JPH0326175Y2 - - Google Patents
Info
- Publication number
- JPH0326175Y2 JPH0326175Y2 JP1983092716U JP9271683U JPH0326175Y2 JP H0326175 Y2 JPH0326175 Y2 JP H0326175Y2 JP 1983092716 U JP1983092716 U JP 1983092716U JP 9271683 U JP9271683 U JP 9271683U JP H0326175 Y2 JPH0326175 Y2 JP H0326175Y2
- Authority
- JP
- Japan
- Prior art keywords
- flat
- steel stranded
- stranded wires
- unbonded
- rust preventive
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 12
- 239000010959 steel Substances 0.000 claims description 12
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 claims description 5
- 230000003449 preventive effect Effects 0.000 claims description 5
- 239000011513 prestressed concrete Substances 0.000 claims description 2
- 230000000694 effects Effects 0.000 description 4
- 239000003795 chemical substances by application Substances 0.000 description 3
- 238000010276 construction Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 229920003002 synthetic resin Polymers 0.000 description 3
- 239000000057 synthetic resin Substances 0.000 description 3
- 238000005452 bending Methods 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004519 grease Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Description
【考案の詳細な説明】
「産業上の利用分野」
本考案は、プレストレストコンクリート用アン
ボンド・フラツトケーブルに係るものである。[Detailed Description of the Invention] "Industrial Application Field" The present invention relates to an unbonded flat cable for prestressed concrete.
「従来の技術と考案が解決しようとする課題」
コンクリート建築物において、大梁やスラブに
アンボンドケーブルを用いてプレストレスを導入
することが知られている。``Problems to be solved by conventional technology and ideas'' In concrete buildings, it is known to introduce prestress into girders and slabs using unbonded cables.
アンボンドケーブルは、1本のPC鋼より線に
防錆剤を塗布し、その周りを合成樹脂製チユーブ
等の被覆材で覆つたものであるが、プレストレス
導入に当たり、強度上、複数本を列べて用いるこ
とも多く、その場合には、多大な手数がかかつて
いる。 Unbonded cables are made by coating a single PC steel strand with a rust preventive agent and surrounding it with a covering material such as a synthetic resin tube, but when introducing prestressing, multiple strands are connected in a row for strength reasons. In many cases, multiple methods are used, which requires a great deal of effort.
複数のアンボンドケーブルを予め束ねて用いる
ことも考えられているが、こうすると、全体とし
ての径が大きくなるため、二方向交差させる場合
に大きく位置がずれ、扁平大梁やスラブにあつて
は、吊上げ効果を得るべく途中を下方へと撓ませ
ていわゆる偏心距離を確保することが困難とな
り、また、各アンボンドケーブルの作用が不均一
となり、ロスが多くなる。 It has been considered to use multiple unbonded cables bundled in advance, but this increases the overall diameter, resulting in large misalignment when crossing in two directions, making it difficult to lift a flat girder or slab. It becomes difficult to secure a so-called eccentric distance by bending the middle part downward in order to obtain the effect, and the action of each unbonded cable becomes uneven, resulting in a large amount of loss.
本考案は、斯る問題点を解決しようとするもの
である。 The present invention attempts to solve such problems.
「課題を解決するための手段」
本考案は、複数のPC鋼より線2……を互いに
隣接させて一列に配列し、これらのPC鋼より線
2……に防錆剤を塗布して、これら全体を1つの
フラツトシース1で包被したことを特徴とする。"Means for Solving the Problem" The present invention consists of arranging a plurality of PC steel stranded wires 2 in a line adjacent to each other, applying a rust preventive to these PC steel strands 2, and It is characterized in that all of these are covered with one flat sheath 1.
上記フラツトシース1は、合成樹脂等から成る
扁平なチユーブ状の被覆材である。 The flat sheath 1 is a flat tube-shaped covering material made of synthetic resin or the like.
「作用」
如上の構成であるから、大梁やスラブにてプレ
ストレス導入の際は、平らな二面を上下に面させ
て配し、交差点では相互に重合させる。また、中
間部では、吊上げ効果を得るべく下方へと撓ま
せ、いわゆる偏心距離を確保する。``Operation'' Because of the above configuration, when prestressing a girder or slab, the two flat surfaces are placed facing up and down, and overlap each other at the intersection. In addition, the intermediate portion is bent downward to obtain a lifting effect, thereby ensuring a so-called eccentric distance.
「実施例」 図面は、本考案の実施例を示している。"Example" The drawings show an embodiment of the invention.
図示のものは、4本のPC鋼より線2……を互
いに隣接させて一列に配列し、これらのPC鋼よ
り線2……にグリース等の防錆剤2を塗布して、
これら全体を合成樹脂製の扁平なチユーブ状被覆
材たるフラツトシース1により包被したものであ
る。 In the illustrated example, four PC steel stranded wires 2... are arranged in a line adjacent to each other, and a rust preventive agent 2 such as grease is applied to these PC steel stranded wires 2.
The entire structure is covered with a flat sheath 1 which is a flat tube-shaped covering material made of synthetic resin.
なお、PC鋼より線2……の本数は、4本に限
るものではなく、所要により適宜である。 The number of PC steel stranded wires 2 is not limited to four, and may be determined as required.
「考案の効果」
本考案によれば、複数のPC鋼より線2……を
1つのフラツトシース1内に一列に並設している
ので、複数のアンボンドケーブルを必要とすると
きは、1回で配線でき、手数を大幅に低減でき
る。``Effect of the invention'' According to the invention, multiple PC steel stranded wires 2 are arranged in a row in one flat sheath 1, so when multiple unbonded cables are required, they can be unbonded at once. Wiring is possible, greatly reducing the amount of work involved.
また、PC鋼より線2……が複数であつてもこ
れらを一列に配列しているので、径の上では1本
の場合と同等に取り扱うことができ、二方向交差
させても平らな面で重ねる限り位置ずれが少な
く、成の低い扁平大梁やスラブにプレストレス導
入を計る場合にも、平らな二面を上下に面させて
配することにより中間部で下方へと十分に弯曲さ
せることができ、十分な扁心距離を確保できて、
所要の吊上げ効果を的確に得ることができ、換言
すれば、大梁及びスラブの厚さを低減でき、建物
の高さを低くできて、空間の有効利用を図ること
ができ、しかも、施工を容易にでき、工期を短縮
でき、躯体コストを低減できる。 In addition, even if there are multiple PC steel stranded wires 2..., they are arranged in a line, so they can be treated as if they were one wire in terms of diameter, and even if they are crossed in two directions, they will not cross each other on a flat surface. As long as they are overlapped, there will be little misalignment, and even when introducing prestress into low-profile flat girders or slabs, by arranging the two flat surfaces facing up and down, it is possible to create a sufficient downward curve in the middle part. is possible, and a sufficient eccentric distance can be secured.
It is possible to accurately obtain the required lifting effect, in other words, it is possible to reduce the thickness of girders and slabs, the height of the building can be lowered, and space can be used effectively, and construction is easy. This can shorten the construction period and reduce the construction cost.
更に、PC鋼より線2……を一列に配列してい
るので、これらの作用を均一にでき、効率よくプ
レストレス導入ができ、巻き取り、取り扱いを容
易にできる。 Furthermore, since the PC steel strands 2 are arranged in a line, these effects can be made uniform, prestress can be efficiently introduced, and winding and handling can be facilitated.
図面は、本考案の実施例で、第1図は、斜視
図、第2図は、断面図である。
1……フラツトシース、2……PC鋼より線、
3……防錆剤。
The drawings show an embodiment of the present invention, with FIG. 1 being a perspective view and FIG. 2 being a sectional view. 1...Flat sheath, 2...PC steel stranded wire,
3... Rust preventive agent.
Claims (1)
一列に配列し、これらのPC鋼より線2……に防
錆剤を塗布して、これら全体を1つのフラツトシ
ース1で包被したことを特徴とするプレストレス
トコンクリート用アンボンド・フラケツトケーブ
ル。 A plurality of PC steel stranded wires 2... are arranged in a line adjacent to each other, a rust preventive agent is applied to these PC steel stranded wires 2, and all of them are covered with one flat sheath 1. Features: Unbonded and flatketed cable for prestressed concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9271683U JPS59196617U (en) | 1983-06-15 | 1983-06-15 | Unbonded flat cable for prestressed concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9271683U JPS59196617U (en) | 1983-06-15 | 1983-06-15 | Unbonded flat cable for prestressed concrete |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS59196617U JPS59196617U (en) | 1984-12-27 |
JPH0326175Y2 true JPH0326175Y2 (en) | 1991-06-06 |
Family
ID=30223064
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9271683U Granted JPS59196617U (en) | 1983-06-15 | 1983-06-15 | Unbonded flat cable for prestressed concrete |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS59196617U (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5239246A (en) * | 1975-09-25 | 1977-03-26 | Mitsubishi Heavy Ind Ltd | Device of carrying loads for use in fork lift |
-
1983
- 1983-06-15 JP JP9271683U patent/JPS59196617U/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5239246A (en) * | 1975-09-25 | 1977-03-26 | Mitsubishi Heavy Ind Ltd | Device of carrying loads for use in fork lift |
Also Published As
Publication number | Publication date |
---|---|
JPS59196617U (en) | 1984-12-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH02217551A (en) | Reinforced concrete structure | |
JPH0326175Y2 (en) | ||
KR101957207B1 (en) | Apparatus for prestressing a PSC girder and method of making a PSC girder using the same | |
JPS6363698B2 (en) | ||
CN209817123U (en) | Anchoring structure of pre-tensioning method prefabricated superposed beam steel strand at beam column node | |
CN209779955U (en) | Cast-in-place reinforced concrete shear wall | |
JPH0532542B2 (en) | ||
JPH0118817B2 (en) | ||
JPS621311Y2 (en) | ||
JPS6346573Y2 (en) | ||
JPS59134261A (en) | Floor structure | |
JPH0245298Y2 (en) | ||
JPS61151371A (en) | Reinforcement of existing pillar | |
JPH01158146A (en) | Method of torus-reinforced thin precast floor board driving formwork construction | |
JP2612425B2 (en) | Fixing method of unbonded PC steel strand | |
JP2764334B2 (en) | Lift slab construction method | |
JPS605949A (en) | Floor structure of construction | |
JPS6335776B2 (en) | ||
DE540360C (en) | Reinforced ceiling made of panels | |
JPS60253649A (en) | Attachement structure of shearing reinforcing wire | |
CN115652794A (en) | Steel bundle arrangement structure suitable for cast-in-place box girder branch pier position and method thereof | |
JPH01118521U (en) | ||
JPH0259250B2 (en) | ||
JPH078676Y2 (en) | Building floor structure | |
JPS605954A (en) | Beam structure of construction |