
状態に載置されている。14は、作業室9より立管13
、ロック装Y?12を通って、クレーン(図示しない)
等により吊り上げられて掘削土砂を大気中に搬出する土
砂1般出用バケツである。 また、天井スラブ10には前記立管13と所定の距離を
隔てて開口部15が設けられ、この開口部15のL方に
は、−ヒ端が鏡板16によって閉塞され、下端に7ラン
ジ17が固着された中空円筒状の別の立管18が、開r
コ部15を覆うように、アンカーボルト1つによって、
気密状態に載置されている。 この立管18の上部には、支持梁20が取りつけられ、
この支持梁20には、例えばチェーンブロック等の揚重
装置21が取り付けられている。 この揚重装置21は、操作電源ケーブル22が立管18
の側壁を気密状態に貫通して、地上の運転制御室23ま
で延長され、運転制御室23に設置されたモニターテレ
ビ24に、立管18内に設置されたテレビカメラ25が
ら伝送される映像を見ながら、遠隔操作によって揚重装
置21の吊りチェーン26の巻き上げ、繰り出し方向の
運転ができるようにされている。 27は地上より遠隔操作によって運転される掘削機(図
示しない)により掘削された土砂を収容する土砂積替用
バケツで、第2図に示すように、その底蓋は半月状に分
割されており、半月状の底蓋28.28°は各々、土砂
積替用バヶッ27の側板29の下部に固着された蝶番3
o、30’ によって、開閉自在に取り付けられている
。 31は、逆円錐台状の開口部を有するボス32が固着さ
れた吊り手で、この吊り手31は、土砂積替用バケツ2
7の側板29の上部に固着されたブラケット33.33
 に、ピン34.34゛ を介して、揺動自在に取り付
けられている。 また、揚重装置21がら繰り出される土砂積替用バケツ
27の吊りチェーン26の垂下端には、前記吊り手3〕
に国賓されたボス32の開口部に、下方より貫入して前
記吊り手31に連結される円錐台状の吊り金物35が取
り付けられている。 36.36 は、土砂積替用バケッ27の底蓋28.2
8°の開閉用ロープで、その一端は底蓋28.28゛の
各々に固ン1されたブラケット3737 に連結さ1+
−1その他端は前記吊すチェン26の垂下端に取り付け
られた吊り金物35に連結されている。 この開閉用ロープ36.36゛は揚重装置21を作動し
て吊りチェーン26を巻き取り、吊り金物35が吊り手
31のボス32の開口部に貫入して吊り手31に連結さ
れたとき、土砂積替用バケソ27の底蓋28.28゛が
水平位置で停止する、即ち土砂積替用バケツ27の底蓋
28.28゛が閉じられた長さに調整する。 38は土砂積替用バケツ27の支持用シリンダで、その
ロッド39の先端には、バケツ支持部材40が取り付け
られている。 また、天井スラブ10の下面には、第3図に示すように
、一対の断面[型のレール41が、アンカーボルト42
により固定されている。このレル41には、走行装置4
3を備えた走行台車44が走行輪45を介して懸吊され
ている。 この走行台車44は、土砂搬出用バケッ14を装架でき
るようその中央部には、開口部46が設けられ、その上
面にはバケツ支持部材47が固着されている。 なお、この走行台車44は走行装置43より電源操作ケ
ーブル(図示しない)が、前記揚重装置2】と同様に、
地上の運転制御室23まで延長され、運転制御室23よ
り遠隔操作によって運転、停止ができるようにされてい
る。 〈作 用〉 り上のように構成されたこの発明の土砂搬出装置による
掘削土砂の搬出方法を以下に説明する。 [掘削土砂の積込み作業] まず、地上の運転制御室23より遠隔操作によって揚重
装置21をその吊りチェーン26の縁り出し方向へ運転
して、土砂積替用バケツ27を作業室9内の地盤48上
に位置させる。次に、作業室9内で地上より遠隔操作に
よって運転される掘削機(図示しない)により掘削され
た土砂を土砂積替用バケツ27に積み込む。 次に運転制御室23より遠隔操作によって、揚重装置2
]を吊りチェーン26の巻き上げ方向に運転し、土砂積
替用バケツ27が立管18内の所定の位置まで吊り上げ
られたとき、揚重装置21の運転を停止するとともに、
シリンダー38のロッド39を伸長し、ロンド39の先
端に取り付けられた支持部材40によって、土砂積替用
バヶッ27を支持し、土砂積替用バケツ27を立管18
内にて待機させる。 [掘削土砂の積替え作業] 次に、クレーン等により作業室9内に吊り降ろされた空
の土砂搬出用バケツ14を走行台車44に装架して、前
記、立管18内の所定の位置で待機する土砂積替用バケ
ツ27の直下まで水平移動させる。 次に、揚重装置21を吊りチェーン26の繰り出し方向
に運転させ、吊りチェーン26を繰り出していくことに
より、支持部材40によって支持された土砂積替用バケ
ツ27の蝶番性された底蓋28.28”は第2図に示す
水平位置から下方に回転し、収容された土砂は土砂積替
用バケッ27から放荷されて、土砂搬出用バケッ14に
移し替えられる。
<Industrial Application Field> This invention relates to an extraction device for excavated soil in the pneumatic caisson construction method. As shown in the figure, earth and sand excavated by an excavator (not shown) is loaded into an earth and sand transport bucket L, and this earth and sand transport bucket 1 is locked by a locking device 3 installed at the part between the work room 2 and the outside. The excavated soil was carried out into the atmosphere by vertically lifting the inside of the hollow cylindrical standpipe 4, which communicated through the pipe, with a crane or the like. If the soil was carried out, it would take time to load the soil with an excavator, and the efficiency of discharging the soil would be poor, so two 1.1-inch buckets were used to transport the soil.
One bucket 1 for carrying out the earth and sand is lifted up through the inside of the standpipe 4, the earth and sand is carried out into the atmosphere, and the empty bucket 1 for carrying out the earth and sand passes through the Ronku device 3 and the standpipe 4 again to the work room. 2, the other earth and sand carrying bucket 1 is loaded with earth and sand by an excavator in the work room 2, and the excavated earth and sand is loaded and carried out using two bags 1 and 1. By performing this alternately, the single discharge efficiency of excavated soil is increased. However, when using two buckets 1.1", a worker 5 is placed in the work room 2, and the wire rope 6 for lifting earth and sand (hanging the bucket for public use) is attached and changed manually. As the submersion depth of the submersible case body 7 becomes deeper, the atmospheric pressure inside the working chamber 2 also increases, so the working time of the worker 5 in the working chamber 2 must be shortened, which reduces work efficiency. The object of the present invention is to eliminate the above-mentioned drawbacks, provide a device that has high efficiency in transporting excavated soil, and can transport excavated soil without placing a worker in the work room. .Means for solving the above problems〉 In order to solve the technical problems of the above-mentioned conventional technology,
The earth and sand transporting device for the new Madinok caisson construction method of the present invention includes an earth and sand transfer bucket 27 in which earth and sand excavated and loaded by an excavator is released by opening a hinged bottom cover 28, 28'. is communicated with the work chamber 9 and lifted to a predetermined position within the standpipe 18 by a lifting device 21 attached to the top of the hollow cylindrical standpipe 18 whose one end is closed by the end plate 1G, An earth and sand transfer bucket 27 is supported by a bucket support member 40 and placed on standby, and an earth and sand transport bag 14 is lifted by a crane or the like, and is mounted on a rail 41 fixed to the lower surface of the ceiling slab 10 of the work room 9.
It is mounted on a traveling cart 44 which is suspended by a traveling device 43 and can be horizontally moved by a traveling device 43, and horizontally moved to directly below the T-sand transshipment bucket 27 which has been lifted to a predetermined position within the standpipe 18. After stopping, the lifting chain 26 of the lifting device 21 is let out and the hinged bottom cover 28.28 of the earth and sand transshipment bucket 27 is opened. Transfer to the bucket 14, move the traveling trolley 44 horizontally, and move the bucket 14 for carrying out the earth and sand.
is carried out into the atmosphere via a standpipe 13 and a lock device 12. <Example> Hereinafter, an example of the present invention will be described in detail based on the drawings. A hollow cylindrical standpipe 13, which communicates between the work chamber 9 and the outside via a locking device 12 installed at the top, is placed in an airtight state so as to cover the opening 11. 14 is a standpipe 13 from the work room 9
, Lock Sou Y? 12, a crane (not shown)
This is a bucket for general excavation of earth and sand that is lifted up by a crane and carried out into the atmosphere. Further, an opening 15 is provided in the ceiling slab 10 at a predetermined distance from the standpipe 13, and on the L side of the opening 15, the -H end is closed by a mirror plate 16, and the lower end has a 7-lunge 17. Another hollow cylindrical standpipe 18 to which the
With one anchor bolt so as to cover the part 15,
It is kept airtight. A support beam 20 is attached to the top of this standpipe 18,
A lifting device 21 such as a chain block is attached to the support beam 20, for example. This lifting device 21 has an operation power cable 22 connected to the standpipe 18.
It penetrates the side wall of the standpipe in an airtight state and extends to the operation control room 23 on the ground, and the video transmitted from the television camera 25 installed in the standpipe 18 is transmitted to the monitor television 24 installed in the operation control room 23. The hoisting chain 26 of the lifting device 21 can be operated in the hoisting and unwinding directions by remote control while watching. 27 is an earth and sand transfer bucket that stores earth and sand excavated by an excavator (not shown) operated by remote control from the ground, and as shown in Figure 2, its bottom cover is divided into half-moon shapes. , the half-moon-shaped bottom lids 28.28° each have a hinge 3 fixed to the lower part of the side plate 29 of the bag 27 for earth and sand transfer.
o, 30', it is attached so that it can be opened and closed. 31 is a hanging hand to which a boss 32 having an opening in the shape of an inverted truncated cone is fixed;
Bracket 33.33 fixed to the upper part of the side plate 29 of 7
It is swingably attached to via pins 34 and 34. Furthermore, the hanging hand 3 is attached to the hanging end of the hanging chain 26 of the earth and sand transshipment bucket 27 that is fed out from the lifting device 21.
A truncated conical hanging hardware 35 is attached to the opening of the boss 32, which was used as a state guest, to penetrate from below and to be connected to the hanging handle 31. 36.36 is the bottom cover 28.2 of the bucket 27 for earth and sand transfer.
An 8° opening/closing rope, one end of which is connected to a bracket 3737 fixed to each of the bottom lids 28.28.
-1 The other end is connected to a hanging hardware 35 attached to the hanging end of the hanging chain 26. This opening/closing rope 36.36'' operates the lifting device 21 to wind up the hanging chain 26, and when the hanging hardware 35 penetrates into the opening of the boss 32 of the hanging hand 31 and is connected to the hanging hand 31, The bottom cover 28.28' of the earth and sand transshipment bucket 27 stops at a horizontal position, that is, the bottom cover 28.28' of the earth and sand transshipment bucket 27 is adjusted to a closed length. 38 is a cylinder for supporting the earth and sand transshipment bucket 27, and a bucket support member 40 is attached to the tip of the rod 39. Further, on the lower surface of the ceiling slab 10, as shown in FIG.
Fixed by This rail 41 has a traveling device 4.
3 is suspended via running wheels 45. The traveling trolley 44 has an opening 46 in its center so that the bucket 14 for transporting earth and sand can be mounted thereon, and a bucket support member 47 is fixed to the upper surface of the opening 46. Note that this traveling trolley 44 has a power supply operation cable (not shown) connected to the traveling device 43, similarly to the lifting device 2].
It is extended to an operation control room 23 on the ground, and can be started and stopped by remote control from the operation control room 23. <Function> A method for transporting excavated earth and sand using the earth and sand transporting device of the present invention configured as above will be described below. [Loading work of excavated earth and sand] First, the lifting device 21 is operated by remote control from the operation control room 23 on the ground in the direction of the edge of the hanging chain 26, and the earth and sand transshipment bucket 27 is moved into the work room 9. It is located on the ground 48. Next, earth and sand excavated in the work room 9 by an excavator (not shown) operated by remote control from the ground is loaded into the earth and sand transfer bucket 27. Next, by remote control from the operation control room 23, the lifting device 2
] is operated in the hoisting direction of the lifting chain 26, and when the earth and sand transshipment bucket 27 is lifted to a predetermined position in the standpipe 18, the operation of the lifting device 21 is stopped, and
The rod 39 of the cylinder 38 is extended, the earth and sand transshipment bag 27 is supported by the support member 40 attached to the tip of the iron rod 39, and the earth and sand transshipment bucket 27 is moved to the standpipe 18.
Please wait inside. [Transshipment work of excavated earth and sand] Next, the empty earth and sand transport bucket 14, which has been lowered into the work chamber 9 by a crane or the like, is mounted on the traveling cart 44 and placed at a predetermined position in the standpipe 18. It is moved horizontally to just below the waiting earth and sand transshipment bucket 27. Next, by operating the lifting device 21 in the direction in which the hanging chain 26 is fed out, the hinged bottom cover 28 of the earth and sand transshipment bucket 27 supported by the support member 40 is moved. 28'' is rotated downward from the horizontal position shown in FIG. 2, and the stored earth and sand is released from the earth and sand transfer bucket 27 and transferred to the earth and sand transport bucket 14.

【土砂搬出作業】[Earth removal work]

次に、走行装置43を駆動して、走行台車44に装架さ
れ、掘削土砂の収容された土砂搬出用バケッ14を、天
井スラブ10に設けられた開口部11の直下まで水平移
動させ、クレーン等により土砂搬出用バケッ14を立管
13内を吊り上げ、ロック装置12を介して大気中に搬
出する。 以上の作業を繰り返すことにより、作業室9内に作業員
を配置することなく、掘削土砂を搬出することができる
。 〈発明の効果〉 以」−のような構成と作用のこの発明の土砂搬出装置は
、以下のような効果を有する。 (1)掘削機により掘削された土砂を一旦、土砂積替用
バケツに積み込んで待機させ、空の土砂搬出用バケツが
作業室に戻ってくると、直ちに走行台車により土砂搬出
用バケツを水平移動させて、土砂を土砂積替用バケツか
ら土砂搬出用バケツに積み替えて土砂を搬出するように
したことにより、従来、土砂搬出用バケツへの掘削土砂
の積み込みに時間を要していたのに比して、積み込み時
間が短縮でき、掘削土砂の搬出能率が増大する。 (2)従来、潜函の沈設深度が深くなると、作業時間を
短縮しなければならながったのに比して、この発明の土
砂搬出装置では、地上に設置したモニターテレビに立管
内に設置したテレビカメラにより伝送される映像を見な
がら、揚重装置および走行台車を地上より遠隔操作によ
って、運転操作するようにしたことにより、作業室内に
作業員を配置する必要はない。したがって、潜函の沈設
深度が深くなっても作業時間が制約されることなく、高
能率な土砂搬出作業を行うことができる。また、作業員
が圧気下の作業から解放さt′シ、快適な作業環境が提
供される。
Next, the traveling device 43 is driven to horizontally move the earth and sand carrying bucket 14 mounted on the traveling cart 44 and containing the excavated earth and sand to just below the opening 11 provided in the ceiling slab 10, and the crane The earth and sand carrying bucket 14 is lifted up inside the standpipe 13 and carried out into the atmosphere via the locking device 12. By repeating the above operations, the excavated earth and sand can be carried out without arranging a worker in the work chamber 9. <Effects of the Invention> The earth and sand transport device of the present invention having the configuration and operation as described below has the following effects. (1) The earth and sand excavated by the excavator is once loaded into the earth and sand transfer bucket and kept on standby. When the empty earth and sand transport bucket returns to the work room, the earth and sand transport bucket is immediately moved horizontally by a traveling cart. By transferring the earth and sand from the earth transfer bucket to the earth transport bucket and transporting the earth, the time taken to load the excavated earth and sand into the earth transport bucket was reduced compared to the conventional method. As a result, loading time can be shortened and excavated soil removal efficiency can be increased. (2) Conventionally, when the depth of the submerged box deepened, the work time had to be shortened, but with the earth and sand removal device of this invention, the monitor TV installed on the ground can be installed inside the vertical pipe. Since the lifting device and the traveling truck are remotely operated from the ground while viewing images transmitted by a television camera, there is no need for a worker to be placed inside the work room. Therefore, even if the depth of the submerged box becomes deeper, the work time is not restricted, and highly efficient earth and sand removal work can be performed. In addition, the worker is relieved from working under pressure, and a comfortable working environment is provided.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の土砂搬出装置の全体配置図、第2図
は土砂積替用バケツの詳細説明図、第3図は走行台車の
一部断面図、第4図は走行台車の平面図、第5図は従来
の掘削土砂の搬出方法の説明図である。 (主な記号)
Fig. 1 is an overall layout of the earth and sand transport device of the present invention, Fig. 2 is a detailed explanatory view of the earth and sand transfer bucket, Fig. 3 is a partial cross-sectional view of the traveling cart, and Fig. 4 is a plan view of the moving cart. , FIG. 5 is an explanatory diagram of a conventional method for carrying out excavated earth and sand. (Main symbols)

Claims (1)

【特許請求の範囲】[Claims] (1)ニューマチックケーソン工法により地下構造物を
沈設する際の掘削土砂の搬出装置において、掘削装置に
より掘削、積み込まれた土砂を収容し、蝶番付された底
蓋28、28′を開くことにより、収容土砂を放荷する
ようにした上下移動可能な土砂積替用バケツ27と、 掘削土砂を立管13上部のロック装置12を介して大気
中に搬出する土砂搬出用バケツ14と、作業室9の天井
スラブ10の下面に固設されたレール41に懸架され、
走行装置43を備え、前記土砂搬出用バケツ14の前記
土砂積替用バケツ27の直下位置への水平移動ができる
ようにした走行台車44とにより構成されかつ、これら
がそれぞれ遠隔操作されるものであることを特徴とする
ニューマチックケーソン工法における土砂搬出装置。
(1) In the equipment for transporting excavated earth and sand when submerging underground structures using the pneumatic caisson construction method, the earth and sand excavated and loaded by the excavation equipment is stored, and the hinged bottom covers 28, 28' are opened. , an earth and sand transfer bucket 27 that is movable up and down to release stored earth and sand, an earth and sand transport bucket 14 that transports excavated earth and sand into the atmosphere via a locking device 12 at the top of the standpipe 13, and a work room. 9 is suspended on a rail 41 fixed to the lower surface of the ceiling slab 10,
It is equipped with a traveling device 43 and a traveling trolley 44 capable of horizontally moving the earth and sand transporting bucket 14 to a position directly below the earth and sand transfer bucket 27, and each of these is remotely controlled. An earth and sand transport device for the pneumatic caisson construction method, which is characterized by:
JP27866290A 1990-10-15 1990-10-15 Sediment unloading device for pneumatic caisson method Expired - Lifetime JPH068541B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27866290A JPH068541B2 (en) 1990-10-15 1990-10-15 Sediment unloading device for pneumatic caisson method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27866290A JPH068541B2 (en) 1990-10-15 1990-10-15 Sediment unloading device for pneumatic caisson method

Publications (2)

Publication Number Publication Date
JPH04153415A true JPH04153415A (en) 1992-05-26
JPH068541B2 JPH068541B2 (en) 1994-02-02

Family

ID=17600412

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27866290A Expired - Lifetime JPH068541B2 (en) 1990-10-15 1990-10-15 Sediment unloading device for pneumatic caisson method

Country Status (1)

Country Link
JP (1) JPH068541B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001317059A (en) * 2000-05-11 2001-11-16 Maruto Kogyo Kk Mounting method for bottom door of caisson
JP2011089249A (en) * 2009-10-20 2011-05-06 Hazama Corp Bucket delivery device
JP5730429B1 (en) * 2014-06-10 2015-06-10 大洋基礎株式会社 Ground improvement pile creation method and ground improvement pile creation device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001317059A (en) * 2000-05-11 2001-11-16 Maruto Kogyo Kk Mounting method for bottom door of caisson
JP2011089249A (en) * 2009-10-20 2011-05-06 Hazama Corp Bucket delivery device
JP5730429B1 (en) * 2014-06-10 2015-06-10 大洋基礎株式会社 Ground improvement pile creation method and ground improvement pile creation device

Also Published As

Publication number Publication date
JPH068541B2 (en) 1994-02-02

Similar Documents

Publication Publication Date Title
JPH04153415A (en) Earth carrying out device in pneumatic caisson method
KR101861688B1 (en) A Salvage Device of a Crane Bucket
JP2016164347A (en) Earth removing method based on pneumatic caisson method
JP2018127822A (en) Earth removal apparatus
CN208916624U (en) A kind of shield-tunneling construction slag discharging system
CN110980504A (en) A turn over sediment soil collecting box for super deep shaft construction vertical transport system
JPH0643103Y2 (en) Opening and closing device for earth and sand bucket
CN108706447A (en) A kind of shield-tunneling construction slag discharging system and slag dumping method
JP2014047583A (en) Skater crane
JP3602623B2 (en) Transport equipment
KR101229614B1 (en) The Device of Moving Soil for excavating underground
JP2538585Y2 (en) Cargo containers and transport equipment for cranes
JPH06321495A (en) Conveyor device
JPH05148859A (en) Clamshell bucket
JPH1087077A (en) Safekeeping device for container
JP2008303052A (en) Hanging device of self-propelled vehicle for high lift work
JP3082151B2 (en) Lifting bucket
JPS60181422A (en) Mucking device for pneumatic caisson process
JPH01185484A (en) Setting method of reactor pressure vessel
JPH0333786Y2 (en)
JPH07103575B2 (en) Pneumatic caisson
JPS6113462Y2 (en)
JP2909647B2 (en) Lifting equipment
JPH07119155A (en) Soil and sand carrying-out device for pneumatic caisson
JPH06235284A (en) Shaft facility