Method for collecting work data

Info

Publication number
JPH01181155A
JPH01181155A JP63004739A JP473988A JPH01181155A JP H01181155 A JPH01181155 A JP H01181155A JP 63004739 A JP63004739 A JP 63004739A JP 473988 A JP473988 A JP 473988A JP H01181155 A JPH01181155 A JP H01181155A
Authority
JP
Japan
Prior art keywords
work
list
label
construction
order
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP63004739A
Other languages
Japanese (ja)
Inventor
Osamu Nagai
修 永易
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP63004739A priority Critical patent/JPH01181155A/en
Publication of JPH01181155A publication Critical patent/JPH01181155A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PURPOSE:To improve the efficiency of construction work by producing a work label list which shows the work code numbers in the order of works. CONSTITUTION:A work level list 2 is produced to show in steps each work menu for finishing construction of each house on each floor of each building of an apartment house for instance. The list 2 is distributed to each house before the start of construction. Thus a worker cuts out a relevant work code label out of the list 2 and gives it to a superintendent, etc. The superintendent reads the received label via a bar code reader and inputs the read contents to a data collector. In this case, it is inhibited to proceed to the next construction process if the step label is not removed yet since the list 2 is arranged in the order of process steps. In such a way, each process is smoothly carried out with no confusion.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、例えばマンション、ホテル等の集合住宅の建
設工事での仕上げ工事等の工程管理に適用される製図等
に用いられる作業用データの収集方法、特にデータ収集
の省力化及び標準化を図り、前工程の終了、未了を明確
に把握することができるようにした作業用データの収集
方法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention is directed to the use of work data used in drafting, etc., applied to process control of finishing work, etc., in the construction of apartment complexes such as condominiums and hotels. The present invention relates to a data collection method, and in particular to a work data collection method that saves labor and standardizes data collection, and makes it possible to clearly understand whether a previous process has been completed or not.

[従来技術とその課題] 例えばマンション、ホテル等の集合住宅を建設する場合
、作業工程が多段階的であり、また各作業により工種及
び作業員が異なることから、各段階での仕上げ工事の作
業完了データを収集して工程管理し、各段階の作業工程
を明確に把握することにより、工程間の混乱や手戻り等
をできるだけなくして、全体的な建設工事を能率良く行
なうことが必要である。
[Prior art and its problems] For example, when constructing apartment complexes such as condominiums and hotels, the work process is multi-stage, and the types of work and workers differ depending on each work, so finishing work at each stage is difficult. By collecting completion data, managing the process, and clearly understanding the work process at each stage, it is necessary to eliminate confusion and rework between processes as much as possible, and to perform the overall construction work efficiently. .

[発明の目的コ 本発明は、上記の事情のもとになされたもので、その目
的とするところは、データ収集の省力化及び標準化を図
り、前工程の終了、未了を明確に把握して、建設工事を
能率良く行なうことができるようにした作業用データの
収集方法を提供することにある。
[Purpose of the invention] The present invention was made under the above circumstances, and its purpose is to save labor and standardize data collection, and to clearly understand the completion and non-completion of previous processes. Therefore, it is an object of the present invention to provide a method for collecting work data that allows construction work to be carried out efficiently.

[課題を解決するための手段] 上記した課題を解決するために、本発明は、多段階工程
の一連の作業を行なうにあたり、各作業の工程ステップ
にコード番号を付けて各作業間の作業順序を決め、この
工程ステップにより作業コード番号を各作業毎の順に表
す作業ラベル表を作成するとともに、この作業ラベル表
を各作業終了毎の順に切り取ってデータ収集手段により
読み取す収集してなることを特徴とするものである。
[Means for Solving the Problems] In order to solve the above-mentioned problems, the present invention, when performing a series of operations in a multi-step process, assigns a code number to the process step of each operation and distinguishes the work order between each operation. In this process step, a work label table is created that shows the work code number in the order of each work, and this work label table is cut out in the order of each work completion and read by the data collection means. This is a characteristic feature.

し作  用] すなわち、本発明によれば、各作業の工程ステップにコ
ード番号を付けて各作業間の作業順序を決め、この工程
ステップにより作業コード番号を各作業毎の順に表す作
業ラベル表を作成し、さらに、この作業ラベル表を各作
業終了毎の順に切り取ってデータ収集手段により読み取
り収集しながら多段階工程の一連の作業を行なうように
してなることから、データ収集の省力化及び標準化を図
ることができるため、パーソナルコンピュータ等による
データの総合的利用を行なうことができ、また、前工程
の終了、未了を明確に把握することができるために、工
程間の混乱や手戻り等をなくすことができ、これによっ
て、各段階毎の作業を能率良く行なうことが可能になる
In other words, according to the present invention, a code number is attached to each process step of each operation to determine the order of the operations, and a work label table is created that indicates the operation code number in the order of each operation based on this process step. Furthermore, this work label table is cut out in the order of each work completion, read and collected by a data collection means, and a series of multi-step processes are performed, which saves labor and standardizes data collection. This makes it possible to comprehensively utilize data using personal computers, etc., and it is also possible to clearly understand whether the previous process has been completed or not, so there is no need to worry about confusion or rework between processes. This enables efficient work at each stage.

[実 施 例コ 以下、本発明を図示の一実施例を参照しながら詳絽に説
明する。
[Embodiment] Hereinafter, the present invention will be explained in detail with reference to an illustrated embodiment.

第1図に示す図中(1)は例えばマンション等の各棟、
各階及び各住戸等の工事出来形を工事毎に表す出来高表
、第2図に示す図中(2)は各棟、  及び各階の各住
戸内における仕上げ工事の各作業メニューを段階的に表
す作業ラベル表、第3図に示す図中(3)は各住戸内に
おける仕上げ工事の各作業メニューの工事途中段階の作
業ラベル表である。
In the diagram (1) shown in Figure 1, for example, each building such as an apartment building,
The completed table shows the progress of construction work for each floor and each dwelling unit, etc., and (2) in the figure shown in Figure 2 shows the work menu for each finishing work step by step in each building and each dwelling unit on each floor. Label table (3) in FIG. 3 is a work label table for each work menu of finishing work in each dwelling unit at an intermediate stage of construction.

すなわち、本発明に係る作業データの収集方法を説明す
ると、まず作業工程を決め、作業の能率や手戻りがない
ことを考慮して、第4図に示すフローチャートような工
程表を作成し、また、各作業には、例えば「墨出し」は
N002、rAW取付」はNo、4等のように工程ステ
ップ(ST−1〜19)に基づき作業コード番号を(N
o、1〜22)付ける。この場合、例えば工程ステップ
(ST−6)の作業コード(No、7)と作業コード(
No、8)の作業のように同一工程ステップ内での複数
作業は許可し、さらに、複数ステップ作業に渡る作業を
作らないようにして、作業コード番号の連続しない作業
の同時並行作業はないものとし、例えば工程ステップ(
ST−5)における作業コード(No、6)の「とろ詰
め」は、工程ステップ(ST−4)における作業コード
(No、4)のrA、W取付」と作業コード(No。
That is, to explain the method of collecting work data according to the present invention, first, a work process is determined, and a process chart like the flowchart shown in Fig. 4 is created, taking into account work efficiency and the absence of rework. , for each job, a job code number (N
o, 1-22) Attach. In this case, for example, the work code (No. 7) of the process step (ST-6) and the work code (
As in No. 8), multiple operations within the same process step are allowed, and operations that span multiple steps are not created, and there are no concurrent operations with non-consecutive operation code numbers. For example, a process step (
``Toro filling'' of the work code (No. 6) in ST-5) is the same as ``rA, W installation'' of the work code (No. 4) in the process step (ST-4).

5)のrSD取付」の両作業の終了を待って行なうとい
う、規則でもって行なうものとする。
The rule is to wait for the completion of both operations in 5) "rSD installation" before performing this procedure.

そして、このような工程表に基づいて、第2図に示すよ
うな各住戸毎にバーコード化された作業ラベル表(2)
を作成する。この作業ラベル表(2)の特徴は、下から
工程ステップ順に作業コートのバーコードが印刷され、
各ラベル間には、用紙にミシン目を入れて一枚づつ剥離
可能になっているとともに、各バーコードは1部屋番号
と作業コードを組合せてなるもので、例えば1156号
室の部屋の作業コードがNo、15であれば、rl15
61:5J と略記したコードとするものである。
Based on this process chart, a barcoded work label chart (2) is created for each housing unit as shown in Figure 2.
Create. The feature of this work label table (2) is that the work coat barcodes are printed in order of process steps from the bottom.
There are perforations in the paper between each label so that they can be peeled off one by one, and each barcode is a combination of a room number and work code.For example, the work code for room 1156 is a combination of a room number and a work code. No, if 15, rl15
The code is abbreviated as 61:5J.

以上の準備の後、上記した作業ラベル表(2)を各住戸
に配備して工事に取り掛かり、これにより、作業員は、
工事が終了した段階で、作業ラベル表(2)から該当す
る作業コードラベルを切り取り、これを作業監督者等に
提出し、そのデータをバーコードリーダが装備された図
示しないデータ収集機に入力する。このとき、前記した
作業ラベル表(2)は、工程ステップ順になっているた
め、前工程のステップのラベル表が切り取られていない
と、工事を続行してはならないものとしておけば、各工
程間の混乱を避けることができる。
After the above preparations, the work label table (2) described above is placed in each dwelling unit and construction begins.
When construction is completed, cut out the relevant work code label from the work label table (2), submit it to the work supervisor, etc., and enter the data into a data collection machine (not shown) equipped with a barcode reader. . At this time, since the work label table (2) described above is in the order of process steps, if the work label table (2) is set in the order of process steps, if the label table of the step of the previous process is not cut out, the construction should not be continued. confusion can be avoided.

また、第3図に示す各住戸内における仕上げ工事の各作
業メニューの工事途中段階の作業ラベル表(3)の例で
あり、この場合、第4図の工程表に示す工程ステップ(
ST−7)における作業コード(No、9)の「断熱材
貼」と作業コード(No、10)の「フレキ貼」が表の
最下段であることから、作業をして良いことになり、逆
に、工程ステップ(ST−8)における作業コード(N
o、11)の「ユニットバス」より上の作業は、先行作
業が残っているため、作業を行なうことができず、ラベ
ル表を切り取ることができないようになっている。
Also, this is an example of a work label table (3) for the intermediate stage of construction for each work menu of finishing work in each dwelling unit shown in Fig. 3. In this case, the process step (3) shown in the process chart of Fig. 4 is shown.
In ST-7), the work code (No. 9) "Insulating material pasting" and the work code (No. 10) "Flexible pasting" are at the bottom of the table, so it is okay to perform the work. Conversely, the work code (N
The work above "unit bus" in o and 11) cannot be performed because the previous work remains, and the label table cannot be cut out.

このようにすれば、作業ラベル表(2)(3)から切り
取られる各作業完了の実績データであるラベル表は、間
違えることなく簡単に収集することができるもので、こ
れによって、収集されたデータに基づき、第5図に示す
ように、作業毎に出来高実績を検討したり、あるいは、
第6図に示すように、住戸毎の工程の管理終了作業、作
業可能の作業を確認して住戸毎の工程管理を行なうこと
が容易にできる。
In this way, the label table, which is the performance data of each work completed that is cut out from the work label sheets (2) and (3), can be easily collected without making any mistakes. Based on the above, as shown in Figure 5, the actual output of each work is examined, or
As shown in FIG. 6, it is possible to easily manage the process for each dwelling unit by checking the completed work and the work that can be done.

なお、上記の実施例においては、バーコードの種類とし
てN W −7を用いたが、多の種類のものでも良く、
また、データ収集機がバーコード以外のコードでも読み
込めればコードの種類は問わない。
In addition, in the above embodiment, NW-7 was used as the type of barcode, but other types of barcodes may be used.
Furthermore, as long as the data collection device can read codes other than barcodes, the type of code does not matter.

さらに、作業ラベル表において、ラベル配列は、場合に
よって上下逆または左右に並べても良く、また、同一工
程ステップにおいても、単一作業に限定するならば、作
業ラベル表を、例えば「日めくり暦」のように重ねてお
き、上から順に切り取るようにすることも可能である。
Furthermore, in the work label table, the labels may be arranged upside down or left and right depending on the case, and even if the same process step is limited to a single work, the work label table may be arranged, for example, in a "daily calendar". It is also possible to stack them like this and cut them out from the top.

また、バーコード・リーダ付きのハンディ・ターミナル
等を用いてデータを入力する場合も、入力後、ラベル表
を外すことで、上記したラベル表を用いることが可能に
なる。
Furthermore, even when data is input using a handy terminal equipped with a barcode reader, etc., the above-described label table can be used by removing the label table after inputting data.

さらにまた、本発明は、作業者による作業報告としての
使い方ばかりでなく、作業監督者による作業チエツク用
としても同様のラベル表を使用することが可能である。
Furthermore, the present invention allows similar label sheets to be used not only as work reports by workers, but also for work checks by work supervisors.

なお、本発明は、上記の実施例には何等限定されないも
のであり、本発明の要旨を変えない範囲で種々変更実施
可能なことは勿論である。
It should be noted that the present invention is not limited to the above embodiments in any way, and it goes without saying that various changes can be made without departing from the gist of the present invention.

[発明の効果] 以上の説明から明らかなように1本発明によれば、多段
階工程の一連の作業を行なうにあたり。
[Effects of the Invention] As is clear from the above description, according to the present invention, a series of multi-step processes can be carried out.

各作業の工程ステップにコード番号を付けて各作業間の
作業順序を決め、この工程ステップにより作業コード番
号を各作業毎の順に表す作業ラベル表を作成するととも
に、この作業ラベル表を各作業終了毎の順に切り取って
データ収集手段により読み取り収集してなることから、
データ収集の省力化及び標や化を図ることができるため
、パーソナルコンピュータ等によるデータの総合的利用
を行なうことができ、また、前工程の終了、未了を明確
に把握することができるために、工程間の混乱や手戻り
等をなくすことができ、これによって、各段階毎の作業
を能率良く行なうことができるというすぐれた効果を奏
するものである。
A code number is attached to the process step of each operation to determine the order of operations between each operation, and a work label table is created that shows the operation code number in order for each operation based on this process step, and this work label table is used at the end of each operation. Because each piece is cut out in order and read and collected by a data collection means,
Because it is possible to save labor and standardize data collection, it is possible to make comprehensive use of data using personal computers, etc., and it is also possible to clearly understand whether the previous process has been completed or not. It is possible to eliminate confusion and rework between processes, thereby achieving the excellent effect that work at each stage can be carried out efficiently.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る作業用データの収集方法に用いら
れる工事出来形を工事毎に表す出来裏表、第2図は仕上
げ工事の各作業メニューを段階的に表す作業ラベル表、
第3図は同じく仕上げ工事の各作業メニューの工事途中
段階の作業ラベル表、第4図は多段階工程の一連の作業
を行なう各作業の工程ステップにコード番号を付けて各
作業間の作業順序を決めめようにしたフローチャート、
第S図は作業毎の出来高を示す説明図、第6図は住戸毎
の工程の管理状態を示す説明図である。 (2)(3)作業ラベル表。
FIG. 1 is a work label table that shows the work completed form for each work used in the work data collection method according to the present invention, and FIG. 2 is a work label table that shows each work menu of finishing work step by step.
Figure 3 is a work label table for the middle stages of construction in each work menu of finishing work, and Figure 4 is a work order between each work with code numbers attached to the process steps of each work that performs a series of work in a multi-step process. A flowchart that allows you to decide
FIG. S is an explanatory diagram showing the output of each work, and FIG. 6 is an explanatory diagram showing the state of process management for each dwelling unit. (2) (3) Work label table.

Claims (1)

【特許請求の範囲】[Claims] 多段階工程の一連の作業を行なうにあたり、各作業の工
程ステップにコード番号を付けて各作業間の作業順序を
決め、この工程ステップにより作業コード番号を各作業
毎の順に表す作業ラベル表を作成するとともに、この作
業ラベル表を各作業終了毎の順に切り取ってデータ収集
手段により読み取り収集してなることを特徴とする作業
用データの収集方法。
When performing a series of operations in a multi-step process, a code number is assigned to the process steps of each operation to determine the order of each operation, and a work label table is created that shows the operation code numbers in order for each operation based on this process step. At the same time, this work data collection method is characterized in that the work label table is cut out in the order of each work completion and read and collected by a data collection means.
JP63004739A 1988-01-14 1988-01-14 Method for collecting work data Pending JPH01181155A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63004739A JPH01181155A (en) 1988-01-14 1988-01-14 Method for collecting work data

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63004739A JPH01181155A (en) 1988-01-14 1988-01-14 Method for collecting work data

Publications (1)

Publication Number Publication Date
JPH01181155A true JPH01181155A (en) 1989-07-19

Family

ID=11592283

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63004739A Pending JPH01181155A (en) 1988-01-14 1988-01-14 Method for collecting work data

Country Status (1)

Country Link
JP (1) JPH01181155A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2676846A1 (en) * 1991-05-23 1992-11-27 Investor Associes Srl Automatic entry of elementary data on construction sites

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5061772A (en) * 1973-10-05 1975-05-27

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5061772A (en) * 1973-10-05 1975-05-27

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2676846A1 (en) * 1991-05-23 1992-11-27 Investor Associes Srl Automatic entry of elementary data on construction sites

Similar Documents

Publication Publication Date Title
CN109360123B (en) Multi-professional construction management method and system based on room
JPH01181155A (en) Method for collecting work data
JP2002121817A (en) Method and device for producing building member
Ding A pairwise interchange solution procedure for a scheduling problem with production of components at a single facility
JPH0799522B2 (en) Equipment used for production control
JP2522057B2 (en) Distributed control system
JPS6294252A (en) System for controlling process information
JPH09279843A (en) Construction management equipment for wooden architecture
JP2674333B2 (en) Semiconductor device manufacturing history collection system
JP2607201B2 (en) Comprehensive production method by linking design and production of framed wall method
JP2588788B2 (en) File extraction method
JPH08123534A (en) Program transmission system
JPH02244286A (en) Work managing method using portable handy terminal
JPH0625993B2 (en) Work management method using a portable barcode printer
JPH0254587B2 (en)
US20020120483A1 (en) Method for dynamically identifying operation entity and system thereof
JPH10309655A (en) Production planning forming method
CN117020748A (en) Semi-automatic material-saving and material-opening system
JPH1022188A (en) Arithmetic method and arithmetic device
JPH10283363A (en) Maintenance part retrieval supporting device for building equipment
CN112306002A (en) Production auxiliary system and operation platform thereof
JPH02244258A (en) Task control method using bar code
JPH10309654A (en) Process planning forming device, and recording medium capable of being read by computer having recorded process planning forming program
JPH03278907A (en) Automatic manufacturing of sheathing
JPS62271662A (en) Result of actual work processing system