JP4222580B2 - Building foundation construction method - Google Patents
Building foundation construction method Download PDFInfo
- Publication number
- JP4222580B2 JP4222580B2 JP30048698A JP30048698A JP4222580B2 JP 4222580 B2 JP4222580 B2 JP 4222580B2 JP 30048698 A JP30048698 A JP 30048698A JP 30048698 A JP30048698 A JP 30048698A JP 4222580 B2 JP4222580 B2 JP 4222580B2
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- bridge
- frame
- plate
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、住居、店舗用建物等の建築物の基礎を構築するための基礎工事方法に関する。更に詳しくは、建築物の基礎を構築するとき、基礎ボルト、鉄筋等の位置決めと組立が迅速にかつ正確に構築できるようにした建築物の基礎工事方法に関する。
【0002】
【従来の技術】
上部構造物を支える基礎は、柱の部分のみの点状の基礎、単一の基礎版で支える布基礎等が知られている。これらの基礎を構築するには、最初に平面で基礎の部分だけ飛び飛びに掘削する壺堀り、帯状に掘削する布堀り、又は建物が建つ全面に掘削する総堀り等の地盤の掘削を行う。これらの掘削された穴の底に砂利を敷き、型枠、鉄筋、基礎ボルトを組み立て、これに生コンクリートを流して基礎を作るのが一般的である。
【0003】
この基礎工には、鉄筋の加工、組立、配筋、結束等を行う鉄筋工事の作業、コンクリートを打ち込むための型枠の作成工事等の熟練した作業が要求される。近年は熟練技能者の確保が難しい時代でもあり、可能な限り未熟練者でも工事ができる基礎工法が望ましい。しかしながら、近年は鉄骨部材で組み立てる構造形式である鉄骨構造を採用する建造物が多い。鉄骨構造は、鉄骨構造部材を工場で加工、組立の後に工事現場で施工されるのが一般的である。
【0004】
従って、鉄骨構造は、寸法精度が高く精密な建築物が構築できる。この鉄骨構造に合致するように、基礎は精密に構築する必要がある。特に、鉄骨の柱と柱の間隔と、柱を基礎へ固定するための基礎ボルトのピッチ間隔とは正確に構築しないと、鉄骨構造の組立が困難になる。仮に、組立ができても誤差の原因ともなる。
【0005】
【発明が解決しようとする課題】
本発明は上述のような技術背景のもとになされたものであり、下記目的を達成する。
本発明の目的は、未熟練者でも基礎が構築できる建築物の基礎工事方法を提供することにある。
本発明の他の目的は、現場での迅速な作業ができる建築物の基礎工事方法を提供することにある。
本発明の更に他の目的は、精密な位置に基礎、基礎ボルト、鉄筋の配筋ができる建築物の基礎工事方法を提供することにある。
【0006】
【課題を解決するための手段】
本発明は、前記目的を達成するため、次の手段を採る。
本発明の建築物の基礎工事方法は、
建築物の柱を配置する位置に基礎を構築するための組立式の基礎枡枠(4)を配置するための窪穴(2)を掘削して、前記基礎枡枠(4)を地盤に配置し、
前記基礎に埋め込み1本の前記柱を固定し位置決めするために矩形を構成する4本の基礎ボルト(10)を配置し、
前記4本の基礎ボルト(10)間の四辺を構成し、位置決め部材と鉄筋の役割を果たす4枚の橋梁板(11)と、対角線状に配置した1枚の対角橋梁板(12)とからなる第1橋梁部材(11,12)を配置し、
前記第1橋梁部材(11,12)と他の基礎の前記第1橋梁部材(11,12)とを連結し、かつ間隔を配置する第2橋梁部材(13,14)とからなる鉄筋を配置し、
前記基礎枡枠(4)、及び前記基礎枡枠(4)の外周を囲む土間枠(20)を掘削した地盤に配置し、前記基礎枡(4)内、及び前記土間枠(20)内に生コンクリートを流して前記基礎と土間を構築することを特徴とする。
【0007】
前記基礎枡は、複数の金属板を折曲げて造られた折曲板に孔と突起が形成され、前記孔と前記突起とを相互に連結して造られたものである。前記第1橋梁部材は、前記基礎ボルトを挿入して位置決めするための位置決め孔と前記第2橋梁部材を係止するための係止孔とを備えている。
【0008】
前記橋梁板(11)と対角橋梁板(12)は、金属の板材が望ましいが、前記位置決め孔と前記係止孔を備えているものであれば板材でなくても良い。前記位置決め孔と前記係止孔は、孔でなくても位置決めと係止できるものであれば、ノッチ、フック等の他の構造であっても良い。第2橋梁部材の両端には、前記橋梁板(11)と対角橋梁板(12)の前記係止孔と連結するための係止部とを備えている。前記生コンクリート打設工事の後、前記打設表面を平面にするために平面部を備え、かつ振動装置を備えた金鏝で、基礎及び土間の表面を容易に平らにできる。
【0009】
【発明の実施の形態】
[基礎工事]
次に、本発明の実施の形態を説明する。図1(a),(b)は、本発明の基礎の施工例を示す図である。図2は基礎を作る型枠の外観を示す図である。建設しようとする建築物の柱の位置の地盤を掘削し、壺堀りにより窪穴2を掘る。窪穴2の深さと径の大きさは、従来技術による施工と変わることはないので従来と同様に地盤の状態に応じた基礎の大きさで良い。窪穴2の掘削を終了させると、窪穴2の底部に砂利3を敷き、振動等を加えて突き固める。砂利3の突固めが完了すると、砂利3の上に組み立てられた基礎枡枠4を載置する。
【0010】
基礎枡枠4は、同一形状の4枚の折曲板6を連結し組立てされて作られている。基礎枡枠4の下部は、球根状に大きく形成されている。折曲板6は、金属板を曲げ、切断、打ち抜き加工して作られる。折曲板6の下部は、大径部9を形成するために2ヶ所で曲げられており、組立てられたときその部分が大径部となる。折曲板6の一方の側部には、複数の組突起8が一定間隔で形成されている。また、折曲板6の他方の側部には、複数の組合せ孔7が形成されている(図3(a)参照)。
【0011】
組突起8が他の折曲板6の組合せ孔7に互いに挿入されて、基礎枡枠4を構成する。4枚の折曲板6を組立てた後、組突起8の先端を角度90度程度ペンチで捻って組突起8が組合せ孔7から抜けないようする(図3(b)参照)。基礎枡枠4の内部空間には、後記するように生コンクリートを注入して基礎枡枡5が形成される。窪穴2の間の面である土間は、総堀りされている(図6参照)。
【0012】
基礎枡枠4には、図4に示すように4本の基礎ボルト10が矩形の形になるように挿入されて配置されている。4本の基礎ボルト10の間隔は、四辺を構成する4枚の橋梁板11と対角線状に配置した1枚の対角橋梁板12とから位置決めされ配置される。これらの部材は、基礎ボルト10の位置決めと鉄筋の役割を果たす。橋梁板11には、3個の位置決め孔11a,位置決め孔11b,係止孔11cが所定間隔を置いて形成されている。
【0013】
位置決め孔11aと位置決め孔11bとの間隔Lは、基礎ボルト10の間隔と同一である。橋梁板11の一端部の係止孔11cは、橋梁棒13を連結し係止するための孔である。橋梁棒13の両端は、L字状に曲げられた挿入部13aが形成されている。基礎枡枠4と他の基礎枡枠4は、橋梁棒13の挿入部13aが橋梁板11の係止孔11cに挿入されることにより互いに連結されている。同様に、基礎枡枠4と他の基礎枡枠4は、対角橋梁棒14の挿入部が対角橋梁板12の孔に挿入して係止させることにより互いに連結されている。
【0014】
2つの基礎枡枠4の間隔と、各基礎ボルト10間のピッチ間隔とは、橋梁板11,対角橋梁板12、橋梁棒13及び対角橋梁棒14により決められるので、正確に基礎ボルト10間の間隔と基礎枡枠4間の間隔を配置できるという利点がある。図6は、これらの組立てが完了した状態を示す断面図である。基礎枡枠4の部分に生コンクリートを流し込んだ後、折曲板6を取り除けば基礎枡枠4の部分は完成する。
【0015】
ただし、折曲板6をそのまま埋め殺す場合は、この段階では生コンクリートを流し込むことなく、図6に示す状態のままで次の工事を続行する。すなわち、基礎枡枠4の間の土間17に相当する領域の地盤を掘削し、土間枠20を配置する。土間枠20は、板金材で作られたものであり、矩形の形をしたものである。土間枠20の断面は、コ字状に形成されており、上縁及び下縁はL字状に曲げられている。
【0016】
次に、土間17の底に砂利3を一面に敷き、加圧ローラー等で砂利3を固める。砂利3を固めた後、この上に防湿シート21を敷設する。防湿シート21は、地盤の下から染み出る水分を土間に出ないように遮蔽するためのものである。次に生コンクリートを基礎枡枠4と土間17に流し込む。流し込んだ後が図6の右断面図に示したような状態になる。
【0017】
なお、土間に埋設する水道管、下水管、トイレ管、ガス管あるいは雨水管等の配管、土間部分に鉄筋、鉄網等の敷設が必要なときは、生コンクリートを流し込む前に工事を完了しておく必要がある。これらを敷設することは、建造物では周知でありその詳細な説明は省略する。
【0018】
生コンクリートを流し込んだとき表面の土間17を水平面にするには、相当の熟練を要した技能者でなければできない。そこで、本施工では非熟練者でも水平にできる特殊な金鏝25を使用する。図7は、金鏝25を土間枠20の上に載置して土間17の表面を平にしている状況を示す図である。金鏝25の本体は断面がL字状の部材で作られており、両端には操作のための引綱26が固定配置されている。2人の作業者が金鏝25の引綱26をそれぞれを手で掴み、土間枠20の上面を滑らせて土間17の表面を平らにする。
【0019】
この金鏝25の移動により、寄せ27は余分な生コンクリートをモルタル29として寄せて土間17の表面を均一にして平らにする。金鏝25の中央部には、振動装置28が配置されている。振動装置28で金鏝25を振動させるので、振動で生コンクリートの表面に細粒子が集まり滑らかになる。従って、土間17の表面は平でしかも滑らかになる。
【0020】
振動装置28は、1台で効果がないようであれば複数個配置すると良い。なお、振動装置28は、本例では偏芯ホイールによる振動を発生するものであるが、ソレノイドで振動を発生するものであっても良い。生コンクリートを流す面積が広く金鏝25が短くてカバーできないときは、継手30をボルト31で固定して所望の長さにして使用する。
【0021】
[鉄骨構造34]
図9は、柱部分の鉄骨構造を示す斜軸投影図である。形鋼柱35は、圧延された形鋼を用いた柱であり中空で断面が正四角形のパイプである。1階部分の柱である形鋼柱35の下端には、基礎継手36の上部が挿入して配置されている。基礎継手36は、内部が中空で断面が正四角形の形鋼で作られたパイプである。基礎継手36の4辺の各面は、補強板39が溶接により固着され補強されている。
【0022】
基礎継手36の下端面には、4角形の固定板40が溶接により固定されている。基礎継手36は、形鋼柱35の下端から挿入されてボルト41により形鋼柱35の下端に固定されている。固定板40には、一定間隔で複数の取付穴43が配置され開けられている。取付穴43の内周面には雌ネジが形成されている。取付穴43は、L字状のブラケット44がボルトにより固定されている。ブラケット44は、建造物の梁である橋梁(図示せず)を固定するためのものである。
【0023】
2本の形鋼柱35を連結するには、中間継手37を介在させて相互に連結する。中間継手37の構造は、基礎継手36の固定板40を備えていないのみで他の構造は基礎継手36と同一である。中間継手37の下端部は、1階部分の形鋼柱35の上端から挿入され、ボルト46で形鋼柱35に連結固定されている。中間継手37の上端部は、2階部分の形鋼柱35の下端に挿入されボルト48で形鋼柱35に連結固定されている。
【0024】
中間継手37には、橋梁45がブラケット(図示せず)を介して固定されている。2階部分の形鋼柱35の上端には、天井継手38の下端部が挿入され、ボルト49により形鋼柱35に連結固定されている。天井継手38の上端には、固定板50が溶接により固定されている。天井継手38には、同様に橋梁(図示せず)が連結固定される。完成した基礎枡枠4の上に、基礎継手36を搭載し、基礎ボルト10を基礎継手36のボルト孔47を貫通させて基礎ボルト10にナット(図示せず)をねじ込んで基礎継手36を基礎に固定して組立てる。
【0025】
これらの鉄骨構造物の特徴の一つは、採寸された建築構造用鋼材への孔開け、及びタップ加工をNC工作機械、又は鉄骨専用のNC工作機械を用いて行うことができる点にある。これらの加工は、管理された工場で加工できるので、寸法精度が極めて良く高速加工もできるので、精密機械のような精度で建物の構造を作ることもできる。また、建築現場での加工が極めて少なくて済むので工期が短くて済むという利点もある。
【0026】
[外壁パネル55]
次に、鉄骨構造物の外周に固定して外壁として使用される図11の外壁パネル55の製造方法を説明する。外壁パネル55は、平板状で矩形の板状のもので窓枠59を備えたものであり、外壁として使用するためにユニット化されたものである。工場生産される外壁パネル55を採用すると、現場での窓サッシの取付け工事、外壁の塗装工事が必要なくなる。外壁パネル55の鉄骨への固定は、パネル固定ボルト77をパネル固定用の鉄骨に固定された固定部材に挿入してナットにより固定される。
【0027】
図10に示すものは、外壁パネル55の製造のための型枠台56、型枠57,鉄筋58、窓枠59を示す。型枠台56は、矩形の板であり型枠57を載置するための台である。型枠台56中央部には、窓枠59を位置決めするための窓枠受69が配置されている。型枠台56には、複数のボルト受穴60が形成されている。ボルト受穴60は、パネル固定ボルト77を挿入してパネル固定ボルト77のネジ山を生コンクリートが被覆しないように保護するためのものである。なお、このネジ山に保護のためにテープを巻いておくと更に良い。
【0028】
型枠57は、矩形の形をした4本の部材からなる。外壁パネル55の上端面の形状を形成するための上型枠材61と、下端面の形状を形成するための下型枠材62と、左の端面の形状を形成するための左型枠材63と、右の端面の形状を形成するための右型枠材65とからなる。上型枠材61には、長手方向に窪んだ溝である凹溝64が形成されている。凹溝64は、外壁パネル55の上端面の凸部80を形成するためのものである(図11参照)。
【0029】
下型枠材62には、長手方向に突起した凸部66が形成されている。凸部66は、外壁パネル55の下端面の凹部81を形成するためのものである。外壁パネル55の上端面の凸部80と下端面の凹部81とは、外壁パネル55を順次挿入して連結して外壁とするためのものである。なお、外壁パネル55の凹部81、凸部80にシール材を介在させると効果的に雨水の侵入を防ぐことができる。
【0030】
左型枠材63は、外壁パネル55の左端面の形状を形成するためのものである。左型枠材63の隅部には、断面が矩形の隅部材67が固定されている。隅部材67は、外壁パネル55の左端部に係合部82を形成するためのものである(図11参照)。右型枠材65は、外壁パネル55の右端面の形状を形成するためのものである。
【0031】
右型枠材65の上端の角部には、段部68が形成されている。段部68は、外壁パネル55の係合部83を形成するためのものである。外壁パネル55の左右の係合部82,83は互いに接合される。一方の外壁パネル55の係合部82と他方の外壁パネル55の係合部83とは、重ねるように接合されるので、防水が容易である。防水を完璧にするには、この接合部分に中に水が浸出しないようにパッキン材等を介在させたほうが良い。
【0032】
型枠台56の上面には、窓枠受69が固定されている。窓枠受69は、工場生産されたアルミニウム製の建具である窓枠59を生コンクリートを流すときに位置決め固定のためのものである。従って、窓枠受69は窓枠59の内側のサイズに合致する大きさである。鉄筋58は、外壁パネル55の補強に用いるものである。鉄筋58は、異形鉄筋であり、断面がL字状のアングル材である4本の額縁鉄筋75と、クロス状に配置され帯状の鋼材であるクロス鉄筋76とから構成されている。
【0033】
額縁鉄筋75は、外壁パネル55の外周を補強するための鉄筋であり、クロス鉄筋76は外壁パネル55の横方向の変形を防ぎ剛性を高めるための筋交いである。これらは、互いにパネル固定ボルト77とナット78で一体になるように固定されており、外壁パネル55の鉄筋58を構成する。一体に組み付けられた鉄筋58は、型枠台56上に載置される。
【0034】
パネル固定ボルト77は、鉄筋58の固定と完成後の外壁パネル55の建築物への固定と兼用しているので組立て工数が少なくて済む。すなわち鉄筋の組立及び結束と、外壁パネル55の固定用のボルトの取り付け作業が同時にできる。また、鉄筋58にパネル固定ボルト77が直接連結固定されているので確実に外壁パネル55を建築物に固定できるので、地震等の振動にも耐えうることができる。生コンクリートを型枠57に流すときは、パネル固定ボルト77の先端はボルト受穴60に挿入された状態である。
【0035】
この挿入されたパネル固定ボルト77の先端部分は、完成された外壁パネル55から突出することになる。このパネル固定ボルト77を鉄筋構造物に固定された部材に開けられた孔に挿入し、ナット(図示せず)で固定し外壁パネル55を建築物の外壁とする。窓枠受69に挿入される窓枠59には、窓枠固定穴79からピッチが大きく、ネジ山が高いビス84が窓枠59から突出するように出ている。この状態で、窓枠59は、窓枠受69に載置される。ビス84のネジ山が生コンクリートに食い込みしっかりと固定される。
【0036】
以上の工程が終了すると、型枠57に生コンクリートを流し込む。このとき、型枠57の表面を前述した金鏝25で平らにすると良い。このままで特別な表面処理を行う必要はないが装飾壁が必要なときは、表面にタイル模様、石組模様等が付けられた加圧板(図示せず)で加圧して、外壁パネル55の表面に模様を作ると良い。更に、必要であれば装飾と防水を兼ねて加圧された面に耐候性の高い塗料で塗装を行う。
【0037】
以上の工程で、外壁パネル55は、完成する。外壁パネル55は、クレーンで吊ってパネル固定ボルト77とナットにより、鉄骨に直接又は間接的に固定する。外壁工事、コーキング工事、塗装工事が必要でない外壁パネル55となる。コンクリートを軽量コンクリートにすると、外壁パネル55の重量が通常のコンクリートに比して概略20〜50%程度軽量化される。
【0038】
更にALCを使用すれば軽量になり、現場組立が容易になる以外に、ALCの特徴である断熱性、遮音性、耐火性、耐力性を備え、かつ窓枠も備えた外壁パネル55が構成できる。ALCは、石灰質原料とケイ素質原料を主原料とし、発泡剤を加えて発泡させるか、予め作った気泡を混入して多孔質化させた後、オートクレーブ養生して得られる軽量の気泡コンクリート、必要に応じてポルトランドセメントを混合したものである。
【0039】
また、装飾壁が必要の場合、軽量コンクリートを充填した上面、すなわち建築後は外側面になる面側に、白セメント又はカラーセメントに防水剤を混合して生モルタル化して数ミリ程度の厚さを塗布して仕上げる。更に、この表面にタイル模様、石組模様等が付けられた加圧板で加圧して、外壁パネル55の表面に模様を形成する。
【0040】
この方法は、塗装したものと異なり、長期間、表面の剥離変色が少ない外壁板を作ることができる。以上のように、窓枠をアルミ素材にすれば表面は処理されているから、外壁工事、窓サッシの取付工事、防水工事が一挙にできる利点がある。なお、前述したものは窓枠を備えた外壁パネルであったが、窓枠のない外壁パネルも同様の方法で製造する。
【0041】
[床90]
次に2階と3階の床工事の方法について説明する。2階と3階の床90は、基本的には同一構造、同一工事方法を採用する。橋梁45の上に波付けした広幅の帯鋼であるデッキプレート91を載せる。この幅は製造上決められているが、長さ方向に足りないときは、他のデッキプレート92を突き合わせて使用する。突き合わせたものを使用するときは、デッキプレート91とデッキプレート92との接合面に、粘着性のある防水テープ93を接着して突き合わせ面に生じた隙間を埋める。
【0042】
デッキプレート91の両側面には、断面形状がL字状の鋼材である小口塞94が配置されている。小口塞94の間には、両小口塞94を互いに引っ張る方向に張力を負荷する、すなわちコンクリートにプレストレスを与える張力鉄筋機構95が配置されている。プレストレスを床90のコンクリートに与えると、床90の全断面が外部からの曲げ等の荷重に対して有効に働き強い荷重にも耐えることができる。また、床90のコンクリートのヒビ割れを効果的に防ぐこともできる。
【0043】
張力鉄筋機構95は、2個の引っ張りボルト96、2個のフックナット97、2個のフック98、1本のPC鋼線99等から構成されている。小口塞94には、一定間隔で引っ張りボルト96を挿入するためのボルト孔100が開けられている。引っ張りボルト96は、小口塞94のボルト孔100に挿入された後、フックナット97にねじ込んである。フックナット97は、板金材で作られたフック98の一端に溶接で固着されている。フック98の他端には、係合孔101が開けられている。
【0044】
係合孔101には、PC鋼線99の両端がU字状に曲げられた係止部102が挿入され係止されている。同様にPC鋼線99の他端も同様に他のフック98の係合孔101に挿入されている。他のフック98も同様に他方の引っ張りボルト96によって引っ張られている。張力の大きさの調節は、引っ張りボルト96を回すことにより調節することができる。
【0045】
小口塞94とデッキプレート91,92との接合部103には、鋼材の歪み、組立誤差等の原因で精度良い機械加工であっても若干の隙間が生じること避けられない。接合部103に防水のために防水テープ104を貼付する。防水テープ104に換えて又は併用してアスファルト、高分子材等で作られた防水材でコーキングしても良い。これらの作業が完了したら、小口塞94とデッキプレート91,92とで囲まれた領域に、軽量コンクリートを流し込む。この後、前述した金鏝25で床の表面を平にする。
【0046】
以上詳記したように、床90は、水漏れの防止ができと共に、張力鉄筋機構95が組み込んであるので、曲げ等の外力に対して強い床が実現でき、しかも軽量コンクリートを用いると軽量、断熱性、遮音性、耐火性、耐力性とも備えた床が実現できた。また、前記説明では建築現場での施工を説明したが、同様の方法で工場で床パネルとして製造できる。
【0047】
屋上の屋根、ベランダも同様の工法で施工できる。ただ、生コンクリート、軽量コンクリートを打設するとき、半硬化前に数ミリないし数十ミリ程度の防水剤を混入したモルタルを塗布して仕上げる。この仕上げには、排水のために若干の勾配を付けると排水を効果的にできる。なお、排水溝、排水口、これと連結されるドレインパイプを当然ながら配置する。これらの技術は周知であり、詳細な説明は省略する。
【0048】
[天井工事]
次に天井工事について詳記する。図14は、天井の取付け構造を示す斜軸投影図である。前述したデッキプレート91の裏面には、吊り板(吊木ともいう。)110の一端が固定されている。吊り板110は、予め工場生産でデッキプレート91の裏面に固定されている。吊り板110の詳細な形状は、図15に示す。吊り板110は、帯状の長い金属板で作られている。吊り板110の両側部は、補強のために曲げられた補強辺111が形成されている。
【0049】
吊り板110には、長孔である補助孔112が開けられている。補助孔112は、断熱材、電線等を固定するときに固定のための針金、金具を挿入又は固定するためのものである。吊り板110の上端部には取付孔113が開けられている。取付孔113は、タップボルト114によりデッキプレート91に工場でねじ込む。なお、この固定は、抵抗溶接等により固定しても良い。
【0050】
取付孔113の近くには、板厚が薄い部分である曲げ溝115が形成されている。曲げ溝115は、現場でこの部分を曲げるために形成されたものであり、工場出荷時にはデッキプレート91に取付孔113の部分が固定された状態である。固定されているが、デッキプレート91に沿うように配置されているので輸送中に邪魔になりにくい。
【0051】
吊り板110の下端部は、天井板を固定する野縁125の溝に挿入し吊るための吊耳116が形成されている。野縁125は、一般には天井板を取り付けるために軽鉄下地である。通常の天井構造は、吊木により天井に吊り下げされて固定される野縁受に野縁125が取り付けられる。この野縁125に天井板が取り付けられる。本例では、従来の野縁と野縁受とを兼用したものであるともいえる。吊耳116の両側部には、上方に突出する突起117が形成されている。
【0052】
突起117を野縁125の溝に挿入すると、野縁125の縁に突起117が係合して野縁125を吊り下げる。大きいサイズの野縁125を使用するときは、取付孔118に大径吊耳120を固定して組み立てる(図15(b)参照)。大径吊耳120は、両側部に突出した突起121が形成されている。大径吊耳120の中央部には、母材を切断し曲げて作られた二股突起122が形成されている。大径吊耳120の二股突起122は、取付孔118に挿入された後に曲げられて吊耳116に固定される(図15(d)参照)。
【0053】
吊り板110は、工場でデッキプレート91にタップボルト114でねじ込み固定されている。現場の天井工事のとき、デッキプレート91に固定されている吊り板110の曲げ溝115の部分から約90度曲げてデッキプレート91に対して垂直状態になるようにする。この後、吊り板110の吊耳116を野縁125の溝に挿入して摺動させて複数の吊り板110で1本の野縁125を吊り下げる。野縁125は、断面形状がU字状で溝が形成され、その先端が更に曲げられているのでこの曲げられた部分が吊耳116の突起117に係合される。
【0054】
デッキプレート91と化粧石膏天井板(以下、ジプトーンという。)132との間には、断熱グラスウール130が敷き詰められている。断熱グラスウール130は、屋根と天井との間を断熱するための断熱材であり、本例では厚さ100×幅430の長尺のものを用いた。通常断熱グラスウール130は、ジプトーン132の裏面、すなわち上面に配置されるが、ここに敷き詰めるとメイテナンス作業のとき邪魔になることがある。吊り板110の補助孔112にワイヤー131を通して配設し、このワイヤー131の上にジプトーン132が載せられている。
【0055】
ジプトーン132は、家屋、事務所に通常良く使用されている天井板であり、耐火性を強化するために石膏を含んだ板材で、本例では厚み9.5×幅455×長さ910mmである。ジプトーン132は、タップボルト133で野縁125にねじ込んで固定されている。ジプトーン132の固定で天井工事は完了する。ここで省略した現場工事は、従来工事でいうと吊りボルト工事、ハンガー工事、吊り板110と野縁125とのクリップ工事、天井塗装等多くの工事が不要になり、費用と時間が大幅に節約できる。
【0056】
前記実施の形態では、吊り板110で直接に野縁125を吊り下げている。しかし一般的な構造である吊り下げ天井の構造のように、野縁125を細長い材である野縁受(裏桟ともいう。)に取り付け、野縁受を吊り板110によって吊り下げても良い。
【0057】
[内装工事]
以上の工事で、床工事と天井工事は終了しており、次に内装工事を行う。この内装工事に先立って、前述した基礎工事、土間工事、床工事のとき、水道管、下水管、ガス管、電力線、電灯線、電話線、火災報知器用配線、テレビアンテナ、又はCATV線等予め工事を完了させておく。内装工事の間仕切りについては、本発明者が既に提案した(特開平10−18482号)。提案したものは、収納庫兼用間仕切り、及び縦横方向格子部材を用いて内壁工事及び間仕切り工事の方法である。以下、この内装と間仕切り方法の概略を説明する。
【0058】
図16は、間仕切り構造の断面を示す断面図である。図17は、図16の正面図である。前述した外壁パネル55の内側全面に断熱グラスウール140を貼る。この内側に耐火性の化粧石膏ボード141の両側部を石膏ボード用のビス142で側板143と共に固定する。側板143は、金属板を断面がコ字状に曲げ加工して作られている。
【0059】
側板143は、内壁側の縦方向に各化粧石膏ボード141の両側に沿って複数本配置されている(図17参照)。従って、各化粧石膏ボード141の接合部には、側板143の接合面144となる。側板143の上部は、基天井145に挿入されて固定されている。基天井145は、ジプトーン132にタップネジ146でねじ込んで固定されている。基天井145は、板金材で作られ断面形状がコ字状の形をしたものである。
【0060】
側板143の下部は、床基150に挿入固定されている。床基150は、床153にコンクリートネジ151でねじ込んで固定されている。床基150は、板金材で作られ断面形状がコ字状の形をしたものである。更に、上下の中間位置には、必要段数の棚板152が化粧石膏ボード141と側板143にビスにより固定配置されている。棚板152の間隔は、希望のサイズにできる。各棚は、書棚、洋服棚等必要な用途に使える。
【0061】
図18は、棚を収納庫や収納家具として使うときの構造を説明する。棚扉155は、棚の前面を蓋するものであり、前記した外壁材と同様の組立式型枠を造りこれに外表面をビニルクロス156で外装をして製造する。内部は発泡コンクリート等の軽量コンクリート157であり、この材料は断熱性、耐火性に優れている。
【0062】
棚扉155の外周には、溝158が形成されている。溝158には、Oリング159がはめ込んであり、Oリング159によりビニルクロス156を固定する。棚扉155の上下の端面には、軸であるポイントヒンジ160が上下方向に固定して設けてある。ポイントヒンジ160は、固定部161に一体に固定されている。
【0063】
固定部161は、コンクリートボルト162により棚扉155に固定されている。ポイントヒンジ160は、ポイント軸受163によりそれぞれ揺動自在に支持されている。上部のポイント軸受163と一体の固定部164は、ビス165により基天井145に固定されている。下部のポイント軸受163と一体の固定部164は、ビス165により床基150に固定されている。
【0064】
棚扉155のための開閉は、指引手170を指で掴んで行う。指引手170は、棚扉155を閉じているときは見えない位置である。指引手170には、円孔173が開けられている。円孔173は、これに指を入れて棚扉155を開閉するためのものである。軸172は棚扉155の側面に固定され、この軸172により指引手170は揺動自在に設けられている。指引手170の側面には、突起171が形成されている。突起171は、棚扉155を閉じたとき指で接触して指引手170を軸172を中心に揺動させるためのものである。なお、棚扉155の引き手は、この構造以外のものでも使用できることはいうまでもない。
【0065】
[三階の建造物180]
前述した基礎構造、鉄骨構造、床構造、間仕切り構造、内装構造等の構造と、工法を用いて、エレベータも備えた三階建の建造物の例を示す。図19は、その外観を示す透視図である。3階建の建造物180は、1階を商店又は事務所181と駐車場182、2階を住居183、3階の半分を住居184、他の半分をベランダ185とした。エレベータ186は、本発明者が提案した建造物を特別に改造することなく設置できるユニット式のエレベータを備えた(特願平10−261339号)。
【0066】
図20は、窓の断面構造を示す。外壁パネル55の内側に矩形の金属製又は木製の額縁190がネジ(図示せず)により固定配置されている。この額縁190にブラインド191及び二重窓192に配置されている。内部の仕切り又は外は収納壁を有しているので収納空間が大きく、しかも内壁に沿って配置されているのでスペース効率が良い。
【0067】
【発明の効果】
以上詳記したように、本発明の建築物の基礎工事方法は、未熟練者でも基礎が構築できる、現場での迅速な作業ができる、精密な位置に基礎、基礎ボルト、鉄筋の配筋ができる等の効果がある。
【図面の簡単な説明】
【図1】図1(a),(b)は、本発明の基礎の施工方法を示す図である。
【図2】図2は、基礎枡枠の外観を示す図である。
【図3】図3(a)は、基礎枡枠を構成する折曲板を連結する部分の拡大図であり、図3(b)は、連結部分を変形させて基礎枡枠を固定する状態を示す図である。
【図4】図4は、基礎ボルトと橋梁板と橋梁棒の組立状況を示す斜軸投影図である。
【図5】図5、基礎ボルト間の間隔を決め鉄筋の役割を果たす橋梁板と橋梁棒を示す図である。
【図6】図6は、基礎の断面を示す図である。
【図7】図7は、金鏝を土間枠の上に載置して土間の表面を平にしている状況を示す図である。
【図8】図8(a)は、図7のa−a線で切断したときの金鏝に搭載した振動装置を示し、図8(b)は、図7のb−b線で切断したときの金鏝の連結部分の断面図である。
【図9】図9は、鉄骨構造部分を示す斜軸投影図である。
【図10】図10は、外壁パネルを製造するための型枠、鉄筋、窓枠を示す分解図である。
【図11】図11は、外壁パネルの外観図である。
【図12】図12は、床の施工時の構造を示す斜軸投影図である。
【図13】図13は、張力鉄筋機構の詳細を示す断面図である。
【図14】図14は、天井の構造を示す斜軸投影図である。
【図15】図15(a),(b),(c),(d),(e)及び(f)は、天井の吊り板とその連結の状態を示す斜軸投影図である。図15(a)は吊り板の外観を示す斜軸投影図であり、図15(b)は吊り板に固定する大径吊耳の外観図であり、図15(c)は大径吊耳を組立てたときの外観図であり、図15(d)は図15(c)のd−d線で切断したときの断面図であり、図15(e)は図15(a)のe−e線で切断したときの断面図であり、図15(f)は天井板に吊り板を固定する状況を示す断面図である。
【図16】図16は、内壁の断熱構造を示す断面図である。
【図17】図17は、内壁の収納棚の例を示す正面図である。
【図18】図18は、開閉式の扉を付けた収納壁の例を示す斜軸投影図である。
【図19】図19は、エレベータ付3階建住宅の外観を示すもので屋根を外した外観図である。
【図20】図20は、2重窓部分の構造を示す断面図である。
【符号の説明】
4…基礎枡枠
5…基礎枡
6…折曲板
8…組突起
10…基礎ボルト
11…橋梁板
12…対角橋梁板
13…橋梁棒
14…対角橋梁棒
20…土間枠
21…防湿シート
25…金鏝
28…振動装置
35…形鋼柱
36…基礎継手
55…外壁パネル
57…型枠
58…鉄筋
59…窓枠
90…デッキプレート
94…小口塞
95…張力鉄筋機構
99…PC鋼線
110…吊り板
120…大径吊耳
125…野縁
155…棚扉
180…3階建建造物[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a foundation construction method for constructing a foundation of a building such as a residence or a store building. More particularly, the present invention relates to a building foundation construction method in which the positioning and assembly of foundation bolts, reinforcing bars and the like can be quickly and accurately constructed when building the foundation of a building.
[0002]
[Prior art]
As the foundation for supporting the superstructure, a dotted foundation having only a pillar portion, a cloth foundation supported by a single foundation version, and the like are known. To construct these foundations, first excavate the ground such as dredging excavating only the foundation part in a flat plane, cloth excavating in a strip shape, or total excavating excavating the entire surface of the building. Do. It is common to lay gravel at the bottom of these excavated holes, assemble formwork, rebars, and foundation bolts, and then pour ready-mixed concrete into it to make foundations.
[0003]
This foundation work requires skilled work such as rebar work for rebar processing, assembly, bar arrangement, bundling, etc., and creation of a formwork for placing concrete. In recent years, it is also difficult to secure skilled technicians, and it is desirable to have a foundation method that allows even unskilled workers to work. However, in recent years, there are many buildings that employ a steel structure, which is a structural form assembled with steel members. In general, a steel structure is processed at a construction site after processing and assembling steel structure members at a factory.
[0004]
Therefore, the steel structure can be constructed with high dimensional accuracy and a precise building. The foundation must be precisely constructed to match this steel structure. In particular, it is difficult to assemble the steel structure unless the distance between the columns of the steel frame and the pitch interval of the foundation bolts for fixing the column to the foundation are accurately constructed. Even if it can be assembled, it may cause errors.
[0005]
[Problems to be solved by the invention]
The present invention has been made based on the technical background as described above, and achieves the following object.
The objective of this invention is providing the foundation construction method of the building which a foundation can construct even an unskilled person.
Another object of the present invention is to provide a building foundation construction method capable of quick work on site.
Still another object of the present invention is to provide a foundation work method for a building in which foundations, foundation bolts, and reinforcing bars can be arranged at precise positions.
[0006]
[Means for Solving the Problems]
In order to achieve the above object, the present invention employs the following means.
The foundation construction method of the building of the present invention is
Excavation holes (2) for placing an assembling-type foundation frame (4) for constructing the foundation at the position where the pillars of the building are to be placed are arranged on the ground. And
In order to fix and position one of the pillars embedded in the foundation, four foundation bolts (10) constituting a rectangle are arranged,
Configure the four sides between the four foundation bolts (10) , Acting as a positioning member and rebar A first bridge member (11, 12) comprising four bridge plates (11) and one diagonal bridge plate (12) arranged diagonally;
Reinforcing bars consisting of second bridge members (13, 14) that connect the first bridge members (11, 12) and the first bridge members (11, 12) of other foundations and that are spaced from each other are arranged. And
The basic frame (4) ,as well as A dirt frame surrounding the outer periphery of the foundation frame (4) (20) Placed on the excavated ground , In the basic basket (4), and The soil frame (20) Within The foundation and soil are constructed by pouring ready-mixed concrete.
[0007]
The foundation rod is formed by forming a hole and a protrusion on a bent plate formed by bending a plurality of metal plates, and connecting the hole and the protrusion to each other. The first bridge member includes a positioning hole for inserting and positioning the foundation bolt and a locking hole for locking the second bridge member.
[0008]
Above Bridge plate (11) and diagonal bridge plate (12) Is preferably a metal plate, but may not be a plate as long as the positioning hole and the locking hole are provided. The positioning hole and the locking hole may be other structures such as notches and hooks as long as they can be positioned and locked without being a hole. At both ends of the second bridge member, The bridge plate (11) and the diagonal bridge plate (12) A locking portion for connecting to the locking hole is provided. After the ready-mixed concrete placing work, the surface between the foundation and the soil can be easily flattened with a hammer having a flat portion for making the placing surface flat and having a vibration device.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
[Foundation work]
Next, an embodiment of the present invention will be described. FIGS. 1A and 1B are diagrams showing an example of the foundation construction of the present invention. FIG. 2 is a view showing an appearance of a mold forming a foundation. Excavate the ground at the location of the pillar of the building to be constructed, and dig the hollow 2 by digging. Since the depth and diameter of the
[0010]
The
[0011]
The assembly protrusions 8 are inserted into the combination holes 7 of the other folded
[0012]
As shown in FIG. 4, four
[0013]
The distance L between the
[0014]
Since the distance between the two
[0015]
However, when the
[0016]
Next, the
[0017]
If pipes such as water pipes, sewage pipes, toilet pipes, gas pipes or rainwater pipes buried in the soil, or laying of reinforcing bars or nets, etc. are required between the soil, complete the construction before pouring the ready-mixed concrete. It is necessary to keep. The laying of these is well known in buildings and will not be described in detail.
[0018]
In order to make the surface of the
[0019]
Due to the movement of the
[0020]
A plurality of
[0021]
[Steel structure 34]
FIG. 9 is an oblique projection showing the steel structure of the column portion. The shaped
[0022]
A
[0023]
In order to connect the two shaped
[0024]
A
[0025]
One of the features of these steel structures is that drilling and tapping can be performed on the measured building structural steel using an NC machine tool or an NC machine tool dedicated to steel. Since these processes can be performed in a controlled factory, the dimensional accuracy is very good and high-speed processing can be performed, so that the structure of a building can be made with the precision of a precision machine. In addition, there is an advantage that the construction period can be shortened because the processing at the construction site is extremely small.
[0026]
[Outer wall panel 55]
Next, the manufacturing method of the
[0027]
FIG. 10 shows a
[0028]
The
[0029]
The
[0030]
The
[0031]
A step portion 68 is formed at the corner of the upper end of the
[0032]
A
[0033]
The
[0034]
Since the
[0035]
The tip portion of the inserted
[0036]
When the above steps are completed, ready-mixed concrete is poured into the
[0037]
The
[0038]
Furthermore, if ALC is used, it will be lighter and easier to assemble on-site. In addition to ALC's features, heat insulation, sound insulation, fire resistance, strength, and an
[0039]
If a decorative wall is required, the top surface filled with lightweight concrete, that is, the outer surface after construction, is mixed with white cement or color cement with a waterproofing agent to make a raw mortar, which is about a few millimeters thick. Apply and finish. Further, the surface is pressed with a pressure plate having a tile pattern, a stonework pattern, or the like, and a pattern is formed on the surface of the
[0040]
This method can make an outer wall plate with less surface discoloration for a long period of time, unlike a painted one. As described above, since the surface is treated if the window frame is made of an aluminum material, there is an advantage that outer wall construction, window sash installation construction, and waterproof construction can be performed at once. In addition, although what was mentioned above was the outer wall panel provided with the window frame, the outer wall panel without a window frame is also manufactured by the same method.
[0041]
[Floor 90]
Next, the method of floor construction on the second and third floors will be described. The second and
[0042]
On both side surfaces of the
[0043]
The tension reinforcing
[0044]
The engaging
[0045]
In the
[0046]
As described in detail above, the
[0047]
The rooftop roof and veranda can be constructed in the same way. However, when placing ready-mixed concrete and lightweight concrete, mortar mixed with a waterproofing agent of several millimeters to several tens of millimeters is applied before semi-curing. For this finishing, drainage can be effectively performed by adding a slight gradient for drainage. Of course, a drainage groove, a drainage port, and a drain pipe connected thereto are arranged. These techniques are well known and will not be described in detail.
[0048]
[Ceiling work]
Next, the ceiling construction will be described in detail. FIG. 14 is an oblique projection showing a ceiling mounting structure. One end of a suspension plate (also called suspension tree) 110 is fixed to the back surface of the
[0049]
The
[0050]
In the vicinity of the
[0051]
A
[0052]
When the
[0053]
The
[0054]
[0055]
[0056]
In the embodiment, the
[0057]
[Interior construction]
With the above construction, floor work and ceiling work have been completed, and then interior work will be performed. Prior to this interior work, the above-mentioned foundation work, earthwork work, floor work, water pipe, sewer pipe, gas pipe, power line, light line, telephone line, fire alarm wiring, TV antenna, CATV line, etc. Complete the construction. The present inventor has already proposed a partition for interior work (Japanese Patent Laid-Open No. 10-18482). What has been proposed is a method of inner wall construction and partition construction using a storage / compartment partition and vertical / horizontal lattice members. The outline of the interior and the partitioning method will be described below.
[0058]
FIG. 16 is a cross-sectional view showing a cross section of the partition structure. FIG. 17 is a front view of FIG. Insulating
[0059]
A plurality of
[0060]
The lower part of the
[0061]
FIG. 18 illustrates a structure when a shelf is used as a storage or storage furniture. The
[0062]
A
[0063]
The fixing
[0064]
The
[0065]
[
An example of a three-story building provided with an elevator using the construction method and the structure such as the basic structure, the steel structure, the floor structure, the partition structure, and the interior structure described above will be shown. FIG. 19 is a perspective view showing the appearance. The three-
[0066]
FIG. 20 shows a sectional structure of the window. A rectangular metal or
[0067]
【The invention's effect】
As described in detail above, the building foundation construction method of the present invention enables foundations, foundation bolts, and reinforcing bars to be placed at precise positions, even if unskilled persons can build foundations, can be quickly performed on site. There are effects such as being able to.
[Brief description of the drawings]
FIGS. 1 (a) and 1 (b) are diagrams showing a foundation construction method according to the present invention.
FIG. 2 is a diagram showing an external appearance of a basic frame.
FIG. 3 (a) is an enlarged view of a portion that connects bent plates constituting the base frame, and FIG. 3 (b) shows a state in which the base frame is fixed by deforming the connection part. FIG.
FIG. 4 is an oblique axis projection view showing an assembly state of a foundation bolt, a bridge plate, and a bridge bar.
FIG. 5 is a diagram showing a bridge plate and a bridge bar that determine the distance between foundation bolts and play the role of a reinforcing bar.
FIG. 6 is a view showing a cross section of a foundation.
FIG. 7 is a diagram showing a situation in which a hammer is placed on a soil frame and the surface of the soil is flattened.
8A shows a vibration device mounted on a hammer when cut along line aa in FIG. 7, and FIG. 8B is cut along line bb in FIG. 7; It is sectional drawing of the connection part of a hammer.
FIG. 9 is an oblique axis projection view showing a steel structure portion.
FIG. 10 is an exploded view showing a formwork, a reinforcing bar, and a window frame for manufacturing an outer wall panel.
FIG. 11 is an external view of an outer wall panel.
FIG. 12 is an oblique axis projection view showing a structure during construction of a floor.
FIG. 13 is a cross-sectional view showing details of a tension reinforcing bar mechanism.
FIG. 14 is an oblique projection showing a ceiling structure.
15 (a), (b), (c), (d), (e) and (f) are oblique axis projection views showing a ceiling suspension plate and its connection state. 15A is an oblique projection showing the external appearance of the suspension plate, FIG. 15B is an external view of a large-diameter suspension ear fixed to the suspension plate, and FIG. 15C is a large-diameter suspension ear. 15 (d) is a sectional view taken along the line dd in FIG. 15 (c), and FIG. 15 (e) is an e-section in FIG. 15 (a). It is sectional drawing when cut | disconnecting by e line, FIG.15 (f) is sectional drawing which shows the condition which fixes a suspension board to a ceiling board.
FIG. 16 is a cross-sectional view showing the heat insulation structure of the inner wall.
FIG. 17 is a front view showing an example of a storage shelf on the inner wall.
FIG. 18 is an oblique projection showing an example of a storage wall with an openable door.
FIG. 19 is an external view showing the external appearance of a three-story house with an elevator, with the roof removed.
FIG. 20 is a cross-sectional view showing a structure of a double window portion.
[Explanation of symbols]
4. Basic frame
5 ... Basics
6 ... bent plate
8 ... Assembly protrusion
10 ... Foundation bolt
11 ... Bridgeboard
12 ... Diagonal bridge plate
13 ... Bridge bar
14 ... Diagonal bridge bar
20 ... Soil frame
21 ... Moisture-proof sheet
25 ...
28 ... Vibration device
35 ... Shaped steel pillar
36 ... Foundation joint
55 ... External wall panel
57 ... Formwork
58 ... Rebar
59 ... Window frame
90 ... Deck plate
94 ... Small fortress
95 ... Tension reinforcement mechanism
99 ... PC steel wire
110 ... hanging plate
120 ... Large diameter hanging ear
125 ...
155 ... Shelf door
180 ... 3 stories building
Claims (4)
前記基礎に埋め込み1本の前記柱を固定し位置決めするために矩形を構成する4本の基礎ボルト(10)を配置し、
前記4本の基礎ボルト(10)間の四辺を構成し、位置決め部材と鉄筋の役割を果たす4枚の橋梁板(11)と、対角線状に配置した1枚の対角橋梁板(12)とからなる第1橋梁部材(11,12)を配置し、
前記第1橋梁部材(11,12)と他の基礎の前記第1橋梁部材(11,12)とを連結し、かつ間隔を配置する第2橋梁部材(13,14)とからなる鉄筋を配置し、
前記基礎枡枠(4)、及び前記基礎枡枠(4)の外周を囲む土間枠(20)を掘削した地盤に配置し、前記基礎枡(4)内、及び前記土間枠(20)内に生コンクリートを流して前記基礎と土間を構築する
ことを特徴とする建築物の基礎工事方法。Excavation holes (2) for placing an assembling-type foundation frame (4) for constructing the foundation at the position where the pillars of the building are to be placed are arranged on the ground. And
In order to fix and position one of the pillars embedded in the foundation, four foundation bolts (10) constituting a rectangle are arranged,
Four bridge plates (11) constituting four sides between the four foundation bolts (10) and serving as positioning members and reinforcing bars, and one diagonal bridge plate (12) arranged diagonally, The first bridge member (11, 12) consisting of
Reinforcing bars consisting of second bridge members (13, 14) that connect the first bridge members (11, 12) and the first bridge members (11, 12) of other foundations and that are spaced from each other are arranged. And
The foundation frame (4) and the earth frame (20) surrounding the outer periphery of the foundation frame (4) are arranged on the excavated ground, and are placed in the foundation frame ( 4) and the earth frame (20). A foundation construction method for a building, characterized by pouring ready-mixed concrete and building the foundation and soil.
前記基礎枡枠(4)は、複数の金属板を折曲げて造られた折曲板に孔と突起が形成され、前記孔と前記突起とを相互に連結して造られたものである
ことを特徴とする建築物の基礎工事方法。In claim 1,
The base frame (4) is formed by forming holes and protrusions on a bent plate formed by bending a plurality of metal plates, and connecting the holes and the protrusions to each other. A basic construction method for buildings.
前記橋梁板(11)と対角橋梁板(12)は、前記基礎ボルトを挿入して位置決めするための位置決め孔と前記第2橋梁部材を係止するための係止孔とを備え、
第2橋梁部材の両端には、前記橋梁板(11)と対角橋梁板(12)の前記係止孔と連結するための係止部とを備えていることを特徴とする建築物の基礎工事方法。In claim 1 or 2,
The bridge plate (11) and the diagonal bridge plate (12) include a positioning hole for inserting and positioning the foundation bolt and a locking hole for locking the second bridge member,
The foundation of a building characterized in that both ends of the second bridge member are provided with locking portions for connecting with the locking holes of the bridge plate (11) and the diagonal bridge plate (12). Construction method.
前記生コンクリート打設工事の後、前記打設表面を平面にするために平面部を備え、かつ振動装置を備えた金鏝と
からなることを特徴とする建築物の基礎工事方法。In claim 1 or 2,
A foundation construction method for a building, comprising: a hammer having a flat part and a vibration device for making the placing surface flat after the ready concrete placing work.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30048698A JP4222580B2 (en) | 1998-10-22 | 1998-10-22 | Building foundation construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30048698A JP4222580B2 (en) | 1998-10-22 | 1998-10-22 | Building foundation construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2000129691A JP2000129691A (en) | 2000-05-09 |
JP4222580B2 true JP4222580B2 (en) | 2009-02-12 |
Family
ID=17885397
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30048698A Expired - Fee Related JP4222580B2 (en) | 1998-10-22 | 1998-10-22 | Building foundation construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4222580B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3875216B2 (en) * | 2003-06-16 | 2007-01-31 | 株式会社松本建築デザイン | Precise positioning of anchor bolts to the foundation using swing-type anchor bolts |
CN113250225A (en) * | 2021-04-14 | 2021-08-13 | 中国五冶集团有限公司 | Rapid dismounting and reusing method of bearing platform foundation cup mouth template |
-
1998
- 1998-10-22 JP JP30048698A patent/JP4222580B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2000129691A (en) | 2000-05-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7958687B2 (en) | Concrete panel construction system | |
US8490363B2 (en) | Modular concrete building | |
US8132388B2 (en) | Modular concrete building | |
KR20080065290A (en) | Bolt-a-blok-a system for unitized, post-tensioned mansonry structures | |
JP4339695B2 (en) | Architectural panel and construction method | |
US20050155297A1 (en) | Massive construction system using rock masonry | |
JP4087959B2 (en) | Building floor panels and construction methods | |
JP4222580B2 (en) | Building foundation construction method | |
JP4004056B2 (en) | Construction method of pre-insulated prestressed building using precast concrete body | |
JP4173230B2 (en) | Ceiling construction method and its suspension | |
JP4236221B2 (en) | Exterior wall panel of building and its manufacturing method | |
KR20190030885A (en) | Construction Method for Model House combining of the concept Korean Houses and Wood Houses | |
CN104652662B (en) | Prefabricated panel system | |
JP3823269B2 (en) | Seismic structure of wooden structure | |
NZ248942A (en) | Constructing a building; form footing, place panels and then connect a perimeter beam to the inside or outside of the panel top | |
WO2002010529A1 (en) | Prefabricated building | |
JP2009215750A (en) | Chamber unit reinforcing structure of wooden house | |
KR100414594B1 (en) | Block for a Steel House and The Constructing Method | |
JP2002097760A (en) | Terraced roof structure | |
CA2311222C (en) | Concrete panel construction system | |
JP2003301546A (en) | External heat insulation building of reinforced concrete construction | |
EP1185748B1 (en) | Concrete panel construction system | |
JPH0932310A (en) | Reinforcing method for existing wood building | |
KR200246526Y1 (en) | Block for a Steel House | |
JPH01210538A (en) | Building structure made of precast concrete panels |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051007 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070925 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080111 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080311 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20080707 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080904 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080815 |
|
A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20080916 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20081014 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081021 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20081112 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081117 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111128 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131128 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |