JP7333708B2 - Foundation structure and its construction method - Google Patents

Foundation structure and its construction method Download PDF

Info

Publication number
JP7333708B2
JP7333708B2 JP2019085536A JP2019085536A JP7333708B2 JP 7333708 B2 JP7333708 B2 JP 7333708B2 JP 2019085536 A JP2019085536 A JP 2019085536A JP 2019085536 A JP2019085536 A JP 2019085536A JP 7333708 B2 JP7333708 B2 JP 7333708B2
Authority
JP
Japan
Prior art keywords
beams
cast
hole
foundation
place
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019085536A
Other languages
Japanese (ja)
Other versions
JP2020180516A (en
Inventor
裕一 平田
健治 田野
覚 貫洞
秀和 平野
俊彦 西尾
輝久 甲田
徹 横山
由 西成田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2019085536A priority Critical patent/JP7333708B2/en
Publication of JP2020180516A publication Critical patent/JP2020180516A/en
Application granted granted Critical
Publication of JP7333708B2 publication Critical patent/JP7333708B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は基礎構造とその施工方法に関し、特に基礎梁の構造に関する。 BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation structure and its construction method, and more particularly to the structure of foundation beams.

建物の基礎杭と上部構造との間に基礎梁が設けられることがある。基礎梁は上部構造の自重や地震荷重を複数の基礎杭に伝達するために設けられている。近年、工期短縮や品質向上のため、プレキャスト化された基礎梁(以下、PCa基礎梁という)が用いられることがある(特許文献1,2)。 Foundation beams are sometimes provided between the foundation piles of the building and the superstructure. Foundation beams are provided to transmit the weight of the superstructure and seismic loads to multiple foundation piles. In recent years, precast foundation beams (hereinafter referred to as PCa foundation beams) are sometimes used to shorten the construction period and improve quality (Patent Documents 1 and 2).

特開2017-125322号公報JP 2017-125322 A 特開2018-21445号公報JP 2018-21445 A

上部構造で発生する排水を下水道などに排出するため、建物の内部には排水配管が設置される。排水配管は上部構造から建物の地下空間まで延びて、建物の外部に埋設された下水管に接続される。このため、排水配管が基礎梁を貫通することがある。通常、排水配管の引き回しルートは好ましい下り勾配が確保されるように計画され、基礎梁の貫通孔の位置は引き回しルートによって決定される。一方、PCa基礎梁は工場製作されるため、据付工事の数ヶ月前には、貫通孔の位置まで含めて設計が完了している必要がある。しかし、建物の設備計画は着工の直前まで確定しないことがあり、また基礎梁は着工後早期に施工されることから、貫通孔の位置がPCa基礎梁の設計時に確定しない可能性がある。このような工程上のミスマッチを避けるため、従来、基礎梁は現場施工されてきた。すなわち、基礎梁配筋、貫通孔のスリーブ設定及びコンクリート打設は現場で行われている。この方法によれば、基礎梁の貫通孔の位置やサイズを現場で調整できるため、工程上のミスマッチが生じる可能性は低い。しかしながら、この結果、上部構造では一般的に行われるプレキャスト構造を基礎梁に採用することが困難な場合が生じている。 Drainage pipes are installed inside the building in order to discharge the wastewater generated in the upper structure to the sewage system. Drainage piping extends from the superstructure to the underground space of the building and is connected to a sewage pipe buried outside the building. For this reason, drainage pipes sometimes penetrate foundation beams. Normally, the drainage pipe routing route is planned so as to ensure a favorable downward slope, and the position of the through-hole in the foundation beam is determined by the routing route. On the other hand, since PCa foundation beams are manufactured in a factory, it is necessary to complete the design, including the positions of through holes, several months before the installation work. However, the facility plan of the building may not be finalized until just before the start of construction, and since the foundation beams will be constructed early after the construction starts, there is a possibility that the positions of the through-holes will not be finalized at the time of designing the PCa foundation beams. To avoid such process mismatches, foundation beams have traditionally been constructed on site. That is, foundation beam reinforcement arrangement, through-hole sleeve setting, and concrete placement are performed on site. According to this method, the position and size of the through-holes in the foundation beams can be adjusted on site, so there is a low possibility of mismatches occurring in the process. As a result, however, there are cases where it is difficult to adopt precast structures, which are commonly used in superstructures, for foundation beams.

本発明は、工程上のミスマッチが生じる可能性を低減することが可能なプレキャスト造の基礎構造を提供することを目的とする。 SUMMARY OF THE INVENTION It is an object of the present invention to provide a precast basic structure capable of reducing the possibility of occurrence of process mismatch.

本発明の板状集合住宅の基礎構造は、建物の外周部に沿って配置された複数の外周梁と、複数の外周梁の内側に設けられた複数の内部梁と、を有している。外周部は一方の長辺と他方の長辺と一対の短辺とからなる。複数の内部梁の各々は、内部梁の長さ方向に、一方の長辺に隣接するプレキャスト部と、中央のプレキャスト部と、他方の長辺に隣接する現場打設部とに3分割されている。排水配管が貫通する少なくとも一つの第1の貫通孔現場打設部だけに設けられ、人通口が中央のプレキャスト部だけに設けられている。 The basic structure of the flat collective housing of the present invention has a plurality of outer beams arranged along the outer periphery of the building and a plurality of inner beams provided inside the plurality of outer beams. The outer peripheral portion consists of one long side, the other long side, and a pair of short sides. Each of the plurality of inner beams is divided in the length direction of the inner beam into three parts, a precast part adjacent to one long side , a central precast part, and a cast-in-place part adjacent to the other long side. there is At least one first through- hole through which a drain pipe passes is provided only in the cast-in-place section , and a feed-through is provided only in the central precast section .

本発明によれば、排水配管が貫通する第1の貫通孔は現場打設部だけに設けられるため、工程上のミスマッチが生じる可能性を低減することができる。 According to the present invention, the first through-hole through which the drainage pipe passes is provided only in the cast-in-place portion, so that the possibility of occurrence of mismatch in the process can be reduced.

本発明が適用される板状集合住宅の正面図である。BRIEF DESCRIPTION OF THE DRAWINGS It is a front view of the plate-shaped housing complex to which this invention is applied. 図1のA-A線からみた基礎梁の平面図である。FIG. 2 is a plan view of the foundation beam viewed from line AA in FIG. 1; 基礎構造の斜視図である。1 is a perspective view of a foundation structure; FIG. 図3に示す基礎構造の分解斜視図である。FIG. 4 is an exploded perspective view of the foundation structure shown in FIG. 3; 図2のB-B線に沿った断面図である。FIG. 3 is a cross-sectional view taken along line BB of FIG. 2; 図2のC-C線に沿った断面図である。3 is a cross-sectional view taken along line CC of FIG. 2; FIG. 外周梁とフーチングの上面図を示す図2のD部拡大図である。3 is an enlarged view of part D in FIG. 2 showing a top view of the outer peripheral beam and the footing; FIG. 図2のE-E線からみた内部梁の側面図である。3 is a side view of the internal beam as seen from line EE of FIG. 2; FIG. 従来技術における工程ミスマッチを説明する概念図である。It is a conceptual diagram explaining the process mismatch in a prior art. 本発明の他の実施形態を示す図5と同様の図である。FIG. 6 is a view similar to FIG. 5 showing another embodiment of the invention;

図面を参照して本発明の実施形態について説明する。本発明は基礎梁を有するあらゆる建物に適用できるが、ここでは板状集合住宅を例に説明する。以下の説明及び図面においてX方向は板状集合住宅の桁行方向、Y方向は板状集合住宅の梁間方向、Z方向は鉛直方向ないし上下方向を示し、X方向、Y方向、Z方向は互いに直交している。図1は板状集合住宅1の正面図を示している。基礎杭3が地盤27に設置され、基礎梁4が基礎杭3の杭頭3Aに設置され、建物の上部構造5が基礎梁4に支持されている。基礎杭3と基礎梁4を合わせて基礎構造2という。図2は図1のA-A線からみた基礎梁4の平面図を、図3は基礎構造2の斜視図を、図4は基礎構造2の分解斜視図を、図5は図2のB-B線に沿った断面図を、図6は図2のC-C線に沿った断面図を、図7は、外周梁6とフーチング9の上面図(図2のD部拡大図)を示している。なお、図2においてハッチングをした部位は、現場打設梁6Bまたは現場打設部7Bを示す。 An embodiment of the present invention will be described with reference to the drawings. Although the present invention can be applied to any building having foundation beams, a plate-like housing complex will be described here as an example. In the following description and drawings, the X direction is the girder direction of the plate-like apartment building, the Y direction is the direction between the beams of the plate-like apartment building, the Z direction is the vertical direction or the vertical direction, and the X, Y, and Z directions are orthogonal to each other. are doing. FIG. 1 shows a front view of a flat collective housing 1 . A foundation pile 3 is installed on the ground 27 , a foundation beam 4 is installed on the pile head 3A of the foundation pile 3 , and the superstructure 5 of the building is supported by the foundation beam 4 . The foundation piles 3 and the foundation beams 4 are collectively referred to as a foundation structure 2 . 2 is a plan view of the foundation beam 4 viewed from line AA in FIG. 1, FIG. 3 is a perspective view of the foundation structure 2, FIG. 4 is an exploded perspective view of the foundation structure 2, and FIG. Fig. 6 is a cross-sectional view along the line -B, Fig. 6 is a cross-sectional view along the CC line in Fig. 2, and Fig. 7 is a top view of the outer peripheral beam 6 and the footing 9 (enlarged view of part D in Fig. 2). showing. In addition, the hatched portion in FIG. 2 indicates the cast-in-place beam 6B or the cast-in-place portion 7B.

板状集合住宅1は桁行方向Xに複数スパンが、梁間方向Yに1スパンが設けられた板状の建物である。基礎梁4は建物の外周部に沿って配置された複数の外周梁6と、外周梁6の内側に設けられた少なくとも一つの内部梁7と、を有している。外周梁6と内部梁7は1階の床スラブ24とともに地下空間8を形成し、地下空間8は内部梁7によって複数の区画8Aに分割されている。 The plate-like collective housing 1 is a plate-like building having a plurality of spans in the girder direction X and one span in the beam-to-beam direction Y. As shown in FIG. The foundation beams 4 have a plurality of outer beams 6 arranged along the outer periphery of the building and at least one inner beam 7 provided inside the outer peripheral beams 6 . The outer beams 6 and the inner beams 7 form an underground space 8 together with the floor slab 24 of the ground floor, and the underground space 8 is divided by the inner beams 7 into a plurality of compartments 8A.

外周梁6は基本的にプレキャスト化されているが、後述するように、少なくとも一つの外周梁6、本実施形態では一つの外周梁6だけが現場打設梁6Bとされ、残りはプレキャスト化されている。桁行方向Xの外周梁6はスパン毎に区分されたプレキャスト梁(PCa梁)6Aであり、梁間方向Yの外周梁6は3つのPCa部6Cに等分割されている。梁間方向Yの外周梁6は構造的には一つの梁であり、PCa部6C同士はモルタルで接合される。 The outer peripheral beam 6 is basically precast, but as will be described later, at least one outer peripheral beam 6, in this embodiment only one outer peripheral beam 6, is a cast-in-place beam 6B, and the rest are precast. ing. The outer peripheral beam 6 in the girder direction X is a precast beam (PCa beam) 6A divided by span, and the outer peripheral beam 6 in the inter-beam direction Y is equally divided into three PCa portions 6C. The outer peripheral beams 6 in the beam-to-beam direction Y are structurally one beam, and the PCa portions 6C are joined with mortar.

内部梁7はスパン毎に設けられ、Y方向に互いに対向する外周梁6同士を接続している。各内部梁7は3つの部分、すなわち2つのプレキャスト部(PCa部)7Aと1つの現場打設部7Bに等分割されている。内部梁7は構造的には一つの梁であり、PCa部7A同士はモルタルで接合される。PCa部7Aと現場打設部7Bは現場打設のコンクリートで接合される。本実施形態では内部梁7のY方向端部に現場打設部7Bが設けられているが、内部梁7のY方向中央部に現場打設部7Bを設けてもよい。現場打設部7Bは内部梁7のどこかに設けられていればよく、そのY方向位置やY方向長さは限定されない。梁間方向Yの外周梁6及び内部梁7の分割数は3つに限定されず、2つまたは4つ以上でもよい。PCa梁6A,PCa部6C,7Aは揚重機で据え付けられることから、分割数は揚重機の性能を考慮して決定するのが好ましい。なお、PCa部7Aの範囲をできるだけ確保するため、現場打設部7BのY方向長さは内部梁7のY方向長さの概ね1/3以下とすることが好ましい。 The internal beams 7 are provided for each span and connect the peripheral beams 6 facing each other in the Y direction. Each internal beam 7 is equally divided into three parts: two precast parts (PCa parts) 7A and one cast-in-place part 7B. The internal beam 7 is structurally one beam, and the PCa portions 7A are joined together by mortar. The PCa portion 7A and the cast-in-place portion 7B are joined with cast-in-place concrete. In this embodiment, the cast-in-place part 7B is provided at the end of the internal beam 7 in the Y direction, but the cast-in-place part 7B may be provided at the central part of the internal beam 7 in the Y direction. The on-site placement portion 7B may be provided anywhere on the internal beam 7, and its Y-direction position and Y-direction length are not limited. The number of divisions of the outer beams 6 and the internal beams 7 in the inter-beam direction Y is not limited to three, and may be two or four or more. Since the PCa beam 6A and the PCa portions 6C and 7A are installed by a lifting machine, it is preferable to determine the number of divisions in consideration of the performance of the lifting machine. In order to secure the range of the PCa portion 7A as much as possible, it is preferable that the length of the cast-in-place portion 7B in the Y direction is approximately 1/3 or less of the length of the internal beam 7 in the Y direction.

外周梁6と内部梁7の交差部にはフーチング9が設けられている。フーチング9は概ね直方体の鉄筋コンクリート構造物であり、現場で施工される。フーチング9は建物の外壁側で上部がカットされた形状となっている。フーチング9の下には基礎杭3が、フーチング9の上には柱10が設けられている。基礎杭3は鋼管杭であり、杭頭3Aには複数の杭頭補強筋11が設けられている。杭頭補強筋11は基礎杭3の杭頭3A近傍の側面に溶接などによって周方向に設けられ、鉛直方向Z上方に延びている。基礎杭3の杭頭3Aと杭頭補強筋11はフーチング9で覆われている。基礎構造2の施工性を考慮し、外周梁6と内部梁7の下端レベルは一致している。フーチング9の下端は外周梁6と内部梁7の下端より下方にある。すなわち、施工時には地盤27はフーチング9の範囲だけが周囲より深く掘削される。 A footing 9 is provided at the intersection of the outer beam 6 and the internal beam 7 . The footing 9 is a roughly rectangular parallelepiped reinforced concrete structure that is constructed on site. The footing 9 has a shape in which the upper part is cut on the outer wall side of the building. A foundation pile 3 is provided under the footing 9, and a column 10 is provided above the footing 9. - 特許庁The foundation pile 3 is a steel pipe pile, and the pile head 3A is provided with a plurality of pile head reinforcing bars 11 . The pile head reinforcement 11 is provided in the circumferential direction by welding or the like on the side surface of the foundation pile 3 near the pile head 3A, and extends upward in the vertical direction Z. As shown in FIG. The pile head 3A of the foundation pile 3 and the pile head reinforcement 11 are covered with a footing 9. Considering the workability of the foundation structure 2, the lower end levels of the outer peripheral beam 6 and the inner beam 7 are the same. The lower end of footing 9 is below the lower ends of outer beam 6 and inner beam 7 . That is, during construction, the ground 27 is excavated deeper than the surroundings only in the range of the footing 9 .

外周梁6はその下部に幅方向(Y方向)両側に張り出した張出部12を有している。フーチング9は杭頭補強筋11、外周梁6の鉄筋14、内部梁7の鉄筋15などが集中するため、鉄筋の納まりが困難となる場合がある。特にX方向及びY方向に設けられる鉄筋14,15と円周上に設けられる杭頭補強筋11は干渉が生じやすい。図4~7に示すように、外周梁6の下端筋14Aの少なくとも一部、本実施形態ではY方向両側の下端筋14Aは張出部12に設けられ、張出部12に設けられた下端筋14Aは杭頭補強筋11の幅方向(Y方向)外側を通っている。このため、鉄筋の配置スペースに余裕が生じ、鉄筋の納まりが改善される。 The outer peripheral beam 6 has projecting portions 12 projecting on both sides in the width direction (Y direction) at its lower portion. Since the pile head reinforcing bars 11, the reinforcing bars 14 of the outer beam 6, the reinforcing bars 15 of the inner beams 7, and the like concentrate on the footing 9, it may be difficult to fit the reinforcing bars. In particular, the reinforcing bars 14 and 15 provided in the X and Y directions and the pile head reinforcing bar 11 provided on the circumference are likely to interfere with each other. As shown in FIGS. 4 to 7, at least part of the bottom reinforcements 14A of the outer beam 6, in this embodiment, the bottom reinforcements 14A on both sides in the Y direction are provided on the protruding portion 12, and the lower ends provided on the protruding portion 12 The reinforcement 14A passes through the outside of the pile head reinforcement 11 in the width direction (Y direction). As a result, a space for arranging the reinforcing bars is increased, and the fitting of the reinforcing bars is improved.

図8は図2のE-E線からみた内部梁7の側面図である。内部梁7には様々な貫通孔が設けられている。貫通孔は円形であるが、矩形その他の形状であってもよい。現場打設部7Bには排水配管23が貫通する4つの第1の貫通孔16が設けられている(図2には1本の排水配管23を例として示している)。このうち3つの第1の貫通孔16は浴室、トイレ、キッチン、洗面所などで発生する排水を排出する排水配管が貫通するためのものである。排水配管23は、通常は板状集合住宅1の外部の地下に埋設された公共下水管に接続される。このため、各住戸で発生した排水は集合住宅内で1本または数本の排水配管23に集約され、外周梁6と内部梁7とで仕切られる地下空間8まで引き回され、地下空間8から外周梁6を通って板状集合住宅1の外部に排出される。もう一つの第1の貫通孔16は雨水などを排水する排水配管(以下、上述の排水配管と区別するためドレン配管という)が貫通するためのものである。本実施形態では、ドレン配管も他の排水配管と同様に公共下水管に接続される。現場打設部7Bにはさらに通気口17と連通管18が設けられている。通気口17は、地下空間8に立ち入る人の安全確保のため、内部梁7で区画された地下空間8の各区画8Aを空気が連通可能となるように設けられている。連通管18は、地下空間8の一区画8Aで溢水が発生したときに水を分散させるために、内部梁7の底部に設けられている。中央のPCa部7Aには人が各区画8Aを移動できるようにするための人通口19と、給水配管、ガス配管の共通貫通孔20とが設けられている。端部のPCa部7Aには通気口17と、連通管18と、強電系ケーブルの貫通孔21と、弱電系ケーブルの貫通孔22とが設けられている。 FIG. 8 is a side view of the inner beam 7 seen from line EE in FIG. Various through holes are provided in the internal beam 7 . Although the through holes are circular, they may be rectangular or other shapes. Four first through holes 16 through which drain pipes 23 pass are provided in the field placing portion 7B (one drain pipe 23 is shown as an example in FIG. 2). Three of the first through holes 16 are for the passage of drainage pipes for discharging waste water generated in bathrooms, toilets, kitchens, washrooms, and the like. The drain pipe 23 is normally connected to a public sewage pipe that is buried underground outside the plate-like housing complex 1 . For this reason, the wastewater generated in each dwelling unit is concentrated in one or several drainage pipes 23 in the housing complex, and is routed to the underground space 8 partitioned by the outer beam 6 and the internal beam 7, and is routed from the underground space 8 to the underground space 8. It is discharged to the outside of the flat collective housing 1 through the outer peripheral beams 6 . Another first through-hole 16 is for passing a drainage pipe for draining rainwater (hereinafter referred to as a drain pipe to distinguish it from the above-described drain pipe). In this embodiment, the drain line is also connected to the public sewer like other drain lines. A ventilation port 17 and a communication pipe 18 are further provided in the field placing portion 7B. The vents 17 are provided so as to allow air to communicate with each section 8A of the underground space 8 partitioned by the internal beams 7 in order to ensure the safety of people who enter the underground space 8 . A communication pipe 18 is provided at the bottom of the internal beam 7 to disperse water when a flood occurs in one section 8A of the underground space 8. As shown in FIG. The central PCa portion 7A is provided with a passage port 19 for allowing a person to move between the compartments 8A, and a common through hole 20 for water supply pipes and gas pipes. The PCa portion 7A at the end is provided with a vent 17, a communicating pipe 18, a through hole 21 for a strong electric system cable, and a through hole 22 for a weak electric system cable.

排水配管23はフロア間を貫通する部位では概ね鉛直方向に延びており、フロア内では排水が重力で流れるように、所定の下り勾配が付けられている。下り勾配は汚物等が水に同伴して流れやすくするように、例えば1/100~3/100程度の比較的緩い勾配に設定される。地下空間8においても、排水配管23の引き回しルートはこの下り勾配を目安に計画される。しかし、内部梁7を全てPCa化すると工程上のミスマッチが生じる可能性がある。図9は、内部梁7を全てPCa化したときの、集合住宅の主な設計工程と工事工程を示している。設計が開始されると、まず各住戸の大まかな間取りなどが決定され、次に構造設計や設備計画が行われる。排水配管23のルートは設備計画で決定されるが、そのためにはトイレやキッチンなどの配置が決定している必要がある。従って、排水配管23のルートは設備計画の後半から終盤にならないと確定しないことがある。一方、工事については設計が終了し、建築確認などの手続が終わり次第着工可能となる。着工後は基礎杭3がまず施工され、続いて基礎梁4が施工される。PCa基礎梁は、据付のタイミングにあわせて予め設計及び製作が行われる。PCa基礎梁の設計では貫通孔計画、すなわち貫通孔の設置位置、形状及び大きさに関する情報が必要となる。しかし、PCa基礎梁の設計は着工よりかなり早いタイミングで行われるため、その時点で貫通孔計画が確定していない可能性がある。すなわち、工程上のミスマッチが生じる可能性がある。ミスマッチが生じると、PCa基礎梁の施工が遅れるなど工期に重大な影響が生じる可能性がある。これを避けるためには、予め決定された貫通孔の位置に合わせて排水配管23の引き回しを計画する必要がある。しかし、上述のように排水配管23は下り勾配に関して厳しい制約があるため、合理的な引き回しルートが実現できないなど、設備計画に大きな影響が生じる可能性がある。以上の問題はPCa基礎梁に特有のものであり、現場打設の基礎梁では貫通孔計画は施工時までに確定していればいいため、このような問題は基本的に起こらない。 The drainage pipe 23 extends in a substantially vertical direction at a portion penetrating between the floors, and has a predetermined downward slope so that the drainage flows within the floor by gravity. The descending slope is set to a relatively gentle slope of, for example, about 1/100 to 3/100 so that dirt and the like can easily flow along with the water. In the underground space 8 as well, the routing route of the drainage pipe 23 is planned with this downslope as a guideline. However, if all the internal beams 7 are made of PCa, there is a possibility that a process mismatch will occur. FIG. 9 shows the main design process and construction process of collective housing when all the internal beams 7 are made of PCa. When the design starts, first the rough layout of each dwelling unit is decided, and then the structural design and equipment planning are carried out. The route of the drain pipe 23 is determined by the facility plan, but for that purpose, the layout of the toilet, kitchen, etc. must be determined. Therefore, the route of the drainage pipe 23 may not be determined until the latter half or the final stage of the facility planning. On the other hand, construction can be started as soon as the design is completed and procedures such as building confirmation are completed. After the start of construction, the foundation piles 3 are constructed first, and then the foundation beams 4 are constructed. PCa foundation beams are designed and manufactured in advance according to the timing of installation. The design of PCa foundation beams requires through-hole planning, ie information about the location, shape and size of the through-holes. However, since the design of the PCa foundation beams is carried out considerably earlier than the start of construction, there is a possibility that the plans for the through holes have not been finalized at that time. That is, there is a possibility that a mismatch in the process will occur. If a mismatch occurs, there is a possibility that the construction schedule will be seriously affected, such as delays in the construction of PCa foundation beams. In order to avoid this, it is necessary to plan the routing of the drainage pipe 23 in accordance with the predetermined position of the through hole. However, as described above, the drainage pipe 23 is severely restricted in terms of downward slope, which may have a significant impact on the facility planning, such as the impossibility of realizing a rational routing route. The above problems are peculiar to PCa foundation beams, and such problems basically do not occur in field-cast foundation beams, as long as the through-hole plan is fixed by the time of construction.

本実施形態では、少なくとも排水配管23が貫通する第1の貫通孔16は現場打設部7Bだけに設けられている。上述のように、現場打設部7Bでは貫通孔計画が早期に確定している必要がないため、工程上のミスマッチが生じにくい。一方、排水配管23以外の配管、ケーブル等が貫通する貫通孔は引き回しの自由度が高いため、事前に貫通孔の位置が決定していても引き回し上の大きな制約は生じない。例えば、水道水や消化水などの給水配管は通常加圧されているため、勾配に関して大きな制約はなく、下り勾配と上り勾配が混在していても大きな問題とはならない。ケーブルは勾配に関する制約がないため、引き回しルートへの影響はほとんどない。さらに、配管やケーブルが貫通しない貫通孔(通気口17、連通管18、人通口19)に関してはこのような問題はそもそも生じない。 In this embodiment, at least the first through hole 16 through which the drainage pipe 23 passes is provided only in the field placing portion 7B. As described above, the on-site casting section 7B does not need to determine the plan for the through holes at an early stage, so mismatches in the process are less likely to occur. On the other hand, since the through-holes through which pipes other than the drainage pipe 23, cables, etc. pass through have a high degree of freedom in routing, even if the positions of the through-holes are determined in advance, there is no major limitation in routing. For example, since water supply pipes for tap water, fire water, etc. are usually pressurized, there are no major restrictions on the slope, and even if there is a mixture of downward slopes and upward slopes, it will not be a big problem. Cables have no gradient restrictions, so they have little impact on routing routes. Furthermore, such a problem does not occur in the first place with respect to the through holes (ventilation port 17, communication pipe 18, and access port 19) through which pipes and cables do not pass.

排水配管23が貫通する第1の貫通孔16は少なくとも一つ設けられていればよく、その数は限定されない。しかし、本実施形態では、設備計画の自由度を確保するため、複数の第1の貫通孔16が設けられており、第1の貫通孔16の少なくとも一部は互いに口径が異なっており、且つ互いに異なる高さに設けられている。また、PCa部7Aに設けられる貫通孔はできる限り集約することが好ましい。例えば本実施形態では、給水配管と消火配管とガス配管の貫通孔20は共用されている。これによってPCa部7Aの貫通孔の数を削減することができ、PCa部7Aの設計が簡略化される。 At least one first through-hole 16 through which the drain pipe 23 penetrates should be provided, and the number is not limited. However, in this embodiment, a plurality of first through holes 16 are provided in order to ensure flexibility in equipment planning, and at least some of the first through holes 16 have different diameters, and provided at different heights. Moreover, it is preferable that the through-holes provided in the PCa portion 7A be concentrated as much as possible. For example, in this embodiment, the through hole 20 is shared by the water supply pipe, the fire extinguishing pipe, and the gas pipe. As a result, the number of through-holes in the PCa portion 7A can be reduced, simplifying the design of the PCa portion 7A.

前述のように、桁行方向Xの外周梁6は、複数のプレキャスト梁6Aと、一つの現場打設梁6Bとからなっている。現場打設梁6Bは排水配管23が貫通する部位だけに設けられている。本実施形態では排水配管23を外部に引き出すための貫通孔(以下、第2の貫通孔25という)は一つの現場打設梁6Bだけに設けられている。従って、桁行方向Xの外周梁6のうち現場打設梁6Bは一つだけであり、残りはすべてPCa梁6Aとなっている。排水配管23の引き回しによっては複数の現場打設梁6Bを設けることも可能である。 As described above, the outer peripheral beam 6 in the girder direction X consists of a plurality of precast beams 6A and one cast-in-place beam 6B. The cast-in-place beam 6B is provided only at a portion through which the drain pipe 23 penetrates. In this embodiment, a through-hole (hereinafter referred to as a second through-hole 25) for drawing out the drain pipe 23 to the outside is provided only in one of the on-site placement beams 6B. Therefore, among the outer peripheral beams 6 in the girder direction X, only one is the cast-in-place beam 6B, and the rest are all PCa beams 6A. Depending on how the drainage pipe 23 is routed, it is possible to provide a plurality of cast-in-place beams 6B.

このように、本実施形態では内部梁7のうち、排水配管23が貫通する第1の貫通孔16が設けられる部位だけが現場打設部7Bとされ、その他はPCa部7Aとされている。また、外部梁6のうち、排水配管23が貫通する第2の貫通孔25が設けられる部位だけが現場打設梁6Bとされ、その他はPCa梁6AまたはPCa部6Cとされている。例えば桁行方向Xに6スパン、梁間方向Yに1スパンの板状集合住宅1で、梁間方向Yの梁が3分割される場合、外周梁6は17個のPCaブロックと1個の現場打設ブロックとからなり、内部梁7は10個のPCaブロックと5個の現場打設ブロックとからなる。従って、PCaブロックは合計27個、現場打設ブロックは合計6個となる。つまり、全体の約8割をPCa造とすることができるため、工期短縮と基礎構造の品質確保が可能となる。 Thus, in this embodiment, only the portion of the internal beam 7 where the first through-hole 16 through which the drain pipe 23 passes is provided is the on-site placement portion 7B, and the rest is the PCa portion 7A. In addition, only the portion of the external beam 6 where the second through hole 25 through which the drain pipe 23 penetrates is provided is the cast-in-place beam 6B, and the rest is the PCa beam 6A or the PCa portion 6C. For example, in a plate-like collective housing 1 with 6 spans in the girder direction X and 1 span in the beam direction Y, if the beams in the beam direction Y are divided into 3, the outer beam 6 consists of 17 PCa blocks and 1 cast-in-place. The internal beam 7 consists of 10 PCa blocks and 5 cast-in-place blocks. Therefore, there are a total of 27 PCa blocks and a total of 6 cast-in-place blocks. In other words, about 80% of the entire building can be made of PCa, so it is possible to shorten the construction period and ensure the quality of the foundation structure.

図10は本発明の他の実施形態を示す図5と同様の図である。本実施形態では、外周梁6と内部梁7の下端レベルが、それぞれの下端筋設置領域61,71が重ならないように鉛直方向Zにずれている。より具体的には、内部梁7の下端レベルと外周梁6の張出部12の上端レベルが一致している。これによって鉄筋の配置スペースにさらに余裕が生じ、鉄筋の納まりが一層改善される。 FIG. 10 is a view similar to FIG. 5 showing another embodiment of the invention. In this embodiment, the lower end levels of the outer peripheral beam 6 and the inner beam 7 are shifted in the vertical direction Z so that the respective lower muscle installation regions 61 and 71 do not overlap. More specifically, the lower end level of the internal beam 7 and the upper end level of the projecting portion 12 of the outer peripheral beam 6 are aligned. As a result, there is more room in the space for arranging the reinforcing bars, and the fitting of the reinforcing bars is further improved.

1 板状集合住宅
2 基礎構造
3 基礎杭
6 外周梁
6A プレキャスト梁(PCa梁)
6B 現場打設梁
6C プレキャスト部(PCa部)
7 内部梁
7A プレキャスト部(PCa部)
7B 現場打設部
9 フーチング
11 杭頭補強筋
12 張出部
16 第1の貫通孔
25 第2の貫通孔
1 Plate-like housing complex 2 Foundation structure 3 Foundation pile 6 Peripheral beam 6A Precast beam (PCa beam)
6B Field cast beam 6C Precast part (PCa part)
7 Internal beam 7A Precast part (PCa part)
7B Field placing part 9 Footing 11 Pile head reinforcing bar 12 Overhang part 16 First through hole 25 Second through hole

Claims (10)

建物の外周部に沿って配置された複数の外周梁と、前記複数の外周梁の内側に設けられた複数の内部梁と、を有し、前記外周部は一方の長辺と他方の長辺と一対の短辺とからなり、
前記複数の内部梁の各々は、前記内部梁の長さ方向に、前記一方の長辺に隣接するプレキャスト部と、中央のプレキャスト部と、前記他方の長辺に隣接する現場打設部とに3分割され、
排水配管が貫通する少なくとも一つの第1の貫通孔前記現場打設部だけに設けられ、人通口が前記中央のプレキャスト部だけに設けられている、板状集合住宅の基礎構造。
A plurality of perimeter beams arranged along the perimeter of the building and a plurality of interior beams provided inside the plurality of perimeter beams, the perimeter having one long side and the other long side and a pair of short sides,
Each of the plurality of internal beams has , along the length of the internal beam, a precast portion adjacent to the one long side , a central precast portion, and a cast-in-place portion adjacent to the other long side. divided into three
A basic structure of a plate-like housing complex, wherein at least one first through- hole through which a drainage pipe passes is provided only in said cast-in-place portion, and a access port is provided only in said central precast portion .
前記現場打設部の長さは前記内部梁の長さの1/3以下である、請求項1に記載の基礎構造。 2. Foundation structure according to claim 1, wherein the cast-in-place portion is less than or equal to 1/3 the length of the internal beam. 前記少なくとも一つの第1の貫通孔は複数の第1の貫通孔であり、前記複数の第1の貫通孔は前記現場打設部の互いに異なる高さに設けられている、請求項1または2に記載の基礎構造。 3. The at least one first through-hole is a plurality of first through-holes, and the plurality of first through-holes are provided at different heights of the cast-in-place portion. Substructure as described in . 前記複数の第1の貫通孔の口径は互いに異なる、請求項3に記載の基礎構造。 4. The substructure according to claim 3, wherein diameters of said plurality of first through holes are different from each other. 電気配線の貫通孔、ガス配管の貫通孔、給水配管の貫通孔、通気口、連通管の少なくともいずれかが前記プレキャスト部に設けられている、請求項1から4のいずれか1項に記載の基礎構造。 5. The precast portion according to any one of claims 1 to 4, wherein at least one of a through hole for electric wiring, a through hole for gas piping, a through hole for water supply piping, a vent, and a communicating pipe is provided in the precast portion. foundation structure. 前記複数の外周梁は、プレキャスト梁と、現場打設梁と、前記排水配管が貫通する少なくとも一つの第2の貫通孔と、を有し、前記少なくとも一つの第2の貫通孔は前記複数の外周梁の前記現場打設梁のみに設けられている、請求項1から5のいずれか1項に記載の基礎構造。 The plurality of peripheral beams have precast beams, cast-in-place beams, and at least one second through hole through which the drainage pipe passes, and the at least one second through hole is formed in the plurality of 6. Foundation structure according to any one of claims 1 to 5, provided only on the cast-in-place beams of the perimeter beams . 前記外周梁と前記内部梁の交差部の下に設けられた基礎杭と、前記基礎杭の杭頭に設けられ、前記基礎杭の上方に延びる杭頭補強筋と、有し、
前記外周梁はその下部に幅方向両側に張り出した張出部を有し、前記外周梁の下端筋の少なくとも一部は、前記杭頭補強筋の幅方向外側を通るように前記張出部に設けられている、請求項1から6のいずれか1項に記載の基礎構造。
A foundation pile provided under the intersection of the outer peripheral beam and the internal beam, and a pile head reinforcing bar provided at the pile head of the foundation pile and extending upward from the foundation pile,
The outer peripheral beam has an overhang portion projecting on both sides in the width direction at its lower portion, and at least a part of the lower end reinforcement of the outer peripheral beam is attached to the overhang portion so as to pass through the outside of the pile head reinforcement in the width direction. 7. A substructure according to any one of claims 1 to 6, provided.
前記外周梁と前記内部梁の下端レベルが一致している、請求項1から7のいずれか1項に記載の基礎構造。 8. The foundation structure according to any one of claims 1 to 7, wherein lower end levels of said peripheral beams and said internal beams are coincident. 前記外周梁と前記内部梁の下端レベルが、それぞれの下端筋設置領域が重ならないように鉛直方向にずれている、請求項1から7のいずれか1項に記載の基礎構造。 8. The foundation structure according to any one of claims 1 to 7, wherein the lower end levels of said peripheral beams and said inner beams are vertically offset so that their respective lower reinforcement installation areas do not overlap. 外周部を形成する複数の外周梁を施工するとともに、前記複数の外周梁の内側に複数の内部梁を施工することを有し、
前記外周部は一方の長辺と他方の長辺と一対の短辺とからなり、
前記複数の内部梁の各々は、前記内部梁の長さ方向に、前記一方の長辺に隣接するプレキャスト部と、中央のプレキャスト部と、前記他方の長辺に隣接する現場打設部とに3分割され、
排水配管が貫通する少なくとも一つの第1の貫通孔前記現場打設部だけに設けられ、人通口が前記中央のプレキャスト部だけに設けられる、板状集合住宅の基礎構造の施工方法。
constructing a plurality of outer beams forming an outer circumference, and constructing a plurality of inner beams inside the plurality of outer beams;
The outer peripheral portion consists of one long side, the other long side and a pair of short sides,
Each of the plurality of internal beams has , along the length of the internal beam, a precast portion adjacent to the one long side , a central precast portion, and a cast-in-place portion adjacent to the other long side. divided into three
A method of constructing a foundation structure for a plate-like housing complex, wherein at least one first through- hole through which a drainage pipe penetrates is provided only in the cast-in-place portion, and a access port is provided only in the central precast portion .
JP2019085536A 2019-04-26 2019-04-26 Foundation structure and its construction method Active JP7333708B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019085536A JP7333708B2 (en) 2019-04-26 2019-04-26 Foundation structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019085536A JP7333708B2 (en) 2019-04-26 2019-04-26 Foundation structure and its construction method

Publications (2)

Publication Number Publication Date
JP2020180516A JP2020180516A (en) 2020-11-05
JP7333708B2 true JP7333708B2 (en) 2023-08-25

Family

ID=73023793

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019085536A Active JP7333708B2 (en) 2019-04-26 2019-04-26 Foundation structure and its construction method

Country Status (1)

Country Link
JP (1) JP7333708B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005155092A (en) 2003-11-21 2005-06-16 Shimizu Corp Foundation structure for structure
JP2016186186A (en) 2015-03-27 2016-10-27 三井住友建設株式会社 Architectural structure
JP2016186183A (en) 2015-03-27 2016-10-27 三井住友建設株式会社 Construction method for building
JP2017125322A (en) 2016-01-13 2017-07-20 大成建設株式会社 Base structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0444522A (en) * 1990-06-11 1992-02-14 Misawa Homes Co Ltd Housing continuous foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005155092A (en) 2003-11-21 2005-06-16 Shimizu Corp Foundation structure for structure
JP2016186186A (en) 2015-03-27 2016-10-27 三井住友建設株式会社 Architectural structure
JP2016186183A (en) 2015-03-27 2016-10-27 三井住友建設株式会社 Construction method for building
JP2017125322A (en) 2016-01-13 2017-07-20 大成建設株式会社 Base structure

Also Published As

Publication number Publication date
JP2020180516A (en) 2020-11-05

Similar Documents

Publication Publication Date Title
CA3109393C (en) Precast building construction system
CA1282570C (en) Building system for multi-storey buildings
SG187296A1 (en) A multi-storey building with prefabricated members and a semi-prefabricating construction method thereof
KR20070097891A (en) Precast concrete panel with mortar and its method of construction
KR20150029512A (en) The horizontal structural frame and the underground construction methods using it
KR20090064711A (en) Construction method of basement exterior wall applying the floor slab as the strut against the earth pressure from the temporary earth wall = tsw(thrusting slabbed wall) method
CN111119332A (en) Novel electromechanical wire pipe prefabricating and mounting connection construction method for fabricated building
CN114737573A (en) Deep foundation pit engineering main building area rear-dismantling support structure and construction method
JP7333708B2 (en) Foundation structure and its construction method
JP7189001B2 (en) How to construct the foundation of a building
US20150040499A1 (en) Precast concrete module which can be adapted internally to multiple uses
CN116084591A (en) Horizontal connection structure of multi-layer and high-layer concrete modularized combined building and construction method
KR101279139B1 (en) a Connecting Device of Modular Unit Corridor
KR102146077B1 (en) Construction method of top slab with opening for vertical shaft
KR102115352B1 (en) Construction method of slurrry wall using prefabrecated reinforcing bar cage
JP2016186183A (en) Construction method for building
JP4234660B2 (en) Building structure of apartment house
JP2020012330A (en) Building foundation block
CN210507974U (en) Prefabricated folded plate for same-layer drainage of toilet
GB2147635A (en) Foundation for suspended floors
CN211949009U (en) Middle support of ring rib double-skin wall
CN211949008U (en) Intermediate support of annular rib shear wall
JP2005155092A (en) Foundation structure for structure
Elhouar et al. Rehabilitation of the Hotel Africa building
JP2000291197A (en) Building structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220304

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20221109

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20221115

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20230404

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230628

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20230629

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20230719

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230808

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230815

R150 Certificate of patent or registration of utility model

Ref document number: 7333708

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150