JPH03275900A - Excavation method of shield tunnel - Google Patents

Excavation method of shield tunnel

Info

Publication number
JPH03275900A
JPH03275900A JP2076243A JP7624390A JPH03275900A JP H03275900 A JPH03275900 A JP H03275900A JP 2076243 A JP2076243 A JP 2076243A JP 7624390 A JP7624390 A JP 7624390A JP H03275900 A JPH03275900 A JP H03275900A
Authority
JP
Japan
Prior art keywords
tunnel
concrete
formwork
arc
circumferential direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2076243A
Other languages
Japanese (ja)
Inventor
Akira Nakanishi
章 中西
Toshimi Ino
伊野 敏美
Isao Hashimoto
功 橋本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2076243A priority Critical patent/JPH03275900A/en
Publication of JPH03275900A publication Critical patent/JPH03275900A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To prevent a non-filled cavity from generating against soil subsidence by placing concrete, while moving mold frames having the same curvature as the inner circumference of tunnel to the circumferential direction of the tunnel, and excavating along the circumferential direction of the tunnel. CONSTITUTION:A part of arc frames 4 is pressed on the inside face of respective tunnel bodies 5a-5e and the arc frames 4 is fixed while being shifted. Next, a gable plate 6 is fitted to the periphery of the arc frame 4 and high-early- strength concrete 7 is charged in the arc frame 4 from a shielding machine. Next, after the concrete 7 is cured, the arc frame 4 is removed off and transferred to the front direction of the next tunnel body 5b. And a shield jack 2 is pressed on the whole face of the cured tunnel body 5 at the periphery except the placed range of the concrete 7 to get a reaction force in order to parallely carry out excavation work of the shielding machine 1 and construction work of the tunnel body 5. In this way, the construction term can be reduced.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は場所打ちライニング技術に関し、詳細にはシー
ルド掘進と並行して覆工可能なシールドトンネルの覆工
方法に関する。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to cast-in-place lining technology, and more particularly to a method for lining a shield tunnel that can be lined in parallel with shield excavation.

〈従来の技術〉 シールド工法の覆工法として、場所打ちライニング法が
知られている。
<Conventional Technology> A cast-in-place lining method is known as a lining method for the shield method.

この方法はシールド機のテール部の内側に環状に型枠を
組み立て、型枠と地山との間にコンクリートを打設して
最終覆工とする方法である。
This method involves assembling a ring-shaped formwork inside the tail of a shielding machine, and pouring concrete between the formwork and the ground to form the final lining.

またこの種の覆工法においては、コンクリートに所要の
強度が発現したときに型枠を反力受けとしてシールド機
を推進させている。
In addition, in this type of lining method, when the concrete has developed the required strength, the shielding machine is propelled by using the formwork as a reaction force receiver.

〈本発明が解決しようとする問題点〉 前記した従来の場所打ちライニング技術にはつぎのよう
な問題点がある。
<Problems to be Solved by the Present Invention> The conventional cast-in-place lining technology described above has the following problems.

くイ〉 型枠と地山間の広乾囲にコンクリートを直接打
設するため、隅々までコンクリートが充填され難い。
Because concrete is placed directly in the wide dry area between the formwork and the ground, it is difficult to fill every corner with concrete.

そのため、−地山と覆工との間にコンクリートの未充填
部分(テールボイド)を生じ、地盤沈下の原因になる。
Therefore, an unfilled portion (tail void) of concrete is created between the ground and the lining, causing ground subsidence.

〈口〉 型枠の組立作業の都度、掘削作業を中断しなけ
ればならず、工期が長期化する傾向の原因になっている
<Examination> Excavation work has to be interrupted each time the formwork is assembled, which tends to lengthen the construction period.

〈本発明の目的〉 本発明は以上の問題点を解決するために成されたもので
、その目的とするところは施工性に優れ、工期の短縮を
図れるシールドトンネルの覆工方法を提供することにあ
る。
<Objective of the present invention> The present invention was made in order to solve the above problems, and its purpose is to provide a shield tunnel lining method that has excellent workability and can shorten the construction period. It is in.

〈問題点を解決するための手段〉 即ち本発明はシールド機内で組み立てた型枠内にコンク
リートを打設してトンネル躯体を構築するシールドトン
ネルの覆工方法において、トンネルの内周と同し曲率を
有する型枠を使用し、前記型枠をトンネルの円周方向に
移動しながらコンクリートを打設し、トンネルの円周方
向に沿って覆工することを特徴とする、シールドトンネ
ルの覆工方法である。
<Means for Solving the Problems> That is, the present invention provides a shield tunnel lining method in which a tunnel body is constructed by pouring concrete into a formwork assembled in a shield machine. A method for lining a shield tunnel, characterized by using a formwork having a structure, placing concrete while moving the formwork in the circumferential direction of the tunnel, and lining the tunnel along the circumferential direction. It is.

〈本発明の説明〉 以下、図面を参照しながら本発明について説明する。<Description of the present invention> The present invention will be described below with reference to the drawings.

〈イ〉型枠 第1図にトンネル先端部の縦断面図を示す。<A> Formwork Figure 1 shows a longitudinal cross-sectional view of the tunnel tip.

1は公知のシールド機で、内部に複数組のシールドジヤ
ツキ2を備えている。
Reference numeral 1 denotes a known shield machine, which is equipped with a plurality of sets of shield jacks 2 inside.

本発明はシールド機1のテール部3内で組み立てる円弧
型枠4の形状と、円弧型枠4の使用方法に特徴を有する
The present invention is characterized by the shape of the arcuate formwork 4 assembled within the tail portion 3 of the shield machine 1 and the method of using the arcuate formwork 4.

従来の型枠が円環形であるのに対し、本発明で使用する
円弧型枠4は円弧形である。
While the conventional formwork has an annular shape, the arc formwork 4 used in the present invention has a circular arc shape.

また、従来が円環状に覆工するのに対し、本発明では円
弧形の覆工を渦巻き状に連続して覆工する。
Furthermore, whereas in the past the lining is circular, in the present invention the arc-shaped lining is continuous in a spiral shape.

〈口〉シールド機の推進反力 従来は型枠からシールド機の推進反力を得ていたが、本
発明ではコンクリート打設中の範囲を除く硬化したトン
ネル5の躯体から反力を得る。
<Exposure> Propulsion reaction force of the shield machine Conventionally, the propulsion reaction force of the shield machine was obtained from the formwork, but in the present invention, the reaction force is obtained from the hardened skeleton of the tunnel 5 except for the area during concrete pouring.

〈作用〉 つぎにトンネルの覆工方法について説明する。<Effect> Next, the tunnel lining method will be explained.

〈イ〉型枠の組み立て 型枠4をシールド機1のテール部3内で組み立てること
は従来と同様である。
<A> Assembling the formwork The formwork 4 is assembled within the tail portion 3 of the shielding machine 1 in the same manner as in the conventional method.

第2図に示すようにトンネル躯体5aを延長する場合は
、円弧型枠4の一部を既設の各トンネル躯体5a、5b
、5eの内側面に押し当てる。
When extending the tunnel body 5a as shown in FIG.
, 5e.

この際、トンネル躯体5aの切羽側にコンクリート打設
空間を隔成できるように円弧型枠4をずらして固定する
At this time, the arcuate formwork 4 is shifted and fixed so that a space for placing concrete can be isolated on the face side of the tunnel body 5a.

円弧型枠4の周縁部に妻板6を取り付ける。An end plate 6 is attached to the peripheral edge of the arc formwork 4.

これによりテール部3と円弧型枠4との間にコンクリー
ト打設用の区画した空間が形成される。
As a result, a partitioned space for pouring concrete is formed between the tail portion 3 and the arcuate formwork 4.

〈口〉コンクリートの打設 予め円弧型枠4または妻板6にコンクリート注入用の開
口を開設しておく。
<Opening> Before pouring concrete, an opening for pouring concrete is opened in the arc formwork 4 or end board 6.

そして、シールド機1内から円弧型枠4内に早強性のコ
ンクリートを充填する。
Then, early-strengthening concrete is filled into the arcuate formwork 4 from within the shielding machine 1.

一 コンクリート7が硬化しり円弧型枠4を脱型する。one The concrete 7 hardens and the arcuate formwork 4 is removed from the mold.

脱型した円弧型枠4を隣のトンネル躯体5bの前方へコ
ンクリート打設するために枠組する。
The demolded arc formwork 4 is assembled in order to cast concrete in front of the adjacent tunnel frame 5b.

以下円弧型枠4をトンネル躯体5C15d、5e・・・
の前方にコンクリートを打設するために順次移動しなが
ら、渦巻き状にトンネル5の躯体を増設していく。
Below, the arc formwork 4 is used as the tunnel frame 5C15d, 5e...
While moving one by one to place concrete in front of the tunnel, the frame of the tunnel 5 is added in a spiral manner.

〈ハ〉シールド機の掘進 従来はコンクリートの養生期間中にシールド機を掘進て
きなかった。
<C> Excavation with shield machine Traditionally, shield machine was not used to excavate during the concrete curing period.

本発明はトンネル5の全周に亘ってコンクリートを打設
するのではなく、円周の一部の範囲に打設する。
In the present invention, concrete is not poured over the entire circumference of the tunnel 5, but concrete is poured over a part of the circumference.

コンクリートの打設範囲を除く円周部分は硬化している
から、この硬化しているトンネル躯体の全面にシールド
ジヤツキ2を押し当てて反力を得る。
Since the circumferential portion excluding the area where concrete is placed is hardened, the shield jack 2 is pressed against the entire surface of this hardened tunnel body to obtain a reaction force.

したがって、シールド機1の掘進作業とトンネル躯体の
構築作業を並行して行える。
Therefore, the excavation work of the shield machine 1 and the construction work of the tunnel frame can be performed in parallel.

〈その他の実施例〉 前記実施例は1枚の円弧型枠4を使って覆工する場合に
ついて説明したが、トンネル5が大断面である場合は、
複数枚の円弧型枠4を用いて施工してもよい。
<Other Examples> In the above example, the case where the lining was performed using one circular arc formwork 4 was explained, but when the tunnel 5 has a large cross section,
Construction may be performed using a plurality of arcuate formworks 4.

また、型枠は円弧形に限定されず、トンネル5の断面形
状に応じた形状を有すればよい。
Furthermore, the formwork is not limited to an arcuate shape, but may have a shape that corresponds to the cross-sectional shape of the tunnel 5.

また、前記実施例はコンクリートの躯体を渦巻き状に打
ち継ぎする場合について説明したが、−円弧形のトンネ
ル躯体を円周方向に打ち継ぎして1リングを構築し、こ
れを連続してトンネルを覆工してもよい。
In addition, although the above embodiment described the case where the concrete frame is poured in a spiral shape, - one ring is constructed by piecing the arc-shaped tunnel frame in the circumferential direction, and this ring is continuously poured into the tunnel. may be lined.

〈口〉 コンクリートの打設作業と、シールド機の掘進
を並行して行えるので、工期の短縮を図れる。
<Exposure> Concrete placement work and shield machine excavation can be performed in parallel, reducing construction time.

〈ハ〉 −度に円環状にトンネル躯体を構築する場合と
比べて、小段取りで済む。
<C> - Compared to the case where the tunnel frame is constructed in a circular manner, only a small number of setups are required.

【図面の簡単な説明】[Brief explanation of drawings]

第1図二本発明の覆工方法を説明するためのトンネルの
先端部の縦断面図 第2図:トンネル躯体の増設順序を説明するためのトン
ネルの斜視図 〈本発明の効果〉 本発明は以上説明したようになるから次の効果が得られ
る。 〈イ〉 トンネルの躯体を部分的に構築できるので、未
充填空間の発生を有効に阻止できる。 これにより効果的に地盤沈下を防止できる。
Fig. 1.2: A vertical sectional view of the tip of a tunnel for explaining the lining method of the present invention. Fig. 2: A perspective view of the tunnel for explaining the order of adding the tunnel body. <Effects of the present invention> The present invention As explained above, the following effects can be obtained. <B> Since the tunnel framework can be constructed partially, the occurrence of unfilled spaces can be effectively prevented. This effectively prevents ground subsidence.

Claims (1)

【特許請求の範囲】[Claims] (1)シールド機内で組み立てた型枠内にコンクリート
を打設してトンネル躯体を構築するシールドトンネルの
覆工方法において、 トンネルの内周と同じ曲率を有する型枠を 使用し、 前記型枠をトンネルの円周方向に移動しな がらコンクリートを打設し、トンネルの円 周方向に沿って覆工することを特徴とする、シールドト
ンネルの覆工方法。
(1) In a shield tunnel lining method in which a tunnel frame is constructed by pouring concrete into a formwork assembled in a shield machine, a formwork having the same curvature as the inner circumference of the tunnel is used, and the formwork is A shield tunnel lining method characterized by placing concrete while moving in the circumferential direction of the tunnel and lining the tunnel along the circumferential direction.
JP2076243A 1990-03-26 1990-03-26 Excavation method of shield tunnel Pending JPH03275900A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2076243A JPH03275900A (en) 1990-03-26 1990-03-26 Excavation method of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2076243A JPH03275900A (en) 1990-03-26 1990-03-26 Excavation method of shield tunnel

Publications (1)

Publication Number Publication Date
JPH03275900A true JPH03275900A (en) 1991-12-06

Family

ID=13599742

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2076243A Pending JPH03275900A (en) 1990-03-26 1990-03-26 Excavation method of shield tunnel

Country Status (1)

Country Link
JP (1) JPH03275900A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106150521A (en) * 2016-06-29 2016-11-23 上海朗兆公路铁路养护工程技术有限公司 A kind of construction method preventing and treating uneven changeover portion duct pieces of shield tunnel cracking
CN112983467A (en) * 2021-04-08 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Treatment method for tunnel gate closing type large collapse

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106150521A (en) * 2016-06-29 2016-11-23 上海朗兆公路铁路养护工程技术有限公司 A kind of construction method preventing and treating uneven changeover portion duct pieces of shield tunnel cracking
CN112983467A (en) * 2021-04-08 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Treatment method for tunnel gate closing type large collapse

Similar Documents

Publication Publication Date Title
JPH055040B2 (en)
JP3285261B2 (en) Precast formwork for tunnel lining
JPH03275900A (en) Excavation method of shield tunnel
KR20010026028A (en) Shaft construction system using precasted segment block
JPH07324595A (en) Inner concrete form and secondary lining method for shield tunnel of internal water pressure compliance type
JP2544829B2 (en) How to build an underground cavity
JPH032498A (en) Construction of tunnel lining
JPH011894A (en) In-situ lining method for shield tunnels
JP2814020B2 (en) Inner formwork
JPH01182498A (en) Cut-off method for tail part in cast-in-place concrete lining process
JPH05287983A (en) Construction of underground space having long and large diametral dimension
JPH01198995A (en) Cast-in-place lining method
JPS62220698A (en) Early stage stabilizing construction method of ground in non-segment shield construction method
JPH08199970A (en) Construction method of large sectional tunnel and divided segments
JPH07119167A (en) Building structure and execution method thereof
JPH0493498A (en) Concrete placing device for covering tunnel
JPS63107697A (en) Lining method of shield tunnel
JPS63312417A (en) Water construction of continuous wall using steel caisson
JPH01235798A (en) Concrete mold device
JPH05118194A (en) Sealing method of lining in cast-in-place lining shield method
JPH0439355Y2 (en)
JPS6354875B2 (en)
JPS63300200A (en) Method of cast-in-place lining shielding construction
JPS6332239Y2 (en)
JPH01271600A (en) Concrete placing for cast-in-place concrete lining construction