JPH01287373A - Assembly structure of toilet - Google Patents

Assembly structure of toilet

Info

Publication number
JPH01287373A
JPH01287373A JP11745588A JP11745588A JPH01287373A JP H01287373 A JPH01287373 A JP H01287373A JP 11745588 A JP11745588 A JP 11745588A JP 11745588 A JP11745588 A JP 11745588A JP H01287373 A JPH01287373 A JP H01287373A
Authority
JP
Japan
Prior art keywords
toilet
assembly structure
frame
main body
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11745588A
Other languages
Japanese (ja)
Other versions
JP2579342B2 (en
Inventor
Satoshi Nakatogawa
仲戸川 智
Kosuke Takei
武井 浩介
Hiroshi Kawamura
浩 河村
Yumi Fujita
藤田 由美
Miyuki Takizaki
滝崎 深雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toto Ltd
Original Assignee
Toto Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toto Ltd filed Critical Toto Ltd
Priority to JP11745588A priority Critical patent/JP2579342B2/en
Publication of JPH01287373A publication Critical patent/JPH01287373A/en
Application granted granted Critical
Publication of JP2579342B2 publication Critical patent/JP2579342B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To permit a toilet to function as part of the steel frame of building by a method in which in assembling a toilet in a building by a prefabrication work, the toilet body is connected with the steel frame of the building. CONSTITUTION:In assembling a toilet T in a building B, the toilet body Tm is connected with the steel frame of the building B. Structures other than the toilet T can thus be supported and the toilet body Tm can be utilized positively.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は鉄骨造若しくは鉄骨鉄筋コンリート造ビルジン
グの屋内に設けられる架構式プレファプトイレの組立構
造に間する。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to the assembly structure of a frame-type prefabricated toilet installed indoors in a steel-framed or steel-reinforced concrete building.

(従来の技術) ビルジングの屋内にプレファブエ法によりトイレを組立
てる際、躯体に支柱を立て一架構を組み、これを主体と
して張壁を施すことによりトイレスペースの周壁を形成
することがあり、架構式と称され、主体の張壁は、通常
、壁パネルを建付けて行なう。
(Conventional technology) When assembling a toilet indoors in a building using the prefabricated method, a frame is constructed by setting up supports on the main frame, and a wall is built around this as the main body to form the peripheral wall of the toilet space. The main part of the wall is usually constructed using wall panels.

一方、鉄骨造ビルジング及び鉄骨鉄筋コンリート造ビル
ジングの躯体は、共に鉄骨架構をコンクリートで被覆し
た構造になっており、後者の場合、コンクリート被覆に
配筋が施されている。
On the other hand, both the frameworks of steel-framed buildings and steel-reinforced concrete buildings have a structure in which a steel frame is covered with concrete, and in the latter case, the concrete covering is reinforced.

従来、斯かるビルジングに架構式のプレファブトイレを
設ける場合、躯体のコンクリート被覆にアンカ一部材を
植設し、これで主体の基部を定着するに留めていた。
Conventionally, when installing a frame-type prefabricated toilet in such a building, an anchor member was installed in the concrete covering of the frame, and the base of the main body was fixed with this.

(発明が解決しようとする課題) この為、トイレ主体の活用を図る上で、これにトイレ以
外の構造物を支持させようとする場合等、剛度の確保を
容易に行ない難い一面があった。
(Problems to be Solved by the Invention) For this reason, it is difficult to ensure rigidity when the toilet is intended to support structures other than the toilet.

本発明は斯かる従来の架構式プレファブトイレの組立構
造における問題点を有効に解決すべく為されたもので、
その目的とする処は、たとえトイレ主体にトイレ以外の
構造物を支持させるような場合であっても、剛度の確保
に困ることのないトイレの組立構造を提供するにある。
The present invention was made to effectively solve the problems in the assembly structure of the conventional frame type prefabricated toilet.
The purpose is to provide an assembly structure for a toilet that does not have any difficulty in ensuring rigidity even when the toilet itself supports a structure other than the toilet.

(課題を解決するための手段) 上記目的を達成すべく本発明は、トイレ主体をビルジン
グの鉄骨架構に緊結するようにした。
(Means for Solving the Problems) In order to achieve the above object, the present invention is configured such that the main body of the toilet is tightly connected to the steel frame of the building.

(作用) 上記手段によれば、トイレ主体を鉄骨架構の一部として
扱える。
(Operation) According to the above means, the main body of the toilet can be treated as a part of the steel frame.

(実施例) 以下、本発明の実施例に付き、添付図面に基ずいて詳細
な説明を行なう。
(Embodiments) Hereinafter, embodiments of the present invention will be described in detail based on the accompanying drawings.

図面は本発明を鉄骨鉄筋造ビルジングに適用する場合の
実施例に付き、その施工手順を示したもので、第1図は
トイレ主体と鉄骨架構の緊結状態図、第2図はコンクリ
ートによる被覆状態図、第3図及び第4図は夫々トイレ
主体の内装及び外装状態図である。
The drawings show the construction procedure for an embodiment in which the present invention is applied to a steel reinforced building. Figure 1 shows the state in which the toilet main body and the steel frame are connected, and Figure 2 shows the state covered with concrete. Figures 3 and 4 are diagrams showing the interior and exterior of the toilet, respectively.

図中、Bはビルジング躯体、Tはトイレの全体を表し、
躯体Bは鉄骨架構sbとコンクリート被覆cbから成り
、トイレTは、第3図に示すように矩形架構の主体Tm
とこれを被覆内装する周壁Tw、吊天井Tc及び防水下
地タイル仕上床Tfを備えて成る。尚、第4図のW1〜
W7はトイレ主体Tmを利用して組立られた大小のプレ
ファブルームR1,R2の側壁、Psは共用配管スペー
スである。
In the diagram, B represents the building frame, T represents the entire toilet,
The main body B consists of a steel frame sb and a concrete covering cb, and the toilet T has a rectangular frame main body Tm as shown in Fig. 3.
It is comprised of a surrounding wall Tw, a suspended ceiling Tc, and a waterproof base tile-finished floor Tf that cover and interior this. In addition, W1~ in Figure 4
W7 is the side wall of large and small prefabricated rooms R1 and R2 assembled using the toilet main body Tm, and Ps is a shared piping space.

トイレ主体Tm(第1図)は、四隅の支柱1・・・と、
その足元1aを繋なぐ前後左右の土台2〜5及び頭tb
を繋なぐ桁梁6〜9とで構成され、平面視重なり合う結
梁と土台、即ち、6と2.7と3.8と4、それに9と
5を夫々上下の建付枠として壁パネル10・・・(第3
図)を建並べ、連結することによりトイレ周壁Twの各
平壁部が形成されている。
The main body of the toilet Tm (Fig. 1) is the pillars 1 at the four corners...
Front, rear, left and right bases 2 to 5 and head tb connecting the feet 1a
The wall panel 10 is composed of girder beams 6 to 9 that connect the girder beams 6 to 9, which overlap in plan view, and the connecting beams and the foundation, that is, 6, 2.7, 3.8, and 4, and 9 and 5 as upper and lower construction frames, respectively. ...(3rd
Each flat wall portion of the toilet peripheral wall Tw is formed by arranging and connecting the toilet walls Tw.

尚、天井Tc(第4UgJ)は、桁梁8,9間に横梁1
1・・・を架設し、これから野縁受12・・・を介して
吊設する0図中、Et(第3図)はトイレスペースTs
への出入口、2a(第1図)はそのドア枠13(第4図
)を嵌着するため土台2に設けた段差部、14(第3図
)は大便所ブースの仕切パネルである。
In addition, the ceiling Tc (4th UgJ) has cross beam 1 between girder beams 8 and 9.
In Figure 0, Et (Figure 3) is the toilet space Ts.
2a (FIG. 1) is a step provided on the base 2 to fit the door frame 13 (FIG. 4), and 14 (FIG. 3) is the partition panel of the toilet booth.

一方、鉄骨架構sbは1組立柱20・・・を立設すると
共に、その間各層毎に大梁21.21’  。
On the other hand, the steel frame sb has one assembly column 20 erected, and there are girders 21, 21' for each layer between them.

22.22’  を渡し、ガセット23・・・、23°
・・・やスプライスを添当て、プレースを飼い、溶接及
びリベ−/ )締めして緊結したもので、床梁21゜2
2間に床梁や不図示の小梁を組渡して同様に緊結するこ
とにより床組Ffが形成されている。
22. Pass 22', gusset 23..., 23°
...and splices, fixing the place, welding, and rebating/) tightened the floor beam 21゜2
A floor assembly Ff is formed by assembling floor beams and small beams (not shown) between the two and similarly tightening them.

本実施例では、以上において、床組Ffを設ける際、第
1図に示すように、トイレ主体Tmの左右の土台4,5
と平面視重なり合う位置に一対の床梁24,24を配設
しておき、これに各支柱lの下端底板15を溶接且つリ
ベット締めして緊結するようにしており、これによりト
イレ主体Tmの剛性及び強度を飛躍的に増大せしめてい
る。
In this embodiment, when installing the floor assembly Ff in the above, as shown in FIG.
A pair of floor beams 24, 24 are arranged at positions overlapping with each other in plan view, and the lower end bottom plate 15 of each support column l is welded and fastened with rivets to these beams, thereby increasing the rigidity of the toilet main body Tm. and its strength has been dramatically increased.

そして、第2−に示すように、上記架構sbにコンクリ
ート被覆cbを施して、ビルジング躯体Bを得ており、
Ii体床Fbは鉄筋コンクリートの床版30〜34を敷
詰めて構成される。
Then, as shown in No. 2-, a concrete coating cb is applied to the above-mentioned frame sb to obtain a building frame B,
The Ii body floor Fb is constructed by laying reinforced concrete floor slabs 30 to 34.

尚、本実施例では、土台2〜5各端を支柱l下端より若
干上方位置に固着して、土台2〜5の下面と床躯体Fb
との間に隙間を設けておき、ご覧にコンクリートを打設
して基礎梁34〜37を形成するが、トイレ主体の土台
を直接床梁に緊結固着し、その上又は脇に支柱を緊結立
設するようにしても良い。
In this embodiment, each end of the foundations 2 to 5 is fixed at a position slightly above the lower end of the support column l, so that the lower surface of the foundations 2 to 5 and the floor frame Fb
Leave a gap between the two and pour concrete to form the foundation beams 34 to 37. However, the foundation for the main body of the toilet is directly fixed to the floor beams, and the pillars are firmly attached above or beside it. You may also set it.

以上によりトイレ主体Tmの構築を終え、その後、第3
図に示すように、壁パネル10・・・を建付けてトイレ
周壁Twを形成し、床Tfを仕上げ、仕切パネル14を
立てへ配管ユニットその他のトイレ設備を施し、途中、
適宜な時期に、天井Ct(第4図)を吊設し、斯くして
トイレTを完成することになる。
After completing the construction of the toilet-based Tm, the third
As shown in the figure, the wall panels 10... are erected to form the toilet surrounding wall Tw, the floor Tf is finished, the partition panel 14 is erected, the piping unit and other toilet equipment are installed, and in the middle,
At an appropriate time, the ceiling Ct (Fig. 4) will be suspended, and the toilet T will be completed in this way.

この点、本実施例では、そうした作業に平行して、床躯
体Fb上にモルタル下地の防水層38を形成しておき、
以って、第4図に示すように、床仕上材40を貼着する
一方、トイレ主体Tmと躯体壁wbで支持した軸組40
を組廻し、これに内装パネル41〜43を張り並べて側
壁WI NW6を形成すると共に、間仕切パネル44を
立て渡して、大小のプレファブルームR1,R2を得る
ようにしており、側壁W2〜W4がトイレ周壁Twを外
装した形になっている。
In this regard, in this embodiment, in parallel with such work, a waterproof layer 38 of mortar base is formed on the floor structure Fb,
Therefore, as shown in FIG. 4, while the floor finishing material 40 is attached, the framework 40 supported by the toilet main body Tm and the frame wall wb is attached.
The interior panels 41 to 43 are lined up to form side walls WI NW6, and the partition panels 44 are stood up to form prefabricated rooms R1 and R2 of different sizes, with side walls W2 to W4 serving as toilets. It is in the form of an exterior surrounding wall Tw.

斯かる自由な構成は、トイレ主体Tmが鉄骨架構Sbに
緊結一体化されていることによるが、この緊結位置を、
例えば、トイレ主体の桁材と躯体゛の壁側等、任意に選
定することは差支えない。
This free configuration is due to the fact that the main body of the toilet Tm is tightly integrated with the steel frame Sb.
For example, the girder material for the main body of the toilet and the wall side of the frame may be selected arbitrarily.

(発明の効果) 以上の説明により明らかな如く、本発明によれば、架構
式プレファブトイレの主体をビルジングの鉄骨架構に緊
結しているので、トイレ主体を鉄骨架構の一部として扱
え、たとえトイレ以外の構造物を支持させるような場合
であっても、用度の確保に困らずに済む。
(Effects of the Invention) As is clear from the above explanation, according to the present invention, the main body of the frame-type prefabricated toilet is tightly connected to the steel frame of the building, so the toilet main body can be treated as a part of the steel frame, and even if the toilet Even when supporting other structures, there is no problem in ensuring availability.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の実施例に係るトイレを鉄骨鉄筋造ビルジ
ングに設ける場合の施工手順を表したもので、第1図は
トイレ主体と鉄骨架構の緊結状態を示す斜視図、第2図
はコンクリートによる被覆状態を示す斜視図、第3図及
び第4図は夫々トイレ主体の内装及び外装状態を示す斜
視図である。 尚、図中、1は支柱、1aと1bはその足元と頭、2〜
5は土台、6〜9は桁材、10は壁パネル、11は横梁
、15は底板、24は床梁、Bはビルジング躯体、Bf
は躯体床、cbはコンクリート被覆、Ffは床組、sb
は鉄骨架構、Tはトイレ、Tcはトイレ天井、Tmはト
イレ主体、Tsはトイレスペース、Twはトイレ周壁を
表している。
The drawings show the construction procedure when a toilet according to an embodiment of the present invention is installed in a steel-frame reinforced building. Figure 1 is a perspective view showing the state in which the toilet main body and the steel frame are connected, and Figure 2 is a concrete construction procedure. A perspective view showing the covered state, and FIGS. 3 and 4 are perspective views showing the interior and exterior states of the toilet, respectively. In addition, in the figure, 1 is the pillar, 1a and 1b are its feet and head, 2~
5 is the foundation, 6 to 9 are the girders, 10 is the wall panel, 11 is the cross beam, 15 is the bottom plate, 24 is the floor beam, B is the building frame, Bf
is the frame floor, cb is the concrete covering, Ff is the floor assembly, sb
is the steel frame, T is the toilet, Tc is the toilet ceiling, Tm is the toilet main body, Ts is the toilet space, and Tw is the toilet surrounding wall.

Claims (8)

【特許請求の範囲】[Claims] (1)鉄骨架構をコンクリートで被覆したビルジングの
躯体に支柱を立てゝ主体を構築し、該主体に壁パネルを
建付けてトイレスペースの周壁を形成するようにしたト
イレの組立構造において、前記主体を前記架構に緊結し
て成るトイレの組立構造。
(1) In a toilet assembly structure in which a main body is constructed by erecting supports on a building frame made of a steel frame covered with concrete, and wall panels are erected on the main body to form a peripheral wall of a toilet space, the main body is An assembly structure for a toilet, which comprises: being tightly connected to the frame.
(2)前記主体は、前記支柱の下端で、前記架構の床組
材に緊結されている請求項1記載のトイレの組立構造。
(2) The toilet assembly structure according to claim 1, wherein the main body is tightly connected to a floor member of the frame at a lower end of the support column.
(3)前記床組材は前記周壁の平壁部と平行に配設した
梁材から成る請求項2記載のトイレの組立構造。
(3) The toilet assembly structure according to claim 2, wherein the floor assembly comprises beams arranged parallel to the flat wall portion of the peripheral wall.
(4)前記主体は前記支柱を繋なぐ桁材及び土台を備え
、前記壁パネルは該桁材及び土台を上下の建付枠として
いる請求項1若しくは3記載のトイレの組立構造。
(4) The toilet assembly structure according to claim 1 or 3, wherein the main body includes a girder and a base that connect the pillars, and the wall panel uses the girder and the base as upper and lower construction frames.
(5)前記土台を前記架構の床組に緊結して成る請求項
4記載のトイレの組立構造。
(5) The toilet assembly structure according to claim 4, wherein the base is tightly connected to the floor assembly of the frame.
(6)前記桁材に横梁を架設し、該横梁より組天井を吊
設して成る請求項4記載のトイレの組立構造。
(6) The toilet assembly structure according to claim 4, wherein a cross beam is constructed on the girder, and a set ceiling is suspended from the cross beam.
(7)前記周壁を前記ビルジング躯体の内壁で外装した
請求項1記載のトイレの組立構造。
(7) The toilet assembly structure according to claim 1, wherein the peripheral wall is covered with an inner wall of the building frame.
(8)前記コンクリート被覆は鉄筋で補強されている請
求項1記載のトイレの組立構造。
(8) The toilet assembly structure according to claim 1, wherein the concrete covering is reinforced with reinforcing bars.
JP11745588A 1988-05-13 1988-05-13 Toilet assembly structure Expired - Lifetime JP2579342B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11745588A JP2579342B2 (en) 1988-05-13 1988-05-13 Toilet assembly structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11745588A JP2579342B2 (en) 1988-05-13 1988-05-13 Toilet assembly structure

Publications (2)

Publication Number Publication Date
JPH01287373A true JPH01287373A (en) 1989-11-20
JP2579342B2 JP2579342B2 (en) 1997-02-05

Family

ID=14712087

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11745588A Expired - Lifetime JP2579342B2 (en) 1988-05-13 1988-05-13 Toilet assembly structure

Country Status (1)

Country Link
JP (1) JP2579342B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006283332A (en) * 2005-03-31 2006-10-19 Daiwa House Ind Co Ltd Construction method of moveable room part of building and its building
US9021620B1 (en) 2009-01-15 2015-05-05 Modular Services Company Cantilevered brace assembly for wall-mounted toilet

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006283332A (en) * 2005-03-31 2006-10-19 Daiwa House Ind Co Ltd Construction method of moveable room part of building and its building
JP4727274B2 (en) * 2005-03-31 2011-07-20 大和ハウス工業株式会社 Method for constructing relocatable room part of building and its building
US9021620B1 (en) 2009-01-15 2015-05-05 Modular Services Company Cantilevered brace assembly for wall-mounted toilet

Also Published As

Publication number Publication date
JP2579342B2 (en) 1997-02-05

Similar Documents

Publication Publication Date Title
SK161099A3 (en) Building framework
JPH01287373A (en) Assembly structure of toilet
JP3843161B2 (en) Piloti
JP2003049484A (en) Construction method for wooden house
JP3045034B2 (en) Structural method of RC building
JP2003049480A (en) Construction method for wooden house
JP2003049481A (en) Construction method for wooden house
JP2001220818A (en) Steel framework structure
JP2000328664A (en) Building unit and unit type building
JPH053636Y2 (en)
JP3401311B2 (en) Building construction method using unit panels
JP2000336748A (en) Erection method of two-story house
JP2971339B2 (en) Building construction method
JP2001132266A (en) Installation structure of very soft panel damper in precast rc construction structure and its installing method
JP2574866B2 (en) Toilet wall assembly method
JP2537255B2 (en) How to assemble a prefabricated toilet
JPH0738501Y2 (en) Prefabricated partition wall
JP2696196B2 (en) Construction method of concrete building
JP2537256B2 (en) How to assemble a prefabricated toilet
JPH04124340A (en) Frame for combined construction
JPH10152890A (en) Building structure of wooden building
JP2904043B2 (en) How to build a composite frame
JP2000038773A (en) Unitized building
JPS58173239A (en) Slab with beam in pc building
JPH0735925Y2 (en) Building frame