JPH0341558Y2 - - Google Patents

Info

Publication number
JPH0341558Y2
JPH0341558Y2 JP1985188932U JP18893285U JPH0341558Y2 JP H0341558 Y2 JPH0341558 Y2 JP H0341558Y2 JP 1985188932 U JP1985188932 U JP 1985188932U JP 18893285 U JP18893285 U JP 18893285U JP H0341558 Y2 JPH0341558 Y2 JP H0341558Y2
Authority
JP
Japan
Prior art keywords
cover
rod
temporary frame
sleeve
frame panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1985188932U
Other languages
Japanese (ja)
Other versions
JPS6296433U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1985188932U priority Critical patent/JPH0341558Y2/ja
Publication of JPS6296433U publication Critical patent/JPS6296433U/ja
Application granted granted Critical
Publication of JPH0341558Y2 publication Critical patent/JPH0341558Y2/ja
Expired legal-status Critical Current

Links

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、仮枠組後のコンクリート打設工事に
おいて、配管用スリーブ、給排水金物等の配管設
備の設置に使用する固定セツターに関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a fixed setter used for installing piping equipment such as piping sleeves and water supply and drainage hardware during concrete pouring work after temporary framing.

〔従来の技術〕[Conventional technology]

従来、鉄骨、鉄筋コンクリート建造物の工事は
仮枠パネルで造作した後に鉄筋を該仮枠パネル面
に沿つて配筋し、さらに配管や電気配線のために
スリーブ等の配管設備を設置し、この後にコンク
リート打設工事を行うのが通常である。
Conventionally, in the construction of steel frames and reinforced concrete buildings, temporary frame panels are constructed, reinforcing bars are placed along the surface of the temporary frame panels, and piping equipment such as sleeves are installed for piping and electrical wiring. Usually, concrete pouring work is carried out.

配管のためのスリーブは、コンクリート打設後
にパイプ配管が建屋の床、天井及び壁を貫通する
場合に必須なもので、その内部をコンクリートと
遮断し打設後の空間をパイプの挿通孔として利用
している。
Sleeves for piping are essential when pipe piping penetrates the floor, ceiling, and walls of a building after concrete is poured.The sleeve is used to isolate the inside from the concrete and use the space after pouring as a hole for the pipe to pass through. are doing.

このスリーブの取付け施工は、芯出し板を下端
に備え、該芯出し板の上方においてスリーブ等の
上端開口部を閉塞する板体(押さえ板)を備えた
ロツドを用い、上記芯出し板を仮枠パネルに釘打
ちし、かつ上記板体(押さえ板)で、スリーブ等
の上端開口部を閉塞した後、コンクリート打設し
て取り付けるようにしている(特公昭59−49990
号公報参照)。
To install this sleeve, use a rod that is equipped with a centering plate at the lower end and a plate (holding plate) that closes the upper end opening of the sleeve, etc. above the centering plate, and temporarily holds the centering plate. After nailing into the frame panel and closing the upper end opening of the sleeve etc. with the above-mentioned plate (holding plate), it is installed by pouring concrete (Special Publication No. 59-49990
(see publication).

〔考案が解決しよとする問題点〕[Problem that the idea aims to solve]

しかし、上述したような埋込み施工の場合、次
ぎのような問題がある。すなわち、 押さえ板を、スリーブ等の上端開口部を閉塞
するためにナツトで締め付けていくと、ロツド
と芯出し板とが一体化されているので、仮枠パ
ネルに打ち付けている釘が抜けて、不安定な状
態に成りやすい。
However, in the case of embedding construction as described above, there are the following problems. In other words, when the holding plate is tightened with a nut to close the upper end opening of the sleeve etc., since the rod and centering plate are integrated, the nails nailed to the temporary frame panel will come out. It is easy to become unstable.

押さえ板が、平板であるため、締め付けの際
に端部が浮き上がり、コンクリート打設時に、
コンクリートがスリーブ内に入り込みやすく、
またコンクリート打設時に捩れを生じやすくな
る。
Since the holding plate is a flat plate, the edges will lift up when tightening, causing problems when pouring concrete.
Concrete easily enters the sleeve,
Furthermore, the concrete is more likely to be twisted during concrete placement.

芯だし板を、仮枠パネルに打ち付けるための
釘打ち作業が必要である。
Nailing work is required to attach the centering board to the temporary frame panel.

等の問題がある。There are other problems.

本考案は、以上のような点に対処して創案した
ものであつて、その目的とする処は、仮枠パネル
を余り傷めることなく、配管用スリーブや給排水
金物等の配管設備を所定の位置に確実に固定で
き、またその内部へのコンクリートの流入を防止
できると共に、取り扱いが簡単に行える固定用セ
ツターを提供することを目的とするものである。
The present invention was devised in response to the above-mentioned problems, and its purpose is to place piping equipment such as piping sleeves and water supply/drainage fittings in their designated positions without damaging the temporary frame panels. The object of the present invention is to provide a fixing setter that can be securely fixed to the concrete, prevent concrete from flowing into the setter, and is easy to handle.

〔問題点を解決するための手段〕[Means for solving problems]

そして、上記目的を達成するための本考案のコ
ンクリート打設工事用固定セツターは、配管用ス
リーブや給排水金物等の配管設備を設置するため
のコンクリート打設工事用固定セツターであつ
て、仮枠パネルに係止するためのコーチスクリユ
ーを下端に形成しかつ上部側に雄螺子を有するロ
ツドと、該コーチスクリユーの上位においてロツ
ドに一体化しかつ上記仮枠パネルに当接する下面
が該ロツド軸線と直交するスタピライザと、該ス
タピライザの上位においてロツドに昇降自在に装
着した配管設備の上端開口部を閉塞するカバー
と、該カバーの上位において上記ロツドの雄螺子
に螺合し該カバーを押さえるカバー固定具とを有
し、該カバーは縁端にカバー中央部に対して低く
なる段差を有し、該段差部分が上記配管設備の端
部に当接するようにした構成よりなる。
In order to achieve the above object, the fixed setter for concrete pouring work of the present invention is a fixed setter for concrete pouring work for installing piping equipment such as piping sleeves and water supply and drainage hardware, and is a fixed setter for concrete pouring work that is used for temporary frame panels. A rod having a coach screw formed at its lower end and having a male screw on its upper side, and a rod which is integrated with the rod above the coach screw and whose lower surface abuts against the temporary frame panel coincides with the axis of the rod. A stabilizer that intersects at right angles, a cover that closes the upper end opening of the piping equipment that is attached to a rod above the stabilizer so that it can be raised and lowered, and a cover fixing device that is screwed onto the male screw of the rod above the cover and holds the cover. The cover has a step at its edge that is lower than the center of the cover, and the step portion comes into contact with the end of the piping equipment.

〔作用〕[Effect]

そして、上記構成に基づく本考案の固定用セツ
ターは、配管用スリーブ、排水トラツプ等の配管
設備を仮枠パネル上に載置して、次いで、その配
管設備を貫通してロツドの下端に形成した係止具
をロツドを作動させて上記仮枠パネル面に係止す
るとともに、縁端にカバー中央部より低くなる段
差を有するカバーを降下させて上記配管設備の上
面にカバー固定具により、該カバーの段差部分を
当接固定した後、該配管設備の外側にコンクリー
トを打設する。次いで、上記コンクリートが養生
した後、上記カバーを上動させるとともにロツド
を作動させてコーチスクリユーを仮枠パネルより
外すことにより配管設備の設置がコンクリート工
事時と同時に埋込み施工できるように作用する。
The fixing setter of the present invention based on the above structure has piping equipment such as a piping sleeve and drainage trap placed on a temporary frame panel, and then penetrates through the piping equipment and is formed at the lower end of the rod. The locking tool is actuated by a rod to lock it to the surface of the temporary frame panel, and a cover having a step lower than the center of the cover at the edge is lowered, and the cover is attached to the top surface of the piping equipment using the cover fixing tool. After the stepped portion is abutted and fixed, concrete is placed on the outside of the piping equipment. Next, after the concrete has cured, the cover is moved up and the rod is operated to remove the coach screw from the temporary frame panel, so that the piping equipment can be installed simultaneously with the concrete work.

以上のように、本願考案のセツターは、ロツド
の下端にコーチスクリユーを設けていることよ
り、釘打ち作業を必要とすることなく仮枠パネル
への設置が簡単に行え、また、カバーと配管設備
との当接を、該カバーの縁端に形成したカバー中
央部より低くなる段差部分で行うようにしている
ことより、その強度が強くなり、該カバーと配管
設備との間での隙間発生が軽減され、コンクリー
トの流入が防止できるように作用する。
As described above, the setter of the present invention has a coach screw at the lower end of the rod, so it can be easily installed on the temporary frame panel without the need for nailing work, and the setter can be easily installed on the temporary frame panel without the need for nailing. By making contact with the equipment at the stepped part formed at the edge of the cover that is lower than the center of the cover, its strength is increased and gaps can occur between the cover and piping equipment. It acts to reduce the amount of water and prevent the inflow of concrete.

〔実施例〕〔Example〕

以下、図面を参照しながら、本考案を具体化し
た実施例について説明する。
Hereinafter, embodiments embodying the present invention will be described with reference to the drawings.

ここに、第1図は本考案の実施例を示す斜視
図、第2,3図は施工状態を示す断面図である。
Here, FIG. 1 is a perspective view showing an embodiment of the present invention, and FIGS. 2 and 3 are sectional views showing the construction state.

本実施例の固定セツターは、大別すると、ロツ
ド10とカバー11とより構成されている。
The fixed setter of this embodiment is roughly composed of a rod 10 and a cover 11.

ロツド10は下端12に先端が鋭角状をした係
止具13を有し、また上端14に該係止具13を
仮枠パネル15にねじ込むためのねじ込み用ハン
ドル16を備えている。ここで、係止具13はコ
ーチスクリユーで形成されている。
The rod 10 has a locking tool 13 with an acute angle at its lower end 12, and a screwing handle 16 at its upper end 14 for screwing the locking tool 13 into a temporary frame panel 15. Here, the locking tool 13 is formed of a coach screw.

また、該ロツド10の略中央部分からねじ込み
用ハンドル16の下位までには雄螺子17が形成
され、該雄螺子17と螺合するカバー固定具18
が配設されており、係止具13の上位には仮枠パ
ネル15のパネル面に直交する方向に中空半球面
状スタピライザ19が装着されている。ここに、
スタピライザ19は係止具13が必要以上に仮枠
パネル15にねじ込まないように、そのねじ込み
を規制するとともにロツド10の横揺れを規制す
るためのものであるので、中空半球面状のものに
限られる必要はない。
Further, a male screw 17 is formed from the approximate center of the rod 10 to the lower part of the screw handle 16, and a cover fixture 18 is screwed into the male screw 17.
A hollow hemispherical stabilizer 19 is installed above the locking tool 13 in a direction perpendicular to the panel surface of the temporary frame panel 15. Here,
The stabilizer 19 is used to prevent the locking tool 13 from being screwed into the temporary frame panel 15 more than necessary and to restrict the screwing of the rod 10 and to restrict the horizontal shaking of the rod 10, so it is limited to a hollow hemispherical shape. There's no need to be.

カバー11は、仮枠パネル15に載置するスリ
ーブ20や排水トラツプ22の上部開口部21の
大きさに合致する形状(円板)であつて、中央に
ロツド10が貫通する孔が穿けられて、ロツド1
0のカバー固定具18と係止具13との間に昇降
自在に配設されている。そして、カバー11は昇
降によりスリーブ20や排水トラツプ22等の配
管設備(以下、スリーブという)の上部開口部2
1に当接した時、カバー固定具18で締め付ける
ようにしている。ここで、カバー11はコンクリ
ートの流入を防止するとともに、スリーブ20や
排水トラツプ22等のスリーブの傾きを防止する
ためのものである。
The cover 11 has a shape (disk) that matches the size of the sleeve 20 placed on the temporary frame panel 15 and the upper opening 21 of the drain trap 22, and has a hole in the center for the rod 10 to pass through. , Rod 1
It is disposed between the cover fixing tool 18 of No. 0 and the locking tool 13 so as to be movable up and down. The cover 11 is raised and lowered to open the upper opening 2 of the piping equipment (hereinafter referred to as sleeve) such as the sleeve 20 and the drain trap 22.
1, the cover fixture 18 is used to tighten the cover. Here, the cover 11 is used to prevent concrete from flowing in and to prevent the sleeves such as the sleeve 20 and the drain trap 22 from tilting.

また、カバー11の縁端は段差が形成され、カ
バー自体の補強と、コンクリート打設時における
捲れを排除するようにしている。カバー11の大
きさ等は設置する配管設備により異なり、必要に
応じて該スリーブの上側開口部21より大きい形
状としてもよい。さらに、カバー11とカバー固
定具18とは一体化した構造としてもよい。
Further, a step is formed at the edge of the cover 11 to reinforce the cover itself and to prevent it from turning over during concrete pouring. The size of the cover 11 varies depending on the piping equipment to be installed, and the cover 11 may have a larger shape than the upper opening 21 of the sleeve, if necessary. Furthermore, the cover 11 and the cover fixture 18 may have an integrated structure.

続いて、本実施例の固定用セツターの施工状態
を示した第2図に基づき、その作用について説明
する。
Next, the function of the fixing setter of this embodiment will be explained based on FIG. 2 showing the construction state of the fixing setter of this embodiment.

第2図は、配管設備としてスリーブ20を設置
する場合を示していいる。第2図において、仮設
パネル15面の上面にスリーブ20を載せて芯出
しをし、該芯にロツド10の係止具13をねじ込
み用ハンドル16によりスタピライザ19の下面
が仮枠パネル15の上面に達するまでねじ込む。
これにより、ロツド10がスリーブ20と同軸上
に設定される。
FIG. 2 shows a case where a sleeve 20 is installed as piping equipment. In FIG. 2, the sleeve 20 is placed on the upper surface of the temporary panel 15 for centering, and the locking tool 13 of the rod 10 is screwed onto the center. Screw in until it reaches the end.
Thereby, the rod 10 is set coaxially with the sleeve 20.

次に、カバー11をロツド10に沿つて降下さ
せてスリーブ20の上面に当接するとともに、カ
バー固定具18をロツド10の雄螺子17と螺合
によりカバー11上に降下しカバー10をスリー
ブ20の上面と、カバー固定具18とで締めつけ
る。そして、カバー11がスリーブ20の上側開
口部を閉塞するとともに仮枠パネル15上のスリ
ーブ20を釘等を用いることなく、安定状態で固
定するように作用する。
Next, the cover 11 is lowered along the rod 10 and comes into contact with the upper surface of the sleeve 20, and the cover fixture 18 is lowered onto the cover 11 by being screwed into the male screw 17 of the rod 10, and the cover 10 is lowered onto the sleeve 20. Tighten the top surface and the cover fixture 18. Then, the cover 11 closes the upper opening of the sleeve 20 and acts to stably fix the sleeve 20 on the temporary frame panel 15 without using nails or the like.

続いて、スリーブ20の外側にコンクリートを
打設すると、該コンクリートがスリーブ20内に
流入することなく、また、スリーブ20が設置位
置よりずれることなく保持される。つぎに、該コ
ンクリートが養生した後、ねじ込み用ハンドル1
6を作動させることによりロツド10の係止具1
3が仮枠パネル15よりの係合が解除され、該ロ
ツド10をスリーブ20内より取り出して該スリ
ーブ20の据え付け作業が終了する。
Subsequently, when concrete is placed on the outside of the sleeve 20, the concrete does not flow into the sleeve 20, and the sleeve 20 is held without shifting from its installed position. Next, after the concrete has cured, screw handle 1
By actuating 6, the locking tool 1 of the rod 10 is
3 is disengaged from the temporary frame panel 15, the rod 10 is taken out from the sleeve 20, and the installation work of the sleeve 20 is completed.

第3図に示すものは、第2図においてスリーブ
の代わりに排水トラツプ22を施工するようにし
たものである。これも前述した実施例と同様に作
用する。
The one shown in FIG. 3 is the same as in FIG. 2 except that a drainage trap 22 is installed instead of the sleeve. This also works in the same way as the previous embodiment.

そして、上述した本実施例においては、仮枠パ
ネル15を係止するための係止具としてのコーチ
スクリユー13をロツド10の下端11に一体的
に形成した構成としたが、該コーチスクリユー1
3は仮枠パネル15の材質、厚みによりその形状
等が異なるもので、これに対処するために、任意
に交換できる形状であつてもよい。また、ロツド
10はその長さを調節(継ぎ足し等により)でき
るようにした構成、あるいは、先端部方向が末広
がり状になつた構成等としてもよい。
In the present embodiment described above, the coach screw 13 as a locking tool for locking the temporary frame panel 15 was formed integrally with the lower end 11 of the rod 10. 1
3 differs in shape depending on the material and thickness of the temporary frame panel 15, and in order to cope with this, the shape may be arbitrarily exchangeable. Further, the rod 10 may have a structure in which its length can be adjusted (by adding parts, etc.), or a structure in which the tip end is flared toward the end.

なお、本考案は上述した実施例に限定されるも
のでなく、本考案の要旨を変更しない範囲内で
種々変形実施できることは明らかである。
It should be noted that the present invention is not limited to the embodiments described above, and it is clear that various modifications can be made without changing the gist of the present invention.

〔考案の効果〕[Effect of idea]

以上の記載より明らかなように、本考案の固定
セツターによれば、ロツドの下端にコーチスクリ
ユーを設けていることにより、釘打ち作業を必要
とすることなく仮枠パネルへの設置が簡単に行
え、また、カバーと配管設備との当接を、該カバ
ーの縁端に形成したカバー中央部より低くなる段
差部分で行うようにしていることより、その強度
が強くなり、該カバーと配管設備との間での隙間
発生が軽減され、コンクリートの流入が防止でき
るという効果を有する。
As is clear from the above description, according to the fixed setter of the present invention, by providing a coach screw at the lower end of the rod, it can be easily installed on a temporary frame panel without requiring nailing work. In addition, since the cover and the piping equipment come into contact with each other at the stepped part formed at the edge of the cover that is lower than the center of the cover, its strength is increased, and the cover and the piping equipment come into contact with each other. This has the effect of reducing the occurrence of gaps between the concrete and the concrete and preventing the inflow of concrete.

また、従来の施工法とことなりスリーブ等の各
種配管設備と仮枠パネル板とを釘、線材等で固定
する必要がないので、該仮枠パネルを傷めること
が少なく該仮枠パネルを複数回の使用できるとい
う効果を有する。
In addition, unlike conventional construction methods, there is no need to fix various piping equipment such as sleeves and the temporary frame panel board with nails, wires, etc., so there is less damage to the temporary frame panel, and the temporary frame panel can be used multiple times. It has the effect that it can be used for.

従つて、本考案によれば、スリーブ等の配管設
備等の固定と上端開口部の閉塞とを仮枠パネル面
上で同時に行え、釘、線材等を使用する必要がな
ので、施工時間の短縮化を図れるコンクリート打
設工事用固定セツターを提供できるという効果を
有する。
Therefore, according to the present invention, it is possible to simultaneously fix piping equipment such as sleeves and close the upper end opening on the surface of the temporary frame panel, and it is not necessary to use nails, wires, etc., so the construction time is shortened. This has the effect of providing a fixed setter for concrete pouring work that can achieve

【図面の簡単な説明】[Brief explanation of the drawing]

第1〜3図は、本考案の一実施例を示し、第1
図は斜視図、第2,3図は施工状態を示す断面図
である。 10:ロツド、11:カバー、13:係止具
(コーチスクリユー)、15:仮枠パネル、17:
雄螺子、16:ねじ込み用ハンドル、19:スタ
ピライザ、20:スリーブ、22:排水トラツ
プ。
1 to 3 show one embodiment of the present invention;
The figure is a perspective view, and Figures 2 and 3 are sectional views showing the construction state. 10: Rod, 11: Cover, 13: Locking tool (coach screw), 15: Temporary frame panel, 17:
Male screw, 16: Screw-in handle, 19: Stapillizer, 20: Sleeve, 22: Drainage trap.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 配管用スリーブや給排水金物等の配管設備を設
置するためのコンクリート打設工事用固定セツタ
ーであつて、仮枠パネルに係止するためのコーチ
スクリユーを下端に形成しかつ上部側に雄螺子を
有するロツドと、該コーチスクリユーの上位にお
いてロツドに一体化しかつ上記仮枠パネルに当接
する下面が該ロツド軸線と直交するスタピライザ
と、該スタピライザの上位においてロツドに昇降
自在に装着した配管設備の上端開口部を閉塞する
カバーと、該カバーの上位において上記ロツドの
雄螺子に螺合し該カバーを押さえるカバー固定具
とを有し、該カバーは縁端にカバー中央部に対し
て低くなる段差を有し、該段差部分が上記配管設
備の端部に当接するようにしたことを特徴とする
コンクリート打設工事用固定セツター。
This is a fixed setter for concrete pouring work for installing piping equipment such as piping sleeves and water supply and drainage hardware, and has a coach screw formed at the lower end for locking to the temporary frame panel and a male screw on the upper side. a rod having a rod, a stabilizer that is integrated with the rod above the coach screw and whose lower surface that contacts the temporary frame panel is orthogonal to the axis of the rod; and an upper end of piping equipment that is mounted on the rod above the stabilizer so that it can be raised and lowered. It has a cover that closes the opening, and a cover fixture that is screwed onto the male screw of the rod above the cover and holds the cover, and the cover has a step at the edge that is lower than the center of the cover. A fixed setter for concrete pouring work, characterized in that the stepped portion is in contact with an end of the piping equipment.
JP1985188932U 1985-12-07 1985-12-07 Expired JPH0341558Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1985188932U JPH0341558Y2 (en) 1985-12-07 1985-12-07

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1985188932U JPH0341558Y2 (en) 1985-12-07 1985-12-07

Publications (2)

Publication Number Publication Date
JPS6296433U JPS6296433U (en) 1987-06-19
JPH0341558Y2 true JPH0341558Y2 (en) 1991-08-30

Family

ID=31140758

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1985188932U Expired JPH0341558Y2 (en) 1985-12-07 1985-12-07

Country Status (1)

Country Link
JP (1) JPH0341558Y2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5949990A (en) * 1982-09-16 1984-03-22 Seiko Epson Corp Ink ribbon driving device for printer

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5949990A (en) * 1982-09-16 1984-03-22 Seiko Epson Corp Ink ribbon driving device for printer

Also Published As

Publication number Publication date
JPS6296433U (en) 1987-06-19

Similar Documents

Publication Publication Date Title
MX2008010910A (en) Mock shower drain and associated methods.
JP3251262B2 (en) PC board mounting method and mounting structure
JPH0341558Y2 (en)
JP3068799B2 (en) Scaffolding connection structure
JPH10238067A (en) Outer wall plate mounting tool
KR100737995B1 (en) Insert for ceiling finish panel installation
JP2706640B2 (en) Installation structure of renovated building and windows in renovated windows
KR200289587Y1 (en) Anchor bolt fastener for slab of building
JPH0334972Y2 (en)
JP3989381B2 (en) Basic rain drain
JP2716357B2 (en) Rising section formwork fixing jig
JPS6319475Y2 (en)
JP2736622B2 (en) Installation method of kitchen equipment, etc. and equipment / members used in the method
JPS63184665A (en) Method for embedding anchor for mounting handrail support
KR20190019449A (en) Distribution Panel for Easy Wall Distance Adjustment
KR970006047Y1 (en) Insert-cap anchor nut
KR0115315Y1 (en) Adjustable supporting construction of ceiling
JPH0229127Y2 (en)
JPH0598800A (en) Anchoring of handrail for opening curing and its fixture
JPS6336086Y2 (en)
JPS5840183Y2 (en) Corner drain mounting fixing device
JP3052276U (en) Fixing device for construction of square drain
EA044797B1 (en) COMBINED RETAINER AND FASTENER ASSEMBLY PRIMARILY DESIGNED FOR CONCRETE STRUCTURES AND METHOD FOR ITS USE
JPH04136636A (en) Installation device for air conditioner
KR200262708Y1 (en) A work mold of an outlet box