JPH04124400A - Method of constructing underground cave - Google Patents

Method of constructing underground cave

Info

Publication number
JPH04124400A
JPH04124400A JP2241112A JP24111290A JPH04124400A JP H04124400 A JPH04124400 A JP H04124400A JP 2241112 A JP2241112 A JP 2241112A JP 24111290 A JP24111290 A JP 24111290A JP H04124400 A JPH04124400 A JP H04124400A
Authority
JP
Japan
Prior art keywords
tunnel
walls
tunnel wall
wall
tunnel walls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2241112A
Other languages
Japanese (ja)
Other versions
JP2544829B2 (en
Inventor
Tatsuo Tanaka
達雄 田中
Kiyoshi Miya
清 宮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2241112A priority Critical patent/JP2544829B2/en
Publication of JPH04124400A publication Critical patent/JPH04124400A/en
Application granted granted Critical
Publication of JP2544829B2 publication Critical patent/JP2544829B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to construct an underground cave with high strength by providing continuously a succeeding tunnel wall between upper and lower preceding tunnel walls to form a circular or spiral tunnel wall, and cutting off steel segments provided in connecting sections to place concrete. CONSTITUTION:Preceding and succeeding tunnel walls 14 and 16 are formed to the lower end of side walls of a cave 10, grout 28 is injected into a grouting hole 26, and it is discharged between the peripheral surfaces of both tunnel walls 14 and 16 to secure cut-off efficiency. After that, beam members 22b and 24b of steel segments 22 and 24 for parts opposed to both tunnel walls 14 and 16 are left remaining, and the skin plates 22a and 24a are cut off. Then, excavation between the tunnel walls 14 and 16 is made, the beam members 22b and 24b of the steel segments 22 and 24 are left remaining to cut off the skin plates 22a and 24a, and the tunnel walls 14 and 16 are linked with each other. After reinforcing bars 30 are assembled, concrete is placed in the tunnel walls 14 and 16, and the cave 10 is constructed.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、地下空洞の構築方法に関し、特に空洞の外周
壁をシールド掘進機で構築する方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method of constructing an underground cavity, and more particularly to a method of constructing an outer circumferential wall of a cavity using a shield excavator.

(従来の技術) 近時、都市部などの土地を有効利用するために、地下に
大容積の空洞部を形成することが提案されている。
(Prior Art) Recently, in order to effectively utilize land in urban areas, it has been proposed to form large-volume cavities underground.

このような地下空洞の構築方法として、例えば、特開昭
64−43699号公報には、空洞の側壁部分をトンネ
ルで形成する方法が提案されている。
As a method for constructing such an underground cavity, for example, Japanese Patent Laid-Open No. 64-43699 proposes a method in which the side wall portion of the cavity is formed by a tunnel.

同号報に開示されている空洞の構築方法は、地中におい
て構築しようとする空洞の壁面に相当する部分に曲線状
のトンネルを掘削し、この掘削部をコンクリートで補強
して補強リングとし、複数の補強リングを上下方向に隣
接させて形成し、しかる後に補強リングの内部を掘削す
るものであるが、この方法には、以下に説明する技術的
課題があった。
The method for constructing a cavity disclosed in the same issue involves excavating a curved tunnel underground in a portion corresponding to the wall of the cavity to be constructed, and reinforcing this excavated portion with concrete to form a reinforcing ring. This method involves forming a plurality of reinforcing rings adjacent to each other in the vertical direction and then excavating the interior of the reinforcing rings, but this method has the following technical problems.

(発明が解決しようとする課題) すなわち、上記公報に記載されている空洞の構築方法で
は、環状ないしは螺旋状に形成されるトンネルは、コン
クリートが充填されて補強されているが、上下方向に位
置する補強リングは、相互に隣接して配置されるものの
、これらの間は一体性がない。
(Problem to be Solved by the Invention) In other words, in the cavity construction method described in the above publication, the tunnel formed in an annular or spiral shape is filled with concrete and reinforced; Although the reinforcing rings are placed adjacent to each other, there is no integrity between them.

従って、構築される空洞の止水性や強度面で問題があっ
た。
Therefore, there were problems in terms of water-tightness and strength of the constructed cavity.

この発明は、このような従来の問題点に鑑みてなされた
ものであり、その目的とするところは、止水性や強度上
の問題が解決される地下空洞の構築方法を提供すること
にある。
The present invention has been made in view of these conventional problems, and its purpose is to provide a method for constructing an underground cavity that solves the problems in terms of water-tightness and strength.

(課題を解決するための手段) 上記目的を達成するたtに、本発明は、地上に繋がった
立坑からシールド掘進機を発進し、このシールド掘進機
の後部側に順次セグメントを組立てて環状ないしは螺旋
状のトンネル壁を形成し、この後に前記トンネル壁の内
部を掘削する地下空洞の構築方法において、前記環状な
いしは螺旋状に形成されたトンネル壁は、上下方向に隣
接するトンネル壁間で相互に連通させられ、この後に前
記トンネル壁内にコンクリートを充填して相互に連結す
ることを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the present invention starts a shield tunneling machine from a vertical shaft connected to the ground, and sequentially assembles segments on the rear side of the shield tunneling machine to form a circular or circular shape. In a method for constructing an underground cavity in which a spiral tunnel wall is formed and the inside of the tunnel wall is then excavated, the tunnel wall formed in an annular or spiral shape is arranged so that vertically adjacent tunnel walls are mutually connected to each other. The tunnel walls are made to communicate with each other, and then the tunnel walls are filled with concrete to connect them to each other.

上記トンネル壁は、上下方向に所定の間隔をおいて形成
される先行トンネル壁と、この先行トンネル壁間に形成
される後行トンネル壁とから構成することができる。
The tunnel wall may include a leading tunnel wall formed at a predetermined interval in the vertical direction, and a trailing tunnel wall formed between the leading tunnel walls.

上記トンネル壁の連通させられる部分には、予め切断可
能な鋼製セグメントを用いることが望ましい。
It is desirable to use steel segments that can be cut in advance for the portions of the tunnel wall that are to be communicated.

上記後行トンネル壁と上記先行トンネル壁とを連通させ
る前に、これらのトンネル壁の外周間に内部から止水グ
、ラウドを注入してもよい。
Before the trailing tunnel wall and the leading tunnel wall are made to communicate with each other, a water sealing agent or loud may be injected from inside between the outer peripheries of these tunnel walls.

(発明の作用効果) 上記構成の地下空洞の構築方法によれば、空洞の側壁と
なるトンネル壁は、上下方向に隣接するものが相互に連
通した状態で、その内部にコンクリートが充填されて連
結されるので、止水性が向上するとともに、その強度も
大きくなる。
(Operations and Effects of the Invention) According to the method for constructing an underground cavity having the above configuration, the tunnel walls, which are the side walls of the cavity, are interconnected by vertically adjacent ones that are filled with concrete and connected to each other. As a result, water-stopping properties are improved and its strength is also increased.

請求項2の構成によれば、先行トンネル壁の間に後行ト
ンネル壁が形成されるので、特に、後行トンネル壁を形
成する際には、その上下に先行トンネル壁が位置してい
て、土庄のバランスを保つことができる。
According to the structure of claim 2, since the trailing tunnel wall is formed between the leading tunnel walls, in particular, when forming the trailing tunnel wall, the leading tunnel wall is located above and below it, Tonosho's balance can be maintained.

請求項3の構成によれば、トンネル壁間の連通させる部
分に鋼製セグメントが用いられているので、そのスキン
プレートを切断すると、トンネル壁間を簡単に連通させ
ることができる。
According to the structure of claim 3, since steel segments are used in the portions that communicate between the tunnel walls, by cutting the skin plate, the tunnel walls can be easily communicated.

(実施例) 以下、この発明の好適な実施例について添付図面を参照
にして詳細に説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

第1図および第2図は、この発明にかかる地下空洞の構
築方法の一実施例を示している。
FIGS. 1 and 2 show an embodiment of the method for constructing an underground cavity according to the present invention.

同図に示す構築方法は、第1図に示すように、ドーム型
の上部壁と、この上部壁の下方に一体に形成される円筒
状の側部壁とからなる空洞10を構築する方法を示して
おり、上部壁の上端には、地上に繋がる立坑12か設け
られている。
The construction method shown in FIG. 1 is a method of constructing a cavity 10 consisting of a dome-shaped upper wall and a cylindrical side wall integrally formed below the upper wall. A vertical shaft 12 connected to the ground is provided at the upper end of the upper wall.

この実施例では、構築される空洞10の上部および側部
壁は、立坑12から発進されるシールド掘進機により螺
旋状に掘削、構築されるものであり、掘進に伴なってシ
ールド掘進機の後部側に順次セグメントを組立ててトン
ネル状の壁とされる。
In this embodiment, the upper and side walls of the cavity 10 to be constructed are spirally excavated and constructed by a shield excavator launched from a shaft 12, and as the shield excavator excavates, the rear part of the shield excavator Segments are sequentially assembled on the sides to form a tunnel-like wall.

なお、この場合、空洞10の上部壁の頂部近傍では、シ
ールド掘進機による掘削が急角度となることが予測され
るので、頂部近傍はシールド掘進機の掘削によらず、別
の手段、例えば、在来の山岳トンネル掘削工法などによ
り形成することもできる。
In this case, it is predicted that near the top of the upper wall of the cavity 10, the excavation by the shield excavator will be at a steep angle, so the area near the top will not be excavated by the shield excavator, but by another means, for example, It can also be formed using conventional mountain tunnel excavation methods.

また、この実施例では、トンネル壁は、一対のシールド
掘進機を用いて構築され、まず、先行トンネル壁14か
上下方向に所定の間隔をおいて形成され、その後に先行
トンネル壁14間に後行トンネル壁16が形成される。
Further, in this embodiment, the tunnel wall is constructed using a pair of shield tunneling machines, and first, the leading tunnel wall 14 is formed at a predetermined interval in the vertical direction, and then the trailing tunnel wall is formed between the leading tunnel wall 14. A row tunnel wall 16 is formed.

第2図はこの状態を示しており、同図では、18か先行
トンネル壁14のセグメント、20が後行トンネル壁1
6のセグメントである。
FIG. 2 shows this state, where 18 is a segment of the leading tunnel wall 14 and 20 is a segment of the trailing tunnel wall 14.
6 segments.

各トンネル壁14,16は、これらが相互に上下方向で
対向する部分に、予め切断可能な鋼製セグメント22.
24が全長に互って用いられており、これ以外の部分は
鉄筋コンクリート製となっていて、その下部側にはグラ
ウト注入孔26が設けられている。
Each tunnel wall 14, 16 is formed by pre-cutting steel segments 22.
24 are used alternately along the entire length, and the other parts are made of reinforced concrete, and a grout injection hole 26 is provided in the lower part thereof.

各鋼製セグメント22.24は、外周に配置されたスキ
ンプレート22a、24aと、スキンプレート22a、
24aの内面側に設けられた補強用の桁材22b、24
bとから構成されている。
Each steel segment 22.24 has a skin plate 22a, 24a disposed on its outer periphery, a skin plate 22a,
Reinforcing beam members 22b and 24 provided on the inner surface of 24a
It is composed of b.

以上の構成からなる先行および後行トンネル壁14.1
6か、構築しようとする空洞10の側壁下端まで形成さ
れると、各トンネル壁1.4.16間の連結工程が行わ
れる。
Leading and trailing tunnel walls 14.1 consisting of the above configurations
6 or the lower end of the side wall of the cavity 10 to be constructed, a connection process between each tunnel wall 1.4.16 is performed.

この連結工程は、まず、グラウト注入孔26にグラウト
28を注入し、グラウト28を先行および後行トンネル
壁14.16の外周部間に排出して、これを硬化させる
ことにより、止水性か確保される。
This connection process first injects grout 28 into the grout injection hole 26, discharges the grout 28 between the outer peripheries of the leading and trailing tunnel walls 14, 16, and hardens it to ensure water-tightness. be done.

次いで、先行ないしは後行トンネル壁14,16の対向
する部分において、その長さ方向に沿って順次上部側に
位置する鋼製セグメント22,24の桁材22b、24
bを残して、そのスキンプレート22a、24aのみが
切断される。
Next, in the opposing portions of the leading or trailing tunnel walls 14, 16, the beam members 22b, 24 of the steel segments 22, 24 are positioned successively on the upper side along the length direction thereof.
Only the skin plates 22a and 24a are cut, leaving the skin plates 22a and 24a.

そして、トンネル壁14,16間の土砂が掘削除去され
、その後先行ないしは後行トンネル壁14.16の下部
側に位置する鋼製セグメント22゜24の桁材22b、
24bを残して、そのスキンプレート22a  24a
が切断され、これにより先行、後行トンネル壁14.1
6間が連通されることになる。
Then, the earth and sand between the tunnel walls 14 and 16 is excavated and removed, and then the girders 22b of the steel segments 22 and 24 located on the lower side of the leading or trailing tunnel walls 14 and 16,
Leaving 24b, the skin plate 22a 24a
is cut, thereby leading and trailing tunnel walls 14.1
6 will be connected.

先行および後行トンネル壁14.16間が連通させられ
ると、この部分を貫通するようにして鉄筋30が組立て
られ、その後トンネル壁14,16内にコンクリートか
充填され、コンクリートが硬化することにより、トンネ
ル壁14.16が連結されると、その内部の掘削が行わ
れて空洞10が構築される。
When the leading and trailing tunnel walls 14 and 16 are brought into communication, reinforcing bars 30 are assembled so as to pass through these parts, and then concrete is filled into the tunnel walls 14 and 16, and as the concrete hardens, Once the tunnel walls 14,16 are connected, excavation within them is performed to construct the cavity 10.

上記構成の地下空洞の構築方法によれば、空洞10の側
壁となるトンネル壁14.16は、上下方向に隣接する
ものが相互に連通した状態で、その内部に鉄筋30を組
立ててコンクリートが充填されて連結されるので、止水
性が向上するとともに、その強度も大きくなる。
According to the method for constructing an underground cavity having the above configuration, the tunnel walls 14 and 16 serving as the side walls of the cavity 10 are filled with concrete by assembling reinforcing bars 30 inside the tunnel walls 14 and 16, with the vertically adjacent walls communicating with each other. Since they are connected together, their water-stopping properties are improved and their strength is also increased.

また、先行トンネル壁14を形成した後に、その間に後
行トンネル壁16が形成されるので、特に、後行トンネ
ル壁16を形成する際には、その上下に先行トンネル壁
14が位置していて、土庄のバランスを保つことができ
る。
Furthermore, after forming the preceding tunnel wall 14, the trailing tunnel wall 16 is formed between them, so especially when forming the trailing tunnel wall 16, the preceding tunnel wall 14 is located above and below it. , able to maintain Tonosho's balance.

さらに、トンネル壁14,16間の連通させる部分に鋼
製セグメント22.24が用いられているので、その折
部22b、24bを残して、スキンプレート22a、、
24aだけを切断すると、トンネル壁14.16間を簡
単かつ安全に連通させることかできる。
Further, since the steel segments 22, 24 are used in the communication portion between the tunnel walls 14, 16, the skin plates 22a,
By cutting only 24a, the tunnel walls 14 and 16 can be easily and safely communicated with each other.

第3図は、この発明の他の実施例を示しており、この実
施例では、立坑12aか構築しようとする空洞10aの
側方に設けられ、この立坑12aから発進されたシール
ド掘進機は周回して再び立坑1、2 aに戻り、立坑1
2a内で下方ないしは上方に移動させられて、別のトン
ネル壁部を掘削する。
FIG. 3 shows another embodiment of the present invention. In this embodiment, a shaft 12a is provided on the side of a cavity 10a to be constructed, and a shield excavator launched from this shaft 12a goes around. Then return to shafts 1 and 2 a again, and go to shaft 1
2a to excavate another tunnel wall.

つまり、この実施例ではトンネル壁が環状に形成され、
上下方向に位置するトンネル壁は上記実施例と同様な工
程により相互に連結されることになる。
That is, in this embodiment, the tunnel wall is formed in an annular shape,
The tunnel walls located in the vertical direction are interconnected by the same process as in the above embodiment.

なお、この実施例の場合には、空洞10aの上端は、例
えば、在来の山岳トンネル掘削工法などにより形成され
る。
In the case of this embodiment, the upper end of the cavity 10a is formed by, for example, a conventional mountain tunnel excavation method.

このように構成された空洞10aの構築方法でも上記実
施例と同様な作用効果が得られる。
The method of constructing the cavity 10a configured in this manner also provides the same effects as those of the above embodiment.

なお、上記実施例では、先行および後行トンネル壁14
.16をすべて形成した後に、鋼製セグメント22.2
4の切断作業およびトンネル壁14.16間の連結作業
を行うことで説明したが、例えば、第1図に仮想線で示
すように、各トンネル壁14.16内に点検用の小トン
ネルを設ければ、形成されたトンネル壁の部分から順に
前述した作業を行うこともできる。
In addition, in the above embodiment, the leading and trailing tunnel walls 14
.. After forming all 16, the steel segment 22.2
Although the explanation has been made by performing the cutting work in Step 4 and the connecting work between the tunnel walls 14 and 16, for example, as shown by the imaginary lines in Fig. 1, a small tunnel for inspection is provided within each tunnel wall 14 and 16. If so, the above-described operations can be performed sequentially from the tunnel wall portion that has been formed.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明にかかる地下空洞の構築方法の一実施例
を示す全体図、第2図は第1図の要部拡大図、第3図は
同構築方法の他の実施例を示す全体図である。 10.10a・・・空洞 12.128・・・立坑 14.16・・・・・・トンネル壁 22.24・・・・・・鋼製セグメン 28・・・・・・・・・・・・・・・グラウトト
Fig. 1 is an overall view showing one embodiment of the underground cavity construction method according to the present invention, Fig. 2 is an enlarged view of the main part of Fig. 1, and Fig. 3 is an overall view showing another embodiment of the same construction method. It is a diagram. 10.10a...Cavity 12.128...Shaft 14.16...Tunnel wall 22.24...Steel segment 28... ...grout

Claims (4)

【特許請求の範囲】[Claims] (1)地上に繋がった立坑からシールド掘進機を発進し
、このシールド掘進機の後部側に順次セグメントを組立
てて環状ないしは螺旋状のトンネル壁を形成し、この後
に前記トンネル壁の内部を掘削する地下空洞の構築方法
において、前記環状ないしは螺旋状に形成されたトンネ
ル壁は、上下方向に隣接するトンネル壁間で相互に連通
させられ、この後に前記トンネル壁内にコンクリートを
充填して相互に連結することを特徴とする地下坑道の構
築方法。
(1) A shield tunneling machine is launched from a shaft connected to the ground, and segments are sequentially assembled on the rear side of the shield tunneling machine to form a ring-shaped or spiral tunnel wall, and then the inside of the tunnel wall is excavated. In the method for constructing an underground cavity, the tunnel walls formed in an annular or spiral shape are made to communicate with each other between vertically adjacent tunnel walls, and after that, the tunnel walls are filled with concrete to connect them to each other. A method for constructing an underground tunnel characterized by:
(2)上記トンネル壁は、上下方向に所定の間隔をおい
て形成される先行トンネル壁と、この先行トンネル壁間
に形成される後行トンネル壁とからなることを特徴とす
る請求項1記載の地下空洞の構築方法。
(2) The tunnel wall includes a leading tunnel wall formed at a predetermined interval in the vertical direction, and a trailing tunnel wall formed between the leading tunnel walls. How to build underground cavities.
(3)上記トンネル壁の連通させられる部分には、予め
切断可能な鋼製セグメントが用いられることを特徴とす
る請求項1または2記載の地下空洞の構築方法。
(3) The method for constructing an underground cavity according to claim 1 or 2, wherein a steel segment that can be cut in advance is used for the portion of the tunnel wall that is to be communicated.
(4)上記後行トンネル壁と上記先行トンネル壁とを連
通させる前に、これらのトンネル壁の外周間に内部から
止水グラウトが注入されることを特徴とする請求項2ま
たは3記載の地下空洞の構築方法。
(4) The underground according to claim 2 or 3, characterized in that before the trailing tunnel wall and the leading tunnel wall are brought into communication, a water-stop grout is injected from inside between the outer peripheries of these tunnel walls. How to build a cavity.
JP2241112A 1990-09-13 1990-09-13 How to build an underground cavity Expired - Lifetime JP2544829B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2241112A JP2544829B2 (en) 1990-09-13 1990-09-13 How to build an underground cavity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2241112A JP2544829B2 (en) 1990-09-13 1990-09-13 How to build an underground cavity

Publications (2)

Publication Number Publication Date
JPH04124400A true JPH04124400A (en) 1992-04-24
JP2544829B2 JP2544829B2 (en) 1996-10-16

Family

ID=17069466

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2241112A Expired - Lifetime JP2544829B2 (en) 1990-09-13 1990-09-13 How to build an underground cavity

Country Status (1)

Country Link
JP (1) JP2544829B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113389564A (en) * 2021-06-29 2021-09-14 中铁建工集团有限公司 Safety auxiliary structure of material is transported in underground tunnel construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113389564A (en) * 2021-06-29 2021-09-14 中铁建工集团有限公司 Safety auxiliary structure of material is transported in underground tunnel construction
CN113389564B (en) * 2021-06-29 2023-09-05 中铁建工集团有限公司 Safety auxiliary structure for underground tunnel construction material

Also Published As

Publication number Publication date
JP2544829B2 (en) 1996-10-16

Similar Documents

Publication Publication Date Title
JP4687986B2 (en) Construction method of large section tunnel
JP2816397B2 (en) Method of expanding and reducing diameter of tunnel
JP2897667B2 (en) Subway station structure and construction method
JP2004353264A (en) Construction method of tunnel confluence section and tunnel confluence section
JP6862237B2 (en) Outer skeleton construction method and outer skeleton
JP2942874B2 (en) How to join tunnels
JPH04124400A (en) Method of constructing underground cave
JP6765566B1 (en) Construction method of the skeleton and the skeleton
JPH05280296A (en) Large scale underground structure and construction method thereof
JPH10227199A (en) Construction method of large sectional tunnel
JPH04213695A (en) Segment for shield tunnel
JPH04319198A (en) Construction method of tunnel
JP3765048B2 (en) How to build a tunnel
JP3584416B2 (en) Tunnel and its construction method
JP2849605B2 (en) Large section tunnel and its construction method
JPH03244799A (en) Large sectional tunnel structure and constucting method thereof
JPH0819824B2 (en) Construction method of underground space
JP6756892B1 (en) Underground skeleton and how to build an underground skeleton
JP2929220B2 (en) Connection method of shield tunnel
JPH02153196A (en) Tunnel excavation method and shield excavation
JP2788956B2 (en) How to join tunnels
JP3900686B2 (en) Underground structure and its construction method
JP6730540B2 (en) Outer shell structure and outer shell structure construction method
JP7403390B2 (en) Synthetic structure and method of constructing the synthetic structure
JPH04309694A (en) Underground space construction method