JPH0334532B2 - - Google Patents

Info

Publication number
JPH0334532B2
JPH0334532B2 JP10759684A JP10759684A JPH0334532B2 JP H0334532 B2 JPH0334532 B2 JP H0334532B2 JP 10759684 A JP10759684 A JP 10759684A JP 10759684 A JP10759684 A JP 10759684A JP H0334532 B2 JPH0334532 B2 JP H0334532B2
Authority
JP
Japan
Prior art keywords
joint
small
concrete
beams
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10759684A
Other languages
Japanese (ja)
Other versions
JPS60253639A (en
Inventor
Kazuo Takei
Shinichiro Sato
Minoru Shinbayashi
Mitsuo Nakagawa
Kazumitsu Tsubonuma
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tobishima Corp
Original Assignee
Tobishima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tobishima Corp filed Critical Tobishima Corp
Priority to JP10759684A priority Critical patent/JPS60253639A/en
Publication of JPS60253639A publication Critical patent/JPS60253639A/en
Publication of JPH0334532B2 publication Critical patent/JPH0334532B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、鉄筋コンクリート構造物、鉄骨鉄筋
コンクリート構造物、プレハブ工法による構造物
等の構造物において、プレキヤストコンクリート
製の小梁材を用いて小梁を構築する工法に関す
る。
Detailed Description of the Invention "Field of Industrial Application" The present invention is directed to the use of small beams made of precast concrete in structures such as reinforced concrete structures, steel reinforced concrete structures, and structures made by prefabricated construction methods. Concerning construction methods for constructing beams.

「従来の技術」 従来のこの種の工法は、主筋及びスターラツプ
筋等を埋設した中実のプレキヤストコンクリート
製小梁材を用い、コンクリート製の大梁の側面の
中途所定位置に突設された接合プレートと小梁材
の端面に突設された接合プレートとを接合具(ボ
ルト、ナツト等)によつて互いに接合及び溶接し
た後、その接合部分の周りに型枠を組んでコンク
リートを打設していた。
"Conventional technology" This type of conventional construction method uses solid precast concrete beams with main reinforcements, stirrup reinforcements, etc. buried, and joints that protrude at predetermined positions midway through the sides of the large concrete beams. After the plates and the joint plates protruding from the end faces of the small beams are joined and welded together using joints (bolts, nuts, etc.), a formwork is constructed around the joint and concrete is poured. was.

「発明が解決しようとする問題点」 しかし、これによると次のような問題点があつ
た。
``Problems that the invention seeks to solve'' However, according to this, there were the following problems.

(1) 大梁への架構と同時にそのまま小梁を完成す
る中実のプレキヤストコンクリート製小梁材を
用いるので、小梁自体の成型作業は現場では不
要であるが、小梁とスラブとを現場打ちコンク
リートによつて一体化できないため、小梁とス
ラブとの接合に特別の工法を必要とし、その作
業に高度の技術を要するばかりでなく、現場打
ちする場合に比べて材料コストが高くつく。
(1) Solid precast concrete beams are used to complete the small beams at the same time as the construction of the main beams, so there is no need to form the small beams themselves on site, but the small beams and slabs can be assembled on site. Because it cannot be integrated with poured concrete, special construction methods are required to join the beams and slabs, which not only requires advanced technology, but also costs more materials than pouring on-site.

(2) 小梁材が中実で重量が重いため、その搬送、
架構等の取扱いが容易でない。
(2) Because the small beams are solid and heavy, transporting them,
The structure, etc. is not easy to handle.

(3) 小梁材は主筋を埋設して成型されているた
め、現場で任意に適当な長さに切断して用いる
ことができなく、長さの異なるものを多数種用
意しなければならなく、コスト高になる。
(3) Because the small beams are molded with the main reinforcing bars buried, they cannot be cut to an appropriate length on site and many different lengths must be prepared. , the cost will be high.

(4) 大梁と小梁材とを接合プレートと接合具を用
いて接合するため、その材料コストが高くつく
とともに、その作業に高度の技術を要する。
(4) Since the main beam and the small beam are joined using a joining plate and a joining tool, the cost of materials is high and the work requires advanced technology.

(5) 接合部をコンクリートで部分的に被覆する必
要があるため、大梁と小梁との交叉部において
部分的な型枠をつくらなければならず、型枠工
事、その解体工事が甚だ面倒であるに加え、コ
ンクリート打設も入念に行わなければならな
く、多くの手間と時間を要する。
(5) Since it is necessary to partially cover the joint with concrete, a partial formwork must be made at the intersection of the major beam and the minor beam, making the formwork work and its dismantling extremely troublesome. In addition to this, concrete pouring must be done carefully, which requires a lot of effort and time.

本発明は、このような問題点を解消することを
目的とする。
The present invention aims to solve these problems.

「問題点を解決するための手段」 本発明は、小梁材として、断面U字状で全長に
わたつて凹溝を形成しかつ主筋は埋設しないで、
スターラツプ筋のみを埋設したプレキヤストコン
クリート製小梁材を用い、大梁の側面の中途所定
位置に予め仕口用凹部と横孔を形成し、小梁材の
端面を上記仕口用凹部に一致させ、小梁材の凹溝
内に主筋を配筋するとともにその主筋に連結する
ジヨイント筋を上記横孔内に配筋し、その後、こ
れら凹溝と横孔の内部及び仕口用凹部と小梁材の
端面との間にコンクリートを打設することを特徴
とする。
"Means for Solving the Problems" The present invention is a small beam material that has a U-shaped cross section and has a concave groove formed over its entire length, without burying the main reinforcing bars.
Using precast concrete beams with only stirrup reinforcements buried, a recess for a joint and a horizontal hole are formed in advance at a predetermined position midway on the side of the main beam, and the end face of the small beam is aligned with the recess for a joint. , Arrange the main reinforcement in the concave groove of the small beam material, and place the joint reinforcement that connects to the main reinforcement in the horizontal hole, and then insert the inside of these grooves and the horizontal hole, the joint recess, and the small beam. It is characterized by pouring concrete between the end faces of the timber.

「実施例」 以下に本発明の実施例を図面に基づいて詳述す
る。
"Example" Examples of the present invention will be described in detail below based on the drawings.

第1,2図において、大梁1は壁2と一体成型
されたプレキヤストコンクリート製で、H型鋼3
を埋設している。この大梁1の中途所定位置に
は、その両側面に、小梁材4を接合するための方
形な仕口用凹部5が形成されているとともに、そ
の両側面に貫通する横長長方形状の横孔6が形成
されている。各凹部5は、大梁1の上端から下端
部中途まで伸びて下端に段部7を形成している。
凹部5の内面は凹凸のある粗面になつている。横
孔6は段部7の少し上方において開口している。
In Figures 1 and 2, the girder 1 is made of precast concrete integrally formed with the wall 2, and the H-shaped steel 3
is buried. At a predetermined midway position of this large beam 1, a rectangular joint recess 5 for joining the small beam material 4 is formed on both sides thereof, and an oblong rectangular horizontal hole penetrating both sides thereof. 6 is formed. Each recess 5 extends from the upper end of the main beam 1 to the middle of the lower end, and forms a step 7 at the lower end.
The inner surface of the recess 5 is a rough surface with unevenness. The horizontal hole 6 opens slightly above the step 7.

小梁材4もプレキヤストコンクリート製で、断
面U字状に成型され、その凹溝8の内周面に沿つ
て多数のスターラツプ筋9を埋設しているが、主
筋は埋設していない。スターラツプ筋9の上枠部
は小梁材4の両側上面より突出している。
The small beam material 4 is also made of precast concrete and is formed into a U-shaped cross section, and has a large number of stirrup reinforcements 9 buried along the inner peripheral surface of the groove 8, but no main reinforcement. The upper frame portions of the stirrup bars 9 protrude from both upper surfaces of the small beam members 4.

小梁材4は隣接する平行な2本の大梁1間に次
のようにして架構する。
The small beam material 4 is constructed between two adjacent parallel large beams 1 in the following manner.

先ず、配列しているスターラツプ筋9の上枠部
の内側に、複数本の上主筋10を針金等を用いて
保持し、また凹溝8内に複数本の下主筋11を挿
入しておいた後、合成樹脂ベルト12とワイヤー
12′を用いて小梁材4をクレーン等で懸吊し、
直下階のスラブ上に起立させた伸縮自在な支持脚
13上に第3,4図に示すように載置する。この
状態で小梁材4の端面を大梁1の凹部5に一致さ
せる。その際、小梁材4の架構調整のため、小梁
材4は、その端面を凹部5に密着させずしかも段
部7上に載置しないで、凹部5との間に適当な間
隙が形成される状態にするのが望ましい。
First, a plurality of upper main reinforcements 10 were held inside the upper frame part of the arranged stirrup muscles 9 using a wire or the like, and a plurality of lower main reinforcements 11 were inserted into the grooves 8. After that, the small beam material 4 is suspended using a crane or the like using the synthetic resin belt 12 and the wire 12'.
It is placed on retractable support legs 13 that are erected on the slab on the floor immediately below, as shown in FIGS. 3 and 4. In this state, the end face of the small beam 4 is aligned with the recess 5 of the main beam 1. At this time, in order to adjust the frame of the small beam 4, the end surface of the small beam 4 is not brought into close contact with the recess 5, nor is it placed on the step 7, so that an appropriate gap is formed between it and the recess 5. It is desirable to have it in a state where it is possible.

大梁1と小梁材4とをこのような関係にする
と、大梁1の両側に設置された直列する2本の小
梁材4の凹溝8は横孔6を介して互いに連通し、
また大梁1の上面と小梁材4の両側上面とはほぼ
同一水平面上に位置する。
When the main beam 1 and the small beam members 4 are in such a relationship, the concave grooves 8 of the two small beam members 4 installed in series on both sides of the main beam 1 communicate with each other via the horizontal holes 6,
Further, the upper surface of the main beam 1 and the upper surfaces of both sides of the small beam members 4 are located on substantially the same horizontal plane.

次に、並列する小梁材4間に第5〜7図に示す
ように従来公知のスラブ用薄肉プレキヤストコン
クリート板14を設置した後、第8図に示すよう
に大梁1を挟んで直列する小梁材4相互の上主筋
10同士を上ジヨイント筋15で、また下主筋1
1同士を大梁1の横孔6中を貫通させた下ジヨイ
ント筋16でそれぞれ連結する一方、第9図に示
すように小梁材4の両側のトラス板14の上端筋
17同士を上ジヨイント筋18で連結し、また両
側のトラス板14の上面間に下ジヨイント筋19
を設置する。鉄筋の連結は例えば針金を巻き付け
るなど仮止め程度の連結で十分である。
Next, as shown in FIGS. 5 to 7, conventionally known thin precast concrete plates 14 for slabs are installed between the parallel small beams 4, and then they are placed in series across the girders 1 as shown in FIG. The upper main reinforcements 10 of the small beams 4 are connected to each other by the upper joint reinforcements 15, and the lower main reinforcements 1
1 are connected to each other by lower joint reinforcements 16 passing through the horizontal holes 6 of the main beams 1, and upper joint reinforcements 17 of the truss plates 14 on both sides of the small beam members 4 are connected to each other by upper joint reinforcements 17, as shown in FIG. 18, and a lower joint bar 19 between the upper surfaces of the truss plates 14 on both sides.
Set up. For example, it is sufficient to temporarily connect the reinforcing bars by wrapping wire around them.

この後、小梁材4の凹溝8内、大梁1の横孔6
内、小梁材4の端面と凹部5との間、及び薄肉プ
レキヤストコンクリート板14上にコンクリート
を打設し、上下主筋10,11及びスターラツプ
筋9の上枠部をコンクリート20中に埋設して小
梁を構築すると同時に、薄肉プレキヤストコンク
リート板14の上端筋17及びラチス筋21を同
じくコンクリート20中に埋設してスラブを構築
する。
After this, inside the concave groove 8 of the small beam material 4, the horizontal hole 6 of the main beam 1
Concrete is poured between the end face of the small beam 4 and the recess 5 and on the thin precast concrete plate 14, and the upper and lower main reinforcements 10, 11 and the upper frame part of the stirrup reinforcement 9 are buried in the concrete 20. At the same time, the upper end reinforcements 17 and lattice reinforcements 21 of the thin precast concrete plate 14 are buried in the concrete 20 to construct a slab.

なお、上記実施例では、大梁1と壁2を一体な
プレキヤストコンクリート製としたが、これらは
第10図に示すように一体に現場打ちしてもよ
く、また第11図に示すように小梁材4と同じ構
造、つまり断面U字状で凹溝22の内周面に沿つ
て多数のスターラツプ筋23を埋設したプレキヤ
ストコンクリート製の大梁材24を用いる場合に
は、凹溝22を形成する側壁の外側面に仕口用凹
部5を設けるとともにそこに横孔6を貫通形成
し、その凹部5に小梁材4を上記と同様にして架
構し、かつ、主筋11及びジヨイント筋16を上
記と同じようにして配筋した後、その凹溝22内
にコンクリートを打設して大梁を小梁及びスラブ
と同時に構築し、壁2はこれとは別に現場打ちし
てもよい。また、上記実施例は、小梁材4を大梁
1の両側に架構する場合を想定したが、一方側だ
け架構する場合には上下のジヨイント筋15,1
6が大梁1の他方側に突出しないようにすればよ
い。この場合、仕口用凹部5は大梁1の一方側に
のみ形成する。
In the above embodiment, the girder 1 and the wall 2 are made of integral precast concrete, but they may be cast in the field as one piece as shown in Fig. 10, or they may be made of small-sized concrete as shown in Fig. 11. When using a girder 24 made of precast concrete that has the same structure as the beam 4, that is, a U-shaped cross section and a large number of stirrup bars 23 embedded along the inner peripheral surface of the groove 22, the groove 22 is formed. A recess 5 for a joint is provided on the outer surface of the side wall, and a horizontal hole 6 is formed therethrough, and a small beam material 4 is constructed in the recess 5 in the same manner as above, and the main reinforcement 11 and joint reinforcement 16 are installed. After arranging reinforcement in the same manner as described above, concrete is poured into the groove 22 to construct the girder at the same time as the girder and the slab, and the wall 2 may be cast separately on site. In addition, in the above embodiment, the case where the small beam members 4 are constructed on both sides of the large beam 1 is assumed, but when only one side is constructed, the upper and lower joint bars 15, 1
6 should be prevented from protruding to the other side of the girder 1. In this case, the joint recess 5 is formed only on one side of the girder 1.

「発明の効果」 叙上のように本発明によれば次のような効果が
ある。
"Effects of the Invention" As mentioned above, the present invention has the following effects.

小梁をスラブと同時にしかも現場打ちコンク
リートによつてそれと一体に構築できるため、
従来に比べスラブの施工作業が著しく単純化さ
れるとともに、材料コストも割安になる。
Because the beams can be constructed simultaneously with the slab and integrally with it using cast-in-place concrete,
Slab construction work is significantly simpler than before, and material costs are also lower.

小梁材が中空で軽量であるため、その搬送、
架構等の取扱いが容易である。
Because the beams are hollow and lightweight, they are easy to transport,
The structure is easy to handle.

小梁材は、スターラツプ筋は埋設しているが
主筋は埋設していないため、小梁材を現場で任
意に適当な長さに切断して用いることができ、
従つて従来のように長さの異なるものを多数種
用意する必要はなく、経済的である。
The stirrup bars are buried in the small beams, but the main bars are not, so the small beams can be cut to any desired length on site.
Therefore, there is no need to prepare a large number of different lengths as in the past, which is economical.

小梁材の端面を大梁の仕口用凹部に一致さ
せ、小梁材の凹溝内に主筋を配筋するとともに
その主筋に連結するジヨイント筋を大梁の横孔
内に配筋し、その後、コンクリートを打設する
ことによつて小梁を構築できるため、大梁と小
梁材とを接合プレートと接合具とを用いて接合
していた従来工法に比べ、材料コストが安くな
るとともに、作業も簡単である。
Align the end faces of the small beams with the joint recesses of the girders, place main reinforcements in the grooves of the small beams, and place joint reinforcements that connect to the main reinforcements in the horizontal holes of the girders. Because the small beams can be constructed by pouring concrete, the material costs are lower and the work is easier compared to the conventional construction method in which the large beams and small beams are joined using joining plates and fittings. It's easy.

小梁材の凹溝内にコンクリートを充填すれ
ば、それと同時に大梁の横孔及びその仕口用凹
部と小梁材の端面との間にもコンクリートが填
入され、大梁と小梁とがコンクリートによつて
一体化されるもので、従来のような複雑な型枠
工事及びその解体工事並びにコンクリート打設
工事が不要となるため、従来に比べ工期を著し
く短縮できるとともに工費の節減を図れる。
When concrete is filled into the concave groove of the small beam, concrete is also filled between the horizontal hole of the large beam, its joint recess, and the end face of the small beam, so that the large beam and the small beam are filled with concrete. This eliminates the need for complex form work, its dismantling work, and concrete pouring work as in the past, making it possible to significantly shorten the construction period and reduce construction costs compared to the past.

【図面の簡単な説明】[Brief explanation of drawings]

第1〜9図は本発明の一実施例を施工手順に従
つて示し、第1,3,5,7図は斜視図、第2,
4,6図は断面図、第8,9図は拡大断面図、第
10,11図はそれぞれ他の実施例を示す要部断
面図である。 1……大梁、5……仕口用凹部、6……横孔、
4……小梁材、8……凹溝、9……スターラツプ
筋、10,11……上下主筋、15,16……ジ
ヨイント筋。
Figures 1 to 9 show an embodiment of the present invention according to the construction procedure; Figures 1, 3, 5, and 7 are perspective views;
4 and 6 are sectional views, FIGS. 8 and 9 are enlarged sectional views, and FIGS. 10 and 11 are sectional views of main parts showing other embodiments. 1... girder, 5... recess for joint, 6... horizontal hole,
4...Small beam material, 8...Concave groove, 9...Starlap reinforcement, 10, 11...Upper and lower main reinforcement, 15, 16...Joint reinforcement.

Claims (1)

【特許請求の範囲】[Claims] 1 プレキヤストコンクリート製または現場打ち
コンクリート製の大梁の側面の中途所定位置に仕
口用凹部と横孔を形成し、スターラツプ筋が埋設
された断面U字状のプレキヤストコンクリート製
の小梁材の端面を上記仕口用凹部に一致させ、小
梁材の凹溝内に主筋を配筋するとともにこの主筋
に連結するジヨイント筋を上記横孔内に配筋し、
その後、これら凹溝と横孔の内部及び仕口用凹部
と小梁材の端面との間にコンクリートを打設する
ことを特徴とする小梁の構築工法。
1 A small precast concrete beam with a U-shaped cross section and a stirrup reinforcement is formed by forming a joint recess and a horizontal hole at a predetermined position midway on the side of a large beam made of precast concrete or cast-in-place concrete. Align the end face with the concave part for the joint, arrange the main reinforcement in the concave groove of the small beam material, and arrange the joint reinforcement connected to this main reinforcement in the horizontal hole,
Thereafter, concrete is poured inside the groove and the horizontal hole and between the concave part for the joint and the end face of the beam material.
JP10759684A 1984-05-29 1984-05-29 Construction of small beam Granted JPS60253639A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10759684A JPS60253639A (en) 1984-05-29 1984-05-29 Construction of small beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10759684A JPS60253639A (en) 1984-05-29 1984-05-29 Construction of small beam

Publications (2)

Publication Number Publication Date
JPS60253639A JPS60253639A (en) 1985-12-14
JPH0334532B2 true JPH0334532B2 (en) 1991-05-23

Family

ID=14463164

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10759684A Granted JPS60253639A (en) 1984-05-29 1984-05-29 Construction of small beam

Country Status (1)

Country Link
JP (1) JPS60253639A (en)

Also Published As

Publication number Publication date
JPS60253639A (en) 1985-12-14

Similar Documents

Publication Publication Date Title
JP2928475B2 (en) Precast concrete girder for composite floor slab
JP2885055B2 (en) Construction method of frame with precast members
JPH0334532B2 (en)
JPH0868113A (en) Connecting structure for steel beam and reinforced concrete beam
JPH0270850A (en) Pc coupled beam and execution of construction using same
JPH04237735A (en) Constructing method for pillar and beam of building
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH0375704B2 (en)
JPH01174735A (en) Construction of framework member in precast rc framework structure
JPH0514063B2 (en)
JPH05179700A (en) Jointing method of precast girder to precast beam
JPS6347201Y2 (en)
JP3749935B2 (en) Column and beam construction method and enclosure
JP2700740B2 (en) Prefabricated method using precast beam
JPH079921Y2 (en) Joint structure between reinforced concrete column and steel beam
JPS6139457B2 (en)
JPH02274938A (en) Combining method for src column
JPH04128442A (en) Method for joining pc column and pc wall
JPH0443131B2 (en)
JPH0781315B2 (en) Construction method of composite structure with precast reinforced concrete columns and steel beams
JPH067075Y2 (en) Building foundation
JPS6134549B2 (en)
JPH0751802B2 (en) Prefabricated unit made of steel reinforced concrete
JPH04140366A (en) Preceding erection method of prefabricated column bar and semi-pc girder in pc construction

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees