Prior art keywords
vertical joint
lead wire
vertical
exterior wall
wall panels
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP25193283A
Other languages
Japanese (ja)
Other versions
JPS60141939A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP25193283A priority Critical patent/JPS60141939A/en
Publication of JPS60141939A publication Critical patent/JPS60141939A/en
Publication of JPH0355622B2 publication Critical patent/JPH0355622B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Finishing Walls (AREA)
  • Building Environments (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Description

【発明の詳細な説明】 本発明は、縦目地施工方法、詳しくはカーテン
ウオール工法における外壁パネル間の縦目地施工
方法の改良に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a vertical joint construction method, and more particularly to an improvement in a vertical joint construction method between exterior wall panels in a curtain wall construction method.

PC版等予め工場で製造された外壁パネルを鉄
骨コンクリートの躯体にフアスナーを用いて張設
する、いわゆるカーテンウオール工法では、構造
上及び美観上隣接する外壁パネル間に隙を設ける
必要がある。このため、外壁パネルを総て張設し
た後、必ずその隙、即ち目地をコーキングして外
部からの雨水等の浸入を防止しなければならな
い。この目地処理において、横目地は、外壁パネ
ル間に水切り板を介在させたり、或いは外壁パネ
ルの上端及び下端に互いに嵌め合い可能な段部を
形成する等して外壁パネルの継目部分の形状を工
夫することで比較的容易に処理できるが、縦目地
は構造上横目地と同様には処理できない。
In the so-called curtain wall construction method, in which prefabricated exterior wall panels such as PC boards are attached to a steel-framed concrete frame using fasteners, gaps must be created between adjacent exterior wall panels for structural and aesthetic reasons. For this reason, after all the exterior wall panels are installed, the gaps, or joints, must be caulked to prevent rainwater from entering from outside. In this joint treatment, the shape of the joint part of the exterior wall panels is modified by interposing a draining board between the exterior wall panels, or by forming steps that can fit into each other at the top and bottom ends of the exterior wall panels. However, vertical joints cannot be treated in the same way as horizontal joints due to their structure.

従来、縦目地の処理は、第6図に示すように、
外壁パネル20,20間の目地21に、スポンジ
等のバツクアツプ材22を予め外壁パネル20,
20張設時に装填しておき、全外壁パネル張設
後、そのバツクアツプ材22の前面に、油性のコ
ーキング材23、例えばチオコール系コーキング
材を充填することにより行つている。尚、図中2
4はフアスナー、25は躯体、26は二次シー
ル、27は気圧調整スペースである。
Traditionally, vertical joints were treated as shown in Figure 6.
A backup material 22 such as sponge is applied to the joint 21 between the outer wall panels 20 and 20 in advance.
This is done by filling the front surface of the back-up material 22 with an oil-based caulking material 23, for example, a thiocol-based caulking material, after the entire outer wall panel is tensioned. In addition, 2 in the figure
4 is a fastener, 25 is a frame, 26 is a secondary seal, and 27 is an air pressure adjustment space.

上記のような方法は、主に中高層建造物におい
て行われるが、第7図に示すような3階建てまで
の低層鉄骨コンクリート住宅にあつては、第8図
に示すように、例えば、ALC版等の外壁パネル
30,30を躯体31に張設していく毎に外壁パ
ネル30,30間の目地32に鉄筋33を挿入す
ると共に、この目地32内にバツクアツプ材とし
てコンクリート34を流し込んでいき、最後にコ
ンクリート34前面にコンクリート34前面に上
記したようなコーキング材35を充填することに
より行つている。
The above method is mainly used for medium-to-high-rise buildings, but for low-rise steel-framed concrete houses up to 3 stories as shown in Figure 7, for example, ALC version is used as shown in Figure 8. Each time the outer wall panels 30, 30, etc. are stretched on the frame 31, reinforcing bars 33 are inserted into the joints 32 between the outer wall panels 30, 30, and concrete 34 is poured into the joints 32 as a backup material. Finally, this is done by filling the front surface of the concrete 34 with the caulking material 35 as described above.

ところで、上記したようなコーキング材充填作
業は、外壁の周りに広いスペースがあれば何等支
障なく行うことができるが、周りに他の建物が立
て込んでいる、いわゆる狭小地では外壁と隣接す
る建築物との間が非常に狭いため、上記コーキン
グ材充填作業はほとんど不可能である。この場
合、作業員が手に直接コーキング材を付けて手の
届く範囲の目地にだけ手探りで充填しているのが
現状で、どうしてもコーキング不良を避けること
ができない。
Incidentally, the caulking filling work described above can be carried out without any problems if there is a wide space around the exterior wall, but in so-called narrow areas where other buildings are built around the exterior wall, it may be necessary to fill the caulking material with the exterior wall and the adjacent building. Since the space between the two is very narrow, the above-mentioned caulking material filling operation is almost impossible. In this case, the current situation is that workers apply caulk directly to their hands and fill only the joints within reach, making it impossible to avoid caulking defects.

本発明は係る点に鑑み、外壁周りに作業スペー
スが全くなくとも外壁パネル間の縦目地処理を完
全に行うことができ、しかも縦目地処理工程及び
処理部材の節減、さらには作業効率の向上も図る
ことのできる新規な縦目地施工方法を提供するこ
とを目的とする。
In view of the above points, the present invention enables complete treatment of vertical joints between exterior wall panels even if there is no work space around the exterior wall, reduces vertical joint treatment process and processing materials, and further improves work efficiency. The purpose of this study is to provide a new vertical joint construction method that can achieve the desired results.

本発明の要旨は、外壁パネル間に形成される縦
目地内には上方または下方からリード線を挿通
し、該リード線の先端に軟質で適当な水密性を有
する長尺の縦目地材を取り付けた後、前記リード
線を引き戻して前記縦目地内に前記縦目地材を装
着することを特徴とする縦目地施工方法に存す
る。
The gist of the present invention is to insert a lead wire from above or below into the vertical joint formed between exterior wall panels, and attach a long vertical joint material that is soft and has appropriate watertightness to the tip of the lead wire. The vertical joint construction method is characterized in that the lead wire is then pulled back and the vertical joint material is installed in the vertical joint.

以下、本発明の構成を実施例について図面を参
照して説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The configuration of the present invention will be described below with reference to embodiments with reference to the drawings.

第1図乃至第3図において、本発明に係る縦目
地施工方法は、まず全外壁パネル1…を躯体2の
スラブ3または梁4に縦目地5…が縦に一直線と
なるように取り付けた後、屋上6から縦目地5内
にリード線7を挿入し、該リード線7の先端8を
縦目地5の下端5bより引き出す。尚、リード線
7の先端8が引き出し易いように、基礎9には縦
目地5の相当する箇所に切り欠き10を設けてい
る。次に、縦目地5の下端5bから引き出された
リード線7の先端8に、縦目地材11をガイド部
材12を介して取り付けた後、リード線7を屋上
6から引き上げ、縦目地5内に縦目地材11を挿
通していく。そして、縦目地材11の先端が屋上
6に達するまでのリード線7を引き上げたら、即
ち縦目地材11の装着が完了したら引き上げるの
をやめ、最後に縦目地5の上端5a及び下端5b
で縦目地材11を切断すると共に、基礎9の切り
欠き10をモルタル等で閉塞して縦目地施工を完
了する。
1 to 3, the vertical joint construction method according to the present invention involves first attaching all the external wall panels 1 to the slab 3 or beam 4 of the frame 2 so that the vertical joints 5 are aligned vertically. A lead wire 7 is inserted into the vertical joint 5 from the rooftop 6, and the tip 8 of the lead wire 7 is pulled out from the lower end 5b of the vertical joint 5. Note that a notch 10 is provided in the foundation 9 at a location corresponding to the vertical joint 5 so that the tip 8 of the lead wire 7 can be easily pulled out. Next, after attaching the vertical joint material 11 to the tip 8 of the lead wire 7 pulled out from the lower end 5b of the vertical joint 5 via the guide member 12, the lead wire 7 is pulled up from the rooftop 6 and inserted into the vertical joint 5. The vertical joint material 11 is inserted. Then, when the lead wire 7 is pulled up until the tip of the vertical joint material 11 reaches the rooftop 6, that is, when the installation of the vertical joint material 11 is completed, the pulling is stopped, and finally the upper end 5a and the lower end 5b of the vertical joint material 5 are pulled up.
The vertical joint material 11 is cut, and the notch 10 of the foundation 9 is closed with mortar or the like to complete the vertical joint construction.

尚、横目地13…の処理は、外壁パネル1…を
張設していく際にシート状の目地材を介在させる
か、或いは縦目地5の処理が完了した後にコーキ
ング材を充填する等作業条件に応じて適宜従来通
りに行えばよい。
The horizontal joints 13... may be treated according to work conditions such as interposing a sheet-like joint material when installing the exterior wall panels 1... or filling the vertical joints 5 with caulking material after the vertical joints 5 have been treated. Depending on the situation, it may be carried out in the conventional manner.

本発明に係る縦目地施工方法において用いられ
る上記リード線7は、金属線、例えば電話工事等
の配線工事に用いられるものが好適である。また
その他硬質の合成樹脂材からなるものであつても
よい。
The lead wire 7 used in the vertical joint construction method according to the present invention is preferably a metal wire, for example, one used for wiring work such as telephone work. It may also be made of other hard synthetic resin materials.

このリード線7を引き戻すにはウインチを用い
てもよいし、手で行つてもよい。
A winch may be used to pull back the lead wire 7, or this may be done manually.

また、上記縦目地材11は、軟質で適当な水密
性を有する、例えば合成ゴム等の弾性材料が好ま
しい。この縦目地材11は、第4図に示すよう
に、断面略円形の中空の長尺体であつて、その中
空部11aの内壁11bには軸方向に複数のV字
状の溝11c…が適当間隔で設けられている。こ
の溝11cは、縦目地材11に径方向に適当な弾
性を与え、縦目地5の内部を挿通する時には径方
向に収縮して縦目地5との摩擦抵抗が減るよう
に、また挿通後には径方向に復元して水密性が高
くなるように設けられたものである。また、縦目
地材11の先端の中空部11aの内壁11bに
は、第5図に示すように、前記ガイド部材12を
装着するためのねじ11dが刻設されている。
尚、この縦目地材11の外周面全体に潤滑剤を塗
付しておくと、縦目地5内の挿通がより容易とな
る。
Further, the vertical joint material 11 is preferably made of an elastic material such as synthetic rubber, which is soft and has appropriate watertightness. As shown in FIG. 4, this vertical joint material 11 is a hollow elongated body with a substantially circular cross section, and a plurality of V-shaped grooves 11c are formed in the inner wall 11b of the hollow portion 11a in the axial direction. They are placed at appropriate intervals. This groove 11c gives appropriate elasticity to the vertical joint material 11 in the radial direction, so that when it is inserted into the vertical joint 5, it contracts in the radial direction and reduces the frictional resistance with the vertical joint 5. It is designed to restore watertightness in the radial direction. Further, as shown in FIG. 5, a screw 11d for mounting the guide member 12 is cut into the inner wall 11b of the hollow portion 11a at the tip of the vertical joint filler 11.
Incidentally, if a lubricant is applied to the entire outer circumferential surface of the vertical joint material 11, insertion into the vertical joint material 5 becomes easier.

上記ガイド部材12は、金属或いは硬質の合成
樹脂材からなり、例えば第5図に示すように、円
錐体状に形成された尖鋭部12aと、この尖鋭部
12aの下部に縦目地材11のねじ11dと螺合
する雄ねじ12cが刻設された胴体部12bとが
一体に形成されたものである。その尖鋭部12a
の先端には前記リード線7を取り付けるための取
付孔12dが設けられている。この取付孔12d
にリード線7を取り付けるには、リード線7の先
端8を取付孔12dに挿通した後、リード線7の
先端8に取付孔12dより大きな結び目を作り、
この結び目と取付孔12dとを係合させることに
より行う。
The guide member 12 is made of metal or a hard synthetic resin material, and as shown in FIG. 11d and a body portion 12b having a male screw 12c carved thereon to be screwed together are integrally formed. The sharp part 12a
An attachment hole 12d for attaching the lead wire 7 is provided at the tip. This mounting hole 12d
To attach the lead wire 7, insert the tip 8 of the lead wire 7 into the attachment hole 12d, then tie a knot larger than the attachment hole 12d at the tip 8 of the lead wire 7.
This is done by engaging this knot with the attachment hole 12d.

尚、このガイド部材12を用いずに、リード線
7の先端8に係止爪を設けて縦目地材11に係止
する等してリード線7と縦目地材11とを直接取
り付けてもよい。
Note that, without using this guide member 12, the lead wire 7 and the vertical joint material 11 may be directly attached by providing a locking claw at the tip 8 of the lead wire 7 and locking it to the vertical joint material 11. .

本発明に係る縦目地施工方法は、前述したよう
に全外壁パネル張設後、縦目地全長に亘つて一度
に縦目地材を装着することに限らず、各階の外壁
パネル張設作業を終了する毎に行つてもよい。ま
た、縦目地材の挿通方向は上方、下方いずれから
でもよい。
The vertical joint construction method according to the present invention is not limited to installing vertical joint materials all at once over the entire length of the vertical joint after all the exterior wall panels have been stretched, as described above, but also by completing the work of constructing the exterior wall panels on each floor. You can go every time. Further, the direction of insertion of the vertical joint material may be either from above or from below.

以上説明したように、本発明は、外壁パネル間
に形成される縦目地内に上方または下方からリー
ド線を挿通し、該リード線の先端に軟質で適当な
水密性を有する長尺の縦目地材を取り付けた後、
前記リード線を引き戻して前記縦目地内に前記縦
目地材を装着するもので、従来のように縦目地の
処理を外壁周りから行うものではないため、狭小
地であつても完全な縦目地処理ができる。また、
足場やゴンドラを一切使用することなく縦目地の
処理を行うことができ、作業の安全を図ることが
できると共に工期の短縮さらには建築コストの低
減化を図ることができる。さらに、縦目地が縦一
直線に形成されている場合は、全階に亘つて一括
して縦目地材を取り付けることができるので、極
めて作業性がよく、壁体工事全体の工期を大幅に
短縮することができる等優れた効果を奏する。
As explained above, the present invention involves inserting a lead wire from above or below into a vertical joint formed between exterior wall panels, and forming a long vertical joint that is soft and has appropriate watertightness at the tip of the lead wire. After installing the material,
The lead wire is pulled back and the vertical joint material is installed inside the vertical joint, and the vertical joint is not treated from around the outer wall as in the past, so it is possible to completely treat the vertical joint even in narrow spaces. I can do it. Also,
Vertical joints can be treated without using any scaffolding or gondolas, making work safer, shortening construction time, and reducing construction costs. Furthermore, if the vertical joints are formed vertically in a straight line, it is possible to install the vertical joint material on all floors at once, making it extremely easy to work and significantly shortening the overall construction period for wall construction. It has excellent effects such as:

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第5図は本発明に係る縦目地施工方
法の一実施例を示し、第1図は外壁の正面図、第
2図は第1図で示す−線断面図、第3図は基
礎上における縦目地の下端を躯体内側から見た部
分斜視図、第4図は第1図における−線断面
図、第5図はリード線、ガイド部材及び縦目地材
を示す斜視図、第6図は従来例を示す縦断面図、
第7図は3階建て鉄骨コンクリート住宅の斜視
図、第8図は従来例を示すよこ断面図である。 1…外壁パネル、5…縦目地、7…リード線、
8…先端、11…縦目地材。
1 to 5 show an embodiment of the vertical joint construction method according to the present invention, in which FIG. 1 is a front view of an outer wall, FIG. 2 is a sectional view taken along the line shown in FIG. 1, and FIG. FIG. 4 is a partial perspective view of the lower end of the vertical joint on the foundation seen from the inside of the building frame; FIG. 4 is a sectional view taken along the line - - in FIG. 1; FIG. The figure is a vertical cross-sectional view showing a conventional example.
FIG. 7 is a perspective view of a three-story steel-framed concrete house, and FIG. 8 is a horizontal sectional view showing a conventional example. 1... External wall panel, 5... Vertical joint, 7... Lead wire,
8...Tip, 11...Vertical joint material.

Claims (1)

【特許請求の範囲】[Claims] 1 外壁パネル間に形成される縦目地内に上方ま
たは下方からリード線を挿通し、該リード線の先
端に軟質で適当な水密性を有する長尺の縦目地材
を取り付けた後、前記リード線を引き戻して前記
縦目地内に前記縦目地材を装着することを特徴と
する縦目地施工方法。
1. Insert a lead wire from above or below into the vertical joint formed between exterior wall panels, attach a long vertical joint material that is soft and has appropriate watertightness to the tip of the lead wire, and then insert the lead wire A vertical joint construction method, comprising: pulling back the vertical joint material and installing the vertical joint material inside the vertical joint.
JP25193283A 1983-12-27 1983-12-27 Construction of vertical joint Granted JPS60141939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25193283A JPS60141939A (en) 1983-12-27 1983-12-27 Construction of vertical joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25193283A JPS60141939A (en) 1983-12-27 1983-12-27 Construction of vertical joint

Publications (2)

Publication Number Publication Date
JPS60141939A JPS60141939A (en) 1985-07-27
JPH0355622B2 true JPH0355622B2 (en) 1991-08-23

Family

ID=17230112

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25193283A Granted JPS60141939A (en) 1983-12-27 1983-12-27 Construction of vertical joint

Country Status (1)

Country Link
JP (1) JPS60141939A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS635108U (en) * 1986-06-28 1988-01-13
JP2556352Y2 (en) * 1992-08-07 1997-12-03 堀江金属工業株式会社 Fuel tank

Also Published As

Publication number Publication date
JPS60141939A (en) 1985-07-27

Similar Documents

Publication Publication Date Title
US5555698A (en) Building panel apparatus and method
US6928778B2 (en) Stucco anchorage nail
US5099623A (en) Prefabricated wall insert and method of installation
EP1266106A2 (en) Sealing and insulating system having a sealing and insulating profile
JPH0355622B2 (en)
CH662849A5 (en) METHOD FOR PRODUCING A BUILDING AND A BUILDING PRODUCED BY THIS METHOD.
DE3128246A1 (en) Mounting system for facing-masonrywork elements
WO2006012661A1 (en) Method for in-situ production of a flat roof or terrace
JP4087959B2 (en) Building floor panels and construction methods
EP2154303A2 (en) Expansion joint profile for covering an expansion joint
KR101115016B1 (en) Construction method for building remodeling by using precast panel, and connecting structure for remodeling precast panel
JPS5830946Y2 (en) Anchor structure for replacement sash
JP4222580B2 (en) Building foundation construction method
JPH0626167A (en) Joint structure
DE19841294A1 (en) Finishing strip for plastering walls in corner or border regions e.g. around windows, doors, cavities, recesses and supports
JP7310502B2 (en) Opening construction method
DE3415252A1 (en) Lightweight building-element system which conforms to more stringent thermal requirements
JP4173230B2 (en) Ceiling construction method and its suspension
KR960009416Y1 (en) Assembling wall structure
JP4236221B2 (en) Exterior wall panel of building and its manufacturing method
JP2001090236A (en) External wall alc panel and method for installing the same
JPS6336092Y2 (en)
JP3004904B2 (en) How to convert to veranda
JP2699535B2 (en) Drainer and its construction method
DE4408306A1 (en) Manufacturing process for prefabricated walls