JPH0122405B2 - - Google Patents

Info

Publication number
JPH0122405B2
JPH0122405B2 JP56032578A JP3257881A JPH0122405B2 JP H0122405 B2 JPH0122405 B2 JP H0122405B2 JP 56032578 A JP56032578 A JP 56032578A JP 3257881 A JP3257881 A JP 3257881A JP H0122405 B2 JPH0122405 B2 JP H0122405B2
Authority
JP
Japan
Prior art keywords
formwork
slope
formworks
connection body
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP56032578A
Other languages
Japanese (ja)
Other versions
JPS57146835A (en
Inventor
Koji Okudaira
Tadamori Takino
Hidetaka Mizukami
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MUSASHI KENSETSU KOGYO KK
OKABE KK
Original Assignee
MUSASHI KENSETSU KOGYO KK
OKABE KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MUSASHI KENSETSU KOGYO KK, OKABE KK filed Critical MUSASHI KENSETSU KOGYO KK
Priority to JP3257881A priority Critical patent/JPS57146835A/en
Publication of JPS57146835A publication Critical patent/JPS57146835A/en
Publication of JPH0122405B2 publication Critical patent/JPH0122405B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 この発明は、地山の崩壊を防止し、その安定化
を図るために実施される法面に補強構造物を構築
する方法及びその方法に使用される型枠に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a reinforcing structure on a slope, which is carried out to prevent the collapse of the ground and stabilize the same, and a formwork used in the method. It is.

従来、地山を補強するため、第1図に示したよ
う、法面A上にコンクリート類によつて格子状の
法枠構造物Bを構築している。そして、その施工
法としては、プレキヤストコンクリート部材を用
いて法枠を組立てる方法や、一般のコンクリート
構造物の施工と同様に、現場において配筋し、型
枠を取付けてこれにコンクリート類を打設する方
法が実施されている。ところが、プレキヤストコ
ンクリート部材を用いる工法では、その部材の重
量が大きく、斜面上での施工が困難なため、近頃
は現場打ち工法によるものが多く実施されてい
る。
Conventionally, in order to reinforce the ground, a lattice-shaped slope structure B is constructed using concrete on a slope surface A, as shown in FIG. The construction methods include assembling a legal framework using precast concrete members, and similar to the construction of general concrete structures, arranging reinforcement on site, installing formwork, and pouring concrete into it. The method of setting is implemented. However, in the construction method using precast concrete members, the weight of the members is large and it is difficult to construct on slopes, so recently, the cast-in-place method is often used.

この現場打ちによる方法は、一般に第2図に示
したように、法面A上に格子状に鉄筋Cを配設す
ると共に、型枠Dを設置してコンクリート類を打
設するようにしている。しかし、この方法でもか
なりの重量のある型枠を斜面に運び上げて設置
し、また型枠組みも足場の悪い斜面上で行なわな
ければならないため、施工性が非常に悪く、施工
費が高価である等多くの欠点がある。
Generally, as shown in Figure 2, this cast-in-place method involves arranging reinforcing bars C in a lattice pattern on the slope A, installing formwork D, and pouring concrete. . However, even with this method, the formwork, which is quite heavy, must be carried up the slope and installed, and the formwork must also be installed on the slope with poor footing, making it very difficult to construct and expensive. There are many drawbacks.

この発明は、前記従来の欠点を解決するために
なされたもので、軽量で折畳み自在な型枠を連結
し、この連結した各型枠を扁平に折畳んだ状態で
施工場所の上部に運び、各型枠を上方から順次下
方に設置して行き、型枠の設置後鉄筋を配設して
コンクリート類を打設するようにし、これによつ
て最も手数と労力を要する型枠の組付けを著しく
簡易化し、地山補強構造物の施工の経済性と能率
化の向上を図らんとするものである。
This invention was made in order to solve the above-mentioned conventional drawbacks, and involves connecting lightweight and collapsible formwork, transporting each connected formwork in a flat folded state to the upper part of the construction site. Each formwork is installed sequentially from the top to the bottom, and after the formwork is installed, reinforcing bars are placed and concrete is poured, thereby eliminating the most time-consuming and labor-intensive formwork assembly. The aim is to significantly simplify and improve the economic efficiency and efficiency of construction of earth reinforcement structures.

以下、この発明の実施例を図面を参照して説明
する。
Embodiments of the present invention will be described below with reference to the drawings.

第3図は本発明施工方法において使用する型枠
連結体の斜面図、第4図は同型枠連結体の折畳み
の態様を示した平面図で、これらの図において1
は平面方形の囲枠状に形成された型枠で、ダンボ
ール等の紙板や軽金属板、合成樹脂板等の軽い板
材を用い、各隅角部は折線等3によつて折曲自在
となつている。また、型枠1の下辺部には所要間
隔をおいて多数の切込4,4が設けられている。
Fig. 3 is a perspective view of the formwork connection body used in the construction method of the present invention, and Fig. 4 is a plan view showing the manner in which the formwork connection body is folded.
is a formwork formed in the shape of a rectangular frame in plan, using light board materials such as paper board such as cardboard, light metal board, synthetic resin board, etc., and each corner part can be bent freely by folding lines etc. 3. There is. Further, a large number of notches 4, 4 are provided at required intervals on the lower side of the formwork 1.

そして、前記の型枠1はその適数個をそれぞれ
互に所定の間隔が保持できるように屈曲自在なロ
ープ状の連結具5,5によつて結合し、型枠連結
体Eが構成される。連結具5の材料としては柔軟
性のある繊維製ロープ或はワイヤーロープ等が好
適である。そして、連結具5はその端部を型枠1
に貫通させ、端末に抜止めのためのコブ6等を設
けておけばよい。
Then, an appropriate number of the formworks 1 are connected by bendable rope-like connectors 5, 5 so as to maintain a predetermined distance from each other, thereby forming a formwork connection body E. . A suitable material for the connector 5 is a flexible fiber rope or wire rope. Then, the connector 5 connects its end to the formwork 1
It is sufficient that the terminal is provided with a knob 6 or the like to prevent it from coming off.

型枠連結体Eの設置にあたつては、第3図のよ
うに連結具5,5を直線に伸ばした状態とし、ま
た、型枠連結体Eの運搬や収納、保管の場合に
は、第4図のように各型枠1を扁平に折畳んで重
ね合わせるようにする。この場合、連結体5は屈
曲自在なため、型枠1の折畳みや重ね合せに支障
をきたすことはない。
When installing the formwork connector E, the connectors 5, 5 should be stretched in a straight line as shown in Fig. 3, and when transporting, housing, or storing the formwork connector E, As shown in FIG. 4, each formwork 1 is folded flat and stacked on top of each other. In this case, since the connecting body 5 is bendable, folding and stacking of the formwork 1 will not be hindered.

第5図及び第6図は、型枠1の他の実施例と、
同型枠の折畳みの態様を示したもので、この実施
例のものは、連結具5を取付けない辺の各中央部
にも折線3a,3aを設けて、第6図のようにそ
の辺を内方に折込むようにしている。このような
折畳みをすれば、折畳み状態での厚さは増加する
が巾が縮少される。なお、型枠1の折畳みの構成
は、前述の実施例に限るものではなく、その他適
宜な折畳方法のものを採用することができる。
5 and 6 show other embodiments of the formwork 1,
This figure shows how the same formwork is folded, and in this example, folding lines 3a, 3a are also provided at the center of each side on which the connecting tool 5 is not attached, and the sides are folded inside as shown in Fig. 6. I try to fold it towards the side. By folding in this manner, the thickness in the folded state increases, but the width decreases. Note that the folding structure of the formwork 1 is not limited to the above-described embodiment, and other suitable folding methods can be adopted.

この発明の施工方法は、前述のような型枠連結
体Eを使用して行なわれる。
The construction method of the present invention is carried out using the formwork connector E as described above.

まず、型枠連結体Eは第4図或は第6図のよう
に所要数連結された型枠1,1をそれぞれ扁平に
折畳んで重ね合せた状態で、第7図のように施工
場所の上部に運び上げ、最上部の型枠1aを法面
A上にアンカー7等を利用して固定し、次いで型
枠1aに連結されている他の型枠1b〜1nを法
面Aに沿つて順次連結具5,5を伸長させて下げ
降しながら型枠を第3図、第5図のような使用状
態に吊下げ拡開して行くのである。それによつて
各型枠1a〜1nは第8図のように拡開され、連
結具5の長さに相当する間隔を保つて、順次下方
に連設されることになる。この型枠1a〜1nの
設置は、型枠自体が軽量であるため、作業は簡易
にしかも迅速に行なうことができる。なお、この
場合、各型枠1b〜1nは、最上部の型枠1aに
連結具5を介して吊下支持されているので、その
状態のままとしておいてもよいが、必要に応じて
型枠を各個に或は何個おきかにアンカーやペツグ
等を用いて法面Aに固定させるようにしてもよ
い。
First, the formwork connected body E is made by folding the required number of formworks 1, 1 connected flatly and overlapping each other as shown in Fig. 4 or Fig. 6, and moving it to the construction site as shown in Fig. 7. The uppermost formwork 1a is fixed on the slope A using anchors 7, etc., and then the other formworks 1b to 1n connected to the formwork 1a are moved along the slope A. Then, the connectors 5, 5 are successively extended and lowered to hang and expand the formwork into the usage condition as shown in FIGS. 3 and 5. As a result, the molds 1a to 1n are expanded as shown in FIG. 8, and are successively arranged downward at intervals corresponding to the length of the connector 5. The installation of the formworks 1a to 1n can be carried out easily and quickly since the formworks themselves are lightweight. In this case, each of the formworks 1b to 1n is suspended and supported by the uppermost formwork 1a via the connector 5, so they may be left in that state, but if necessary, The frames may be fixed to the slope A using anchors, pegs, etc. for each frame or every few frames.

上述の作業によつて、法面Aの上下方向に対す
る型枠の設置が行なえることになる。そして、こ
のような型枠連結体Eによる型枠設置作業を法面
Aの横方向に沿つて繰返し行なつて行けば、所定
の型枠設置が完了するのである。なお、型枠の設
置にあたり、法面Aの横方向における隣接型枠の
間隔は、所定の寸度に合せて行なわれることは言
うまでもない。また、法面Aは多くの凹凸が形成
されているのが通常であつて、そのため、型枠1
の下縁と法面Aとの間に大きな空隙のできること
があるが、そのような場合には、型枠1の下部に
ある切込4を利用して、型枠1の下部を部分的に
外方に折曲げてやるようにすれば、型枠の下縁と
法面Aとのなじみがよくなつて、空隙が小さくな
り、後に打込むコンクリート類の漏出を防止でき
る。
By the above-mentioned work, the formwork can be installed in the vertical direction of the slope A. Then, by repeating the formwork installation work using the formwork connection body E along the lateral direction of the slope A, the predetermined formwork installation is completed. It goes without saying that when installing the formwork, the interval between adjacent formwork in the lateral direction of the slope A is adjusted to a predetermined dimension. In addition, the slope A usually has many unevenness, and therefore the formwork 1
In some cases, a large gap may be formed between the lower edge of the formwork 1 and the slope A. In such cases, the lower part of the formwork 1 can be partially cut using the notch 4 at the bottom of the formwork 1. By bending it outward, the lower edge of the formwork will fit better with the slope A, the gap will become smaller, and the leakage of concrete to be poured later can be prevented.

法面A上への型枠の設置が終えれば、第9図の
ように各型枠間に鉄筋8,8の配設を行なう。そ
して、これらの鉄筋8,8はその所要個所をアン
カー9,9によつて固定される。また、この場
合、各型枠1は相互にセパレータ10,10(第
9図鎖線で示す)によつて連結してもよく、或は
配設された鉄筋8に固定してもよい。なお、鉄筋
8の配設にあたつて連結具5がじやまになるよう
な場合には、連結具を切断して除去するのがよ
い。その場合には、各型枠1はそれぞれアンカー
やペツグを用いる等適宜な手段で法面Aに固定し
ておけばよい。
Once the formwork has been installed on the slope A, reinforcing bars 8, 8 are placed between each formwork as shown in FIG. These reinforcing bars 8, 8 are fixed at required locations by anchors 9, 9. Further, in this case, the formworks 1 may be connected to each other by separators 10, 10 (shown by chain lines in FIG. 9), or may be fixed to the reinforcing bars 8 provided. In addition, if the connecting tool 5 becomes awkward when installing the reinforcing bar 8, it is preferable to cut the connecting tool and remove it. In that case, each formwork 1 may be fixed to the slope A by appropriate means such as using anchors or pegs.

鉄筋8の配設を終えれば、必要に応じて連結具
5を除去し、各型枠1間にコンクリート或はモル
タルを打設するのである。このコンクリート類が
硬化後は、通常、設置した型枠1は撤去される
が、型枠1がダンボールのような紙製のものであ
れば、所謂使い捨てとして撤去せずにそのまま放
置しておいてもよい。
Once the reinforcing bars 8 have been placed, the connectors 5 are removed if necessary, and concrete or mortar is poured between the formworks 1. After the concrete hardens, the installed formwork 1 is usually removed, but if the formwork 1 is made of paper such as cardboard, it can be left as is without being removed as it is disposable. Good too.

なお、法枠等の構造物においては、その隅部等
の施工に平面三角形或は梯形等の型枠を要するこ
とがあるが、このような場合には、それに適合す
る形状の型枠を作製して前述の型枠連結体と連設
して使用することができる。
In addition, for structures such as legal frameworks, formwork such as planar triangular or trapezoidal forms may be required for construction at the corners, but in such cases, formwork with a shape that is compatible with that may be manufactured. It can be used in conjunction with the above-mentioned formwork connection body.

以上説明したように、この発明は、地山を補強
する法枠等の構造物の現場打ち施工において、多
大な労力と経費を要する型枠の設置を、軽量かつ
折畳み自在な型枠を連結した型枠連結体を用いる
ことによつて極めて簡易なものにすると共に、こ
の型枠の設置を先行させて、その後に鉄筋の配設
を行なうようにしたので、鉄筋の配設もすでに設
置された型枠を利用して容易、迅速、適確に行な
うことができ、全体として施工性が著しく向上で
き、工期と工費を大巾に節減することができる等
多くの優れた効果を発揮するものである。
As explained above, this invention aims to replace the installation of formwork, which requires a great deal of labor and expense, by connecting lightweight and collapsible formwork in the on-site construction of structures such as legal frames for reinforcing the ground. By using formwork connections, we made it extremely simple, and because the formwork was installed first and the reinforcing bars were placed afterwards, the reinforcing bars were already installed. It can be carried out easily, quickly, and accurately using formwork, and has many excellent effects, such as significantly improving workability as a whole and greatly reducing construction time and construction costs. be.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は法面に補強構造物を構築した状態を示
した斜面図、第2図は従来の現場打ちによる施工
状態を示した平面図、第3図は本発明の施工方法
において使用する型枠連結体の実施例を示した斜
面図、第4図は同型枠連結体の折畳状態を示した
平面図、第5図は型枠連結体の他の実施例を示し
た平面図、第6図は同型枠連結体の折畳状態を示
した平面図、第7図は折畳んだ型枠連結体を法面
上部に設置したところを示した側面図、第8図は
同じく型枠連結体を拡開して各型枠を設置したと
ころを示した側断面図、第9図は型枠間に鉄筋を
配設したところを示した平面図である。 A…法面、B…法枠、C…鉄筋、D…型枠、E
…型枠連結体、1…型枠、3…折線、4…切込、
5…連結具、6…コブ、7,9…アンカー、8…
鉄筋、10…セパレータ。
Fig. 1 is a slope view showing the reinforcing structure constructed on the slope, Fig. 2 is a plan view showing the conventional cast-in-place construction, and Fig. 3 is the mold used in the construction method of the present invention. FIG. 4 is a perspective view showing an embodiment of the frame connection body; FIG. 4 is a plan view showing the same formwork connection body in a folded state; FIG. Figure 6 is a plan view showing the formwork connection in the folded state, Figure 7 is a side view showing the folded formwork connection installed on the top of the slope, and Figure 8 is the same formwork connection. FIG. 9 is a side sectional view showing the body expanded and each formwork installed, and FIG. 9 is a plan view showing reinforcing bars arranged between the formworks. A...Slope, B...Slope, C...Reinforcement, D...Formwork, E
...Formwork connection body, 1...Formwork, 3...Fold line, 4...Notch,
5...Connector, 6...Kob, 7, 9...Anchor, 8...
Rebar, 10... Separator.

Claims (1)

【特許請求の範囲】 1 軽量な板材を用いて、囲枠状かつ折畳み自在
に形成した型枠の複数個を、互に所定長さの屈曲
自在なロープ状連結具により直列に結合して型枠
連結体を構成し、この型枠連結体の複数を施工場
所の上部に所定の間隔をおいて配置し、各型枠連
結体の各型枠を順次連結具を介して下方に吊り下
げ、各型枠連結体を拡開した状態で法面上に設置
し、しかる後型枠間に鉄筋を配設し、次いで型枠
間にコンクリート類を打設することを特徴とす
る、法面補強構造物の施工方法。 2 軽量の板材を用いて、折畳み自在な囲枠状の
型枠を形成し、この型枠の複数個を互に所定長さ
の屈曲自在なロープ状連結具により直列に結合し
たことを特徴とする、法面補強構造物の施工に使
用する型枠連結体。
[Scope of Claims] 1. A mold is created by connecting a plurality of frame-like and foldable formworks using lightweight plate materials in series with each other by bendable rope-like connectors of a predetermined length. A frame connection body is constructed, a plurality of these formwork connection bodies are arranged at a predetermined interval above the construction site, each formwork of each formwork connection body is sequentially suspended downward via a connecting tool, Slope reinforcement characterized by installing each formwork connection body on a slope in an expanded state, then placing reinforcing bars between the formworks, and then pouring concrete between the formworks. Construction methods for structures. 2 A foldable enclosing formwork is formed using lightweight board material, and a plurality of these formworks are connected in series by bendable rope-like connectors of a predetermined length. A formwork connection body used in the construction of slope reinforcement structures.
JP3257881A 1981-03-07 1981-03-07 Construction of slope-reinforcing structure and connected form therefor Granted JPS57146835A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3257881A JPS57146835A (en) 1981-03-07 1981-03-07 Construction of slope-reinforcing structure and connected form therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3257881A JPS57146835A (en) 1981-03-07 1981-03-07 Construction of slope-reinforcing structure and connected form therefor

Publications (2)

Publication Number Publication Date
JPS57146835A JPS57146835A (en) 1982-09-10
JPH0122405B2 true JPH0122405B2 (en) 1989-04-26

Family

ID=12362753

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3257881A Granted JPS57146835A (en) 1981-03-07 1981-03-07 Construction of slope-reinforcing structure and connected form therefor

Country Status (1)

Country Link
JP (1) JPS57146835A (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2056454C (en) * 1989-04-07 2001-07-03 James Heselden Improvements relating to building and shoring blocks
CA2111063C (en) * 1993-02-18 1996-04-23 Gary M. Bach Reinforced cell material
US8721229B2 (en) 2005-11-24 2014-05-13 Hesco Bastion Limited Gabions
CA2632249C (en) 2005-11-24 2016-05-17 Hesco Bastion Limited Gabions
GB2445356B (en) 2007-01-02 2011-05-04 Hesco Bastion Ltd Gabion deployment
MX2009007882A (en) 2007-01-24 2010-02-09 Reynolds Consumer Prod Clamp device for portable porous pavement system.
WO2008091879A1 (en) 2007-01-24 2008-07-31 Reynolds Consumer Products, Inc. Portable porous pavement system and method for assembling such a pavement system
GB2453711B (en) 2007-08-06 2012-01-11 Hesco Bastion Ltd Gabions

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS605092Y2 (en) * 1978-04-25 1985-02-15 岡部株式会社 Core formwork for concrete structure construction

Also Published As

Publication number Publication date
JPS57146835A (en) 1982-09-10

Similar Documents

Publication Publication Date Title
US5596857A (en) Masonry reinforcement
US4865781A (en) Method of constructing a wall
JPH0122405B2 (en)
US5845444A (en) Masonry reinforcement
JP3240964B2 (en) Construction method of pile foundation
JPS6115085Y2 (en)
JP3830055B2 (en) Concrete formwork and method for constructing concrete structure using the concrete formwork
JPH04118423A (en) Precast l type retaining wall
JPS605092Y2 (en) Core formwork for concrete structure construction
JPS6134539B2 (en)
JPH04330119A (en) Building foundation constructing method
JPH0122827Y2 (en)
JPH11107293A (en) Foundation structure of building, foundation construction method, and block for foundation
JPS59165734A (en) Construction of concrete structure
JPS5856265Y2 (en) Reinforcement structure unit
KR200398758Y1 (en) Wale having reinforcement structure for preventing from buckling and falling down
JP2963613B2 (en) Foundation structure and construction method
JP3242160B2 (en) Concrete formwork and its construction method
JPS6232292B2 (en)
JPS6195127A (en) Concrete formwork process
JPH09264031A (en) Form for constructing concrete structure
JPS5810756Y2 (en) Concrete block retaining wall structure
JPH0355638Y2 (en)
JPH0716758Y2 (en) Formwork unit
JPH0220269Y2 (en)