JPH04102624A - Positioning plate for anchor bolt - Google Patents

Positioning plate for anchor bolt

Info

Publication number
JPH04102624A
JPH04102624A JP21617290A JP21617290A JPH04102624A JP H04102624 A JPH04102624 A JP H04102624A JP 21617290 A JP21617290 A JP 21617290A JP 21617290 A JP21617290 A JP 21617290A JP H04102624 A JPH04102624 A JP H04102624A
Authority
JP
Japan
Prior art keywords
anchor bolt
foundation
module
anchor
positioning plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21617290A
Other languages
Japanese (ja)
Other versions
JP2504613B2 (en
Inventor
Yoshiharu Osada
長田 義治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP2216172A priority Critical patent/JP2504613B2/en
Publication of JPH04102624A publication Critical patent/JPH04102624A/en
Application granted granted Critical
Publication of JP2504613B2 publication Critical patent/JP2504613B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To enhance accuracy in positioning as well as to facilitate embedding operations by employing a positioning plate for anchor bolts for the foundation of a dwelling house which is industrialized based on a reference module. CONSTITUTION:An anchor bolt positioning plate 5 composed of an L-shaped plate main body 5a which is of the same dimension of L identical to the foundation 10 in the whole width. In the second place, anchor bolt insertion holes 5b are provided for the plate main body 5a while being aligned with each anchor bolt 2 in position in such a way that one is provided at a position parted by the length of d1 which is the sum of 1/8 module and 1/2 of a wall thickness on the module center line X-Y, and the other is provided at a position parted by the length (d) of 1/8 module from the module center line X-Y on the module center line W-Z. And when the anchor bolts 2 are inserted, the shape of each hole is formed in such a way that each bolt is enclosed by plural slices 5c which elastically make contact with the outer circumference of the bolt.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明はプレハブ住宅性のような、−1モとして木製パ
ネルの接合によって建築物の躯体を形成する方式の工業
化住宅を構築する際に好適に適用されるアンカーボルト
位置決め用プレートであって、基礎の出隅位置もしくは
T字型に交差する位置に設置されて、アンカーボルトを
立てた状態に位置決め保持するアンカーボルト位置決め
用プレートに関するものである。
[Detailed Description of the Invention] "Industrial Application Field" The present invention is suitable for constructing industrialized housing, such as prefabricated housing, where the framework of the building is formed by joining wooden panels as -1 mode. This is an anchor bolt positioning plate that is applied to an anchor bolt positioning plate that is installed at a protruding corner position of a foundation or at a position intersecting a T-shape, and positions and holds the anchor bolt in an upright state. .

「従来の技術」 工業化住宅のプランニングの一つに、基本モジュールに
従ったグリッドプランニングを主体とした手法がある。
``Conventional technology'' One of the methods of planning for industrialized housing is a method that mainly uses grid planning according to basic modules.

当該不法は、外壁や惜造体を初めとするすべての部品の
寸法、種類をできる限り少なく押さえながら、できるだ
け自由にプランを行うものであるが、基本モジュールは
システム毎に様々であり、またグリッドに対して部品を
どのようにおさめるかの考えかたも同様に様々なものが
ある(たとえば特公平1−12890号公報参照)。
The purpose of this illegal method is to plan as freely as possible while keeping the dimensions and types of all parts, including the exterior walls and spare parts, as small as possible, but the basic modules vary depending on the system, and the grid Similarly, there are various ways of thinking about how to fit the parts into the space (for example, see Japanese Patent Publication No. 1-12890).

従来、このような基本モジュールに従って工業化を推し
進めた住宅施工方法の一つに、框材(芯材)を四角枠状
に組んだ枠体の両面に面板を貼り付けてなる矩形状の木
製パネルを用いて、床、壁等を組み立てる方法がある。
In the past, one of the housing construction methods that promoted industrialization based on this basic module was to create rectangular wooden panels made by attaching face plates to both sides of a square frame made of frame materials (core materials). There is a method of using it to assemble floors, walls, etc.

この施工方法は、たとえば、現場施工のコンクリート基
礎の上にユニット化した木製の床パネルを敷き込み、そ
の上に1階および2階の木製壁パネル(以下壁パネルと
言う)を組み上げ、さらに、軸組、木組等をして、屋根
パネルを組み立てて、建築物を構築するといった方法で
ある。
This construction method involves, for example, laying unitized wooden floor panels on a concrete foundation built on-site, and assembling wooden wall panels for the first and second floors (hereinafter referred to as wall panels) on top of them, and then This method involves constructing a building by assembling frames, timber, etc., and assembling roof panels.

なお、前記各パネル(床パネル、壁パネル等)は、接着
剤とスクリュー釘等により一体化され、また床パネルは
、基礎(図示例では布基礎)の上面に調整した調整モル
タルの上に台輪を介して敷き込められるとともに、1階
部分の各壁パネルは、コンクリート基礎の上面より突出
するアンカーボルトへ壁パネルの下端の孔(ボルト挿通
孔)を落とし込んでボルト締めにより、基礎と一体化さ
れるようになっている。
Each of the panels (floor panel, wall panel, etc.) is integrated with adhesive and screw nails, and the floor panel is mounted on a mortar adjusted to the top surface of the foundation (fabric foundation in the illustrated example). At the same time, each wall panel on the first floor is integrated with the foundation by inserting the hole (bolt insertion hole) at the bottom end of the wall panel into the anchor bolt that protrudes from the top of the concrete foundation and tightening the bolt. It is now possible to do so.

ところで、このような住宅の施工方法において、アンカ
ーボルトの施工は、従来、モジュール芯とモジュール芯
との交差する位置を基準にして、それぞれ一定間隔を開
けながらアンカーボルトの埋め込み位置を設定しておき
、基礎成型用型枠に打設したコンクリートが固まらない
うちに、作業員が手でアンカーボルトを押し込んで固定
するといった手段が採られている。
By the way, in the construction method of such a house, in the construction of anchor bolts, conventionally, the anchor bolt embedding position is set with a certain interval between each module core based on the intersection position between the module cores. In some cases, workers manually push in anchor bolts to secure the concrete in place before the concrete poured into the foundation formwork hardens.

[発明が解決しようとする課題」 ところが、このような従来技術におけるアンカーボルト
の施工では、基礎の型枠に打設したコンクリートが固ま
らないうちに、作業員が手で直接アンカーボルトを押し
込んで固定するといった手段が採用されているため、ア
ンカーボルトの位置決め精度が悪く、また、手作業によ
るため、モジュール芯上に粘度良く、アンカーボルトを
設置することができず、アンカーボルトを取り付ける際
の作業能率が悪くなるといった解決すべき課題が残され
ていた。
[Problem to be solved by the invention] However, in the construction of anchor bolts using such conventional technology, workers manually push the anchor bolts into place before the concrete cast in the foundation formwork hardens. Because the anchor bolt positioning accuracy is poor because of the method used, and because it is done manually, the anchor bolt cannot be installed due to the viscosity on the module core, which reduces the work efficiency when installing the anchor bolt. However, there were still issues to be resolved, such as the worsening of

本発明は前記事情に鑑みて提案されたもので、その目的
とするところは、基礎に埋め込むべきアンカーボルトの
位置決め精度を向上することができ、また、アンカーボ
ルトの埋め込み作業を容易に実施し得て、基礎の施工作
業の工業化を達成することができるアンカーボルト位置
決め用プレートを捉供することにある。
The present invention has been proposed in view of the above circumstances, and its purpose is to improve the positioning accuracy of anchor bolts to be embedded in the foundation, and to facilitate the work of embedding anchor bolts. An object of the present invention is to provide an anchor bolt positioning plate that can achieve industrialization of foundation construction work.

[課題を解決するための手段」 かかる目的を達成するために本発明は、基本モジュール
に従ったグリッドに応じて壁体を割り付けし、このよう
にして割付けした壁体を、木製の壁パネルを面方向に接
合するとともに床面上にアンカーボルトを介して立設す
ることにより溝築する構造において、基礎を構築する際
に、基礎の出隅位置もしくはT字型に交差する位置に設
置されかつアンカーポル+を立てた状態に位置決め保持
するアンカーボルト位置決め用プレートであって、全体
が基礎の幅と同一の幅寸法によってL字型若しくはT字
型に形成されたプレート本体と、このプレート本体のモ
ジュール芯上に位置して形成されたアンカーボルト挿通
孔とからなり、かつ、前記アンカーボルト挿通孔には、
アンカーボルトの外周に弾性的に接触してアンカーボル
トを立てた状態に保持する複数の舌片が挿通孔の周囲に
沿って並んで形成されていることを特徴とするものであ
る。
[Means for Solving the Problems] In order to achieve the above object, the present invention allocates walls according to a grid according to a basic module, and uses wooden wall panels for the walls thus allocated. In a structure constructed by trench construction by joining in the plane direction and erecting on the floor via anchor bolts, when constructing the foundation, This is an anchor bolt positioning plate that positions and holds the Anchor Pol+ in an upright state, and includes a plate body that is formed in an L-shape or T-shape with the same width as the foundation, and a plate body that is An anchor bolt insertion hole formed on the module core, and the anchor bolt insertion hole includes:
It is characterized in that a plurality of tongue pieces are formed in line along the periphery of the insertion hole to elastically contact the outer periphery of the anchor bolt and hold the anchor bolt in an upright state.

「作用J 基礎成型用型枠内にコンクリートを打設した後、L字型
若しくはT字型となった基礎のコンクリート上面にアン
カーボルト位置決め用プレートを載せ、コンクリートが
硬化する前に、アンカーボルト挿通孔を介してアンカー
ボルトを基礎に突き差す。
"Action J: After pouring concrete into the formwork for forming the foundation, place an anchor bolt positioning plate on the top of the concrete of the L-shaped or T-shaped foundation, and insert the anchor bolts before the concrete hardens. Insert the anchor bolt into the foundation through the hole.

位置決め用プレートのアンカーボルト挿通孔に挿入され
たアンカーボルトはプレート本体の挿通孔に形成された
複数の舌片によって弾性的に支持され、基礎上に傾げる
ことなく支持される。
The anchor bolt inserted into the anchor bolt insertion hole of the positioning plate is elastically supported by a plurality of tongue pieces formed in the insertion hole of the plate body, and is supported without tilting on the foundation.

また、プレート本体は、基礎の幅と同一の幅寸法によっ
てL字型若しくはT字型に形成され、ブレ−ト本体に形
成されたアンカーボルト挿通孔はモジュール芯に沿って
形成されているので、プレート本体を基礎の型枠の中に
設置し、アンカーボルトを挿通孔に通すという単純な操
作によって、アンカーボルトを精度良く、基礎に施工す
ることが可能になる。
In addition, the plate body is formed in an L-shape or T-shape with the same width as the foundation, and the anchor bolt insertion holes formed in the plate body are formed along the module core. By simply installing the plate body into the formwork of the foundation and passing the anchor bolt through the insertion hole, it becomes possible to install the anchor bolt into the foundation with high precision.

「実施例」 以下、本発明の一実施例を図面を参照して説明する。"Example" Hereinafter, one embodiment of the present invention will be described with reference to the drawings.

第1図ないし第4図は本発明に係るアンカーボルト位置
決め用プレートの一実施例を示すもので、これらの図に
おいて、全体として符号5,6で示されるものがアンカ
ーボルト位置決め用プレートである。
1 to 4 show an embodiment of the anchor bolt positioning plate according to the present invention. In these figures, the anchor bolt positioning plates are generally designated by numerals 5 and 6.

符号5で示されるアンカーボルト位置決め用プレートは
、基礎を1み築する際に、基礎の出隅位置に設置されか
つアンカーボルト2を立てた状態に位置決め保持するも
のであり、具体的には、第1図ないし第3図に示すよう
に、全体が基e10の幅と同一の幅寸法りによってL字
型に形成されたプレート本体5aと、このプレート本体
5aのモジュール芯x−y、w−z上に位置して形成さ
れたアンカーボルト挿通孔5bとを主体として構成され
、かつ、前記アンカーボルト挿通孔5bには、アンカー
ボルト2の外周に弾性的に接触してアンカーボルト2を
立てた状態に保持する複数の舌片5cが挿通孔5bの周
囲に沿って並んで形成されている(第2図及び第3図参
照)。
The anchor bolt positioning plate indicated by the reference numeral 5 is installed at the protruding corner position of the foundation when building the foundation, and positions and holds the anchor bolt 2 in an upright state. Specifically, As shown in FIGS. 1 to 3, there is a plate main body 5a formed in an L-shape with the same width as the base e10, and module cores x-y, w- of this plate main body 5a. z, and the anchor bolt 2 is erected in elastic contact with the outer periphery of the anchor bolt 2 in the anchor bolt insertion hole 5b. A plurality of tongue pieces 5c that maintain the state are formed in line along the periphery of the insertion hole 5b (see FIGS. 2 and 3).

そして、前記アンカーボルト挿通孔5bは、実施例では
、基本モジュールに従ったグリッドプランニングにより
割付けされた壁パネルに形成されたボルト挿通孔の位置
にアンカーボルト2を位置させるごとくするため、モジ
ュール芯X−Y上においては、l/8モジユールに壁パ
ネル1の厚みの1/2の長さ寸法を加えた長さdiだけ
他のモジュール芯W−Zよりも離して形成され、またモ
ジュール芯W−Z上においては、他のモジュール芯X−
Yよりも1/8モジユールの長さ寸法dだけを離した位
置に形成された椙造となっている。
In the embodiment, the anchor bolt insertion hole 5b is arranged so that the anchor bolt 2 is positioned at the position of the bolt insertion hole formed in the wall panel allocated by grid planning according to the basic module. -Y, the module core W-Y is formed apart from other module cores W-Z by a length di, which is the addition of 1/2 the thickness of the wall panel 1 to the 1/8 module. On Z, other module core X-
It is a tsugi-zukuri structure formed at a position separated from Y by the length dimension d of 1/8 module.

なお、モジュール芯X−Y上のアンカーボルト挿通孔5
bを、もう一方の挿通孔5bよりも壁パネル1の厚みの
1/2の長さ寸法大きくとっているのは、出隅の位置で
パネルを据え付けたときに、パネルに勝ち負けができて
、壁パネルに形成したボルト挿通孔の位置が壁パネルl
の厚みの半分だけずれるからである。
In addition, the anchor bolt insertion hole 5 on the module core X-Y
The reason why b is made longer than the other insertion hole 5b by 1/2 the thickness of the wall panel 1 is because when the panel is installed at the position of the protruding corner, the panel can be damaged. The position of the bolt insertion hole formed in the wall panel is
This is because the difference is half the thickness of the

また舌片5cは、第3図に示すように、先端に行くに従
って先細りの形状とされ、アンカーボルト2を差し込む
とき、あるいは、アンカーボルト2からプレートを取り
外すときに第3図矢印に示すように上下にしなって、ア
ンカーボルト2の干渉をできる限り除くように配慮され
ている。
Further, as shown in FIG. 3, the tongue piece 5c has a tapered shape toward the tip, and when inserting the anchor bolt 2 or removing the plate from the anchor bolt 2, the tongue piece 5c is shaped as shown in the arrow in FIG. 3. The anchor bolts 2 are arranged vertically to eliminate interference with the anchor bolt 2 as much as possible.

一方、符号6で示されるアンカーボルト位置決め用プレ
ートは、基礎を構築する際に、基礎のT字型の位置に設
置されかつアンカーボルト2を立てた状態に位置決め保
持するものであり、具体的には、第4図に示すように、
全体が基礎10の幅と同一の幅寸法りによってT字型に
形成されたプレート本体6aと、このプレート本体6a
のモジュール芯x−y、w−z上に位置して形成された
アンカーボルト挿通孔6bとを主体として構成されてい
る。
On the other hand, the anchor bolt positioning plate indicated by the reference numeral 6 is installed at a T-shaped position on the foundation when constructing the foundation and positions and holds the anchor bolt 2 in an upright state. As shown in Figure 4,
A plate main body 6a whose whole is formed into a T-shape with the same width as the width of the foundation 10, and this plate main body 6a.
The anchor bolt insertion hole 6b is formed to be located on the module cores x-y and w-z.

そして、前記アンカーボルト挿通孔6bには、アンカー
ボルト2の外周に弾性的に接触してアンカーボルト2を
立てた状態に保持する複数の舌片6Cが挿通孔6bの周
囲に沿って並んで形成されている点は先のL字型をした
位置決めプレート5と同一である。
In the anchor bolt insertion hole 6b, a plurality of tongue pieces 6C are arranged along the periphery of the insertion hole 6b and elastically contact the outer periphery of the anchor bolt 2 to hold the anchor bolt 2 in an upright state. The points shown are the same as those of the L-shaped positioning plate 5 described above.

しかしながら、このT字型の位置決め用プレート6にお
いては、挿通孔6bがモジュール芯に沿って2列に配列
されている点が前述したL字型と異なる点である。これ
は、T字型の位置では、壁パネルの勝ち負けの組み合わ
せが種々考えられるからであり、実施例では、壁パネル
の勝ち負けの組み合わせを配慮して、1/8モジユール
の長さ寸法dだけを離した位置と、1/8モジユールに
壁パネル1の厚みの1/2の長さ寸法を加えた長さdi
だけを離した位置の2種類の位置にそれぞれボルト挿通
孔6bを有した形態となっている。
However, this T-shaped positioning plate 6 differs from the L-shaped plate described above in that the insertion holes 6b are arranged in two rows along the module core. This is because in the T-shaped position, various combinations of winning and losing wall panels are possible. The separated position and the length di, which is 1/8 module plus 1/2 the thickness of wall panel 1.
The bolt insertion hole 6b is provided at two different positions separated by a distance.

以上のように構成された位置決め用プレート5゜6は、
次のような壁体の構築方法に適用される。
The positioning plate 5゜6 configured as above is
This applies to the following wall construction methods:

すなわち、第5図に示すように、1基本モジュール(D
)に従ったグリッドに応じて壁体を割り付けし、このよ
うにして割付けした壁体を、木製の壁パネル1を面方向
に接合するとともに床面上にアンカーボルトを介して立
設することにより壁体を構築する方法において、前記ア
ンカーボルト2を基礎10に埋め込む場合に用いられる
ものである。
That is, as shown in FIG.
) by allocating the walls according to the grid, and by joining the wooden wall panels 1 in the plane direction and standing the walls upright on the floor via anchor bolts. This is used when the anchor bolt 2 is embedded in the foundation 10 in a method of constructing a wall.

しかも、この場合の施工方法では、壁体を構築する壁パ
ネル1の横框には、予めアンカーボルトの挿通孔1bを
、壁パネル1の接合端面1aから基本モジュールの1/
8の長さ寸法を離した位置に設定して形成してあり、ア
ンカーボルト2は、基礎上に据え付けるべき前記壁パネ
ル1のボルト挿通孔1bの位置に合わせて、基礎に埋め
込まれる工程が採られる。
Moreover, in the construction method in this case, the anchor bolt insertion holes 1b are made in advance in the horizontal stile of the wall panel 1 that constructs the wall, from the joint end surface 1a of the wall panel 1 to 1/2 of the basic module.
The anchor bolts 2 are embedded in the foundation in accordance with the positions of the bolt insertion holes 1b of the wall panel 1 to be installed on the foundation. It will be done.

次に、実施例にかかる位置決め用プレートの作用を、壁
体を実際に構築する場合を例にとって、第6図ないし第
11図に示す具体例に従って工程順に述べる。
Next, the function of the positioning plate according to the embodiment will be described in the order of steps according to the specific example shown in FIGS. 6 to 11, taking as an example the case where a wall is actually constructed.

!壁パネルの作成】 まず、壁体の構築方法において用いられる木製の壁パネ
ル1には、第6図及び第7図に示すようなボルト挿通孔
1bが形成される。すなわち、壁パネル1は、左右一対
の縦框1cとこれら縦框1cの上下端を接続する横框1
dとにより四角枠状に組まれ、かつ、その内部に十字に
補強用芯材1eが配設されるとともに、枠体の両面にそ
れぞれ面板1fが貼り付けられてなり、また、910m
mを1基本モジュールとした割付けに応じて、壁パネル
1の幅寸法が1基本モジュールを構成するように輻91
0mmとなるように形成される。
! Creation of Wall Panel] First, bolt insertion holes 1b as shown in FIGS. 6 and 7 are formed in the wooden wall panel 1 used in the wall construction method. That is, the wall panel 1 includes a pair of left and right vertical frames 1c and a horizontal frame 1 that connects the upper and lower ends of these vertical frames 1c.
d is assembled into a square frame shape, and a reinforcing core material 1e is arranged in a cross shape inside the frame, and face plates 1f are attached to both sides of the frame.
According to the assignment where m is one basic module, the width dimension of wall panel 1 is set to 91 so that it constitutes one basic module.
It is formed so that it is 0 mm.

そして、前記壁パネルlの上下の横框1dには、それぞ
れ壁パネル1の接合端面1aより1モジユール(D)の
1/8の長さ寸法d離した位置にボ。
The upper and lower horizontal frames 1d of the wall panel 1 are each provided with a hole at a position d apart from the joint end surface 1a of the wall panel 1 by a length of 1/8 of 1 module (D).

ルト挿通孔1bが形成され、またこのボルト挿通孔1b
はモジュール芯X−Y上に中心が位置するように形成さ
れる(第7図参照)。
A bolt insertion hole 1b is formed, and this bolt insertion hole 1b
is formed so that its center is located on the module core X-Y (see FIG. 7).

なお、実施例では壁パネルlの縦框】Cに、ダボ穴1g
が形成され、ダボ穴1gに嵌合する嵌合ビンを介して隣
接する壁パネルどうしが一体化されるようになっている
In addition, in the example, there is a dowel hole 1g in the vertical stile of wall panel L.
are formed, and adjacent wall panels are integrated with each other via fitting pins that fit into the dowel holes 1g.

そして、以上のように構成された壁パネル1は、たとえ
ば工場などにおいて、fIS8図に示すように、’!f
fI枚分の大きさのパネルPとして形成され、現場にお
いてアンカーボルト2にねじ止め固定されるものである
。ちなみに、第8図に示す図示例では、4つの壁パネル
1.l、IA、1Bが面方向に接合されて中央に開口部
を有したパネルPとされている。
The wall panel 1 configured as described above can be used, for example in a factory, as shown in fIS8. f
It is formed as a panel P having the size of fI sheets, and is fixed to the anchor bolt 2 with screws at the site. Incidentally, in the illustrated example shown in FIG. 8, four wall panels 1. 1, IA, and 1B are joined in the plane direction to form a panel P having an opening in the center.

また、このパネルPの中央部を構成する壁パネルIA、
IBは、横長に形成されて、パネルPをjh成する下端
および上端となる横框にそれぞれボルト挿通孔1bが形
成されたJR成となっている。
In addition, a wall panel IA that constitutes the center part of this panel P,
The IB is formed in a horizontally elongated manner, and has a JR configuration in which bolt insertion holes 1b are formed in the lower and upper horizontal frames forming the panel P, respectively.

なお、前記壁パネル1.A、IBに形成されたボルト挿
通孔1bも第6図及び第7図で説明した壁パネル1と同
様に、壁パネルの接合端面1aより1モジユール(D)
の1/8の長さ寸法d離した位置に形成されていること
は言うまでもなく、また、壁パネルIAの横框に形成さ
れたボルト挿通孔は2階壁パネルを連結する胴差しボル
トのボルト挿通孔として作用するようになっている。
Note that the wall panel 1. The bolt insertion holes 1b formed in A and IB are also 1 module (D) from the joint end surface 1a of the wall panel, similar to the wall panel 1 explained in FIGS. 6 and 7.
Needless to say, the bolt insertion holes formed in the horizontal stile of the wall panel IA are located 1/8 of the length d apart from the bolts of the bolts connecting the second floor wall panels. It is designed to act as an insertion hole.

[アンカーボルトの埋め込み1 璧パネルの作成工程で作成されたパネルは工場から現場
に運搬され、現場で施工された基礎10の上にアンカー
ボルト2を介して固定されるものであるが、MalOに
埋め込むべきアンカーボルト2は、壁パネルに形成した
ボルト挿通孔1bの位r、に合わせて基礎10に埋め込
まれる。
[Embedding of anchor bolts 1 The panels created in the wall panel creation process are transported from the factory to the site and fixed via anchor bolts 2 on the foundation 10 constructed at the site. The anchor bolts 2 to be embedded are embedded in the foundation 10 in alignment with the bolt insertion holes 1b formed in the wall panel.

アンカーボルト2を埋め込む場合には、次のような手順
が採られる。すなわち、出隅の位置においては、第1図
などに示すように、L字型の位置決め用プレートを基e
、10の成型型枠20の中に配置し、T字型に交差する
位置には、第4図などに示すように、T字型をした位置
決め用プレート6を配置する。
When embedding the anchor bolt 2, the following steps are taken. That is, at the position of the protruding corner, as shown in FIG.
, 10, and a T-shaped positioning plate 6 is placed at a position where the T-shape intersects, as shown in FIG.

そして、コンクリートが硬化する前に、アンカーボルト
挿通孔5b、6bを介してアンカーボルト2を基、礎1
0に突き差せば、位置決め用プレート5.6のアンカー
ボルト挿通孔5b、6bに挿入されたアンカーボルト2
はプレート本体5a、6aの挿通孔5b、6bに形成さ
れた複数の舌片5c、6cによって弾性的に支持され、
基礎10上に傾げることなく支持される。
Then, before the concrete hardens, anchor bolts 2 are inserted into the foundation 1 through the anchor bolt insertion holes 5b and 6b.
0, the anchor bolts 2 inserted into the anchor bolt insertion holes 5b and 6b of the positioning plate 5.6
are elastically supported by a plurality of tongue pieces 5c, 6c formed in the insertion holes 5b, 6b of the plate bodies 5a, 6a,
It is supported without tilting on the foundation 10.

また、プレート本体5a、6aは、基礎IOの幅と同一
の幅寸法によってL字型若しくはT字型に形成され、プ
レート本体5a、6aに形成されたアンカーボルト挿通
孔5b、6bはモジュール芯に沿って適宜の長さ寸法(
実施例では、予め壁パネルの勝ち負けを配處してモジュ
ール芯X−Y上では1/8モジユールに壁パネル1の厚
みの半分の長さを加えた長さdlをずらした位置と、モ
ジュール芯W−Z上では1/8モジユールの長さdをず
らした位置)に位置決めされて形成されているので、プ
レート本体5a、6aを基礎10の型枠20の中に設置
し、アンカーボルト2を挿通孔5b、6bに通すという
単純な操作によって、アンカーボルト2を精度良く、基
礎に施工することが可能になる。
Further, the plate bodies 5a, 6a are formed in an L-shape or T-shape with the same width as the width of the base IO, and the anchor bolt insertion holes 5b, 6b formed in the plate bodies 5a, 6a are formed in the module core. Along the appropriate length dimension (
In the example, the winning and losing of the wall panels are arranged in advance, and on the module core On W-Z, the plate bodies 5a and 6a are positioned at a position shifted by the length d of the 1/8 module, so the plate bodies 5a and 6a are installed in the formwork 20 of the foundation 10, and the anchor bolts 2 are The simple operation of passing the anchor bolt 2 through the insertion holes 5b and 6b allows the anchor bolt 2 to be installed on the foundation with high precision.

特に、このような壁体の溝築方法においては、壁パネル
のボルト挿通孔に合わせてアンカーボルト2の位置を設
定する構造上、出隅位置あるいはT字型に交差する位置
におけるアンカーボルト2を、第10図及び第11図な
どに示すように、モジュール芯X−Y上においては、1
/8モジユールに壁パネル1の厚みの1/2の長さ寸法
を加えた長さdlだけ他のモジュール芯W−Zよりも離
して埋め込み、またモジュール芯W−Z上においては、
他のモジュール芯X−Yよりも1/8モジユールの長さ
寸法dだけを離した位置に埋め込まなければならないが
、実施例にかかる位置決め用プレート5.6を用いた場
合には、アンカーボルト挿通孔5b、6bが予めそれら
の位置にすなわちアンカーボルト2を埋め込むべき位置
に形成されているので、アンカーボルト2を挿通孔5b
、6bに通すという単純な操作によって、アンカーボル
ト2を施工することができ、現場での作業性を向上でき
るといった利点を奏することができる。
In particular, in this wall groove construction method, the anchor bolts 2 are set at positions that match the bolt insertion holes in the wall panel. , as shown in FIGS. 10 and 11, on the module core X-Y, 1
/8 module plus 1/2 of the thickness of wall panel 1, which is the length dl, apart from other module cores W-Z and embedded, and on module core W-Z,
Although it is necessary to embed the module at a position separated by the length dimension d of 1/8 module from other module cores X-Y, when using the positioning plate 5.6 according to the embodiment, the anchor bolt insertion Since the holes 5b and 6b are formed in advance at those positions, that is, at the position where the anchor bolt 2 is to be embedded, the anchor bolt 2 is inserted into the insertion hole 5b.
, 6b, the anchor bolt 2 can be installed by a simple operation of passing it through the anchor bolts 6b and 6b, which has the advantage of improving workability on site.

「発明の効果」 以上説明したように本発明は、基本モジュールに従った
グリッドに応じて壁体を割り付けし、このようにして割
付けした壁体を、木製の壁パネルを面方向に接合すると
ともに床面上にアンカーボルトを介して立設することに
より構築する構造において、基礎を構築する際に、基礎
の出隅位置もしくはT字型に交差する位置に設置されか
つアンカーボルトを立てた状態に位置決め保持するアン
カーボルト位置決め用プレートであって、全体が基礎の
幅と同一の幅寸法によってL字型若しくはT字型に形成
されたプレート本体と、このプレート本体のモジュール
芯上に位置して形成されたアンカーボルト挿通孔とから
なり、かつ、前記アンカーボルト挿通孔には、アンカー
ボルトの外周に弾性的に接触してアンカーボルトを立て
た状態に保持する複数の舌片が挿通孔の周囲に沿って並
んで形成されていることを特徴とするものであるから、
基礎成型用型枠内にコンクリートを打設した後、L字型
若しくはT字型となった基礎のコンクリート上面にアン
カーボルト位置決め用プレートを載せ、コンクリートが
硬化する前に、アンカーボルト挿通孔を介してアンカー
ボルトを基礎に突き差す単純な操作によって、アンカー
ボルトを基礎上に傾げることなく支持することができる
ので、現場での作業性を向上することができ、またアン
カーボルトを粘度良く、基礎に施工することが可能にな
る。
"Effects of the Invention" As explained above, the present invention allocates walls according to a grid according to a basic module, and connects wooden wall panels in the plane direction to the walls thus allocated. In a structure that is constructed by standing on the floor via anchor bolts, when constructing the foundation, the structure is installed at a protruding corner position of the foundation or at a position that intersects in a T-shape, and the anchor bolt is erected. An anchor bolt positioning plate for positioning and holding, comprising a plate body whose entire shape is L-shaped or T-shaped with the same width as the width of the foundation, and a plate body positioned on the module core of this plate body. The anchor bolt insertion hole has a plurality of tongue pieces around the insertion hole that elastically contact the outer periphery of the anchor bolt and hold the anchor bolt in an upright state. It is characterized by being formed side by side along the
After pouring concrete into the foundation forming form, place an anchor bolt positioning plate on the top of the concrete of the L-shaped or T-shaped foundation, and insert the anchor bolt positioning plate through the anchor bolt insertion hole before the concrete hardens. By simply pushing the anchor bolt into the foundation, the anchor bolt can be supported on the foundation without tilting, improving work efficiency on site. It becomes possible to construct.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明にかかるアンカーボルト位置決め用プレー
トの一実施例を示すもので、第1図はL字型をした位置
決め用プレートの斜視図、第2図及び第3図は位置決め
用プレートの詳細を示すもので、f!;2図はその平面
図、第3図はその断面図、第4UAはT字型をした位置
決め用プレートの斜視図、第5図はこのアンカーボルト
位置決め用プレートを適用する場合の壁体の構築方法を
説明するために示した平面図、第6図ないし第11図は
壁体の構築方法を具体的に説明するために示したもので
、第6図及び第7図はそれぞれこの壁体の構築構造に用
いられる壁パネルの斜視図、第8図は複数の壁パネルを
接合して形成した1枚の大型の壁パネルを示す正面図、
第9図はアンカーボルトの埋め込み位置を説明するため
に示した基礎の斜視図、第10図は出隅位置のアンカー
ボルトの位置を説明するための平面図、第11図はT字
型に壁体が交差する位置のアンカーボルトの位置を説明
するための平面図である。 D・・・・・・基本モジュール、1・・・・・・壁パネ
ル、1a・・・・・・接合端面、1b・・・・・・アン
カーボルト挿通孔、2・・・・・・アンカーボルト、5
,6・・・・・・アンカーボルト位置決め用プレート、
lO・・・・・・基礎。
The drawings show an embodiment of the anchor bolt positioning plate according to the present invention, and FIG. 1 is a perspective view of the L-shaped positioning plate, and FIGS. 2 and 3 show details of the positioning plate. In what is shown, f! Figure 2 is a plan view thereof, Figure 3 is a sectional view thereof, 4UA is a perspective view of a T-shaped positioning plate, and Figure 5 is a construction of a wall when this anchor bolt positioning plate is applied. The plan views, Figures 6 to 11, shown to explain the method are shown to specifically explain the method of constructing the wall, and Figures 6 and 7 respectively show the construction of the wall. A perspective view of a wall panel used in the construction structure; FIG. 8 is a front view showing one large wall panel formed by joining a plurality of wall panels;
Figure 9 is a perspective view of the foundation shown to explain the embedded position of the anchor bolt, Figure 10 is a plan view to explain the position of the anchor bolt at the protruding corner position, and Figure 11 is a T-shaped wall. It is a top view for explaining the position of the anchor bolt at the position where bodies intersect. D: Basic module, 1: Wall panel, 1a: Joint end surface, 1b: Anchor bolt insertion hole, 2: Anchor bolt, 5
, 6... Anchor bolt positioning plate,
lO...Basic.

Claims (1)

【特許請求の範囲】 基本モジュールに従ったグリッドに応じて壁体を割り付
けし、このようにして割付けした壁体を、木製の壁パネ
ルを面方向に接合するとともに床面上にアンカーボルト
を介して立設することにより構築する構造において、基
礎を構築する際に、基礎の出隅位置もしくはT字型に交
差する位置に設置されかつアンカーボルトを立てた状態
に位置決め保持するアンカーボルト位置決め用プレート
であって、 全体が基礎の幅と同一の幅寸法によってL字型若しくは
T字型に形成されたプレート本体と、このプレート本体
のモジュール芯上に位置して形成されたアンカーボルト
挿通孔とからなり、かつ、前記アンカーボルト挿通孔に
は、アンカーボルトの外周に弾性的に接触してアンカー
ボルトを立てた状態に保持する複数の舌片が挿通孔の周
囲に沿って並んで形成されていることを特徴とするアン
カーボルト位置決め用プレート。
[Claims] Wall bodies are allocated according to a grid according to a basic module, and the thus allocated wall bodies are connected to wooden wall panels in the plane direction and attached to the floor surface via anchor bolts. Anchor bolt positioning plate that is installed at a protruding corner position of the foundation or at a position crossing a T-shape when constructing the foundation in a structure constructed by standing the anchor bolt upright. The plate body is formed into an L-shape or T-shape with a width dimension that is the same as the width of the foundation, and an anchor bolt insertion hole formed on the module core of the plate body. and the anchor bolt insertion hole is formed with a plurality of tongue pieces arranged along the periphery of the insertion hole to elastically contact the outer periphery of the anchor bolt and hold the anchor bolt in an upright state. An anchor bolt positioning plate characterized by:
JP2216172A 1990-08-16 1990-08-16 Anchor bolt positioning plate Expired - Lifetime JP2504613B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2216172A JP2504613B2 (en) 1990-08-16 1990-08-16 Anchor bolt positioning plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2216172A JP2504613B2 (en) 1990-08-16 1990-08-16 Anchor bolt positioning plate

Publications (2)

Publication Number Publication Date
JPH04102624A true JPH04102624A (en) 1992-04-03
JP2504613B2 JP2504613B2 (en) 1996-06-05

Family

ID=16684416

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2216172A Expired - Lifetime JP2504613B2 (en) 1990-08-16 1990-08-16 Anchor bolt positioning plate

Country Status (1)

Country Link
JP (1) JP2504613B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS568175A (en) * 1979-05-29 1981-01-27 Toshiba Corp Operating method of cleaning blade
JPS601849U (en) * 1983-06-20 1985-01-09 積水ハウス株式会社 Anchor bolt installation jig

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS568175A (en) * 1979-05-29 1981-01-27 Toshiba Corp Operating method of cleaning blade
JPS601849U (en) * 1983-06-20 1985-01-09 積水ハウス株式会社 Anchor bolt installation jig

Also Published As

Publication number Publication date
JP2504613B2 (en) 1996-06-05

Similar Documents

Publication Publication Date Title
KR102447901B1 (en) Connection system and method for prefabricated volumetric construction modules
US20080047225A1 (en) Construction Configurations and Construction Methods of Steel Houses
JP2010019075A (en) Interior substrate structure and method for forming interior substrate structure
US3813832A (en) Wall framing system using prefabricated panels
JPH04102624A (en) Positioning plate for anchor bolt
JPH0351452A (en) Panel unit for partitioning and work method for partitioning
JPH04102625A (en) Anchor bolt installation method
TWM587673U (en) Systematic formwork for buildings
CN217998513U (en) Partition plate convenient to set up door opening
JPH04209234A (en) Precast concrete panel and manufacture thereof
KR102476406B1 (en) Tile mounting fixture
JPH0489926A (en) Joining structure for substructure and superstructure
JPH04102651A (en) Construction method of wall body
JPH0794749B2 (en) Wall construction structure
JPH077384Y2 (en) Panels for surface formation of concrete foundations
JP3701707B2 (en) Ceiling structure of building unit
TWM645994U (en) Beam bottom support head of building formwork
JP2007191927A (en) Partition wall panel
JPH03279547A (en) Exterior wall panel and exterior wall construction method
JPH05295745A (en) Installing method for unit building
JP2796222B2 (en) Folded PC basic formwork
KR200229303Y1 (en) The corner type vertical unit for assembly of the light weight wall
JP2936492B2 (en) Concrete assembling basement and concrete assembling basement construction method
JPH1150582A (en) Floor structure
JPH02115459A (en) Assembling method for prefabricated room