JPH0399775A - Welding equipment for steel frame materials of multistoried structure - Google Patents
Welding equipment for steel frame materials of multistoried structureInfo
- Publication number
- JPH0399775A JPH0399775A JP23674589A JP23674589A JPH0399775A JP H0399775 A JPH0399775 A JP H0399775A JP 23674589 A JP23674589 A JP 23674589A JP 23674589 A JP23674589 A JP 23674589A JP H0399775 A JPH0399775 A JP H0399775A
- Authority
- JP
- Japan
- Prior art keywords
- story
- working
- floor
- frames
- welding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000003466 welding Methods 0.000 title claims abstract description 30
- 229910000831 Steel Inorganic materials 0.000 title claims description 5
- 239000010959 steel Substances 0.000 title claims description 5
- 239000000463 material Substances 0.000 title description 2
- 230000003028 elevating effect Effects 0.000 claims description 9
- 238000010276 construction Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
Abstract
Description
【発明の詳細な説明】
産業上の利用分野
本発明は、高層構造物における鉄骨材の溶接装置に関す
るものである。DETAILED DESCRIPTION OF THE INVENTION Field of the Invention The present invention relates to an apparatus for welding steel frames in high-rise structures.
従来の技術
従来、高層構造物例えば高層ビルディングの鉄骨材すな
わち骨組みを構築する場合、タワークレーンにより骨組
みを順次上方に運び上げて、熟練した作業具により骨組
み同士の位置合わせおよび組み立てが行われている。こ
の構築方法によると、人手により骨組みの位置合わせお
よび組み立てが行われるため、その構築に時間を要する
とともに風雨が強い1ヨなどは作業を行うことができず
、工期に影響を及ぼすという問題がある。これを防止す
る方法として、クレーンなどの作業装置を配置するとと
もに安全を図るために広いスペースを確保し得る作業階
を設け、かつ最後にこの作業階を構造物の最上階として
使用することが考えられる。BACKGROUND ART Conventionally, when building steel frames for high-rise structures, such as high-rise buildings, the frames are sequentially lifted upward by a tower crane, and the frames are aligned and assembled using skilled workers. . According to this construction method, the positioning and assembly of the framework is done manually, so there is a problem in that it takes time to construct the structure and work cannot be done in strong winds and rain, which affects the construction period. . As a way to prevent this, it is possible to install work equipment such as cranes, create a work floor that can secure a large space for safety, and finally use this work floor as the top floor of the structure. It will be done.
発明が解決しようとする課題
ところで、上記のように作業階を設けてその下層階を順
次組み立てていく場合でも、骨組み同士の溶接は、やは
り手作業で行われるため、したがって時間を要するとと
もに、溶接機などをその階の作業終了ごとに次の組立て
階に移動させる必要があり、非常に面倒な作業になると
いう問題が生じる。Problems to be Solved by the Invention By the way, even in the case where a working floor is provided and the lower floors are assembled one after another as described above, welding between the frames is still done manually, which takes time and requires a lot of welding. It is necessary to move the machine to the next assembly floor every time the work on that floor is completed, which creates a problem that the work becomes extremely troublesome.
課題を解決するための手段
上記課題を解決するため、本発明の高層構造物における
鉄骨材の溶接装置は、高層構造物の最」二階の層となる
ように骨組みが組み立てられるとともにこれよりも下層
階の骨組みの組み立て用作業装置が配置された作業階に
、走行レールを設け、この走行レール上を走行自在にさ
れ且つ昇降自在にされた昇降部材を設け、この昇降部材
に多関節式の溶接ロボットを設けたものである。Means for Solving the Problems In order to solve the above problems, the present invention provides a welding apparatus for steel frames for high-rise structures, in which the frame is assembled to be the second-most floor of the high-rise structure, and the frame is assembled to the second floor of the high-rise structure. A traveling rail is provided on the working floor where the work equipment for assembling the floor frame is arranged, and an elevating member that can run freely on the traveling rail and can be raised and lowered is provided, and this elevating member is welded with multiple joints. It is equipped with a robot.
作用
上記構成によると、高層構造物を構築する際の各層の骨
組みを溶接する溶接ロボットを、その構造物の最上階と
なる作業階に配置された昇降部材に取り付けたので、溶
接ロボットは作業階と一緒に」1昇されるため、従来の
ように溶接機をその都度、持ち上げる必要が無い。Function According to the above configuration, the welding robot that welds the framework of each layer when constructing a high-rise structure is attached to the lifting member placed on the working floor, which is the top floor of the structure. Since the welding machine is raised by 1 at the same time as the welding machine, there is no need to lift the welding machine each time.
実施例 以下、本発明の一実施例を図面に基づき説明する。Example Hereinafter, one embodiment of the present invention will be described based on the drawings.
本発明に係る溶接装置は、高層構造物を構築する際に、
予め最上階として組み立てられるとともにクレーンなど
の各種組立て用の作業装置が配置された作業階に設けら
れるものであり、この作業階を使用して順次骨組み祠が
組み立てられていく。The welding device according to the present invention, when constructing a high-rise structure,
It is pre-assembled as the top floor and is installed on a working floor where various assembly work devices such as cranes are arranged, and this working floor is used to sequentially assemble the skeleton shrine.
すなわち、第1図および第2図において、1は高層構造
物の最上階として組み立てられるとともに各種組立て用
の作業装置および昇降装置2が配置された作業階である
。なお、上記昇降装置2は作業階1自身を昇降させるた
めのものである。」二足作業階1の周囲、例えば左右の
両側部の上下には走行レール3が設けられている。そし
て、これら両レール3には、下端部に多関節式の溶接ロ
ボット4が取り付けられた昇降部材5が支持されている
。この昇降部材5は、例えば第1図の右側に示すように
、走行レール3」二を走行駆動輪6を介して走行自在な
走行台車7と、この走行台車7にラック・ピニオン機構
8を介して昇降自在に設けられた昇降棒9とから構成さ
れ、または第1図の左側に示すように、上記昇降部材5
として、上部に走行レール3上を走行する走行駆動輪1
0が設けられた多段式の伸縮棒11を使用してもよい。That is, in FIGS. 1 and 2, numeral 1 is a working floor that is assembled as the top floor of a high-rise structure, and in which various assembly work devices and lifting devices 2 are arranged. Note that the lifting device 2 is for raising and lowering the work floor 1 itself. '' Traveling rails 3 are provided around the two-legged work floor 1, for example above and below both left and right sides. Both rails 3 support an elevating member 5 having an articulated welding robot 4 attached to its lower end. For example, as shown on the right side of FIG. 1, this elevating member 5 includes a traveling truck 7 that can freely travel on a traveling rail 3'2 via driving wheels 6, and a rack and pinion mechanism 8 connected to the traveling truck 7. or as shown on the left side of FIG.
As shown in FIG.
A multistage telescopic rod 11 provided with 0 may be used.
上記作業階1を使用して、高層構造物を組み立てる場合
、まず作業階1を基礎12上に配置するとともに、作業
階1に設けれられた昇降装置2の脚部2aを伸ばして、
この作業階1を所定高さに維持した後、この作業階1の
下方の部分に1階部分の骨組み13を配置してその下端
部を基礎12側に固定する。この時、互いに隣接する骨
組み13同士の接合端部、例えば第3図および第4図に
示すように、水平桁材14のフランジ部同士は、溶接ロ
ボット4により自動的に溶接される。勿論、溶接ロボッ
ト4は、各溶接位置に昇降部材5を介して案内される。When assembling a high-rise structure using the working floor 1, first place the working floor 1 on the foundation 12, and extend the legs 2a of the lifting device 2 provided on the working floor 1.
After this working floor 1 is maintained at a predetermined height, the framework 13 of the first floor part is placed in the lower part of this working floor 1, and its lower end is fixed to the foundation 12 side. At this time, the welding robot 4 automatically welds the joint ends of the frames 13 adjacent to each other, for example, the flanges of the horizontal beam members 14 as shown in FIGS. 3 and 4. Of course, the welding robot 4 is guided to each welding position via the elevating member 5.
1階部分の組立てが済むと、再び昇降装置2を使用して
作業階1を上昇させた後、2階部分の骨組み15を配置
する。そして、2階から」二層部分の各骨組み15の溶
接は、同じ階の骨組み15同士の溶接の他に、その階よ
り1階下側の骨組み13との溶接も行われる。すなわち
、第5図および第6図に示すように、柱部16同士の溶
接も行われる。このようにして、所定高さの構造物が組
み立てが終了すると、作業階1がそのまま最上階として
使用される。勿論、最後に各種5
作業装置および溶接ロボット4などの装置は、分解して
ウィンチ装置などにより、地上に降ろされる。When the first floor part is assembled, the lifting device 2 is used again to raise the working floor 1, and then the frame 15 of the second floor part is placed. The welding of each frame 15 in the two-story section from the second floor is performed not only with welding between frames 15 on the same floor, but also with frames 13 one floor below that floor. That is, as shown in FIGS. 5 and 6, the pillar portions 16 are also welded together. In this way, when a structure of a predetermined height is assembled, the working floor 1 is used as the top floor. Of course, at the end, the various 5 working devices and devices such as the welding robot 4 are disassembled and lowered to the ground using a winch device or the like.
発明の効果
以」二のように本発明の構成によると、高層構造物を構
築する際の各層の骨組みを溶接する溶接ロボットを、そ
の構造物の最上階となる作業階に配置された昇降部材に
取り付けたので、溶接ロボットは作業階と一緒に上昇さ
れるため、従来のように溶接機をその都度、持ち上げる
必要が無く、シたがって組立て作業が非常に容易に行う
ことができる。Effects of the Invention According to the structure of the present invention as described in 2., a welding robot that welds the frames of each layer when constructing a high-rise structure is connected to a lifting member placed on the working floor that is the top floor of the structure. Since the welding robot is mounted on the floor, the welding robot is raised together with the work floor, so there is no need to lift the welding machine each time as in the conventional case, and assembly work can therefore be performed very easily.
図面は本発明の一実施例を示すもので、第1図は高層構
造物の組立て作業を示す概略正面図、第2図は第1図に
おいて溶接装置を省略した側面図、第3図は水平桁材の
溶接作業を示す平面図、第4図は第3図のI−I矢視図
、第5図は柱部の溶接作業を示す平面図、第6図は第5
図の■−■矢視図である。
6
1・・・・作業階、2・・・・昇降装置、3・・・・走
行レール、4・・・・溶接ロボット、5・・・・昇降部
材、7・・・・走行台車、8・・・・ラック・ピニオン
機構、9・・・・昇降棒、11・・・・伸縮棒、13.
15・・・・骨組み。The drawings show one embodiment of the present invention; Fig. 1 is a schematic front view showing the assembly work of a high-rise structure, Fig. 2 is a side view with the welding equipment omitted from Fig. 1, and Fig. 3 is a horizontal view. FIG. 4 is a plan view showing the welding work of the girder material, FIG. 4 is a view taken along the I-I arrow in FIG. 3, FIG.
It is a view taken along the ■-■ arrow in the figure. 6 1... Working floor, 2... Elevating device, 3... Traveling rail, 4... Welding robot, 5... Elevating member, 7... Traveling trolley, 8 ... Rack and pinion mechanism, 9 ... Lifting rod, 11 ... Telescopic rod, 13.
15...Skeleton.
Claims (1)
立てられるとともにこれよりも下層階の骨組みの組み立
て用作業装置が配置された作業階に、走行レールを設け
、この走行レール上を走行自在にされ且つ昇降自在にさ
れた昇降部材を設け、この昇降部材に多関節式の溶接ロ
ボットを設けたことを特徴とする高層構造物における鉄
骨材の溶接装置。1. A running rail is installed on the work floor where the framework is assembled to be the top floor of a high-rise structure, and where work equipment for assembling the framework on the lower floors is installed, and the vehicle runs on this running rail. 1. A welding device for steel frames in a high-rise structure, characterized in that an elevating member that is movable and movable up and down is provided, and an articulated welding robot is provided on the elevating member.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP23674589A JPH0399775A (en) | 1989-09-12 | 1989-09-12 | Welding equipment for steel frame materials of multistoried structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP23674589A JPH0399775A (en) | 1989-09-12 | 1989-09-12 | Welding equipment for steel frame materials of multistoried structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0399775A true JPH0399775A (en) | 1991-04-24 |
Family
ID=17005161
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP23674589A Pending JPH0399775A (en) | 1989-09-12 | 1989-09-12 | Welding equipment for steel frame materials of multistoried structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0399775A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0510034A (en) * | 1991-07-01 | 1993-01-19 | Fujita Corp | Structural body moving equipment |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62246487A (en) * | 1986-04-16 | 1987-10-27 | 学校法人早稲田大学 | Wall-member mounting robot in push-up system |
-
1989
- 1989-09-12 JP JP23674589A patent/JPH0399775A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62246487A (en) * | 1986-04-16 | 1987-10-27 | 学校法人早稲田大学 | Wall-member mounting robot in push-up system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0510034A (en) * | 1991-07-01 | 1993-01-19 | Fujita Corp | Structural body moving equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6749573B1 (en) | Construction method based on mobile work platform for steel box girder overpass construction | |
JP2008162749A (en) | Jib crane | |
JP2909413B2 (en) | Suspension device for building exterior walls | |
CN113404281A (en) | Climbing type scaffold, climbing and mounting method thereof and construction method of fabricated building | |
JPH0399775A (en) | Welding equipment for steel frame materials of multistoried structure | |
JP2539150B2 (en) | Bridge erection equipment | |
JPH05133016A (en) | Peripheral supporting self-rising type building engineering method | |
JPH0319567Y2 (en) | ||
JPH08333898A (en) | Trestle for vertically and horizontally conveying building blocks | |
JP2580734Y2 (en) | Mobile hanging scaffolding equipment | |
JPH10245994A (en) | Temporary curing body | |
JPH04213668A (en) | Building construction method using floor climbing type movable jib crane | |
JP2761518B2 (en) | Construction method of building | |
JP2622320B2 (en) | Building construction method for building erection factory | |
CN215331380U (en) | Rail type suspension platform | |
JP2539142Y2 (en) | Lifting device for temporary roof | |
JP2776128B2 (en) | Lifting device for building frame | |
JP2810967B2 (en) | Pre-assembly method of column-beam integrated unit and its apparatus | |
JP3192543B2 (en) | Building demolition method | |
JP2934567B2 (en) | Work gondola for multi-story parking lot construction | |
JPH028098B2 (en) | ||
JPH0445629B2 (en) | ||
JPH04319172A (en) | Skeleton building construction workbench | |
CN117703448A (en) | Multi-degree-of-freedom mobile trolley for assembled subway station | |
KR100195784B1 (en) | Construction materials yard on a building |