JPH01287340A - Construction of heavyweight temporary structure - Google Patents

Construction of heavyweight temporary structure

Info

Publication number
JPH01287340A
JPH01287340A JP11797088A JP11797088A JPH01287340A JP H01287340 A JPH01287340 A JP H01287340A JP 11797088 A JP11797088 A JP 11797088A JP 11797088 A JP11797088 A JP 11797088A JP H01287340 A JPH01287340 A JP H01287340A
Authority
JP
Japan
Prior art keywords
groove
receiving plate
temporary structure
flange
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11797088A
Other languages
Japanese (ja)
Other versions
JPH0649962B2 (en
Inventor
Shoichiro Otsuji
正一郎 尾辻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BURUMAN KK
NIKKO KAIHATSU KK
Original Assignee
BURUMAN KK
NIKKO KAIHATSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BURUMAN KK, NIKKO KAIHATSU KK filed Critical BURUMAN KK
Priority to JP11797088A priority Critical patent/JPH0649962B2/en
Publication of JPH01287340A publication Critical patent/JPH01287340A/en
Publication of JPH0649962B2 publication Critical patent/JPH0649962B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To make easy, quick and firm connection of a horizontal member to an upright column in crossing condition by holding a flange of the upright column in a groove and a notched groove of a connecting metal fixture, by joining the horizontal member against a support plate of the connecting metal fixture and by holding the support plate and the flange of the horizontal member by a vise. CONSTITUTION:A connecting metal fixture 4 is composed of a groove-shaped metal fixture 1, a support plate 2, integrally fitted to the groove-shaped metal fixture 1, and a notched groove 3 provided on the support plate 2 along the groove 1' of the groove-shaped metal fixture 1. Then, a middle flange 5' of an upright column 5 made of shape steel is inserted into the groove 1' and the notched groove 3 of the connecting metal fixture 4, and the middle flange is held by the tips of two bolts 6 that are inserted and screwed into the groove 1' from both sides of the groove-shaped metal fixture 1. A horizontal member 7, made of a shape steel, is then joined against the support face of the support plate 2, and a flange 7' of the horizontal member 7 and the support plate 2 are held from both sides by a vise 8. With such arrangement, connection of the horizontal member 7 in crossing with the upright column 5 can be made easily, quickly and firmly.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は重仮設物の構築法に関するものである。[Detailed description of the invention] "Industrial application field" The present invention relates to a method for constructing heavy temporary structures.

「従来の技WIJ 従来建設現場における構台、桟橋、支保構、覆工路面等
の重仮設物の構築に際し形鋼による立柱と形鋼による横
材との交差部の接続に万力を用いる技術が開発された(
特公昭58−2307号、実公昭57−16964号)
。しかし立柱の中程において横材の上下面を挾持したた
め挟持間隔が大となし、大形の挟持金具を必要とするば
かりか挟持力に限界があって強力安全容易かつ迅速に接
続することは困難であった。
``Conventional Techniques WIJ'' Traditionally, when constructing heavy temporary structures such as trestles, piers, supporting structures, and road linings at construction sites, there is a technique that uses a vise to connect the intersections of vertical columns made of shaped steel and horizontal members made of shaped steel. It has been developed(
Special Publication No. 58-2307, Actual Publication No. 57-16964)
. However, since the upper and lower surfaces of the horizontal members are clamped in the middle of the vertical columns, the clamping interval is large, which not only requires large clamping metal fittings, but also has a limit to the clamping force, making it difficult to connect powerfully, safely, easily, and quickly. Met.

「発明が解決しようとする問題点J 本発明は形鋼による立柱の中程に形鋼による横材を強力
安全容易かつ迅速に交差状態に接続することを目的とす
る。
``Problems to be Solved by the Invention J'' The object of the present invention is to connect cross members made of section steel to the middle of vertical columns made of section steel in a strong, safe, easy, and quick manner in a crossing state.

「問題点を解決するための手段」 本発明は上記目的を達成するため溝形金具の一端に受板
を一体に接続し、該受板に上記金具の溝に沿って切欠溝
を形成してなる接続金具を用い、上記溝形金具の溝及び
上記切欠溝の内部に形鋼による立柱の中程フランジを挿
入し、上記溝形金具の両性側から溝内にボルトを対向方
向に螺入して該ボルトの先端によって上記フランジの両
側面を挾持し、かつその状態において受板の受面に形鋼
"Means for Solving the Problems" In order to achieve the above object, the present invention includes integrally connecting a receiving plate to one end of a groove-shaped metal fitting, and forming a cutout groove in the receiving plate along the groove of the metal fitting. Using the connecting fitting, insert the middle flange of the vertical column made of shaped steel into the groove of the grooved fitting and the notched groove, and screw the bolts into the groove from both sides of the grooved fitting in opposite directions. The ends of the bolts are used to clamp both sides of the flange, and in this state, the shaped steel is attached to the receiving surface of the receiving plate.

による横材を接し、横材のフランジと受板とを万力で挾
持することによって横材を上記立柱の中程に支持するこ
とな特徴とする重仮設物構築法を特定発明とし、 万力がC形金具の両端部に穿設した螺孔にボルトを対向
方向に螺入する上記特定発明の重仮設物構築法 万力がC形金具の一端部に穿設した螺孔にボルトを螺入
り他端部に該ボルトの先端に対向する突起を設けたもの
である上記特定発明記載の重仮設物構築法 立柱がH形鋼であり横材がコ形形鋼である上記発明記載
の重仮設物構築法 受板の受面に1個の横材を接する上記発明記載の重仮設
物構築法 受板の受面に互に直交する2個の横材を接する上記発明
記載の恵仮設物構築法 受面が上向又は下向である上記発明記載の重仮設物構築
法 横材の上下フランジに受面を上向及び下向に接する2個
の接続金具によって該横材を立柱に支持する上記発明記
載の京仮設物構築法 受板に透孔を穿設し該透孔に万力のボルトの先端部を挿
通し、該先端部とざルトとの境界段面を受板に接して挾
持する上記発明記載の重仮設物構築法 ボルトの先端面に突出刃を設けた上記発明記載の重仮設
物構築法 境界段面をボルトに螺合したナツトによって形成した上
記発明記載の重仮設物構築法 受板とフランジとを万力の両端部のボルト又はボルトの
先端面の突出刃で挾持する上記発明記載の重仮設物構築
法によって構成される。
A method for constructing a heavy temporary structure is defined as a specified invention, which is characterized in that the cross member is supported in the middle of the above-mentioned upright column by bringing the cross member into contact with each other and holding the flange of the cross member and the receiving plate in a vise. A method for constructing heavy temporary structures according to the above specified invention, in which the bolts are screwed in opposite directions into the screw holes drilled at both ends of the C-shaped metal fitting. Heavy temporary structure construction method according to the above-mentioned specified invention, in which the other end of the bolt is provided with a protrusion opposite to the tip of the bolt. The heavy temporary structure construction method according to the above invention, in which the receiving surface of the receiving plate is in contact with one horizontal member.The temporary structure according to the above invention, in which two horizontal members perpendicular to each other are in contact with the receiving surface of the receiving plate. Construction method A method for constructing a heavy temporary structure according to the above invention in which the receiving surface faces upward or downward. The horizontal member is supported on a vertical column by two connecting fittings whose receiving surfaces are in contact with the upper and lower flanges of the horizontal member upward and downward. The Kyoto temporary structure construction method according to the above invention, in which a through hole is bored in the receiving plate, the tip of a vise bolt is inserted into the through hole, and the boundary surface between the tip and the bolt is brought into contact with the receiving plate. Heavy temporary structure construction method according to the above invention, in which the boundary step surface is formed by a nut screwed onto a bolt Object Construction Method The heavy temporary structure construction method described in the invention is constructed by clamping the receiving plate and the flange with bolts at both ends of a vise or with protruding blades on the tip surfaces of the bolts.

「作用」 従って複数のH形鋼立柱5.5の中程間に水平方向にコ
形形鋼横材7.7を架設する際、先ず立柱5のフランジ
5′の中程に溝形金具1の溝1及び受板2の切欠溝3を
嵌合し、ボルト6.6を対向方向に螺入することによっ
て先端面の突出刃13.13を上記7ラング50両側面
に圧入して該フラランジ5に固定する。このようにする
と溝形金具1の一端の受板2がH形鋼立柱5の中程に水
平に固定されかつ該立柱5の外側に突出するから、該受
板2の受面に上記横材7のフランジ7′を載せ該フラン
ジ7′と受板2とを万力8で挾持することによって横材
7は立柱5に交差状に支持される。又受板2の受面は立
柱5の正面及び側面に突出するため互に直交する横材7
.7を該正面及び側面において上記受板2上に載せて万
力8.8で挾持して直交横材7.7を立柱5の中程に同
一水準位置に支持することができる。万力8はC形金具
80両端部にボルト9.9を対向方向に螺入したもので
も一端部にボルト9を螺入し他端部に対向突起10を設
けた吃のでも差支えない0又接続金具4は上向又は/及
び下向に立柱5に支持し横材7の上下フランジ7’、7
’と受板2とをそれぞれ挾持することができる。
``Operation'' Therefore, when erecting the U-shaped steel horizontal member 7.7 horizontally between the middles of the plurality of H-shaped steel columns 5.5, first place the groove-shaped metal fitting 1 in the middle of the flange 5' of the vertical column 5. The protruding blades 13.13 on the tip surface are press-fitted into both sides of the seven rungs 50 by fitting the grooves 1 and the notch grooves 3 of the receiving plate 2, and screwing the bolts 6.6 in opposite directions. Fixed at 5. In this way, the receiving plate 2 at one end of the groove-shaped metal fitting 1 is fixed horizontally to the middle of the H-shaped steel column 5 and protrudes to the outside of the column 5, so that the receiving surface of the receiving plate 2 is attached to the horizontal member. By placing the flange 7' of 7 and holding the flange 7' and the receiving plate 2 in a vise 8, the cross member 7 is supported by the vertical column 5 in a crosswise manner. Also, since the receiving surface of the receiving plate 2 protrudes from the front and side surfaces of the vertical column 5, the horizontal members 7 are perpendicular to each other.
.. 7 is placed on the receiving plate 2 on the front and side surfaces and clamped with a vise 8.8, so that the orthogonal cross member 7.7 can be supported at the same level in the middle of the vertical column 5. The vise 8 can be a C-shaped metal fitting 80 with bolts 9 and 9 screwed in opposite directions at both ends, or a vise with a bolt 9 screwed into one end and a facing protrusion 10 at the other end. The connecting fitting 4 is supported upwardly and/or downwardly on the vertical column 5, and is connected to the upper and lower flanges 7', 7 of the cross member 7.
' and the receiving plate 2 can be respectively held.

受板2に透孔11を穿設し、該透孔11に万力80ボル
ト9の先端部を挿通し、先端部の突出刃13をフランジ
7′に圧入しかつ境界段面1′2を受板2に圧着して受
板2とフランジ7とを万力8で挾持することができる(
第11図、第12図、第13図)。上記ボルト6.9の
先端面には突出刃13を設けて挟持時にフランジ5′、
7’に食い込ませることができる0勿論第14図に示す
ように受板2に透孔を設けることなく万力8の両端部ボ
ルト9.9及び突出刃13.13によって受板2とフラ
ンジ7′とを挟持することができる(第14図、第15
図)。
A through hole 11 is bored in the receiving plate 2, the tip of the vise 80 bolt 9 is inserted into the through hole 11, the protruding blade 13 at the tip is press-fitted into the flange 7', and the boundary step surface 1'2 is The support plate 2 and flange 7 can be clamped with a vise 8 by being crimped onto the support plate 2 (
11, 12, 13). A protruding blade 13 is provided on the tip surface of the bolt 6.9, so that when clamping, the flange 5',
Of course, as shown in FIG. 14, the bolts 9.9 and the protruding blades 13.13 at both ends of the vise 8 can be used to attach the receiving plate 2 and the flange 7 without providing a through hole in the receiving plate 2, as shown in FIG. ' (Fig. 14, 15)
figure).

「実施例」 短い溝形金具1の一端を方形の受板2の裏面中央部に溶
着して一体となL1該受板2の一辺中央部から上記金具
1の溝1′に沿って切欠溝3を形成して接続金具4を形
成する(第3図)。上記溝形金具1の中程には側斜側か
ら溝1内に向って螺孔を有り該螺孔に対同方向に向うボ
ルト6.6を螺入するようにしてあし、該ボルト6.6
の先端面には対向方向に突出する刃13が形成されてい
る。
``Example'' One end of the short groove-shaped metal fitting 1 is welded to the center of the back surface of the rectangular receiving plate 2 to form an integral part L1. 3 to form a connecting fitting 4 (FIG. 3). In the middle of the groove-shaped metal fitting 1, there is a screw hole extending from the side slope side into the groove 1, into which a bolt 6.6 facing in the same direction is screwed. 6
A blade 13 is formed on the distal end surface of the blade 13 and protrudes in the opposite direction.

本発明はこのような接続金具4を用いるものであってH
形鋼による仮設立柱5.5のフランジ5に上記溝1及び
切欠溝3を挿入し上記ボルト6.6を対向方向に螺入し
て該フランジ5の両側面を該ボルト6.6及び突出刃1
3.13で挾持し固定する。この状態では受板2は立柱
5の正面及び側面に水平に突出する(第3図)。従って
受板2の上記正面側にコ形形鋼による横材7を水平方向
に載置し該横材7のフランジ7と該受板2とを万力8で
挾持するものである。万力8はC形金具80両端部に穿
設した螺孔にボルト9.9を対向方向に螺入しく第9図
、第15図)或は一端部にのみ螺孔を設け、これにボル
ト9を螺入し、他端部に該ボルト9の先端に対向する突
起10を設けたものであっても差支えない(第7図)。
The present invention uses such a connecting fitting 4, and H
Insert the groove 1 and the notched groove 3 into the flange 5 of the temporarily installed column 5.5 made of shaped steel, screw in the bolt 6.6 in opposite directions, and attach the bolt 6.6 and the protruding blade to both sides of the flange 5. 1
3. Clamp and fix in step 13. In this state, the receiving plate 2 projects horizontally from the front and side surfaces of the upright column 5 (FIG. 3). Therefore, a horizontal member 7 made of U-shaped steel is placed horizontally on the front side of the receiving plate 2, and the flange 7 of the horizontal member 7 and the receiving plate 2 are held in a vise 8. The vise 8 can be used by screwing the bolts 9.9 in opposite directions into the screw holes drilled at both ends of the C-shaped metal fitting 80 (Figs. 9 and 15), or by providing a screw hole only at one end and screwing the bolts into this. 9 may be screwed into the bolt 9, and a protrusion 10 facing the tip of the bolt 9 may be provided at the other end (FIG. 7).

又上記ボルト9.9の先端面にも突出刃13を設けるこ
とができる。そして上記受板2の側面側にも上記横材7
と直交する横材7を載置し万力8によって上述同様に受
板2と該横材7のフランジ7とを挾持し第1図、第2図
及び第3図に示すように仮設物の角部立柱5.5を形成
することができる。上記接続金具4は上向又は及び下向
に立柱5に固定することによって横材7の上下のフラン
ジ7.7を同時に立柱5に固定することができるし、受
板2に穿設した透孔11に万力8のボルト9の先端部9
を挿通し先端部9との境界段面12で受板2を押圧しか
つ先端部9の先端面又は及び突出刃13によってフラン
ジ7′を押圧固定し該フランジ7′と受板2とを挾持す
ることができる0境界段面12は第7図、第8図、第9
図、第11図及び第13図に示すが第12図に示すよう
にボルト9に螺合したナツト14によって形成すること
ができる。尚図中15で示す本のけ接続金具4における
補強用リプ、16は仮設桟橋の覆板である。
Further, a protruding blade 13 can also be provided on the tip end surface of the bolt 9.9. The horizontal member 7 is also placed on the side surface of the receiving plate 2.
Place the horizontal member 7 orthogonal to the horizontal member 7, and clamp the receiving plate 2 and the flange 7 of the horizontal member 7 with a vise 8 in the same manner as described above, and as shown in FIGS. 1, 2, and 3, the temporary structure is A corner upright column 5.5 can be formed. By fixing the connecting fitting 4 upwardly or downwardly to the vertical column 5, the upper and lower flanges 7.7 of the cross member 7 can be fixed to the vertical column 5 at the same time. Tip 9 of bolt 9 in vise 8 to 11
is inserted, and the receiving plate 2 is pressed by the boundary step surface 12 with the tip part 9, and the flange 7' is pressed and fixed by the tip surface of the tip part 9 or the protruding blade 13, and the flange 7' and the receiving plate 2 are sandwiched. The zero boundary step surface 12 that can be
11 and 13, it can be formed by a nut 14 screwed onto a bolt 9 as shown in FIG. In the figure, 15 is a reinforcing lip on the bookshelf connection fitting 4, and 16 is a cover plate of the temporary pier.

「効果」 本実は上述の方法によったので仮設構造物の形鋼立柱5
の中程に形鋼横材7を簡便迅速かつ強力に架設し得て仮
設構造物の安全性と工期を短縮することができる。
``Effect'' Actually, the above method was used, so the shape steel column of the temporary structure 5
The cross member 7 of the shaped steel can be easily, quickly and strongly erected in the middle of the structure, and the safety of the temporary structure and the construction period can be shortened.

又1個の接続金具4によって立柱5の中程に互に直交す
る横材7.7を簡便迅速かつ強力に架設することができ
る。
Further, by using one connecting fitting 4, the mutually orthogonal cross members 7, 7 can be easily, quickly and strongly erected in the middle of the vertical column 5.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の重仮設物の構築法を示す正面図、第2
図は該構築法による桟橋の斜視図、第3図は受板の平面
図、第4図は受板の正面図、第5図は第3図を右方から
見た側面図、第6図は接続金具の斜視図、第7図は万力
の側面図、第8図はボルトの境界段面の側面図、第9図
は万力の他の実施例の側面図、第10図は突出刃の側面
図、第11図は受板の透孔部の縦断面図、第12図は境
界段の他例の側面図、第13図は上記透孔部の他例の縦
断面図、第14図は受板に透孔がない場合の平面−、第
15図は万力によるフランジ、受板挾持状態の縦断面図
である。 l・・溝形金具、2−・受板、1・・溝、3・・切欠溝
、4・・接続金具、5・・立柱、5・・中程フランジ、
6・・ボルト、7・・横材、7・・フランジ、8・・万
力、〆・・C彫金具、9・・ボルト、9′・・先端部、
10・・突起、11・・透孔、12・・境界段面、13
・・突出刃、14・・ナツト。
Figure 1 is a front view showing the method for constructing heavy temporary structures of the present invention;
The figure is a perspective view of the pier constructed by the construction method, Figure 3 is a plan view of the receiving plate, Figure 4 is a front view of the receiving plate, Figure 5 is a side view of Figure 3 viewed from the right, and Figure 6 is a perspective view of the connecting fitting, Figure 7 is a side view of the vise, Figure 8 is a side view of the boundary step of the bolt, Figure 9 is a side view of another embodiment of the vise, and Figure 10 is the protrusion. FIG. 11 is a side view of the blade, FIG. 11 is a longitudinal sectional view of the through-hole part of the receiving plate, FIG. 12 is a side view of another example of the boundary stage, FIG. 13 is a longitudinal sectional view of another example of the above-mentioned through-hole part, and FIG. FIG. 14 is a plan view when the receiving plate does not have a through hole, and FIG. 15 is a longitudinal sectional view of the flange and the receiving plate being held in a vise. l..Groove metal fitting, 2..Socket plate, 1..Groove, 3..Notch groove, 4..Connection fitting, 5..Standard, 5..Middle flange,
6... Bolt, 7... Horizontal material, 7... Flange, 8... Vise, Finish... C carving tool, 9... Bolt, 9'... Tip,
10...Protrusion, 11...Through hole, 12...Boundary step surface, 13
...Protruding blade, 14...nut.

Claims (13)

【特許請求の範囲】[Claims] (1)溝形金具の一端に受板を一体に接続し、該受板に
上記金具の溝に沿つて切欠溝を形成してなる接続金具を
用い、上記溝形金具の溝及び上記切欠溝の内部に形鋼に
よる立柱の中程フランジを挿入し、上記溝形金具の両外
側から溝内にボルトを対向方向に螺入して該ボルトの先
端によつて上記フランジの両側面を挾持し、かつその状
態において受板の受面に形鋼による横材を接し、横材の
フランジと受板とを万力で挾持することによつて横材を
上記立柱の中程に支持することを特徴とする重仮設物構
築法。
(1) Using a connecting fitting in which a receiving plate is integrally connected to one end of the grooved fitting and a notched groove is formed in the receiving plate along the groove of the fitting, the groove of the grooved fitting and the notched groove are formed. Insert a middle flange of a vertical column made of shaped steel into the inside of the groove-shaped metal fitting, screw bolts into the groove in opposite directions from both outsides of the groove-shaped metal fitting, and clamp both sides of the flange with the tips of the bolts. , and in that state, the horizontal member made of shaped steel is brought into contact with the receiving surface of the receiving plate, and the flange of the horizontal member and the receiving plate are held in a vise to support the horizontal member in the middle of the above-mentioned vertical column. A distinctive method of constructing heavy temporary structures.
(2)万力がC形金具の両端部に穿設した螺孔にボルト
を対向方向に螺入するものである請求項(1)記載の重
仮設物構築法。
(2) The method for constructing a heavy temporary structure according to claim (1), wherein the vise screws the bolts in opposite directions into screw holes bored at both ends of the C-shaped metal fitting.
(3)万力がC形金具の一端部に穿設した螺孔にボルト
を螺入し他端部に該ボルトの先端に対向する突起を設け
たものである請求項(1)記載の重仮設物構築法。
(3) The vice according to claim (1), wherein a bolt is screwed into a screw hole drilled at one end of the C-shaped metal fitting, and a protrusion opposite the tip of the bolt is provided at the other end. Temporary construction method.
(4)立柱がH形鋼であり、横材がチャンネル形鋼であ
る請求項(1)(2)又は(3)記載の重仮設物構築法
(4) The method for constructing a heavy temporary structure according to claim (1), (2) or (3), wherein the upstanding columns are made of H-shaped steel and the cross members are made of channel-shaped steel.
(5)受板の受面に1個の横材を接する請求項(1)〜
(4)にそれぞれ記載の重仮設物構築法。
(5) Claims (1) to 1 in which one horizontal member is in contact with the receiving surface of the receiving plate.
Heavy temporary structure construction methods described in (4) respectively.
(6)受板の受面に互に直交する2個の横材を接する請
求項(1)〜(5)にそれぞれ記載の重仮設物構築法。
(6) The heavy temporary structure construction method according to each of claims (1) to (5), wherein two cross members perpendicular to each other are in contact with the receiving surface of the receiving plate.
(7)受面が上向である請求項(1)〜(6)にそれぞ
れ記載の重仮設物構築法。
(7) The heavy temporary structure construction method according to each of claims (1) to (6), wherein the receiving surface faces upward.
(8)受面が下向である請求項(1)〜(7)にそれぞ
れ記載の重仮設物構築法。
(8) The heavy temporary structure construction method according to each of claims (1) to (7), wherein the receiving surface faces downward.
(9)横材の上下フランジに受面を上向及び下向に接す
る2個の接続金具によつて該横材を立柱に支持する請求
項(1)〜(6)にそれぞれ記載の重仮設物構築法。
(9) The heavy temporary construction according to each of claims (1) to (6), wherein the cross member is supported on the vertical pillar by two connecting fittings whose receiving surfaces are in contact with the upper and lower flanges of the cross member in an upward and downward direction. Object construction method.
(10)受板に透孔を穿設し該透孔に万力のボルトの先
端部を挿通し、該先端部とボルトとの境界段面を受板に
接して挾持する請求項(1)〜(9)にそれぞれ記載の
重仮設物構築法。
(10) Claim (1) wherein a through hole is bored in the receiving plate, the tip of a bolt in a vise is inserted into the through hole, and the boundary surface between the tip and the bolt is held in contact with the receiving plate. The heavy temporary structure construction methods described in (9) to (9) respectively.
(11)ボルトの先端面に突出刃を設けた請求項(1)
〜(10)それぞれ記載の重仮設物構築法。
(11) Claim (1) in which a protruding blade is provided on the tip end surface of the bolt.
~(10) Heavy temporary structure construction methods as described respectively.
(12)境界段面をボルトに螺合したナットによつて形
成した請求項(10)記載の重仮設物構築法。
(12) The heavy temporary structure construction method according to claim (10), wherein the boundary stepped surface is formed by a nut screwed onto a bolt.
(13)受板とフランジとを万力の両端部のボルトによ
つて挾持する請求項(1)(2)又は(11)記載の重
仮設物構築法。
(13) The heavy temporary structure construction method according to claim (1), (2) or (11), wherein the receiving plate and the flange are clamped by bolts at both ends of a vise.
JP11797088A 1988-05-14 1988-05-14 Heavy temporary construction method Expired - Fee Related JPH0649962B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11797088A JPH0649962B2 (en) 1988-05-14 1988-05-14 Heavy temporary construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11797088A JPH0649962B2 (en) 1988-05-14 1988-05-14 Heavy temporary construction method

Publications (2)

Publication Number Publication Date
JPH01287340A true JPH01287340A (en) 1989-11-20
JPH0649962B2 JPH0649962B2 (en) 1994-06-29

Family

ID=14724783

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11797088A Expired - Fee Related JPH0649962B2 (en) 1988-05-14 1988-05-14 Heavy temporary construction method

Country Status (1)

Country Link
JP (1) JPH0649962B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821073B (en) * 2014-03-14 2018-08-28 江苏四通路桥工程有限公司 A kind of small bridge and its construction method

Also Published As

Publication number Publication date
JPH0649962B2 (en) 1994-06-29

Similar Documents

Publication Publication Date Title
US4379651A (en) Method for releasably rigidly fastening two intersected overlapping metal profiles and means therefor
US6532713B2 (en) Joint structure for joining composite beam and column
JP3655584B2 (en) Column structure of building unit
EP0032418A1 (en) Method and means for releasably rigidly fastening together beams and like profiles
JPH01287340A (en) Construction of heavyweight temporary structure
JP2883262B2 (en) Jig for adjusting joints of steel columns
JP3978361B2 (en) Joints for construction and civil engineering
JPH0738486Y2 (en) Connection structure of columns and beams
JP3220627B2 (en) Building hardware
JP2004232440A (en) Steel structure connector
JPH069131Y2 (en) Connection structure of columns and beams
JP2988813B2 (en) Column-beam joint structure of wooden structure
JP3968007B2 (en) Horizontal material joining device
JP3015580U (en) Joining structure of horizontal materials for wooden structures and its tools
JP2891415B1 (en) Equipment for joining horizontal members in wooden buildings
JPH03206227A (en) Construction method for connecting construction member, etc.
JP3940777B2 (en) Wooden shaft joint
JPH0821012A (en) Connector fitting for building
JPH0243463A (en) Method and device for constructing temporary frame base
JPH1025811A (en) Horizontal member joint structure and reinforcing hardware therefor
JP2006104774A (en) Building member connection structure
JPH04306335A (en) Structure for jointing part between column and beam
JPH03206230A (en) Method for connecting architectural member, etc.
JP2592099Y2 (en) Metal fittings
JPH03206231A (en) Method for connecting architectural member, etc.

Legal Events