JPH03256744A - Integrated printing production control system - Google Patents

Integrated printing production control system

Info

Publication number
JPH03256744A
JPH03256744A JP2056876A JP5687690A JPH03256744A JP H03256744 A JPH03256744 A JP H03256744A JP 2056876 A JP2056876 A JP 2056876A JP 5687690 A JP5687690 A JP 5687690A JP H03256744 A JPH03256744 A JP H03256744A
Authority
JP
Japan
Prior art keywords
department
production
host computer
management
computer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2056876A
Other languages
Japanese (ja)
Other versions
JP2941338B2 (en
Inventor
Shinichi Hikosaka
彦坂 眞一
Yoshiji Morioke
森桶 義嗣
Takuo Hida
飛田 拓郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dai Nippon Printing Co Ltd
Original Assignee
Dai Nippon Printing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dai Nippon Printing Co Ltd filed Critical Dai Nippon Printing Co Ltd
Priority to JP5687690A priority Critical patent/JP2941338B2/en
Publication of JPH03256744A publication Critical patent/JPH03256744A/en
Application granted granted Critical
Publication of JP2941338B2 publication Critical patent/JP2941338B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Small-Scale Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Inking, Control Or Cleaning Of Printing Machines (AREA)

Abstract

PURPOSE:To perform process control from receiving order to shipment integrally by a method wherein respective department computers are connected to one another by a local area network centering a process control part, and respective computers share a data in a common use memory in the process control part. CONSTITUTION:Since a host computer 10 is installed at a head office and a subhost computer 20 is installed at a printing works, both are connected by a communication circuit. Besides, computers installed at a production control department 21, a production planning department 22, a material supply department 23, an outside order department 24, a physical distribution department 25, a production department 26, and a analytical department 27 are connected to the subhost computer 20. Furthermore, those respective departments 21-27 are so connected as to construct a local net work so that a memory in the subhost computer 20 can be commonly used. The data in the common use memory can be utilized by accessing from any computer among the departments 21-27, and can be accessed also by the host computer 10.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は印刷統合生産管理システム、特に種々の部門に
おかれたコンピュータをローカルエリアネットワークを
用いて接続することにより、受注から出荷までを統合管
理することのできる印刷統合生産管理システムに関する
[Detailed Description of the Invention] [Industrial Application Field] The present invention is an integrated printing production management system, and in particular, a printing integrated production management system that integrates everything from order receipt to shipping by connecting computers located in various departments using a local area network. This invention relates to a printing integrated production management system that can be managed.

〔従来の技術〕[Conventional technology]

一般に、印刷を業とする企業体は、営業部門、生産計画
部門、資材調達部門、物流部門、生産部門、など複数の
部門を構成し、効率的な業務形態を採って印刷業務を行
っている。これらの各部門間の情報伝達は、伝票の受は
渡しや、電話による照会によって行っているのが実情で
ある。
In general, corporate entities engaged in printing consist of multiple departments, such as a sales department, production planning department, material procurement department, logistics department, and production department, and carry out printing operations using an efficient business structure. . In reality, information is communicated between these departments by handing over invoices or making telephone inquiries.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかしながら、伝票や電話を用いた各部門間における情
報伝達は、非常に効率が悪いという問題がある。特に、
印刷物が多品種化、小ロツト化してくると、伝票や電話
を用いた情報伝達は極めて煩雑な作業となる。更に、原
価計算、会計処理などを行うホストコンピュータを備え
た財務管理部門と、実際の生産に関する工程管理を行う
部門との間の情報伝達も伝票に頼っているため、集計作
業に多くの人手と時間を費やすという問題かある。
However, there is a problem in that information transmission between departments using slips and telephones is extremely inefficient. especially,
As printed matter becomes more diverse and produced in smaller lots, communicating information using slips and telephone calls becomes extremely complicated. Furthermore, information transmission between the financial management department, which is equipped with a host computer that performs cost calculations and accounting processing, and the department that performs process control for actual production also relies on slips, which requires a large amount of manpower to complete tabulation work. There is a problem with wasting time.

また、受注から出荷までの全体の工程の流れを伝票で管
理することは非常に困難である。
Furthermore, it is extremely difficult to manage the entire process flow from order receipt to shipment using slips.

そこで本発明は、各部門間の情報伝達を容易にするとと
もに、受注から出荷までの工程管理を統合して行うこと
のできる印刷統合生産管理システムを提供することを目
的とする。
SUMMARY OF THE INVENTION Therefore, an object of the present invention is to provide an integrated printing production management system that facilitates information transmission between departments and can integrate process management from order receipt to shipping.

〔課題を解決するための手段〕[Means to solve the problem]

(1)  本願第1の発明は、印刷統合生産管理システ
ムにおいて、 受注した印刷物に関する仕様を作成する生産管理部門と
、 この仕様に基づいて生産計画を作成し、報告された生産
実績に基づいてこの生産計画を修正する生産計画部門と
、 生産計画に基づいて必要な資材を調達する資材調達部門
と、 生産計画に基づいて外注処理を行う外注部門と、資材調
達部門によって調達された資材の入庫を管理する物流部
門と、 物流部門の管理下で入庫された資材を用い、生産計画に
基づいた生産を行い、生産実績を報告する生産部門と、 生産実績に基づいて、生産部門の機械の稼働状況を分析
し、この分析結果を報告する分析部門と、の各部門に、
それぞれ他の部門に伝達すべき情報を取り扱うためのコ
ンピュータを設け、これらの各コンピュータから共通し
てアクセスできる共用メモリをもった工程管理部を用い
、これらの各コンピュータをローカルエリアネットワー
クによって相互接続するようにしたものである。
(1) The first invention of the present application is a printing integrated production management system that includes a production management department that creates specifications regarding printed matter ordered, and a production management department that creates a production plan based on the specifications and plans based on reported production results. A production planning department that corrects production plans, a material procurement department that procures necessary materials based on the production plan, an outsourcing department that performs outsourcing processing based on the production plan, and a material procurement department that manages the receipt of materials procured by the material procurement department. A logistics department that manages the logistics department, a production department that carries out production based on production plans using materials received under the management of the logistics department and reports production results, and a production department that reports the operating status of the machines in the production department based on the production results. to the analysis department that analyzes and reports the results of this analysis, and to each department.
Each department has a computer for handling information to be transmitted to other departments, a process control department with a shared memory that can be commonly accessed from each of these computers is used, and these computers are interconnected by a local area network. This is how it was done.

(2)  本願第2の発明は、上述の本願第1の発明に
係る印刷統合生産管理システムにおいて、印刷物に関す
る受注を行う営業部門に設けられ、この受注に関する情
報を入力する営業部門用端末と、 この営業部門用端末から与えられる受注に関する情報を
入力し、この受注に関する財務管理、資材管理、および
製品管理を行う機能をもったホストコンピュータと、 を更に設け、ホストコンピュータを工程管理部に接続し
、この工程管理部をホストコンピュータの管理下で動作
させるようにしたものである。
(2) The second invention of the present application provides, in the printing integrated production management system according to the first invention of the present application, a terminal for the sales department that is provided in a sales department that receives orders for printed matter and inputs information regarding the orders; A host computer is also provided, which has the function of inputting information regarding orders given from this sales department terminal and performing financial management, materials management, and product management regarding these orders, and the host computer is connected to the process control department. , this process control section is operated under the control of a host computer.

〔作 用〕[For production]

本願第1の発明の印刷統合生産管理システムによれば、
各部門のコンピュータが工程管理部を中心としてローカ
ルエリアネットワークによって相互接続され、各コンピ
ュータは工程管理部内の共用メモリ内のデータを共用す
ることができる。このため、従来のように、伝票や電話
によって各部門間の情報伝達を行う必要はなくなり、受
注から出荷までの統合管理が可能になる。また、本願第
2の発明では、ホストコンピュータと工程管理部とを接
続するようにしたため、生産管理に関する情報と、財務
管理に関する情報とか、コンピュータ間で受は渡してき
るようになり、従来行っていた集計作業などの手間を省
くことがてきる。
According to the printing integrated production management system of the first invention of the present application,
Computers in each department are interconnected by a local area network centered around the process control department, and each computer can share data in a shared memory within the process control department. Therefore, there is no need to communicate information between departments using slips or telephone calls as in the past, and integrated management from order receipt to shipment becomes possible. In addition, in the second invention of the present application, since the host computer and the process control department are connected, information related to production control and information related to financial management can be passed between computers, which was not done previously. This can save you the trouble of tabulating data.

〔実施例〕〔Example〕

以下、本発明を図示する実施例に基づいて説明する。第
1図は本発明の一実施例に係る印刷統合生産管理システ
ムの構成を示すブロック図である。
The present invention will be described below based on illustrated embodiments. FIG. 1 is a block diagram showing the configuration of an integrated printing production management system according to an embodiment of the present invention.

このシステムの中枢となる部分は、ホストコンピュータ
10とこれに接続されたサブホストコンピュータ20で
ある。この実施例では、ホストコンピュータ10は本社
に設置され、サブホストコンピュータ20は印刷工場に
設置されているため、両者間は通信回線によって接続さ
れている。ホストコンピュータ10には、また、営業部
門11の端末が接続されている。営業部門が本社外にあ
る場合には、この接続も通信回線によって行われる。
The central parts of this system are a host computer 10 and a sub-host computer 20 connected thereto. In this embodiment, the host computer 10 is installed at the head office, and the sub-host computer 20 is installed at the printing factory, so that the two are connected by a communication line. A terminal of a sales department 11 is also connected to the host computer 10 . If the sales department is located outside the headquarters, this connection is also made via communication lines.

一方、サブホストコンピュータ20には、生産管理部門
21、生産計画部門22、資材調達部門23、外注部門
24、物流部門25、生産部門26、分析部門27、の
各部門に設けられたコンピュータが接続されている。し
かも、これらの各部門21〜27は、サブホストコンピ
ュータ20内のメモリを共用できるように、ローカルエ
リアネットワークを構成するように接続されている。
On the other hand, the sub-host computer 20 is connected to computers installed in each department: a production management department 21, a production planning department 22, a material procurement department 23, an outsourcing department 24, a logistics department 25, a production department 26, and an analysis department 27. ing. Furthermore, each of these departments 21 to 27 is connected to form a local area network so that the memory within the sub-host computer 20 can be shared.

共用メモリ内のデータは、部門21〜27のうちのいず
れのコンピュータからもアクセスして利用することがで
きるし、ホストコンピュータ10によってアクセスする
こともできる。サブホストコンピュータ20は、各部門
で行われる工程を統合管理する工程管理部として機能す
ることになる。
The data in the shared memory can be accessed and used by any computer in the departments 21-27, and can also be accessed by the host computer 10. The sub-host computer 20 will function as a process management unit that integrally manages processes performed in each department.

たとえば、共用メモリ内のデータのうち、ある特定のデ
ータについては、特定の部門からの読出しのみを可能に
したり、ある特定のデータについては、特定の部門によ
ってのみ書き替え可能にしたりする制御が、サブホスト
コンピュータ20によって行われる。
For example, certain data in shared memory can be controlled to only be readable by a specific department, or to be rewritten only by a specific department. This is performed by the sub-host computer 20.

ここで、各部門の業務内容を簡単に説明しておく。営業
部門11は、顧客から印刷物の注文を受け、この受注を
ホストコンピュータ10に報告するとともに、受注した
原稿を生産管理部門21に入稿する。生産管理部門21
は、この原稿に基づいて印刷作業の仕様を作成する。生
産計画部門22は、この仕様に基づいて生産計画を立案
する。
Here, I will briefly explain the work content of each department. The sales department 11 receives an order for printed matter from a customer, reports this order to the host computer 10, and submits the ordered manuscript to the production control department 21. Production control department 21
creates specifications for printing work based on this manuscript. The production planning department 22 formulates a production plan based on this specification.

資材調達部門23は、生産計画に基づいて必要な資材の
発注・調達を行う。外注部門24は、生産計画に基づい
て外注処理をする。物流部門25は、資材の入庫管理を
行う。生産部門26は、生産計画に基づいて実際の生産
を行う。分析部門27は、生産部門26の機械の稼働状
況を分析する。また、ホストコンピュータ10では、原
価計算や会計処理といった財務管理や、資材管理、製品
管理が行われる。
The material procurement department 23 orders and procures necessary materials based on the production plan. The outsourcing department 24 performs outsourcing processing based on the production plan. The logistics department 25 manages the warehousing of materials. The production department 26 performs actual production based on the production plan. The analysis department 27 analyzes the operating status of the machines in the production department 26. Further, the host computer 10 performs financial management such as cost calculation and accounting processing, material management, and product management.

続いて、第2図に示す作業工程の流れ図に基づいて、受
注から出荷に至るまでの一品目についての工程を説明す
る。まず、ステップS1において受注が行われる。すな
わち、営業部門11が顧客から印刷物の依頼を受けるこ
とになる。営業部門11は、この受注内容を端末に入力
する。営業部門11の端末は、ホストコンピュータ10
に接続されているため、受注情報は営業部門11からホ
ストコンピュータ10へと転送され、更に、サブホスト
コンピュータ20内の共用メモリに保存される。一方、
営業部門11は、顧客から受は取った原稿を、生産管理
部門21に入稿する。一般に、この原稿は文字原稿たけ
に限らず、写真の原稿や図柄の原稿が含まれている。し
たがって、この実施例では、原稿は郵送あるいは手渡し
の形で生産管理部門21に入稿している。なお、営業部
門11に、原稿をデジタルデータとして取り込むスキャ
ナ装置などを備え付ければ、原稿をデジタルデータの形
で通信回線を介して入稿する方法も可能である。
Next, based on the flowchart of the work process shown in FIG. 2, the process for one item from receiving an order to shipping will be explained. First, an order is accepted in step S1. That is, the sales department 11 receives a request for printed matter from a customer. The sales department 11 inputs the details of the received order into a terminal. The terminal of the sales department 11 is the host computer 10
Since the sales department 11 is connected to the host computer 10, order information is transferred from the sales department 11 to the host computer 10, and is further stored in a shared memory within the sub-host computer 20. on the other hand,
The sales department 11 submits the manuscript received from the customer to the production management department 21. In general, this manuscript is not limited to only text manuscripts, but also includes photographic manuscripts and graphic manuscripts. Therefore, in this embodiment, the manuscript is submitted to the production control department 21 by mail or hand delivery. Note that if the sales department 11 is equipped with a scanner device or the like that captures manuscripts as digital data, it is also possible to submit manuscripts in the form of digital data via a communication line.

次に、ステップS2において、仕様作成が行われる。す
なわち、生産管理部門21が入稿された原稿に基づいて
、印刷対象となる品目について、版サイズ、色数、印刷
枚数、納期などの詳細な仕様を作成するのである。この
仕様は、共用メモリに書き込まれる。
Next, in step S2, specifications are created. That is, the production control department 21 creates detailed specifications for the item to be printed, such as plate size, number of colors, number of sheets to be printed, and delivery date, based on the received manuscript. This specification is written to shared memory.

続いて、ステップS3において、生産計画の立案が行わ
れる。これは、共用メモリ内の仕様に基づいて、生産計
画部門22において立案される。
Subsequently, in step S3, a production plan is drawn up. This is planned in the production planning department 22 based on the specifications in the shared memory.

この生産計画は、工程間の予定と、1工程内で用いる生
産機械の予定と、を含むものである。また、自社だけで
は処理しきれないと判断した場合には、外注の予定が組
み込まれる。こうして立案された生産計画も、共用メモ
リに書き込まれる。
This production plan includes schedules between processes and schedules for production machines used within one process. Additionally, if it is determined that the process cannot be handled by the company alone, outsourcing is planned. The production plan created in this way is also written into the shared memory.

次に、ステップS4において、資材調達が行われる。す
なわち、資材調達部門23は、共用メモリ内の生産計画
および資材データに基づいて、この品目の印刷に必要な
資材(たとえば、用紙やインキ)を認識し、この必要な
資材に関する情報を調達指示として取込む。そして、こ
の必要な資材を外部に対して発注する。この発注作業に
より、どの資材がいつ入荷し、価格はいくらであるかと
いう資材情報を得ることができたら、この資材情報を共
用メモリに保存する。
Next, in step S4, materials are procured. That is, the material procurement department 23 recognizes the materials (for example, paper and ink) necessary for printing this item based on the production plan and material data in the shared memory, and provides information regarding the necessary materials as procurement instructions. Take in. Then, the necessary materials are ordered from outside. Through this ordering process, if material information such as which materials will arrive when and what their prices are can be obtained, this material information is stored in the shared memory.

ステップS5では、外注処理が行われる。すなわち、共
用メモリ内の生産計画の中で外注予定として組み込まれ
ている作業内容を、外注部門が外注指示として取込む。
In step S5, outsourcing processing is performed. That is, the outsourcing department takes in the work content that is included as an outsourcing schedule in the production plan in the shared memory as an outsourcing instruction.

そして、この外注指示に基づいて、他社に外注の依頼を
行う。また、外注先から納品があった場合には、これを
外注実績としてサブホストコンピュータ20に報告する
。この外注実績も共用メモリ内に保存される。
Then, based on this outsourcing instruction, outsourcing is requested to another company. Furthermore, when there is a delivery from a subcontractor, this is reported to the sub-host computer 20 as an outsourcing record. This outsourcing performance is also stored in the shared memory.

続いて、ステップS6における生産が行われる。Subsequently, production in step S6 is performed.

すなわち、生産部門26において、実際の生産作業が開
始することになる。ただし、生産作業に必要な用紙やイ
ンキなどの資材が入庫していなければ、作業を開始する
ことはできないので、共用メモリ内の資材データを確認
し、作業を開始することができるか否かを判断する。物
流部門25は、サブホストコンピュータ20からの照会
を受け、倉庫に資材が搬入されたり、搬出されたりした
事実を報告する。これにより、共用メモリ内の資材デー
タが更新される。なお、この資材データは、ホストコン
ピュータ10からもアクセスされ、資材管理が行われる
。生産部門26は、必要な資材の入庫を確認したら、生
産作業を開始する。具体的には、製版、刷版、印刷、加
工、検査などの処理を生産計画に基づいて各装置を稼働
して行うことになる。こうして、装置の稼働によって得
られた生産実績(たとえば、印刷枚数)は、逐次サブホ
ストコンピュータ20に与えられ、共用メモリに保存さ
れる。なお、各生産機械(たとえば、印刷機)に、生産
実績を検出する検出装置を設けておけば、サブホストコ
ンピュータ20に対する生産実績の報告が自動的に行わ
れるようにすることがてきる。このような検出装置を用
いない場合には、生産部門26に設けられたコンピュー
タに対して、現場のオペレータが逐次生産実績を入力す
るようにすればよい。
That is, actual production work begins in the production department 26. However, if the materials necessary for production work, such as paper and ink, are not in stock, work cannot be started, so check the material data in the shared memory and check whether or not work can be started. to decide. The logistics department 25 receives an inquiry from the sub-host computer 20 and reports the fact that materials have been brought into and taken out of the warehouse. This updates the material data in the shared memory. Note that this material data is also accessed from the host computer 10 to perform material management. After confirming that the necessary materials have been received, the production department 26 starts production work. Specifically, processes such as plate making, printing plates, printing, processing, and inspection are performed by operating each device based on the production plan. In this way, the production results (for example, the number of printed sheets) obtained through the operation of the apparatus are sequentially given to the sub-host computer 20 and stored in the shared memory. Note that if each production machine (for example, a printing press) is provided with a detection device for detecting production results, the production results can be automatically reported to the sub-host computer 20. If such a detection device is not used, an on-site operator may sequentially input production results into a computer provided in the production department 26.

また、この生産実績は、生産計画部門22にフィードバ
ックされる。生産計画部門22は、このフィードバック
された生産実績に基づき、納期遅れなどが生じることが
ないか否かをチエツクし、必要に応じて、新たな生産計
画を作成して、サブホストコンピュータ20に与える。
Further, this production result is fed back to the production planning department 22. The production planning department 22 checks whether there will be a delay in delivery based on the fed back production results, creates a new production plan as necessary, and provides it to the sub-host computer 20.

この場合、生産部門26は、新たな生産計画に基づいて
生産作業を行うことになる。一方、ホストコンピュータ
10は、サブホストコンピュータ20に与えられた生産
実績を、進捗情報として入力し、これを営業部門11に
知らしめる。営業部門11は、この進捗情報を、必要に
応して顧客に報告することができる。なお、生産部門2
6から報告される生産実績としては、製品不良に関する
情報を含ませておくことができる。たとえば、ある印刷
物の巻取ロールの所定位置に不良箇所があるというよう
な情報を、不良箇所の位置を特定して報告するようにし
ておけば、サブホストコンピュータ20あるいはホスト
コンピュータ10は、各製品についての品質情報を得る
ことができ、製品管理に役立たせることができる。
In this case, the production department 26 will perform production work based on the new production plan. On the other hand, the host computer 10 inputs the production results given to the sub-host computer 20 as progress information, and notifies the sales department 11 of this. The sales department 11 can report this progress information to customers as necessary. In addition, production department 2
The production results reported from 6 can include information regarding product defects. For example, if information such as that there is a defective part at a predetermined position on the take-up roll of a certain printed matter is reported by identifying the position of the defective part, the sub-host computer 20 or host computer 10 can report information about each product. quality information, which can be useful for product management.

こうして、生産部門26における生産作業が完了すると
、製品が出来上がることになる。そこで、ステップS7
において、製品管理が行われる。すなわち、製品に関す
る情報がサブホストコンピュータ20からホストコンピ
ュータ10に与えられる。半製品の場合には、仕掛りに
関する情報が代わりに与えられる。ホストコンピュータ
10では、資材に関するデータや、外注に関するデータ
を用いて、この製品についての原価計算を行うことがで
きる。また、この製品を出荷販売し、会計処理を行うこ
とができる。
In this way, when the production work in the production department 26 is completed, the product is completed. Therefore, step S7
Product management is carried out at That is, information regarding the product is provided from the sub-host computer 20 to the host computer 10. In the case of semi-finished products, information regarding the work in progress is given instead. The host computer 10 can calculate the cost of this product using data regarding materials and data regarding outsourcing. In addition, this product can be shipped and sold, and accounting processing can be performed.

また、ステップS8では、分析部門27における分析が
行われる。これは、生産部門26から与えられる生産実
績に基づいて、生産部門26の機械の稼働状況を分析す
る作業である。たとえば、ある機械については、準備時
間が平均どれ程必要であるかというような分析データを
得ることもできるであろうし、ある機械は連続稼働時間
が所定時間を越えたのて、給油などのメンテナンスのた
めに所定時間停止させる必要があるというような分析デ
ータを得ることもできるであろう。要するにここでは、
機械の生産実績に基づいて、その機械の稼働状況を分析
することができれば、どのような分析を行ってもよい。
Further, in step S8, analysis in the analysis department 27 is performed. This is a task of analyzing the operating status of the machines in the production department 26 based on the production results given from the production department 26. For example, it may be possible to obtain analytical data such as how much preparation time is required on average for a certain machine, or if a certain machine has been in continuous operation for more than a predetermined period of time, it may require maintenance such as refueling. It would also be possible to obtain analytical data such as the need to stop the system for a predetermined period of time. In short, here,
Any kind of analysis may be performed as long as the operating status of the machine can be analyzed based on the machine's production results.

このような分析結果は、サブホストコンピュータ20に
報告され、共用メモリ内に保存される。したがって、生
産計画部門22は、このような分析結果を生産計画の立
案に反映させることができる。
Such analysis results are reported to the sub-host computer 20 and stored in the shared memory. Therefore, the production planning department 22 can reflect such analysis results in the formulation of a production plan.

以上、本発明を図示する一実施例に基づいて説明したが
、本発明はこの実施例のシステムに限定されるものでは
なく、種々の態様で実施可能である。たとえば、生産管
理部門21をポストコンピュータ10に接続するような
構成にしてもよい。
Although the present invention has been described above based on the illustrated embodiment, the present invention is not limited to the system of this embodiment, and can be implemented in various ways. For example, the configuration may be such that the production management department 21 is connected to the post computer 10.

また、ホストコンピュータ10をローカルエリアネット
ワーク内に配置するような構成にしてもよく、ホストコ
ンピュータ10とサブホストコンピュータ2oとに分け
ずに、ホストコンピュータ1台だけで両方の機能を行わ
せるような構成にしてもかまわない。また、第2図に示
す工程流れ図は、第1図のシステムによる作業の一例を
示すものであり、必ずしも、この順に作業を行う必要は
ない。
Alternatively, the host computer 10 may be arranged in a local area network, or the host computer 10 and the sub-host computer 2o may not be separated, but only one host computer can perform both functions. It doesn't matter. Further, the process flowchart shown in FIG. 2 shows an example of the work performed by the system shown in FIG. 1, and the work does not necessarily have to be performed in this order.

要するに、本発明のシステムの特徴は、複数の部門のコ
ンピュータが、工程管理部内の共用メモリを共通してア
クセスできるようにした点にある。
In short, the system of the present invention is characterized in that computers in a plurality of departments can commonly access the shared memory within the process control department.

これにより、他の部門に関する情報を容易に得ることが
可能になる。たとえば、生産部門において、現在どの印
刷機、どの製本機、あるいはどの丁合機が稼働中である
がというリアルタイムの情報を生産実績として逐次共用
メモリに入れておくようにすれば、他の部門のコンピュ
ータからもこの情報を随時アクセスすることができるの
である。また、共用メモリ内のデータに基づいて、各部
門におけるオペレータに、作業指示を与えることもてき
る。
This makes it possible to easily obtain information regarding other departments. For example, in a production department, if real-time information such as which printing presses, binding machines, or collating machines are currently in operation is stored in the shared memory as production results, it is possible for other departments to This information can also be accessed from a computer at any time. It is also possible to give work instructions to operators in each department based on the data in the shared memory.

〔発明の効果〕〔Effect of the invention〕

以上のとおり、本発明の印刷統合生産管理システムによ
れば、各部門のコンピュータが工程管理部を中心として
ローカルエリアネットワークによって相互接続され、工
程管理部内の共用メモリ内のデータを共用することがで
きるようになるため、受注から出荷までの統合管理が可
能になる。
As described above, according to the printing integrated production management system of the present invention, computers in each department are interconnected by a local area network centered on the process control department, and data in the shared memory within the process control department can be shared. This enables integrated management from order receipt to shipment.

【図面の簡単な説明】[Brief explanation of drawings]

m1図は本発明の一実施例に係る印刷統合生産V理シス
テムの基本構成を示すブロック図、第2図は第1図の装
置による作業工程を示す流れ図である。 尭1図 綿2図 特開平3−256744 (6)
FIG. m1 is a block diagram showing the basic configuration of an integrated printing production V management system according to an embodiment of the present invention, and FIG. 2 is a flowchart showing the work process performed by the apparatus shown in FIG. 1. Japanese Patent Publication No. 3-256744 (6)

Claims (2)

【特許請求の範囲】[Claims] (1)受注した印刷物に関する仕様を作成する生産管理
部門と、 前記仕様に基づいて生産計画を作成し、報告された生産
実績に基づいてこの生産計画を修正する生産計画部門と
、 前記生産計画に基づいて必要な資材を調達する資材調達
部門と、 前記生産計画に基づいて外注処理を行う外注部門と、 前記資材調達部門によって調達された資材の入庫を管理
する物流部門と、 前記物流部門の管理下で入庫された資材を用い、前記生
産計画に基づいて生産を行い、生産実績を報告する生産
部門と、 前記生産実績に基づいて、生産部門の機械の稼働状況を
分析し、この分析結果を報告する分析部門と、 の各部門に、それぞれ他の部門に伝達すべき情報を取り
扱うためのコンピュータを設け、これらの各コンピュー
タから共通してアクセスできる共用メモリをもった工程
管理部を用い、これらの各コンピュータをローカルエリ
アネットワークによって相互接続したことを特徴とする
印刷統合生産管理システム。
(1) A production control department that creates specifications regarding the ordered printed matter; a production planning department that creates a production plan based on the specifications and corrects this production plan based on reported production results; a material procurement department that procures necessary materials based on the production plan; an outsourcing department that performs outsourcing processing based on the production plan; a logistics department that manages the receipt of materials procured by the material procurement department; and a management of the logistics department. A production department that carries out production based on the above-mentioned production plan using the materials received under the above mentioned production plan and reports the production results, and a production department that analyzes the operating status of the machines in the production department based on the above-mentioned production results and reports the results of this analysis. The reporting analysis department and each department are equipped with computers to handle information to be transmitted to other departments, and a process control department with shared memory that can be commonly accessed from these computers is used to An integrated printing production management system characterized by interconnecting each computer by a local area network.
(2)請求項1に記載の印刷統合生産管理システムにお
いて、 印刷物に関する受注を行う営業部門に設けられ、この受
注に関する情報を入力する営業部門用端末と、 前記営業部門用端末から与えられる受注に関する情報を
入力し、この受注に関する財務管理、資材管理、および
製品管理を行う機能をもったホストコンピュータと、 を更に設け、前記ホストコンピュータを工程管理部に接
続し、この工程管理部を前記ホストコンピュータの管理
下で動作させるようにしたことを特徴とする印刷統合生
産管理システム。
(2) The printing integrated production management system according to claim 1, further comprising: a sales department terminal provided in a sales department that receives orders for printed matter and for inputting information regarding the orders; and a sales department terminal for inputting information regarding the orders received from the sales department terminal. A host computer with functions for inputting information and performing financial management, materials management, and product management regarding this order is further provided, and the host computer is connected to a process control department, and the process control department is connected to the host computer. An integrated printing production management system characterized by operating under the control of
JP5687690A 1990-03-07 1990-03-07 Integrated printing production management system Expired - Fee Related JP2941338B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5687690A JP2941338B2 (en) 1990-03-07 1990-03-07 Integrated printing production management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5687690A JP2941338B2 (en) 1990-03-07 1990-03-07 Integrated printing production management system

Publications (2)

Publication Number Publication Date
JPH03256744A true JPH03256744A (en) 1991-11-15
JP2941338B2 JP2941338B2 (en) 1999-08-25

Family

ID=13039624

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5687690A Expired - Fee Related JP2941338B2 (en) 1990-03-07 1990-03-07 Integrated printing production management system

Country Status (1)

Country Link
JP (1) JP2941338B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003112409A (en) * 2001-10-05 2003-04-15 Nissha Printing Co Ltd Printing material determination program, printing material determination method and printing material determination system employing printing material determination method
US10800181B2 (en) 2018-03-23 2020-10-13 Fuji Xerox Co., Ltd. Production system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003112409A (en) * 2001-10-05 2003-04-15 Nissha Printing Co Ltd Printing material determination program, printing material determination method and printing material determination system employing printing material determination method
US10800181B2 (en) 2018-03-23 2020-10-13 Fuji Xerox Co., Ltd. Production system
US10946668B2 (en) 2018-03-23 2021-03-16 Fuji Xerox Co., Ltd. Production system

Also Published As

Publication number Publication date
JP2941338B2 (en) 1999-08-25

Similar Documents

Publication Publication Date Title
CN1326081C (en) A ccount opening facilitation system, method and computer program product
CN101751030A (en) Manufacturing collaboration hub data exchange interface
US20050080721A1 (en) Automated financial transaction due diligence systems and methods
CN109034622A (en) A kind of data processing method and system
CN115471154A (en) Intelligent warehouse management system based on spring-closed micro-service framework
US20030154143A1 (en) Collaborative system and method for monitoring imported and exported goods
CN1979542A (en) Factory mfg. executing system combined standard operation programe
JP2941338B2 (en) Integrated printing production management system
CN116205256A (en) Transmission universal bar code label printing management system and operation method
RU2308083C2 (en) Method for automated recording and presentation of information about presence and movement of goods in place of storage and selection of goods for realization and electronic system for realization of the method
US20040061891A1 (en) Enterprise production management of a print shop
WO2022057295A1 (en) Pump performance data processing management system and management method
JPH0245871A (en) Delivery checking system
EP1193630A1 (en) Agile information system and management method
JPH058157A (en) Manufacturing prodess management system
KR20050111458A (en) Print ordering system using PD file automatic conversion and its method
CN101421699B (en) System and method of managing a ticket order
JP2003114965A (en) Electronic book filing processing system
TW518496B (en) Management method and system of delivering goods
CN112381556A (en) Digital quality tracking single scanning system and method
JP2002029607A (en) Physical distribution system
Hoffmann-Walbeck et al. Scope of Workflows
CN113780732A (en) Ordering management platform and ordering method based on Internet of things and data analysis
CN116128439A (en) Method, device, equipment and medium for tracking quality information of veneer products
KR20230055187A (en) Method for providing package production service

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080618

Year of fee payment: 9