JPH0241608B2 - - Google Patents

Info

Publication number
JPH0241608B2
JPH0241608B2 JP18862384A JP18862384A JPH0241608B2 JP H0241608 B2 JPH0241608 B2 JP H0241608B2 JP 18862384 A JP18862384 A JP 18862384A JP 18862384 A JP18862384 A JP 18862384A JP H0241608 B2 JPH0241608 B2 JP H0241608B2
Authority
JP
Japan
Prior art keywords
hole
joint
formwork
slope
present
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP18862384A
Other languages
Japanese (ja)
Other versions
JPS6168927A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP18862384A priority Critical patent/JPS6168927A/en
Publication of JPS6168927A publication Critical patent/JPS6168927A/en
Publication of JPH0241608B2 publication Critical patent/JPH0241608B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】 本発明は、法面保護のために施工される法枠の
構築において透孔を有する孔管杭を打ち込んで型
枠材と同時に孔管杭内にコンクリート等を注入す
る法枠工における注入アンカー工法に係るもので
ある。
[Detailed description of the invention] The present invention involves driving a hole pipe pile having a through hole in constructing a slope frame constructed for slope protection, and pouring concrete, etc. into the hole pipe pile at the same time as formwork material. This is related to the injection anchor method in slope construction.

(従来の技術) 現在、法面保護のために各種の法枠材が使用さ
れており、その斜面上での固定には鋼製の棒状ア
ンカーが使用されることが多い。このアンカーは
法枠材の交点に打ち込まれ、法枠材及び中詰客土
等の重量を支える役目を有しているが、アンカー
と法枠材の接合力が弱いために法枠材がアンカー
から離脱して崩落するという問題が発生する。
又、その施工に当つては硬質地山の場合にはアン
カーの打ち込みが困難となるためドリルで穿孔し
てアンカーを挿入して施工されることが多く、盛
土の場合は打ち込みが容易である為、単に打ち込
み式となつている。しかしこのいずれの場合もア
ンカーと地山の密着性が不良であるため引抜き抵
抗力が極度に低く、霜柱等の少しの外力でアンカ
ーが引き抜かれてその支持力を喪失するという問
題がある。
(Prior Art) Currently, various types of slope frame materials are used to protect slopes, and steel rod-shaped anchors are often used to secure them on slopes. This anchor is driven into the intersection of the law frame materials and has the role of supporting the weight of the law frame materials and filler soil. The problem arises that it separates from the base and collapses.
In addition, in the case of hard ground, it is difficult to drive anchors, so the construction is often done by drilling holes and inserting anchors, but in the case of embankments, driving is easy. , it is simply a drive-in type. However, in any of these cases, the adhesion between the anchor and the ground is poor, resulting in extremely low pull-out resistance, and there is a problem in that the anchor is pulled out by the slightest external force, such as a frost column, and loses its supporting force.

本発明者は、これら従来の法枠に使用されるア
ンカーの問題点を解決できる新規なアンカー構築
方法について種々検討した結果、一定長さを有す
る端面形状中空矩形の型枠材を法面上に組立て設
置するに際し、透孔を有する孔管杭を打ち込んで
型枠材と同時に孔管杭内にコンクリート等を注入
すれば、上記欠点を解決できるとの結論に達し、
本発明に到達した。
As a result of various studies on new methods of constructing anchors that can solve the problems of these conventional anchors used in slope frames, the inventor of the present invention has discovered that a formwork material with a hollow rectangular end face shape having a certain length is placed on a slope surface. When assembling and installing, we came to the conclusion that the above drawbacks could be solved by driving a hole pipe pile with a through hole and pouring concrete, etc. into the hole pile at the same time as the formwork material.
We have arrived at the present invention.

(本発明の構成) 本発明の構成を以下図面に基き説明する。(Configuration of the present invention) The configuration of the present invention will be explained below based on the drawings.

第1図は本発明に使用する型枠材の斜視図。第
2図は本発明に使用するジヨイントの一実施例を
示す斜視図。第3図は本発明の施工状況を示す部
分斜視図。第4図は本発明の施工断面図である。
FIG. 1 is a perspective view of a formwork material used in the present invention. FIG. 2 is a perspective view showing one embodiment of a joint used in the present invention. FIG. 3 is a partial perspective view showing the construction status of the present invention. FIG. 4 is a cross-sectional view of the construction of the present invention.

まず、本発明に使用する型枠材につき説明する
と、材質は軽量で強度に優れているということか
ら、高密度ポリエチレンを使用するのが望まし
い。
First, to explain the formwork material used in the present invention, it is desirable to use high-density polyethylene because the material is lightweight and has excellent strength.

型枠材1の形状は、第1図に示す如く、端面形
状中空矩形である。
As shown in FIG. 1, the formwork material 1 has a hollow rectangular end face shape.

以上説明した型枠材の組み立てに際し用いるジ
ヨイントは十字、K字、T字、L字、E字の形状
がある。
The joints used in assembling the formwork materials described above have the shapes of a cross, a K-shape, a T-shape, an L-shape, and an E-shape.

その一例として十字ジヨイントにつき説明する
と、第2図に示す様に、型枠材が嵌合する深さを
有する端面形状略U字材を十字方向に相互に連通
可能に重ね合わせた形状をしており、孔管杭挿通
部8、並びに締め付け金具5を固定する為のボル
ト3を設けてある。
As an example, a cross joint is explained. As shown in Fig. 2, it has a shape in which U-shaped end faces with a depth that allows the formwork material to fit are overlapped in a cross direction so that they can communicate with each other. A bolt 3 for fixing the hole pipe pile insertion part 8 and the tightening fitting 5 is provided.

次に上記した型枠材とジヨイント及び締め付け
金具を用いて法枠を組み立てる方法につき第3
図、第4図に基づき説明する。
Next, we will explain the third method of assembling the frame using the above-mentioned formwork materials, joints, and fastening fittings.
This will be explained based on FIG.

法面30に一定長さを有する端面形状中空矩形
の法枠材1をジヨイント2に差し込みながら法面
下部より組立ててゆくに際し、ジヨイントの底面
に設けた穴を貫通させて透孔7を有する孔管杭6
を杭の頭がジヨイントの内部に残るよう打ち込ん
で固定した後、ジヨイントの開口部を締め付け金
具5でボルト3とナツト2を利用して封鎖固定し
ながら法枠材を組立ててゆく。
When assembling the slope material 1, which has a hollow rectangular end face shape and has a fixed length on the slope surface 30, from the bottom of the slope surface while inserting it into the joint 2, a hole having a through hole 7 is inserted through a hole provided in the bottom surface of the joint. Pipe pile 6
After driving and fixing the pile so that the head of the pile remains inside the joint, the opening of the joint is tightened and sealed and fixed using the bolt 3 and nut 2 with the metal fitting 5, and the legal frame material is assembled.

組立てが完了したならば型枠材の上部適宜箇所
よりコンクリート等の流動物を注入する。注入さ
れたコンクリート等の流動物は法枠材の内部を流
下し、下部より充填されてゆき、さらに透孔を有
する孔管杭の頭部開口部より流入して内部に充填
される。杭の透孔はコンクリート等流動物が流入
時に内部の空気をぬく役目を果すとともに、透孔
から浸出したコンクリートに含まれる主としてモ
ルタルミルクが孔管杭の周辺の土壌間隙に注入圧
によつて充填されるようになる。
Once the assembly is complete, concrete or other fluid is poured into the upper part of the formwork. The poured concrete and other fluids flow down the inside of the legal frame material, filling it from the lower part, and then flowing through the head opening of the hole pipe pile having a through hole and filling the inside. The through holes in the pile serve to remove air from inside when concrete fluids flow in, and the mortar milk, which is mainly contained in the concrete that has leached through the through holes, fills the soil gaps around the hole pipe pile by injection pressure. will be done.

(本発明の効果) 以上のように本発明は、合成樹脂等により成型
された一定長さを有する端面形状中空矩形の型枠
材を法面上に組立て設置するに際し、透孔を有す
る孔管杭をジヨイントの底面に設けた穴を貫通さ
せて杭の頭部がジヨイントの内部に残るように打
ち込み、ジヨイントの開口部を締め付け金具で封
鎖固定した後、該型枠材の上部適宜箇所よりコン
クリート等の流動物を注入し、型枠材と共に孔管
杭内にコンクリート等を注入して構築する法枠工
における注入アンカー工法であるから、高所や急
傾斜面での作業には最適であり、地山、アンカ
ー、法枠の各々が一体化した重量で強度のある構
造体が形成できる。
(Effects of the present invention) As described above, the present invention provides a hole tube having a through hole when assembling and installing a hollow rectangular formwork molded from synthetic resin or the like and having a fixed length on a slope. Drive the pile through the hole provided on the bottom of the joint so that the head of the pile remains inside the joint, seal and fix the opening of the joint with a tightening fitting, and then pour concrete from appropriate places on the top of the formwork material. This is an injection anchor method for construction work in which concrete is injected into the hole pipe pile along with the formwork material, making it ideal for work at high places or on steeply sloped surfaces. , the ground, the anchors, and the legal framework can all be integrated into a heavy and strong structure.

本発明によつて構築する法枠工における注入ア
ンカー工法は、アンカーと法枠が一体化された構
造となるため法枠材がアンカーから離脱して崩落
することはなくなつた。さらに孔管杭の透孔から
浸出したコンクリートに含まれる主としてモルタ
ルミルクが孔管杭の周辺の土壌間隙に注入圧によ
つて充填されて、アンカーの引抜き抵抗力が飛躍
的に向上し、霜柱等の外力でアンカーが引き抜か
れてその支持力を喪失することはなくなつた。
The injection anchor construction method in the slope construction constructed according to the present invention has a structure in which the anchor and the slope are integrated, so that the slope material does not separate from the anchor and collapse. Furthermore, mortar milk, which is mainly contained in the concrete that has leached from the perforations of the hole pipe pile, is filled into the soil gaps around the hole pipe pile by injection pressure, and the pull-out resistance of the anchor is dramatically improved, resulting in frost pillars etc. The anchor no longer loses its supporting capacity due to being pulled out by external force.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に使用する型枠材の斜視図。第
2図は本発明に使用するジヨイントの一実施例を
示す斜視図。第3図は本発明の施工状況を示す部
分斜視図。第4図は本発明の施工断面図である。 図中30は法面、1は型枠材、2はジヨイン
ト、3はボルト、4はナツト、5は締め付け金
具、6は透孔を有する孔管杭、7は孔管杭の透
孔、8は孔管杭挿通部である。
FIG. 1 is a perspective view of a formwork material used in the present invention. FIG. 2 is a perspective view showing one embodiment of a joint used in the present invention. FIG. 3 is a partial perspective view showing the construction status of the present invention. FIG. 4 is a cross-sectional view of the construction of the present invention. In the figure, 30 is a slope, 1 is a formwork material, 2 is a joint, 3 is a bolt, 4 is a nut, 5 is a tightening fitting, 6 is a hole pipe pile with a through hole, 7 is a hole in the hole pipe pile, 8 is the hole pipe pile insertion part.

Claims (1)

【特許請求の範囲】[Claims] 1 合成樹脂等により成型された一定長さを有す
る端面形状中空矩形の型枠材を法面上に組立て設
置するに際し、透孔を有する孔管杭をジヨイント
の底面に設けた穴を貫通させて杭の頭部がジヨイ
ントの内部に残るように打ち込み、ジヨイントの
開口部を締め付け金具で封鎖固定した後、該型枠
材の上部適宜箇所よりコンクリート等の流動物を
注入し、型枠材と共に孔管杭内にコンクリート等
を注入して構築することを特徴とする法枠工にお
ける注入アンカー工法。
1. When assembling and installing a hollow rectangular formwork molded from synthetic resin or the like with a certain length on a slope, a hole pipe pile with a through hole is passed through a hole provided at the bottom of the joint. After driving the pile so that the head remains inside the joint, and sealing and fixing the opening of the joint with a tightening metal fitting, concrete or other fluid is injected from the upper part of the formwork material, and the hole is closed together with the formwork material. An injection anchor construction method for legal framework construction, which is characterized by pouring concrete, etc. into pipe piles.
JP18862384A 1984-09-07 1984-09-07 Pouring anchoring method for installation of slope form Granted JPS6168927A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18862384A JPS6168927A (en) 1984-09-07 1984-09-07 Pouring anchoring method for installation of slope form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18862384A JPS6168927A (en) 1984-09-07 1984-09-07 Pouring anchoring method for installation of slope form

Publications (2)

Publication Number Publication Date
JPS6168927A JPS6168927A (en) 1986-04-09
JPH0241608B2 true JPH0241608B2 (en) 1990-09-18

Family

ID=16226922

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18862384A Granted JPS6168927A (en) 1984-09-07 1984-09-07 Pouring anchoring method for installation of slope form

Country Status (1)

Country Link
JP (1) JPS6168927A (en)

Also Published As

Publication number Publication date
JPS6168927A (en) 1986-04-09

Similar Documents

Publication Publication Date Title
US6161360A (en) Apparatus for supporting reinforcement bar
KR102093071B1 (en) A seismic portal structures attached out-plane square framed type strengthened by level-gap plates and sleeve-cap anchors
JP2004504521A (en) Joints and structures for joining steel pipe pile heads to concrete foundations
US4126001A (en) Method for constructing a soil structure
JPH0241608B2 (en)
JPS6227546Y2 (en)
JPH0371534B2 (en)
KR102093070B1 (en) A seismic portal structures attached in-plane square framed type strengthened by level-gap plates and sleeve-cap anchors
JP2863440B2 (en) Lining sheet for concrete corrosion protection
JPH0324930B2 (en)
JPH0250246B2 (en)
JPH041325A (en) Box-like slope frame and its construction
JPH0219249B2 (en)
JPH0243848B2 (en)
JPH03275806A (en) Method of making knotting pile
JPS6146606B2 (en)
JP3098717B2 (en) Steel pipe sheet pile
JPH0333783Y2 (en)
JPH038922A (en) Executing method for hollow foundation pile and pile head filling-in stuff
JPH031223Y2 (en)
JPH089274Y2 (en) Tunnel lining structure with curved plate for tunnel lining
JPH0328416A (en) Construction method to build up pile
JPS63945Y2 (en)
JPS6151097B2 (en)
JPS6245370B2 (en)