JPH03147920A - Horizontal burying method of drain material and burying device thereof - Google Patents

Horizontal burying method of drain material and burying device thereof

Info

Publication number
JPH03147920A
JPH03147920A JP28756789A JP28756789A JPH03147920A JP H03147920 A JPH03147920 A JP H03147920A JP 28756789 A JP28756789 A JP 28756789A JP 28756789 A JP28756789 A JP 28756789A JP H03147920 A JPH03147920 A JP H03147920A
Authority
JP
Japan
Prior art keywords
drain material
burying
guide
buried
drain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP28756789A
Other languages
Japanese (ja)
Other versions
JPH0670322B2 (en
Inventor
Yuichi Tani
雄一 谷
Hiroshi Niiya
博 新舎
Masashi Takahashi
正志 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP28756789A priority Critical patent/JPH0670322B2/en
Publication of JPH03147920A publication Critical patent/JPH03147920A/en
Publication of JPH0670322B2 publication Critical patent/JPH0670322B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PURPOSE:To make it possible to improve uniformly a poor subsoil by burying a drain material into the poor subsoil while moving forward a drain material burying guide at the buried starting end of the drain material and, at the same time, raising the drain material while moving forward the guide at the buried last end. CONSTITUTION:On the buried starting end side, a drawing frame 25B on the rear side is pulled out to pull a drain material buried guide 20 up to a poor subsoil 30, the drain material 16 is passed over a guide roll 22 to lead out, and a vacuum pulling hose is connected to the end of the drain material 16. Then, a drawing frame 25A on the front side is pulled out, the guide 20 is penetrated into the subsoil 30, and the drain material 16 is drawn out to bury it into the subsoil 30. After that, an operation ship 11 is advanced, and the drain material 16 is subsequently pulled out to bury. In addition, the advancement of the operation ship 11 is stopped at the position of the buried last end, a blank cap is loaded to the last end of the drain material 16, and the drawing frame 25A is pulled up to turn the guide 20 forward to pull it up to the subsoil 30.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、浚渫による埋立地やヘドロ処理地等の超軟弱
地盤中に、水平方向に高さを違えて複数のドレーン材を
埋設する水平ドレーン材の埋設方法及びその装置に関す
る。
Detailed Description of the Invention (Industrial Application Field) The present invention is a horizontal method for burying a plurality of drain materials at different heights in the horizontal direction in ultra-soft ground such as a dredged landfill or sludge treatment site. The present invention relates to a method for burying drain material and an apparatus therefor.

(従来の技術) 一般にポンプ浚渫船で海底等の水底に堆積している軟弱
な粘性上を浚渫して埋立地へ投入すると、超軟弱地盤が
形成される。このような超軟弱地盤は従来、自然圧密を
持って、次の浚渫土を投入したり、自然圧密によりある
程度の耐力が発現した後、ドレーン材を上下に打ち込み
、その上に砂等のウェイトを載せた強制圧密方法が採ら
れていた。
(Prior Art) Generally, when a pump dredger is used to dredge soft, viscous soil deposited on the bottom of a seabed or the like and then dump the dredged material into a landfill, extremely soft ground is formed. Conventionally, ultra-soft ground like this has undergone natural consolidation and then the next dredged soil is put in, or after natural consolidation has developed a certain degree of bearing capacity, drain materials are driven up and down, and weights such as sand are placed on top. The forced consolidation method described above was used.

このような方法では、自然圧密に長時間を要し、従来の
地盤改良工法の施工が可能な状態になるまでに長時間を
要していた。
With such methods, it takes a long time for natural consolidation, and it takes a long time to reach a state where conventional ground improvement methods can be implemented.

かかる点にかんがみ、軟弱地盤中に水平にドレーン材を
埋設し、該ドレーン材を通して軟弱地盤中の水を吸い出
す地盤改良方法が検討され、第9図に示すようにドレー
ン材1を巻取ったリール2を船上に搭載し、かつ、船底
下にドレーン材1を繰り出すためのドレーン材埋設ガイ
ド3を突出させたドレーン材埋設船4を軟弱地盤5上の
水面上に浮かべ、軟弱地盤5中に、ドレーン材埋設ガイ
ド3から繰り出したドレーン材lの先端を杭6等の固定
部材に固定し、この状態でドレーン材埋設船4を移動さ
せつつドレーン材埋設ガイド3からドレーン材1を繰り
出しつつ水平埋設を行う方法及び装置が開発されている
(特開昭64−10813号公報)。
In view of this point, a ground improvement method was investigated in which a drain material was buried horizontally in the soft ground and the water in the soft ground was sucked out through the drain material, and a reel wound with the drain material 1 was developed as shown in Fig. 9. A drain material burying vessel 4 with a drain material embedding guide 3 protruding from which the drain material 1 is fed out under the bottom of the ship is floated on the water surface above the soft ground 5, and in the soft ground 5, The tip of the drain material l fed out from the drain material burying guide 3 is fixed to a fixing member such as a pile 6, and in this state, the drain material 1 is fed out from the drain material burying guide 3 while moving the drain material burying ship 4 and is buried horizontally. A method and apparatus for doing this have been developed (Japanese Patent Application Laid-Open No. 10813/1983).

(発明が解決しようとする課題) このような従来のドレーン材の水平埋設方法では、埋設
始端部から埋設終端位置まで水平配置にドレーン材が連
続して埋設されるものであるが、第10図に示すように
始端及び終端から築堤7a7bまでの間にドレーン材が
埋設されない部分a。
(Problems to be Solved by the Invention) In such a conventional horizontal burying method of drain material, the drain material is buried continuously in a horizontal arrangement from the burying start end to the burying end position. As shown in Fig. 3, a part a where no drain material is buried between the start and end ends and the embankment 7a7b.

bができ、このため築堤7a、7bに近い部分に改良効
果が出ない部分ができる。このため、耐力にむらが生じ
、その後の覆土等の作業に大きな支障を来すという問題
があった。
b is formed, and as a result, there are areas near the embankments 7a and 7b where no improvement effect is produced. For this reason, there was a problem in that the yield strength was uneven, which greatly hindered subsequent soil-covering operations.

本発明はこのような従来の問題にかんがみ、ドレーン材
の埋設始端及び終端においても、均一な密度にドレーン
材を埋設することができ、地盤改良が全域にわたって均
一に行われるドレーン材の水平埋設方法及びその埋設装
置の提供を目的としたものである。
In view of these conventional problems, the present invention provides a method for horizontally burying drain material, in which drain material can be buried at a uniform density even at the starting and ending ends of the drain material, and ground improvement can be performed uniformly over the entire area. The purpose is to provide buried equipment for the same.

(課題を達成するための手14) 上述の如き従来の問題を解決し、所期の目的を達成する
ための本発明方法の特徴は船底より下方に垂下させたド
レーン材埋設ガイドに沿わせて必要な高さ位置にドレー
ン材を繰出し自在な埋設作業船を使用し、前記ドレーン
材埋設ガイドを軟弱地盤中に挿入させた状態で、該地盤
中を進行させ、その進行に伴ってドレーン材を繰り出す
水平ドレーン材の埋設方法において、前記ドレーン材の
埋設始端部分位置にて前記ドレーン材埋設ガイドを軟弱
地盤上より除々に該#!!盤内に埋設させつつ進行方向
側に移動させ、所定深さまで降下させた状態で作業船と
ともに水平移動させ、埋設終端位置にて前記ドレーン材
埋設ガイドを軟弱地盤表面まで除々に昇降させつつ進行
させることにあり、また本発明装置の特徴は上部にリー
ルに巻き取ったドレーン材を搭載した埋設作業船の略中
央に、該埋設作業船の進行方向側前後に回動自在に上端
部を枢着したドレーン材埋設ガイドを垂下させ、該ドレ
ーン材埋設ガイドの複数高さ位置に、前記リールから引
き出したドレーン材を順次繰り出すドレーン材繰出部を
備え、かつ、前記ドレーン材埋設ガイドを、その先r4
A側を、前方及び後方側に強制回動させるドレーン材埋
設ガイド姿勢制御手段を備えたことにある。
(Measures 14 to Achieve the Problem) The feature of the method of the present invention for solving the above-mentioned conventional problems and achieving the intended purpose is to bury the drain material along the drain material embedding guide suspended below the bottom of the ship. Using a burying work boat that can freely deliver drain material to the required height position, advance through the soft ground with the drain material burying guide inserted into the soft ground, and drain the drain material as it progresses. In the method of burying horizontal drain material, the drain material burying guide is gradually moved from above the soft ground at the starting end position of the drain material. ! While burying it in the board, move it in the advancing direction, lower it to a predetermined depth, and then move it horizontally with the work boat, and at the end of the burying position, gradually raise and lower the drain material burying guide to the soft ground surface and advance. In particular, the feature of the present invention device is that the upper end is pivoted approximately at the center of the burying work vessel, which carries the drain material wound on a reel on the upper part, so as to be freely rotatable back and forth in the direction of movement of the burying work vessel. The drain material embedding guide is made to hang down, and drain material feeding parts are provided at a plurality of height positions of the drain material burying guide for sequentially feeding out the drain material pulled out from the reel, and the drain material burying guide is connected to
The present invention is provided with a drain material embedding guide attitude control means for forcibly rotating the A side forward and backward.

〈伴用) 本発明においてはドレーン材の埋設始端部では、ドレー
ン材埋設船を停止させ、もしくはゆっくり前進させなが
らドレーン材埋設ガイドを埋設作業船の進行方向側に回
動させつつ、その回動長さ分のドレーン材を順次繰出し
、水平埋設しようとする深さまで先fIA側を回動降下
さる。なお、このとき、ドレーン材の先端には予め真空
引きホースを連結しておき、ドレーン材が軟弱地盤表面
より稍下部位置からその先端が繰り出されるようにする
<Accompanying use> In the present invention, at the starting end of drain material burying, the drain material burying guide is rotated in the direction of movement of the drain material burying work vessel while the drain material burying vessel is stopped or slowly advanced. The length of the drain material is paid out one by one, and it is rotated and lowered on the forward fIA side to the desired depth for horizontal burial. At this time, a vacuum hose is connected in advance to the tip of the drain material so that the tip of the drain material is drawn out from a position slightly below the surface of the soft ground.

次いでこの状態で埋設作業船を移動させ、これに応じて
ドレーン材を繰出し、水平埋設する。埋設終端部におい
ては、埋設作業船を停止させ、もしくはゆっくり前進さ
せながらドレーン材埋設ガイドを前方に回動させて軟弱
地盤上まで上昇させ、その回動に伴ってドレーン材を繰
出し、ドレーン材の後端を軟弱地盤の表面稍下部位置ま
で導出させる。
Next, in this state, the burying work boat is moved, and the drain material is paid out accordingly and buried horizontally. At the end of the burial, the drain material burying guide is rotated forward to rise above the soft ground while the burying work vessel is stopped or slowly moved forward, and the drain material is fed out as it rotates. The rear end is led out to a position slightly below the surface of the soft ground.

このような動作を埋設作業船の往動作もしくは往復動作
毎に行い、軟弱地盤全域にドレーン材を埋設する。
This operation is performed every time the burying work vessel makes a forward movement or a reciprocating movement, and the drain material is buried in the entire soft ground area.

また、このようにして始端及び終端でドレーン材端部が
地盤表面近くに導出されることにより埋設されない部分
を残さないでドレーン材の埋設がなされる。
Moreover, in this way, the end portions of the drain material are brought out near the ground surface at the start and end ends, so that the drain material can be buried without leaving any unburied portions.

(実施例) 次に本発明の実施の一例を第1図〜第8図について説明
する。第1図、第2図は本発明の装置の実施例を示して
おり、図において、11は本発明を実施したドレーン材
埋設作業船である。この埋設作業船1】は双胴型の船体
12を有し、該船体12には枠体内に発泡スチロール等
のフロート13が収容されて構成されている。この船体
12の船底には、スタビライザ12aが前後方向に向け
て突出され、後述する軟弱地盤にこれを貫入した状態で
推進させることにより直進性を維持させるようにしてい
る。
(Example) Next, an example of implementation of the present invention will be described with reference to FIGS. 1 to 8. FIGS. 1 and 2 show an embodiment of the apparatus of the present invention, and in the figures, reference numeral 11 is a drain material burying work vessel in which the present invention is implemented. This burying work vessel 1 has a twin-hulled hull 12, and the hull 12 has a float 13 made of styrene foam or the like accommodated in a frame. A stabilizer 12a is protruded from the bottom of the hull 12 in the front-rear direction, and is propelled while penetrating the soft ground described later to maintain straightness.

船体12の上面には複数のリール14がブラヶント15
を介して回転自在に搭載されている。
A plurality of reels 14 are mounted on the upper surface of the hull 12.
It is rotatably mounted via the

各リール14には不繊布等よりなる中空のドレーン材1
6かそれぞれ巻き取られている。ドレーン材16は第3
図に示すように四角形の平型をなしていて、一端16 
A側は盲キャップ2つで閉じられ、基端16Bには真空
引き用ホース17がコネクタ18を介して接続されてる
ようになっている。船体12の底部には、上端を船体中
央部分の枢支部19で枢支させたドレーン材埋設ガイド
20が船体12の前後方向に回動自在に支持されている
。このドレーン材埋設ガイド20は、片面が開口したチ
ャンネル材等よりなるガイド本体21がその開口部を後
向きにして枢支部1つで支持され、このガイド本体21
内を経てガイドされる各ドレーン材16が該ガイド本体
21に上下方向に位置を異にして取り付けられたガイド
ロール22で向きを変えて水平に繰り出される構造にな
っている。即ち、ガイドロール22の位置によりドレー
ン材16の上下方向の埋設位置が定められるようになっ
ている。
Each reel 14 has a hollow drain material 1 made of nonwoven fabric, etc.
6 each are wound up. The drain material 16 is the third
As shown in the figure, it has a rectangular flat shape, and one end is 16
The A side is closed with two blind caps, and a vacuum hose 17 is connected to the base end 16B via a connector 18. A drain material buried guide 20 whose upper end is pivotally supported by a pivot 19 at the center of the hull is supported at the bottom of the hull 12 so as to be rotatable in the longitudinal direction of the hull 12 . This drain material embedding guide 20 has a guide body 21 made of a channel material or the like with an opening on one side, supported by a single pivot with the opening facing backward, and this guide body 21
Each drain material 16 guided through the inside is turned around by guide rolls 22 attached to the guide body 21 at different positions in the vertical direction and is fed out horizontally. That is, the vertical buried position of the drain material 16 is determined by the position of the guide roll 22.

船体12の前後部には一対のドレーン材埋設ガイド用の
姿勢制御手J−U23A、23Bが設けられている。こ
の各姿勢制御手段23A、23Bは、それぞれドレーン
材埋設ガイド20の中央より梢先端側の位置に枢軸24
A、24Bによって先端部が枢着された引抜枠25A、
25Bを有し、この引抜枠25A、25Bの後端側が船
体12の前後部に枢支された摺動ガイド筒26A、26
Bに摺動自在に挿通されている。各貫入引抜枠25A2
6Bは図には詳示してないが、それぞれラックピニオン
機構を介してモータ27A、27Bの駆動により軸方向
に往復動作させるようにしている。
A pair of posture control hands J-U 23A and 23B for guiding drain material embedding are provided at the front and rear of the hull 12. Each of the attitude control means 23A and 23B has a pivot 24 located at a position closer to the tip of the treetop than the center of the drain material embedding guide 20.
A, a drawing frame 25A whose tip is pivotally connected by 24B,
25B, and the rear end sides of the drawing frames 25A, 25B are pivotally supported at the front and rear of the hull 12.
It is slidably inserted into B. Each penetration pull-out frame 25A2
6B is not shown in detail in the figure, but is reciprocated in the axial direction by driving motors 27A and 27B via rack and pinion mechanisms, respectively.

而して、この姿勢制御手段23A、23Bは前方側の引
抜枠25Aを引き上げ、後方側の貫入引抜枠25Bを押
し込むことによりドレーン材埋設ガイド20が前方側に
回動され、逆に後方側の引抜枠25Bを引上げ、前方側
の貫入引抜枠25Aを押し込むことにより、ドレーン材
埋設ガイド20か後方側に回動されるようになっている
The posture control means 23A, 23B pull up the front drawing frame 25A and push in the rear penetrating drawing frame 25B, thereby rotating the drain material embedding guide 20 forward, and vice versa. By pulling up the pull-out frame 25B and pushing in the penetrating pull-out frame 25A on the front side, the drain material embedding guide 20 is rotated to the rear side.

次に上述した埋設作業船11を使用した本発明方法の実
施例について説明する。
Next, an embodiment of the method of the present invention using the above-mentioned burying work vessel 11 will be described.

まず、埋設始端側において、第4図に示すように後方側
の引抜枠25Bを引き上げてドレーン材埋設ガイド20
を軟弱地盤30上まで引き上げ、各ドレーン材16.1
6・・・・・・をガイドロール22に掛は回して導出さ
せ、各ドレーン材16の先端にそれぞれコネクタ18を
介して真空引きホース17を連結する。
First, on the burying start end side, as shown in FIG.
Raise the material to above the soft ground 30 and remove each drain material 16.1.
6... are placed on the guide roll 22 and turned to lead out, and the vacuum hose 17 is connected to the tip of each drain material 16 via the connector 18, respectively.

次いで第5図に示すように前方側の引抜枠25Aを引上
げ、ドレーン材埋設ガイド20を直立もしくはそれに近
い状態になるまで貫入させる。このとき、各ホース17
もしくは各ドレーン材16が軟弱地盤30中に引き込ま
れないように固定することにより各ドレーン材16はド
レーン材埋設ガイド20の貫入に従って繰り出され、埋
設始端部の軟弱地盤中に築堤31aの前面に沿って円弧
状に埋設される。
Next, as shown in FIG. 5, the front drawing frame 25A is pulled up and the drain material embedding guide 20 is inserted until it is upright or close to it. At this time, each hose 17
Alternatively, by fixing each drain material 16 so that it is not drawn into the soft ground 30, each drain material 16 is paid out according to the penetration of the drain material embedding guide 20, and is inserted into the soft ground at the starting end of the burying along the front surface of the embankment 31a. It is buried in an arc shape.

このようにドレーン材埋設ガイド20を貫入させた状態
でドレーン材埋設作業船11を前方側に進行させる。こ
の進行は、−例として岸上に設置したウィンチにより行
う、この進行に件ってドレーン材16は軟弱土の抵抗に
よって順次引き出され、水平方向に埋設される。
With the drain material burying guide 20 penetrating in this manner, the drain material burying work boat 11 is advanced forward. This advancement is carried out, for example, by a winch installed on the shore.During this advancement, the drain material 16 is successively pulled out by the resistance of the soft soil and buried in the horizontal direction.

そして、反対側の対岸の築堤31.bの前面の埋設終端
位置にて埋設作業船11の進行を止め、船上にて各ドレ
ーン材I6を必要な長さだけ残し、終端に盲キャップ2
つを装着した状態で第6図に示すように前方側の引抜枠
25Aを引上げてドレーン材埋設ガイド20を前方側に
回動させ、軟弱地盤30上まで引き上げる。これによっ
て築堤31bに沿って終端側が円弧状に湾曲され、その
先端が軟弱地盤表面積下部位置まで到達した状態に埋設
される。
And embankment 31 on the opposite bank. Stop the progress of the burying work vessel 11 at the burying end position in front of b, leave each drain material I6 for the required length on board, and install a blind cap 2 at the end.
With the drain material installed, as shown in FIG. 6, pull up the front drawing frame 25A, rotate the drain material embedding guide 20 forward, and pull it up above the soft ground 30. As a result, the terminal end side is curved into an arc shape along the embankment 31b, and the embankment is buried with its tip reaching a position below the soft ground surface area.

上述の操作によって一理設工程が終了する。これによっ
て第7図に示すようにドレーン材16の埋設始終端部1
6a、16bが弧状に埋設され、前述した従来例のよう
に埋設始終端部にドレーン材のない部分を残すことなく
均一な埋設がなされる。
The above-described operation completes the installation process. As a result, as shown in FIG.
6a and 16b are buried in an arc shape, and the drain material is buried uniformly without leaving any part without drain material at the beginning and end of the burial as in the conventional example described above.

なお、埋設の始終端部において、ドレーン材埋a船11
全体をゆっくり移動させつつドレーン材埋設ガイド20
を貫入させることにより、第8図に示すように始終端部
16a、16bを直線的に降下及び上昇させたように埋
設することらできる。
In addition, at the beginning and end of the burial, drain material burial vessel 11
Drain material embedding guide 20 while moving the whole slowly
As shown in FIG. 8, the starting and ending portions 16a and 16b can be buried in a linearly descending and ascending manner.

次いで埋設作業船11を元の位置に戻し、1ピッチ分だ
け横移動させ、前述と同様に操作し、これを繰り返して
軟弱地盤全面に一定ピッチ毎ドレーン材を埋設する。
Next, the burying work boat 11 is returned to its original position, moved horizontally by one pitch, and operated in the same manner as described above.This is repeated to bury the drain material at a constant pitch over the entire soft ground.

なお、埋設作業完了後は、真空引ホース17を減圧ポン
プに連結し、ドレーン材16内を減圧して軟弱地盤30
中の水を吸い出し、地盤改良する。
In addition, after the burying work is completed, the vacuum hose 17 is connected to a pressure reducing pump, and the pressure inside the drain material 16 is reduced to drain the soft ground 30.
The water inside is sucked out and the ground is improved.

(発明の効果) 上述したように、本発明方法においては、ドレーン材の
埋設始端においてドレーン材埋設ガイドを前進させつつ
軟弱地盤中に埋設させるようにするとともに、埋設終端
においてドレーン材埋設ガイドを前進させつつ上昇させ
るようにしたことにより、始端及び終端部において築堤
の前面に沿ってドレーン材が埋設されることとなり、軟
弱地盤全域が均一に改良されることとなり、その後の処
理がスムーズに、かつ完全に進めることかできる。
(Effects of the Invention) As described above, in the method of the present invention, the drain material burying guide is moved forward at the burying start end of the drain material to be buried in soft ground, and at the same time, the drain material burying guide is moved forward at the burying end. By raising the embankment at the same time, the drain material is buried along the front of the embankment at the beginning and end, and the entire soft ground is improved uniformly, making subsequent treatment smooth and easy. You can proceed completely.

また本発明の装置においては、ドレーン材埋設ガイドの
上@側を船体の中央部分に枢着させ、前後方向に軟弱地
盤上まで回動できるようにしたことにより、埋設作業船
を埋設始端及び終端において進行方向側に回動させると
いう簡単な作業により、両端位置に未依良部分を残さな
いようにドレーン材の埋設が可能となったものである。
In addition, in the device of the present invention, the upper @ side of the drain material burying guide is pivotally attached to the center part of the hull so that it can be rotated in the front and back direction up to the soft ground, so that the burying work vessel can be moved from the beginning of burying to the end of burying. By simply rotating the drain material in the advancing direction, it is possible to bury the drain material without leaving any undamaged portions at both ends.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る装置の実施例の平面図、第2図は
同側面図、第3図はドレーン材の端部の斜視図、第4図
〜第6図はそれぞれ本発明の方法の実施例の各工程を示
す側面図、第7図、第8図はそれぞれドレーン材の埋設
状態を示す断面図、第9図は従来装置の側面図、第1O
図は従来装置によるドレーン材埋設状態の側面図である
。 11・・・・・・埋設作業船、12・・・・・・船体、
12a・・・・・・スタビライザ、13・・・・・・フ
ロート、14・・・・・・リール、15・・・・・・ブ
ラケット、16・・・・・・ドレーン材、I7・・・・
・・X空引きホース、18・・・・・・コネクタ、19
・・・・・・枢支部、20・・・・・・ドレーン材埋設
ガイド。 21・・・・・・ガイド本体、22・・・・・・ガイド
ロール、23A、23B・・・・・・姿勢制御手段、2
4A、24B・・・・・・枢軸、 25A、25B・・・・・・引抜枠、 26A、26B・・・・・・摺動ガイド筒、27A、2
7B・・・・・・モーター 30・・・・・・軟弱地盤、31a、31b・・・・・
・築堤。
FIG. 1 is a plan view of an embodiment of the apparatus according to the present invention, FIG. 2 is a side view of the same, FIG. 3 is a perspective view of the end of the drain material, and FIGS. 4 to 6 are each a method of the present invention. Fig. 7 and Fig. 8 are sectional views showing the buried state of the drain material, Fig. 9 is a side view of the conventional device, and Fig.
The figure is a side view of a drain material buried state using a conventional device. 11... Buried work boat, 12... Hull,
12a... Stabilizer, 13... Float, 14... Reel, 15... Bracket, 16... Drain material, I7...・
...X empty hose, 18...Connector, 19
...Principle, 20...Drain material embedding guide. 21... Guide body, 22... Guide roll, 23A, 23B... Attitude control means, 2
4A, 24B...Pivot, 25A, 25B...Drawing frame, 26A, 26B...Sliding guide tube, 27A, 2
7B...Motor 30...Soft ground, 31a, 31b...
·embankment.

Claims (2)

【特許請求の範囲】[Claims] (1)船底より下方に垂下させたドレーン材埋設ガイド
に沿わせて必要な高さ位置にドレーン材を繰出し自在な
埋設作業船を使用し、前記ドレーン材埋設ガイドを軟弱
地盤中に挿入させた状態で、該地盤中を進行させ、その
進行に伴ってドレーン材を繰り出す水平ドレーン材の埋
設方法において、前記ドレーン材の埋設始端部分位置に
て前記ドレーン材埋設ガイドを軟弱地盤上より除々に該
地盤内に埋設させつつ進行方向側に移動させ、所定深さ
まで降下させた状態で作業船とともに水平移動させ、埋
設終端位置にて前記ドレーン材埋設ガイドを軟弱地盤表
面まで除々に昇降させつつ進行させることを特徴として
なるドレーン材の水平埋設方法。
(1) Using a burying work boat that can freely feed drain material to the required height position along a drain material burying guide suspended below the bottom of the ship, the drain material burying guide was inserted into the soft ground. In this horizontal drain material burying method, the horizontal drain material is moved through the ground and the drain material is paid out as it progresses, and the drain material burying guide is gradually moved from above the soft ground at the position of the burying start end of the drain material. While burying it in the ground, move it in the advancing direction, lower it to a predetermined depth, and then move it horizontally with the work boat, and at the end of the burial position, gradually raise and lower the drain material burying guide to the soft ground surface and advance. This is a method for horizontally burying drain material.
(2)上部にリールに巻き取ったドレーン材を搭載した
埋設作業船の略中央に、該埋設作業船の進行方向側前後
に回動自在に上端部を枢着したドレーン材埋設ガイドを
垂下させ、該ドレーン材埋設ガイドの複数高さ位置に、
前記リールから引き出したドレーン材を順次繰り出すド
レーン材繰出部を備え、かつ、前記ドレーン材埋設ガイ
ドを、その先端側を、前方及び後方側に強制回動させる
ドレーン材埋設ガイド姿勢制御手段を備えてなるドレー
ン材の水平埋設装置。
(2) A drain material burying guide, whose upper end is pivoted so as to be rotatable back and forth in the direction of movement of the burying work boat, is suspended approximately at the center of the burying work boat with the drain material wound on a reel mounted on the upper part. , at multiple height positions of the drain material buried guide,
A drain material feeding section that sequentially feeds out the drain material pulled out from the reel is provided, and a drain material embedding guide posture control means for forcibly rotating the distal end side of the drain material embedding guide forward and backward. A horizontal burial device for drain material.
JP28756789A 1989-11-06 1989-11-06 Horizontal burying method for drain material and burying apparatus therefor Expired - Lifetime JPH0670322B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28756789A JPH0670322B2 (en) 1989-11-06 1989-11-06 Horizontal burying method for drain material and burying apparatus therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28756789A JPH0670322B2 (en) 1989-11-06 1989-11-06 Horizontal burying method for drain material and burying apparatus therefor

Publications (2)

Publication Number Publication Date
JPH03147920A true JPH03147920A (en) 1991-06-24
JPH0670322B2 JPH0670322B2 (en) 1994-09-07

Family

ID=17719010

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28756789A Expired - Lifetime JPH0670322B2 (en) 1989-11-06 1989-11-06 Horizontal burying method for drain material and burying apparatus therefor

Country Status (1)

Country Link
JP (1) JPH0670322B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08169392A (en) * 1994-12-16 1996-07-02 Tokyu Constr Co Ltd Method for laying horizontal drain material and work barge for laying the same
WO1999047755A1 (en) * 1998-03-16 1999-09-23 Toyoha Mining Co. Ltd. Consolidation deposition method of materials containing moisture at deposition site
CN115075228A (en) * 2022-05-11 2022-09-20 中铁时代建筑设计院有限公司 Connecting device of cast-in-place pipe pile water storage system, water storage system and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08169392A (en) * 1994-12-16 1996-07-02 Tokyu Constr Co Ltd Method for laying horizontal drain material and work barge for laying the same
WO1999047755A1 (en) * 1998-03-16 1999-09-23 Toyoha Mining Co. Ltd. Consolidation deposition method of materials containing moisture at deposition site
CN115075228A (en) * 2022-05-11 2022-09-20 中铁时代建筑设计院有限公司 Connecting device of cast-in-place pipe pile water storage system, water storage system and construction method

Also Published As

Publication number Publication date
JPH0670322B2 (en) 1994-09-07

Similar Documents

Publication Publication Date Title
JPS62189215A (en) Penetrating equipment for draining core
US4877355A (en) Underwater cable laying system
US4445290A (en) Appliance for dredging the bottom of a body of water
JPH03147920A (en) Horizontal burying method of drain material and burying device thereof
CN87102670A (en) The device of laying subterranean plastic tape and pipe
US3813888A (en) Apparatus for laying sub-surface irrigation pipe
JPH04203011A (en) Horizontal burying apparatus for drain material
CN112072557A (en) Cable laying device for electrical automation control
CN210597268U (en) Soft foundation treatment reinforcing apparatus of plastics drain bar
JPS57172039A (en) Method and apparatus for placing under-water concrete
US2906501A (en) Excavating apparatus
US4244664A (en) Method and apparatus for on-site treatment of mud and silt
JPH0522768B2 (en)
JP2010229816A (en) Vacuum consolidation method using horizontal drain
US8944725B2 (en) Method and system for temporarily supporting a soil mass susceptible to slide
JP3363303B2 (en) Dredging equipment
JP3218525B2 (en) Removal method of existing pile
JP2751007B2 (en) Underwater walking dredging method and dredging machine
GB2179386A (en) Inserting anti-seepage barrier material into the ground
CN113586802B (en) Water conservancy pipeline pre-embedding device and construction method thereof
JPH08311854A (en) No-vibration and no-noise compaction sand pile formation method
JP5669040B2 (en) Drain material horizontal burying equipment
JPS649418B2 (en)
JP2849250B2 (en) Horizontal drain material laying method and laying work boat
JP2012132226A (en) Method for horizontally installing drain materials to weak ground, and device for horizontally installing drain materials

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070907

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080907

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090907

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 16

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100907

Year of fee payment: 16