JPH0414221B2 - - Google Patents

Info

Publication number
JPH0414221B2
JPH0414221B2 JP60122168A JP12216885A JPH0414221B2 JP H0414221 B2 JPH0414221 B2 JP H0414221B2 JP 60122168 A JP60122168 A JP 60122168A JP 12216885 A JP12216885 A JP 12216885A JP H0414221 B2 JPH0414221 B2 JP H0414221B2
Authority
JP
Japan
Prior art keywords
steel plate
concrete
steel
piping
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60122168A
Other languages
Japanese (ja)
Other versions
JPS61282530A (en
Inventor
Tomoyasu Kato
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP12216885A priority Critical patent/JPS61282530A/en
Publication of JPS61282530A publication Critical patent/JPS61282530A/en
Publication of JPH0414221B2 publication Critical patent/JPH0414221B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、原子力発電所建屋やサイロ等の特殊
構造物に適する鋼板コンクリート構造体の施工法
に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing a steel plate concrete structure suitable for special structures such as nuclear power plant buildings and silos.

〔従来の技術とその問題点〕[Conventional technology and its problems]

鋼板コンクリート構造体は、例えばこれによる
耐力壁は第7図に示すように壁体両面にコンクリ
ート型枠を兼ねる鋼板1,1′を配し、該鋼板1,
1′を垂直もしくは水平な鋼板ウエブ2で連結し
て鋼板ブロツク3を形成し、内部にコンクリート
4を充填してなる。また、床はスタツドジベル等
のシヤコネクタ6を突出した鋼板5上に鉄筋7を
配筋し適宜の厚さでコンクリート4を打設するも
のである。そして、このような壁や床は鋼とコン
クリートの複合効果から構造安全が向上し、また
構造システムの構成から施工の合理化への寄与が
大きく、従つて原子力やサイロ等の大型構造物の
築造に適している。
For example, a load-bearing wall made of a steel plate concrete structure has steel plates 1 and 1', which also serve as concrete formwork, arranged on both sides of the wall as shown in FIG.
1' are connected by vertical or horizontal steel plate webs 2 to form a steel plate block 3, and the inside is filled with concrete 4. Further, the floor is constructed by placing reinforcing bars 7 on a steel plate 5 with a shear connector 6 such as a stud dowel projecting thereon, and pouring concrete 4 to an appropriate thickness. These walls and floors have improved structural safety due to the combined effect of steel and concrete, and the composition of the structural system greatly contributes to the rationalization of construction, making them ideal for building large structures such as nuclear power plants and silos. Are suitable.

しかし、かかる鋼板コンクリート構造体を用い
た実例は土木分野の柱、梁などにその先行例が少
し見られるだけであり、施工の詳細部分などでは
確立された技術は未だ存在しない。
However, there are only a few examples of actual use of such steel plate concrete structures, such as columns and beams in the civil engineering field, and there is still no established technology for detailed construction.

ところで、原子力発電所の連屋を例にとると従
来これRC(鉄筋コンクリート)構造で施工される
ことがほとんどであり、例えばRC造の耐力壁や
床に関しては配管貫通個所は型枠を組んだ後に配
管用スリーブを型枠内に取付け、その周囲に開口
補強筋などを配筋するものである。
By the way, if we take the example of row buildings at a nuclear power plant, most of them have conventionally been constructed using RC (reinforced concrete) structures.For example, when it comes to load-bearing walls and floors made of RC, pipe penetration points are constructed after the formwork has been constructed. A piping sleeve is installed within the formwork, and opening reinforcing bars are placed around it.

型枠の組立や配筋作業は通常の場合でも面倒な
ものであるが、このように配管用スリーブをセツ
トすると狭いスペースでの細かな作業が増し、一
層作業が煩雑となり労力と手間を要する。
Assembling formwork and reinforcing work is troublesome even in normal cases, but setting piping sleeves in this way increases the amount of detailed work in a narrow space, making the work even more complicated and requiring more effort and effort.

本発明の目的は前記従来例の不都合を解消し、
施工の合理化とコストダウンを図かり、信頼すべ
き構造体が得られる鋼板コンクリート構造体の施
工法を提供することにある。
The purpose of the present invention is to eliminate the disadvantages of the conventional example,
The purpose of this invention is to provide a construction method for steel plate concrete structures that streamlines construction and reduces costs, and provides reliable structures.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は前記目的を達成するため、型枠を兼ね
る鋼板とコンクリートとを複合材とする鋼板コン
クリート構造体を形成するに際し、鋼板の補強リ
ブを介して配管用の鋼管を該鋼板に沿つて予め設
けておき、かかる鋼管付きの鋼板を建込んでコン
クリートを打設することを要旨とするものであ
る。
In order to achieve the above-mentioned object, the present invention, when forming a steel plate concrete structure made of a composite material of a steel plate that also serves as a formwork and concrete, a steel pipe for piping is installed in advance along the steel plate through reinforcing ribs of the steel plate. The gist of the project is to install a steel plate with such a steel pipe and pour concrete.

〔作用〕[Effect]

本発明によれば、配管用の鋼管は工場加工等で
鋼板に先付けされるので、施工現場における配筋
作業が省力化され工程が短縮されるとともに補強
が確実であり、補強による品質が保証される。
According to the present invention, steel pipes for piping are attached to steel plates in advance during factory processing, etc., so the reinforcement work at the construction site is labor-saving and the process is shortened, and the reinforcement is reliable and the quality of the reinforcement is guaranteed. Ru.

〔実施例〕〔Example〕

以下、図面について本発明の実施例を詳細に説
明する。
Embodiments of the present invention will be described in detail below with reference to the drawings.

第1図は壁における本発明の施工法の1実施例
を示す斜視図、第2図は同上要部の横断平面図
で、図中1,1′は鋼板を示す。
FIG. 1 is a perspective view showing one embodiment of the construction method of the present invention on a wall, and FIG. 2 is a cross-sectional plan view of the main part of the same, and in the figure, 1 and 1' indicate steel plates.

該鋼板1,1′は耐力壁を構成する構造部材と
して壁体両面に配され、垂直及び水平な鋼板ウエ
ブ2で相互に連結されて鋼板ブロツク3の一部を
形成している点は前記第7図と同一である。な
お、この鋼板ブロツクは工場等で製作され、現場
に運び込まれて後述のごとく相互に組合され、そ
の内部にコンクリートを充填して耐力壁を構成す
るものである。
The steel plates 1 and 1' are arranged on both sides of the wall as structural members constituting the load-bearing wall, and are interconnected by vertical and horizontal steel plate webs 2 to form a part of the steel plate block 3. It is the same as Figure 7. The steel plate blocks are manufactured in a factory or the like, transported to the site, assembled together as described below, and filled with concrete to form a load-bearing wall.

前記鋼板ウエブ2は鋼板ブロツク3において補
強リブとしての役割を有するものであるが、本発
明では、かかる鋼板ブロツク3の鋼板ウエブ2の
中央に配管用の鋼管8を配設した。該鋼管8は鋼
板ウエブ2を2分割し、これと溶接で一体となる
もので、該ウエブ2を介して鋼板1,1′に沿つ
て予め設けられることになる。
The steel plate web 2 has a role as a reinforcing rib in the steel plate block 3, and in the present invention, a steel pipe 8 for piping is arranged in the center of the steel plate web 2 of the steel plate block 3. The steel pipe 8 is made by dividing the steel plate web 2 into two parts and welding them into one piece, and is provided in advance along the steel plates 1 and 1' via the web 2.

さらに、必要がある場合には、鋼板1,1′を
直交して貫通するように短尺な配管用鋼管9を取
付け、該鋼管9の開口周辺には補正のために補強
鋼板10を取付ける。この鋼管9は、前記長尺な
鋼管8と直交して連通している。
Furthermore, if necessary, a short piping steel pipe 9 is installed so as to pass orthogonally through the steel plates 1 and 1', and a reinforcing steel plate 10 is installed around the opening of the steel pipe 9 for correction. This steel pipe 9 communicates orthogonally with the long steel pipe 8.

このようにして、配管用鋼管8や9を予め取付
けた鋼板ブロツク3を工場等で製作し、これを現
場へ搬入する。現場では上方の鋼板ブロツク3を
クレーン等で吊り上げて下方のブロツク3上に組
合せ、溶接等で接合して内部にコンクリートを打
設すれば、鋼板コンクリート構造体の耐力壁が得
られる。
In this way, the steel plate block 3 to which the piping steel pipes 8 and 9 are attached in advance is manufactured in a factory or the like, and then transported to the site. At the site, the upper steel plate block 3 is lifted by a crane or the like, assembled on the lower block 3, joined by welding or the like, and concrete is poured inside to obtain a load-bearing wall of the steel plate concrete structure.

次に床の場合について述べると、第3図、第4
図に示すように、鋼板5から垂直に立上がるよう
に補強リブ11を縦又は横に溶接等で設けるが、
この補強リブ11を介してこれに沿つて配管用の
鋼管12を溶接で取付けた。図中、13は鋼管1
2に連通する配管取出口を示す。
Next, let's talk about the floor case. Figures 3 and 4
As shown in the figure, reinforcing ribs 11 are provided vertically or horizontally by welding or the like so as to stand up vertically from the steel plate 5.
A steel pipe 12 for piping was attached by welding along the reinforcing rib 11. In the figure, 13 is steel pipe 1
The piping outlet connected to 2 is shown.

この上に適宜鉄筋7を配筋し、コンクリート4
を打設して鋼板コンクリート構造の耐力床を得
る。
Reinforcement bars 7 are placed on top of this as appropriate, and concrete 4
to obtain a load-bearing floor of steel plate concrete structure.

なお、以上の実施例では配管用の鋼管8,9,
12はすべて円筒で示したが、第5図、第6図に
示すように角筒の管を用いてもよい。円管の管で
もウエブ2やリブ11と一体となつてシヤコネク
タ的な役割を発揮し、コンクリート4と鋼板1,
1′又は5との一体性を向上させるのに役立つが、
これが角筒の場合にはその効果が一層大きいもの
となる。
In addition, in the above embodiment, the steel pipes 8, 9,
12 are all shown as cylinders, but rectangular tubes may also be used as shown in FIGS. 5 and 6. Even a circular pipe functions as a shear connector by integrating with the web 2 and ribs 11, and connects the concrete 4 and the steel plate 1,
It helps to improve unity with 1' or 5, but
If this is a rectangular tube, the effect will be even greater.

〔発明の効果〕〔Effect of the invention〕

以上述べたように本発明の鋼板コンクリート構
造体の施工法は、鋼板とコンクリートとの複合効
果による高強度の構造体が得られるとともに、配
管用の段取りは工場加工ですべて行うことができ
るので現場施工が改善され、また煩雑な型枠組作
業が無くなり、工程が短縮されコストダウンを実
現できるものである。さらに、補強による強度上
の効果が確実となり、品質の向上もはかれる。
As described above, the method of constructing a steel plate concrete structure of the present invention not only provides a high-strength structure due to the combined effect of steel plates and concrete, but also allows for all piping setup to be done on-site at the factory. This improves the construction process, eliminates the need for complicated formwork, shortens the process, and reduces costs. Furthermore, the effect of reinforcement on strength is ensured, and quality can also be improved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の鋼板コンクリート構造体の施
工法の耐力壁の場合の実施例を示す斜視図、第2
図は同上要部の横断平面図、第3図は床の場合の
実施例を示す斜視図、第4図は同上縦断側面図、
第5図は壁の場合の他の実施例を示す横断平面
図、第6図は床の場合の他の実施例を示す縦断側
面図、第7図は一般的鋼板コンクリート構造の壁
の横断平面図、第8図は同上床の縦断側面図であ
る。 1,1′,5……鋼板、2……鋼板ウエブ、3
……鋼板ブロツク、4……コンクリート、5……
鋼板、6……シヤコネクタ、7……鉄筋、8,
9,12……配管用の鋼管、10……補強鋼板、
11……補強リブ、13……配管取出口。
Fig. 1 is a perspective view showing an example of the construction method for a steel plate concrete structure of the present invention in the case of a load-bearing wall;
The figure is a cross-sectional plan view of the main part of the above, Figure 3 is a perspective view showing an embodiment in the case of a floor, Figure 4 is a longitudinal cross-sectional side view of the same,
Fig. 5 is a cross-sectional plan view showing another example in the case of a wall, Fig. 6 is a longitudinal cross-sectional side view showing another example in the case of a floor, and Fig. 7 is a cross-sectional plane of a wall of a general steel plate concrete structure. FIG. 8 is a longitudinal sectional side view of the same floor. 1, 1', 5... Steel plate, 2... Steel plate web, 3
...Steel plate block, 4...Concrete, 5...
Steel plate, 6... Shear connector, 7... Reinforcement bar, 8,
9, 12... steel pipe for piping, 10... reinforcing steel plate,
11... Reinforcement rib, 13... Piping outlet.

Claims (1)

【特許請求の範囲】[Claims] 1 型枠を兼ねる鋼板とコンクリートとを複合材
とする鋼板コンクリート構造体を形成するに際
し、鋼板の補強リブを介して配管用の鋼管を該鋼
板に沿つて予め設けておき、かかる鋼管付きの鋼
板を建込んでコンクリートを打設することを特徴
とした鋼板コンクリート構造体の施工法。
1. When forming a steel plate concrete structure that is a composite material of a steel plate that also serves as a formwork and concrete, a steel pipe for piping is provided in advance along the steel plate through the reinforcing ribs of the steel plate, and the steel plate with the steel pipe is A construction method for steel plate concrete structures, characterized by erecting concrete and pouring concrete.
JP12216885A 1985-06-05 1985-06-05 Construction of steel plate/concrete structure Granted JPS61282530A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12216885A JPS61282530A (en) 1985-06-05 1985-06-05 Construction of steel plate/concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12216885A JPS61282530A (en) 1985-06-05 1985-06-05 Construction of steel plate/concrete structure

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2725193A Division JPH0674615B2 (en) 1993-01-22 1993-01-22 Construction method of bearing floor

Publications (2)

Publication Number Publication Date
JPS61282530A JPS61282530A (en) 1986-12-12
JPH0414221B2 true JPH0414221B2 (en) 1992-03-12

Family

ID=14829260

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12216885A Granted JPS61282530A (en) 1985-06-05 1985-06-05 Construction of steel plate/concrete structure

Country Status (1)

Country Link
JP (1) JPS61282530A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10160881A (en) * 1996-11-29 1998-06-19 Toshiba Corp Building structure and building construction method for reactor power station

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4882620A (en) * 1972-02-03 1973-11-05
JPS5334811B2 (en) * 1974-03-16 1978-09-22

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5536653Y2 (en) * 1976-09-01 1980-08-29

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4882620A (en) * 1972-02-03 1973-11-05
JPS5334811B2 (en) * 1974-03-16 1978-09-22

Also Published As

Publication number Publication date
JPS61282530A (en) 1986-12-12

Similar Documents

Publication Publication Date Title
CN106013455B (en) A kind of manufacture of Prefabricated composite steel reinforcement cage component assembly method, reinforced concrete structure body method of construction
CN107859206A (en) Pre-manufactured steel structure overlapped shear wall and its construction method
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JPH04261934A (en) Building frame construction method using form member made of pre-cast concrete
JPH0414221B2 (en)
JP3154020B2 (en) Reinforced steel framed concrete beam-column connection
JPH02300439A (en) Prefabricating method
JPH04222742A (en) Composite beam
US3349539A (en) Construction of two-way composite building system
JP2620118B2 (en) Net formwork method for walls and floors
US1099953A (en) Fireproof-building construction.
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH0447737B2 (en)
JPH0674615B2 (en) Construction method of bearing floor
JPH044091Y2 (en)
JPH02120441A (en) Precast concrete wall panel and constructing wall therewith
JPS6232303B2 (en)
JPS61282529A (en) Construction of steel plate/concrete structure
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JPS645134B2 (en)
JPH0211521Y2 (en)
JP3105038B2 (en) Unit building
JPH0480169B2 (en)