JPH0313606A - Construction method and apparatus for structure - Google Patents
Construction method and apparatus for structureInfo
- Publication number
- JPH0313606A JPH0313606A JP14810989A JP14810989A JPH0313606A JP H0313606 A JPH0313606 A JP H0313606A JP 14810989 A JP14810989 A JP 14810989A JP 14810989 A JP14810989 A JP 14810989A JP H0313606 A JPH0313606 A JP H0313606A
- Authority
- JP
- Japan
- Prior art keywords
- cable
- eccentric
- jack
- tension
- execution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 20
- 239000000463 material Substances 0.000 claims abstract description 10
- 210000002435 tendon Anatomy 0.000 claims description 8
- 238000000034 method Methods 0.000 description 5
- 238000001125 extrusion Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 239000004567 concrete Substances 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は、押出し工法のように施工時の構造系が変化
する構造物の構築、あるいは架設時と完成時の応力が逆
転するような架設、例えば桁の回転架設、さらには橋梁
等の構造物の解体への利用が考えられるアウトケーブル
方式を用いた偏心移動法による構造物の構築法及びその
装置に関するものである。[Detailed Description of the Invention] (Field of Industrial Application) This invention is applicable to the construction of structures where the structural system changes during construction, such as the extrusion method, or construction where the stresses at the time of erection and completion are reversed. The present invention relates to a method and apparatus for constructing a structure using an eccentric movement method using an out-cable method, which can be used, for example, for the rotational erection of girders and the demolition of structures such as bridges.
(従来の技術)
従来、プレストレストコンクリート構造物ではコンクリ
ート部材の内部に緊張材を配置したインナーケーブル方
式が主流となっている。(Prior Art) Conventionally, in prestressed concrete structures, an inner cable method in which tension members are placed inside a concrete member has been mainstream.
(発明が解決しようとする課B)
ところで前記従来の方式では、緊張材の位置が部材内部
に固定されているため架設時において作用モーメントが
変動し正負逆転することもある部材においては不向きと
いえる。すなわち緊張材の偏心位置が逆効果になる場合
も生じ、軸心配置等の方法によって対処せざるを得ない
のが現状である。その結果完成時において不要ケーブル
が残存するなど非常に不経済となっている。そればかり
か、完成系においてオーバープレストレスになる場合に
は、緊張力を解放する必要が生じるなど材料面だけでな
く作業手間においても不経済となる、等の難点があった
。(Problem B to be solved by the invention) By the way, in the conventional method described above, the position of the tension material is fixed inside the member, so it can be said that it is unsuitable for members where the acting moment fluctuates during erection and the positive and negative changes may be reversed. . In other words, the eccentric position of the tendon sometimes has the opposite effect, and the current situation is that it must be dealt with by methods such as axial center placement. As a result, unnecessary cables remain at the time of completion, making it very uneconomical. Moreover, if over-prestress occurs in the completed system, it becomes necessary to release the tension, which is disadvantageous not only in terms of materials but also in terms of labor.
この発明は従来の難点を解消するために開発したもので
、完成系で不要となる施工時用緊張材の数量やそれに伴
なう作業手間を少なく、または無くすことのできる構築
法およびその装置を提供することを目的とする。This invention was developed in order to solve the conventional difficulties, and it provides a construction method and device that can reduce or eliminate the amount of tension material during construction that is unnecessary in the completed system and the associated work effort. The purpose is to provide.
(課題を解決するための手段)
前記目的を達成するためにこの発明では、緊張材の一部
あるいは全部をアウトケーブル配置とし、このアウトケ
ーブルの位置を偏心位置移動装置により随時上下方向に
移動させ、かつこれに伴なう緊張材の長さ変動に対して
は張力調節装置により同時に所定の緊張力を保持するよ
うなしたものである。(Means for Solving the Problems) In order to achieve the above-mentioned object, in this invention, a part or all of the tension material is arranged as an out cable, and the position of the out cable is moved vertically as needed by an eccentric position moving device. , and a predetermined tension is maintained at the same time by a tension adjustment device against the accompanying length variation of the tendon material.
そして偏心移動装置はケーブル偏心用ジヤツキからなり
、このケーブル偏心用ジヤツキは構造物上面に設置し、
また張力調節装置は張力調節用ジヤツキからなり、この
張力調節用ジヤツキは緊張材の端部に設置するものであ
る。The eccentric moving device consists of a cable eccentric jack, which is installed on the top surface of the structure.
Further, the tension adjustment device includes a tension adjustment jack, and this tension adjustment jack is installed at the end of the tendon.
(実 施 例)
以下、この発明を図示した押出し工法の実施例に基づい
て説明する。第1図乃至第3図はこの発明に使用するケ
ーブル偏心位置移動装置およびケーブルの張力調節装置
を示すものであり、基本的には再装置の構造は油圧ジヤ
ツキからなるものである。そして偏心位置移動装置とし
て、ケーブル偏心用ジヤツキlを構造物2の支点上面、
および支間中央上面のそれぞれに施工の進行に伴ない順
次設置し、張力調節装置としては張力調節用ジヤツキ3
を緊張材の先端部に設置し、所定のケーブル偏心量およ
び緊張力を確保するため、各施工状態における設計値に
応じて互いに連動させる。また施工管理は、中央制御盤
(図示せず)によってケーブル偏心用ジヤツキlについ
てはそのストロークを、張力調節用ジヤツキ3について
は油圧をそれぞれ集中コントロールする。(Example) The present invention will be described below based on an illustrated example of the extrusion method. 1 to 3 show a cable eccentric position moving device and a cable tension adjusting device used in the present invention, and the structure of the resetting device basically consists of a hydraulic jack. Then, as an eccentric position moving device, a cable eccentric jack l is placed on the upper surface of the fulcrum of the structure 2,
and the upper surface of the center of the span as the construction progresses.
are installed at the tip of the tension member, and are interlocked with each other according to the design values for each construction state in order to ensure a predetermined cable eccentricity and tension. For construction management, a central control panel (not shown) centrally controls the stroke of the cable eccentric jack 1 and the hydraulic pressure of the tension adjustment jack 3.
第2図および第3図はケーブル偏心用ジヤツキ1の設置
状態をより具体的に示したものである。ケーブル偏心用
ジヤツキlは構造物2の左右側にそれぞれ設置され、構
造物2のウェブ4に沿ってケーブル偏心用ジヤツキ1の
ロッド5が上、上移動できるよう固定され、ロッド5の
下端に緊張材としてアウトケーブル6を取付けである。FIGS. 2 and 3 show the installed state of the cable eccentric jack 1 in more detail. The cable eccentric jacks l are installed on the left and right sides of the structure 2, and are fixed so that the rod 5 of the cable eccentric jack 1 can move up and down along the web 4 of the structure 2, and is tensioned at the lower end of the rod 5. Out cable 6 is attached as a material.
そして第2図における左側のケーブル偏心用ジヤツキl
はロッド5を上方に移動させる状態を示し、右側のケー
ブル偏心用ジヤツキ1は盛替時の状態を示したものであ
り、第3図における左側のケーブル偏心用ジヤツキ1は
ロッド5を下方に移動させる状態を示し、右側のケーブ
ル偏心用ジヤツキlは盛替時の状態を示したものである
。And the left cable eccentric jack l in Figure 2.
shows the state in which the rod 5 is moved upward, the cable eccentricity jack 1 on the right side shows the state at the time of repositioning, and the cable eccentricity jack 1 on the left side in Fig. 3 moves the rod 5 downward. The cable eccentric jack 1 on the right side is shown in the state when it is replaced.
第4図、第5図は施工中の緊張材配置状態を示すもので
ある。第4図においては先端に手延ベガーダー7を取付
けた構造物2は支点ptと支点22間に跨って架設され
てあり、支点P】上ではアウトケーブル6は偏心用ジヤ
ツキlを上方へ作動させることにより最高高さ位置に配
設され、支点P1と支点P2の支間中央においては偏心
用ジヤツキ1を下方に作動させることによりアウトケー
ブル6は第7図にも示すように最低高さ位置に配設され
る。また支点P2上ではアウトケーブル6は中間高さ位
置に配置される。そしてこれに伴なうアウトケーブル6
の長さ変動に対しては張力調節用ジヤツキ3によりアウ
トケーブル6の緊張力を調節する。Figures 4 and 5 show the arrangement of tendons during construction. In Fig. 4, a structure 2 with a hand-stretched begirder 7 attached to its tip is constructed across a fulcrum pt and a fulcrum 22, and above the fulcrum P, an out cable 6 operates an eccentric jack l upward. By operating the eccentric jack 1 downward at the center of the span between the fulcrums P1 and P2, the out cable 6 is placed at the lowest height position as shown in FIG. will be established. Further, on the fulcrum P2, the out cable 6 is arranged at an intermediate height position. And the accompanying out cable 6
For changes in length, the tension of the out cable 6 is adjusted by the tension adjustment jack 3.
第5図においては、構造物2はさらに押出され、手延ベ
ガーダー7の先端部が支点P3上に配置された状態を示
すもので、支点P2上ではアウトケーブル6は偏心用ジ
ヤツキ1を上方の作動させることにより第8図にも示し
たように最高高さ位置に配設される。また支点P2と支
点P3の支間中央では偏心用ジヤツキ1を下方に作動さ
せることによりアウトケーブル6ば最低高さ位置に配設
される。In FIG. 5, the structure 2 is further extruded and the tip of the hand-stretched begirder 7 is placed on the fulcrum P3. On the fulcrum P2, the out cable 6 connects the eccentric jack 1 upward. When activated, it is placed at the highest height position as shown in FIG. Further, by operating the eccentric jack 1 downward at the center of the span between the fulcrum P2 and the fulcrum P3, the out cable 6 is disposed at the lowest height position.
以上のように押出し施工中は所要のピッチに設置した偏
心用ジヤツキ1によって支間中央部では断面の下方へ、
支点上では断面の上方へとアウトケーブル6の上下移動
を繰り返し各施工段階における作用モーメントの状態に
対応してアウトケーブル6の配設形状を変化させ、アウ
トケーブル6は第6図に示す完成系における配設状態と
なる。As mentioned above, during extrusion construction, the eccentric jacks 1 installed at the required pitch move the center part of the span downwards in the cross section.
On the fulcrum, the out cable 6 is repeatedly moved upward and downward in the cross section, and the arrangement shape of the out cable 6 is changed according to the state of the acting moment at each construction stage. The arrangement state is as follows.
所要の位置に配設されたアウトケーブル6の全体をカバ
ー7によって被覆する。このカバー7は第11図に示す
ように断面半円状に形成してあり、アンカーボルト8に
より構造物2のウェブ4内面に取付けられる。またカバ
ー7とウェブ4の間の内部空間にはウェブ4内面よりジ
ベル9を突設し、さらに内部空間においてグラウトを行
う。そしてアウトケーブル6の折曲部分においてケーブ
ル位置固定アンカー10によってさらにウェブ4に固定
するものである。The entire out cable 6 disposed at a required position is covered with a cover 7. The cover 7 has a semicircular cross section as shown in FIG. 11, and is attached to the inner surface of the web 4 of the structure 2 with anchor bolts 8. Further, in the internal space between the cover 7 and the web 4, a dowel 9 is provided to protrude from the inner surface of the web 4, and grouting is further performed in the internal space. The out cable 6 is further fixed to the web 4 at the bent portion by a cable position fixing anchor 10.
(発明の効果)
この発明は施工時の各断面における桁自重モーメントの
変動に追随して緊張材を上下に移動することで、従来施
工中のためだけに必要であった施工時用緊張材の数量を
大幅に節減し、さらに完成後における緊張力の解放など
の作業を省くことができる。また施工終了後における完
成ケーブルの後挿入や、施工時鋼棒の緊張力解放などの
作業を省くことができる。(Effects of the Invention) This invention moves the tendons up and down in accordance with the fluctuations of the girder self-weight moment at each cross section during construction, thereby reducing the need for tendons during construction, which was conventionally required only during construction. It is possible to significantly reduce the quantity and also eliminate work such as releasing tension after completion. In addition, it is possible to eliminate the work of inserting the completed cable after the completion of construction and releasing the tension of the steel rod during construction.
第1図はこの発明の装置の設置状態を示した概略側面図
、第2図は偏心用ジヤツキのロッドを上方に移動させた
状態とジヤツキ盛替時の状態を示した横断面図、第3図
は偏心用ジヤツキのロッドを下方に移動させた状態とジ
ヤツキ盛替時の状態を示した横断面図、第4図、第5図
は施工時のアウトケーブルの配設状態を示した概略側面
図、第6図は完成系のアウトケーブルの配設状態を示し
た概略側面図、第7図はA−A断面図、第8図はB−B
断面図、第9図は完成系のアウトケーブルの固定状態を
示した概略側面図、第10図はC−C断面図、第11図
はアウトケーブルの構造物部分における取付状態を示し
た断面図である。
1・・・ケーブル偏心用ジヤツキ、2・・・構造物、3
・・・張力調節用ジヤツキ、4・・・ウェブ、5・・・
ロッド、6・・・アウトケーブル、7・・・手延ベガー
ダ、8・・・アンカーボルト、9・・・ジベル、10・
・・ケーブル位置固定アンカー 11・・・PC鋼棒。
34−Fig. 1 is a schematic side view showing the installation state of the device of the present invention, Fig. 2 is a cross-sectional view showing the state in which the rod of the eccentric jack is moved upward and the state when the jack is replaced; The figure is a cross-sectional view showing the state in which the rod of the eccentric jack is moved downward and the state in which the jack is replaced. Figures 4 and 5 are schematic side views showing the arrangement of the out cable during construction. Figure 6 is a schematic side view showing the arrangement of out cables in the completed system, Figure 7 is a sectional view taken along A-A, and Figure 8 is shown along B-B.
9 is a schematic side view showing the fixed state of the out cable of the completed system, FIG. 10 is a C-C sectional view, and FIG. 11 is a sectional view showing the state of attachment of the out cable in the structure part. It is. 1... Cable eccentric jack, 2... Structure, 3
...Tension adjustment jack, 4...Web, 5...
Rod, 6...Out cable, 7...Hand-stretched begada, 8...Anchor bolt, 9...Dowel, 10.
...Cable position fixing anchor 11...PC steel rod. 34-
Claims (2)
る応力の変動ないし正負逆転するような構造物の構築法
において、緊張材の一部あるいは全部をアウトケーブル
配置とし、このアウトケーブルの位置を偏心位置移動装
置により随時アクティブに上下方向に移動させ、かつこ
れに伴なう緊張材の長さ変動に対しては張力調節装置に
より同時に所定の緊張力を保持することを特徴とする構
造物の構築法。(1) In a structure construction method in which the stress acting on the same cross section of a member fluctuates or reverses its polarity due to changes in construction conditions, some or all of the tension members are placed with out-cables, and the position of the out-cables is A structure characterized in that the structure is actively moved vertically at any time by an eccentric position moving device, and at the same time a predetermined tension is maintained by a tension adjustment device in response to the accompanying length fluctuations of the tendon material. Construction method.
、このケーブル偏心用ジャッキは構造物上面に設置し、
また張力調節装置は張力調節用ジャッキからなり、この
張力調節用ジャッキは緊張材の端部に設置したことを特
徴とする構造物の構築装置。(2) The eccentric moving device consists of a cable eccentric jack, which is installed on the top surface of the structure,
The apparatus for constructing a structure is characterized in that the tension adjustment device includes a tension adjustment jack, and the tension adjustment jack is installed at an end of the tendon material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1148109A JPH0692643B2 (en) | 1989-06-09 | 1989-06-09 | Construction method of structure and its equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1148109A JPH0692643B2 (en) | 1989-06-09 | 1989-06-09 | Construction method of structure and its equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0313606A true JPH0313606A (en) | 1991-01-22 |
JPH0692643B2 JPH0692643B2 (en) | 1994-11-16 |
Family
ID=15445451
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1148109A Expired - Lifetime JPH0692643B2 (en) | 1989-06-09 | 1989-06-09 | Construction method of structure and its equipment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0692643B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020000541A (en) * | 2001-12-13 | 2002-01-05 | 임인숙 | dish drainer |
JP2006348685A (en) * | 2005-06-20 | 2006-12-28 | Penta Ocean Constr Co Ltd | Method for lifting concrete member and lifting fixture |
JP2007089681A (en) * | 2005-09-27 | 2007-04-12 | Kai R & D Center Co Ltd | Dish drainer |
CN105648890A (en) * | 2016-03-18 | 2016-06-08 | 大连理工大学 | U-shaped prestressed structure for webs and bottom board of concrete box beam |
CN112458902A (en) * | 2020-11-05 | 2021-03-09 | 滁州职业技术学院 | Multi-angle steering control platform for corrugated steel web prestressed box girder bridge |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5436041A (en) * | 1977-08-26 | 1979-03-16 | Yuuji Kawai | Method of pushing out bridge girder |
-
1989
- 1989-06-09 JP JP1148109A patent/JPH0692643B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5436041A (en) * | 1977-08-26 | 1979-03-16 | Yuuji Kawai | Method of pushing out bridge girder |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020000541A (en) * | 2001-12-13 | 2002-01-05 | 임인숙 | dish drainer |
JP2006348685A (en) * | 2005-06-20 | 2006-12-28 | Penta Ocean Constr Co Ltd | Method for lifting concrete member and lifting fixture |
JP4541978B2 (en) * | 2005-06-20 | 2010-09-08 | 五洋建設株式会社 | Method of lifting concrete member and lifting jig |
JP2007089681A (en) * | 2005-09-27 | 2007-04-12 | Kai R & D Center Co Ltd | Dish drainer |
CN105648890A (en) * | 2016-03-18 | 2016-06-08 | 大连理工大学 | U-shaped prestressed structure for webs and bottom board of concrete box beam |
CN112458902A (en) * | 2020-11-05 | 2021-03-09 | 滁州职业技术学院 | Multi-angle steering control platform for corrugated steel web prestressed box girder bridge |
Also Published As
Publication number | Publication date |
---|---|
JPH0692643B2 (en) | 1994-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108708498B (en) | External prestress reinforced concrete frame beam structure and construction method thereof | |
DE60226173T2 (en) | INDIRECTLY PREPARED EBENER CONCRETE COVER CONSTRUCTION | |
EP2054553B1 (en) | Tilt-lift method for erecting a bridge and vertical lift bridge manufactured accordingly | |
WO2007025947A1 (en) | Method for vertically extruding a concrete element, device for producing a concrete element and wind turbine generator tower produced by this method | |
US3427773A (en) | Structure for increasing the loadcarrying capacity of a beam | |
CN106522282B (en) | A kind of liftable post-cast strip template structure and system and its construction method | |
JPH0313606A (en) | Construction method and apparatus for structure | |
CN114214915A (en) | Partially prefabricated and assembled corrugated steel web combined box girder bridge structure and construction method | |
CN110524675B (en) | Pre-tensioning prefabricated I-beam and construction method thereof | |
JPH05106210A (en) | Erecting method for concrete skew bridge | |
JP2000054319A (en) | Formation of concrete floor slab and construction of suspended deck bridge | |
JP4057724B2 (en) | Support structure of bridge girder in extrusion method | |
JP2017214738A (en) | Demolition system and demolition method for high-rise building | |
CN1147589A (en) | Prestressed reinforced concrete structure and its construction method | |
KR20050018195A (en) | large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method | |
JP4436585B2 (en) | Cable-stayed bridge construction method | |
KR101120163B1 (en) | Construction method for temporary bridge | |
CN202108156U (en) | Long-span prestress string beam | |
JP2009097197A (en) | Method of constructing pillar head | |
CN210507788U (en) | Gate-type steel frame construction based on many concatenations | |
CN109972531B (en) | External prestressing device for improving temporary support span of bailey beam | |
US4319374A (en) | Method of constructing a stayed girder bridge | |
KR20040102272A (en) | Prestressed concrete double-t beam bridge & formwork applying incremental launching method | |
JPH07109711A (en) | Continuous feeding method of concrete slab | |
JPH05331808A (en) | Erection method for reversed langer arch bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091116 Year of fee payment: 15 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091116 Year of fee payment: 15 |