JPH0291314A - Forming method for opening portion of underground continuous wall - Google Patents

Forming method for opening portion of underground continuous wall

Info

Publication number
JPH0291314A
JPH0291314A JP24177688A JP24177688A JPH0291314A JP H0291314 A JPH0291314 A JP H0291314A JP 24177688 A JP24177688 A JP 24177688A JP 24177688 A JP24177688 A JP 24177688A JP H0291314 A JPH0291314 A JP H0291314A
Authority
JP
Japan
Prior art keywords
continuous wall
opening
underground continuous
case
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24177688A
Other languages
Japanese (ja)
Inventor
Yoshiaki Ikeuchi
池内 義明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP24177688A priority Critical patent/JPH0291314A/en
Publication of JPH0291314A publication Critical patent/JPH0291314A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To form an opening portion simply and quickly and intend better efficiency and lower cost of construction by inserting into a drilled cavity for a continuous wall a reinforced cage previously incorporated with a steel-made case, which is large enough to match a destroyed and removed portion, at a preset position. CONSTITUTION:A steel-made case 2, with a scale equivalent to a destroyed and removed portion and the same thickness as an underground continuous wall, is made up in such a manner that a reinforcement 1a is projected from a hollow structure comprising respective face plates 2a-2f provided with reinforced ribs 3 inside, and openings 5, 6 are provided in an upper and lower face plates 2e, 2f and covered with a network structure 7 etc. Then, the case 2 is built at a preset position into a reinforced cage 1 which is suspended down in a cavity 9 for the continuous wall, where concrete is placed while putting sand or broken stones into the case 2 to construct the continuous wall. Then an opening is formed, with the inside of the continuous wall drilled, the exposed case 2 cut and withdrawn, and the broken stones etc. removed.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、地中連続壁をトンネル施工における発進坑、
到達坑を形成するものとして利用する場合に、シールド
掘進機等が通過する開口を設けるための地中連続壁の開
口部形成工法に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention is directed to a starting shaft in tunnel construction using an underground continuous wall.
The present invention relates to a method for forming an opening in an underground continuous wall for providing an opening through which a shield excavator or the like passes when used to form an access shaft.

〔従来の技術〕[Conventional technology]

発進坑、到達坑のごとき立坑を地中連続壁で形成した場
合、シールド掘進機等が通過する開口をこのシールド掘
進機が発進又は到達する直前に地中連続壁に設けなけれ
ばならない。
When a vertical shaft such as a starting shaft or a destination shaft is formed using an underground continuous wall, an opening through which a shield tunneling machine, etc. passes must be provided in the underground continuous wall immediately before the shield tunneling machine starts or reaches the shaft.

この開口は地中連続壁を厚さ方向に大きく貫通するもの
で、従来は通常の方法で地中連続壁を施工し、シールド
掘進機にとって進行の障害となる部分の連壁鉄筋コンク
リートをコンクリート破砕機と鋼材鉄筋切断機で取り壊
し、撤去する方法がとられる。
This opening largely penetrates the underground continuous wall in the thickness direction, and in the past, the underground continuous wall was constructed using the normal method, and the reinforced concrete of the continuous wall was removed by a concrete crusher in the part that would be an obstacle for the shield excavator to advance. The method of demolition and removal using a steel reinforcing bar cutting machine was adopted.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかし、以上のごとき鉄筋コンクリートの破砕により開
口を形成する方法では、非常に時間と労力を費やし、ま
た地中連続壁自体に悪影響を与えるおそれがある。
However, the method of forming openings by crushing reinforced concrete as described above requires a great deal of time and effort, and may have an adverse effect on the diaphragm wall itself.

本発明の目的は前記従来例の不都合を解消し、効率よく
かつ迅速に開口部を形成でき、工費も安価ですむ地中連
続壁の開口部形成工法を提供することにある。
SUMMARY OF THE INVENTION An object of the present invention is to provide a method for forming an opening in an underground continuous wall, which eliminates the disadvantages of the conventional example, allows the opening to be formed efficiently and quickly, and is inexpensive.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は前記目的を達成するため、連続壁用溝を掘削し
て、該溝内に取り壊し撤去部分に相当する大きさの鋼製
函体を所定位置に組み込んだ鉄筋篭を挿入し、その後溝
内にコンクリートを打設して地中連続壁を形成し、完成
した地中連続壁の内側部分を掘削した後、鋼製函体部分
をくり抜いて開口を形成することを要旨とするものであ
る。
In order to achieve the above object, the present invention excavates a groove for a continuous wall, inserts into the groove a reinforcing bar cage in which a steel box of a size corresponding to the part to be demolished and removed is installed in a predetermined position, and then The main idea is to pour concrete inside to form an underground continuous wall, excavate the inner part of the completed underground continuous wall, and then hollow out the steel box to form an opening. .

〔作用〕[Effect]

本発明によれば、地中連続壁を形成する場合、打設コン
クリートは鋼製函体内部には回らないでその部分以外で
鉄筋コンクリート壁体が形成される。そして、地中連続
壁の完成後、該地中連続壁の内側部分を掘削して立坑を
形成した後で、この鋼製函体を用いて箱抜きを行えば地
中連続壁を厚さ方向に貫く開口を簡単に形成することが
できる。
According to the present invention, when forming an underground continuous wall, the poured concrete does not go inside the steel box, and a reinforced concrete wall is formed outside that part. After the underground continuous wall is completed and the inner part of the underground continuous wall is excavated to form a shaft, this steel box can be used to punch out the underground wall in the thickness direction. It is possible to easily form an opening that penetrates the

〔実施例〕〔Example〕

以下、図面について本発明の実施例を詳細に説明する。 Embodiments of the present invention will be described in detail below with reference to the drawings.

先に、本発明工法で使用する鉄筋篭について説明する。First, the reinforcing bar cage used in the construction method of the present invention will be explained.

第1図は鉄筋篭1の要部を示す斜視図で、図中2は鋼製
函体である。該鋼製函体2は前面板2a、後面板2b、
左右側面板2c、2d、下面板2e、下面板2fからな
る長方形状の中空体で、前面板2aと後面板2b間、す
なわち左右側面板2c。
FIG. 1 is a perspective view showing the main parts of a reinforcing bar cage 1, and 2 in the figure is a steel box. The steel case 2 has a front plate 2a, a rear plate 2b,
A rectangular hollow body consisting of left and right side plates 2c, 2d, a lower plate 2e, and a lower plate 2f, between the front plate 2a and the rear plate 2b, that is, the left and right side plates 2c.

2dの巾は造成すべき地中連続壁の厚さとほぼ同一とす
る。
The width of 2d is approximately the same as the thickness of the underground continuous wall to be constructed.

さらに、前面板2a、後面板2bなどの内側には、函体
2がコン・クリート圧、土圧、水圧等に耐えられるよう
に補強リブ3を一体的に設け、上面板2e、下面板2f
、左右側面板2c、2dの外側には鉄筋篭lの鉄筋1a
との接続用フランジ4を突設した。
Furthermore, reinforcing ribs 3 are integrally provided on the inside of the front plate 2a, rear plate 2b, etc. so that the box 2 can withstand concrete pressure, earth pressure, water pressure, etc.
, reinforcing bars 1a of the reinforcing bar cage l are placed on the outside of the left and right side plates 2c and 2d.
A flange 4 for connection with is provided protrudingly.

また、上面板2e、下面板2fの中央位置に上部開口5
と下部開口6とをそれぞれ形成するが、このうち下部開
口6は網体7やシート等で覆い、液体は通すがコンクリ
ートは通さないようにする。
Further, an upper opening 5 is provided at the center position of the upper surface plate 2e and the lower surface plate 2f.
and a lower opening 6, of which the lower opening 6 is covered with a net 7, a sheet, etc. to allow liquid to pass through but not concrete.

フランジ4に鉄筋1aを溶接することで、第2図、第3
図に示すようにこのような鋼製函体2を鉄筋篭1の所定
位置(地中連続壁における取り壊し撤去部分に相当する
位置)に予め組み込んでおく。
By welding the reinforcing bar 1a to the flange 4,
As shown in the figure, such a steel box 2 is installed in advance in a predetermined position of the reinforcing bar cage 1 (a position corresponding to the part of the underground continuous wall to be demolished and removed).

第4図〜第11図は本発明工法の各工程を示すもので、
まず第4図に示すように掘削機8を用いて連続壁用の溝
9を削孔し、その中に安定液10を充填する。
Figures 4 to 11 show each step of the construction method of the present invention.
First, as shown in FIG. 4, a groove 9 for a continuous wall is drilled using an excavator 8, and a stabilizing liquid 10 is filled therein.

次いで、第5図に示すように前記のごとく鋼製函体2を
組み込んだ鉄筋篭1を溝9内岬吊り降ろし固定するが、
該函体2には上部開口5と下部開口6とが形成されてい
るので、安定液10は函体2内にも入り浮力は作用しな
い。
Next, as shown in FIG. 5, the reinforcing bar cage 1 incorporating the steel box 2 as described above is suspended and fixed at the cape within the groove 9.
Since the box 2 has an upper opening 5 and a lower opening 6, the stabilizing liquid 10 also enters the box 2 and no buoyant force acts on it.

第6図、第7図に示すようにトレミー管11を降ろして
溝9内にコンクリート12を打設するが、砕石投入管1
3も降ろしてその先端を鋼製函体2の上部開口5内へ差
入れ、打設したコンクリート12の天端が函体2の下端
に達したならば砕石投入管13により函体2内に砂又は
砕石14の投入を開始する。
As shown in FIGS. 6 and 7, the tremie pipe 11 is lowered and concrete 12 is poured into the groove 9.
3, and insert its tip into the upper opening 5 of the steel box 2. When the top of the poured concrete 12 reaches the bottom end of the box 2, pour sand into the box 2 using the crushed stone input pipe 13. Or start adding crushed stone 14.

以後この砂又は砕石14の天端とコンクリート12の天
端とは、常に同レベル程度を維持しながらコンクリート
12の打設を行う。
Thereafter, the concrete 12 is placed while maintaining the top of the sand or crushed stone 14 and the top of the concrete 12 at the same level.

第8図に示すようにコンクリート12の天端が函体2の
上部開口5に達したならば(この時点て函体2の内部は
砂又は砕石14で満たされことになる)、砂又は砕石1
4の投入をやめ、砕石投入管13を抜き取り撤去する。
As shown in FIG. 8, when the top of the concrete 12 reaches the upper opening 5 of the box 2 (at this point, the inside of the box 2 is filled with sand or crushed stone 14), the sand or crushed stone 1
4 is stopped, and the crushed stone input pipe 13 is pulled out and removed.

該砕石投入管13の撤去後は、トレミー管11によりコ
ンクリ−目2の打設を続行して地中連続壁15を完成さ
せる(第9図参照)。第9図中、16は該地中連続壁1
5に接−続する隣接エレメントを示す。
After the crushed stone input pipe 13 is removed, concrete concretion 2 is continued to be placed using the tremie pipe 11 to complete the underground continuous wall 15 (see Fig. 9). In Fig. 9, 16 indicates the underground continuous wall 1
The adjacent element connected to 5 is shown.

このようにして連続壁の施工が完了したならば、内側部
分の土砂を掘削して立坑17を形成するが、外側部分で
函体2の位置する個所は従来工法と同じく薬液注入等で
補強18を施す(第1θ図参照)。
When the construction of the continuous wall is completed in this way, the earth and sand in the inner part is excavated to form the shaft 17, but the outer part where the box 2 is located is reinforced by chemical injection etc. 18 as in the conventional construction method. (See Figure 1θ).

前記立坑17を形成すると、函体2の内側面(前面板2
a)が露出するので、この前面板2aや補強リブ3をガ
ス切断機等で切断撤去して内部の砂又は砕石14を取除
き、さらに後面板2bや補強リブ3を同様に切断撤去し
て地中連続壁15を巾方向に貫通する開口19を形成し
、これをシールド掘進機等の通過口として利用する。
When the vertical shaft 17 is formed, the inner surface of the box 2 (front plate 2
a) is exposed, the front plate 2a and reinforcing ribs 3 are cut and removed using a gas cutter or the like to remove internal sand or crushed stones 14, and the rear plate 2b and reinforcing ribs 3 are also cut and removed in the same manner. An opening 19 is formed that penetrates the underground continuous wall 15 in the width direction, and is used as a passage port for a shield excavator or the like.

なお、鋼製函体2に関してはこれをすべて切断撤去して
開口19を形成してもよいが、左右側面板2c、2dと
上面板2es下面板2fによる枠体を残せばこれを鉄筋
1aと一体の強度部材として利用することもできる。
The steel case 2 may be completely cut and removed to form the opening 19, but if the frame made of the left and right side plates 2c, 2d, the top plate 2es, and the bottom plate 2f are left, this can be used as the reinforcing bar 1a. It can also be used as an integral strength member.

さらに、必要とされる開口19が連続壁の1工レメント
以上にまたがる場合は、鋼製函体2は1エレメント毎に
分割して製作し、当該エレメントの鉄筋篭1の所定の位
置(エレメント相互の継手部側に寄せて)に組み込んで
、同様の工法で施工を行う。
Furthermore, if the required opening 19 spans more than one element of a continuous wall, the steel box 2 is manufactured by dividing it into each element, and the steel box 2 is manufactured in a predetermined position of the reinforcing bar cage 1 of the element (element mutually). (Move it to the joint side) and perform construction using the same method.

また、鋼製函体2の長さがエレメントの長さと同じか若
しくは長くて、コンクリート12の回り込み等に支障が
出ることが懸念される場合には、コンクリート打設用の
トレミー管挿入用の貫通孔を例えば該トレミー管の外径
より大きい内径の鋼管等を用いて函体2に形成し、この
貫通孔にトレミー管11を貫通させてコンクリート12
を打設するようにすればよい。
In addition, if the length of the steel box 2 is the same as or longer than the length of the element, and there is a concern that it may hinder the wrapping of the concrete 12, a through-hole for inserting a tremie pipe for concrete pouring may be used. A hole is formed in the box 2 using, for example, a steel pipe with an inner diameter larger than the outer diameter of the tremie tube, and the tremie tube 11 is passed through the through hole to form the concrete 12.
All you have to do is pour the concrete.

ところで、鋼製函体2が内部に砂又は砕石14を投入せ
ずに安定液lOのみを充満させた状態で浮力に対抗でき
る場合には、この鋼製函体2の上部開口5にも下部開口
6と同様に綱体やシート等で塞ぎ、コンクリート12の
流入を防止するとともに第6図〜第8図で示した砕石投
入管13での砂又は砕石14の投入工程を省略すること
も可能である。
By the way, if the steel case 2 can resist buoyancy by filling only the stabilizing liquid 1O without putting sand or crushed stone 14 inside, the upper opening 5 of the steel case 2 also has a lower part. It is also possible to block the opening 6 with a rope, sheet, etc. to prevent the concrete 12 from flowing in, and to omit the step of introducing sand or crushed stone 14 using the crushed stone input pipe 13 shown in FIGS. 6 to 8. It is.

〔発明の効果〕〔Effect of the invention〕

以上述べたように本発明の地中連続壁の開口部形成工法
は、例え−ば地中連続壁をトンネル施工における発進坑
、到達坑として利用し、この地中連続壁にシールド掘進
機等が通過する開口を設けなければならない場合などに
、厚さ方向に貫通する開口を簡単かつ迅速に形成するこ
とができ、地中連続壁の信頬性を低下させるおそれもな
く、トンネル施工における工費も安価ですむものである
As described above, the method for forming an opening in an underground continuous wall of the present invention uses, for example, the underground continuous wall as a starting hole and a reaching hole in tunnel construction, and a shield tunneling machine or the like is installed in this underground continuous wall. When it is necessary to create an opening to pass through, it is possible to easily and quickly form an opening that penetrates through the thickness, there is no risk of reducing the reliability of the underground continuous wall, and the construction cost for tunnel construction is also reduced. It is inexpensive.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法に使用する鉄筋篭の1例を示す斜視
図、第2図はこの鉄筋を溝内にセットした状態の縦断正
面図、第3図は同上縦断側面図、第4図〜第11図は本
発明工法の各工程を示すもので、第4図〜第9図は縦断
正面図、第10図、第11図は縦断側面図である。 1・・・鉄筋篭 2・・・鋼製函体 2b・・・後面板 2e・・・上面板 3・・・補強リブ 5・・・上部開口 ア・・・網体 9・・・溝 11・・・トレミー管 13・・・枠板投入管 15・・・地中連続壁 17・・・立坑 19・・・開口 1a・・・鉄筋 2a・・・前面板 2c、2d・・・左右側面板 2r・・・下面板 4・・・接続用フランジ 6・・・下部開口 8・・・掘削機 lO・・・安定液 12・・・コンクリート 14・・・砂又は砕石 16・・・隣接エレメント 1日・・・補強 第1図
Fig. 1 is a perspective view showing an example of a reinforcing bar basket used in the construction method of the present invention, Fig. 2 is a longitudinal sectional front view of the reinforcing bars set in a groove, Fig. 3 is a longitudinal sectional side view of the same, and Fig. 4. - Fig. 11 show each step of the construction method of the present invention, Fig. 4 - Fig. 9 are longitudinal sectional front views, and Fig. 10 and Fig. 11 are longitudinal sectional side views. 1... Rebar cage 2... Steel case 2b... Rear plate 2e... Top plate 3... Reinforcement rib 5... Upper opening a... Net body 9... Groove 11 ... Tremy pipe 13 ... Frame plate input pipe 15 ... Underground continuous wall 17 ... Vertical shaft 19 ... Opening 1a ... Reinforcing bars 2a ... Front plate 2c, 2d ... Left and right sides Face plate 2r... Bottom plate 4... Connection flange 6... Lower opening 8... Excavator lO... Stabilizing liquid 12... Concrete 14... Sand or crushed stone 16... Adjacent element 1st...Reinforcement Figure 1

Claims (1)

【特許請求の範囲】[Claims] 連続壁用溝を掘削して、該溝内に取り壊し撤去部分に相
当する大きさの鋼製函体を所定位置に組み込んだ鉄筋篭
を挿入し、その後溝内にコンクリートを打設して地中連
続壁を形成し、完成した地中連続壁の内側部分を掘削し
た後、鋼製函体部分をくり抜いて開口を形成することを
特徴とする地中連続壁の開口部形成工法。
A trench for the continuous wall is excavated, a reinforcing bar cage with a steel box of a size equivalent to the part to be demolished and removed is inserted into the trench, and then concrete is poured into the trench and the construction is carried out underground. A construction method for forming an opening in an underground continuous wall, which is characterized by forming a continuous wall, excavating the inner part of the completed underground continuous wall, and then hollowing out a steel box part to form an opening.
JP24177688A 1988-09-27 1988-09-27 Forming method for opening portion of underground continuous wall Pending JPH0291314A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24177688A JPH0291314A (en) 1988-09-27 1988-09-27 Forming method for opening portion of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24177688A JPH0291314A (en) 1988-09-27 1988-09-27 Forming method for opening portion of underground continuous wall

Publications (1)

Publication Number Publication Date
JPH0291314A true JPH0291314A (en) 1990-03-30

Family

ID=17079355

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24177688A Pending JPH0291314A (en) 1988-09-27 1988-09-27 Forming method for opening portion of underground continuous wall

Country Status (1)

Country Link
JP (1) JPH0291314A (en)

Similar Documents

Publication Publication Date Title
JPH04357293A (en) Flexible pipe and executing method thereof
JPH0291314A (en) Forming method for opening portion of underground continuous wall
JP3116253B2 (en) How to build a continuous underground wall
JPS5829922A (en) Constructing method for underground outer wall
JP3008804B2 (en) Joint structure in underground diaphragm wall
JP2001182477A (en) Device of partition iron plate
JP2001173135A (en) Underground exterior wall of structure and method of construction thereof
JP3091859B2 (en) Piling method for shafts with openings at the top
JP2001040681A (en) Underground exterior wall for structure and construction method therefor
JP3008803B2 (en) Jointing method of vertical joint in underground continuous wall
CN113833018B (en) Existing line reconstruction method
JP2000130070A (en) Construction method for vertical shaft for shield
JP2650539B2 (en) Construction method of underground diaphragm wall
JPH073777A (en) Method for constructing self-supporting land slide protection wall
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JP3245260B2 (en) Foundation structure and construction method
KR100441966B1 (en) Applying Method of Casing as the Concrete Filled Tube
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPH09137693A (en) Method for making shield machine arrive
JPS61257529A (en) Underground continuous wall construction work
JP3292824B2 (en) Burial method of pipe
JP2934932B2 (en) Structure of the reaching shaft and method of reaching the shield machine
JPH0343518A (en) Continuous underground wall having enlarged bottom
JPH10121465A (en) Continuos underground wall engineering method
JPH093896A (en) Underwater concrete placing machine