JPH01190841A - Junction structure of reinforced concrete column with steel girder - Google Patents
Junction structure of reinforced concrete column with steel girderInfo
- Publication number
- JPH01190841A JPH01190841A JP1622588A JP1622588A JPH01190841A JP H01190841 A JPH01190841 A JP H01190841A JP 1622588 A JP1622588 A JP 1622588A JP 1622588 A JP1622588 A JP 1622588A JP H01190841 A JPH01190841 A JP H01190841A
- Authority
- JP
- Japan
- Prior art keywords
- joint
- column
- concrete column
- reinforced concrete
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 17
- 239000010959 steel Substances 0.000 title claims abstract description 17
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 12
- 239000004567 concrete Substances 0.000 claims abstract description 15
- 239000002184 metal Substances 0.000 claims description 14
- 238000003466 welding Methods 0.000 claims description 2
- 230000002787 reinforcement Effects 0.000 description 6
- 230000005540 biological transmission Effects 0.000 description 5
- 210000003205 muscle Anatomy 0.000 description 4
- 230000003014 reinforcing effect Effects 0.000 description 4
- 230000003247 decreasing effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 230000035515 penetration Effects 0.000 description 2
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は、鉄筋コンクリート柱と鉄骨梁とを接合する
ための柱・梁接合構造に関するものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a column-beam joint structure for joining a reinforced concrete column and a steel beam.
(従来の技術)
柱を純粋な鉄筋コンクリート柱とし、梁を純粋な鉄骨梁
とする場合、柱と梁との仕口は、梁の上下フランジのみ
あるいは、梁全体を柱に貫通させる梁貫通方式とする場
合が多い。(Conventional technology) When the columns are pure reinforced concrete columns and the beams are pure steel beams, the connection between the columns and beams can be achieved by a beam penetration method in which only the upper and lower flanges of the beams or the entire beam penetrates the column. Often.
かかる場合の柱と梁との仕口部における応力伝達機構は
、専らコンクリートの付着力によるものである。In such a case, the stress transmission mechanism at the joint between the column and the beam is solely due to the adhesive force of the concrete.
(発明が解決しようとする問題点)
しかしながら、柱と梁間の応力伝達をコンクリートの付
着力にのみ、依存するためには鉄骨梁の付着面積を相当
太き(する必要があるため梁断面およびガセットプレー
トを相当大きくする必要がある。また、一般に鉄骨材は
コンクリートの付着が悪いので、梁やガセットプレート
の表面にスタットボルトを突設する等の工夫をこらす必
要があった。さらに、梁やガセットプレートの断面が大
きくなるにつれて、スタッドボルトを取付けると、コン
クリートの回りが著しく低下することが免れず、コンク
リートの付着力を設計値通り期待することは好ましいこ
とでなく危険でさえあった。(Problem to be solved by the invention) However, in order to rely solely on the adhesion force of concrete for the stress transmission between columns and beams, the adhesion area of the steel beams must be considerably thick, so the beam cross section and gusset It is necessary to make the plate quite large.Also, since steel materials generally have poor adhesion to concrete, it was necessary to take measures such as installing stud bolts protruding from the surface of the beam or gusset plate. As the cross section of the plate becomes larger, when stud bolts are attached, the circumference of the concrete is inevitably reduced significantly, and it is not desirable and even dangerous to expect the adhesion force of concrete to be as designed.
このような事がらを鑑みると従来の梁貫通方式は構造の
割りにはあまり効率の良いものではなく、きわめて不経
済な設計になりがちであった。Considering these circumstances, the conventional beam penetration method was not very efficient in terms of structure and tended to be extremely uneconomical in design.
この発明は、このような前記従来の問題点を解消するた
めに提案されたもので、柱を鉄筋コンクリート柱とし、
梁を鉄骨梁とする場合、柱と梁との仕口部における柱・
梁間の応力伝達機構をきわめて効率良いものとして経済
設計を可能にした鉄筋コンフート柱と鉄骨梁とを接合す
るための柱・梁接合構造を提供することを目的とする。This invention was proposed in order to solve the above-mentioned conventional problems, and the column is a reinforced concrete column,
When the beam is a steel beam, the column and beam at the joint between the column and the beam are
The purpose of the present invention is to provide a column-beam connection structure for connecting reinforced comfort columns and steel beams that enables economical design by making the stress transmission mechanism between the beams extremely efficient.
(問題点を解決するための手段)
この発明は、鉄筋コンクリート柱と鉄骨梁との接合構造
であって、鉛直方向に中空閉鎖状の矩形断面形金物とそ
のコーナー部に水平プレートを溶接し一体化した梁接合
金物を、前記鉄筋コンクリート柱の梁接合部に鉄骨梁の
上下フランジ位置に別々に埋設してあるとともに、コン
クリート柱側面で該梁接合金物と鉄骨梁をポルト接合し
てあることを特徴とする。(Means for Solving the Problems) The present invention is a joint structure of a reinforced concrete column and a steel beam, which are integrated by welding a rectangular cross-sectional metal piece with a vertically closed hollow and a horizontal plate to its corner. The beam joint hardware is separately buried in the beam joint part of the reinforced concrete column at the upper and lower flange positions of the steel beam, and the beam joint hardware and the steel beam are port-jointed on the side of the concrete column. do.
(実 施 例)
以下、この発明を図示する第1実施例によって説明する
。(Example) The present invention will be explained below by referring to a first example illustrated in the drawings.
第1図および第2図において、柱1の仕口部に接合金物
2,2が埋設され、この接合金物2゜2によって梁3,
3が柱1の四側部に接合されている。In FIGS. 1 and 2, metal fittings 2, 2 are buried in the joint part of a column 1, and beams 3,
3 are joined to the four sides of the column 1.
柱1は、鉄筋コンクリートによって矩形断面形に構成さ
れている。The column 1 is made of reinforced concrete and has a rectangular cross section.
柱1の主筋4.・・・は、柱1の外周に一定のかぶり厚
を保有して一定間隔おきに配筋され、この主筋4.・・
・の回りにフープ筋5.・・・が主筋4゜・・・の上下
方向に一定間隔おきに配筋されている。Main reinforcement of column 1 4. ... are arranged at regular intervals on the outer periphery of the column 1 with a constant cover thickness, and these main reinforcements 4.・・・
・Hoop muscle around 5. ... are arranged at regular intervals in the vertical direction of the main reinforcement 4° ....
接合金物2は鉛直方向に中空閉鎖状の正方形断面金物2
aとそのコーナー部2bに水平プレート7を溶接一体化
したものである。また、接合金物2の正方形断面金物2
aの成は、接合される梁3,3の梁成に応じて増減され
るもので、梁3の梁成が大きい場合には、成を大きくす
る。The joining metal fitting 2 is a square cross-section metal fitting 2 with a vertically closed hollow.
A and its corner portion 2b are integrally welded with a horizontal plate 7. In addition, the square cross section metal fitting 2 of the joining metal fitting 2
The size of a is increased or decreased depending on the beam size of the beams 3 to be joined, and when the beam size of the beam 3 is large, the size is increased.
接合金物2の成を大きくすると支圧面積が大きくなり、
接合金物2の支圧耐力が著しく高められる。When the size of the joining metal fitting 2 is increased, the bearing pressure area becomes larger,
The bearing pressure strength of the joining hardware 2 is significantly increased.
したがって、柱、梁間の接合強度は、接合金物の成によ
って決まる。接合強度を高めるには成を大きくすればよ
い。Therefore, the strength of the joint between columns and beams is determined by the composition of the joining hardware. In order to increase the bonding strength, it is sufficient to increase the thickness.
このように形成された接合金物2は、柱1の仕口部の主
筋4.・・・とフープ筋5.・・・によって囲まれたコ
ンクリート中に接合される鉄骨梁3゜3フランジ位置の
上下二段に埋設されている。The joint hardware 2 formed in this way is the main reinforcing bar 4 of the joint part of the column 1. ...and hoop muscle 5. It is buried in two stages above and below the 3°3 flange position of the steel beam that will be joined in the concrete surrounded by...
また、接合金物2は、水平プレート7を柱1の各側面部
の中央部に位置した状態に埋設されている。Further, the joining hardware 2 is buried with the horizontal plate 7 positioned at the center of each side surface of the column 1.
また、上下接合金物2.2間の柱1の側部には、垂直プ
レート6.6が突設されている。Further, a vertical plate 6.6 is provided protruding from the side of the pillar 1 between the upper and lower joining hardware 2.2.
垂直プレート6は、柱1内のフープ筋5,5に連結され
、かつコンクリート中に深く埋設され固定されている。The vertical plate 6 is connected to the hoop reinforcements 5, 5 in the column 1, and is deeply embedded and fixed in concrete.
そして、梁3,3は、上下フランジ3a、3aを上下接
合金物2.2の水平プレート7.7を介して複数本の連
結ボルト8によって連結かつウェブ部3b端部を垂直プ
レート6に複数本の連結ポルト8,8によってボルト止
めすることにより柱1の仕口部に接合されている。The beams 3, 3 are connected by connecting the upper and lower flanges 3a, 3a with a plurality of connecting bolts 8 via the horizontal plate 7.7 of the upper and lower joining hardware 2.2, and connecting the end of the web portion 3b to the vertical plate 6 with a plurality of connecting bolts 8. It is joined to the joint part of the pillar 1 by bolting through the connecting ports 8, 8.
当該実施例においては、場合により上下接合金物2.2
を複数本のタイプレート9,9によって連結する場合も
ある(第4図、第5図参照)。さらに、接合金物2.2
の外周にだけでなく接合金物2,2の内側にも主筋4.
・・・とフープ筋5.・・・を配筋する場合もある(第
6図。In this embodiment, depending on the case, upper and lower joint metal fittings 2.2
may be connected by a plurality of tie plates 9, 9 (see FIGS. 4 and 5). Furthermore, joining hardware 2.2
Main reinforcing bars 4. are placed not only on the outer periphery of the 4.
...and hoop muscle 5. ... may be arranged (Fig. 6).
第7図参照)。(See Figure 7).
第8図および第9図は、この発明の第2実施例を示した
もので、接合金物2が上下別々に形成するのではなく、
接合される梁3.3の梁成に応じた高さに一体形成した
ものである(第8図、第9図参照)。また、接合金物2
の外周にだけでなく接合金物2の内側にも主筋4.・・
・を配筋する場合がある(第10図第11図参照)。8 and 9 show a second embodiment of the present invention, in which the joining hardware 2 is not formed separately on the top and bottom, but
It is integrally formed with a height corresponding to the beam configuration of the beams 3.3 to be joined (see FIGS. 8 and 9). In addition, joining hardware 2
The main reinforcing bars 4.・・・
・In some cases, reinforcement may be arranged (see Figures 10 and 11).
その他の構成は、第1実施例とほぼ同じである。The other configurations are almost the same as the first embodiment.
なお、第1実施例および第2実施例においては、接合金
物2が矩形断面の場合において説明したが、これに限ら
れるものではなく円形断面。In addition, in the first and second embodiments, the joint hardware 2 has a rectangular cross section, but is not limited to this and may have a circular cross section.
多角形断面の接合金物でもよい(第12図、第13図)
。同様に柱1も円形断面や多角形断面でよい。A metal joint with a polygonal cross section may also be used (Figures 12 and 13).
. Similarly, the pillar 1 may also have a circular or polygonal cross section.
(発明の効果)
この発明は、以上の構成からなるので以下の効果を有す
る。(Effects of the Invention) Since the present invention has the above configuration, it has the following effects.
■ 接合金物は、矩形中空断面や円形中空断面といった
閉鎖形断面形に形成され、かつ仕口部のコンクリート中
に中空部が上下方向に連続するように埋設しであるので
、柱と梁間の応力の伝達はコンクリートと梁との付着力
によるものでなく接合金物の支圧力によるため、しかも
接合金物が仕口部中央部のコンクリートを拘束している
ので、応力伝達の効率が良く、梁フランジ応力を柱仕口
部に効果的に伝達できる。■ The joint hardware is formed with a closed cross section such as a rectangular hollow cross section or a circular hollow cross section, and is buried in the concrete at the joint so that the hollow part continues vertically, so the stress between the column and beam is reduced. The transmission of stress is not due to the adhesion force between the concrete and the beam, but is due to the bearing force of the joint hardware, and since the joint hardware restrains the concrete in the center of the joint, the efficiency of stress transmission is high, and the beam flange stress is can be effectively transmitted to the pillar joint section.
■ 接合金物の支圧耐力、すなわち接合金物の接合強度
は、接合金物の成を増減することで、きわめて簡単に設
計できる。■ The bearing capacity of the metal joints, that is, the joint strength of the metal joints, can be designed extremely easily by increasing or decreasing the composition of the metal joints.
■ 接合金物は、梁の上フランジを接合するものと下フ
ランジを接合するものとを別々にすることにより接合金
物の小型化、軽量化並びに運搬取付等の取扱い容易化が
計れる。また、接合金物をプレハブ化された柱鉄筋に先
組みすることも可能で施工の省力化も図れる。■ By separating the parts that join the upper flange of the beam and the parts that join the lower flange of the beam, the joining hardware can be made smaller, lighter, and easier to transport and install. In addition, it is possible to assemble the joining hardware to prefabricated column reinforcing bars in advance, which saves labor during construction.
■ 接合金物は、鉛直方向に中空な閉鎖状の矩形断面形
等に形成されたものが、仕口部に埋設されているので、
コンクリートの打ち込みに際し、コンクリートの流動性
がよく、品質確保が容易である。■ The joint hardware is formed into a vertically hollow closed rectangular cross section and is buried in the joint part.
When pouring concrete, the fluidity of the concrete is good, making it easy to ensure quality.
第1図〜第7図は、この発明の第一実施例を示したもの
で、第1図、第4図および第6図は、柱・梁仕口部部の
横断面図、第2図、第5図および第7図はその縦断面図
、第3図は接合金物の斜視図、第8図〜第13図はこの
発明の第2実施例を示すもので、第8図、第10図およ
び第12図は柱・梁仕口部の横断面図、第9図。
第11図および第13図はその縦断面図である。
1・・柱、2・・接合金物、3・・梁、4・・主筋、5
・・フープ筋、6・・垂直プレート、7・・水平プレー
ト、8・・連結ボルト、9・・タイプレート。1 to 7 show a first embodiment of the present invention, and FIG. 1, FIG. 4, and FIG. 6 are cross-sectional views of the column and beam joints, and FIG. , FIG. 5 and FIG. 7 are longitudinal sectional views thereof, FIG. 3 is a perspective view of the joint metal fittings, and FIGS. 8 to 13 show a second embodiment of the present invention. The figure and Fig. 12 are cross-sectional views of the column and beam joints, and Fig. 9. FIGS. 11 and 13 are longitudinal sectional views thereof. 1. Column, 2. Joining hardware, 3. Beam, 4. Main reinforcement, 5
...Hoop muscle, 6.Vertical plate, 7.Horizontal plate, 8.Connection bolt, 9.Tie plate.
Claims (1)
て、鉛直方向に中空閉鎖状の矩形断面形金物とそのコー
ナー部に水平プレートを溶接し一体化した梁接合金物を
、前記鉄筋コンクリート柱の梁接合部に鉄骨梁の上下フ
ランジ位置に別々に埋設してあるとともに、コンクリー
ト柱側面で当該梁接合金物と鉄骨梁をボルト接合してあ
ることを特徴とする鉄筋コンクリート柱と鉄骨梁との接
合構造。(1) A joint structure between a reinforced concrete column and a steel beam, in which a beam joint hardware is integrated by welding a rectangular cross-sectional metal fixture with a closed hollow in the vertical direction and a horizontal plate to its corner part, and the beam of the reinforced concrete column is integrated with the horizontal plate. A joint structure between a reinforced concrete column and a steel beam, characterized in that the joint parts are separately buried at the upper and lower flange positions of the steel beam at the joint, and the beam joint hardware and the steel beam are connected with bolts on the side of the concrete column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1622588A JPH0635725B2 (en) | 1988-01-27 | 1988-01-27 | Joint structure of reinforced concrete columns and steel beams |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1622588A JPH0635725B2 (en) | 1988-01-27 | 1988-01-27 | Joint structure of reinforced concrete columns and steel beams |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH01190841A true JPH01190841A (en) | 1989-07-31 |
JPH0635725B2 JPH0635725B2 (en) | 1994-05-11 |
Family
ID=11910597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1622588A Expired - Lifetime JPH0635725B2 (en) | 1988-01-27 | 1988-01-27 | Joint structure of reinforced concrete columns and steel beams |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0635725B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102979168A (en) * | 2012-11-26 | 2013-03-20 | 北京工业大学 | Industrialized multi-story high-rise assembled steel structure frame - centrally-braced system |
CN102979174A (en) * | 2012-11-26 | 2013-03-20 | 北京工业大学 | Multi-story high-rise assembled steel structure frame system |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1998036134A1 (en) * | 1997-02-13 | 1998-08-20 | Tanaka Steel Workshop | Joint for steel structure, and combining structure using the same joints for steel structure |
-
1988
- 1988-01-27 JP JP1622588A patent/JPH0635725B2/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102979168A (en) * | 2012-11-26 | 2013-03-20 | 北京工业大学 | Industrialized multi-story high-rise assembled steel structure frame - centrally-braced system |
CN102979174A (en) * | 2012-11-26 | 2013-03-20 | 北京工业大学 | Multi-story high-rise assembled steel structure frame system |
CN102979168B (en) * | 2012-11-26 | 2015-05-20 | 北京工业大学 | Industrialized multi-story high-rise assembled steel structure frame - centrally-braced system |
Also Published As
Publication number | Publication date |
---|---|
JPH0635725B2 (en) | 1994-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2645365B2 (en) | Beam-column joint | |
JP3849554B2 (en) | Beam-column joint structure | |
JP4092873B2 (en) | Structure of beam member and joint part of beam member and column member | |
KR20090105512A (en) | Concrete Filled Steel Tube | |
JPH01190841A (en) | Junction structure of reinforced concrete column with steel girder | |
JPH0723455Y2 (en) | Steel pipe concrete pillar | |
JPH04254646A (en) | Steel framed reinforced concrete beam | |
JP2702104B2 (en) | Joint structure of steel tube column beam, column, column base | |
JPH01260135A (en) | Structure of junction between reinforced concrete column and steel framed beam | |
JP2753916B2 (en) | Joining method of square steel column and beam | |
JPH0533606Y2 (en) | ||
JPH079921Y2 (en) | Joint structure between reinforced concrete column and steel beam | |
JPH0715922Y2 (en) | Joining hardware for reinforced concrete columns and steel beams | |
JPH0325130A (en) | Coupling structure for precast steel frame concrete pillar bodies | |
JPH0443521Y2 (en) | ||
JPH04124338A (en) | Construction for column/beam joining section | |
JPH09111871A (en) | Joining structure of column and beam | |
JP2023149165A (en) | Reinforcement connection part structure for existing frame member | |
JPH04169625A (en) | Joint structure | |
JPH0341521Y2 (en) | ||
JPH01190843A (en) | Structure for joining reinforced concrete column with steel girder | |
JP2723011B2 (en) | Construction method of steel frame reinforced concrete structure | |
JP2023149166A (en) | Reinforcement connection part structure for existing frame member | |
JP3196530B2 (en) | Connection structure of steel column and steel beam with closed section | |
JPS6341443Y2 (en) |