JPH0261209A - Method and apparatus for erecting mail cable for suspension bridge or the like - Google Patents

Method and apparatus for erecting mail cable for suspension bridge or the like

Info

Publication number
JPH0261209A
JPH0261209A JP21339688A JP21339688A JPH0261209A JP H0261209 A JPH0261209 A JP H0261209A JP 21339688 A JP21339688 A JP 21339688A JP 21339688 A JP21339688 A JP 21339688A JP H0261209 A JPH0261209 A JP H0261209A
Authority
JP
Japan
Prior art keywords
line
pull
strand
rollers
transfer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21339688A
Other languages
Japanese (ja)
Inventor
Shunichi Kuwamoto
桑本 俊一
Kenichi Sugii
謙一 杉井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP21339688A priority Critical patent/JPH0261209A/en
Publication of JPH0261209A publication Critical patent/JPH0261209A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To make it possible to start work for temporary pulling on a transfer line by laterally transferring main cable's strand, drawn out on a draw-out line after completion of the drawing out, to transfer rollers provided on a transfer line that is placed on the top of a tower in parallel with the draw-out line. CONSTITUTION:After drawing out a strand 1 along each of draw-out rollers 10 of a draw-out line 11, slack of the drawn-out strand 1 is pulled in. then a supporting frame 21 is lifted up by operation of a lift cylinder 23 and through rise of a jack rod 24, and the drawn-out strand 1 is made afloat over the rollers 10 under free-hanging condition along the whole span of its extension. The drawn-out strand is then transferred horizontally to the side of a transfer line 20 by operation of a travelling cylinder 25. After rollers 11 and 19 are placed levelling each other, the supporting frame 21 is lowered and the strand 1, stretching over each of the draw-out rollers 10, is transferred to ride on each of the transfer rollers 19 of the transfer line 20. Therefore, it becomes possible to start, on the transfer line 20, works for temporary pulling that follow fitting of the temporary pulling clamps.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、長大スパン吊橋を始めとして、パラレルワイ
ヤストランド(平行線ケーブル)を用いて吊橋等の架設
を行なうに当り、そのメインケーブルストランドの架設
のための引出し作業を、引出しラインを連続的に使用可
能とすることにより、より高能率な架設作業の進行を可
能としたものに係る。
[Detailed Description of the Invention] (Industrial Application Field) The present invention is applicable to the construction of suspension bridges, etc., using parallel wire strands (parallel wire cables), including long-span suspension bridges. The present invention relates to a system that enables the construction work to proceed more efficiently by making it possible to use a drawer line continuously for the work of pulling out the construction.

(従来の技術) 鋼索線の多数を平行に並べ、かつ所要断面形状に密に集
束させた処のパラレルワイヤストランドをメインケーブ
ルとして用い、二架設地点間に配設される主塔に亘って
架設し、各種の吊橋を得ることはいうまでもなく既知で
あり、例えば特公昭60−6408号公報、特公昭60
−23202号公報を始めとして各種の技術が開発、提
示されている。ここでは前記メインケーブルを構成する
個々のストランドを、二架設地点間に亘って配設される
各主塔、および各主塔間に設置されるキャツトウオーク
(吊足場)に亘って構成された引出しローラ群による引
出しライン上に引出し架設する処の、ストランドの引出
し作業について従来技術の概要を、第10図乃至第12
図に亘って説示する。
(Prior art) A parallel wire strand in which a large number of steel cables are lined up in parallel and tightly focused into a desired cross-sectional shape is used as the main cable, and is constructed across a main tower located between two construction points. Needless to say, it is known that various suspension bridges can be obtained; for example, Japanese Patent Publication No. 60-6408, Japanese Patent Publication No. 60-60
Various techniques have been developed and presented, including JP-A-23202. Here, the individual strands constituting the main cable are connected to each main tower installed between two installation points, and to a catwalk (hanging scaffold) installed between each main tower. 10 to 12 show an overview of the conventional technology for drawing out the strand when the drawer is installed on the drawing line using a group of rollers.
This will be explained with reference to the figures.

第10図および第11図において例示されるように、メ
インケーブルを構成する個々のストランド1の、二架設
地点間に亘る架設に当っては、架設地点間に所要数の主
塔2を列設するとともに、各主塔2間にキャツトウオー
ク (吊足場)3を設置し、片側の橋台部にストランド
送出機(アンリーラ)4を設置し、これにストランド1
を巻いたリールを取付け、トラムウェイサポートロープ
5、複数のホーリングロープ6A、6Bおよびホーリン
グロープ駆動ウィンチ7.8等によって構成される既知
の架空索道(ホーリングシステムと呼ばれる)における
前記ホーリングロープ6に、移動可能に取付けられたキ
ャリヤ9にストランド1の一端を連結し、ホーリングロ
ープの移動、これに伴うキャリヤ9の、第11図矢印方
向に示す引出し方向への移動を介し、各主塔2およびキ
ャツトウオーク3に亘ってストランド1を逐次引出して
架設するのである。
As illustrated in FIGS. 10 and 11, when installing the individual strands 1 constituting the main cable between two installation points, the required number of main towers 2 are installed in a row between the installation points. At the same time, a catwalk (hanging scaffold) 3 is installed between each main tower 2, and a strand feeder (unleela) 4 is installed on one side of the bridge abutment, to which the strand 1 is installed.
Attach a reel wound with a tramway support rope 5, a plurality of hauling ropes 6A, 6B, a hauling rope drive winch 7.8, etc. to the hauling rope 6 in a known aerial cableway (referred to as a hauling system), One end of the strand 1 is connected to a movably mounted carrier 9, and each main tower 2 and cat The strand 1 is successively pulled out over the walk 3 to construct the structure.

このさい各主塔2およびキャツトウオーク3には多数の
引出しローラ10群が列設され、引出されたストランド
1はこの各引出しローラ10上に亘って支承されるので
あり、これら各引出しローラ10群によって引出しライ
ン11が架設全長に亘って構成されるのである。今この
引出し作業を作動順に列記すれば次の通りである。
At this time, a large number of groups of 10 pull-out rollers are arranged in each main tower 2 and catwalk 3, and the drawn strand 1 is supported on each of these 10 pull-out rollers. Accordingly, the extraction line 11 is constructed over the entire length of the construction. This drawing operation is listed in the order of operation as follows.

■ ストランド送出機(アンリーラ)にストランドリー
ルをセットする。
■ Set the strand reel on the strand feeder (unreeler).

■ ストランド1の一端であるソケット12をホーリン
グ6側に保持されるキャリヤ9に取付ける。
■ Attach the socket 12, which is one end of the strand 1, to the carrier 9 held on the hole ring 6 side.

■ ホーリングロープ6A、6B以下のホーリングシス
テムを駆動してストランド1の引出しを開始する。
- Start pulling out the strand 1 by driving the hauling system for the hauling ropes 6A and 6B.

■ 引出されたストランド1は、キャツトウオーク3お
よび各主塔2に亘って、列設した引出しローラ10群に
よる引出しライン11に沿って、各ローラ10上に支承
させる。
(2) The drawn strand 1 is supported on each roller 10 along a drawing line 11 formed by a group of 10 drawing rollers arranged in a row over the cat walk 3 and each main tower 2.

■ 所要長のストランド1の引出しが終了すれば、キャ
リヤ9をストランドリール側にバックさせる。
- When the drawing of the strand 1 of the required length is completed, the carrier 9 is moved back to the strand reel side.

■ キャリヤ9が次の引出しのために、ホーリングロー
プ6を介してリール側にバックする間に、各主塔2にお
ける各塔頂サドル付近、スプレーサドル付近では、スト
ランド1に対し、第12図に例示するように、引出しラ
インll上においてストランド1に仮引クランプ13を
取付ける。
■ While the carrier 9 moves back to the reel side via the hauling rope 6 for the next draw, near each tower top saddle and spray saddle in each main tower 2, the strand 1 is As illustrated, a temporary tension clamp 13 is attached to the strand 1 on the drawing line ll.

■ 次いで塔頂側に設置した油圧式仮引装置1.4によ
りストランド1を仮引し、引出しライン11の引出しロ
ール10上からストランド1を浮かせ、サドル上に移動
させる。
(2) Next, the strand 1 is temporarily pulled by a hydraulic temporary pulling device 1.4 installed at the top of the tower, and the strand 1 is lifted from above the drawer roll 10 of the drawer line 11 and moved onto the saddle.

■ 各サドル部においてストランド1を整形し、これを
サドル内に納める仮引処理を行なうのであり、15は移
設フレーム、16は仮引ロープを示し、この仮引処理は
いうまでもな(既知のものである。
■ At each saddle part, the strand 1 is shaped and a temporary pulling process is carried out to store it in the saddle. Reference numeral 15 indicates a relocation frame and 16 indicates a temporary pulling rope. It is something.

(発明が解決しようとする課題) 上記したメインケーブル用ストランド1の引出しライン
上に沿っての引出し並び塔頂部において、キャリヤ9の
バック中に各サドル部でストランド1の仮引、整形、移
設を行なう方式は、次の点において問題点がある。即ち
、最近の長大吊橋においては、1本のストランドを引出
した後、ストランド用キャリヤをバックさせるために生
じるロスタイムをなくシ2、高能率なストランド引出し
を行なうために、架設地点の両側にストランド送出機(
アンリーラ)を設置し、キャリヤバックなしで、交互に
ストランドを架設することが考えられているのであるが
、この場合、引出しライン11を構成する引出しローラ
10上に亘り、ストランド1が乗ったままの状態で、収
用クランプ13の取付けや、収用準備を行なうことは、
それだけ引出しライン11の占有時間が長くなり、同ラ
イン11の各引出しローラ10が空かない限り、次の新
しいストランドの引出しは不可能であるため、より高能
率なストランド1の連続的な引出し作業は困難である点
において、解決すべき問題点が存在するのである。
(Problem to be Solved by the Invention) At the top of the tower where the drawers are lined up along the draw-out line of the main cable strand 1 described above, the strand 1 is temporarily drawn, shaped, and relocated at each saddle portion while the carrier 9 is backing up. This method has the following problems. In other words, in recent long suspension bridges, in order to eliminate the loss time caused by backing up the strand carrier after pulling out one strand, and to perform highly efficient strand pulling out, the strands are sent out on both sides of the construction point. Machine (
It has been considered that the strands are laid alternately without a carrier bag by installing an unreeler (unreeler). Attaching the expropriation clamp 13 or making preparations for expropriation in
This increases the occupation time of the drawing line 11, and it is impossible to draw out the next new strand unless each drawing roller 10 on the same line 11 is empty. Therefore, continuous drawing of the strand 1 with higher efficiency is To the extent that it is difficult, there are problems to be solved.

(課題を解決するための手段) 本発明は上記の問題点を解決するために、メインケーブ
ル用ストランドの引出し完了後、引出しラインに引出さ
れたストランドを、塔頂部において引出ラインと平行に
列設した移設ラインにおける移設ローラ上に横移動させ
ることにより、引出しラインを速やかに空け、これによ
って移設ライン上において収用処理を行なうとともに、
空けられた引出しライン上に直ちにストランドの引出し
可能としたものであり、具体的には、二架設地点間に配
設される塔および各塔間に配置されるキャツトウオーク
の両者に亘って列設される引出しローラ群による引出し
ライン上に、移動可能なホーリングロープに保持される
キャリヤに連結したメインケーブル用ストランドを、前
記キャリヤの移動を介して一方向に引出し、所定長の引
出し完了とともに、引出しライン上に亘って引出された
前記ストランドを、引出しラインと平行して列設した複
数の移設ローラによる移設ライン上に、前記引出しライ
ンの引出しローラまたは移設ラインの移設ローラの垂直
昇降および水平移動を介して、移設ラインの移設ローラ
上に亘って移動さ一ヒることにより引出しラインを空け
、移設ライン上に移動されたストランドの収用処理を行
なうとともに、空けられた引出しライン上に新しいスト
ランドの引出しを続行することにあり、更には、前記方
法を実施する装置として、二架設地点間に配設される各
塔頂部において、塔頂サドルと近接する複数個の引出し
ローラを定間隔に列設するとともに、これと平行して移
設ラインに属する複数個の移設ローラを同じ(定間隔に
かつ引出しローラと位置を相違して列設し、引出しライ
ンにおける各引出しローラまたは移設ラインにおける各
移設ローラの何れかを、相手方ローラに対して垂直昇降
および水平移動可能に設けることにある。
(Means for Solving the Problems) In order to solve the above-mentioned problems, the present invention aims to arrange the strands drawn out to the drawing line in parallel to the drawing line at the top of the tower after the drawing of the main cable strands is completed. By moving it laterally onto the relocation roller on the relocation line, the extraction line is quickly vacated, and the expropriation process is carried out on the relocation line.
Strands can be drawn out immediately on the vacant draw-out line, and specifically, strands can be drawn out in a row across both the towers placed between two erection points and the catwalks placed between each tower. A main cable strand connected to a carrier held by a movable hauling rope is pulled out in one direction on a pull-out line by a group of pull-out rollers through the movement of the carrier, and when the predetermined length of pull-out is completed, the pull-out The strand drawn out over the line is moved vertically and horizontally by a plurality of transfer rollers arranged in parallel with the pull-out line onto the transfer line, and the pull-out roller of the draw-out line or the transfer roller of the transfer line is moved vertically and horizontally. The strand is moved over the relocation roller of the relocation line through the relocation line to vacate the withdrawal line, and the strand moved onto the relocation line is expropriated, and a new strand is withdrawn onto the vacated withdrawal line. Furthermore, as a device for carrying out the above method, a plurality of pull-out rollers are arranged in a row at regular intervals in the vicinity of the tower top saddle at the top of each tower disposed between two erection points. In parallel with this, a plurality of transfer rollers belonging to the transfer line are arranged in the same row (at regular intervals and in different positions from the pull-out rollers, and each pull-out roller in the pull-out line or each transfer roller in the transfer line is The purpose of the present invention is to provide a roller that can be vertically raised and lowered and horizontally moved relative to the other roller.

(作 用) 本発明の上記した技術的手段によれば、第1a図および
第1b図において、先に第10.11図に説示したと同
様の従来手法によってメインケーブル用のストランド1
を、引出しローラ10群の列設による引出しライン11
に沿って引出した後、第1a図に示すようにストランド
1の両端における各ソケット部12を、例えばウィンチ
(図示省略)等を用いて引き込み、引出し時に生じるス
トランド1のたるみを、第1b図に示すように除去して
緊張状態として後、第3図乃至第5図に亘って例示する
ように各主塔2における塔頂サドル17を有する頂部1
8において、定間隔に列設される従来の引出しローラ1
0の複数個による引出しライン11の他に、同じく定間
隔にかつ引出しライン11の引出しローラ10の各中間
に位置して配設される複数個の移設ローラ19による移
設ライン20を、引出しライン11平行に設け、回倒で
は引出しライン11における各引出しローラ10を共通
の保持架構21により保持し、かつこの保持架構21を
頂部18上において台車22を介し走行移動可能に設け
た昇降用シリンダ23のジヤツキロッド24に連結し、
また走行用シリンダ25の移動ロッド26を台車22に
連結することによって、第1a図のように引出しライン
1工の各引出しローラ10に沿ってストランド1を引出
して後、第1b図に示すように引出したストランド1の
たるみを除去し、第3.4図に示すように保持架構21
を昇降用シリンダ23の駆動、ジヤツキロッド24の上
昇を介し上昇させ、各引出しローラ10の上昇を介して
引出したストランド1を、その引出全長に亘ってフリー
ハング状に各引出しローラ10から浮かせて後、走行用
シリンダ25を駆動し、その移動ロンド26の移動を介
し移設ライン20側に水平横移動させ、各ローラ11,
19を同列状態として保持架構21を下降させることに
より、各引出しローラ10上に亘るストランド1を、移
設ライン20における各移設ローラ19上に移乗させる
のである。かくして引出しライン11を旧位に復動させ
ることにより、同ライン11における引出しローラ10
は空けられた状態となり、従って移設ライン20上にお
いて、移動させたストランド1aに対し、収用クランプ
の取付以下の飯田処理を開始するとともに、空けられた
引出しラインll上には新しいストランド1の引出しを
直ちに続行することが可能となるのであり、これによっ
て例えば二架設地点の両側にストランド送出機(アンリ
ーラ)を設置し、キャリヤバックなしに交互にストラン
ド1を引出し架設するプログラムも可能となるのである
(Function) According to the above-mentioned technical means of the present invention, in FIGS. 1a and 1b, the strand 1 for the main cable is prepared by the same conventional method as previously illustrated in FIG.
A pull-out line 11 is formed by arranging 10 groups of pull-out rollers.
After pulling out the sockets 12 at both ends of the strand 1 using, for example, a winch (not shown) as shown in FIG. After removal and tensioning as shown, the top section 1 with the top saddle 17 in each main tower 2 is removed as illustrated in FIGS. 3 to 5.
8, conventional pull-out rollers 1 are arranged in a row at regular intervals.
In addition to the pull-out line 11 made up of a plurality of rollers 10, a transfer line 20 made up of a plurality of transfer rollers 19 disposed at regular intervals and located between each of the pull-out rollers 10 of the pull-out line 11 is added to the pull-out line 11. The elevating cylinders 23 are arranged in parallel and each of the drawer rollers 10 in the drawer line 11 is held by a common holding frame 21 during rotation, and the holding frame 21 is movable on the top 18 via a cart 22. Connected to jack rod 24,
Furthermore, by connecting the moving rod 26 of the traveling cylinder 25 to the trolley 22, the strand 1 is pulled out along each drawing roller 10 of the drawing line 1 as shown in Fig. 1a, and then as shown in Fig. 1b. Remove the slack in the pulled out strand 1, and attach it to the holding frame 21 as shown in Figure 3.4.
The strand 1 is raised by driving the lifting cylinder 23 and raising the jack rod 24, and the strand 1 drawn out by raising each drawing roller 10 is floated from each drawing roller 10 in a free-hanging manner over the entire length of the drawer. , drives the traveling cylinder 25 and horizontally moves it to the transfer line 20 side through the movement of the moving iron 26, and each roller 11,
By lowering the holding frame 21 with the rollers 19 in the same line, the strand 1 extending over each pull-out roller 10 is transferred onto each transfer roller 19 in the transfer line 20. By thus returning the drawing line 11 to its previous position, the drawing roller 10 on the same line 11
is now in an empty state, and therefore, on the relocation line 20, the Iida process starting with the installation of the expropriation clamp is started for the moved strand 1a, and at the same time, a new strand 1 is drawn out on the empty drawing line ll. This makes it possible to continue immediately, and this makes it possible, for example, to install a strand unreeler on both sides of the two installation points, and to program a program in which the strands 1 are alternately pulled out and installed without a carrier bag.

(実施例) 本発明による架設方法および装置の適切な実施例を第1
a図以下第8図に亘って、平行的に説示する。
(Example) A suitable example of the erection method and device according to the present invention will be described below.
The explanation will be made in parallel from Figure A to Figure 8.

第1a図、第1b図および第2図において、第1a図は
二架設地点間における各主塔2および各主塔2間に亘っ
て設置されるキャリヤウオーク(吊足場)3に亘って形
成される引出しライン11上に、メインケーブル用スト
ランド1を、第9図において説示した従来手法により引
出した状態を示しており、引出しライン11における引
出しローラ10は、第3図において例示するように既知
の略鼓形ローラを用い、キャツトウオーク3の全長、各
主塔2の頂部18において、所要間隔下に多数の引出し
ロー910群が列設されてライン11を構成することに
なる。第2図は二架設地点の片側における橋台部27の
構造を例示したものであって、第9.10および第1図
に示したと同一符号は同一部材を示しており、引出しラ
イン11に対し、後述するように各主塔2の塔頂に設置
された移設ライン20に吊持されるストランド1のフリ
ーハング状態におけるライン高さは、若干高くなる。同
図において28は橋台クレーン、29はリール交換クレ
ーン、また30はホーリングロープ6の一端側のプラー
を示し、これらは何れも既知構造のものに属する。
In Figures 1a, 1b, and 2, Figure 1a is formed across each main tower 2 between two erection points and a carrier walk (hanging scaffold) 3 installed between each main tower 2. The main cable strand 1 is shown pulled out on the pull-out line 11 by the conventional method illustrated in FIG. Using approximately drum-shaped rollers, a large number of drawer rows 910 are arranged in rows at required intervals along the entire length of the catwalk 3 and at the top 18 of each main tower 2 to form a line 11. FIG. 2 illustrates the structure of the abutment section 27 on one side of the two erection points, and the same reference numerals as shown in FIG. 9.10 and FIG. 1 indicate the same members. As will be described later, the line height of the strand 1 suspended from the relocation line 20 installed at the top of each main tower 2 in a free-hanging state is slightly higher. In the figure, 28 is an abutment crane, 29 is a reel exchange crane, and 30 is a puller at one end of the hauling rope 6, all of which belong to known structures.

第1a図に示すようにキャリヤ9によって引出されたス
トランド1は、全長に亘ってたるみを生じているので、
第1b図に示すように引出されたストランド1の両端に
おけるソケット12.12を、図示省略しであるが既設
のウィンチ等を利用して、それぞれ第1b図矢印方向に
引込み、そのたるみを除去して、移設時に支障を生じな
いようにして置くのである。
As shown in FIG. 1a, the strand 1 pulled out by the carrier 9 has slack over its entire length.
As shown in Fig. 1b, the sockets 12 and 12 at both ends of the pulled out strand 1 are pulled in in the direction of the arrow in Fig. 1b using an existing winch (not shown) to remove the slack. They are placed in such a way that they do not cause any problems during relocation.

第3図乃至第5図に亘って示して実施例は、引出しライ
ン11における各塔頂側の引出しローラ10を、移設ラ
イン20の移設ローラ19に対し可動として、ストラン
ド1の水平横移動による移設を行なうようにしたもので
あり、図示のように塔頂サドル17の設けられる主塔2
の頂部18において、複数個の引出しローラ10を、共
通の保持架構21上に定間隔に列設したブラケット21
a上に引出しローラ10をそれぞれ軸架させ、保持架構
21の全体を、園側では2個の昇降用シリンダ(油圧)
23における加圧昇降可能なジヤツキロッド24によっ
てそれぞれ同期昇降可能に保持し、更にこの昇降用シリ
ンダ23.23の設置され、かつガイドレール31に架
装される車輪32を具備した台車22に、同じく頂部1
8上に設置した走行用シリンダ(油圧)25の移動ロッ
ド26を連結して、保持架構21を塔頂サドル17の側
面に向って進退移動可能としたものである。但しこの垂
直昇降および水平移動機構は園側のみに限定されない。
In the embodiment shown in FIGS. 3 to 5, the pull-out rollers 10 on the top side of each tower in the pull-out line 11 are movable relative to the transfer rollers 19 of the transfer line 20, and the strand 1 is transferred by horizontal lateral movement. As shown in the figure, the main tower 2 is equipped with a tower top saddle 17.
At the top 18 of the bracket 21, a plurality of pull-out rollers 10 are arranged in rows at regular intervals on a common holding frame 21.
The pull-out rollers 10 are each mounted on a shaft, and the entire holding frame 21 is supported by two lifting cylinders (hydraulic) on the nursery school side.
The carriage 22 is held so as to be raised and lowered synchronously by a jack rod 24 that can be raised and lowered under pressure at 23, and is equipped with wheels 32 on which the raising and lowering cylinders 23 and 23 are installed and mounted on a guide rail 31. 1
A moving rod 26 of a traveling cylinder (hydraulic) 25 installed on the tower 8 is connected to enable the holding frame 21 to move forward and backward toward the side surface of the tower top saddle 17. However, this vertical lifting and horizontal movement mechanism is not limited to the kindergarten side.

この引出しローラ10による引出しライン11と平行し
て設ける移設ライン20においては、実施例では塔頂サ
ドル17の側面にブラケット33を介して列設される既
知のサドル脇ローラを移設ローラ19として用いるので
あり、同ローラ19は図示のように各ブラケット33に
よって、引出しローラ10.10の各中間位置に定間隔
に列設され、これによって平行する固定の移設ライン2
0が構成されるのである。このさい移設ローラ19の設
置数によっては、第4図に例示するように、塔頂サドル
17外にもブラケット34を介して移設ローラ19を設
けることもできる。この実施例によれば、先に作用の項
において述べた通り、キャツトウオーク3および主塔2
の全長に亘る引出しラインll上にストランド1を引出
して後、そのたるみを除去した緊張状態下に、保持架構
12の垂直昇降および水平横移動を介して、引出しライ
ン11上のストランド1を、第5図に示すように移設ラ
イン20の各移設ローラ19上に亘って移動させること
ができ、同図において1aは移設ライン20上に移動さ
れたストランドを示している。従ってこの移し変えとと
もに旧位に復した保持架構21上の各引出しライン11
に属する引出しローラ10は空けられることになる。
In the relocation line 20 provided parallel to the pull-out line 11 by the pull-out roller 10, known saddle side rollers arranged in a row on the side surface of the tower top saddle 17 via brackets 33 are used as the relocation rollers 19 in the embodiment. As shown in the figure, the rollers 19 are arranged in rows at regular intervals at intermediate positions of the pull-out rollers 10 and 10 by respective brackets 33, thereby creating parallel fixed transfer lines 2.
0 is constructed. At this time, depending on the number of transfer rollers 19 installed, transfer rollers 19 can also be provided outside the tower top saddle 17 via brackets 34, as illustrated in FIG. According to this embodiment, as described above in the function section, the catwalk 3 and the main tower 2
After drawing out the strand 1 on the drawing line 11 over the entire length of the drawing line 11, the strand 1 on the drawing line 11 is pulled out under tension by removing the slack by vertically lifting and horizontally moving the holding frame 12. As shown in FIG. 5, the strand can be moved over each transfer roller 19 of the transfer line 20, in which 1a indicates the strand that has been moved onto the transfer line 20. Therefore, with this transfer, each pullout line 11 on the holding frame 21 has been restored to its old position.
The pull-out roller 10 belonging to will be vacated.

従って同じく第5図に示すように、この空けられた引出
しライン11上には、次の新しいストランド1を直ちに
引出し架設することが可能である。
Therefore, as also shown in FIG. 5, it is possible to immediately draw out and install the next new strand 1 on this vacated drawing line 11.

一方移設ライン20の各移設ローラ19上のストランド
1aに対しては、収用クランプ13の取付け、収用、整
形、塔頂サドル17内への移設に終る収用作業を容易に
実施でき、同図において1bは俵用中のストランド1を
示している。
On the other hand, for the strands 1a on each transfer roller 19 of the transfer line 20, the removal work that ends with the attachment of the removal clamp 13, removal, shaping, and transfer into the tower top saddle 17 can be easily carried out, and in the figure, 1b indicates strand 1 during bale use.

第3図乃至第5図に示した実施例の説明で容易に推測さ
れるように、引出しライン11における引出しローラ1
0を、移設ライン20における移設ローラ19に対して
垂直昇降および水平横移動とする代りに、移設ライン2
0における移設ローラ19を、引出しライン11におけ
る引出しローラlOに対して垂直昇降および水平横移動
とすることによっても、同様の目的を達成できる。第6
図乃至第8図はその実施例を示している。この場合は図
示のように移設ライン20に属する各移設ローラ19を
、共通の保持架構21に列設保持させ、引出しライン1
1に属する各引出しローラ10は、何れも例えば塔頂サ
ドル17の側面に固設したブラケット33に列設すれば
よく、移設ライン20の保持架構21を走行用シリンダ
25および昇降用シリンダ23に連結して水平横移動お
よび垂直昇降可能とすればよい訳である。このさい第7
図に例示するように、必要に応じては引出しローラ10
を塔頂サドル17外に固定ブラケット34を介して増設
することも可能であり、第8図に例示する通り、第3図
乃至第5図実施例と全く同様の作用、効果が得られるこ
とはいうまでもないのである。何れの可動方式をとるか
は勿論自由である。また実施に当り、第1a図および第
1b図において示したストランド1のたるみを取ると同
時に、ストランド1をフリーハング状態としてもよい。
As can be easily guessed from the description of the embodiment shown in FIGS. 3 to 5, the drawing roller 1 in the drawing line 11
0 is vertically lifted and lowered and horizontally moved horizontally with respect to the transfer roller 19 in the transfer line 20.
The same purpose can also be achieved by vertically moving up and down and horizontally moving the transfer roller 19 at 0 in relation to the pull-out roller 10 in the pull-out line 11. 6th
Figures 8 through 8 show examples thereof. In this case, as shown in the figure, the transfer rollers 19 belonging to the transfer line 20 are arranged and held in a common holding frame 21, and the pull-out line 1
Each of the pull-out rollers 10 belonging to 1 may be arranged in a row on a bracket 33 fixed to the side surface of the tower top saddle 17, for example, and the holding frame 21 of the transfer line 20 is connected to the traveling cylinder 25 and the lifting cylinder 23. In other words, it is sufficient to enable horizontal movement and vertical movement. This time 7th
As illustrated in the figure, if necessary, the pull-out roller 10
It is also possible to add the bracket to the outside of the tower top saddle 17 via the fixing bracket 34, and as illustrated in FIG. 8, the same operation and effect as the embodiments in FIGS. Needless to say. Of course, you are free to choose which movable method to use. Further, in carrying out the invention, the slack of the strand 1 shown in FIGS. 1a and 1b may be taken up, and at the same time, the strand 1 may be placed in a free-hanging state.

なお、本発明は第9図に示す側塔2Aを有するものにも
適用可能であり、この場合には、側塔2Aの頂部に、前
述の引き出しローラ等を有する。
Note that the present invention is also applicable to a device having a side tower 2A shown in FIG. 9, and in this case, the above-mentioned pull-out roller and the like are provided at the top of the side tower 2A.

(発明の効果) 本発明によれば、従来のメインケーブル用ストランドの
架設に当り、引出しラインに沿って引出しが完了したス
トランドを、直ちに同ラインと平行して設けた移設ライ
ンに横移動させ、収用クランプの取付以下のストランド
に対する収用、整形、移設に至る一連の収用処理を、移
設ライン上において行なうことにより、従来のようにキ
ャリヤパックの間に引出しライン上において収用、整形
、移設を行なうため、引出しラインを長時間に亘って占
有し、この収用処理が完了するまで、同引出しラインに
対する引出し架設を不可能とする不合理をなくし、常に
引出しラインを空けることができるので、そのストラン
ドの引出し架設を、はとんどロスタイムなく連続的に実
施できる点において著しく有利であり、ストランド架設
のスピードアップが図れるのである。このさい引出しラ
イン上のストランド1を移動させるための移設ラインを
、各主塔における塔頂において、従来の引出しラインと
平行して移設ラインを構成し、引出しラインまたは移設
ラインにおける何れかのローラ群を、相手方ローラ群に
対して垂直昇降および水平移動可能な可動構造とするこ
とにより、ストランドの横移動は円滑かつ確実に得られ
、各主塔頂部におけるストランドのフリーハング姿勢に
より、架設引出しの全長に亘って確実にストランドをロ
ール上に浮かせられ、その操作は迅速かつ容易化され、
これによって方法としても、又装置としても、簡単な手
段のみで足りるのであり、二架設地点の両側にストラン
ド送出機(アンリーラ)を設置し、キャリヤバック手段
を省略して両側から交互にストランドの連続引出し架設
プログラムも実行可能となるもので、特にパラレルワイ
ヤストランドケーブルのように、多数のストランドを集
合してメインケーブルとする長大吊橋等の架設に当リ、
ストランドの引出し架設作業を高能率下に進行させる点
は著しく有利である。
(Effects of the Invention) According to the present invention, when constructing a conventional main cable strand, the strand that has been completely drawn out along the drawing line is immediately moved laterally to a relocation line provided parallel to the drawing line, By performing a series of expropriation processing for the strands below the attachment of the expropriation clamp on the relocation line, it is possible to perform expropriation, shaping, and relocation on the drawer line between the carrier packs as in the past. This eliminates the unreasonable situation of occupying a drawer line for a long time and making it impossible to construct a drawer on the same drawer line until the expropriation process is completed. It is extremely advantageous in that the erection can be carried out continuously with almost no loss time, and the speed of strand erection can be increased. At this time, a transfer line for moving the strand 1 on the draw-out line is configured at the top of each main tower in parallel with the conventional draw-out line, and any roller group on the draw-out line or transfer line is configured. By making it a movable structure that can move up and down vertically and horizontally relative to the other roller group, the lateral movement of the strand can be achieved smoothly and reliably, and the free-hanging posture of the strand at the top of each main tower allows for The strand can be reliably suspended on the roll over a period of time, making the operation quick and easy.
As a result, only a simple method and device is required, and a strand feeder (unreeler) is installed on both sides of the two erection points, and the carrier back means is omitted and the strands are continuously fed alternately from both sides. It is also possible to execute a drawer construction program, which is especially useful when constructing long suspension bridges where many strands are assembled as the main cable, such as parallel wire strand cables.
It is extremely advantageous that the strand drawer erection work can proceed with high efficiency.

【図面の簡単な説明】[Brief explanation of the drawing]

第1a図および第1b図は本発明ストランドの引出架設
におけるたるみ取り作業を示す説明図、第2図は従来の
架設装置における橋台要部の正面図、第3図は本発明方
法実施例並びに装置実施例の側面図、第4図は同正面図
、第5図は同全体の作動状態を示す斜面図、第6図は開
割実施例の方法および装置を示す側面図、第7図は同正
面図、第8図は同全体の作動状態を示す斜面図、第9図
は側塔を有する本発明実施例の説明図、第1θ図は従来
方法の架設状11硯明図、第11図は同ストランド引出
し状態説明図、第12図は同ストランド俵用状態説明図
である。 1−・−メインケーブル用ストランド、2−主塔、3−
キャツトウオーク、4・−ストランド送出機(アンリー
ラ) 、6− ホーリングロープ、7,8−・−駆動ウ
ィンチ、9−・−キャリヤ、10・−引出しローラ、1
1・−引出しライン、19−・移設ローラ、20・−移
設ライン、21−・保持架構、23・−・昇降用シリン
ダ、24−・−。 ジヤツキロッド、25・−走行用シリンダ、26−移動
ロッド。
Figures 1a and 1b are explanatory diagrams showing slack removal work during drawer erection of the strand of the present invention, Figure 2 is a front view of the main part of the abutment in a conventional erection device, and Figure 3 is an embodiment of the method and apparatus of the present invention. 4 is a front view of the embodiment, FIG. 5 is a perspective view showing the overall operating state, FIG. 6 is a side view showing the method and apparatus of the split embodiment, and FIG. 7 is the same. A front view, FIG. 8 is a perspective view showing the operating state of the whole, FIG. 9 is an explanatory diagram of an embodiment of the present invention having a side tower, FIG. 12 is an explanatory diagram of the strand drawn out state, and FIG. 12 is an explanatory diagram of the strand bale state. 1-・- Main cable strand, 2- Main tower, 3-
Cat walk, 4--Strand feeder (unreeler), 6--Hauling rope, 7, 8--Drive winch, 9--Carrier, 10--Pull-out roller, 1
DESCRIPTION OF SYMBOLS 1.-Drawer line, 19-.Relocation roller, 20.-Relocation line, 21-.Holding frame, 23.--Lifting cylinder, 24-.-. Jacket rod, 25--travel cylinder, 26- moving rod.

Claims (2)

【特許請求の範囲】[Claims] (1)二架設地点間に配設される主塔および各主塔間に
配置されるキャットウオークの両者に亘って列設される
引出しローラ群による引出しライン上に、移動可能にホ
ーリングロープに保持されキャリヤに連結したメインケ
ーブル用ストランドを、前記キャリヤの移動を介して一
方向に引出し、所定長の引出し完了とともに、引出しラ
イン上に亘って引出された前記ストランドを、引出しラ
インと平行して列設した複数の移設ローラによる移設ラ
イン上に、前記引出しラインの引出しローラまたは移設
ラインの移設ローラの垂直昇降および水平移動を介して
、移設ラインの移設ローラ上に亘って移動させることに
より引出しラインを空け、移設ライン上に移動されたス
トランドの仮引処理を行なうとともに、空けられた引出
しライン上に新しいストランドの引出しを続行すること
を特徴とする吊橋等のメインケーブル架設方法。
(1) Movably held on a hauling rope on a pull-out line by a group of pull-out rollers arranged across both the main tower placed between two erection points and the catwalk placed between each main tower. The main cable strand connected to the carrier is pulled out in one direction through the movement of the carrier, and when the predetermined length of drawing is completed, the strand that has been drawn out over the drawing line is lined up parallel to the drawing line. The pull-out line is moved over the transfer rollers of the transfer line by vertically raising and lowering and horizontally moving the pull-out rollers of the pull-out line or the transfer rollers of the transfer line. A method for constructing a main cable for a suspension bridge, etc., characterized by temporarily pulling out strands that have been moved onto a vacant or relocated line, and continuing to pull out new strands on the vacated pull-out line.
(2)二架設地点間に配設される各塔頂部において、塔
頂サドルと近接する付近に引出しラインに属する複数個
の引出しローラを定間隔に列設するとともに、これと平
行して移設ラインに属する複数個の移設ローラを同じく
定間隔にかつ引出しローラと位置を相違して列設し、引
出しラインにおける各引出しローラまたは移設ラインに
おける各移設ローラの何れかを、相手方ローラに対して
垂直昇降および水平移動可能に設けることを特徴とする
吊橋等のメインケーブル架設装置。
(2) At the top of each tower installed between two erection points, a plurality of pull-out rollers belonging to the pull-out line are arranged in a row at regular intervals near the tower top saddle, and a relocation line is placed in parallel with this. A plurality of transfer rollers belonging to the above are arranged in a row at the same regular intervals and in different positions from the pull-out rollers, and each pull-out roller in the pull-out line or each transfer roller in the transfer line is vertically raised and lowered relative to the other roller. and a main cable installation device for a suspension bridge, etc., which is provided so as to be horizontally movable.
JP21339688A 1988-08-26 1988-08-26 Method and apparatus for erecting mail cable for suspension bridge or the like Pending JPH0261209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21339688A JPH0261209A (en) 1988-08-26 1988-08-26 Method and apparatus for erecting mail cable for suspension bridge or the like

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21339688A JPH0261209A (en) 1988-08-26 1988-08-26 Method and apparatus for erecting mail cable for suspension bridge or the like

Publications (1)

Publication Number Publication Date
JPH0261209A true JPH0261209A (en) 1990-03-01

Family

ID=16638514

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21339688A Pending JPH0261209A (en) 1988-08-26 1988-08-26 Method and apparatus for erecting mail cable for suspension bridge or the like

Country Status (1)

Country Link
JP (1) JPH0261209A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100430511C (en) * 2005-06-30 2008-11-05 宝山钢铁股份有限公司 Cold rolled strip steel for shadow mask and its making process

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100430511C (en) * 2005-06-30 2008-11-05 宝山钢铁股份有限公司 Cold rolled strip steel for shadow mask and its making process

Similar Documents

Publication Publication Date Title
CN104278637A (en) No-catwalk cableway erecting method for main cable strands of suspension bridge
CN102587293B (en) System and method for cradle cantilever construction of variable-width section concrete girder
JP2894226B2 (en) Bridge construction method
CN211142840U (en) Suspension bridge main push-towing rope erects system
CN102587292B (en) System and method for cradle cantilever construction
JP4277281B2 (en) Hanging wire type transfer method by net formation
JPH10237821A (en) Device for carrying and installing suspension bridge cable band
CN211034762U (en) Cable winding and unwinding and hoisting integrated combined vehicle
JPH0261209A (en) Method and apparatus for erecting mail cable for suspension bridge or the like
CN210457285U (en) Device for quickly carrying car coupler
JPS5810522B2 (en) How to erect long objects in the air
CN110948676A (en) Prefab steel tensioning device
CN215482363U (en) Become width of cloth formula catwalk suitable for construction of single-column tower space cable suspension bridge
JPS5830963B2 (en) Method and device for transferring parallel cable strands to saddle
CN220246713U (en) Beret beam rapid dismantling system for railway protection shed tunnel adding project under limited space
JPH0419762B2 (en)
CN215887954U (en) Slide rail type auxiliary supporting device for front supporting leg of bridge girder erection machine
RU223746U1 (en) Crane-boom-two-legged for pulling out cars
CN209962541U (en) Device for lifting and horizontal moving of sand table model
CN217733799U (en) Steel-concrete composite beam cable-stayed bridge construction system
CN220825425U (en) Multi-track automatic conversion device for processing steel strand finished product bundles
JPH10194669A (en) Telpher crane moving device inside tunnel
CN101476297A (en) Hauling construction device and method for walking rails of bridge erection machine
SU1181032A1 (en) Method of laying cable on high support sheldes
SU1120080A1 (en) Method of moving a cradle when working at trunk pipelines