JPH01268808A - Method for operating lowered stock level in blast furnace - Google Patents
Method for operating lowered stock level in blast furnaceInfo
- Publication number
- JPH01268808A JPH01268808A JP9493488A JP9493488A JPH01268808A JP H01268808 A JPH01268808 A JP H01268808A JP 9493488 A JP9493488 A JP 9493488A JP 9493488 A JP9493488 A JP 9493488A JP H01268808 A JPH01268808 A JP H01268808A
- Authority
- JP
- Japan
- Prior art keywords
- tuyere
- blasting
- furnace
- raw ore
- positions
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 12
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 claims abstract description 16
- 239000001301 oxygen Substances 0.000 claims abstract description 16
- 229910052760 oxygen Inorganic materials 0.000 claims abstract description 16
- 238000002485 combustion reaction Methods 0.000 claims abstract description 5
- 238000009423 ventilation Methods 0.000 claims description 12
- 239000000463 material Substances 0.000 abstract description 4
- 238000002844 melting Methods 0.000 abstract description 3
- 230000008018 melting Effects 0.000 abstract description 3
- 238000005422 blasting Methods 0.000 abstract 8
- 230000001276 controlling effect Effects 0.000 abstract 1
- 238000007664 blowing Methods 0.000 description 6
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 238000004140 cleaning Methods 0.000 description 3
- 239000000571 coke Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 239000002184 metal Substances 0.000 description 3
- 229910052751 metal Inorganic materials 0.000 description 3
- 230000005855 radiation Effects 0.000 description 3
- 230000003247 decreasing effect Effects 0.000 description 2
- 238000004090 dissolution Methods 0.000 description 2
- 239000007789 gas Substances 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 239000002893 slag Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
- 238000007790 scraping Methods 0.000 description 1
Landscapes
- Manufacture Of Iron (AREA)
Abstract
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、高炉の減尺操業方法に関する。[Detailed description of the invention] [Industrial application field] The present invention relates to a method for reducing the size of a blast furnace.
周知のように、減尺操業は、高炉改修時や中間補修時に
おいて、炉内装入物を全量コークスに置換して徐々にほ
ぼ羽口レベルまで減尺する方法である。As is well known, the scale reduction operation is a method that replaces all of the contents in the furnace with coke and gradually reduces the scale to almost the tuyere level during blast furnace renovation or intermediate repair.
かかる減尺操業においては、各羽目からの送風を減尺末
期まで均等化させることが重要である。In such scale reduction operations, it is important to equalize the air blowing from each panel until the end of scale reduction.
しかし、実際の操業では、炉壁付着物または生鉱の局部
的な脱落、落下により、その部位の送風条件が乱れ、最
終的には温度降下、溶銑滓流路の遮断等を生じ、その部
位の羽口へ溶銑滓が逆流して羽口が閉塞し、遂には送風
が不能になる。その結果、前記部位での炉内コークスの
消費および鉄鉱石等の溶解が不能となり、原料荷下りが
停止し減尺が行うことができず、最終的に半溶融の鉄鉱
石を含む内容物の局部的な残留を招く。However, in actual operations, local shedding or falling of furnace wall deposits or raw ore may disrupt the air blowing conditions in that area, eventually causing a drop in temperature, blocking of the hot metal slag flow path, etc. Hot metal slag flows back into the tuyere, clogging the tuyere and eventually making it impossible to blow air. As a result, it became impossible to consume the coke in the furnace and melt the iron ore, etc. in the above-mentioned area, and the unloading of raw materials was stopped, making it impossible to reduce the size, and eventually the contents, including semi-molten iron ore, Causes local residue.
このように炉内残留物を多く残すことは、その後の炉内
残留物の掻き出し作業に大きな支障となり、特に短期に
作業を終了しなければならない中間補修時には大きなネ
ックとなる。Leaving a large amount of residue in the furnace in this way becomes a major hindrance to the subsequent work of scraping out the residue in the furnace, and becomes a major bottleneck especially during intermediate repairs where the work must be completed in a short period of time.
上記の事態を避けるためには、第1法として事前に炉内
をクリーニングして炉壁付着物を除去することが行われ
ていた。また考えられる第2法としては、羽口閉塞が発
生した時点で減尺操業を一時停止した後、さらにコーク
スを装入し、送風ノズルおよび羽口を整備し、次いで再
送風することが考えられる。In order to avoid the above situation, the first method is to clean the inside of the furnace in advance to remove deposits on the furnace wall. A second possible method would be to temporarily stop the reduced scale operation when tuyere blockage occurs, then charge more coke, prepare the blast nozzle and tuyere, and then start blowing again. .
しかし、上記の第1法では、事前クリーニングを実施す
るとしてもその実施効果が低く、かつ実施に多大な手間
とコストを要する。また第2法では、その実施に伴う分
だけ減尺操業時間が延長してしまい、しかもその後に再
発する虞れがつきまとう。However, in the first method described above, even if preliminary cleaning is performed, its implementation effect is low, and implementation requires a great deal of effort and cost. Furthermore, in the second method, the reduction operation time is extended by the amount associated with its implementation, and there is a risk that the problem will reoccur later.
そこで、本発明の主たる目的は、減尺操業中に羽口閉塞
等のトラブルを未然に防止でき、また周方向に均等なガ
ス流れおよび減尺を実施でき、も、2て従来例にみられ
る減尺操業時間の延長やクリーニングに伴うコスト増を
回避できる減尺操業法を提供することにある。Therefore, the main purpose of the present invention is to prevent troubles such as tuyere clogging during scale reduction operations, and to enable uniform gas flow and reduction in the circumferential direction, as well as to avoid problems seen in conventional examples. It is an object of the present invention to provide a scale reduction operation method that can avoid an extension of the scale reduction operation time and an increase in costs associated with cleaning.
上記課題は、各送風枝管を通る送風流量および各羽口前
の温度のうち少くとも現送風流量に基いて各羽口位置ご
との通風状態を把握し、この通風状態が各羽口位置にお
いて均一になるよう、各羽口からの送風流量を制御する
こと、及び/又は通風状態が悪い送風枝管に酸素富化を
し羽口前燃焼温度の上昇をはかることを減尺操業中に行
うことで解決できる。The above problem is to understand the ventilation condition for each tuyere position based on at least the current flow rate of the air flow rate passing through each ventilation branch pipe and the temperature in front of each tuyere, and to determine whether this ventilation condition is at each tuyere position. During reduced-scale operation, control the flow rate of air from each tuyere so that it is uniform, and/or enrich the air branch pipes with poor ventilation with oxygen to increase the combustion temperature before the tuyere. This can be solved.
本発明に従って、各送風枝管での送風流量を知れば、炉
内付着物が羽口前に脱落したり生鉱下りが生じると送風
条件が悪くなる現象があるため、逆に送風流量に基いて
炉内付着物の脱落や生鉱下りを検知できる。そして、送
風流量が周方向のある個所で極度に低下した場合、その
現象を生じたと判断できる。According to the present invention, if the air flow rate in each air blowing branch pipe is known, air blowing conditions may deteriorate if deposits in the furnace fall off before the tuyeres or raw ore falls, so conversely, it is possible to It is possible to detect the falling off of deposits inside the furnace and the falling of raw ore. If the air flow rate drops extremely at a certain point in the circumferential direction, it can be determined that this phenomenon has occurred.
しかるに、この判断結果に基いて、その現象を生じてい
ると推定される羽目前に対して、送風量を増大させると
、およびまたは酸素富化を行うと、脱落した炉内付着物
または生鉱の溶解を促進でき、やがて通風条件が周方向
に均一化できる。もって、この方策を他の減尺操業制御
要素と併せて実施することで、炉内付着物や生鉱の炉内
残留ならびに羽目閉塞等を確実に未然に防止できる。However, based on this judgment result, if the air flow rate is increased and/or oxygen enrichment is performed when the phenomenon is estimated to be occurring, the deposits or raw ore that have fallen off inside the furnace will be removed. The dissolution of the material can be promoted, and the ventilation conditions can eventually be made uniform in the circumferential direction. Therefore, by implementing this measure in conjunction with other scale reduction operation control elements, it is possible to reliably prevent deposits in the furnace, raw ore remaining in the furnace, clogging of the siding, etc.
他方、本発明者の知見によれば、熱風量の増大のみでは
、効果が薄いこともあるので、羽口前燃焼温度の上昇、
たとえば酸素富化などを併用すると、脱落炉内付着物や
生鉱の熔解を一層確実に行うことができる。On the other hand, according to the findings of the present inventors, increasing the amount of hot air alone may have little effect; therefore, increasing the combustion temperature before the tuyere,
For example, when oxygen enrichment is used in combination, it is possible to more reliably melt deposits in the dropping furnace and raw ore.
以下本発明を図面を参照しながらさらに詳説する。 The present invention will be explained in more detail below with reference to the drawings.
第1図において、1は高炉で、その羽口2としては、た
とえば第4図に示すように、28個形成され、これら羽
口2に対して、送風環状管3から分岐した送風枝管4.
4・・・が連っている。5は熱風炉で、ブロワ−6によ
り供給される空気を熱風化して、送風主管6を介して前
記送風環状管3へ熱風を送るようになっている。また各
送風枝管4.4・・・には開度可変の送風制御弁7,7
・・・がそれぞれ設けられている。In FIG. 1, reference numeral 1 denotes a blast furnace, of which 28 tuyeres 2 are formed, for example, as shown in FIG. ..
4... are in a row. Reference numeral 5 denotes a hot blast furnace, which heats air supplied by a blower 6 and sends hot air to the annular blast pipe 3 through a main blast pipe 6. In addition, each blower branch pipe 4.4... has a blower control valve 7, 7 whose opening degree is variable.
... are provided for each.
上記の設備は基本的に公知のものであるが、本発明では
酸素供給管9が、たとえば第2図のように、送風枝管4
,4・・・に連通される。酸素供給管9は、酸素ホルダ
ー11から酸素をブロワ−12により送るもので、その
途中には流量調量弁13が設けられる。14は各送風枝
管に設けられた流量計である。Although the above-mentioned equipment is basically known, in the present invention, the oxygen supply pipe 9 is connected to the blower branch pipe 4 as shown in FIG.
, 4.... The oxygen supply pipe 9 is used to send oxygen from an oxygen holder 11 using a blower 12, and a flow rate regulating valve 13 is provided in the middle of the pipe. 14 is a flow meter provided in each blower branch pipe.
他方、各送風枝管4の直線部後端に放射温度計15が設
けられ、炉内装入物の輝度に基いてその温度を測定する
ようになっている。また、必要により羽口2上に周方向
にたとえば羽口の数と同じ数をもって炉壁温度計16が
設けられる。On the other hand, a radiation thermometer 15 is provided at the rear end of the linear portion of each blower branch pipe 4, and is adapted to measure the temperature of the contents in the furnace based on the brightness. Further, if necessary, furnace wall thermometers 16 are provided on the tuyere 2 in the circumferential direction, for example, in the same number as the number of tuyeres.
上記の設備の下で次のような減尺操業が行なわれる。す
なわち、第1図のように当初炉内装入物のレベルがり、
であり、減尺に際してコークスに置換しつつレベルL2
まで減尺する過程で、炉内付着物Mの落下や生鉱Rの荷
下りを、各流量計14.14・・・および放射温度計1
5により検知する。各流量計14のうち1つまたは複数
の羽口部位で送風流量が他の部位より極度に低下したな
らば、その羽口部位での炉内付着物Mの落下や生鉱Rの
荷下りがあったと推定される。また、ある羽目部位での
温度が他の部位より極度に低下した場合においても同推
定を行う。The following scale reduction operations are carried out under the above equipment. In other words, as shown in Fig. 1, the level of the contents in the furnace initially increased;
, and when reducing the scale, the level L2 is
In the process of reducing the size to
Detected by 5. If the air flow rate at one or more tuyeres of each flow meter 14 is extremely lower than other locations, the fall of deposits M in the furnace and the unloading of raw ore R at that tuyere are It is estimated that there was. Furthermore, the same estimation is performed even when the temperature in a certain part of the lining is extremely lower than in other parts.
この場合、対応する羽口2について、送風制御弁7の開
度を大きくする又は、対応羽口の開度はそのままでその
他の羽目開度を小さくする、あるいは酸素供給管9を介
して酸素の添加を行う手段のうち1または併行して実施
する。これによって、脱落炉内付着物Mや生鉱Rの溶解
が促進され、やがて他の部位と同じ通風条件とすること
ができる。In this case, for the corresponding tuyere 2, the opening degree of the blow control valve 7 is increased, or the opening degree of the corresponding tuyere remains the same but the other tuyere opening degrees are decreased, or oxygen is supplied via the oxygen supply pipe 9. The addition may be carried out by one of the means or in parallel. This promotes the dissolution of deposits M in the falling furnace and raw ore R, and eventually the same ventilation conditions as other parts can be achieved.
なお、上記例において、炉壁温度計16からの温度信号
を炉内付着物Mの脱落の有無の判断情報としてもよい。In the above example, the temperature signal from the furnace wall thermometer 16 may be used as information for determining whether or not the in-furnace deposits M have fallen off.
また、放射温度計15の位置に元来覗き窓があるので、
そこから作業員が覗いて、炉壁付着物Mの落下環を判断
するようにしてもよい。Also, since there is originally a viewing window at the position of the radiation thermometer 15,
An operator may look through it and judge the falling ring of the matter M attached to the furnace wall.
次に実施例を示す。 Next, examples will be shown.
容量2100m”の高炉において減尺操業を総送風量1
20ONm”/分としながら実施したところ、第5図に
示すように、患5の羽口の送風量が低下したので、患4
〜患6の送風枝管の流量調量弁を全開のまま他の弁の開
度を100%から60%に低下させたところ、N115
羽口での送風量が徐々に増大し、炉内付着物の溶解が完
了したと推定できた。またその完了時点で、寛4〜6以
外の弁について開度を70%に、更にその後全弁につい
て全開にしたところ、通風条件がほぼ均一となった。Reduced scale operation in a blast furnace with a capacity of 2100m" with a total air flow of 1
20 ONm"/min, as shown in Figure 5, the air flow rate of the tuyere of patient 5 decreased, so
~ When the flow control valve of patient 6's ventilation branch pipe was left fully open and the opening of other valves was reduced from 100% to 60%, N115 was detected.
The amount of air blown at the tuyere gradually increased, and it was assumed that the melting of the deposits inside the furnace was completed. At the time of completion, the opening degrees of the valves other than Kan 4 to 6 were set to 70%, and then all the valves were fully opened, and the ventilation conditions became almost uniform.
また、その後、第6図のように患3羽口近くで生鉱下り
が発生したので、階2〜患4羽口で酸素量を1%増加さ
せる酸素富化を行ったところ、患3羽口前温度が徐々に
高まった。Later, as shown in Figure 6, raw ore descent occurred near the 3 affected tuyeres, so oxygen enrichment was carried out to increase the amount of oxygen by 1% at the 2nd to 4th affected tuyeres, and the 3 affected tuyere The temperature in front of his mouth gradually increased.
以上の通り、本発明によれば、減尺操業中における羽口
閉塞等のトラブル等を未然に防止できるとともに、周方
向に各部位において均一なガス流れを行うことができる
とともに、減尺操業時間の延長やクリーニング実施を回
避できるなどの利点がもたらされる。As described above, according to the present invention, it is possible to prevent troubles such as tuyere clogging during scale reduction operation, to ensure uniform gas flow in each part in the circumferential direction, and to increase the time of scale reduction operation. This provides advantages such as extending the time period and avoiding the need for cleaning.
第1図は本発明法を実施するための設備の概略図、第2
図はその羽口部の詳細断面図、第3図は炉内付着物の生
成状況縦断面図、第4図はその水平断面図、第5図およ
び第6図は実施例での操業例のグラフである。
1・・・高炉、2・・・羽口、3・・・送風環状管、4
・・・送風枝管、5・・・熱風炉、7・・・流量調整弁
、9・・・酸素供給管、11・・・酸素ホルダー、13
・・・流量調整弁、14・・・流量計、15・・・放射
温度計。
特許出願人 住友金属工業株式会社
第1図
第2図Figure 1 is a schematic diagram of the equipment for carrying out the method of the present invention, Figure 2
The figure is a detailed cross-sectional view of the tuyere part, Figure 3 is a vertical cross-sectional view of the formation of deposits in the furnace, Figure 4 is a horizontal cross-sectional view, and Figures 5 and 6 are examples of operation in the example. It is a graph. 1... Blast furnace, 2... Tuyere, 3... Air blowing annular pipe, 4
...Blower branch pipe, 5...Hot stove, 7...Flow rate adjustment valve, 9...Oxygen supply pipe, 11...Oxygen holder, 13
...Flow rate adjustment valve, 14...Flow meter, 15...Radiation thermometer. Patent applicant: Sumitomo Metal Industries, Ltd. Figure 1 Figure 2
Claims (1)
のうち少くとも現送風流量に基いて各羽口位置ごとの通
風状態を把握し、この通風状態が各羽口位置において均
一になるよう、各羽口からの送風流量を制御すること、
及び/又は通風状態が悪い送風枝管に酸素富化をし羽口
前燃焼温度の上昇をはかることを減尺操業中に行うこと
を特徴とする高炉の減尺操業方法。(1) Understand the ventilation condition for each tuyere position based on at least the current flow rate of the air flow rate passing through each ventilation branch pipe and the temperature in front of each tuyere, and ensure that this ventilation condition is uniform at each tuyere position. Control the flow rate of air from each tuyere so that
and/or a method for reducing the size of a blast furnace, characterized in that during the reduced size operation, enriching the blower branch pipes with poor ventilation conditions with oxygen to increase the combustion temperature before the tuyere.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9493488A JPH01268808A (en) | 1988-04-18 | 1988-04-18 | Method for operating lowered stock level in blast furnace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9493488A JPH01268808A (en) | 1988-04-18 | 1988-04-18 | Method for operating lowered stock level in blast furnace |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH01268808A true JPH01268808A (en) | 1989-10-26 |
Family
ID=14123789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9493488A Pending JPH01268808A (en) | 1988-04-18 | 1988-04-18 | Method for operating lowered stock level in blast furnace |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH01268808A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02282408A (en) * | 1989-04-21 | 1990-11-20 | Nkk Corp | Lowered stock level operation method for blast furnace |
-
1988
- 1988-04-18 JP JP9493488A patent/JPH01268808A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02282408A (en) * | 1989-04-21 | 1990-11-20 | Nkk Corp | Lowered stock level operation method for blast furnace |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6835229B2 (en) | Method and apparatus for clearing a powder accumulation in a powder delivery tube | |
JPH01268808A (en) | Method for operating lowered stock level in blast furnace | |
JP2914072B2 (en) | Method for removing deposits on furnace wall of blast furnace | |
JP5411466B2 (en) | Iron bath melting furnace and method for producing molten iron using the same | |
KR100368269B1 (en) | Apparatus for monitoring obstruction of tuyere of blast furnace | |
JP2002115007A (en) | Structure for inner wall surface at lower part in blast furnace | |
CN115198044B (en) | Method for rapidly treating freezing of blast furnace hearth | |
CN102534092A (en) | Method for protecting top-bottom combined blown converter | |
JP3444046B2 (en) | Chromium ore powder charging method in smelting reduction furnace | |
JP3292012B2 (en) | Iron smelting reduction equipment | |
CN117778648A (en) | Blast furnace belly pipe cleaning method | |
Ostrowski et al. | Blast furnace operations with injected coal at Weirton | |
JP2000328118A (en) | Structure of blasting tube for blowing hot blast into blast furnace and method for changing blasting quantity from tuyere in blast furnace | |
JP2022152721A (en) | Operation method of blast furnace | |
JP4979209B2 (en) | How to adjust furnace profile | |
JP2741140B2 (en) | Blast furnace operation method | |
JPH07268416A (en) | Operation of blast furnace | |
JP2003253314A (en) | Method for operating blast furnace | |
JP3229069B2 (en) | End point determination method for copper converter operation | |
JPS5935962B2 (en) | How to reheat a dormant blast furnace | |
JPH08225812A (en) | Blast furnace operation | |
JPS62124209A (en) | Method for measuring interior of furnace | |
JP2001262208A (en) | Method for operating blast furnace | |
JPH0129845B2 (en) | ||
JPH0293010A (en) | Method for removing sticking material at circumference of tuyere in smelting reduction furnace |