Japan
Prior art keywords
floor
entrance
wall
door
renovation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2023106687A
Other languages
Japanese (ja)
Other versions
JP2024070792A (en
Inventor
清貴 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2023106687A priority Critical patent/JP7371296B1/en
Application granted granted Critical
Publication of JP7371296B1 publication Critical patent/JP7371296B1/en
Publication of JP2024070792A publication Critical patent/JP2024070792A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Residential Or Office Buildings (AREA)

Abstract

【課題】 将来的な2世帯完全分離住宅への改築に適した戸建て住宅を提供する。【解決手段】 一実施形態に係る戸建て住宅は、1階と2階を有し、1階と2階を繋ぐ階段が屋内に配置されている。この戸建て住宅は、1階に配置された玄関扉を有する玄関と、1階の外壁に面する収納空間と、外壁の下方に配置された基礎と、基礎の上に配置された土台とを備える。外壁は、収納空間に面するとともに玄関扉を設置可能な大きさを有する扉設置予定部を有する。扉設置予定部は、土台の上方で壁材によって塞がれた領域を含み、土台は、扉設置予定部を除く前記外壁の下方に位置する固定部分と、扉設置予定部の下方に位置し固定部分に対して着脱自在に連結された可撤部分とを含む。【選択図】 図1[Problem] To provide a detached house suitable for future renovation into a completely separated two-family house. SOLUTION: A detached house according to one embodiment has a first floor and a second floor, and a staircase connecting the first floor and the second floor is arranged indoors. This detached house includes an entrance with an entrance door located on the first floor, a storage space facing the exterior wall on the first floor, a foundation located below the exterior wall, and a foundation located on the foundation. . The outer wall has a door installation portion facing the storage space and having a size that allows installation of an entrance door. The area where the door is to be installed includes an area above the base that is blocked by wall material, and the base includes a fixed part located below the outer wall excluding the area where the door is to be installed, and the area below the area where the door is to be installed. and a removable portion detachably connected to the fixed portion. [Selection diagram] Figure 1

Description

本発明は、2階建て以上の戸建て住宅およびその改築方法に関する。 TECHNICAL FIELD The present invention relates to a detached house with two or more stories and a method for renovating the same.

我が国の多くの国民はコロナ禍を経験し、人生において経済の一時的な困窮があり得ることを学んだ。現在の住宅は、建築から60年以上経過したものが多く存在する。将来、例えば、30歳代で取得した1世帯用の戸建て住宅を、子供が巣立った後に2世帯完全分離住宅へ改築し、1世帯分を居住用に利用するとともにもう1世帯分を賃貸等で活用すれば、経済的困窮や孤独死、夫源病などの様々な問題に対処することができる。 Many people in our country have experienced the coronavirus pandemic and have learned that temporary economic hardship can occur at some point in our lives. Many of today's houses are more than 60 years old. In the future, for example, a single-family detached house acquired in your 30s may be renovated into a two-family completely separated house after your child leaves the nest, and one household can be used for living while the other can be rented out. If utilized, it will be possible to deal with various problems such as economic hardship, lonely death, and husband's disease.

戸建て住宅の購入時には、返済期間を35年としたローンが組まれることが多い。しかしながら、近年の日本の労働環境では、35年の継続した労働により当該ローンを返済するにも限界がある。上述のように、戸建て住宅を2世帯完全分離するように改築し、1世帯分を賃貸することが可能であれば、人生100年時代における保険かつリスクヘッジとなり得る。また、戸建て住宅の有効活用は、社会への貢献度が極めて高い行いであると言える。 When purchasing a single-family home, a loan with a repayment period of 35 years is often taken out. However, in recent years in Japan's working environment, there is a limit to repaying the loan after 35 years of continuous work. As mentioned above, if a detached house can be renovated to completely separate two households and one household can be rented out, it can serve as insurance and risk hedge in the era of 100-year lifespans. Furthermore, it can be said that the effective use of detached houses is an activity that makes an extremely high contribution to society.

世の中の標準的な1世帯2階建ての戸建て住宅は、改築による1階と2階の2世帯完全分離住宅への変更に多額の費用を要したり、そもそも改築が不可能であったりすることが多い。特に、2つの分離された玄関の設置、各玄関から各階フロアへの動線の確保、部屋間の耐力壁の存在等が障害となり得る。 The standard one-family, two-story detached house in the world requires a large amount of money to transform into a fully separated two-family house on the first and second floors, or it may be impossible to do so in the first place. There are many. In particular, the installation of two separate entrances, ensuring flow lines from each entrance to each floor, and the presence of load-bearing walls between rooms can be obstacles.

すなわち、1階と2階を繋ぐ階段の上り口が1階中央に設けられた廊下や1階リビング付近にある場合、改築後の2階用の玄関から上り口に至る経路が1階用の玄関から1階の生活空間に至る動線の障害になる。さらに、外壁において2つ目の玄関を設置する箇所や当該玄関から生活空間に至る経路に、耐震性を担保する筋交いおよびブレース等を含む耐力壁や柱が存在することもあり得る。このような耐震性に影響を及ぼす構造物を除去することは難しい。これらのことは、将来の2世帯完全分離住宅への戸建て住宅の改築を阻む要因となる。 In other words, if the entrance to the stairs connecting the 1st and 2nd floors is located in the hallway in the center of the 1st floor or near the living room on the 1st floor, the route from the entrance for the 2nd floor to the entrance after renovation will be the same as that for the 1st floor. This will obstruct the line of flow from the entrance to the living space on the first floor. Furthermore, there may be load-bearing walls or columns that include braces, braces, etc. to ensure earthquake resistance at the location where the second entrance is installed on the exterior wall or along the route from the entrance to the living space. It is difficult to remove structures that affect earthquake resistance. These are factors that will hinder future renovations of single-family homes into completely separated two-family homes.

例えば特許文献1には、2階建ての戸建て住宅において、2つの玄関を設置することが可能な幅の1つの玄関を設けておき、この玄関を改装して2つの玄関を設置するとともに、室内に間仕切りを適宜に配置することによって、当該戸建て住宅を2世帯に分離する方法が示されている。 For example, in Patent Document 1, in a two-story detached house, one entrance is provided with a width that allows two entrances to be installed, and this entrance is renovated to install two entrances, and the interior A method is shown in which a detached house can be divided into two households by appropriately arranging partitions.

しかしながら、この方法においては、改築を見据えて通常よりも幅が広い玄関を戸建て住宅の新築当初から設けておく必要がある。そのため、改築前の玄関スペースには無駄が生じ得る。また、2世帯に分離するためには当初の玄関を除去する必要があり、改築費用の増大も懸念される。 However, with this method, it is necessary to prepare a wider entrance than usual from the time the detached house is newly constructed in anticipation of renovation. Therefore, the entrance space before renovation may be wasted. Additionally, in order to separate the house into two households, the original entrance would need to be removed, which raises concerns about increased renovation costs.

特許第6291152号公報Patent No. 6291152

本発明は、上述の事情に鑑みてなされたものであり、将来的な2世帯完全分離住宅への改築に適した戸建て住宅およびその改築方法を提供することを目的の一つとする。より詳細な目的は、本明細書の記載から明らかとなる。 The present invention has been made in view of the above-mentioned circumstances, and one of its objects is to provide a single-family house and a method for remodeling the same that are suitable for future renovation into a two-family completely separated house. More detailed objectives will become apparent from the description herein.

一実施形態に係る戸建て住宅は、1階と2階を有し、前記1階と前記2階を繋ぐ階段が屋内に配置されている。この戸建て住宅は、前記1階に配置された玄関扉を有する玄関と、前記1階に配置され、前記1階の外壁に面する収納空間と、前記外壁の下方に配置された基礎と、前記基礎の上に配置された土台と、を備えている。さらに、前記外壁は、前記収納空間に面するとともに玄関扉を設置可能な大きさを有する扉設置予定部を有している。前記扉設置予定部は、前記土台の上方で壁材によって塞がれた領域を含み、前記土台は、前記扉設置予定部を除く前記外壁の下方に位置する固定部分と、前記扉設置予定部の下方に位置し、前記固定部分に対して着脱自在に連結された可撤部分と、を含む。 The detached house according to one embodiment has a first floor and a second floor, and a staircase connecting the first floor and the second floor is arranged indoors. This detached house includes an entrance having an entrance door arranged on the first floor, a storage space arranged on the first floor and facing an outer wall of the first floor, a foundation arranged below the outer wall, and a foundation arranged below the outer wall. It has a base placed on a foundation. Furthermore, the outer wall has a door installation portion facing the storage space and having a size that allows installation of an entrance door. The planned door installation area includes an area above the base that is blocked by a wall material, and the base includes a fixed part located below the outer wall excluding the planned door installation area, and the planned door installation area. a removable part located below the fixed part and detachably connected to the fixed part.

例えば、前記扉設置予定部は、開口部補強材によって囲われ、かつ壁材によって塞がれた領域である。 For example, the planned door installation area is an area surrounded by an opening reinforcing material and closed by a wall material.

前記戸建て住宅は、前記土台に連結された一対の柱材と、前記一対の柱材に連結された横架材と、をさらに備えてもよい。この場合において、前記扉設置予定部は、前記土台、前記一対の柱材および前記横架材によって囲われ、かつ壁材で塞がれた領域であってもよい。 The detached house may further include a pair of pillar members connected to the foundation, and a horizontal frame member connected to the pair of pillar members. In this case, the planned door installation portion may be an area surrounded by the base, the pair of pillar members, and the horizontal member, and closed by a wall material.

前記固定部分および前記可撤部分の端部にそれぞれ凸部が設けられ、これら凸部が鉛直方向に重ねられるとともに、前記固定部分と前記可撤部分が連結材によって連結されてもよい。 A convex portion may be provided at each end of the fixed portion and the removable portion, and these convex portions may be stacked vertically, and the fixed portion and the removable portion may be connected by a connecting member.

前記扉設置予定部を横切り、前記土台、前記一対の柱材および前記横架材の少なくとも1つに対して着脱自在に連結された可撤式の補強材をさらに備えてもよい。 The door may further include a removable reinforcing member that traverses the planned door installation area and is detachably connected to at least one of the base, the pair of pillar members, and the horizontal member.

前記収納空間は、前記玄関に隣接する部屋、または、前記階段の下に設けられてもよい。 The storage space may be provided in a room adjacent to the entrance or under the stairs.

一実施形態に係る改築方法は、前記戸建て住宅を改築する方法であって、前記外壁のうち前記扉設置予定部を取り除き、前記土台のうち前記可撤部分を取り除き、前記扉設置予定部を取り除いたことで生じる開口部に新たな玄関扉を設置し、前記収納空間を新たな玄関フロアに改築する、ことを含む。 The renovation method according to one embodiment is a method of renovating the detached house, which includes removing the portion of the outer wall where the door is scheduled to be installed, removing the removable portion of the foundation, and removing the portion where the door is scheduled to be installed. This includes installing a new entrance door in the opening created by the accident, and converting the storage space into a new entrance floor.

他の観点によると、改築前の前記戸建て住宅は、前記玄関の内側の玄関フロアに隣接するホールと前記収納空間とを仕切る非耐力壁を備え、改築方法は、前記非耐力壁を撤去し、前記収納空間の入口であった箇所に追加壁を設置する、ことをさらに含む。さらに他の観点によると、改築前の前記戸建て住宅は、前記玄関および前記収納空間の一方と前記階段の上り口を繋ぐ第1動線が前記1階の生活空間を分断せず、かつ他方と前記1階の生活空間を繋ぐ第2動線が前記第1動線と交差しないように構成され、改築方法は、前記第1動線および前記第2動線が空間的に分離されるように、前記1階の内部に追加壁を設置する、ことを含む。 According to another aspect, the detached house before renovation includes a non-load-bearing wall that partitions the storage space from a hall adjacent to the entrance floor inside the entrance, and the renovation method includes removing the non-load-bearing wall, The method further includes installing an additional wall at a location that was an entrance to the storage space. According to still another aspect, in the single-family house before renovation, a first flow line connecting one of the entrance and the storage space to the top of the stairs does not divide the living space on the first floor and connects the other. The second flow line connecting the living spaces on the first floor is configured so as not to intersect the first flow line, and the renovation method is configured such that the first flow line and the second flow line are spatially separated. , installing an additional wall inside the first floor.

本発明によれば、将来的な2世帯完全分離住宅への改築に適した戸建て住宅およびその改築方法を提供することができる。 According to the present invention, it is possible to provide a single-family home suitable for future renovation into a two-family completely separated home, and a method for renovating the same.

改築によって2世帯完全分離が可能であれば、以下に例示するような状況において有利である。なお、以下の例示は、必ずしもこれらの効果を本発明が同時に奏することを意図したものではない。
(1)住宅購入後に夫の急死により妻が経済的に困窮し、子供がおらず、住み慣れた土地を離れたくない。さらに、住宅ローンがまだ残っており住宅を売却したら住む家がなくなり残債も残るような場合に、2世帯完全分離の改築を行い、1世帯分を自身の居住用とし、もう1世帯分を貸し出せば、自身の住居を確保しつつも、賃貸収入を得ることができる。
(2)子供が独立したが、思ったよりも早く退職する必要が生じたか、あるいは勤務先が倒産し、経済的困窮に陥った場合に、上記(1)と同様の対応が可能である。
(3)退職前に病気で働けなくなり、経済的困窮に陥った場合にも上記(1)と同様の対応が可能である。
(4)コロナウイルスのパンデミックなど、思わぬことで収入が減ってしまった場合にも上記(1)と同様の対応が可能である。
(5)老後の資金が足りない場合にも上記(1)と同様の対応が可能である。現状、一人くらしの高齢者の実収入は13万円程度であり、年金で賄えない不足分の生活コストの補填が必要である。
(6)1世帯分に高齢の貸主が居住し、もう1世帯分を貸し出した場合に、貸主が孤独死に陥りにくい。
(7)定年後や一時的に夫婦が距離感を取りたい場合に、夫婦が1階と2階で家庭内別居することが可能であり、離婚や夫源病を回避できる。
(8)将来の様々な家族構成の変化に対応できる。
(9)耐震性の観点から改築時に耐力壁等を除去しないため安心である。
(10)2世帯完全分離可能な住宅は、経済的価値が高まり将来高値で売却できる可能性がある。
(11)2世帯分を別々に貸し出す場合に、同じ建物でも戸建て1世帯4LDKより2世帯1LDK×2の方が家賃収入が多く、利回りが高まる。これにより、不動産物件として商品価値が上がる。1LDKは夫婦でも単身でも生活可能である。
(12)賃貸業としての投下資本が少なく、投資効率が良い。
(13)特に東京23区等の都会では住宅需要も高く、2世帯完全分離による賃貸が有効である。
(14)近年の住宅は、築60年以上保つことがほとんどである。そのため、2世帯完全分離により子育て終了後や配偶者の死後の住居が有効利用でき、重要な資産価値を持つことになる。
(15)将来への経済的安心感を獲得できる。本発明に係る戸建て住宅は、人生100年の保険であり、リスクヘッジとなる。
(16)今後、本発明のように2世帯完全分離可能な戸建て住宅が標準的な2階戸建て4LDK住宅のスタンダードとなり得る。
(17)本発明に係る戸建て住宅を2世帯完全分離住宅へと改築する際には、外階段の設置等の増築が不要であり、新築時の既存の玄関や階段部屋のスペースを使用するため、コスト面で有利である。さらに改築後の建物の一体感が損なわれず、美観が維持される。
(18)増築を要しないため、改築前後で容積率、建坪率の変更がない。
(19)例えば50~60m2の広めの1LDKは、夫婦でも単身でも生活可能であり、賃貸物件としても稀少な存在である。しかしながら、広めの1LDKは利回りが悪いため、あまり新築されない。そのため、2世帯完全分離により1LDKを1世帯分として貸し出せば、稀少なため賃貸人が見つかりやすく、空室率が少なくなると予想される。このような物件は、賃貸事業にとってのリスクも少ない。
(20)賃貸の投下資本が少なくて済み、投資効率が良いし、運営経費も抑えられる。都心のワンルーム経営(例えば2400万円の投資で月10万の収入-管理費、修繕費積立金、固定資産税)の表面利回りが5%程度であるのに対し、管理費や修繕積立金が必要ない。2世帯完全分離による1LDK賃貸経営(例えば400~700万円の投資で8~15万の収入-外壁のペンキなどの修繕費)は、表面利回りが14%から45%程度と高い。なお、戸建て住宅であるため固定資産税は改築前後で変わらない。
(21)改築後を想定してシミュレーションした物件の賃貸収入により、建築時に将来の資金計画が分かり、将来の家計を見通すことができる。子供が巣立った後の35年の住宅ローンの返済プランに賃貸収入を組み入れれば、円滑にローンを返済できる可能性がある。
If it is possible to completely separate two households through renovation, it would be advantageous in situations such as those exemplified below. Note that the following examples do not necessarily mean that the present invention exhibits these effects at the same time.
(1) After purchasing a house, the wife is in financial trouble due to her husband's sudden death, has no children, and does not want to leave the area where she is accustomed to living. Furthermore, if you still have a mortgage loan remaining, and if you sell your house and there is no home left to live in and the remaining debt remains, we will renovate the house to completely separate the two households, using one household for their own living and one for the other household. By renting out your home, you can earn rental income while securing your own home.
(2) If your child becomes independent but needs to retire earlier than expected, or if your employer goes bankrupt and you find yourself in financial hardship, you can take the same steps as in (1) above.
(3) If you are unable to work due to illness before retirement and find yourself in financial hardship, you can take the same measures as in (1) above.
(4) If your income decreases due to an unexpected event such as the coronavirus pandemic, you can respond in the same way as in (1) above.
(5) Even if there is insufficient funds for retirement, the same measures as in (1) above can be taken. Currently, the actual income of elderly people living alone is around 130,000 yen, and it is necessary to compensate for the shortfall in living costs that cannot be covered by pensions.
(6) If an elderly landlord lives in one household and rents out space for another household, the landlord is less likely to die alone.
(7) After retirement or when a couple wants to temporarily distance themselves from each other, it is possible for the couple to live separately on the first and second floors of the home, thereby avoiding divorce and husband's disease.
(8) Be able to respond to various changes in family structure in the future.
(9) From the perspective of earthquake resistance, there is no need to remove load-bearing walls during renovation, so it is safe.
(10) A house where two households can be completely separated has an increased economic value and may be sold at a high price in the future.
(11) When renting out units for two households separately, even in the same building, a 1LDK x 2 unit for 2 households will generate more rental income and a higher yield than a 4LDK unit for 1 household. This increases the value of the property as a real estate property. A 1LDK can be lived in by both a couple and a single person.
(12) Less capital is invested in the rental business, and investment efficiency is high.
(13) Demand for housing is particularly high in urban areas such as Tokyo's 23 wards, and rentals that completely separate two households are effective.
(14) Most houses these days are kept for more than 60 years. Therefore, by completely separating the two households, the residence can be effectively used after raising children or after the death of a spouse, and it has significant asset value.
(15) Gain a sense of financial security for the future. The detached house according to the present invention is a 100-year insurance policy and serves as a risk hedge.
(16) In the future, a detached house in which two households can be completely separated as in the present invention may become a standard two-story detached 4LDK house.
(17) When renovating a detached house according to the present invention into a two-family completely separated house, there is no need for extensions such as installing external stairs, and the space of the existing entrance and staircase room at the time of new construction can be used. , which is advantageous in terms of cost. Furthermore, the integrity of the building will not be compromised and its aesthetic appearance will be maintained after the renovation.
(18) Since no extension is required, there is no change in floor area ratio or building area ratio before and after renovation.
(19) For example, a spacious 1LDK of 50 to 60 m2 can be lived in by a couple or alone, making it a rare rental property. However, large 1LDKs have low yields, so they are not often newly built. Therefore, if two households are completely separated and one LDK is rented out as one household, it is expected that the vacancy rate will decrease as renters will be easier to find due to the scarcity of housing. Such properties also have less risk for the rental business.
(20) Less invested capital is required for rental, which improves investment efficiency and reduces operating expenses. While the surface yield of a one-room operation in the city center (for example, an investment of 24 million yen and a monthly income of 100,000 yen - management fees, reserve for repairs, and fixed asset tax) is around 5%, management costs and reserves for repairs are unnecessary. 1LDK rental management where two households are completely separated (for example, an investment of 4 million to 7 million yen and an income of 80,000 to 150,000 yen - repair expenses such as painting the exterior walls) has a high surface yield of about 14% to 45%. Furthermore, since it is a detached house, the property tax will not change before and after the renovation.
(21) By simulating the rental income of a property after renovation, it is possible to know the future financial plan at the time of construction and to foresee the future household finances. If you incorporate rental income into your 35-year mortgage repayment plan after your children leave the family, you may be able to repay your loan smoothly.

図1は、適用例1に係る戸建て住宅の1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 1 is a schematic plan view showing the structure of the first floor of a detached house according to Application Example 1 (a) before renovation and (b) after renovation. 図2は、図1に示した戸建て住宅の2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 2 is a schematic plan view showing the structure of the second floor of the detached house shown in FIG. 1 (a) before renovation and (b) after renovation. 図3は、一変形例に係る戸建て住宅の1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 3 is a schematic plan view showing the structure of the first floor of a detached house according to a modified example (a) before renovation and (b) after renovation. 図4は、一変形例に係る戸建て住宅の2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 4 is a schematic plan view showing the structure of the second floor of a detached house according to a modified example (a) before renovation and (b) after renovation. 図5は、適用例2に係る戸建て住宅の1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 5 is a schematic plan view showing the structure of the first floor of a detached house according to Application Example 2 (a) before renovation and (b) after renovation. 図6は、適用例3に係る戸建て住宅の1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 6 is a schematic plan view showing the structure of the first floor of a detached house according to Application Example 3 (a) before renovation and (b) after renovation. 図7は、図6に示した戸建て住宅の2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 7 is a schematic plan view showing the structure of the second floor of the detached house shown in FIG. 6 (a) before renovation and (b) after renovation. 図8は、適用例4に係る戸建て住宅の1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 8 is a schematic plan view showing the structure of the first floor of a detached house according to Application Example 4 (a) before renovation and (b) after renovation. 図9は、図8に示した戸建て住宅の2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。FIG. 9 is a schematic plan view showing the structure of the second floor of the detached house shown in FIG. 8 (a) before renovation and (b) after renovation. 図10は、具体例1に係る改築前の戸建て住宅の玄関と扉設置予定部の概略的な正面図である。FIG. 10 is a schematic front view of the entrance and door installation area of a detached house before renovation according to Specific Example 1. 図11は、戸建て住宅が木造である場合に適用し得る床下の構造の一例を示す概略的な斜視図である。FIG. 11 is a schematic perspective view showing an example of an underfloor structure that can be applied when the detached house is made of wood. 図12は、2世帯完全分離住宅への改築後の具体例1に係る戸建て住宅の玄関の概略的な正面図である。FIG. 12 is a schematic front view of the entrance of the detached house according to Specific Example 1 after the remodeling into a two-family completely separated house. 図13は、玄関扉とその近傍の一例を示す概略的な断面図である。FIG. 13 is a schematic cross-sectional view showing an example of an entrance door and its vicinity. 図14は、玄関扉とその近傍の他の例を示す概略的な断面図である。FIG. 14 is a schematic cross-sectional view showing another example of an entrance door and its vicinity. 図15は、具体例2に係る改築前の戸建て住宅の玄関と扉設置予定部の概略的な正面図である。FIG. 15 is a schematic front view of the entrance and door installation area of a detached house before renovation according to Specific Example 2. 図16は、具体例3に係る改築前の戸建て住宅の玄関と扉設置予定部の概略的な正面図である。FIG. 16 is a schematic front view of the entrance and door installation area of a detached house before renovation according to Specific Example 3. 図17は、2世帯完全分離住宅への改築後の具体例3に係る戸建て住宅の玄関の概略的な正面図である。FIG. 17 is a schematic front view of the entrance of a single-family house according to Specific Example 3 after being remodeled into a two-family completely separated house. 図18は、玄関扉とその近傍の一例を示す概略的な断面図である。FIG. 18 is a schematic cross-sectional view showing an example of an entrance door and its vicinity. 図19は、具体例4に係る構造を示す概略的な断面図である。FIG. 19 is a schematic cross-sectional view showing a structure according to specific example 4. 図20は、具体例5に係る改築前の戸建て住宅の玄関と扉設置予定部の概略的な正面図である。FIG. 20 is a schematic front view of the entrance and door installation area of a detached house before renovation according to Example 5. 図21は、2世帯完全分離住宅への改築後の具体例5に係る戸建て住宅の玄関の概略的な正面図である。FIG. 21 is a schematic front view of the entrance of a detached house according to Specific Example 5 after renovation to a two-family completely separated house.

以下、本発明のいくつかの実施形態につき、図面を参照しながら説明する。
本発明に係る戸建て住宅と、この住宅を2世帯完全分離住宅へと改築する改築方法は、標準的な2階戸建ての木造または鉄骨造の4LDK住宅(例えば35~40坪)に適用することができる。ただし、本発明に係る戸建て住宅とその改築方法は、3階建て以上の住宅、あるいは4LDKとは異なる間取りの住宅等に適用することも可能である。
Hereinafter, some embodiments of the present invention will be described with reference to the drawings.
The detached house according to the present invention and the renovation method for converting the house into a two-family completely separated house can be applied to a standard two-story detached wooden or steel-framed 4LDK house (for example, 35 to 40 tsubo). can. However, the detached house and its renovation method according to the present invention can also be applied to houses with three or more floors, or houses with a floor plan different from a 4LDK.

[戸建て住宅への適用例1]
図1は、適用例1に係る戸建て住宅1Aの1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。図2は、図1に示した戸建て住宅1Aの2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。
[Example 1 of application to detached houses]
FIG. 1 is a schematic plan view showing the structure of the first floor of a detached house 1A according to Application Example 1 (a) before renovation and (b) after renovation. FIG. 2 is a schematic plan view showing the structure of the second floor of the detached house 1A shown in FIG. 1 (a) before renovation and (b) after renovation.

図1および図2において、太線で示す部分は耐力壁であり、右上がりの斜線で示す部分は2世帯完全分離住宅への改築時の撤去予定壁であり、左上がりの斜線で示す部分は2世帯完全分離住宅への改築時の追加壁である。 In Figures 1 and 2, the part indicated by the thick line is the load-bearing wall, the part indicated by the diagonal line upward to the right is the wall scheduled to be removed when the house is renovated into a two-family completely separated house, and the part indicated by the diagonal line upward to the left is the This is an additional wall when the house was renovated into a completely separated house.

ここで、耐力壁とは、主に水平方向への力に抗する機能を有した壁であり、一例では筋交いやブレースなどの水平補強材を含んだ壁である。また、撤去予定壁は、仮に除去されたとしても戸建て住宅1Aが所定の建築基準を満たす壁であり、一例では筋交いやブレースを含まない非耐力壁である。 Here, the load-bearing wall is a wall that has a function of resisting force mainly in the horizontal direction, and is, for example, a wall that includes horizontal reinforcing materials such as braces and braces. Further, the wall to be removed is a wall that, even if removed, would satisfy the predetermined building standards of the detached house 1A, and in one example is a non-load-bearing wall that does not include braces or braces.

上記建築基準は、例えば建築基準法にて定められた新耐震基準であるが、任意に定められたより高い基準であってもよいし、他の法令で定められる建築基準であってもよい。例えば、戸建て住宅1Aの設計時において、撤去予定壁が無いものとして戸建て住宅1A全体の構造計算が行われ、耐震性が評価される。これにより、撤去予定壁が撤去された後でも、戸建て住宅1A全体が上記建築基準を満たすこととなる。 The above-mentioned building standard is, for example, the new seismic standard specified by the Building Standards Act, but it may be a higher standard that is arbitrarily specified, or it may be a building standard specified by other laws and regulations. For example, when designing a detached house 1A, the structure of the entire detached house 1A is calculated assuming that there are no walls to be removed, and the seismic resistance is evaluated. As a result, even after the wall scheduled for removal is removed, the entire detached house 1A will meet the above building standards.

図1(a)に示すように、改築前の戸建て住宅1Aの1階は、玄関E1、ホールHL1、リビングダイニングキッチンLDK1、和室JR、押し入れJC、物置SR1、浴室BR1、洗面所PR1およびトイレWC1を外壁10の内側に有している。 As shown in Figure 1(a), the first floor of detached house 1A before renovation consists of entrance E1, hall HL1, living-dining-kitchen LDK1, Japanese-style room JR, closet JC, storeroom SR1, bathroom BR1, washroom PR1, and toilet WC1. is located inside the outer wall 10.

玄関E1には、玄関扉D1が設けられている。玄関扉D1の内側には、例えばタイルなどで構成された玄関フロアF1(格子パターンを付した部分)が設けられており、玄関フロアF1には下駄箱S1が配置されている。 The entrance E1 is provided with an entrance door D1. On the inside of the entrance door D1, an entrance floor F1 (portion with a grid pattern) made of, for example, tiles is provided, and a shoe rack S1 is arranged on the entrance floor F1.

ホールHL1は、例えばフローリングにより構成された床面を有し、玄関フロアF1に隣接している。ホールHL1には、階段STの上り口が位置している。階段STは、外壁10に沿って配置されている。物置SR1は、階段STの下方に設けられている。 The hall HL1 has a floor made of, for example, flooring, and is adjacent to the entrance floor F1. The entrance of the staircase ST is located in the hall HL1. Stairs ST are arranged along the outer wall 10. The storeroom SR1 is provided below the stairs ST.

リビングダイニングキッチンLDK1およびトイレWC1には、ホールHL1に設けられた出入口を通じて出入り可能である。また、洗面所PR1への出入口はリビングダイニングキッチンLDK1に設けられており、浴室BR1への出入口は洗面所PR1に設けられている。洗面所PR1は、例えば洗面台や洗濯機置場を含む。 The living-dining-kitchen LDK1 and toilet WC1 can be entered and exited through an entrance provided in the hall HL1. Furthermore, the entrance to the bathroom PR1 is provided in the living room, dining kitchen, and LDK1, and the entrance to the bathroom BR1 is provided in the bathroom PR1. The washroom PR1 includes, for example, a washstand and a washing machine storage area.

和室JRへの出入口は、リビングダイニングキッチンLDK1に設けられている。押し入れJC(ドットを付した空間)は、和室JRに併設されている。押し入れJCは、ホールHL1に張り出すように配置されており、耐力壁を介して玄関フロアF1に隣接している。さらに、押し入れJCは、外壁10に面している。 The entrance to the JR Japanese-style room is located in the living-dining-kitchen LDK1. Closet JC (space marked with a dot) is attached to the Japanese-style room JR. The closet JC is arranged so as to extend into the hall HL1, and is adjacent to the entrance floor F1 via a load-bearing wall. Furthermore, the closet JC faces the outer wall 10.

外壁10のうち押し入れJCに面した部分には、撤去予定壁の一態様である扉設置予定部11が設けられている。扉設置予定部11は、後述の玄関扉D2を設置可能な大きさを有している。さらに、押し入れJCに面した内壁の一部は、平面視においてL字型の撤去予定壁12aにより構成されている。 A portion of the outer wall 10 facing the closet JC is provided with a door installation portion 11, which is one aspect of the wall scheduled to be removed. The door installation planned portion 11 has a size that allows installation of an entrance door D2, which will be described later. Further, a part of the inner wall facing the closet JC is constituted by an L-shaped wall to be removed 12a in plan view.

図2(a)に示すように、改築前の戸建て住宅1Aの2階は、階段STの下り口が配置されたホールHL2、3つの寝室BD1~BD3、これら寝室BD1~BD3に設けられたクローゼットCL1~CL3、物置SR2およびトイレWC2を外壁20の内側に有している。寝室BD1~BD3、物置SR2およびトイレWC2には、ホールHL2に設けられた出入口を通じて出入り可能である。 As shown in Figure 2(a), the second floor of the detached house 1A before renovation consists of a hall HL2 where the exit of the staircase ST is located, three bedrooms BD1 to BD3, and closets provided in these bedrooms BD1 to BD3. It has CL1 to CL3, a storeroom SR2, and a toilet WC2 inside the outer wall 20. Bedrooms BD1 to BD3, storeroom SR2, and toilet WC2 can be accessed through an entrance provided in hall HL2.

図2(a)の例においては、寝室BD2,BD2が撤去予定壁22aにより仕切られている。さらに、寝室BD3のクローゼットCL3とホールHL2の間の内壁の一部が撤去予定壁22bにより構成されている。 In the example of FIG. 2(a), bedrooms BD2 and BD2 are separated by a wall 22a scheduled for removal. Further, a part of the inner wall between the closet CL3 of the bedroom BD3 and the hall HL2 is constituted by the wall 22b scheduled for removal.

戸建て住宅1Aを2世帯完全分離住宅に改築する際には、図1(a)に示す扉設置予定部11および撤去予定壁12aが撤去される。さらに、図1(b)に示すように、押し入れJCが玄関E2の玄関フロアF2(格子パターンを付した部分)に改装される。扉設置予定部11があった箇所には、玄関E2の玄関扉D2が設置される。 When renovating the detached house 1A into a two-family completely separated house, the door installation portion 11 and the wall 12a to be removed shown in FIG. 1(a) are removed. Furthermore, as shown in FIG. 1(b), the closet JC is renovated to the entrance floor F2 (the part with the grid pattern) of the entrance E2. The entrance door D2 of the entrance E2 is installed at the location where the planned door installation section 11 was located.

さらに、押し入れJCの入口(襖)であった箇所に追加壁13aが設置されるとともに、玄関フロアF1,F2を区切る追加壁13bが設置される。追加壁13bは平面視においてジグザグに屈曲しており、その一部に面して玄関E2用の下駄箱S2が配置されている。 Further, an additional wall 13a is installed at the location that was the entrance (sliding door) of the closet JC, and an additional wall 13b is installed to separate the entrance floors F1 and F2. The additional wall 13b is bent in a zigzag manner in a plan view, and a shoe rack S2 for the entrance E2 is arranged facing a part of the additional wall 13b.

図1(b)の例においては、追加壁13bが階段STの屋内の側壁に繋がっている。追加壁13bにより、改築前のホールHL1の一部が玄関フロアF2に繋がるホールHL3として分離される。さらに、玄関フロアF1、ホールHL1および階段STを含む空間と、玄関フロアF2およびホールHL3を含む空間とが完全に仕切られる。 In the example of FIG. 1(b), the additional wall 13b is connected to the indoor side wall of the stairs ST. The additional wall 13b separates a part of the hall HL1 before the renovation into a hall HL3 connected to the entrance floor F2. Furthermore, a space including the entrance floor F1, hall HL1, and stairs ST is completely partitioned from a space including the entrance floor F2 and hall HL3.

一方で2階に関しては、図2(b)に示すように、撤去予定壁22a,22bが撤去されるとともに、ホールHL2に追加壁23aが設置される。さらに、クローゼットCL3の扉が撤去されて、その部分に追加壁23bが設置される。 On the other hand, regarding the second floor, as shown in FIG. 2(b), the walls 22a and 22b scheduled for removal are removed, and an additional wall 23a is installed in the hall HL2. Furthermore, the door of the closet CL3 is removed, and an additional wall 23b is installed in that area.

撤去予定壁22aが撤去されることにより寝室BD2,BD3が繋がり、2階のリビングダイニングキッチンLDK2に改装されている。追加壁23aは、改築前の寝室BD2,BD3の入口の間に配置されている。 By removing the wall 22a scheduled for removal, bedrooms BD2 and BD3 are connected, and the living-dining-kitchen LDK2 on the second floor is renovated. The additional wall 23a is placed between the entrances of the bedrooms BD2 and BD3 before renovation.

図2(b)の例においては、物置SR2が洗濯機置き場に改装されている。さらに、クローゼットCL3が浴室BR2に改装され、浴室BR2の隣の空間が洗面所PR2に改装されている。 In the example of FIG. 2(b), storeroom SR2 has been renovated into a washing machine storage area. Furthermore, the closet CL3 has been renovated into a bathroom BR2, and the space next to the bathroom BR2 has been renovated into a washroom PR2.

図1(a)(b)に示すように、戸建て住宅1Aには新築当初から2階へのライフライン管Pが設置されている。図1(a)(b)の例においては、ライフライン管Pが洗面所PR1に位置しているが、この例に限られない。 As shown in FIGS. 1(a) and 1(b), a lifeline pipe P to the second floor has been installed in the detached house 1A since it was newly built. In the examples of FIGS. 1(a) and 1(b), the lifeline pipe P is located in the washroom PR1, but the present invention is not limited to this example.

ライフライン管Pは、水道、下水、ガスなどの配管を含む。このライフライン管Pは、2階の床下などを通じて、新築時から既設の2階の水回り部(トイレWC2等)および改築時に設置される予定の水回り想定部(キッチン台の設置予定位置、浴室BR2の設置予定位置、洗面所PR2の設置予定位置、洗濯機置き場の設置予定位置等)に分岐している。水回り想定部への配管に必要な穴などを新築時に形成しておいてもよい。改築時にこのライフライン管Pや穴を利用することで、2回の水回り想定部への配管工事を安価に行うことができる。また、外壁10,20の外面に沿って配管を追加する必要がなくなり、戸建て住宅1Aの美観も保たれる。 The lifeline pipes P include pipes for water, sewage, gas, and the like. This lifeline pipe P is installed under the floor of the 2nd floor, etc., to the existing 2nd floor water area (toilet WC2, etc.) at the time of new construction, and to the water area expected to be installed at the time of renovation (planned location of kitchen stand, etc.) The planned installation position of the bathroom BR2, the planned installation position of the washroom PR2, the planned installation position of the washing machine storage area, etc.) are branched. The holes necessary for piping to the assumed water area may be formed during new construction. By using this lifeline pipe P and holes during renovation, piping work to the expected water area can be carried out twice at low cost. Further, there is no need to add piping along the outer surfaces of the outer walls 10 and 20, and the aesthetic appearance of the detached house 1A is also maintained.

浴室BR2およびキッチンなど、改築後に通気を要する箇所に面する外壁20に対し、換気扇や窓の設置予定部を形成しておいてもよい。このような設置予定部は、柱や筋交いを避けた位置に設けて容易に開口できる構造を有することが好ましい。 A portion where a ventilation fan or a window is to be installed may be formed on the outer wall 20 facing areas that require ventilation after renovation, such as the bathroom BR2 and the kitchen. It is preferable that such a planned installation part has a structure in which it is provided in a position avoiding pillars and braces and can be easily opened.

改築後に2世帯が戸建て住宅1Aに居住することを考慮し、2階から1階に音が漏れにくいように階段STや2階の床の振動防止・防音処置を新築時から施しておくことが好ましい。 Considering that two families will be living in single-family house 1A after renovation, it is recommended to apply anti-vibration and soundproofing measures to the stairs ST and the second floor floor from the time of new construction to prevent sound from leaking from the second floor to the first floor. preferable.

200m未満の建築物については90cmの避難通路を、200m以上の建築物については1.5mの避難通路を玄関の周囲に確保する必要がある。図1(b)の例においては、既設の玄関E1についてこのような避難通路を確保しておけば、玄関E1に隣接する追加の玄関E2も同じ避難通路を活用することができる。なお、玄関E2を玄関E1と隣接しない位置に設ける場合には、予め玄関E2からの避難通路が確保できるように扉設置予定部11を含む戸建て住宅1Aを設計しておく必要がある。 For buildings less than 200m2 , a 90cm evacuation route must be provided, and for buildings larger than 200m2 , a 1.5m evacuation route must be provided around the entrance. In the example of FIG. 1B, if such an evacuation passage is secured for the existing entrance E1, the same evacuation passage can also be used for the additional entrance E2 adjacent to the entrance E1. In addition, when the entrance E2 is provided in a position that is not adjacent to the entrance E1, it is necessary to design the detached house 1A including the planned door installation part 11 in advance so that an evacuation route from the entrance E2 can be secured.

以上のライフライン管P、換気扇や窓の設置予定部の形成、振動防止・防音処置および避難通路に関する構成は、後述する変形例や他の適用例に係る戸建て住宅にも同様に適用される。 The above-described configurations regarding the lifeline pipe P, the formation of the planned installation area for ventilation fans and windows, anti-vibration/soundproofing measures, and evacuation passages are similarly applied to detached houses according to modified examples and other application examples described later.

図1(b)および図2(b)の例においては、1階の生活空間と2階の生活空間が完全に分離された(屋内で繋がっていない)2世帯完全分離住宅が実現されている。ここで、1階の生活空間とは、リビングダイニングキッチンLDK1、和室JR、物置SR1、浴室BR1、洗面所PR1およびトイレWC1等を含む空間を意味する。また、2階の生活空間とは、リビングダイニングキッチンLDK2、寝室BD1、物置SR2、浴室BR2、洗面所PR2およびトイレWC2等を含む空間を意味する。 In the examples shown in Figures 1(b) and 2(b), a two-family completely separated house is realized in which the living space on the first floor and the living space on the second floor are completely separated (not connected indoors). . Here, the living space on the first floor means a space including a living-dining-kitchen LDK1, a Japanese-style room JR, a storeroom SR1, a bathroom BR1, a washroom PR1, a toilet WC1, and the like. Furthermore, the living space on the second floor means a space including a living/dining/kitchen LDK2, a bedroom BD1, a storeroom SR2, a bathroom BR2, a washroom PR2, a toilet WC2, and the like.

玄関E1は2階用であり、玄関E2は1階用である。図1(b)に示すように、改築後の1階においては、玄関E1から階段STの上り口への動線L1(2階の生活空間への動線)と、玄関E2から1階の生活空間への動線L2とが確保されている。これらの動線L1,L2は、新築時からの耐力壁などの内壁や追加壁13bによって、空間的に完全に分離されている。 The entrance E1 is for the second floor, and the entrance E2 is for the first floor. As shown in Figure 1(b), on the first floor after the renovation, there is a flow line L1 from the entrance E1 to the top of the stairs ST (flow line to the living space on the second floor), and a flow line from the entrance E2 to the first floor. A flow line L2 to the living space is secured. These flow lines L1 and L2 are completely separated spatially by inner walls such as load-bearing walls and additional walls 13b from the time of new construction.

既設の玄関を利用した2世帯完全分離住宅への改築を可能とするためには、改築後の2つの玄関から各生活空間への動線を考慮して戸建て住宅を設計しておく必要がある。具体的には、改築前の玄関および改築後に追加の玄関となる収納空間の一方と階段の上り口を繋ぐ第1動線が1階の生活空間を分断せず、かつ他方と1階の生活空間を繋ぐ第2動線が第1動線と交差しないように構成しなければならない。 In order to make it possible to remodel a two-family completely separated house using the existing entrance, it is necessary to design the detached house with consideration to the flow lines from the two entrances to each living space after the renovation. . Specifically, the first flow line that connects one side of the entrance before the renovation and the storage space that will become an additional entrance after the renovation to the top of the stairs will not divide the living space on the first floor, and will not separate the living space from the other and the living space on the first floor. It must be constructed so that the second flow line connecting the spaces does not intersect with the first flow line.

図1(a)の例においては、玄関E1と階段STの上り口を繋ぐ動線L1(第1動線)が1階の生活空間を分断しない。さらに、押し入れJC(収納空間)と1階の生活空間を繋ぐ動線L2(第2動線)が動線L1と交差しない。これにより、図1(b)のように動線L1,L2をそれぞれ1階および2階への動線として活用することができ、屋内の改築箇所を少なく抑えることができる。さらに、新築時からの玄関E1を改築後にも2世帯の一方の玄関としてそのまま使用することができる。なお、図1(a)に示す動線L2は、押し入れJCの撤去予定壁12aが無い場合に形成される動線である。 In the example of FIG. 1(a), the flow line L1 (first flow line) connecting the entrance E1 and the top of the stairs ST does not divide the living space on the first floor. Furthermore, the flow line L2 (second flow line) connecting the closet JC (storage space) and the living space on the first floor does not intersect with the flow line L1. Thereby, the flow lines L1 and L2 can be utilized as flow lines to the first floor and the second floor, respectively, as shown in FIG. 1(b), and the number of indoor renovations can be kept to a small number. Furthermore, the entrance E1 from the time of the new construction can be used as the entrance for one of the two households even after the renovation. Note that the flow line L2 shown in FIG. 1(a) is a flow line formed when there is no wall 12a scheduled for removal of the closet JC.

改築前後の戸建て住宅1Aの構造は、図1および図2に示したものに限られない。以下に、いくつかの変形例を示す。
図3は、一変形例に係る戸建て住宅1Aの1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。本変形例においては、改築前の押し入れJCの奥行が図1の例よりも大きい。例えば一般的な押し入れの奥行きは900mm程度であるが、図3(a)示す押し入れJCの奥行きは1200mm以上である。この押し入れJCを図1の例と同じく玄関E2に改装することにより、十分な幅を有した玄関フロアF2を確保することができる。
The structure of the detached house 1A before and after renovation is not limited to that shown in FIGS. 1 and 2. Some modified examples are shown below.
FIG. 3 is a schematic plan view showing the structure of the first floor of a detached house 1A according to a modified example (a) before renovation and (b) after renovation. In this modification, the depth of the closet JC before renovation is larger than the example in FIG. 1. For example, the depth of a typical closet is about 900 mm, but the depth of the closet JC shown in FIG. 3(a) is 1200 mm or more. By converting this closet JC into an entrance E2 as in the example of FIG. 1, it is possible to secure an entrance floor F2 with sufficient width.

図4は、一変形例に係る戸建て住宅1Aの2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。本変形例においては、図2において物置SR2であった位置に改築前からトイレWC2が配置され、図2においてトイレWC2であった位置に物置SR2が配置されている。このような構造の2階を図2の例と同様に改築することにより、2階の水回り部(トイレWC2、キッチン台、浴室BR2、洗面所PR2等)が隣接して配置されることとなり、ライフライン管Pを用いた配管が容易となる。 FIG. 4 is a schematic plan view showing the structure of the second floor of a detached house 1A according to a modified example (a) before renovation and (b) after renovation. In this modification, the toilet WC2 has been placed in the position that was the storeroom SR2 in FIG. 2 before the renovation, and the storeroom SR2 is placed in the position that was the toilet WC2 in FIG. By renovating the second floor of such a structure in the same way as the example in Figure 2, the water areas on the second floor (toilet WC2, kitchen counter, bathroom BR2, washroom PR2, etc.) will be placed adjacent to each other. , piping using the lifeline pipe P becomes easy.

[戸建て住宅への適用例2]
図5は、適用例2に係る戸建て住宅1Bの1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。戸建て住宅1Bの1階の間取りは、戸建て住宅1Aと同様である。また、戸建て住宅1Bの2階の間取りにも戸建て住宅1Aの2階と同じ間取りを適用でき、その改築前後の構造は例えば図2および図4と同様である。
[Example 2 of application to detached houses]
FIG. 5 is a schematic plan view showing the structure of the first floor of the detached house 1B according to Application Example 2 (a) before renovation and (b) after renovation. The floor plan of the first floor of the detached house 1B is the same as that of the detached house 1A. Furthermore, the same floor plan as the second floor of the detached house 1A can be applied to the second floor of the detached house 1B, and the structure before and after the renovation is the same as, for example, in FIGS. 2 and 4.

図5(a)の例においては、外壁10のうち物置SR1(ドットを付した空間)に面した部分に扉設置予定部11が設けられている。物置SR1は、階段STの下方に位置し、人が通過できる十分な高さを有している。 In the example of FIG. 5A, a door installation planned portion 11 is provided in a portion of the outer wall 10 facing the storeroom SR1 (the space marked with a dot). The storeroom SR1 is located below the stairs ST and has sufficient height for people to pass through.

図5(b)に示すように、戸建て住宅1Bを2世帯完全分離住宅へ改築する際には、扉設置予定部11が撤去される。さらに、物置SR1の扉が撤去されるとともに、物置SR1が玄関E2の玄関フロアF2(格子パターンを付した部分)に改装される。扉設置予定部11には、玄関E2の玄関扉D2が設置される。図5(b)には示されていないが、玄関フロアF2には下駄箱も配置される。 As shown in FIG. 5(b), when renovating the detached house 1B into a two-family completely separated house, the planned door installation portion 11 is removed. Further, the door of the storeroom SR1 is removed, and the storeroom SR1 is renovated into the entrance floor F2 (the part with the grid pattern) of the entrance E2. The entrance door D2 of the entrance E2 is installed in the door installation planned section 11. Although not shown in FIG. 5(b), a shoe rack is also arranged on the entrance floor F2.

また、階段STの上り口の近傍に追加壁13cが設置される。この追加壁13cにより、改築前のホールHL1の一部が玄関フロアF2に繋がるホールHL3として分離される。さらに、玄関E1から階段STの上り口への動線L1(2階の生活空間への動線)と、玄関E2から1階の生活空間への動線L2とが追加壁13cによって空間的に完全に分離される。 Further, an additional wall 13c is installed near the top of the stairs ST. This additional wall 13c separates a part of the hall HL1 before the renovation into a hall HL3 connected to the entrance floor F2. Furthermore, the flow line L1 from the entrance E1 to the top of the stairs ST (flow line to the living space on the second floor) and the flow line L2 from the entrance E2 to the living space on the first floor are spatially separated by the additional wall 13c. Completely separated.

図1の例においては、玄関扉D1と同じ方向を向く外壁10に玄関扉D2が設置されていた。一方で、図5の例においては、玄関扉D1とは異なる方向を向く外壁10に玄関扉D2が設置されている。なお、図5の例においても、扉設置予定部11の外側には、上述の避難通路に適合した幅のスペースが予め確保されている。 In the example of FIG. 1, the entrance door D2 is installed on the outer wall 10 facing in the same direction as the entrance door D1. On the other hand, in the example of FIG. 5, the entrance door D2 is installed on the outer wall 10 facing in a different direction from the entrance door D1. In the example of FIG. 5 as well, a space with a width suitable for the above-mentioned evacuation passage is secured in advance outside the planned door installation section 11.

図1(a)の例と同じく、図5(a)の例においても、玄関E1と階段STの上り口を繋ぐ動線L1(第1動線)が1階の生活空間を分断しない。さらに、物置SR1(収納空間)と1階の生活空間を繋ぐ動線L2(第2動線)が動線L1と交差しない。これにより、図5(b)のように動線L1,L2をそれぞれ1階および2階への動線として活用することができ、屋内の改築箇所を少なく抑えることができる。さらに、新築時からの玄関E1を改築後にも2世帯の一方の玄関としてそのまま使用することができる。 Similarly to the example of FIG. 1(a), also in the example of FIG. 5(a), the flow line L1 (first flow line) connecting the entrance E1 and the top of the stairs ST does not divide the living space on the first floor. Furthermore, the flow line L2 (second flow line) connecting the storeroom SR1 (storage space) and the living space on the first floor does not intersect with the flow line L1. Thereby, the flow lines L1 and L2 can be utilized as flow lines to the first floor and the second floor, respectively, as shown in FIG. 5(b), and the number of indoor renovations can be kept small. Furthermore, the entrance E1 from the time of the new construction can be used as the entrance for one of the two households even after the renovation.

[戸建て住宅への適用例3]
図6は、適用例3に係る戸建て住宅1Cの1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。図7は、図6に示した戸建て住宅1Cの2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。
[Example 3 of application to detached houses]
FIG. 6 is a schematic plan view showing the structure of the first floor of a detached house 1C according to Application Example 3 (a) before renovation and (b) after renovation. FIG. 7 is a schematic plan view showing the structure of the second floor of the detached house 1C shown in FIG. 6 (a) before renovation and (b) after renovation.

図6(a)に示すように、改築前の戸建て住宅1Cの1階は、玄関E1、ホールHL1、リビングダイニングキッチンLDK1、和室JR、押し入れJC、浴室BR1、洗面所PR1およびトイレWC1を外壁10の内側に有している。 As shown in FIG. 6(a), the first floor of the detached house 1C before renovation has an entrance E1, a hall HL1, a living-dining-kitchen LDK1, a Japanese-style room JR, a closet JC, a bathroom BR1, a washroom PR1, and a toilet WC1. It has inside.

玄関E1には玄関扉D1が設けられ、玄関扉D1の内側には玄関フロアF1(格子パターンを付した部分)が設けられている。玄関フロアF1には下駄箱S1が配置されている。ホールHL1には、階段STの上り口が位置している。階段STは、外壁10に沿って配置されている。 An entrance door D1 is provided at the entrance E1, and an entrance floor F1 (portion with a lattice pattern) is provided inside the entrance door D1. A shoe rack S1 is arranged on the entrance floor F1. The entrance of the staircase ST is located in the hall HL1. Stairs ST are arranged along the outer wall 10.

押し入れJCは、外壁10のうち、玄関扉D1が設けられた部分よりも図中の上方に突出した部分に面している。外壁10のうち押し入れJCに面した部分(押し入れJCの奥の面を構成する部分)には、扉設置予定部11が設けられている。 The closet JC faces a portion of the outer wall 10 that protrudes upward in the figure from a portion where the entrance door D1 is provided. A door installation portion 11 is provided in a portion of the outer wall 10 facing the closet JC (a portion constituting the back surface of the closet JC).

図7(a)に示すように、改築前の戸建て住宅1Cの2階は、階段STの下り口が配置されたホールHL2、3つの寝室BD1~BD3、これら寝室BD1~BD3に設けられたクローゼットCL1~CL3、物置SR2およびトイレWC2を外壁20の内側に有している。図7(a)の例においては、クローゼットCL3とホールHL2が撤去予定壁22cにより仕切られている。 As shown in FIG. 7(a), the second floor of the detached house 1C before renovation includes a hall HL2 where the exit of the staircase ST is located, three bedrooms BD1 to BD3, and closets provided in these bedrooms BD1 to BD3. It has CL1 to CL3, a storeroom SR2, and a toilet WC2 inside the outer wall 20. In the example of FIG. 7A, the closet CL3 and the hall HL2 are separated by a wall 22c scheduled for removal.

戸建て住宅1Cを2世帯完全分離住宅に改築する際には、図1の例と同じく扉設置予定部11が撤去され、玄関E2の玄関扉D2が設置される。さらに、押し入れJCが玄関E2の玄関フロアF2(格子パターンを付した部分)に改装される。 When renovating the detached house 1C into a two-family completely separated house, the door installation planned portion 11 is removed and the entrance door D2 of the entrance E2 is installed, as in the example of FIG. Furthermore, the closet JC will be renovated into the entrance floor F2 (the part with the grid pattern) of the entrance E2.

図6(b)の例においては、玄関フロアF2の近傍にL字型の追加壁13dが設置され、和室JRの一部が玄関フロアF2に繋がるホールHL3に改装されている。さらに、和室JRとリビングダイニングキッチンLDK1の間に追加壁13eが設置され、和室JRとリビングダイニングキッチンLDK1をそれぞれホールHL3に繋ぐ出入口が設置されている。 In the example of FIG. 6(b), an L-shaped additional wall 13d is installed near the entrance floor F2, and a part of the Japanese-style room JR is renovated into a hall HL3 connected to the entrance floor F2. Furthermore, an additional wall 13e is installed between the Japanese-style room JR and the living-dining-kitchen LDK1, and an entrance is installed that connects the Japanese-style room JR and the living-dining-kitchen LDK1 to the hall HL3.

また、階段STの近傍に追加壁13fが設置されている。これにより、玄関フロアF1、ホールHL1および階段STを含む空間と、1階の生活空間とが完全に仕切られる。 Further, an additional wall 13f is installed near the stairs ST. As a result, a space including the entrance floor F1, hall HL1, and stairs ST is completely partitioned from the living space on the first floor.

一方で2階に関しては、図7(b)に示すように、撤去予定壁22cが撤去されるとともに、改築前に寝室BD3であった空間に追加壁23c,23dが設置される。さらに、改築前に寝室BD3であった空間とクローゼットCL3であった空間が、物置SR3、浴室BR2および洗面所PR2に改装されている。 On the other hand, regarding the second floor, as shown in FIG. 7(b), the wall 22c scheduled for removal is removed, and additional walls 23c and 23d are installed in the space that was the bedroom BD3 before the renovation. Furthermore, the space that was the bedroom BD3 and the closet CL3 before the renovation has been renovated into a storage room SR3, bathroom BR2, and washroom PR2.

また、図7(b)の例においては、寝室BD2であった空間がダイニングキッチンDKに改装され、クローゼットCL2であった空間にキッチン台が配置されている。 Furthermore, in the example of FIG. 7(b), the space that was the bedroom BD2 has been renovated into the dining kitchen DK, and a kitchen table has been placed in the space that was the closet CL2.

図1(a)の例と同じく、図6(a)の例においても、玄関E1と階段STの上り口を繋ぐ動線L1(第1動線)が1階の生活空間を分断しない。さらに、押し入れJC(収納空間)と1階の生活空間を繋ぐ動線L2(第2動線)が動線L1と交差しない。これにより、図6(b)のように動線L1,L2をそれぞれ1階および2階への動線として活用することができ、屋内の改築箇所を少なく抑えることができる。さらに、新築時からの玄関E1を改築後にも2世帯の一方の玄関としてそのまま使用することができる。 Similarly to the example of FIG. 1(a), also in the example of FIG. 6(a), the flow line L1 (first flow line) connecting the entrance E1 and the top of the stairs ST does not divide the living space on the first floor. Furthermore, the flow line L2 (second flow line) connecting the closet JC (storage space) and the living space on the first floor does not intersect with the flow line L1. Thereby, the flow lines L1 and L2 can be used as flow lines to the first floor and the second floor, respectively, as shown in FIG. 6(b), and the number of indoor renovations can be kept small. Furthermore, the entrance E1 from the time of the new construction can be used as the entrance for one of the two households even after the renovation.

[戸建て住宅への適用例4]
図8は、適用例4に係る戸建て住宅1Dの1階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。図9は、図8に示した戸建て住宅1Dの2階の(a)改築前と(b)改築後の構造を示す概略的な平面図である。
[Example 4 of application to detached houses]
FIG. 8 is a schematic plan view showing the structure of the first floor of the detached house 1D according to Application Example 4 (a) before renovation and (b) after renovation. FIG. 9 is a schematic plan view showing the structure of the second floor of the detached house 1D shown in FIG. 8 (a) before renovation and (b) after renovation.

図8(a)に示すように、改築前の戸建て住宅1Dの1階は、玄関E1、ホールHL1、リビングダイニングキッチンLDK1、多目的の家事室HR、物置SR1,SR2、浴室BR1、洗面所PR1およびトイレWC1を外壁10の内側に有している。 As shown in FIG. 8(a), the first floor of the detached house 1D before renovation consists of an entrance E1, a hall HL1, a living-dining-kitchen LDK1, a multipurpose housekeeping room HR, storage rooms SR1 and SR2, a bathroom BR1, a washroom PR1, and A toilet WC1 is provided inside the outer wall 10.

玄関E1には玄関扉D1が設けられ、玄関扉D1の内側には玄関フロアF1(格子パターンを付した部分)が設けられている。玄関フロアF1には下駄箱S1が配置されている。ホールHL1には、階段STの上り口が位置している。階段STは、外壁10に沿って配置されている。 An entrance door D1 is provided at the entrance E1, and an entrance floor F1 (portion with a lattice pattern) is provided inside the entrance door D1. A shoe rack S1 is arranged on the entrance floor F1. The entrance of the staircase ST is located in the hall HL1. Stairs ST are arranged along the outer wall 10.

リビングダイニングキッチンLDK1への出入口はホールHL1に設けられている。家事室HRおよび洗面所PR1への出入口はリビングダイニングキッチンLDK1に設けられている。物置SR1および浴室BR1への出入口は洗面所PR1に設けられている。 The entrance to the living-dining-kitchen LDK1 is provided in the hall HL1. The entrance to the housekeeping room HR and washroom PR1 is provided in the living-dining-kitchen LDK1. The entrance to the storeroom SR1 and the bathroom BR1 is provided in the washroom PR1.

物置SR2への出入口はホールHL1に設けられている。物置SR2は、階段STの上り口の近傍の外壁10に面している。外壁10のうち物置SR2に面した部分(物置SR2の奥の面を構成する部分)には、扉設置予定部11が設けられている。また、ホールHL1と物置SR2の間の内壁の一部が撤去予定壁12bにより構成されている。 An entrance to the storeroom SR2 is provided in the hall HL1. The storeroom SR2 faces the outer wall 10 near the top of the stairs ST. A door installation planned portion 11 is provided in a portion of the outer wall 10 facing the storeroom SR2 (a portion constituting the back surface of the storeroom SR2). Further, a part of the inner wall between the hall HL1 and the storeroom SR2 is constituted by a wall 12b scheduled for removal.

図9(a)に示すように、改築前の戸建て住宅1Dの2階は、階段STの下り口が配置されたホールHL2、3つの寝室BD1~BD3、これら寝室BD1~BD3に設けられたクローゼットCL1~CL3およびトイレWC2を外壁20の内側に有している。図9(a)の例においては、寝室BD3に2つのクローゼットCL3が設けられ、これらクローゼットCL3が撤去予定壁22dにより仕切られている。 As shown in FIG. 9(a), the second floor of the detached house 1D before renovation includes a hall HL2 where the exit of the staircase ST is located, three bedrooms BD1 to BD3, and closets provided in these bedrooms BD1 to BD3. It has CL1 to CL3 and a toilet WC2 inside the outer wall 20. In the example of FIG. 9A, two closets CL3 are provided in the bedroom BD3, and these closets CL3 are partitioned by a wall to be removed 22d.

戸建て住宅1Dを2世帯完全分離住宅に改築する際には、図1の例と同じく扉設置予定部11が撤去され、図8(b)に示すように扉設置予定部11であった箇所に玄関E2の玄関扉D2が設置される。さらに、物置SR2が玄関E2の玄関フロアF2(格子パターンを付した部分)に改装される。 When renovating a detached house 1D into a two-family completely separated house, the part 11 where the door was to be installed is removed, as in the example in Figure 1, and the part where the door was to be installed is replaced as shown in Figure 8(b). The entrance door D2 of the entrance E2 is installed. Furthermore, the storeroom SR2 is renovated into the entrance floor F2 (the part with the grid pattern) of the entrance E2.

さらに、撤去予定壁12bが撤去され、ホールHL1に追加壁13gが設置される。これにより、改築前にホールHL1であった空間の一部が玄関フロアF2に繋がるホールHL3に改装されている。 Furthermore, the wall scheduled for removal 12b is removed, and an additional wall 13g is installed in the hall HL1. As a result, part of the space that was hall HL1 before the renovation has been renovated into hall HL3, which connects to entrance floor F2.

図8(b)の例においては、リビングダイニングキッチンLDK1であった空間に追加壁13h,13iが設置されている。これにより、リビングダイニングキッチンLDK1であった空間の一部に寝室BDが形成される。 In the example of FIG. 8(b), additional walls 13h and 13i are installed in the space that used to be the living-dining-kitchen LDK1. As a result, a bedroom BD is formed in a part of the space that used to be the living-dining-kitchen LDK1.

一方で2階に関しては、図9(b)に示すように、撤去予定壁22dが撤去されるとともに、改築前に寝室BD3であった空間がダイニングキッチンDKに改装され、クローゼットCL3であった空間にキッチン台が配置されている。 On the second floor, on the other hand, as shown in Figure 9(b), the wall 22d scheduled for removal has been removed, the space that was the bedroom BD3 before the renovation was renovated into the dining kitchen DK, and the space that was the closet CL3 has been renovated. A kitchen table is placed in the room.

さらに、寝室BD2であった空間に追加壁23e,23fが設置され、寝室BD3であった空間とクローゼットCL3であった空間が、物置SR3、浴室BR2および洗面所PR2に改装されている。 Further, additional walls 23e and 23f are installed in the space that was the bedroom BD2, and the space that was the bedroom BD3 and the space that was the closet CL3 have been renovated into a storeroom SR3, a bathroom BR2, and a washroom PR2.

図8(a)の例においては、玄関E1と1階の生活空間を繋ぐ動線L1(第2動線)が1階の生活空間を分断しない。さらに、物置SR2(収納空間)と階段STの上り口を繋ぐ動線L2(第1動線)が動線L1と交差しない。これにより、図8(b)のように動線L1,L2をそれぞれ1階および2階への動線として活用することができ、屋内の改築箇所を少なく抑えることができる。さらに、新築時からの玄関E1を改築後にも2世帯の一方の玄関としてそのまま使用することができる。なお、戸建て住宅1Dにおける1階の生活空間とは、リビングダイニングキッチンLDK1、浴室BR1、洗面所PR1およびトイレWC1等を含む空間を意味する。 In the example of FIG. 8A, the flow line L1 (second flow line) connecting the entrance E1 and the living space on the first floor does not divide the living space on the first floor. Furthermore, the flow line L2 (first flow line) connecting the storeroom SR2 (storage space) and the top of the stairs ST does not intersect with the flow line L1. Thereby, the flow lines L1 and L2 can be used as flow lines to the first floor and the second floor, respectively, as shown in FIG. 8(b), and the number of indoor renovations can be kept small. Furthermore, the entrance E1 from the time of the new construction can be used as the entrance for one of the two households even after the renovation. Note that the living space on the first floor in the detached house 1D means a space including a living room, dining room, and kitchen LDK1, a bathroom BR1, a washroom PR1, a toilet WC1, and the like.

以上説明した適用例1~4においては、2世帯完全分離住宅への改築にあたり、いずれも収納空間(押し入れや物置)を追加の玄関フロアとして利用している。仮に、ホールHL1等に玄関を追加するためのスペースを確保しておく場合には、改築前にそのスペースを有効に活用できない可能性がある。これに対し、戸建て住宅の新築時(設計時)から追加の玄関フロアの設置場所として利用される収納空間を用意することで、玄関フロアを追加するためのスペースを改築前にも有効活用することができる。仮に改築を行わない場合であっても、そのスペースが無駄になることはない。なお、扉設置予定部11は、収納空間以外の部屋(例えば戸建て住宅1Aの和室JRなどの居室)に設けられてもよい。この場合には、改築時に和室JRが玄関フロアとして改装される。 In application examples 1 to 4 explained above, storage space (closet or storeroom) is used as an additional entrance floor when the house is remodeled into a two-family completely separated house. If space is to be secured for adding an entrance to hall HL1 etc., there is a possibility that the space cannot be used effectively before the renovation. In contrast, by preparing a storage space that can be used as a place for installing an additional entrance floor from the time of new construction (design) of a detached house, it is possible to effectively utilize the space for adding an entrance floor even before renovation. I can do it. Even if the renovation is not done, the space will not be wasted. In addition, the door installation planned part 11 may be provided in a room other than the storage space (for example, a living room such as a Japanese-style room JR of the detached house 1A). In this case, the Japanese-style JR room will be renovated as the entrance floor during the renovation.

続いて、2世帯完全分離住宅への改築時に玄関を追加するための構造のいくつかの具体例について説明する。各具体例においては、主に図1に示した戸建て住宅1Aを想定して玄関E1および扉設置予定部11の周囲の構造を例示するが、同様の構造を他の戸建て住宅にも適用できる。 Next, we will explain some specific examples of structures for adding an entrance when renovating a two-family completely separated house. In each specific example, the structure around the entrance E1 and the planned door installation part 11 will be illustrated mainly assuming the detached house 1A shown in FIG. 1, but the same structure can be applied to other detached houses.

[玄関追加の具体例1]
図10は、具体例1に係る改築前の戸建て住宅1Aの玄関E1と扉設置予定部11の概略的な正面図である。この図においては、耐力壁の壁面を構成する壁材を省略し、壁内部の構造も示している。
[Specific example of adding an entrance 1]
FIG. 10 is a schematic front view of the entrance E1 and the scheduled door installation portion 11 of the detached house 1A before renovation according to the first example. In this figure, the wall materials constituting the wall surface of the load-bearing wall are omitted, and the structure inside the wall is also shown.

戸建て住宅1Aは、コンクリートで形成された基礎1を備えている。基礎1の上には基礎パッキン2が配置され、基礎パッキン2の上には水平方向に延びる土台3が配置されている。 The detached house 1A includes a foundation 1 made of concrete. A foundation packing 2 is placed on the foundation 1, and a foundation 3 extending in the horizontal direction is placed on the foundation packing 2.

土台3には、鉛直方向に延びる多数の柱材40が配置されている。これら柱材40は、主柱および主柱よりも細い間柱を含む。なお、鉄骨造の住宅においては、間柱に相当する柱材40がスタッドと呼ばれる。隣り合う2本の柱材40の間には、横架材41が所々配置されている。鉄骨造の住宅においては、横架材41に相当する要素がランナーと呼ばれる。 A large number of pillar members 40 extending in the vertical direction are arranged on the base 3. These pillar materials 40 include main pillars and studs that are thinner than the main pillars. In addition, in a steel-framed house, the pillar material 40 corresponding to a stud is called a stud. Horizontal members 41 are arranged in places between two adjacent pillar members 40. In a steel-framed house, an element corresponding to the horizontal member 41 is called a runner.

各柱材40の上には、水平方向に延びる梁材5が配置されている。開口部を有さない大部分の外壁10においては、土台3、柱材40、横架材41および梁材5等で囲われた領域に水平補強材60が配置されている。水平補強材60は、例えば木造の住宅に用いられる筋交いや鉄骨造の住宅に用いられるブレースであり、住宅の水平方向への変形を抑制する役割を有している。このような水平補強材60を含む部分は、上述の耐力壁に相当する。 A beam member 5 extending in the horizontal direction is arranged on each pillar member 40. In most of the outer walls 10 that do not have openings, horizontal reinforcing members 60 are arranged in areas surrounded by the foundations 3, pillars 40, horizontal members 41, beams 5, and the like. The horizontal reinforcing member 60 is, for example, a brace used in a wooden house or a brace used in a steel frame house, and has the role of suppressing horizontal deformation of the house. A portion including such horizontal reinforcing material 60 corresponds to the above-mentioned load-bearing wall.

土台3、柱材40、横架材41、梁材5および水平補強材60は、互いに連結されている。例えば、土台3、柱材40、横架材41および梁材5は、戸建て住宅1Aが木造である場合にはいずれも木製であり、戸建て住宅1Aが鉄骨造である場合にはいずれも鉄骨である。 The base 3, the pillar members 40, the horizontal members 41, the beam members 5, and the horizontal reinforcing members 60 are connected to each other. For example, the foundation 3, columns 40, horizontal members 41, and beams 5 are all made of wood if the detached house 1A is made of wood, and if the detached house 1A is made of steel, all of them are made of steel. be.

図10の例において、玄関扉D1は、隣り合う一対の柱材40および横架材41で囲われた領域に配置されている。この領域の内側には開口部補強材RM1が配置され、開口部補強材RM1の内側には下地材BM1が配置され、下地材BM1の内側にはドア枠FM1が配置されている。図10の例においては、玄関扉D1の下方で土台3が部分的に取り除かれている。また、玄関扉D1の外側の下方にポーチP1が配置されている。 In the example of FIG. 10, the entrance door D1 is arranged in an area surrounded by a pair of adjacent pillar members 40 and horizontal members 41. An opening reinforcing material RM1 is arranged inside this region, a base material BM1 is arranged inside the opening reinforcing material RM1, and a door frame FM1 is arranged inside the base material BM1. In the example of FIG. 10, the base 3 is partially removed below the entrance door D1. Further, a pouch P1 is arranged below the outside of the entrance door D1.

扉設置予定部11は、土台3と、一対の柱材40と、これら柱材40を連結する横架材41とで囲われた領域に形成されている。この領域は、石膏ボード、合板または断熱材等で構成された壁材7により塞がれている。扉設置予定部11は、改築時に玄関扉D2を設置可能な幅および高さを有している。一例では、扉設置予定部11の幅は800mm以上であり、扉設置予定部11の高さは2000mm以上である。なお、一般的な玄関扉の幅は800~820mmであり、高さは2000~2400mmである。 The planned door installation portion 11 is formed in an area surrounded by the base 3, a pair of pillars 40, and a horizontal member 41 connecting these pillars 40. This area is closed off by a wall material 7 made of gypsum board, plywood, heat insulating material, or the like. The door installation planned portion 11 has a width and height that allows the entrance door D2 to be installed at the time of renovation. In one example, the width of the planned door installation section 11 is 800 mm or more, and the height of the planned door installation section 11 is 2000 mm or more. Note that the width of a typical entrance door is 800 to 820 mm, and the height is 2000 to 2400 mm.

図10の例において、土台3は、互いに分割された固定部分30(固定土台)および可撤部分31(可撤式土台)を有している。固定部分30は、扉設置予定部11を除く外壁10の下方に位置している。可撤部分31は、扉設置予定部11の下方に位置し、固定部分30に対して着脱自在に連結されている。扉設置予定部11は、外壁10のうち可撤部分31の上方に位置する部分と定義することもできる。 In the example of FIG. 10, the base 3 has a fixed part 30 (fixed base) and a removable part 31 (removable base) that are separated from each other. The fixed portion 30 is located below the outer wall 10 excluding the portion 11 where the door is to be installed. The removable portion 31 is located below the scheduled door installation portion 11 and is detachably connected to the fixed portion 30. The scheduled door installation portion 11 can also be defined as a portion of the outer wall 10 located above the removable portion 31.

固定部分30および可撤部分31は、いずれもアンカーボルトによって基礎1に連結されている。図10においては、可撤部分31を基礎1に連結する2本のアンカーボルト8を例示している。例えば、これらアンカーボルト8の間隔は2m以内であり、隣接する柱材40から約15cmの位置に配置されている。 The fixed part 30 and the removable part 31 are both connected to the foundation 1 by anchor bolts. In FIG. 10, two anchor bolts 8 connecting the removable portion 31 to the foundation 1 are illustrated. For example, the distance between these anchor bolts 8 is within 2 m, and the anchor bolts 8 are arranged at positions approximately 15 cm from adjacent pillars 40.

図10の例においては、互いに交差するとともに扉設置予定部11を横切る2本の可撤式のブレース61が設置されている。これらブレース61の両端部は、金具62によって土台3、柱材40よび横架材41の少なくとも1つに対して着脱自在に連結されている。このようなブレース61を設けることにより、扉設置予定部11の強度を高めることができる。他の例として、扉設置予定部11にブレース61が設けられていなくてもよい。また、ブレース61に代えて木製の筋交いが設けられてもよい。これらブレース61や筋交いは、可撤式の補強材の一例である。 In the example of FIG. 10, two removable braces 61 are installed that intersect with each other and cross the door installation area 11. Both ends of these braces 61 are removably connected to at least one of the base 3, the pillars 40, and the horizontal members 41 by metal fittings 62. By providing such a brace 61, the strength of the planned door installation portion 11 can be increased. As another example, the brace 61 may not be provided in the door installation portion 11. Further, instead of the brace 61, a wooden brace may be provided. These braces 61 and braces are examples of removable reinforcing members.

戸建て住宅1Aが木造の場合、図10(a)に拡大して示すように、土台3の固定部分30の端部に水平方向に突出する凸部30aを設け、可撤部分31の端部に水平方向に突出する凸部31aを設け、これら凸部30a,31aを鉛直方向に重ねてもよい。さらに、固定部分30と可撤部分31を、これらの側面に取り付けられた複数の連結材32によって連結してもよい。このような構造であれば、固定部分30と可撤部分31を強固に連結することができる。 When the detached house 1A is made of wood, as shown in an enlarged view in FIG. A convex portion 31a protruding in the horizontal direction may be provided, and these convex portions 30a, 31a may be stacked vertically. Furthermore, the fixed part 30 and the removable part 31 may be connected by a plurality of connecting members 32 attached to the side surfaces thereof. With such a structure, the fixed portion 30 and the removable portion 31 can be firmly connected.

一方、戸建て住宅1Aが鉄骨造の場合、図10(b)に拡大して示すように、土台3の固定部分30と可撤部分31の連結面を鉛直方向と平行に形成し、これらを当接させてもよい。 On the other hand, if the detached house 1A is a steel frame structure, as shown in an enlarged view in FIG. You can also let them touch each other.

可撤部分31を基礎1に連結するアンカーボルト8は、可撤部分31の上方に突出しないことが好ましい。図10の例においては、可撤部分31の上面に座ぐり部31bが設けられ、この座ぐり部31bにアンカーボルト8の頭部(ボルトの先端やナット等)が収容されている。 It is preferable that the anchor bolt 8 connecting the removable part 31 to the foundation 1 does not protrude above the removable part 31. In the example of FIG. 10, a counterbore 31b is provided on the upper surface of the removable portion 31, and the head of the anchor bolt 8 (bolt tip, nut, etc.) is accommodated in the counterbore 31b.

図11は、戸建て住宅1Aが木造である場合に適用し得る床下の構造の一例を示す概略的な斜視図である。この図の例においては、基礎1で囲われた領域の内側に、複数の床束42が配置され、これら床束42によって大引き33が支持されている。大引き33の端部は、土台3に連結されている。大引き33の上に破線で示した複数の根太34が配置されることもある。 FIG. 11 is a schematic perspective view showing an example of an underfloor structure that can be applied when the detached house 1A is made of wood. In the example shown in this figure, a plurality of floor bundles 42 are arranged inside the area surrounded by the foundation 1, and the large puller 33 is supported by these floor bundles 42. The end of the large drawer 33 is connected to the base 3. A plurality of joists 34 indicated by broken lines may be arranged on the main drawer 33.

例えば根太34が配置されていない場合、24mm程度に厚く形成された屋内の床材が大引き33の上に設置される。一方、根太34が配置されている場合、床材が根太34の上に設置される。 For example, if the joist 34 is not placed, an indoor flooring material having a thickness of about 24 mm is installed on the floor joist 33. On the other hand, when the joists 34 are arranged, the flooring material is installed on the joists 34.

例えば、扉設置予定部11の両側の柱材40に対応する位置にも大引き33が配置されている。これら大引き33は、扉設置予定部11の下方の土台3に対して垂直を成す方向に延びている。なお、図11においてはいくつかの柱材40や玄関E1を省略しており、必ずしも図10に示した構造と対応していない。 For example, the large drawers 33 are also arranged at positions corresponding to the pillars 40 on both sides of the door installation portion 11. These large drawers 33 extend in a direction perpendicular to the base 3 below the door installation portion 11. In addition, in FIG. 11, some pillar members 40 and the entrance E1 are omitted, and the structure does not necessarily correspond to that shown in FIG. 10.

図12は、2世帯完全分離住宅への改築後の戸建て住宅1Aの玄関E1,E2の概略的な正面図である。改築にあたっては、扉設置予定部11(壁材7およびブレース61等)が取り除かれる。さらに、土台3の可撤部分31が固定部分30から取り外され、固定部分30の凸部30aが切除される。また、可撤部分31の下方に位置していた基礎パッキン2も取り除かれ、アンカーボルト8のうち基礎1から突出している部分が切除される。 FIG. 12 is a schematic front view of the entrances E1 and E2 of the detached house 1A after the renovation to a two-family completely separated house. During the renovation, the portion 11 where the door is to be installed (wall material 7, brace 61, etc.) is removed. Further, the removable portion 31 of the base 3 is removed from the fixed portion 30, and the convex portion 30a of the fixed portion 30 is removed. Furthermore, the foundation packing 2 located below the removable portion 31 is also removed, and the portion of the anchor bolt 8 that protrudes from the foundation 1 is cut off.

続いて、図12に示すように、扉設置予定部11を取り除いたことで生じる開口部に開口部補強材RM2が配置され、開口部補強材RM2の内側に下地材BM2が配置され、下地材BM2の内側にドア枠FM2が配置される。さらに、ドア枠FM2に玄関扉D2が設置される。図12の例においては、玄関扉D2の外側の下方にポーチP2が設置されている。 Subsequently, as shown in FIG. 12, the opening reinforcing material RM2 is placed in the opening created by removing the door installation portion 11, the base material BM2 is placed inside the opening reinforcing material RM2, and the base material BM2 is placed inside the opening reinforcing material RM2. A door frame FM2 is arranged inside BM2. Furthermore, an entrance door D2 is installed in the door frame FM2. In the example of FIG. 12, a pouch P2 is installed below the outside of the entrance door D2.

このように、戸建て住宅1Aの新築当初から土台3が可撤部分31を有していれば、土台3の一部を除去して玄関扉D2を設置する場合の作業が極めて容易となるし、1本の連続した土台3の一部を改築時に除去するような場合に比べて耐震性への影響も小さい。また、予め可撤部分31を考慮せずに耐震性の建築基準を満たすよう戸建て住宅1Aを設計しておけば、改築後にも十分な耐震性が確保される。 In this way, if the foundation 3 has the removable portion 31 from the beginning of the new construction of the detached house 1A, it will be extremely easy to remove a part of the foundation 3 and install the entrance door D2, The impact on earthquake resistance is also smaller than in the case where part of one continuous foundation 3 is removed during renovation. Furthermore, if the detached house 1A is designed in advance to meet earthquake-resistant building standards without considering the removable portion 31, sufficient earthquake resistance can be ensured even after renovation.

扉設置予定部11の両側の柱材40に対応する位置には、図11に示した大引き33が配置されている。一例として、これら大引き33が配列されるピッチは900mmであり、それぞれの大引き33の幅は90mmである。この場合、玄関扉D2、開口部補強材RM2、下地材BM2およびドア枠FM2を設置するための扉設置予定部11の幅は、900mm-90mm=810mmとなる。この例に限られず、柱材40や大引き33の位置を調整することにより、扉設置予定部11の幅を増やすことも可能である。 Large drawers 33 shown in FIG. 11 are arranged at positions corresponding to the pillars 40 on both sides of the door installation portion 11. As an example, the pitch at which these large drawers 33 are arranged is 900 mm, and the width of each large drawer 33 is 90 mm. In this case, the width of the door installation portion 11 for installing the entrance door D2, the opening reinforcing material RM2, the base material BM2, and the door frame FM2 is 900 mm - 90 mm = 810 mm. The present invention is not limited to this example, and by adjusting the positions of the pillars 40 and the drawers 33, it is also possible to increase the width of the planned door installation section 11.

大引き33は、戸建て住宅1Aの耐震性に影響し得るものであり、改築時に除去せずにそのまま残すことが好ましい。そうすると、玄関扉D2の内側の玄関フロアF2は、例えば隣り合う2本の大引き33の間に形成される。この場合の玄関フロアF2の幅は、例えば上記810mmであるが、この例に限られない。図11に示した根太34が配置されている場合、玄関フロアF2において根太34を除去してもよい。 The large pull 33 can affect the earthquake resistance of the detached house 1A, and is preferably left as is without being removed during renovation. Then, the entrance floor F2 on the inside of the entrance door D2 is formed, for example, between two adjacent large drawers 33. The width of the entrance floor F2 in this case is, for example, the above-mentioned 810 mm, but is not limited to this example. When the joists 34 shown in FIG. 11 are arranged, the joists 34 may be removed at the entrance floor F2.

図13は、玄関扉D2とその近傍の一例を示す概略的な断面図である。図12の例のように土台3の可撤部分31を取り除いて玄関扉D2を設置する場合、基礎1の上面SF1が玄関フロアF2の床面SF2の基準となる。ホールHL3の廊下部分の床面SF3は、例えば床面SF2よりも10cm乃至15cm程度高い位置に形成されている。なお、仮に図11に示した大引き33が扉設置予定部11の下方の土台3と平行に配置されている場合、大引き33の位置が床面SF2,SF3の境目となり得る。 FIG. 13 is a schematic cross-sectional view showing an example of the entrance door D2 and its vicinity. When installing the entrance door D2 by removing the removable portion 31 of the foundation 3 as in the example of FIG. 12, the upper surface SF1 of the foundation 1 becomes the reference for the floor surface SF2 of the entrance floor F2. The floor surface SF3 of the corridor portion of the hall HL3 is formed, for example, at a position approximately 10 cm to 15 cm higher than the floor surface SF2. In addition, if the large drawer 33 shown in FIG. 11 is arranged parallel to the base 3 below the door installation planned portion 11, the position of the large drawer 33 may be the boundary between the floor surfaces SF2 and SF3.

図14は、玄関扉D2とその近傍の他の例を示す概略的な断面図である。この例においては、床面SF2,SF3の境目にスロープSLが形成されている。これにより、車椅子や手押し車(シルバーカー等)を容易にホールHL3に入れることができる。 FIG. 14 is a schematic cross-sectional view showing another example of the entrance door D2 and its vicinity. In this example, a slope SL is formed at the boundary between floor surfaces SF2 and SF3. Thereby, a wheelchair or a handcart (such as a silver car) can be easily put into the hall HL3.

なお、玄関E1にも図14と同様の構造を適用できる。すなわち、玄関フロアF1の床面とホールHL1の床面の境目にスロープSLを設けてもよい。このスロープSLは、新築当初から設けられてもよいし、改築時に追加されてもよい。 Note that the same structure as in FIG. 14 can be applied to the entrance E1 as well. That is, the slope SL may be provided at the boundary between the floor surface of the entrance floor F1 and the floor surface of the hall HL1. This slope SL may be provided from the beginning of new construction, or may be added at the time of renovation.

[玄関追加の具体例2]
図15は、具体例2に係る改築前の戸建て住宅1Aの玄関E1と扉設置予定部11の概略的な正面図である。この図の例においては、格子状に並ぶ複数の胴縁63および複数の間柱64が扉設置予定部11に設置されている。胴縁63および間柱64は、可撤式の補強材の一例である。
[Specific example 2 of adding an entrance]
FIG. 15 is a schematic front view of the entrance E1 and the planned door installation portion 11 of the detached house 1A before renovation according to the second example. In the example shown in this figure, a plurality of furring edges 63 and a plurality of studs 64 arranged in a grid are installed in the door installation area 11. The furring 63 and the studs 64 are examples of removable reinforcing members.

水平方向と平行に配置された胴縁63は、扉設置予定部11を横切り、左右の柱材40に連結されている。鉛直方向と平行に配置された間柱64は、扉設置予定部11を横切り、土台3の可撤部分31と横架材41に連結されている。 The furring 63 arranged parallel to the horizontal direction crosses the door installation area 11 and is connected to the left and right pillars 40. The studs 64 arranged parallel to the vertical direction cross the planned door installation portion 11 and are connected to the removable portion 31 of the base 3 and the horizontal member 41.

図15において拡大して示すように、柱材40の側面には凹部40aが形成されている。胴縁63の端部は、この凹部40aに挿入されている。間柱64は、適宜の方法により可撤部分31および横架材41に連結されている。 As shown in an enlarged view in FIG. 15, a recess 40a is formed in the side surface of the column 40. The end of the furring 63 is inserted into this recess 40a. The studs 64 are connected to the removable portion 31 and the horizontal member 41 by an appropriate method.

このように、図10に示したブレース61に代えて胴縁63および間柱64を設ける場合でも、扉設置予定部11の強度を高めることができる。なお、仮に胴縁63ではなく柱材40や横架材41を貫通する胴貫を設置する場合には、扉設置予定部11の周囲の柱材40や横架材41の強度が低下し得る。これに対し、胴縁63は柱材40を貫通しないため、胴縁63を設けることによる柱材40の強度への影響は軽微である。 In this way, even when the furring 63 and the studs 64 are provided in place of the brace 61 shown in FIG. 10, the strength of the door installation portion 11 can be increased. In addition, if a trunk pierced through the pillars 40 and horizontal members 41 is installed instead of the trunk rim 63, the strength of the pillars 40 and horizontal members 41 around the planned door installation section 11 may be reduced. . On the other hand, since the furring 63 does not penetrate the column 40, the effect of providing the furring 63 on the strength of the column 40 is slight.

[玄関追加の具体例3]
図16は、具体例3に係る改築前の戸建て住宅1Aの玄関E1と扉設置予定部11の概略的な正面図である。この図の例においては、土台3が可撤部分31を有していない。すなわち、土台3の全体が固定部分30により構成されている。さらに、新築時から扉設置予定部11に開口部補強材RM2が設置されている。この場合、扉設置予定部11は、開口部補強材RM2で囲われた領域と定義することができる。開口部補強材RM2の内側は、壁材7によって塞がれている。なお、図16の例と同様に、上述の図10および図15の例において新築時から開口部補強材RM2が設置されていてもよい。
[Example 3 of adding an entrance]
FIG. 16 is a schematic front view of the entrance E1 and the planned door installation portion 11 of the detached house 1A before renovation according to Specific Example 3. In the example shown in this figure, the base 3 does not have a removable part 31. That is, the entire base 3 is constituted by the fixed portion 30. Furthermore, an opening reinforcing material RM2 has been installed in the door installation area 11 since the time of new construction. In this case, the scheduled door installation portion 11 can be defined as an area surrounded by the opening reinforcing material RM2. The inside of the opening reinforcing material RM2 is closed by the wall material 7. Note that, similarly to the example of FIG. 16, the opening reinforcing material RM2 may be installed from the time of new construction in the examples of FIGS. 10 and 15 described above.

図16の例におけるその他の構成は図10の例と同様である。ただし、ブレース61は設けられていなくてもよい。また、ブレース61に代えて図15の例と同様の胴縁63および間柱64や筋交いが設けられてもよい。 Other configurations in the example of FIG. 16 are similar to those of the example of FIG. 10. However, the brace 61 may not be provided. Furthermore, instead of the brace 61, a torso 63, studs 64, or braces similar to the example of FIG. 15 may be provided.

図17は、2世帯完全分離住宅への改築後の戸建て住宅1Aの玄関E1,E2の概略的な正面図である。この図の例においては、土台3を除去することなく下地材BM2、ドア枠FM2および玄関扉D2が扉設置予定部11であった箇所に設置されている。 FIG. 17 is a schematic front view of the entrances E1 and E2 of the detached house 1A after the renovation into a two-family completely separated house. In the example shown in this figure, the base material BM2, the door frame FM2, and the entrance door D2 are installed in the location where the planned door installation section 11 was, without removing the base 3.

図18は、玄関扉D2とその近傍の一例を示す概略的な断面図である。玄関扉D2の下方に土台3(固定部分30)を残す場合には、玄関フロアF2の床面SF2の基準が基礎1の上面SF1よりも土台3や基礎パッキン2の分だけ上方に位置することとなる。そのため、ポーチP2も玄関扉D2の近傍で大き過ぎる段差が生じないように高く形成することが好ましい。 FIG. 18 is a schematic cross-sectional view showing an example of the entrance door D2 and its vicinity. When leaving the base 3 (fixed part 30) below the entrance door D2, the standard of the floor surface SF2 of the entrance floor F2 must be located above the upper surface SF1 of the foundation 1 by the amount of the base 3 and the base packing 2. becomes. Therefore, it is preferable that the porch P2 is also formed high so that an excessively large step does not occur in the vicinity of the entrance door D2.

また、土台3を残す場合には、玄関フロアF2の床面SF2とホールHL3の床面SF3が同じ高さとなる可能性がある。この場合には、図18に示すように、床面SF2,SF3の境目にスロープ材SLMを設置してもよい。スロープ材SLMは、例えば5cmから10cm程度の高さを有し、床面SF2側と床面SF3側に傾斜面を有している。 Furthermore, if the foundation 3 is left, there is a possibility that the floor surface SF2 of the entrance floor F2 and the floor surface SF3 of the hall HL3 will be at the same height. In this case, as shown in FIG. 18, a slope material SLM may be installed at the boundary between floor surfaces SF2 and SF3. The slope material SLM has a height of, for example, about 5 cm to 10 cm, and has slopes on the floor surface SF2 side and the floor surface SF3 side.

[玄関追加の具体例4]
図1等においては、玄関E2の設置に伴い、その周囲の壁の一部が除去されている。このような場合に、必ずしも当該壁の下端から上端までの全体が除去される必要はなく、その一部が除去されてもよい。
[Example 4 of adding an entrance]
In FIG. 1 and the like, a part of the wall around the entrance E2 has been removed due to the installation of the entrance E2. In such a case, it is not necessarily necessary to remove the entire wall from the lower end to the upper end, and a portion thereof may be removed.

図19は、壁の一部を除去する場合の構造を示す概略的な断面図である。改築前には、撤去予定壁9が扉設置予定部11の近傍に配置されていた。改築前の撤去予定壁9は、斜線を付した第1部分91と、一点鎖線で示す第2部分92とを有している。第2部分92は、土台3の直ぐ上に位置している。第1部分91は、例えば第2部分92の上方に位置するか、あるいは第2部分92の周囲を囲っている。撤去予定壁9の右側の空間は玄関E2の玄関フロアF2が設置される領域であり、左側の空間は1階の部屋や既設の玄関フロアF1である。 FIG. 19 is a schematic cross-sectional view showing the structure when part of the wall is removed. Before the renovation, the wall 9 to be removed was placed near the part 11 to be installed with the door. The wall 9 to be removed before renovation has a first portion 91 shown with diagonal lines and a second portion 92 shown with a dashed line. The second portion 92 is located directly above the base 3. The first portion 91 is located above the second portion 92 or surrounds the second portion 92, for example. The space on the right side of the wall 9 to be removed is an area where the entrance floor F2 of the entrance E2 is installed, and the space on the left side is a room on the first floor and the existing entrance floor F1.

改築時には、第2部分92が除去されるが、第1部分91はそのまま残される。すなわち、第2部分92を除去することにより、撤去予定壁9に穴が形成される。図19の例においては、この穴を利用して下駄箱S2が設置されている。下駄箱S2は、玄関フロアF2に隣接する部屋の床101の上に突出している。なお、撤去予定壁9の穴を活用して配置される要素は、下駄箱S2に限られない。 During renovation, the second portion 92 is removed, but the first portion 91 is left as is. That is, by removing the second portion 92, a hole is formed in the wall 9 scheduled for removal. In the example of FIG. 19, the shoe rack S2 is installed using this hole. The shoe rack S2 protrudes above the floor 101 of the room adjacent to the entrance floor F2. Note that the elements placed by utilizing the holes in the wall 9 scheduled for removal are not limited to the shoe rack S2.

[玄関追加の具体例5]
図20は、具体例5に係る改築前の戸建て住宅1Aの玄関E1と扉設置予定部11の概略的な正面図である。ここでは、戸建て住宅1Aが鉄骨造である場合を想定する。
[Example 5 of adding an entrance]
FIG. 20 is a schematic front view of the entrance E1 and the planned door installation portion 11 of the detached house 1A before renovation according to Example 5. Here, it is assumed that the detached house 1A is a steel frame structure.

図20の例においては、基礎1の上方に土台3が設けられておらず、代わりに金属製のベースプレート200が配置されている。ベースプレート200は、柱材40や梁材5に比べて薄く形成されている。鉄骨の柱材40は、アンカーボルト8によって基礎1に固定されている。 In the example of FIG. 20, the base 3 is not provided above the foundation 1, and a metal base plate 200 is provided instead. The base plate 200 is thinner than the pillars 40 and the beams 5. A steel column 40 is fixed to the foundation 1 with anchor bolts 8.

図20の例においては、改築前の扉設置予定部11に開口部補強材RM2およびブレース61が設置されている。他の例として、扉設置予定部11に開口部補強材RM2やブレース61が設けられていなくてもよい。 In the example of FIG. 20, an opening reinforcing material RM2 and a brace 61 are installed in the door installation planned portion 11 before renovation. As another example, the opening reinforcing material RM2 and the brace 61 may not be provided in the door installation portion 11.

図21は、2世帯完全分離住宅への改築後の戸建て住宅1Aの玄関E1,E2の概略的な正面図である。この図の例においては、壁材7およびブレース61が撤去され、下地材BM2、ドア枠FM2および玄関扉D2が扉設置予定部11に設置されている。 FIG. 21 is a schematic front view of the entrances E1 and E2 of the detached house 1A after it has been remodeled into a two-family completely separated house. In the example shown in this figure, the wall material 7 and the brace 61 have been removed, and the base material BM2, door frame FM2, and entrance door D2 are installed in the door installation planned portion 11.

[まとめ]
以上、図1乃至図21を参照して例示した構成により、木造または鉄骨造の戸建て住宅を2世帯完全分離住宅に改築することができる。いずれの例においても、新たな玄関E2は新築時からの収納空間を利用して設置される。
[summary]
With the configurations illustrated above with reference to FIGS. 1 to 21, a wooden or steel-frame detached house can be renovated into a two-family completely separated house. In either example, the new entrance E2 is installed using the storage space left at the time of new construction.

2世帯完全分離住宅への改築後には、1階または2階の一方にそのまま家主が居住し、他方を賃貸に出してもよい。また、1階および2階の双方を賃貸に出してもよい。1階および2階にそれぞれ親とその子供の家族が居住したり、夫婦が別々に居住したりすることもできる。 After the house is renovated into a completely separated two-family home, the landlord may continue to live on one of the first or second floors and rent out the other. Alternatively, both the first and second floors may be rented out. Parents and their children's families can live on the first and second floors, or married couples can live separately.

このような戸建て住宅の設計時には、改築後の各玄関E1,E2から1階の生活空間および2階の生活空間それぞれへの動線が妨げられないようにシミュレーションし、玄関E1、扉設置予定部11および階段STの上り口等の位置を決定する。なお、図1乃至図9の各例においては階段STの上り口が外壁10に面しているため、動線の確保が容易である。しかしながら、上り口が1階の中央付近に位置する場合でも、玄関E1および扉設置予定部11の位置や間取りの調整により、改築後の各玄関E1,E2から1階の生活空間および2階の生活空間それぞれへの動線が妨げられないように設計することが可能である。 When designing such a detached house, we simulated so that the flow lines from each entrance E1 and E2 after renovation to the living space on the first floor and the living space on the second floor would not be obstructed. 11 and the upper entrance of the stairs ST are determined. In each of the examples shown in FIGS. 1 to 9, the entrance of the stairs ST faces the outer wall 10, so it is easy to ensure a flow line. However, even if the ascending entrance is located near the center of the first floor, depending on the position and floor plan of the entrance E1 and door installation area 11, it is possible to access the living space on the first floor and the second floor from each entrance E1 and E2 after renovation. It is possible to design so that flow lines to each living space are not obstructed.

戸建て住宅の耐震性を評価するにあたっては、扉設置予定部11を含む撤去予定壁の強度を考慮せずに、つまり撤去予定壁がなかったとしても新耐震基準等の建築基準を満たす耐震性が得られるように構造計算を行う。扉設置予定部11に図10に示したブレース61等を設ける場合には耐震性をより高めることができるが、改築時にこのブレース61を撤去しても耐震性が建築基準を満たす。 When evaluating the earthquake resistance of a detached house, we do not take into account the strength of the wall scheduled to be removed, including the part 11 where the door is scheduled to be installed. Perform structural calculations to obtain the result. If the brace 61 shown in FIG. 10 or the like is provided in the door installation area 11, the earthquake resistance can be further improved, but even if this brace 61 is removed at the time of renovation, the earthquake resistance still satisfies the building standards.

また、設計時には、改築後の1階および2階の間取り(例えば1LDKとなる部屋の位置、トイレ、浴室、洗面所、収納)を想定し、動線の妨げとなる位置には非耐力壁等の撤去予定壁を設けておく。改築コストを抑制する観点からは、撤去予定壁が極力少ないことが好ましい。当然ながら、設計は上述の避難通路の確保も念頭に置いて行われる。 In addition, at the time of design, the floor plan of the first and second floors after renovation (for example, the location of the 1LDK room, toilet, bathroom, washroom, storage) should be assumed, and non-load-bearing walls should be placed in positions that would obstruct the line of flow. A wall will be set up that will be removed. From the perspective of reducing renovation costs, it is preferable to minimize the number of walls scheduled for removal. Naturally, the design is done with the above-mentioned evacuation route in mind.

改築前の設計図面と改築後の設計図面は、少なくとも新築時に作成され、建築主に手渡される。戸建て住宅の新築時に住宅ローンが組まれる場合には、改築後の賃貸収入を考慮した住宅ローンの返済プランが作成されてもよい。これにより、資金計画が明らかとなり、建築主は将来の家計を見通して長期の住宅ローンを円滑に返済することができる。 Pre-renovation design drawings and post-renovation design drawings are created at least at the time of new construction and handed over to the building owner. When a mortgage is taken out when a new detached house is constructed, a mortgage repayment plan may be created that takes into account the rental income after the renovation. This makes the financial plan clear and allows the owner of the building to predict future household finances and smoothly repay long-term mortgages.

1A,1B,1C,1D…戸建て住宅、10,20…外壁、11…扉設置予定部、E1,E2…玄関、D1,D2…玄関扉、F1,F2…玄関フロア、ST…階段、JC…押し入れ(収納空間)。 1A, 1B, 1C, 1D... Single-family house, 10, 20... Exterior wall, 11... Door installation area, E1, E2... Entrance, D1, D2... Entrance door, F1, F2... Entrance floor, ST... Stairs, JC... Closet (storage space).

Claims (7)

1階と2階を有し、前記1階と前記2階を繋ぐ階段が屋内に配置された戸建て住宅であって、
前記1階に配置された玄関扉を有する玄関と、
前記1階に配置され、前記1階の外壁に面する収納空間と、
前記外壁の下方に配置された基礎と、
前記基礎の上に配置された土台と、
を備え、
前記玄関および前記収納空間の一方と前記階段の上り口を繋ぐ第1動線が前記1階の生活空間を分断せず、かつ他方と前記1階の生活空間を繋ぐ第2動線が前記第1動線と交差しないように構成され、
前記収納空間が前記玄関に隣接する部屋または前記階段の下に設けられるか、あるいは前記収納空間の出入口が前記玄関の内側の玄関フロアに隣接するホールに設けられ、
前記外壁は、前記収納空間に面するとともに玄関扉を設置可能な大きさを有する扉設置予定部を有し、
前記扉設置予定部は、前記土台の上方で壁材によって塞がれた領域を含み、
前記土台は、
前記扉設置予定部を除く前記外壁の下方に位置する固定部分と、
前記扉設置予定部の下方に位置し、前記固定部分に対して着脱自在に連結された可撤部分と、
を含む、
戸建て住宅。
A detached house having a first floor and a second floor, and a staircase connecting the first floor and the second floor located indoors,
an entrance having an entrance door located on the first floor;
a storage space arranged on the first floor and facing an outer wall of the first floor;
a foundation placed below the outer wall;
a foundation placed on the foundation;
Equipped with
A first flow line connecting one of the entrance and the storage space to the top of the stairs does not divide the living space on the first floor, and a second flow line connecting the other and the living space on the first floor is the first flow line. It is configured so that it does not intersect with the 1 flow line,
The storage space is provided in a room adjacent to the entrance or under the stairs, or the entrance to the storage space is provided in a hall adjacent to the entrance floor inside the entrance,
The outer wall has a door installation portion facing the storage space and having a size that allows installation of an entrance door,
The planned door installation area includes an area above the base that is blocked by a wall material,
The base is
a fixed part located below the outer wall excluding the part where the door is planned to be installed;
a removable part located below the scheduled door installation part and detachably connected to the fixed part;
including,
Detached house.
前記固定部分および前記可撤部分の端部にそれぞれ凸部が設けられ、これら凸部が鉛直方向に重ねられるとともに、前記固定部分と前記可撤部分が連結材によって連結されている、
請求項1に記載の戸建て住宅。
A convex portion is provided at each end of the fixed portion and the removable portion, and these convex portions are stacked vertically, and the fixed portion and the removable portion are connected by a connecting member.
The detached house according to claim 1.
前記扉設置予定部は、前記土台に連結された一対の柱材と、前記一対の柱材に連結された横架材と、前記可撤部分とで囲われた領域を含む、
請求項1に記載の戸建て住宅。
The door installation planned portion includes an area surrounded by a pair of pillars connected to the base, a horizontal member connected to the pair of pillars, and the removable part.
The detached house according to claim 1.
前記扉設置予定部は、開口部補強材によって囲われている、
請求項1に記載の戸建て住宅。
The planned door installation portion is surrounded by an opening reinforcing material.
The detached house according to claim 1.
請求項1乃至のうちいずれか1項に記載の戸建て住宅の改築方法であって、
前記外壁のうち前記扉設置予定部を取り除き、
前記土台のうち前記可撤部分を取り除き、
前記扉設置予定部および前記可撤部分を取り除いたことで生じる開口部に新たな玄関扉を設置し、
前記収納空間を新たな玄関フロアに改築する、
ことを含む改築方法。
A method for renovating a detached house according to any one of claims 1 to 4 ,
removing the portion of the outer wall where the door is planned to be installed;
removing the removable portion of the base;
Installing a new entrance door in the opening created by removing the planned door installation part and the removable part,
Renovating the storage space into a new entrance floor,
Renovation methods including.
改築前の前記戸建て住宅は、前記ホールと前記収納空間とを仕切る非耐力壁を備え、
前記非耐力壁を撤去し、
前記収納空間の入口であった箇所に追加壁を設置する、
ことをさらに含む、請求項に記載の改築方法
The detached house before renovation includes a non-load-bearing wall that partitions the hall and the storage space,
removing the non-load-bearing wall;
Installing an additional wall at the location that was the entrance to the storage space;
The renovation method according to claim 5 , further comprising :.
記第1動線および前記第2動線が空間的に分離されるように、前記1階の内部に追加壁を設置することをさらに含む、請求項に記載の改築方法。 The renovation method according to claim 5 , further comprising installing an additional wall inside the first floor so that the first flow line and the second flow line are spatially separated.
JP2023106687A 2022-11-11 2023-06-29 Detached houses and their renovation methods Active JP7371296B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2023106687A JP7371296B1 (en) 2022-11-11 2023-06-29 Detached houses and their renovation methods

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2022181016A JP7309994B1 (en) 2022-11-11 2022-11-11 Detached house and its renovation method
JP2023106687A JP7371296B1 (en) 2022-11-11 2023-06-29 Detached houses and their renovation methods

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2022181016A Division JP7309994B1 (en) 2022-11-11 2022-11-11 Detached house and its renovation method

Publications (2)

Publication Number Publication Date
JP7371296B1 true JP7371296B1 (en) 2023-10-30
JP2024070792A JP2024070792A (en) 2024-05-23

Family

ID=87201161

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2022181016A Active JP7309994B1 (en) 2022-11-11 2022-11-11 Detached house and its renovation method
JP2023106687A Active JP7371296B1 (en) 2022-11-11 2023-06-29 Detached houses and their renovation methods

Family Applications Before (1)

Application Number Title Priority Date Filing Date
JP2022181016A Active JP7309994B1 (en) 2022-11-11 2022-11-11 Detached house and its renovation method

Country Status (1)

Country Link
JP (2) JP7309994B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299616A (en) 2005-04-19 2006-11-02 Asahi Kasei Homes Kk Two-family house
JP2008308931A (en) 2007-06-15 2008-12-25 Sumitomo Forestry Co Ltd Reformed skip floor structure
JP2010077776A (en) 2008-09-29 2010-04-08 Sekisui Chem Co Ltd Building unit with temporary reinforcing member, unit building, and method for constructing the unit building
JP2014084585A (en) 2012-10-19 2014-05-12 Sekisui House Ltd Dwelling house

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299616A (en) 2005-04-19 2006-11-02 Asahi Kasei Homes Kk Two-family house
JP2008308931A (en) 2007-06-15 2008-12-25 Sumitomo Forestry Co Ltd Reformed skip floor structure
JP2010077776A (en) 2008-09-29 2010-04-08 Sekisui Chem Co Ltd Building unit with temporary reinforcing member, unit building, and method for constructing the unit building
JP2014084585A (en) 2012-10-19 2014-05-12 Sekisui House Ltd Dwelling house

Also Published As

Publication number Publication date
JP2024070792A (en) 2024-05-23
JP2024070490A (en) 2024-05-23
JP7309994B1 (en) 2023-07-18

Similar Documents

Publication Publication Date Title
US11186983B2 (en) Prefabricated building module
Douglas Building adaptation
Lawson et al. ‘Hybrid’light steel panel and modular systems
Kumar et al. Analysis of residential building with STAAD. Pro & ETABS
JP7371296B1 (en) Detached houses and their renovation methods
WO2009132387A1 (en) Fire rated, multi-storey, multi-dwelling structure and method to construct same
JP5637357B2 (en) Seismic reinforcement structure of existing reinforced concrete apartment houses
Look The seismic retrofit of historic buildings: keeping preservation in the forefront
JP6303085B2 (en) Multifunctional structure and seismic structure of building using it
JP6538551B2 (en) Disaster prevention shelter and construction method of the disaster prevention shelter
JP3261404B2 (en) Skeleton structure of standardized apartment house
JP2843901B2 (en) Remodeling method of RC apartment house
Hidayati et al. Interior Modification of Residential Housing in Flood Prone Areas
JP7051670B2 (en) building
JP7319216B2 (en) unit building
JP3090050U (en) Apartment house
JP2500827B2 (en) housing complex
Marriage Core: planning
JP2006037714A (en) Building
Collins et al. Proposed Design for the WPI Foisie Innovation Studio
Terrio et al. Upperclassmen Dormitory Design
JP2002106184A (en) Building with storage
Huang et al. McLaughlin-Walsh Residence Hall Expansion
JP4016759B2 (en) High-rise building
JP2006183347A (en) Living room structure of maisonette type house

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230629

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20230629

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230808

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230921

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231003

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231018

R150 Certificate of patent or registration of utility model

Ref document number: 7371296

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150