JP7235829B1 - Electric hour meter switch control method and electric hour meter - Google Patents
Electric hour meter switch control method and electric hour meter Download PDFInfo
- Publication number
- JP7235829B1 JP7235829B1 JP2021174597A JP2021174597A JP7235829B1 JP 7235829 B1 JP7235829 B1 JP 7235829B1 JP 2021174597 A JP2021174597 A JP 2021174597A JP 2021174597 A JP2021174597 A JP 2021174597A JP 7235829 B1 JP7235829 B1 JP 7235829B1
- Authority
- JP
- Japan
- Prior art keywords
- contact
- time
- current
- switch
- movable contact
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 15
- 230000005284 excitation Effects 0.000 claims description 11
- 230000003111 delayed effect Effects 0.000 claims description 7
- 238000001514 detection method Methods 0.000 claims description 3
- 230000005611 electricity Effects 0.000 claims 2
- 230000001934 delay Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 11
- 238000006243 chemical reaction Methods 0.000 description 8
- 238000010891 electric arc Methods 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000007619 statistical method Methods 0.000 description 1
Images
Landscapes
- Arc-Extinguishing Devices That Are Switches (AREA)
- Driving Mechanisms And Operating Circuits Of Arc-Extinguishing High-Tension Switches (AREA)
- Keying Circuit Devices (AREA)
Abstract
【課題】接点へのダメージを抑制し、接点の信頼性及び寿命を向上させる電力量計の開閉器の制御方法及び電力量計。
【解決手段】電力系統と負荷との間に固定接点7aと可動接点7bが設けられ、励磁コイル5への電流の供給又は遮断により可動接点が固定接点に対して開動作と閉動作することにより電力系統の電力の負荷への供給遮断を行う開閉器4備える電力量計であって、可動接点と固定接点との間に流れる接点電流のピーク値を検出する電流センサ8と、接点電流のピーク値を検出した時刻から可動接点を開動作させる接点開時間を制御し、検出した時刻から接点開時間だけ遅延させた後、可動接点を開動作させる駆動信号を開閉器に出力する制御部22と、駆動信号を励磁コイルに出力し、駆動信号を出力した時刻から所定時間経過後に可動接点が開状態となったときに接点電流をゼロ又はゼロ近傍にする開閉器制御回路6とを備える。
【選択図】図1
A control method for a switch of a power meter and a power meter that suppress damage to contacts and improve reliability and life of the contacts.
A fixed contact (7a) and a movable contact (7b) are provided between a power system and a load, and the movable contact opens and closes with respect to the fixed contact by supplying or interrupting current to an exciting coil (5). A power meter equipped with a switch 4 for interrupting the supply of electric power to a load of an electric power system, the current sensor 8 detecting the peak value of the contact current flowing between the movable contact and the fixed contact, and the peak of the contact current. a control unit 22 that controls the contact opening time for opening the movable contact from the time when the value is detected, delays the contact opening time from the time when the value is detected, and then outputs a driving signal for opening the movable contact to the switch; and a switch control circuit 6 for outputting a drive signal to the exciting coil and setting the contact current to zero or near zero when the movable contact is opened after a predetermined time has passed since the time when the drive signal was output.
[Selection drawing] Fig. 1
Description
本発明は、電力量計の開閉器の制御方法及び電力量計に関する。 The present invention relates to a switch control method for a power meter and a power meter.
電力量計の電力系統(Source)から負荷(Load)の間に設けられる開閉器において、開閉器に設けられた可動接点を固定接点に対して閉動作させると、可動接点と固定接点との間に電流が流れる。 In the switch installed between the power system (Source) and the load (Load) of the watt-hour meter, when the movable contact provided in the switch is closed against the fixed contact, current flows through
次に、開閉器の可動接点を固定接点に対して開動作させると、可動接点と固定接点との間に流れていた電流が遮断される。 Next, when the movable contact of the switch is opened with respect to the fixed contact, the current flowing between the movable contact and the fixed contact is interrupted.
しかしながら、電流がゼロではない場合には、可動接点と固定接点との間にアーク(火花)が発生し、可動接点と固定接点とへダメージを与えることになる。両方の接点に与えダメージは、アーク放電電流の大きさとアーク放電の持続時間によって決定される。 However, if the current is not zero, an arc (spark) will occur between the moving and stationary contacts, damaging the moving and stationary contacts. Damage to both contacts is determined by the magnitude of the arcing current and the duration of the arcing.
このため、電流がゼロ又はゼロ近傍のタイミングにおいて、可動接点を固定接点に対して開動作させた方が、両方の接点へのダメージを抑制し、両方の接点を保護することができる。 For this reason, opening the movable contact with respect to the fixed contact at a timing when the current is zero or near zero can suppress damage to both contacts and protect both contacts.
本発明の課題は、接点へのダメージを抑制し、接点の信頼性及び寿命を向上させることができる電力量計の開閉器の制御方法及び電力量計を提供する。 SUMMARY OF THE INVENTION An object of the present invention is to provide a switch control method for a watt hour meter and a watt hour meter that can suppress damage to contacts and improve the reliability and life of the contacts.
上記課題を解決するために、本発明に係る電力量計の開閉器の制御方法の請求項1は、電力系統と負荷との間に固定接点と可動接点が設けられ、励磁コイルへの電流の供給又は遮断により前記可動接点が前記固定接点に対して開動作と閉動作することにより前記電力系統の電力の前記負荷への供給遮断を行う電力量計の開閉器の制御方法であって、前記可動接点と前記固定接点との間に流れる接点電流のピーク値を検出し、制御部が前記接点電流のピーク値の時刻を検出し、前記接点電流の前記ピーク値を検出した時刻から前記可動接点を開動作させる接点開時間だけ遅延させた時刻に、前記可動接点を開動作させる駆動信号を開閉器制御回路に出力し、前記開閉器制御回路が前記駆動信号を前記励磁コイルに出力した時刻から所定時間経過した時刻に前記可動接点が開状態となったときに前記接点電流をゼロ又はゼロ近傍にすることを特徴とする。 In order to solve the above problems, claim 1 of the switch control method for a watt-hour meter according to the present invention provides a fixed contact and a movable contact between the electric power system and the load, and supplies current to the exciting coil. A control method for a switch of a watt-hour meter that cuts off supply of electric power of the power system to the load by opening and closing the movable contact with respect to the fixed contact by supply or cutoff, the method comprising: A peak value of a contact current flowing between the movable contact and the fixed contact is detected, a control unit detects the time of the peak value of the contact current, and the movable contact is detected from the time when the peak value of the contact current is detected. A drive signal for opening the movable contact is output to the switch control circuit at the time delayed by the contact opening time for the opening operation, and from the time when the switch control circuit outputs the drive signal to the excitation coil The contact current is set to zero or near zero when the movable contact is opened after a predetermined time has elapsed .
請求項2は、請求項1記載の電力量計の開閉器の制御方法であって、前記所定時間は、前記開閉器毎に予め定められた一定値であり、前記接点開時間は、前記ピーク値を検出した時刻と前記所定時間と前記接点電流の周期とに基づき設定されることを特徴とする。 According to a second aspect of the present invention, there is provided the switch control method for a watt-hour meter according to the first aspect, wherein the predetermined time is a constant value predetermined for each switch, and the contact opening time is equal to the peak time. It is characterized in that it is set based on the time when the value is detected, the predetermined time, and the cycle of the contact current.
請求項3は、請求項1記載の電力量計の開閉器の制御方法であって、前記励磁コイルの特性のばらつきに対応付けした前記所定時間をメモリに記憶し、前記制御部は、前記所定時間を前記メモリから読み出し、読み出した前記所定時間と電流のピーク値を検出した時刻と接点電流の周期とに基づき前記接点開時間を設定することを特徴とする。 According to a third aspect of the present invention, there is provided a switch control method for a watt-hour meter according to the first aspect , wherein the predetermined time associated with variations in the characteristics of the excitation coil is stored in a memory, and the control unit comprises: The predetermined time is read from the memory, and the contact opening time is set based on the read predetermined time, the time when the peak value of the current is detected, and the cycle of the contact current.
請求項4は、電力系統と負荷との間に固定接点と可動接点が設けられ、励磁コイルへの電流の供給又は遮断により前記可動接点が前記固定接点に対して開動作と閉動作することにより前記電力系統の電力の前記負荷への供給遮断を行う開閉器を備えた電力量計であって、前記可動接点と前記固定接点との間に流れる接点電流のピーク値を検出する電流センサと、前記接点電流のピーク値の時刻を検出し、前記接点電流のピーク値を検出した時刻から前記可動接点を開動作させる接点開時間だけ遅延させた時刻に、前記可動接点を開動作させる駆動信号を開閉器制御回路に出力する制御部とを備え、前記開閉器制御回路が、前記駆動信号を前記励磁コイルに出力した時刻から所定時間経過した時刻に前記可動接点が開状態となったときに前記接点電流をゼロ又はゼロ近傍にすることを特徴とする。 According to a fourth aspect of the present invention, a fixed contact and a movable contact are provided between the electric power system and the load, and the movable contact opens and closes the fixed contact by supplying or interrupting current to an exciting coil. A watt-hour meter comprising a switch that cuts off the supply of power from the power system to the load, the current sensor detecting a peak value of a contact current flowing between the movable contact and the fixed contact; The time of the peak value of the contact current is detected, and a driving signal for opening the movable contact is generated at a time delayed by the contact opening time for opening the movable contact from the time of detection of the peak value of the contact current . a control unit for outputting to a switch control circuit , when the movable contact is opened at a time after a predetermined time has elapsed from the time when the switch control circuit outputs the drive signal to the excitation coil. The contact current is set to zero or near zero.
請求項5は、請求項4記載の電力量計であって、前記所定時間は、前記開閉器毎に予め定められた一定値であり、前記接点開時間は、前記ピーク値を検出した時刻と前記所定時間と前記接点電流の周期とに基づき設定されることを特徴とする。 A fifth aspect of the present invention is the watt-hour meter according to the fourth aspect, wherein the predetermined time is a constant value predetermined for each switch, and the contact opening time is the time when the peak value is detected. It is characterized in that it is set based on the predetermined time and the cycle of the contact current.
請求項6は、請求項4記載の電力量計であって、前記励磁コイルの特性のばらつきに対応付けした前記所定時間を記憶するメモリを備え、前記制御部は、前記所定時間を前記メモリから読み出し、読み出した前記所定時間と電流のピーク値を検出した時刻と接点電流の周期とに基づき前記接点開時間を設定することを特徴とする。 According to a sixth aspect of the present invention, there is provided a watt-hour meter according to the fourth aspect, further comprising a memory for storing the predetermined time associated with variations in the characteristics of the excitation coil, wherein the control section stores the predetermined time The contact opening time is set based on the predetermined time read out from the memory, the time when the peak value of the current is detected, and the cycle of the contact current.
請求項1,4によれば、接点電流のピーク値を検出した時刻から可動接点を開動作させる接点開時間だけ遅延させた時刻に、可動接点を開動作させる駆動信号を開閉器制御回路に出力する。開閉器制御回路が駆動信号を励磁コイルに出力した時刻から所定時間経過した時刻に可動接点が開状態となるので、接点開時間を制御することで、可動接点が開状態となったときに接点電流をゼロ又はゼロ近傍にする。従って、接点へのダメージを抑制し、接点の信頼性及び寿命を向上させることができる。
According to
請求項2,5によれば、接点開時間は、ピーク値を検出した時刻と所定時間と接点電流の周期とに基づき設定されるので、可動接点が開状態となったときに接点電流がゼロ又はゼロ近傍にすることができる。
According to
請求項3,6によれば、励磁コイルの特性のばらつきに対応した所定時間と電流のピーク値を検出した時刻と接点電流の周期とに基づき接点開時間を設定するので、励磁コイルの特性がばらついても可動接点が開状態となったときに接点電流がゼロ又はゼロ近傍にすることができる。
According to
以下、本発明の実施の形態に係る電力量計の開閉器の接点制御方法及び電力量計について、図面を参照しながら詳細に説明する。 Hereinafter, a contact control method for a switch of a watt hour meter and a watt hour meter according to an embodiment of the present invention will be described in detail with reference to the drawings.
(第1の実施形態)
図1に第1の実施形態に係る電力量計の構成図を示す。電力量計1は、電力系統1S,2S(Source側)の系統電圧と電流を検出し、検出された電圧と電流とに基づき電力量を演算する。電力系統1Sは、商用周波数(50Hz又は60Hz)の交流電圧及び交流電流を負荷に供給する。
(First embodiment)
FIG. 1 shows a configuration diagram of a power meter according to the first embodiment. The watt-
電力量計1は、図1に示すようにCPU2(中央処理装置)、電圧信号変換回路3、開閉器4、開閉器制御回路6、電流センサ8、電流信号変換回路10、電源回路11を備えている。
The watt-
電圧信号変換回路3は、電力系統1S,2S(Source側)のアナログ信号の系統電圧をデジタル信号の電圧信号に変換する。CPU2は、演算部21、制御部22、メモリ23を備える。
The voltage
演算部21は、電圧信号変換回路3からの電圧信号と電流センサ8からの電流信号とを入力し、電圧信号の電圧と電流信号の電流とを乗算することにより電力量を演算する。メモリ23は、後述する接点開時間Δt1を記憶する。
The
制御部22は、第1制御部に対応し、メモリ23から接点開時間Δt1を読み出し、電流信号変換回路10を介して電流センサ8から入力される接点電流に基づき接点電流のピーク値とピーク値の時刻を検出し、検出した時刻から接点開時間Δt1だけ遅延させた後、励磁コイル5を駆動するための駆動信号を開閉器制御回路6に出力する。
The
電流センサ8は、電力系統1Sと負荷1Lとの間の電線9に設けられ、可動接点7bが固定接点7aに対して閉動作している時に電力系統1Sから負荷1Lに流れる接点電流を検出する。電流センサ8としては、磁気センサや変流器(CT)やシャント抵抗等がある。
The
電流信号変換回路10は、電流センサ8で検出されたアナログ信号の電流信号をデジタル信号の電流信号に変換し、CPU2に出力する。電源回路11は、CPU2と開閉器制御回路6に電源を供給する。
The current
開閉器制御回路6は、CPU2からの駆動信号に基づき駆動信号により開閉器4内の励磁コイル5を駆動する。
The
開閉器4は、ラッチングリレーからなり、励磁コイル5と、電力系統1Sと負荷1Lとの間に固定接点7aと可動接点7bとが設けられ、可動接点7bが固定接点7aに対して開閉することにより電力系統の電力の負荷1Lへの供給遮断を行う。
The
励磁コイル5に励磁電流を一方向に流すと、電磁力が発生して、電磁力により可動接点7bが固定接点7aに対して閉動作する。一方、励磁コイル5に励磁電流を一方向とは逆方向に流すと、可動接点7bが固定接点7aに対して開動作する。
When an exciting current is passed through the
図2は、本発明の第1の実施形態に係る電力量計の開閉器の閉動作時の接点状態と接点電流波形を示す図である。図2(a)に示すように、可動接点7bが固定接点7aに閉動作している時には、負荷側で電力を消費している場合であり、図2(b)に示すように、商用周波数の電流が流れている。
FIG. 2 is a diagram showing the contact state and the contact current waveform during the closing operation of the switch of the watt-hour meter according to the first embodiment of the present invention. As shown in FIG. 2(a), when the
図3は、本発明の第1の実施形態に係る電力量計の開閉器の開動作時の可動接点7bを開動作させた時の接点状態とアーク放電電流波形を示す図である。図3(a)に示すように、可動接点7bが固定接点7aに開動作させた時、図3(b)に示すように、電流がゼロでない場合には、固定接点7aから可動接点7bにアーク(火花)が発生する。
FIG. 3 is a diagram showing the contact state and the arc discharge current waveform when the
アークが発生した場合、図3(b)に示すように、可動接点7bの開動作の時刻t10から電流がゼロになる時刻t11(ゼロクロス)まで、アークが継続する。従って、図4に示すように、接点電流がゼロになる時刻t12に可動接点7bを開動作させたとき、アークが一番発生しない。
When an arc occurs, as shown in FIG. 3B, the arc continues from time t10 when the
上記とは逆に、図5に示すように、接点電流がゼロを過ぎた直後の時刻t13に可動接点7bを開動作させたときには、時刻t13から、接点電流がゼロクロスする時刻t14までアークが発生し、アーク時間が一番長くなる。
Contrary to the above, as shown in FIG. 5, when the
このように開閉器4の可動接点7bの開動作のタイミングを制御しない場合には、可動接点7bの開動作のタイミングは図4、図5のいずれかのタイミングとなる。
When the timing of the opening operation of the
アークは光と熱を大量に発生させ、アーク時間が長ければ長いほど、熱も発生する。可動接点7bの一度の開動作でのアーク時間が電流の1/4波であった場合でも、可動接点7bと固定接点7aとは、発生する熱によって変形してしまう。
Arcs produce large amounts of light and heat, and the longer the arcing time, the more heat is produced. Even if the arc time in one opening operation of the
可動接点7bの開動作を多数回繰り返すことで可動接点7bと固定接点7aのダメージが蓄積し、いずれ接点が故障に至る。
By repeating the opening operation of the
接点が故障に至るまでの開閉回数寿命は、アーク時間が一定であれば、接点部分の材料や構造を強化するしかない。アークが発生しないまたはアークが発生しても短い時間で常に可動接点7bを開動作制御できるならば、接点のダメージが軽減され、故障までの寿命(開閉回数)を延ばすことができる。
If the arc time is constant, the only way to improve the life of the number of switching operations until the contact fails is to strengthen the material and structure of the contact. If the
そこで、第1の実施形態に係る電力量計においては、制御部22が、電流センサ8からの接点電流(図6(b)に示す電流波形)のピーク値とピーク値の時刻t1を検出し、検出した時刻から接点開時間(t2-t1=Δt1)だけ遅延させた時刻t2に、励磁コイル5を駆動するための駆動信号(図6(a)に示すCPU2からの制御信号)を開閉器制御回路6に出力する。接点開時間Δt1は、図6(b)に示す電流がゼロクロスで可動接点7bを開動作させるための調整時間である。
Therefore, in the watt-hour meter according to the first embodiment, the
開閉器制御回路6は、制御部22からの駆動信号により励磁コイル5を駆動する。時刻t2から電流がゼロクロスする時刻t3までの所定時間Δt2は、励磁コイル5に電流が流れて可動接点7bが開動作(離れる)までの時間である。所定時間Δt2は、開閉器4毎に概ね一定値である。
The
接点開時間Δt1を考慮せずに可動接点7bの開動作を制御した場合には、前述したように図4、図5のようなアーク時間となる。
If the opening operation of the
これに対して、接点開時間Δt1を制御して電流のゼロクロスを狙って制御した場合には、図4に示すようにアークの発生が抑制でき、これによって、接点へのダメージが抑制できる。 On the other hand, when the contact opening time Δt1 is controlled to aim at the zero crossing of the current, arc generation can be suppressed as shown in FIG. 4, thereby suppressing damage to the contacts.
接点開時間Δt1の開始時刻の基準については、図6(b)に示すように電流波形のピーク値としている。電流波形は、様々な形となるため、電流のピーク値を基準にした制御が好適である。 The peak value of the current waveform, as shown in FIG. 6B, is used as the reference for the start time of the contact opening time Δt1. Since the current waveform has various shapes, it is preferable to control based on the peak value of the current.
接点開時間Δt1は、電流のピーク値を検出した時刻と所定時間Δt2と接点電流の周期とに基づき設定される。電力系統の交流電源の商用周波数が例えば50Hzとすると、図6(b)に示す電流波形の周期は、20msである。周期が20msであることから、時刻t1から時刻t3までの時間は、35msである。 The contact opening time Δt1 is set based on the time when the peak value of the current is detected, the predetermined time Δt2, and the cycle of the contact current. Assuming that the commercial frequency of the AC power source of the electric power system is 50 Hz, the period of the current waveform shown in FIG. 6(b) is 20 ms. Since the period is 20 ms, the time from time t1 to time t3 is 35 ms.
所定時間Δt2は、開閉器4毎に概ね一定値で既知であることから、所定時間Δt2が例えば、23msであるとすると、接点開時間Δt1は、12msとなる。
Since the predetermined time Δt2 is known as a substantially constant value for each
従って、ピーク値を検出した時刻t1から12ms遅延した時刻t2に、駆動信号を励磁コイル5に出力すると、所定時間Δt2経過時の時刻t3に可動接点7bが開動作し、その時に電流がゼロクロスする。
Therefore, when the driving signal is output to the
従って、アークの発生が大幅に抑制でき、接点へのダメージが抑制できる。これにより、接点の信頼性及び寿命を向上させることができる。 Therefore, arc generation can be greatly suppressed, and damage to the contacts can be suppressed. This can improve the reliability and life of the contacts.
(第2の実施形態)
次に、第2の実施形態に係る電力量計について説明する。同じ種類の開閉器4を大量生産した場合に、開閉器4内の励磁コイル5の特性がばらつく。この場合には、所定時間Δt2は、一定値ではなく、励磁コイル5毎にばらつき、変化する。
(Second embodiment)
Next, a watt-hour meter according to a second embodiment will be described. When the
しかし、第1の実施形態に係る電力量計のように、一定値の時間Δt2を用いて接点開時間Δt1を設定すると、可動接点7bが開動作した時に電流がゼロクロスせず、アークの発生が抑制できない。
However, if the contact opening time Δt1 is set using a constant time Δt2 as in the watt-hour meter according to the first embodiment, the current does not cross zero when the
即ち、励磁コイル5に電流が流れて接点が動作するまでの時間Δt2にはバラツキがある。このため、第2の実施形態に係る電力量計では、統計的手法を用い、所定時間Δt2の平均時間とバラツキを加味して、時間Δt2を固定値に設定している。
That is, the time Δt2 from when the current flows through the
あるメーカーの開閉器において、制御信号を受けてから接点が「開」になるまでの所定時間(コイル励磁時間)を大量に測定したとき、その測定結果が正規分布に従うものと仮定する。平均時間=Δt2av, 標準偏差=σと仮定する。 It is assumed that when measuring a large amount of predetermined time (coil excitation time) from receiving a control signal to opening a contact in a switch manufactured by a certain manufacturer, the measurement results follow a normal distribution. Assume mean time=Δt2av, standard deviation=σ.
複数個nの開閉器4-1~4-nの励磁コイル5-1~5-nの特性のばらつきにより、所定時間Δt2-1~Δt2-nもばらつくので、制御部22が所定時間Δt2-1~Δt2-nの平均時間Δt2avを求める。平均時間Δt2avは、式(1)で求められる。
Δt2av=(Δt2-1+Δt2-2+Δt2-3…Δt2-n)/n …(1)
理想としては、時間が最も長い(ここではΔt2av+3σとして扱う)開閉器であっても電流がゼロクロスする直前で開閉器が「開」状態になることが望ましい。即ち、図7に示すようになる。
Due to variations in the characteristics of the exciting coils 5-1 to 5-n of the plurality of n switches 4-1 to 4-n, the predetermined times Δt2-1 to Δt2-n also vary. Find the average time Δt2av of 1 to Δt2-n. The average time Δt2av is obtained by Equation (1).
Δt2av=(Δt2−1+Δt2−2+Δt2−3 …Δt2−n)/n (1)
Ideally, even if the switch has the longest time (here, treated as Δt2av+3σ), it is desirable that the switch should be in the “open” state just before the current crosses zero. That is, it becomes as shown in FIG.
この場合、Δt2=Δt2av+3σを固定値として設定し、メモリ23に所定時間Δt2=Δt2av+3σを記憶する。なお、管理上限値を+3σにするか或いは他の値にするかは、採用する開閉器の実態に合わせて決めれば良い。
In this case, Δt2=Δt2av+3σ is set as a fixed value, and the predetermined time Δt2=Δt2av+3σ is stored in the
制御部22は、メモリ23から読み出した所定時間Δt2=Δt2av+3σと電流のピーク値を検出した時刻と接点電流の周期とに基づき平均値化された接点開時間Δt1avを設定する。
The
従って、ピーク値を検出した時刻から接点開時間Δt1avだけ遅延した時刻に、駆動信号を励磁コイル5に出力すると、時間Δt2=Δt2av+3σの時間経過時に可動接点7bが開動作し、その時に電流がゼロクロス又はゼロクロス近傍になる。従って、アークの発生が大幅に抑制でき、接点へのダメージが抑制できる。これにより、接点の信頼性及び寿命を向上させることができる。
Therefore, when the drive signal is output to the
また、使用する開閉器の各々の個体に合わせて時間Δt2を設定する必要がなく、電力量計内蔵のメモリ23で所定時間Δt2=Δt2av+3σを固定値として扱うため、電力量計の製造性が良い。
In addition, there is no need to set the time Δt2 according to each individual switch to be used, and the
(第3の実施形態)
次に、第3の実施形態に係る電力量計について説明する。第2の実施形態に係る電力量計で説明したように、所定時間Δt2は、励磁コイル5毎にばらつく。所定時間Δt2のバラツキが大きい場合、所定時間Δt2を固定値として扱うと、図8に示すように、一部開閉器の制御が電流ピークより前の接点動作となってしまい、アーク時間が伸びて信頼性を損なうこととなる。
(Third embodiment)
Next, a power meter according to the third embodiment will be described. As described for the watt-hour meter according to the second embodiment, the predetermined time Δt2 varies for each
このため、開閉器における所定時間Δt2を個別に測定し、その結果をそれぞれの電力量計内蔵のメモリ23に保存し、制御時にメモリ23から所定時間Δt2を読み出して用いる。
Therefore, the predetermined time Δt2 in the switch is individually measured, the result is stored in the
即ち、第3の実施形態に係る電力量計では、制御部22が、所定時間Δt2のばらつきに応じて、接点開時間Δt1を変化させる制御を行う。
That is, in the watt-hour meter according to the third embodiment, the
この制御方法は、開閉器毎の各々の励磁コイル5に電流を流し、各々の所定時間Δt2を測定し、測定された各々の所定時間Δt2をCPU2内のメモリ23に記憶する。具体的には、複数個の開閉器4-1~4-nにおいて、励磁コイル5-1~5-nの特性のばらつきに対応付けした所定時間Δt2-1~Δt2-nをメモリ23に記憶する。
In this control method, a current is passed through each
次に、制御部22は、開閉器4-1では、励磁コイル5-1の特性のばらつきに対応付けした所定時間Δt2-1をメモリ23から読み出す。制御部22は、所定時間Δt2-1と電流のピーク値を検出した時刻と接点電流の周期とに基づき接点開時間Δt1-1を設定する。
Next, in the switch 4-1, the
また、制御部22は、開閉器4-nでは、励磁コイル5-nの特性のばらつきに対応付けした所定時間Δt2-nをメモリ23から読み出す。制御部22は、所定時間Δt2-nと電流のピーク値を検出した時刻と接点電流の周期とに基づき接点開時間Δt1-nを設定する。
In the switch 4-n, the
このように第3の実施形態に係る電力量計によれば、制御部22が、励磁コイル5の特性のばらつきに対応した所定時間と電流のピーク値を検出した時刻と接点電流の周期とに基づき接点開時間を設定する。
As described above, according to the watt-hour meter according to the third embodiment, the
従って、励磁コイル5の特性がばらついても可動接点7bが開状態となったときに接点電流がゼロ又はゼロ近傍にすることができる。これにより、アークの発生が大幅に抑制でき、接点へのダメージが抑制でき、接点の信頼性及び寿命を向上させることができる。また、開閉器のバラツキを気にしなくて済むので、精度良い接点開制御が行える。
Therefore, even if the characteristics of the
1 電力量計
2,2a CPU
3 電圧信号変換回路
4 開閉器
5 励磁コイル
6 開閉器制御回路
7a 固定接点
7b 可動接点
8 電流センサ
9 電線
10 電流信号変換回路
11 電源回路
21 演算部
22 制御部
23 メモリ
1
3 Voltage
Claims (6)
前記可動接点と前記固定接点との間に流れる接点電流のピーク値を検出し、
制御部が前記接点電流のピーク値の時刻を検出し、前記接点電流の前記ピーク値を検出した時刻から前記可動接点を開動作させる接点開時間だけ遅延させた時刻に、前記可動接点を開動作させる駆動信号を開閉器制御回路に出力し、
前記開閉器制御回路が前記駆動信号を前記励磁コイルに出力した時刻から所定時間経過した時刻に前記可動接点が開状態となったときに前記接点電流をゼロ又はゼロ近傍にすることを特徴とする電力量計の開閉器の制御方法。 A fixed contact and a movable contact are provided between an electric power system and a load, and the electric power of the electric power system is generated by opening and closing the movable contact with respect to the fixed contact by supplying or interrupting current to an exciting coil. A control method for a switch of a watt-hour meter that cuts off the supply to the load of
detecting a peak value of a contact current flowing between the movable contact and the fixed contact;
The control unit detects the peak value time of the contact current, and opens the movable contact at the time delayed by the contact opening time for opening the movable contact from the time when the peak value of the contact current is detected. Output a drive signal to the switch control circuit to
The contact current is set to zero or near zero when the movable contact is opened after a predetermined time has passed since the switch control circuit outputs the drive signal to the excitation coil. A control method for a switch of a watt hour meter.
前記制御部は、前記所定時間を前記メモリから読み出し、読み出した前記所定時間と電流のピーク値を検出した時刻と接点電流の周期とに基づき前記接点開時間を設定することを特徴とする請求項1記載の電力量計の開閉器の制御方法。 storing in a memory the predetermined time associated with variations in the characteristics of the exciting coil;
The control unit reads the predetermined time from the memory, and sets the contact opening time based on the read predetermined time, the time when the peak value of the current is detected, and the cycle of the contact current. 2. The method for controlling a switch of a watt hour meter according to claim 1 .
前記可動接点と前記固定接点との間に流れる接点電流のピーク値を検出する電流センサと、
前記接点電流のピーク値の時刻を検出し、前記接点電流のピーク値を検出した時刻から前記可動接点を開動作させる接点開時間だけ遅延させた時刻に、前記可動接点を開動作させる駆動信号を開閉器制御回路に出力する制御部とを備え、
前記開閉器制御回路が、前記駆動信号を前記励磁コイルに出力した時刻から所定時間経過した時刻に前記可動接点が開状態となったときに前記接点電流をゼロ又はゼロ近傍にすることを特徴とする電力量計。 A fixed contact and a movable contact are provided between an electric power system and a load, and the electric power of the electric power system is generated by opening and closing the movable contact with respect to the fixed contact by supplying or interrupting current to an exciting coil. A watt-hour meter comprising a switch that cuts off the supply to the load of
a current sensor that detects a peak value of contact current flowing between the movable contact and the fixed contact;
The time of the peak value of the contact current is detected, and a driving signal for opening the movable contact is generated at a time delayed by the contact opening time for opening the movable contact from the time of detection of the peak value of the contact current . A control unit that outputs to the switch control circuit ,
The switch control circuit sets the contact current to zero or near zero when the movable contact is opened at a predetermined time after the drive signal is output to the excitation coil. An electricity meter characterized by:
前記制御部は、前記所定時間を前記メモリから読み出し、読み出した前記所定時間と電流のピーク値を検出した時刻と接点電流の周期とに基づき前記接点開時間を設定することを特徴とする請求項4記載の電力量計。 A memory that stores the predetermined time associated with the variation in the characteristics of the excitation coil,
The control unit reads the predetermined time from the memory, and sets the contact opening time based on the read predetermined time, the time when the peak value of the current is detected, and the cycle of the contact current. The electricity meter according to claim 4 .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2021174597A JP7235829B1 (en) | 2021-10-26 | 2021-10-26 | Electric hour meter switch control method and electric hour meter |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2021174597A JP7235829B1 (en) | 2021-10-26 | 2021-10-26 | Electric hour meter switch control method and electric hour meter |
Publications (2)
Publication Number | Publication Date |
---|---|
JP7235829B1 true JP7235829B1 (en) | 2023-03-08 |
JP2023064362A JP2023064362A (en) | 2023-05-11 |
Family
ID=85475716
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2021174597A Active JP7235829B1 (en) | 2021-10-26 | 2021-10-26 | Electric hour meter switch control method and electric hour meter |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7235829B1 (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004241204A (en) | 2003-02-04 | 2004-08-26 | Mitsubishi Electric Corp | Switching device |
JP6933786B1 (en) | 2021-05-13 | 2021-09-08 | 東光東芝メーターシステムズ株式会社 | Contact state detection method for watt-hour meter switch and switch drive circuit for watt-hour meter |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SE516437C2 (en) * | 2000-06-07 | 2002-01-15 | Abb Ab | Method, apparatus, apparatus and use, computer program with computer product for predicting a zero passage of an AC |
-
2021
- 2021-10-26 JP JP2021174597A patent/JP7235829B1/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004241204A (en) | 2003-02-04 | 2004-08-26 | Mitsubishi Electric Corp | Switching device |
JP6933786B1 (en) | 2021-05-13 | 2021-09-08 | 東光東芝メーターシステムズ株式会社 | Contact state detection method for watt-hour meter switch and switch drive circuit for watt-hour meter |
Also Published As
Publication number | Publication date |
---|---|
JP2023064362A (en) | 2023-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3018677B1 (en) | Single pole, single current path switching system and method | |
EP3627529B1 (en) | Operator coil parameter based electromagnetic switching | |
US10393809B2 (en) | Intelligent timed electromagnetic switching | |
EP3018678B1 (en) | Detection of electric motor short circuits | |
EP3018674B1 (en) | Wear-balanced electromagnetic motor control switching | |
US6233132B1 (en) | Zero cross relay actuation method and system implementing same | |
US20100265629A1 (en) | Relay Coil Drive Circuit | |
EP3422379A2 (en) | Modular multiple single-pole electromagnetic switching system and method | |
KR20100125808A (en) | Abnormal current detecting circuit for circuit breaker | |
US9722513B2 (en) | Torque-based stepwise motor starting | |
EP3018679B1 (en) | 5-pole based wye-delta motor starting system and method | |
US9425012B2 (en) | Electromagnetic operation device for vacuum circuit breaker | |
JP7235829B1 (en) | Electric hour meter switch control method and electric hour meter | |
JP6099896B2 (en) | Exciting inrush current suppressing device and its suppressing method | |
JP2022175390A (en) | Watt-hour meter circuit breaker contact point state detection method and watt-hour meter circuit breaker drive circuit | |
JP7235837B1 (en) | Electric hour meter switch control method and electric hour meter | |
KR102045898B1 (en) | Control method of circuit breaker | |
KR20090025619A (en) | Device for compensating zero crossing to prevent fusion of relay contact | |
US10211005B2 (en) | Cost reduced synchronized-switching contactor | |
JP3601406B2 (en) | Inductive load switch opening method and control device | |
JP2022177995A (en) | Electronic type watt-hour meter | |
JPS6286620A (en) | Switch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20220412 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20220412 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20220712 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20221025 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20221108 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20230214 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20230224 |
|