JPH0213111B2 - - Google Patents
Info
- Publication number
- JPH0213111B2 JPH0213111B2 JP17056683A JP17056683A JPH0213111B2 JP H0213111 B2 JPH0213111 B2 JP H0213111B2 JP 17056683 A JP17056683 A JP 17056683A JP 17056683 A JP17056683 A JP 17056683A JP H0213111 B2 JPH0213111 B2 JP H0213111B2
- Authority
- JP
- Japan
- Prior art keywords
- steel frame
- column
- column steel
- frames
- beam steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 80
- 239000010959 steel Substances 0.000 claims description 80
- 238000010276 construction Methods 0.000 claims description 6
- 238000000034 method Methods 0.000 claims description 4
- 238000003466 welding Methods 0.000 description 10
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は建築物における柱鉄骨と梁鉄骨の架構
方法に関する。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing a steel column and a steel beam in a building.
(従来の技術)
従来より、柱・梁の鉄骨架構は、第4,5図に
示すように各階相当位置に予めブラケツト11,
…を突設している柱鉄骨12を揚重して建込み、
その後上記ブラケツト間に梁鉄骨13を揚重し
て、この梁をブラケツト間にセツトし相互の連結
を行うものであつた。(Prior Art) Conventionally, in the steel frame of columns and beams, brackets 11,
Lift and erect the pillar steel frame 12 protruding from...
Thereafter, the beam steel frame 13 was lifted between the brackets, and this beam was set between the brackets to connect them to each other.
(発明が解決しようとする課題)
従来例によれば、柱鉄骨12と梁鉄骨13とは
それぞれ別個に揚重するものであるために揚重効
率が悪く、工期及びそれに伴つてコストがかかつ
ていた。また柱鉄骨に対するブラケツトの工場溶
接作業、梁鉄骨両端の2個所に対するブラケツト
の現場溶接作業とを必要として溶接作業が多く、
手間がかかつていた。(Problem to be Solved by the Invention) According to the conventional example, the column steel frame 12 and the beam steel frame 13 are each lifted separately, so the lifting efficiency is poor, and the construction period and cost are increased accordingly. there was. In addition, there is a lot of welding work, as it requires factory welding of the brackets to the column steel frames and on-site welding of the brackets to two locations on both ends of the beam steel frames.
It was time consuming.
本発明の目的は、柱鉄骨と梁鉄骨とを同時に揚
重可能にして揚重効率を高め、工期の短縮とそれ
に伴なうコストダウンの達成にあり、他の目的は
溶接個所を少なくして作業の省力化を図ることに
ある。 The purpose of the present invention is to make it possible to simultaneously lift column steel frames and beam steel frames to increase lifting efficiency, shorten the construction period, and reduce costs accordingly.Another purpose of the present invention is to reduce the number of welded parts. The purpose is to save labor.
(課題を解決するための手段)
本発明の特徴は、柱鉄骨1と、柱鉄骨1に連結
手段Cにより揺動可能に吊持しかつ柱鉄骨に沿わ
せて閉じた状態にした1/2スパンの長さの梁鉄骨
2とを同時に揚重し、柱鉄骨を建込み、柱鉄骨か
ら上記梁鉄骨を揺動させて柱鉄骨からはね出して
隣接する柱鉄骨の梁鉄骨同志を梁中央で結合する
ようにするところにある。(Means for Solving the Problems) The present invention is characterized by a column steel frame 1 and a 1/2 structure which is swingably suspended from the column steel frame 1 by a connecting means C and is closed along the column steel frame. Lift the beam steel frame 2 with the length of the span at the same time, erect the column steel frame, swing the beam steel frame from the column steel frame, protrude from the column steel frame, and connect the beam steel frames of the adjacent column steel frames to the center of the beam. The point is to connect them with .
(作用)
本発明にあつては、柱鉄骨1と梁鉄骨2とが同
時に揚重可能となる。そして梁鉄骨2同志を梁中
央で結合するために、梁における溶接個所を一個
所ですますことができる。(Function) In the present invention, the column steel frame 1 and the beam steel frame 2 can be lifted simultaneously. Since the two beam steel frames are joined together at the center of the beam, only one welding point is required on the beam.
(実施例)
以下本発明の一実施例を第1図、第2図及び第
3A〜3D図を参照して説明する。(Embodiment) An embodiment of the present invention will be described below with reference to FIG. 1, FIG. 2, and FIGS. 3A to 3D.
予め、第1図に示すように柱鉄骨1のフランジ
1A及びウエブ1Bに1/2スパンの長さの梁鉄骨
2,2aの上辺内側端を連結手段Cによつて矢印
方向に揺動可能に仮止めし、梁鉄骨を柱鉄骨に沿
わせて閉じておく。 As shown in Fig. 1, in advance, the inner ends of the upper sides of the beam steel frames 2, 2a having a length of 1/2 span are connected to the flange 1A of the column steel frame 1 and the web 1B by connecting means C so that they can swing in the direction of the arrow. Temporarily tighten and close the beam steel frame along with the column steel frame.
なお、梁鉄骨2,2aのフランジの下端部で柱
鉄骨1と近接する個所Pを、建方中の養生として
工場で仮止めしておくことが望ましい。これは、
柱鉄骨1の揚重時に梁鉄骨2の位置が安定するか
らである。 In addition, it is desirable that the lower end portions of the flanges of the beam steel frames 2 and 2a, which are close to the column steel frame 1, be temporarily fixed at the factory for curing during erection. this is,
This is because the position of the beam steel frame 2 is stabilized when the column steel frame 1 is lifted.
上記の連結手段Cの具体的構造について説明す
ると、第1,2図に示すように柱鉄骨1のフラン
ジ1Aからこれに溶接した正面フツク状の受プレ
ート5を突設してある。梁鉄骨2の下側のフラン
ジ2Aの下面に丸鋼からなる棒体6を溶接により
固定しており、棒体6は受プレート5の屈曲して
いる内側部に回転可能に係合しており、梁鉄骨2
は棒体6を中心として揺動可能に受プレートに吊
持されている。 To explain the specific structure of the above-mentioned connecting means C, as shown in FIGS. 1 and 2, a front hook-shaped receiving plate 5 protrudes from the flange 1A of the column steel frame 1 and is welded to the flange 1A. A rod 6 made of round steel is fixed to the lower surface of the flange 2A on the lower side of the beam steel frame 2 by welding, and the rod 6 is rotatably engaged with the bent inner side of the receiving plate 5. , beam steel frame 2
is suspended from the receiving plate so as to be swingable about the rod 6.
建方工程は、まず、第3A図に示すように、梁
鉄骨2を柱鉄骨に平行に吊支した状態で、柱鉄骨
と梁鉄骨とをタワークレーンにて同時揚重し、こ
の柱鉄骨を建込み、ついで第3B図に示すように
梁鉄骨2を矢印方向に揺動させて柱鉄骨1に対し
て直角にはね出し、第1図に示すように柱鉄骨の
フランジ1A及びウエブ1Bに突設してあるガセ
ツトプレート3,3aとボルト、ナツトによつて
梁鉄骨を仮連結し、その後隣接する柱鉄骨の梁鉄
骨同志を梁中央で結合する。なお、通常のスパン
(5〜8m程度)の場合は、梁中央はモーメント
が長期荷重のみで小さいので、ウエブジヨイント
のみでよく、端部溶接は現場のみでよい。 In the erection process, first, as shown in Figure 3A, with the beam steel frame 2 suspended parallel to the column steel frame, the column steel frame and the beam steel frame are simultaneously lifted using a tower crane, and this column steel frame is Then, as shown in Fig. 3B, the beam steel frame 2 is swung in the direction of the arrow so as to be pushed out at right angles to the column steel frame 1, and the flange 1A and web 1B of the column steel frame are attached as shown in Fig. 1. The beam steel frames are temporarily connected using the protruding gusset plates 3, 3a, bolts and nuts, and then the beam steel frames of adjacent column steel frames are connected at the center of the beams. In addition, in the case of a normal span (approximately 5 to 8 m), the moment at the center of the beam is only a long-term load and is small, so only a web joint is required, and end welding may be performed only on site.
このように梁鉄骨2を揺動させて、梁中央でウ
エブ間を仮止めし、第3C図に示すように歪直し
をした後、柱鉄骨1と梁鉄骨2とを本締めし、梁
鉄骨のフランジ端部の溶接を行うと、第3D図に
示すような鉄骨架構が完成される。 After swinging the beam steel frame 2 in this way, temporarily fixing the webs at the center of the beam, and correcting the distortion as shown in Figure 3C, the column steel frame 1 and the beam steel frame 2 are fully tightened, and the beam steel By welding the flange ends, a steel frame structure as shown in Fig. 3D is completed.
上例では連結手段は受プレート5と棒体6のみ
からなるために、部品点数が少なくて構成が簡単
であるから、これらの柱鉄骨1や梁鉄骨2に対す
る溶接作業も、従来の柱鉄骨に対するブラケツト
の溶接作業に比較して簡易となる。 In the above example, since the connecting means consists only of the receiving plate 5 and the rod 6, the number of parts is small and the configuration is simple. Therefore, the welding work for these column steel frames 1 and beam steel frames 2 is also similar to that for conventional column steel frames. This is simpler than welding the bracket.
(発明の効果)
以上のとおり本発明によれば、柱鉄骨と梁鉄骨
を同時に揚重できるから、揚重作業が1回ですみ
揚重回数を最小限とすることができ、そのために
鉄骨建方の工期の短縮とこれに伴なうコストダウ
ンを達成できる。そして柱鉄骨側に対向している
端部を除いて梁における溶接個所は梁中央の一個
所ですむから、従来例に比較して溶接手間の省力
化が図れる。(Effects of the Invention) As described above, according to the present invention, since the column steel frame and the beam steel frame can be lifted simultaneously, the lifting work can be done only once, and the number of lifting operations can be minimized. It is possible to shorten the construction period and reduce costs accordingly. Since the beam only needs to be welded at one point in the center of the beam, excluding the end facing the column steel frame, welding labor can be reduced compared to the conventional example.
第1図は柱鉄骨に梁鉄骨を吊支した状態を示す
正面図、第2図は柱鉄骨と梁鉄骨との連結手段を
示す拡大正面図、第3A図〜第3D図は本発明に
よる建方工程を段階的に示す略線図、第4図は従
来例の建方の一工程を示す略線図、第5図は従来
例の鉄骨架構を平面的に表わした略線図である。
1……柱鉄骨、1A……フランジ、2,2a…
…梁鉄骨、2A……フランジ、5……受プレー
ト、6……棒体、C……連結手段。
Fig. 1 is a front view showing a beam steel frame suspended from a column steel frame, Fig. 2 is an enlarged front view showing a means for connecting the column steel frame and beam steel frame, and Figs. 3A to 3D are constructions according to the present invention. FIG. 4 is a schematic diagram showing one step of the construction process in a conventional example, and FIG. 5 is a schematic diagram showing a conventional steel frame structure in a plan view. 1...Column steel frame, 1A...flange, 2, 2a...
...beam steel frame, 2A...flange, 5...receiving plate, 6...rod, C...connection means.
Claims (1)
可能に吊持しかつ柱鉄骨に沿わせて閉じた状態に
した1/2スパンの長さの梁鉄骨とを同時に揚重し、
柱鉄骨を建込み、柱鉄骨から上記梁鉄骨を揺動さ
せて水平状態にして、隣接する柱鉄骨の上記梁鉄
骨同志を梁中央で結合することを特徴とする柱鉄
骨と梁鉄骨の架構方法。 2 連結手段は、柱鉄骨に設けてある受プレート
に、梁鉄骨に固着している棒体が回転可能に係合
しているものであること特徴とする特許請求の範
囲第1項記載の柱鉄骨と梁鉄骨の架構方法。[Scope of Claims] 1. At the same time, a column steel frame and a beam steel frame with a length of 1/2 span, which is swingably suspended from the column steel frame by a connecting means and closed along the column steel frame. Lift and load;
A method of constructing a column steel frame and a beam steel frame, characterized in that a column steel frame is erected, the beam steel frame is swung from the column steel frame to a horizontal state, and the beam steel frames of adjacent column steel frames are joined at the beam center. . 2. The column according to claim 1, wherein the connecting means is a rod fixed to the beam steel frame and rotatably engaged with a receiving plate provided on the column steel frame. Steel frame and beam steel frame construction methods.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17056683A JPS6062369A (en) | 1983-09-17 | 1983-09-17 | Pillar and beam iron skeletal |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17056683A JPS6062369A (en) | 1983-09-17 | 1983-09-17 | Pillar and beam iron skeletal |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6062369A JPS6062369A (en) | 1985-04-10 |
JPH0213111B2 true JPH0213111B2 (en) | 1990-04-03 |
Family
ID=15907210
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP17056683A Granted JPS6062369A (en) | 1983-09-17 | 1983-09-17 | Pillar and beam iron skeletal |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6062369A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2736576B2 (en) * | 1991-11-14 | 1998-04-02 | シバタ建設工業株式会社 | Construction method of steel frame structure and column used for it. |
US9862474B2 (en) | 2010-07-27 | 2018-01-09 | Daewoo Shipbuilding & Marine Engineering Co., Ltd. | Ventilation apparatus of a drillship |
-
1983
- 1983-09-17 JP JP17056683A patent/JPS6062369A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS6062369A (en) | 1985-04-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US2541784A (en) | Roof construction | |
US2871997A (en) | Low pitch rigid frame building | |
JPH0213111B2 (en) | ||
JP3275184B2 (en) | Column-beam connection method | |
JP2882541B2 (en) | A method of mounting a lifting device and a method of joining frame members in a frame material lift-up method | |
JPH0213112B2 (en) | ||
JP2000129958A (en) | Tower-like structural body | |
JPH07310369A (en) | Method and structure for jointing steel post and steel beam | |
JPH03290565A (en) | Erection method of beam | |
KR200255525Y1 (en) | Roof structure of set building | |
JP3247749B2 (en) | Construction method of long span truss beams | |
JPH11131423A (en) | Positioning method of steel pipe | |
JPH11100902A (en) | Installation method of girder | |
JPS6088746A (en) | Roof constructing method | |
JP2600411Y2 (en) | Column-beam joint structure | |
JPH0626236A (en) | High damping frame structuring method | |
JP2556757B2 (en) | Reinforcement structure of column / beam connection and its construction method | |
JPH084113A (en) | Installation method for structural steel small beam | |
JP2681160B2 (en) | E-shaped element of steel frame and its construction | |
CN115749375A (en) | Steel diagonal brace with rotatable end head and construction method thereof | |
JPH0135986B2 (en) | ||
JP2992580B2 (en) | Building construction method | |
JPH09328816A (en) | Y-form column and anchor plate in hexagonal building structure | |
JPS61269947A (en) | Construction method for reinforcing bar structure | |
JP3027550U (en) | Frame structure of a two-story wooden building that is strong against earthquakes |