JP7103958B2 - Temporary fixing position determination system - Google Patents

Temporary fixing position determination system Download PDF

Info

Publication number
JP7103958B2
JP7103958B2 JP2019002956A JP2019002956A JP7103958B2 JP 7103958 B2 JP7103958 B2 JP 7103958B2 JP 2019002956 A JP2019002956 A JP 2019002956A JP 2019002956 A JP2019002956 A JP 2019002956A JP 7103958 B2 JP7103958 B2 JP 7103958B2
Authority
JP
Japan
Prior art keywords
man
temporary fixing
hour
site
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019002956A
Other languages
Japanese (ja)
Other versions
JP2020111942A (en
Inventor
翔太 金子
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Housing Corp
Original Assignee
Toyota Housing Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Housing Corp filed Critical Toyota Housing Corp
Priority to JP2019002956A priority Critical patent/JP7103958B2/en
Publication of JP2020111942A publication Critical patent/JP2020111942A/en
Application granted granted Critical
Publication of JP7103958B2 publication Critical patent/JP7103958B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、現場付けの外壁パネルである現場付けパネルを有するユニット式建物において、その現場付けパネルを建物ユニットに仮固定した状態で施工現場へ輸送する場合に、その現場付けパネルを仮固定する仮固定位置を決定するための仮固定位置決定システムに関するものである。 In the present invention, in a unit type building having a site-mounted panel which is an outer wall panel attached to the site, the site-mounted panel is temporarily fixed when the site-mounted panel is temporarily fixed to the building unit and then transported to the construction site. It relates to a temporary fixing position determination system for determining a temporary fixing position.

複数の建物ユニットを備えて構成されるユニット式建物では、ユニット製造工場においてあらかじめ各建物ユニットが製造されるようになっている。この場合、建物ユニットには、床面材や天井面材、外壁パネル等があらかじめ取り付けられる。そして、各建物ユニットが製造された後、それら製造された各建物ユニットは施工現場へトラック等により輸送され、その施工現場において互いに組み合わされることにより建物が構築されるようになっている。 In a unit-type building having a plurality of building units, each building unit is manufactured in advance at a unit manufacturing factory. In this case, a floor surface material, a ceiling surface material, an outer wall panel, or the like is attached to the building unit in advance. Then, after each building unit is manufactured, each of the manufactured building units is transported to a construction site by a truck or the like, and the building is constructed by combining with each other at the construction site.

ユニット式建物には、隣り合う建物ユニットが互いに離し置きされ、それら離し置きされた建物ユニットの間の離間部分に床パネルや外壁パネル等が別途設けられることで、建物が構築されるものがある。こうした建物では、上記離間部分に設けられる外壁パネルが施工現場において取り付けられることになる。 In some unit-type buildings, adjacent building units are separated from each other, and a floor panel, an outer wall panel, or the like is separately provided in a separated portion between the separated building units to construct a building. .. In such a building, the outer wall panel provided at the separated portion will be attached at the construction site.

特許文献1には、こうした現場付けの外壁パネル(以下、現場付けパネルという)を施工現場へ輸送するに際し、現場付けパネルを建物ユニットに仮固定した状態で輸送する技術が開示されている。この場合、現場付けパネルを建物ユニットに一体化した状態で輸送することができるため、現場付けパネルを個別に輸送する場合と比べ、輸送効率の向上を図ることが可能となる。 Patent Document 1 discloses a technique for transporting such an outer wall panel attached to a site (hereinafter referred to as a panel attached to a site) in a state of being temporarily fixed to a building unit when the panel attached to the site is transported to a construction site. In this case, since the on-site panel can be transported in a state of being integrated with the building unit, it is possible to improve the transportation efficiency as compared with the case where the on-site panel is individually transported.

特開2011-202439号公報Japanese Unexamined Patent Publication No. 2011-202439

ところで、現場付けパネルを建物ユニットに仮固定した状態で施工現場へ輸送する場合には、施工現場において各建物ユニットを所定の設置位置に設置した後、現場付けパネルを建物ユニットから取り外し、所定の取付位置(換言すると本取付位置)に取り付ける作業を行う必要がある。 By the way, when transporting the on-site panel to the construction site in a state of being temporarily fixed to the building unit, after installing each building unit at a predetermined installation position at the construction site, the on-site panel is removed from the building unit and specified. It is necessary to perform the work of mounting at the mounting position (in other words, the main mounting position).

ここで、施工現場においてかかる作業を行うに際しては、現場付けパネルがいずれの建物ユニットのどの位置に仮固定されているかによって、つまり現場付けパネルの仮固定位置によって、当該作業に要する工数が変わってくることが考えられる。例えば、各建物ユニットが所定の設置位置に設置された状態において、現場付けパネルの仮固定位置が建物ユニット内に位置している場合には、現場付けパネルを取り外す作業を建物ユニット内で行う必要が生じうる。その場合、取り外しの作業を行うに際し作業スペースの制約が大きく、取り外しの作業を行うのに大きな工数を要することが考えられる。また、現場付けパネルの仮固定位置が当該現場付けパネルの本取付位置から大きく離れている場合には、現場付けパネルを取り外してからその現場付けパネルを本取付位置まで運ぶのに大きな工数を要してしまうことが考えられる。 Here, when performing such work at the construction site, the man-hours required for the work vary depending on which position of the building unit the on-site panel is temporarily fixed, that is, depending on the temporary fixing position of the on-site panel. It is possible that it will come. For example, when each building unit is installed at a predetermined installation position and the temporary fixing position of the on-site panel is located inside the building unit, it is necessary to remove the on-site panel in the building unit. Can occur. In that case, there is a large restriction on the work space when performing the removal work, and it is conceivable that a large number of man-hours are required to perform the removal work. If the temporary fixing position of the on-site panel is far from the main mounting position of the on-site panel, it takes a large number of man-hours to remove the on-site panel and then carry the on-site panel to the main mounting position. It is conceivable that it will be done.

そこで、これらの点を鑑みると、現場付けパネルを建物ユニットに仮固定した状態で輸送するに際しては、施工現場で発生する上記仮固定に伴う作業について工数低減を図れるよう、現場付けパネルの仮固定位置を決めるのが望ましいと考えられる。 Therefore, in view of these points, when transporting the on-site panel in a temporarily fixed state to the building unit, the on-site panel is temporarily fixed so as to reduce the man-hours for the work associated with the above-mentioned temporary fixing that occurs at the construction site. It is considered desirable to determine the position.

しかしながら、上記特許文献1には、現場付けパネルが建物ユニットにおける特定部分に仮固定される構成しか示されておらず、現場付けパネルの仮固定位置を施工現場での作業工数低減の観点から、決定するようにした点について何も記載されていない。 However, Patent Document 1 only shows a configuration in which the on-site panel is temporarily fixed to a specific portion of the building unit, and the temporary fixing position of the on-site panel is set from the viewpoint of reducing the work man-hours at the construction site. Nothing is said about the points that were decided.

本発明は、上記事情に鑑みてなされたものであり、現場付けパネルを建物ユニットに仮固定した状態で施工現場へ輸送する場合において、その仮固定に伴い発生する施工現場での作業について工数低減を図ることができる現場付けパネルの仮固定位置を決定する仮固定位置決定システムを提供することを主たる目的とするものである。 The present invention has been made in view of the above circumstances, and when the on-site panel is temporarily fixed to the building unit and transported to the construction site, the number of man-hours required for the work at the construction site caused by the temporary fixing is reduced. The main purpose is to provide a temporary fixing position determination system for determining the temporary fixing position of the on-site panel capable of achieving the above.

上記課題を解決すべく、第1の発明の仮固定位置決定システムは、製造工場で製造される複数の建物ユニットを備えて構成されるとともに、外壁パネルとして、施工現場において前記建物ユニットとは異なる所定の取付位置に取り付けられる現場付けパネルを有するユニット式建物において、その現場付けパネルを前記製造工場において前記建物ユニットに仮固定しその仮固定状態で前記施工現場へ輸送する場合に用いられるものであって、前記現場付けパネルを前記各建物ユニットのうちいずれの建物ユニットのどの位置に仮固定するか、その仮固定位置を決定する仮固定位置決定システムであって、前記施工現場において前記各建物ユニットを所定の設置位置に設置した後、前記現場付けパネルの前記仮固定に伴い発生する作業の工数として、前記現場付けパネルを前記仮固定位置から取り外すのに要する第1工数と、前記取り外した前記現場付けパネルを前記仮固定位置から前記所定の取付位置まで運ぶのに要する第2工数と、があり、前記仮固定位置と前記第1工数との関係を示す第1工数基準が予め定められており、前記仮固定位置と前記第2工数との関係を示す第2工数基準が予め定められており、前記ユニット式建物からなる所定の対象建物について、その設計データを取得する取得手段と、その取得した前記対象建物の設計データに基づき、前記対象建物に含まれる前記現場付けパネルの前記仮固定位置を決定する仮固定位置決定手段と、を備え、前記仮固定位置決定手段は、前記対象建物の設計データ上において前記現場付けパネルの前記仮固定位置を複数箇所に仮設定する仮設定手段と、前記仮設定された前記仮固定位置ごとに、その仮設定された仮固定位置に基づき、当該仮固定位置に前記現場付けパネルが仮固定された場合に生じる前記第1工数及び前記第2工数をそれぞれ前記第1工数基準及び前記第2工数基準を用いて算出する工数算出手段と、を有し、前記工数算出手段により算出された前記仮設定された各仮固定位置ごとの前記第1工数及び前記第2工数に基づき、前記仮設定された各仮固定位置のうちいずれかを当該現場付けパネルの前記仮固定位置として決定することを特徴とする。 In order to solve the above problems, the temporary fixing position determination system of the first invention is configured to include a plurality of building units manufactured in a manufacturing factory, and is different from the building units at a construction site as an outer wall panel. In a unit type building having a site-mounted panel that can be mounted at a predetermined mounting position, the site-mounted panel is temporarily fixed to the building unit at the manufacturing plant and transported to the construction site in the temporarily fixed state. It is a temporary fixing position determination system that determines the position of the building unit to be temporarily fixed to which the on-site panel is temporarily fixed, and the temporary fixing position of each building at the construction site. After the unit is installed at a predetermined installation position, as the man-hours for the work generated by the temporary fixing of the site-mounted panel, the first man-hour required to remove the site-mounted panel from the temporary fixing position and the removal are performed. There is a second man-hour required to carry the on-site panel from the temporary fixing position to the predetermined mounting position, and a first man-hour standard indicating the relationship between the temporary fixing position and the first man-hour is predetermined. A second man-hour standard indicating the relationship between the temporary fixed position and the second man-hour is set in advance, and an acquisition means for acquiring design data of a predetermined target building composed of the unit type building, and an acquisition means for acquiring the design data. Based on the acquired design data of the target building, the temporary fixing position determining means for determining the temporary fixing position of the site-mounted panel included in the target building is provided, and the temporary fixing position determining means is the target. Based on the temporary setting means for temporarily setting the temporary fixing position of the site-mounted panel at a plurality of locations on the design data of the building and the temporarily set temporary fixing position for each of the temporarily set temporary fixing positions. A man-hour calculation means for calculating the first man-hour and the second man-hour, which are generated when the on-site panel is temporarily fixed at the temporary fixing position, using the first man-hour standard and the second man-hour standard, respectively. Based on the first man-hours and the second man-hours for each of the temporarily set temporary fixing positions calculated by the man-hour calculation means, any one of the temporarily set temporary fixing positions is set at the site. It is characterized in that it is determined as the temporary fixing position of the attachment panel.

現場付けパネルを建物ユニットに仮固定した状態で施工現場へ輸送する場合に、その仮固定に伴い施工現場で発生する作業の工数としては、現場付けパネルを仮固定位置から取り外すのに要する第1工数と、その取り外した現場付けパネルを所定の取付位置に取り付けるべく、当該現場付けパネルを仮固定位置から所定の取付位置まで運ぶのに要する第2工数とがある。これら第1工数及び第2工数は、現場付けパネルを各建物ユニットのうちいずれの建物ユニットのどの位置に仮固定するかによって、つまり現場付けパネルの仮固定位置によって、変わることが考えられる。そこで、本発明では、このような点に着目し、現場付けパネルの仮固定位置を仮固定位置決定システムを用いて決定することとしている。 When transporting the on-site panel to the construction site with it temporarily fixed to the building unit, the man-hours required for the work required at the construction site due to the temporary fixing are the first required to remove the on-site panel from the temporary fixing position. There are man-hours and a second man-hour required to carry the on-site panel from the temporary fixing position to the predetermined mounting position in order to mount the removed on-site panel at a predetermined mounting position. It is conceivable that these first man-hours and second man-hours change depending on which position of each building unit the on-site panel is temporarily fixed, that is, depending on the temporary fixing position of the on-site panel. Therefore, in the present invention, paying attention to such a point, the temporary fixing position of the on-site panel is determined by using the temporary fixing position determination system.

この仮固定位置決定システムによれば、現場付けパネルを有する所定の対象建物(ユニット式建物)の設計データが取得され、その取得された設計データに基づき現場付けパネルの仮固定位置が決定される。この仮固定位置の決定に際しては、対象建物の設計データ上において現場付けパネルの仮固定位置が複数箇所に仮設定され、それら仮設定された各仮固定位置ごとに、その仮設定された仮固定位置に基づき、当該仮固定位置に現場付けパネルが仮固定された場合に生じる第1工数及び第2工数がそれぞれ算出される。この場合、第1工数の算出に際しては、仮固定位置と第1工数との関係を予め定めた第1工数基準が用いられ、第2工数の算出に際しては、仮固定位置と第2工数との関係を予め定めた第2工数基準が用いられる。 According to this temporary fixing position determination system, the design data of a predetermined target building (unit type building) having the on-site panel is acquired, and the temporary fixing position of the on-site panel is determined based on the acquired design data. .. When determining the temporary fixing position, the temporary fixing position of the on-site panel is temporarily set at a plurality of places on the design data of the target building, and the temporary fixing position is temporarily set for each of the temporarily set temporary fixing positions. Based on the position, the first man-hours and the second man-hours that occur when the on-site panel is temporarily fixed at the temporary fixing position are calculated, respectively. In this case, when calculating the first man-hours, the first man-hour standard in which the relationship between the temporarily fixed position and the first man-hours is predetermined is used, and when calculating the second man-hours, the temporarily fixed position and the second man-hours are used. The second man-hour standard in which the relationship is predetermined is used.

そして、上記のように算出された、仮設定された仮固定位置ごとの第1工数及び第2工数に基づき、仮設定された各仮固定位置のうちいずれかが現場付けパネルの仮固定位置として決定(本決定)される。この場合、仮設定された仮固定位置ごとの第1工数及び第2工数を参照して現場付けパネルの仮固定位置を決定することが可能となる。したがって、例えば、仮設定された各仮固定位置のうち、第1工数及び第2工数が小さくなる位置を仮固定位置として決定することが可能となる。これにより、現場付けパネルの仮固定に伴い発生する施工現場での作業について工数低減を図ることが可能な仮固定位置を得ることができる。 Then, based on the first man-hours and the second man-hours for each temporarily set temporary fixing position calculated as described above, one of the temporarily set temporary fixing positions is used as the temporary fixing position of the on-site panel. It will be decided (final decision). In this case, it is possible to determine the temporary fixing position of the on-site panel by referring to the first man-hours and the second man-hours for each temporarily set temporary fixing position. Therefore, for example, among the temporarily set temporary fixing positions, the position where the first man-hours and the second man-hours are small can be determined as the temporary fixing position. As a result, it is possible to obtain a temporary fixing position that can reduce the man-hours for the work at the construction site that occurs due to the temporary fixing of the on-site panel.

第2の発明の仮固定位置決定システムは、第1の発明において、前記仮固定位置決定手段は、前記対象建物に含まれる複数の前記現場付けパネルについて前記仮固定位置を決定するものであり、前記仮設定手段は、前記各現場付けパネルの前記仮固定位置を複数の配置パターンで仮設定するものであり、前記工数算出手段は、前記各配置パターンごとに、前記配置パターンで仮設定された前記各現場付けパネルの前記仮固定位置に基づき、それら各現場付けパネルについて前記仮固定に伴い生じる前記第1工数及び前記第2工数をそれぞれ算出し、前記仮固定位置決定手段は、前記工数算出手段により算出された前記各配置パターンごとの前記各現場付けパネルの前記第1工数及び前記第2工数に基づき、前記各配置パターンのうちいずれかの配置パターンで仮設定された前記各現場付けパネルの前記仮固定位置をそれら各現場付けパネルの前記仮固定位置として決定することを特徴とする。 In the temporary fixing position determining system of the second invention, in the first invention, the temporary fixing position determining means determines the temporary fixing position with respect to the plurality of on-site panels included in the target building. The temporary setting means temporarily sets the temporary fixing position of each on-site panel with a plurality of arrangement patterns, and the man-hour calculation means is temporarily set with the arrangement pattern for each arrangement pattern. Based on the temporary fixing positions of the on-site panels, the first man-hours and the second man-hours generated by the temporary fixing are calculated for each of the on-site panels, and the temporary fixing position determining means calculates the man-hours. Based on the first man-hours and the second man-hours of the on-site panel for each of the arrangement patterns calculated by the means, each of the on-site panels temporarily set in any of the arrangement patterns. The temporary fixing position of the above is determined as the temporary fixing position of each of the on-site panels.

ユニット式建物には、現場付けパネルを複数有しているものがある。かかるユニット式建物では、各現場付けパネルがそれぞれ建物ユニットに仮固定された状態で輸送されることになる。そこで本発明では、このように各現場付けパネルが建物ユニットに仮固定された状態で輸送される場合にあって、それら各現場付けパネルの仮固定位置がそれぞれ決定されるようになっている。 Some unit-type buildings have multiple on-site panels. In such a unit-type building, each on-site panel is transported in a state of being temporarily fixed to the building unit. Therefore, in the present invention, when each on-site panel is transported in a state of being temporarily fixed to the building unit in this way, the temporary fixing position of each of the on-site panels is determined.

これら各仮固定位置の決定に際して、各現場付けパネルの仮固定位置が複数の配置パターンで仮設定され、そして、各配置パターンごとに、その配置パターンで仮設定された各現場付けパネルの仮固定位置に基づき、それら各現場付けパネルについて仮固定に伴い生じる第1工数及び第2工数が算出される。そして、このように算出された各配置パターンごとの各現場付けパネルの第1工数及び第2工数に基づき、各配置パターンのうちいずれかの配置パターンで仮設定された各現場付けパネルの仮固定位置がそれら各現場付けパネルの仮固定位置として決定(本決定)される。この場合、各配置パターンごとに算出された各現場付けパネルの第1工数及び第2工数を参照して、各現場付けパネルの仮固定位置を決定することが可能となる。したがって、例えば、各配置パターンのうち、各現場付けパネルの第1工数及び第2工数が小さくなる配置パターンで仮設定された各現場付けパネルの仮固定位置をそれら各現場付けパネルの仮固定位置として決定することが可能となる。これにより、複数の現場付けパネルを建物ユニットに仮固定して輸送する場合において、それら各現場付けパネルの仮固定に伴い生じる作業について工数低減を図ることが可能な、各現場付けパネルの仮固定位置を得ることが可能となる。 When determining each of these temporary fixing positions, the temporary fixing position of each on-site panel is temporarily set by a plurality of arrangement patterns, and for each arrangement pattern, the temporary fixing of each on-site panel temporarily set by the arrangement pattern is temporarily fixed. Based on the position, the first man-hours and the second man-hours generated by the temporary fixing of each of the on-site panels are calculated. Then, based on the first man-hours and the second man-hours of each on-site panel for each arrangement pattern calculated in this way, the on-site panels temporarily fixed in any of the arrangement patterns of each arrangement pattern are temporarily fixed. The position is determined (finally determined) as a temporary fixing position of each of these on-site panels. In this case, it is possible to determine the temporary fixing position of each site-mounted panel by referring to the first man-hours and the second man-hours of each site-mounted panel calculated for each arrangement pattern. Therefore, for example, in each arrangement pattern, the temporary fixing position of each site-mounted panel temporarily set in the arrangement pattern in which the first man-hours and the second man-hours of each site-mounted panel are reduced is set to the temporary fixing position of each site-mounted panel. It becomes possible to determine as. As a result, when a plurality of on-site panels are temporarily fixed to the building unit and transported, it is possible to reduce the man-hours for the work caused by the temporary fixing of each of the on-site panels, and the temporary fixing of each on-site panel can be achieved. It is possible to obtain a position.

第3の発明の仮固定位置決定システムは、第1又は第2の発明において、前記施工現場において前記現場付けパネルの前記仮固定に伴い発生する作業の工数として、前記仮固定位置が設定された前記建物ユニット内に、その仮固定位置に仮固定される前記現場付けパネルと干渉する干渉部材が存在する場合に、当該現場付けパネルを前記仮固定位置から取り外した後、前記干渉部材を前記建物ユニット内に組み込む組み込み作業に要する第3工数があり、前記工数算出手段は、前記対象建物の設計データに基づき、前記仮設定された前記仮固定位置に前記現場付けパネルが仮固定された場合に、当該現場付けパネルと干渉する前記干渉部材が当該仮固定位置が仮設定された前記建物ユニット内に存在するか否かを判定する干渉部材判定手段と、その干渉部材判定手段により前記干渉部材が存在すると判定された場合に、当該干渉部材について生じる前記第3工数を算出する第3工数算出手段と、を備え、前記仮固定位置決定手段は、前記第3工数算出手段により算出された前記第3工数を加味して、前記現場付けパネルの前記仮固定位置を決定することを特徴とする。 In the temporary fixing position determination system of the third invention, the temporary fixing position is set as the man-hours of the work generated by the temporary fixing of the on-site panel at the construction site in the first or second invention. When there is an interference member in the building unit that interferes with the site-mounted panel that is temporarily fixed at the temporary fixing position, after removing the site-mounted panel from the temporary fixing position, the interference member is removed from the building. There is a third man-hour required for the installation work to be incorporated into the unit, and the man-hour calculation means is used when the on-site panel is temporarily fixed at the temporarily set temporary fixing position based on the design data of the target building. The interference member determining means for determining whether or not the interference member that interferes with the on-site panel exists in the building unit in which the temporary fixing position is temporarily set, and the interference member determining means for the interference member The third man-hour calculation means for calculating the third man-hour generated for the interference member when it is determined to exist, and the temporary fixed position determining means is the first man-hour calculation means calculated by the third man-hour calculation means. It is characterized in that the temporary fixing position of the on-site panel is determined in consideration of three man-hours.

ところで、現場付けパネルが仮固定される仮固定位置によっては、仮固定された現場付けパネルが建物ユニット内の部材(干渉部材)と干渉する場合がある。このような仮固定位置に現場付けパネルを仮固定する場合には、製造工場において干渉部材を建物ユニット内に組み込むのをやめ、施工現場にて仮固定された現場付けパネルを取り外してから干渉部材を建物ユニット内に組み込む必要が生じる。そのため、この場合、施工現場において、干渉部材を建物ユニット内に組み込む工数(第3工数)が発生することになる。 By the way, depending on the temporary fixing position where the on-site panel is temporarily fixed, the temporarily fixed on-site panel may interfere with a member (interference member) in the building unit. When temporarily fixing the on-site panel to such a temporary fixing position, stop incorporating the interference member into the building unit at the manufacturing factory, remove the temporarily fixed on-site panel at the construction site, and then remove the interference member. Will need to be built into the building unit. Therefore, in this case, a man-hour (third man-hour) for incorporating the interference member into the building unit is required at the construction site.

そこで、本発明では、このような点に鑑み、仮設定された現場付けパネルの仮固定位置に、当該現場付けパネルと干渉する干渉部材が存在する場合には、その干渉部材を建物ユニット内に組み込むのに要する第3工数を算出し、その第3工数を加味して現場付けパネルの仮固定位置を決定することとしている。この場合、仮設定された現場付けパネルの各仮固定位置ごとの第1工数及び第2工数に加え、上記第3工数を加味して仮固定位置が決定される。したがって、例えば、仮設定された各仮固定位置のうち、第1工数及び第2工数が小さく、かつ第3工数が生じない位置を仮固定位置として決定することが可能となる。これにより、現場付けパネルの仮固定に伴い発生する施工現場での作業について工数低減を図ることが可能な仮固定位置をより確実に得ることができる。 Therefore, in view of these points, in the present invention, if there is an interference member that interferes with the site-mounted panel at the temporarily fixed position of the site-mounted panel, the interference member is placed in the building unit. The third man-hour required for incorporation is calculated, and the temporary fixing position of the on-site panel is determined in consideration of the third man-hour. In this case, in addition to the first man-hours and the second man-hours for each temporary fixing position of the temporarily set on-site panel, the temporary fixing position is determined in consideration of the third man-hour. Therefore, for example, among the temporarily set temporary fixing positions, a position where the first man-hours and the second man-hours are small and the third man-hour does not occur can be determined as the temporary fixing position. As a result, it is possible to more reliably obtain a temporary fixing position that can reduce the man-hours for the work at the construction site that occurs due to the temporary fixing of the on-site panel.

第4の発明の仮固定位置決定システムは、第1乃至第3のいずれかの発明において、前記第1工数基準は、前記仮固定位置が、前記建物ユニットの側面部のうち、他の前記建物ユニットと隣接する隣接側面部に設定される場合と、他の前記建物ユニットと隣接しない非隣接側面部に設定される場合とについてそれぞれ前記第1工数をいずれとするのか規定したものであることを特徴とする。 In the temporary fixing position determination system of the fourth invention, in any one of the first to third inventions, the first man-hour standard is that the temporary fixing position is the other building among the side surface portions of the building unit. It stipulates which of the first man-hours should be set for the case where it is set on the adjacent side surface portion adjacent to the unit and the case where it is set on the non-adjacent side surface portion not adjacent to the other building unit. It is a feature.

現場付けパネルが仮固定される建物ユニットの側面部には、他の建物ユニットと隣接する隣接側面部と、他の建物ユニットと隣接しない非隣接側面部とがある。ここで、現場付けパネルが隣接側面部に仮固定される場合には、仮固定された現場付けパネルを取り外す作業が建物ユニット内で行われることになる。この場合、建物ユニット内で現場付けパネルを仮固定しているボルト等を取り外し、その後、現場付けパネルを上方に吊り上げて取り外す、等の作業が行われることになる。しかしながら、建物ユニット内では、これらの作業を行うスペースの確保が困難であるため、取り外しの作業に際し大きな工数(第1工数)を要することが考えられる。その一方で、現場付けパネルが非隣接側面部に仮固定される場合には、現場付けパネルを取り外す作業を屋外にて行うことが可能となる。この場合、取り外しの作業を行うためのスペースが広く確保されているため、取り外し作業に際し工数(第1工数)の低減を図ることが可能となる。 The side surface portion of the building unit to which the site-mounted panel is temporarily fixed includes an adjacent side surface portion adjacent to another building unit and a non-adjacent side surface portion not adjacent to the other building unit. Here, when the on-site panel is temporarily fixed to the adjacent side surface portion, the work of removing the temporarily fixed on-site panel is performed in the building unit. In this case, work such as removing the bolts and the like that temporarily fix the on-site panel in the building unit, and then lifting and removing the on-site panel upward is performed. However, since it is difficult to secure a space for performing these operations in the building unit, it is conceivable that a large number of man-hours (first man-hours) is required for the removal work. On the other hand, when the on-site panel is temporarily fixed to the non-adjacent side surface portion, the work of removing the on-site panel can be performed outdoors. In this case, since a large space for performing the removal work is secured, it is possible to reduce the man-hours (first man-hours) for the removal work.

そこで本発明では、上記の点に鑑み、第1工数の算出に用いる第1工数基準として、仮固定位置が隣接側面部にある場合と非隣接側面部にある場合とでそれぞれ第1工数を規定したものを用いている。この場合、第1工数基準として、仮固定位置が隣接側面部にある場合には第1工数を大きく、仮固定位置が非隣接側面部にある場合には第1工数を小さく規定したものを用いることが考えられる。これにより、第1工数基準を用いて第1工数を算出するにあたって、その第1工数を好適に算出することができる。 Therefore, in view of the above points, in view of the above points, as the first man-hour reference used for calculating the first man-hour, the first man-hour is defined for each of the case where the temporary fixing position is on the adjacent side surface portion and the case where the temporary fixing position is on the non-adjacent side surface portion. I am using the one that I did. In this case, as the first man-hour standard, the first man-hour is specified to be large when the temporary fixing position is on the adjacent side surface portion, and the first man-hour is specified to be small when the temporary fixing position is on the non-adjacent side surface portion. Can be considered. As a result, when calculating the first man-hour using the first man-hour standard, the first man-hour can be preferably calculated.

第5の発明の仮固定位置決定システムは、第1乃至第4のいずれかの発明において、前記第2工数基準は、前記各建物ユニットが所定の設置位置に設置された状態における前記仮固定位置から前記所定の取付位置までの移動距離と前記第2工数との関係を規定したものであり、前記工数算出手段は、前記対象建物の設計データに基づき、その対象建物において、前記仮設定手段により仮設定された前記仮固定位置から前記所定の取付位置までの前記移動距離を算出する移動距離算出手段と、その算出された前記移動距離に基づき、当該仮固定位置に前記現場付けパネルが仮固定された場合に生じる前記第2工数を前記第2工数基準を用いて算出する第2工数算出手段と、を有することを特徴とする。 The temporary fixing position determination system of the fifth invention is the temporary fixing position in any one of the first to fourth inventions, wherein the second manpower standard is a state in which each building unit is installed at a predetermined installation position. The relationship between the moving distance from the to the predetermined mounting position to the predetermined mounting position and the second manpower is defined, and the manpower calculation means is based on the design data of the target building and is used by the temporary setting means in the target building. The on-site panel is temporarily fixed at the temporary fixing position based on the moving distance calculating means for calculating the moving distance from the temporarily set temporary fixing position to the predetermined mounting position and the calculated moving distance. It is characterized by having a second manpower calculation means for calculating the second manpower generated in the case of the above using the second manpower standard.

施工現場にて仮固定位置から取り外した現場付けパネルをその仮固定位置から所定の取付位置まで運ぶのに要する作業工数(第2工数)は、仮固定位置から所定の取付位置までの移動距離に依存することが考えられる。そこで本発明では、この点に着目し、第2工数の算出に用いる第2工数基準として、仮固定位置から所定の取付位置までの移動距離と第2工数との関係を規定したものを用いるようにしている。この場合、第2工数基準としては、例えば移動距離が大きいほど第2工数が大きくなる関係を規定したものを用いることが考えられる。第2工数の算出に際しては、仮設定された仮固定位置から所定の取付位置までの移動距離が算出され、その算出された移動距離に基づき第2工数基準を用いて第2工数が算出される。これにより、第2工数基準を用いて第2工数を算出するにあたって、その第2工数を好適に算出することができる。 The work man-hours (second man-hours) required to carry the on-site panel removed from the temporary fixing position at the construction site from the temporary fixing position to the predetermined mounting position is the moving distance from the temporary fixing position to the predetermined mounting position. It is possible to depend on it. Therefore, in the present invention, paying attention to this point, as the second man-hour standard used for calculating the second man-hour, the one that defines the relationship between the moving distance from the temporarily fixed position to the predetermined mounting position and the second man-hour is used. I have to. In this case, as the second man-hour standard, for example, it is conceivable to use one that defines the relationship that the second man-hour increases as the moving distance increases. When calculating the second man-hour, the moving distance from the temporarily set temporary fixed position to the predetermined mounting position is calculated, and the second man-hour is calculated using the second man-hour standard based on the calculated moving distance. .. As a result, when calculating the second man-hour using the second man-hour standard, the second man-hour can be preferably calculated.

第6の発明の仮固定位置決定システムは、第1乃至第5のいずれかの発明において、過去に施工された前記ユニット式建物について、前記現場付けパネルが仮固定された前記仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に発生した前記第1工数のデータとが対応付けられた状態で第1工数実績データとして記憶されている第1工数データベースと、その第1工数データベースに記憶された前記第1工数実績データに基づき、前記第1工数基準を作成する第1工数基準作成手段と、を備えることを特徴とする。 The temporary fixing position determination system of the sixth invention provides information on the temporary fixing position in which the on-site panel is temporarily fixed to the unit type building constructed in the past in any one of the first to fifth inventions. And the first man-hour database stored as the first man-hour actual data in a state in which the data of the first man-hour actually generated by the temporary fixing at the temporary fixing position is associated with the first man-hour database and the first man-hour. It is characterized by including a first man-hour standard creating means for creating the first man-hour standard based on the first man-hour actual data stored in a database.

本発明によれば、過去に施工されたユニット式建物において、現場付けパネルが仮固定された仮固定位置ごとに、その仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に生じた第1工数とが対応付けられた状態で第1工数実績データとして記憶されている。そして、その記憶された第1工数実績データに基づき、第1工数基準が作成されるようになっている。この場合、第1工数基準を用いて第1工数を算出するにあたり、現場での実際の作業に即した工数を算出することが可能となる。 According to the present invention, in a unit-type building constructed in the past, for each temporary fixing position where the on-site panel is temporarily fixed, information on the temporary fixing position and the actual fixing at the temporary fixing position are accompanied. It is stored as the first man-hour actual data in a state in which the generated first man-hour is associated with it. Then, the first man-hour standard is created based on the stored first man-hour actual data. In this case, when calculating the first man-hour using the first man-hour standard, it is possible to calculate the man-hour according to the actual work at the site.

第7の発明の仮固定位置決定システムは、第1乃至第6のいずれかの発明において、過去に施工された前記ユニット式建物について、前記現場付けパネルが仮固定された前記仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に発生した前記第2工数のデータとが対応付けられた状態で第2工数実績データとして記憶されている第2工数データベースと、その第2工数データベースに記憶された前記第2工数実績データに基づき、前記第2工数基準を作成する第2工数基準作成手段と、を備えることを特徴とする。 The temporary fixing position determination system of the seventh invention provides information on the temporary fixing position in which the on-site panel is temporarily fixed to the unit type building constructed in the past in any one of the first to sixth inventions. And the second man-hour database stored as the second man-hour actual data in a state in which the data of the second man-hour actually generated by the temporary fixing at the temporary fixing position is associated with the second man-hour database and the second man-hour. A second man-hour standard creating means for creating the second man-hour standard based on the second man-hour actual data stored in the database is provided.

本発明によれば、過去に施工されたユニット式建物において、現場付けパネルが仮固定された仮固定位置ごとに、その仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に生じた第2工数とが対応付けられた状態で第2工数実績データとして記憶されている。そして、その記憶された第2工数実績データに基づき、第2工数基準が作成されるようになっている。この場合、第2工数基準を用いて第2工数を算出するにあたり、現場での実際の作業に即した工数を算出することが可能となる。 According to the present invention, in a unit-type building constructed in the past, for each temporary fixing position where the on-site panel is temporarily fixed, information on the temporary fixing position and the actual fixing at the temporary fixing position are accompanied. It is stored as the second man-hour actual data in a state in which the generated second man-hour is associated with it. Then, the second man-hour standard is created based on the stored second man-hour actual data. In this case, when calculating the second man-hours using the second man-hour standard, it is possible to calculate the man-hours according to the actual work at the site.

ユニット式建物の構成を示す平面図。Top view showing the structure of the unit type building. 建物ユニットを示す斜視図。A perspective view showing a building unit. 建物を構築する際の流れを説明するための平面図。A plan view to explain the flow when constructing a building. 仮固定位置決定装置の概略構成を示す図。The figure which shows the schematic structure of the temporary fixing position determination device. 現場付けパネルの仮固定位置を決定する制御処理の流れを示すフローチャート。A flowchart showing the flow of control processing for determining the temporary fixing position of the on-site panel. 仮固定可能領域を特定する処理を説明するための図。The figure for demonstrating the process of specifying a temporary fixable area. 各現場付けパネルの仮固定パターンを例示した図。The figure which illustrated the temporary fixing pattern of each on-site panel. 仮固定位置決定処理の流れを示すフローチャート。A flowchart showing the flow of the temporary fixed position determination process. 工数算出処理の流れを示すフローチャート。A flowchart showing the flow of man-hour calculation processing. (a)が第1工数実績データの内容を例示した図であり、(b)が第2工数実績データの内容を例示した図であり、(c)が第3工数実績データの内容を例示した図である。(A) is a diagram illustrating the content of the first man-hour actual data, (b) is a diagram illustrating the content of the second man-hour actual data, and (c) is a diagram illustrating the content of the third man-hour actual data. It is a figure.

以下に、本発明を具体化した一実施の形態について図面を参照しつつ説明する。本実施形態では、現場付けの外壁パネルである現場付けパネルを有するユニット式建物において、その現場付けパネルを建物ユニットに仮固定した状態で施工現場へ輸送する場合に、その現場付けパネルを仮固定する仮固定位置を決定するための仮固定位置決定装置について具体化している。以下では、その仮固定位置決定装置の説明を行うのに先立ち、まずユニット式建物の構成について説明する。図1は、そのユニット式建物の構成を示す平面図であり、図2は、そのユニット式建物を構成する建物ユニットを示す斜視図である。なお、ユニット式建物は二階建てとなっており、図1にはそのユニット式建物の一階部分を示している。 Hereinafter, an embodiment embodying the present invention will be described with reference to the drawings. In the present embodiment, in a unit type building having a site-mounted panel which is an outer wall panel attached to the site, the site-mounted panel is temporarily fixed when the site-mounted panel is temporarily fixed to the building unit and then transported to the construction site. The temporary fixing position determining device for determining the temporary fixing position to be used is embodied. In the following, prior to the description of the temporary fixing position determining device, the configuration of the unit type building will be described first. FIG. 1 is a plan view showing the configuration of the unit-type building, and FIG. 2 is a perspective view showing the building units constituting the unit-type building. The unit-type building has two floors, and FIG. 1 shows the first floor of the unit-type building.

図1に示すように、ユニット式建物30(以下、略して建物30という)は、直方体状に形成された複数の建物ユニット20を備えて構成されている。建物30の一階部分には、複数の建物ユニット20が横並びに設けられており、詳しくは4つの建物ユニット20が横並びに設けられている。これら各建物ユニット20は、平面視において各建物ユニット20の短手方向に並ぶように配置されている。また、図示は省略するが、建物30の二階部分にも、複数の建物ユニット20が設けられている。 As shown in FIG. 1, the unit type building 30 (hereinafter, abbreviated as building 30) is configured to include a plurality of building units 20 formed in a rectangular cuboid shape. A plurality of building units 20 are provided side by side on the first floor of the building 30, and more specifically, four building units 20 are provided side by side. Each of these building units 20 is arranged so as to be arranged in the lateral direction of each building unit 20 in a plan view. Further, although not shown, a plurality of building units 20 are also provided on the second floor of the building 30.

なお、以下の説明では、建物30の一階部分における各建物ユニット20を区別して建物ユニット20A~20Dともいう。これら各建物ユニット20A~20Dは、各建物ユニット20A~20Dが並ぶ方向における一方側から他方側に向けて順に建物ユニット20A、建物ユニット20B、建物ユニット20C、建物ユニット20Dとなっている。 In the following description, each building unit 20 on the first floor of the building 30 is distinguished and also referred to as building units 20A to 20D. Each of these building units 20A to 20D is a building unit 20A, a building unit 20B, a building unit 20C, and a building unit 20D in this order from one side to the other side in the direction in which the building units 20A to 20D are arranged.

建物ユニット20は、図2に示すように、その四隅に配設される4本の柱21と、各柱21の上端部及び下端部をそれぞれ連結する各4本の天井大梁22及び床大梁23とを備える。建物ユニット20では、それら柱21、天井大梁22及び床大梁23により直方体状の骨格(フレーム)が形成されている。 As shown in FIG. 2, the building unit 20 has four pillars 21 arranged at its four corners, and four ceiling girders 22 and floor girders 23 connecting the upper ends and lower ends of the pillars 21, respectively. And. In the building unit 20, a rectangular cuboid skeleton (frame) is formed by the pillars 21, the ceiling girder 22, and the floor girder 23.

建物ユニット20の天井部には、対向する各天井大梁22の間に複数の天井小梁24が架け渡されている。これら天井小梁24には天井面材(図示略)が取り付けられる。また、建物ユニット20の床部には、対向する各床大梁23の間に複数の床小梁25が架け渡されている。これら床小梁25には床面材(図示略)が取り付けられる。また、建物ユニット20の各側面部では、一対の柱21と、それら各柱21の上端部及び下端部を連結する天井大梁22及び床大梁23とにより矩形状のフレームが形成されている。これら建物ユニット20の側面部(詳しくはフレーム)には、外壁パネル32(図1参照)や内壁パネル等が取り付けられる。 A plurality of ceiling beams 24 are bridged between the ceiling beams 22 facing each other on the ceiling of the building unit 20. A ceiling surface material (not shown) is attached to these ceiling beams 24. Further, on the floor of the building unit 20, a plurality of floor beams 25 are bridged between the floor girders 23 facing each other. Floor surface materials (not shown) are attached to these floor beams 25. Further, in each side surface portion of the building unit 20, a rectangular frame is formed by a pair of pillars 21 and a ceiling girder 22 and a floor girder 23 connecting the upper end and lower ends of the pillars 21. An outer wall panel 32 (see FIG. 1), an inner wall panel, or the like is attached to the side surface portion (detailed frame) of the building unit 20.

図1の説明に戻り、建物30の一階部分においては、隣り合う建物ユニット20A,20B同士が互いに離し置きされており、かつ、隣り合う建物ユニット20C,20D同士が互いに離し置きされている。これにより、各建物ユニット20A,20Bの間、及び各建物ユニット20C,20Dの間はそれぞれ建物ユニット20の存在しない離し置き領域28となっている。これら各離し置き領域28には、床部を構成する平板状の床ユニット29が設けられている。この場合、それら床ユニット29と各建物ユニット20A~20Dの床部とにより建物30の床部が構成されている。 Returning to the description of FIG. 1, in the first floor portion of the building 30, adjacent building units 20A and 20B are separated from each other, and adjacent building units 20C and 20D are separated from each other. As a result, between the building units 20A and 20B and between the building units 20C and 20D, there is a separate area 28 in which the building unit 20 does not exist. A flat plate-shaped floor unit 29 constituting a floor portion is provided in each of these separated areas 28. In this case, the floor portion of the building 30 is composed of the floor units 29 and the floor portions of the building units 20A to 20D.

建物30には、その外周部に沿って外壁部31が設けられている。この外壁部31により屋内と屋外とが仕切られている。外壁部31は、建物外周部に沿って並べられた複数の外壁パネル32,33を有して構成されている。外壁パネル32,33には、建物ユニット20の側面部26に取り付けられた外壁パネル32と、各建物ユニット20A,20Bの間及び各建物ユニット20C,20Dの間に取り付けられた外壁パネル33とがある。これら各外壁パネル32,33はいずれも、外壁面材とその裏面側に設けられた下地フレームとを有して構成されている。なお、図1では、建物ユニット20の一の側面部26に1つの外壁パネル32しか示されていないが、実際には一の側面部26に複数の外壁パネル32が横並びで設けられている。 The building 30 is provided with an outer wall portion 31 along the outer peripheral portion thereof. The indoor and outdoor areas are separated by the outer wall portion 31. The outer wall portion 31 is configured to have a plurality of outer wall panels 32, 33 arranged along the outer peripheral portion of the building. The outer wall panels 32 and 33 include an outer wall panel 32 attached to the side surface portion 26 of the building unit 20 and an outer wall panel 33 attached between the building units 20A and 20B and between the building units 20C and 20D. be. Each of these outer wall panels 32 and 33 is configured to have an outer wall material and a base frame provided on the back surface side thereof. In FIG. 1, only one outer wall panel 32 is shown on one side surface portion 26 of the building unit 20, but in reality, a plurality of outer wall panels 32 are provided side by side on one side surface portion 26.

外壁パネル33には、各建物ユニット20A,20Bの間に設けられた一対の外壁パネル33A,33Bと、各建物ユニット20C,20Dの間に設けられた一対の外壁パネル33C,33Dとがある。外壁パネル33A,33Bは、各建物ユニット20A,20Bの間に架け渡された横架材(図示略)に取り付けられ、外壁パネル33C,33Dは各建物ユニット20C,20Dの間に架け渡された横架材(図示略)に取り付けられている。また、外壁パネル33A,33Bは、その幅が外壁パネル33C,33Dよりも大きくなっている。 The outer wall panel 33 includes a pair of outer wall panels 33A and 33B provided between the building units 20A and 20B, and a pair of outer wall panels 33C and 33D provided between the building units 20C and 20D. The outer wall panels 33A and 33B were attached to a horizontal member (not shown) bridged between the building units 20A and 20B, and the outer wall panels 33C and 33D were bridged between the building units 20C and 20D. It is attached to a horizontal member (not shown). Further, the widths of the outer wall panels 33A and 33B are larger than those of the outer wall panels 33C and 33D.

各外壁パネル33A~33Dは、施工現場において各建物ユニット20A,20Bの間及び各建物ユニット20C,20Dの間にそれぞれ取り付けられるようになっている。したがって、これらの外壁パネル33A~33Dはいわゆる現場付けの外壁パネルとなっている。それに対し、外壁パネル32は、製造工場において建物ユニット20の側面部26に取り付けられるようになっている。したがって、外壁パネル32はいわゆる工場付けの外壁パネルとなっている。 The outer wall panels 33A to 33D are attached between the building units 20A and 20B and between the building units 20C and 20D at the construction site, respectively. Therefore, these outer wall panels 33A to 33D are so-called on-site outer wall panels. On the other hand, the outer wall panel 32 is attached to the side surface portion 26 of the building unit 20 in the manufacturing factory. Therefore, the outer wall panel 32 is a so-called factory-attached outer wall panel.

次に、上述した建物30を構築する際の流れについて図3に基づいて説明する。図3は、建物30を構築する際の流れを説明するための平面図である。 Next, the flow when constructing the above-mentioned building 30 will be described with reference to FIG. FIG. 3 is a plan view for explaining the flow when constructing the building 30.

まず、図3(a)に示すように、製造工場において、建物30を構成する各建物ユニット20を製造する。この場合、各外壁パネル32,33のうち、工場付けの外壁パネル32については建物ユニット20の側面部26に固定(本固定)する。一方、現場付けの外壁パネル33(以下、現場付けパネル33という)については建物ユニット20の側面部26において外壁パネル32が固定されていない領域に仮固定する。図3(a)の例では、各現場付けパネル33A~33Dのうち、現場付けパネル33B,33Cが建物ユニット20Bの側面部26に仮固定され、現場付けパネル33A,33Dが建物ユニット20Cの側面部26に仮固定されている。現場付けパネル33A~33Dの仮固定は、例えば当該パネル33A~33Dの下地フレームを建物ユニット20の側面部26(詳しくは天井大梁22及び床大梁23)にボルト等で(仮)固定することにより行われる。 First, as shown in FIG. 3A, each building unit 20 constituting the building 30 is manufactured in the manufacturing factory. In this case, of the outer wall panels 32 and 33, the factory-attached outer wall panel 32 is fixed (mainly fixed) to the side surface portion 26 of the building unit 20. On the other hand, the outer wall panel 33 attached to the site (hereinafter referred to as the on-site panel 33) is temporarily fixed to the area where the outer wall panel 32 is not fixed on the side surface portion 26 of the building unit 20. In the example of FIG. 3A, of the on-site panels 33A to 33D, the on-site panels 33B and 33C are temporarily fixed to the side surface 26 of the building unit 20B, and the on-site panels 33A and 33D are the side surfaces of the building unit 20C. It is temporarily fixed to the portion 26. Temporary fixing of the on-site panels 33A to 33D is performed, for example, by (temporarily) fixing the base frame of the panels 33A to 33D to the side surface portion 26 (specifically, the ceiling girder 22 and the floor girder 23) of the building unit 20 with bolts or the like. Will be done.

各建物ユニット20を製造した後、それら各建物ユニット20をトラック等で施工現場へ輸送する。この場合、各現場付けパネル33A~33Dは建物ユニット20B,20Cに仮固定された状態で施工現場へと輸送される。 After manufacturing each building unit 20, each building unit 20 is transported to the construction site by a truck or the like. In this case, the on-site panels 33A to 33D are temporarily fixed to the building units 20B and 20C and transported to the construction site.

施工現場では、図3(b)に示すように、輸送された各建物ユニット20をそれぞれ所定の設置位置に設置する。これにより、各建物ユニット20A,20Bの間、及び、各建物ユニット20C,20Dの間にそれぞれ離し置き領域28が形成される。その後、各離し置き領域28にそれぞれ床ユニット29を設置する。 At the construction site, as shown in FIG. 3B, each of the transported building units 20 is installed at a predetermined installation position. As a result, a separated area 28 is formed between the building units 20A and 20B and between the building units 20C and 20D, respectively. After that, the floor unit 29 is installed in each of the separated areas 28.

続いて、建物ユニット20B,20Cに仮固定された現場付けパネル33A~33Dを建物ユニット20B,20Cから取り外し、その取り外した現場付けパネル33A~33Dをそれぞれ所定の取付位置に取り付ける(本固定する)作業を行う。この作業では、建物ユニット20B,20Cから取り外した現場付けパネル33A~33Dを所定の取付位置まで運び、その後、現場付けパネル33A~33Dを当該所定の取付位置に取り付けることとなる。詳しくは、各現場付けパネル33A,33Bについては、各建物ユニット20A,20Bの間に取り付け、各現場付けパネル33C,33Dについては、各建物ユニット20C,20Dの間に取り付ける。なお、図3(b)では、建物ユニット20から取り外した現場付けパネル33A~33Dを本取付位置まで運ぶ際の移動経路を矢印線で示している。 Subsequently, the on-site panels 33A to 33D temporarily fixed to the building units 20B and 20C are removed from the building units 20B and 20C, and the removed on-site panels 33A to 33D are attached (mainly fixed) to the predetermined mounting positions, respectively. Do the work. In this work, the site-mounted panels 33A to 33D removed from the building units 20B and 20C are carried to a predetermined mounting position, and then the site-mounted panels 33A to 33D are mounted at the predetermined mounting position. Specifically, the on-site panels 33A and 33B are attached between the building units 20A and 20B, and the on-site panels 33C and 33D are attached between the building units 20C and 20D. In FIG. 3B, the arrow lines indicate the movement route when the on-site panels 33A to 33D removed from the building unit 20 are carried to the main mounting position.

その後、各建物ユニット20の上方に屋根が設置される等して、建物30が構築される。 After that, the building 30 is constructed by installing a roof above each building unit 20.

ここで、施工現場において、建物ユニット20に仮固定された現場付けパネル33を当該建物ユニット20から取り外し、所定の取付位置(以下、本取付位置ともいう)に取り付ける作業を行うに際しては、現場付けパネル33が各建物ユニット20のうちいずれの建物ユニット20のどの位置に仮固定されているかによって、つまり現場付けパネル33の仮固定位置によって、当該作業に要する工数が変わってくることが考えられる。例えば、現場付けパネル33の仮固定位置が当該現場付けパネル33の本取付位置から大きく離れている場合には、現場付けパネル33を仮固定位置から取り外して本取付位置まで運ぶ際に大きな工数がかかってしまうことが考えられる。 Here, at the construction site, when the on-site panel 33 temporarily fixed to the building unit 20 is removed from the building unit 20 and attached to a predetermined attachment position (hereinafter, also referred to as the main attachment position), the on-site attachment is performed. It is conceivable that the man-hours required for the work vary depending on which position of the building unit 20 of the building units 20 the panel 33 is temporarily fixed, that is, the position of the temporary fixing position of the on-site panel 33. For example, if the temporary fixing position of the on-site panel 33 is far from the main mounting position of the on-site panel 33, a large number of man-hours are required to remove the on-site panel 33 from the temporary fixing position and carry it to the main mounting position. It is possible that it will take.

そこで、本実施形態では、現場付けパネル33の仮固定に伴い発生する上記の作業について工数低減を図るべく、現場付けパネル33の仮固定位置を仮固定位置決定装置10を用いて決定することとしている。以下においては、その仮固定位置決定装置10について図4を用いながら説明を行う。図4は、仮固定位置決定装置10の概略構成を示す図である。なお、仮固定位置決定装置10は、例えば建物メーカに設けられ、同メーカの設計者(ユーザ)により用いられる。 Therefore, in the present embodiment, the temporary fixing position of the on-site panel 33 is determined by using the temporary fixing position determining device 10 in order to reduce the man-hours for the above-mentioned work generated by the temporary fixing of the on-site panel 33. There is. In the following, the temporary fixing position determining device 10 will be described with reference to FIG. FIG. 4 is a diagram showing a schematic configuration of the temporary fixing position determining device 10. The temporary fixing position determining device 10 is provided in, for example, a building maker and is used by a designer (user) of the same maker.

図4に示すように、仮固定位置決定装置10は、パーソナルコンピュータにより構成され、建物の設計を行うためのCADプログラムを有している。仮固定位置決定装置10は、制御部11と、操作部12と、表示部13と、記憶部14とを備える。制御部11は、現場付けパネル33の仮固定位置を決定する制御処理等、各種処理を行うもので、操作部12、表示部13及び記憶部14とそれぞれ接続されている。 As shown in FIG. 4, the temporary fixing position determining device 10 is configured by a personal computer and has a CAD program for designing a building. The temporary fixing position determining device 10 includes a control unit 11, an operation unit 12, a display unit 13, and a storage unit 14. The control unit 11 performs various processes such as a control process for determining a temporary fixing position of the on-site panel 33, and is connected to the operation unit 12, the display unit 13, and the storage unit 14, respectively.

操作部12は、制御部11による処理に必要な情報を入力操作するためのもので、キーボードやマウス等を備えて構成されている。表示部13は、制御部11による処理の結果を表示するためのもので、ディスプレイからなる。記憶部14は、制御部11による処理に必要な各種情報を記憶するもので、複数のデータベース15~17を有している。 The operation unit 12 is for inputting and operating information necessary for processing by the control unit 11, and is configured to include a keyboard, a mouse, and the like. The display unit 13 is for displaying the result of processing by the control unit 11, and includes a display. The storage unit 14 stores various information necessary for processing by the control unit 11, and has a plurality of databases 15 to 17.

続いて、仮固定位置決定装置10により行われる制御処理の内容について説明する。ここでは、現場付けパネル33の仮固定位置を決定する制御処理の内容について図5に基づき説明する。図5は、かかる制御処理の流れを示すフローチャートとなっている。なお、本処理は、ユーザ(例えば設計者)の操作部12による開始操作をトリガとして開始され、制御部11により実行されるものとなっている。また、ここでは、上述した建物30を対象として、本処理が行われることを想定している。したがって、この場合、建物30が対象建物に相当する。 Subsequently, the content of the control process performed by the temporary fixing position determining device 10 will be described. Here, the content of the control process for determining the temporary fixing position of the on-site panel 33 will be described with reference to FIG. FIG. 5 is a flowchart showing the flow of such control processing. This process is started by the start operation by the operation unit 12 of the user (for example, the designer) as a trigger, and is executed by the control unit 11. Further, here, it is assumed that this processing is performed on the above-mentioned building 30. Therefore, in this case, the building 30 corresponds to the target building.

図5に示すように、まずステップS11では、建物30の設計データ(詳しくはCADデータ)を取得する。記憶部14には、あらかじめ建物30の設計データが記憶されており、その記憶部14から当該設計データを読み出して取得する。続くステップS12では、その取得した建物30の設計データに基づいて、建物30に含まれる現場付けパネル33(33A~33D)を特定する。 As shown in FIG. 5, first, in step S11, the design data (specifically, CAD data) of the building 30 is acquired. The design data of the building 30 is stored in the storage unit 14 in advance, and the design data is read out from the storage unit 14 and acquired. In the following step S12, the on-site panels 33 (33A to 33D) included in the building 30 are specified based on the acquired design data of the building 30.

ステップS13では、上記特定した現場付けパネル33(33A~33D)を仮固定するための建物ユニット20の候補を選定する。この場合、各建物ユニット20のうち、現場付けパネル33と同じ一階部分に設けられた各建物ユニット20A~20Dを、仮固定するための建物ユニット20の候補として選定する。 In step S13, a candidate for the building unit 20 for temporarily fixing the specified on-site panels 33 (33A to 33D) is selected. In this case, among the building units 20, the building units 20A to 20D provided on the same first floor as the on-site panel 33 are selected as candidates for the building unit 20 for temporary fixing.

ステップS14及びS15では、上記選定した各建物ユニット20A~20Dの側面部26において、現場付けパネル33を仮固定することが可能な仮固定可能領域を特定する処理を行う。この仮固定可能領域を特定する処理は、建物30の設計データに基づいて行う。以下、この処理の流れについて、図6を参照しながら説明する。図6は、仮固定可能領域を特定する処理を説明するための図である。 In steps S14 and S15, on the side surface portions 26 of the above-selected building units 20A to 20D, a process of specifying a temporarily fixable area where the on-site panel 33 can be temporarily fixed is performed. The process of specifying the temporary fixable area is performed based on the design data of the building 30. Hereinafter, the flow of this process will be described with reference to FIG. FIG. 6 is a diagram for explaining a process of specifying a temporary fixable area.

まずステップS14において、各建物ユニット20A~20Dにおける4つの側面部26のうち、工場付けの外壁パネル32が取り付けられていない側面部26を未取付側面部36として特定する。図6(a)では、その特定された未取付側面部36が長円により囲まれた状態で示されている。図6(a)に示すように、各建物ユニット20A~20Dのうち、端部に配置されている各建物ユニット20A,20Dについては、4つの側面部26のうち3面に外壁パネル32が取り付けられている。そのため、これらの建物ユニット20A,20Dについては残りの一面が未取付側面部36として特定される。また、中間部に配置されている各建物ユニット20B,20Cについては、4つの側面部26のうち2面に外壁パネル32が取り付けられている。そのため、これらの建物ユニット20B,20Cについては残りの2面が未取付側面部36として特定される。 First, in step S14, of the four side surface portions 26 in each building unit 20A to 20D, the side surface portion 26 to which the factory-attached outer wall panel 32 is not attached is specified as the unattached side surface portion 36. In FIG. 6A, the specified unattached side surface portion 36 is shown in a state of being surrounded by an oval. As shown in FIG. 6A, of the building units 20A to 20D, the outer wall panels 32 are attached to three of the four side surface portions 26 of the building units 20A and 20D arranged at the ends. Has been done. Therefore, for these building units 20A and 20D, the remaining one surface is specified as the unmounted side surface portion 36. Further, for each of the building units 20B and 20C arranged in the intermediate portion, the outer wall panel 32 is attached to two of the four side surface portions 26. Therefore, for these building units 20B and 20C, the remaining two surfaces are specified as unmounted side surface portions 36.

続いて、ステップS15において、上記特定した各建物ユニット20A~20Dの未取付側面部36のうち、現場付けパネル33を実際に仮固定することが可能な領域を仮固定可能領域37として特定する。図6(b)では、その特定された仮固定可能領域37が長円により囲まれた状態で示されている。本実施形態では、現場付けパネル33の仮固定を禁止する仮固定禁止領域38が予め定められている。そして、本ステップでは、未取付側面部36ごとに、未取付側面部36に仮固定禁止領域38が含まれているか否かを判断し、含まれている場合には、未取付側面部36のうち、仮固定禁止領域38以外の領域を仮固定可能領域37として特定する。また、未取付側面部36に仮固定禁止領域38が含まれていない場合には未取付側面部36全体を仮固定可能領域37として特定する。 Subsequently, in step S15, among the unattached side surface portions 36 of the above-specified building units 20A to 20D, an area where the on-site panel 33 can actually be temporarily fixed is specified as a temporary fixing possible area 37. In FIG. 6B, the specified temporary fixable area 37 is shown in a state of being surrounded by an oval. In the present embodiment, a temporary fixing prohibition area 38 for prohibiting temporary fixing of the on-site panel 33 is predetermined. Then, in this step, it is determined for each unattached side surface portion 36 whether or not the unattached side surface portion 36 includes the temporary fixing prohibited area 38, and if it is included, the unattached side surface portion 36 Of these, an area other than the temporary fixing prohibited area 38 is specified as the temporary fixing possible area 37. When the non-attached side surface portion 36 does not include the temporary fixing prohibited area 38, the entire unattached side surface portion 36 is specified as the temporary fixing possible area 37.

図6(b)の例では、建物ユニット20Aにおいて、未取付側面部36における一部の領域が仮固定禁止領域38としての通路領域38a及び階段出入領域38bとなっている。したがって、建物ユニット20Aにおいては、未取付側面部36のうち、通路領域38a及び階段出入領域38bを除いた領域が仮固定可能領域37として特定される。なお、通路領域38aとは、建物ユニット20A内に出入りする際に通る領域であり、この領域に現場付けパネル33が仮固定されると、建物ユニット20Aに出入りすることができなくなってしまう。また、階段出入領域38bとは、建物ユニット20A内に設置された階段41に出入りする際に通る領域であり、この領域に現場付けパネル33が仮固定されると、階段41への出入りができなくなってしまう。このため、本実施形態では、これら通路領域38a及び階段出入領域38bをそれぞれ仮固定禁止領域38として定めている。 In the example of FIG. 6B, in the building unit 20A, a part of the unattached side surface portion 36 is a passage area 38a and a stairway entry / exit area 38b as a temporary fixing prohibited area 38. Therefore, in the building unit 20A, the area of the unattached side surface portion 36 excluding the passage area 38a and the stairway entry / exit area 38b is specified as the temporary fixable area 37. The passage area 38a is an area through which the building unit 20A passes when entering and exiting, and if the site-mounted panel 33 is temporarily fixed in this area, the building unit 20A cannot enter and exit. Further, the stairs entry / exit area 38b is an area through which the stairs 41 installed in the building unit 20A is entered / exited, and when the on-site panel 33 is temporarily fixed in this area, the stairs 41 can be entered / exited. It will disappear. Therefore, in the present embodiment, these passage areas 38a and stairway entry / exit areas 38b are defined as temporary fixing prohibited areas 38, respectively.

また、各建物ユニット20B,20Cにおいては、2面の各未取付側面部36のうち、一方の未取付側面部36において、その一部が仮固定禁止領域38としての間仕切・建具領域38cとなっている。したがって、この未取付側面部36においては、間仕切・建具領域38c以外の領域が仮固定可能領域37として特定される。なお、間仕切・建具領域38cとは、建物ユニット20B,20C内に設けられた間仕切壁42及び建具43の少なくとも一方が存在する領域であり、この領域に対しては現場付けパネル33を仮固定することが不可能となっている。このため、本実施形態では、この間仕切・建具領域38cを仮固定禁止領域38として定めている。 Further, in each of the building units 20B and 20C, of the two unattached side surface portions 36, a part of the unattached side surface portion 36 becomes a partition / fitting area 38c as a temporary fixing prohibited area 38. ing. Therefore, in the non-attached side surface portion 36, an area other than the partition / fitting area 38c is specified as a temporary fixable area 37. The partition / fitting area 38c is an area where at least one of the partition wall 42 and the fitting 43 provided in the building units 20B and 20C exists, and the on-site panel 33 is temporarily fixed to this area. Is impossible. Therefore, in the present embodiment, the partition / fitting area 38c is defined as the temporary fixing prohibited area 38.

また、各建物ユニット20B,20Cでは、他方の未取付側面部36に仮固定禁止領域38が含まれていない。また、建物ユニット20Dでは、その未取付側面部36に仮固定禁止領域38が含まれていない。そのため、これらの未取付側面部36では、その全体が仮固定可能領域37として特定される。 Further, in each of the building units 20B and 20C, the temporary fixing prohibition area 38 is not included in the other unattached side surface portion 36. Further, in the building unit 20D, the temporary fixing prohibition area 38 is not included in the unattached side surface portion 36. Therefore, the entire unattached side surface portion 36 is specified as a temporary fixable region 37.

ステップS16では、各現場付けパネル33A~33Dを建物ユニット20A~20Dの仮固定可能領域37において仮固定する際の、各現場付けパネル33A~33Dの仮固定位置について、複数の配置パターン(以下、仮固定パターンという)を作成する。この場合、例えば、各現場付けパネル33A~33Dの仮固定パターンとして想定されうる全てのパターンを作成する。図7には、その作成された仮固定パターンが複数例示されている。なお、図7(a)~(d)では、図3(b)と同様、現場付けパネル33A~33Dを仮固定位置から取り外して本取付位置へと運ぶ際の移動経路が示されている。 In step S16, when the on-site panels 33A to 33D are temporarily fixed in the temporary fixing area 37 of the building units 20A to 20D, a plurality of arrangement patterns (hereinafter, hereinafter,) are arranged for the temporary fixing positions of the on-site panels 33A to 33D. Create a temporary fixed pattern). In this case, for example, all patterns that can be assumed as temporary fixing patterns of the on-site panels 33A to 33D are created. FIG. 7 illustrates a plurality of the created temporary fixing patterns. Note that FIGS. 7 (a) to 7 (d) show a movement route when the on-site panels 33A to 33D are removed from the temporary fixing position and carried to the main mounting position, as in FIG. 3 (b).

ステップS17では、各現場付けパネル33A~33Dの仮固定位置を決定する仮固定位置決定処理を行う。以下、この仮固定位置決定処理について図8に基づいて説明する。図8は、仮固定位置決定処理の流れを示すフローチャートである。 In step S17, a temporary fixing position determination process for determining the temporary fixing positions of the on-site panels 33A to 33D is performed. Hereinafter, this temporary fixing position determination process will be described with reference to FIG. FIG. 8 is a flowchart showing the flow of the temporary fixing position determination process.

図8に示すように、仮固定位置決定処理では、まずステップS21において、ステップS16で作成された複数の仮固定パターンのうちいずれかの仮固定パターンを選択する。例えば、図7(a)~(d)のうちいずれかに示す仮固定パターンを選択する。続くステップS22では、その選択した仮固定パターンにしたがって、建物30の設計データ上に各現場付けパネル33A~33Dの仮固定位置を仮設定する。 As shown in FIG. 8, in the temporary fixing position determination process, first, in step S21, one of the plurality of temporary fixing patterns created in step S16 is selected. For example, the temporary fixing pattern shown in any one of FIGS. 7A to 7D is selected. In the following step S22, the temporary fixing positions of the on-site panels 33A to 33D are temporarily set on the design data of the building 30 according to the selected temporary fixing pattern.

ステップS23~S26では、上記のように仮設定された各現場付けパネル33A~33Dの仮固定位置にそれら各現場付けパネル33A~33Dが仮固定された場合に、施工現場にて発生する当該仮固定に伴う作業について、その作業に要する工数を算出する。ここでは、かかる作業工数を各現場付けパネル33A~33Dごとに順次算出することとしており、以下においては、その算出の流れについて詳しく説明する。 In steps S23 to S26, when the on-site panels 33A to 33D are temporarily fixed at the temporarily fixed positions of the on-site panels 33A to 33D temporarily set as described above, the temporary fixing occurs at the construction site. For the work involved in fixing, calculate the man-hours required for that work. Here, the work man-hours are sequentially calculated for each of the on-site panels 33A to 33D, and the flow of the calculation will be described in detail below.

まずステップS23では、各現場付けパネル33A~33Dのうち、工数算出の対象となる現場付けパネル33を選択する。続くステップS24では、その選択した現場付けパネル33を対象として、工数算出処理を行う。以下、この工数算出処理について図9に示すフローチャートに基づき説明する。なお、以下では、工数算出処理の対象となる現場付けパネル33を現場付けパネル33Xという。 First, in step S23, the on-site panel 33 for which the man-hours are calculated is selected from the on-site panels 33A to 33D. In the following step S24, the man-hour calculation process is performed for the selected on-site panel 33. Hereinafter, this man-hour calculation process will be described with reference to the flowchart shown in FIG. In the following, the on-site panel 33 that is the target of the man-hour calculation process will be referred to as the on-site panel 33X.

図9に示すように、工数算出処理では、まずステップS41において、仮設定された現場付けパネル33Xの仮固定位置に当該現場付けパネル33Xが仮固定された場合に、その現場付けパネル33Xを当該仮固定位置から取り外すのに要する工数(以下、第1工数という)を算出する。この場合、仮設定された現場付けパネル33Xの仮固定位置に基づき、第1工数を算出する。具体的には、第1工数の算出に際しては、現場付けパネル33の仮固定位置と第1工数との関係を予め定めた第1工数基準を用いる。 As shown in FIG. 9, in the man-hour calculation process, when the on-site panel 33X is temporarily fixed at the temporarily fixed position of the temporarily set on-site panel 33X in step S41, the on-site panel 33X is first fixed. The man-hours required to remove the man-hours from the temporarily fixed position (hereinafter referred to as the first man-hours) are calculated. In this case, the first man-hour is calculated based on the temporarily fixed position of the temporarily set on-site panel 33X. Specifically, when calculating the first man-hours, the first man-hour standard in which the relationship between the temporarily fixed position of the on-site panel 33 and the first man-hours is predetermined is used.

第1工数基準は、現場付けパネル33の仮固定位置が、建物ユニット20の側面部26のうち、他の建物ユニット20と隣接する隣接側面部26aに設定される場合と、他の建物ユニット20と隣接しない非隣接側面部26bに設定される場合とについてそれぞれ第1工数を規定したものである。この第1工数基準について詳しく説明すると、例えば現場付けパネル33の仮固定位置が建物ユニット20の隣接側面部26aに設定されている場合(例えば図7(b)における現場付けパネル33C,33Dを参照)、現場付けパネル33を仮固定位置から取り外す作業を建物ユニット20内で行う必要がある。つまり、現場付けパネル33を仮固定しているボルト等を取り外し、その後現場付けパネル33を上方に吊り上げて取り外す、といった作業を建物ユニット20内で行う必要がある。しかしながら、建物ユニット20内ではこれらの作業を行うスペースの確保が困難であり、取り外しの作業に大きな工数を要することが考えられる。一方、現場付けパネル33の仮固定位置が建物ユニット20の非隣接側面部26bに設定されている場合(例えば図7(a)における現場付けパネル33A,33Cを参照)、現場付けパネル33を仮固定位置から取り外す作業を屋外(詳しくは離し置き領域28)で行うことが可能となる。このため、取り外しの作業を行うためのスペースが広く確保されており、取り外しの作業に大きな工数を要しないと考えられる。 The first man-hour standard is that the temporary fixing position of the on-site panel 33 is set to the adjacent side surface portion 26a adjacent to the other building unit 20 among the side surface portions 26 of the building unit 20, and the other building unit 20. The first man-hours are specified for each of the cases where the man-hours are set to the non-adjacent side surface portions 26b which are not adjacent to each other. Explaining the first man-hour standard in detail, for example, when the temporary fixing position of the site-mounted panel 33 is set on the adjacent side surface portion 26a of the building unit 20 (see, for example, the site-mounted panels 33C and 33D in FIG. 7B). ), It is necessary to remove the on-site panel 33 from the temporarily fixed position in the building unit 20. That is, it is necessary to perform work such as removing the bolts and the like that temporarily fix the site-mounted panel 33, and then lifting and removing the site-mounted panel 33 upward in the building unit 20. However, it is difficult to secure a space for performing these operations in the building unit 20, and it is considered that a large number of man-hours are required for the removal operation. On the other hand, when the temporary fixing position of the site-mounted panel 33 is set to the non-adjacent side surface portion 26b of the building unit 20 (see, for example, the site-mounted panels 33A and 33C in FIG. 7A), the site-mounted panel 33 is temporarily fixed. The work of removing from the fixed position can be performed outdoors (specifically, the remote storage area 28). Therefore, a large space for performing the removal work is secured, and it is considered that the removal work does not require a large number of man-hours.

そこで、本実施形態では、上記の点を鑑み、第1工数基準として、現場付けパネル33の仮固定位置が建物ユニット20の隣接側面部26aに設定される場合には第1工数をa1とし、現場付けパネル33の仮固定位置が建物ユニット20の非隣接側面部26bに設定される場合には第1工数をa1よりも小さいa2とする規定を用いることとしている(a1>a2)。したがって、本ステップS41においては、仮設定された現場付けパネル33Xの仮固定位置が隣接側面部26aにある場合には当該現場付けパネル33Xの第1工数K1をa1として算出し、また仮設定された現場付けパネル33Xの仮固定位置が非隣接側面部26bにある場合には当該現場付けパネル33Xの第1工数K1をa2として算出する。 Therefore, in this embodiment, in view of the above points, as the first man-hour standard, when the temporary fixing position of the site-mounted panel 33 is set to the adjacent side surface portion 26a of the building unit 20, the first man-hour is set to a1. When the temporary fixing position of the on-site panel 33 is set on the non-adjacent side surface portion 26b of the building unit 20, the provision that the first man-hour is a2, which is smaller than a1, is used (a1> a2). Therefore, in this step S41, when the temporarily set temporary fixing position of the on-site panel 33X is on the adjacent side surface portion 26a, the first man-hour K1 of the on-site panel 33X is calculated as a1 and temporarily set. When the temporary fixing position of the on-site panel 33X is on the non-adjacent side surface portion 26b, the first man-hour K1 of the on-site panel 33X is calculated as a2.

ステップS42では、各建物ユニット20A~20Dが所定の設置位置に設置された状態における、仮設定された現場付けパネル33Xの仮固定位置から当該現場付けパネル33Xの本取付位置までの移動距離を算出する。この移動距離の算出は、建物30の設計データに基づき行う。 In step S42, the moving distance from the temporarily set temporary fixing position of the site-mounted panel 33X to the main mounting position of the site-mounted panel 33X in the state where the building units 20A to 20D are installed at the predetermined installation positions is calculated. do. This movement distance is calculated based on the design data of the building 30.

ステップS43では、上記算出された移動距離に基づき、仮固定位置から取り外した現場付けパネル33Xを当該仮固定位置から本取付位置まで運ぶのに要する工数(以下、第2工数という)を算出する。この第2工数の算出に際しては、現場付けパネル33の仮固定位置と第2工数との関係を予め定めた第2工数基準を用いる。この第2工数基準は、仮固定位置から本取付位置までの移動距離と第2工数との関係を規定したものであり、詳しくは移動距離をLとした場合、第2工数はα×L(αは定数)であると規定したものである。したがって、本ステップS43では、上記ステップS42で算出された移動距離Lにαを掛けることにより現場付けパネル33Xの第2工数K2を算出する。 In step S43, based on the calculated moving distance, the man-hours required to carry the on-site panel 33X removed from the temporarily fixed position from the temporarily fixed position to the main mounting position (hereinafter referred to as the second man-hour) are calculated. In calculating the second man-hour, the second man-hour standard in which the relationship between the temporarily fixed position of the on-site panel 33 and the second man-hour is predetermined is used. This second man-hour standard defines the relationship between the moving distance from the temporarily fixed position to the main mounting position and the second man-hour. Specifically, when the moving distance is L, the second man-hour is α × L ( α is defined as a constant). Therefore, in this step S43, the second man-hour K2 of the on-site panel 33X is calculated by multiplying the moving distance L calculated in step S42 by α.

ステップS44では、仮設定された現場付けパネル33Xの仮固定位置に当該現場付けパネル33Xが仮固定された場合に、当該現場付けパネル33Xと干渉する干渉部材が建物ユニット20内に存在するか否かを判定する。この判定は、建物30の設計データに基づき行う。干渉部材としては、キッチン設備や、空調設備といった設備機器等が挙げられる。例えば図7(a)では、建物ユニット20Aに仮固定された現場付けパネル33Bが建物ユニット20A内に設けられたキッチン設備45と干渉している。したがって、この場合、キッチン設備45が干渉部材に相当することになる。 In step S44, when the site-mounted panel 33X is temporarily fixed at the temporarily fixed position of the temporarily set site-mounted panel 33X, whether or not there is an interference member in the building unit 20 that interferes with the site-mounted panel 33X. Is determined. This determination is made based on the design data of the building 30. Examples of the interference member include kitchen equipment, equipment such as air conditioning equipment, and the like. For example, in FIG. 7A, the on-site panel 33B temporarily fixed to the building unit 20A interferes with the kitchen equipment 45 provided in the building unit 20A. Therefore, in this case, the kitchen equipment 45 corresponds to the interference member.

ここで、設備機器等の干渉部材は、製造工場においてあらかじめ建物ユニット20内に組み込まれるのが通常である。そのため、現場付けパネル33の仮固定位置が干渉部材と干渉する位置にある場合、現場付けパネル33を製造工場において仮固定位置に仮固定することができなくなってしまう。したがって、現場付けパネル33をかかる仮固定位置に仮固定するに際しては、製造工場において干渉部材を建物ユニット20内に組み込むのをやめ、施工現場において、現場付けパネル33を仮固定位置から取り外した後、干渉部材を建物ユニット20内に組み込む必要がある。したがって、この場合、施工現場において、干渉部材を建物ユニット20内に組み込む工数(以下、第3工数という)が発生することになってしまう。 Here, the interference member such as equipment is usually incorporated in the building unit 20 in advance at the manufacturing factory. Therefore, when the temporary fixing position of the on-site panel 33 is at a position where it interferes with the interference member, the on-site panel 33 cannot be temporarily fixed at the temporary fixing position in the manufacturing factory. Therefore, when temporarily fixing the on-site panel 33 to such a temporary fixing position, after stopping incorporating the interference member into the building unit 20 at the manufacturing factory and removing the on-site panel 33 from the temporary fixing position at the construction site. , It is necessary to incorporate the interference member in the building unit 20. Therefore, in this case, a man-hour (hereinafter referred to as a third man-hour) for incorporating the interference member into the building unit 20 is required at the construction site.

そこで、ステップS44において、現場付けパネル33Xと干渉する干渉部材が存在する場合、ステップS45及びS46において、その干渉部材について生じる第3工数を算出するための処理を行う。この場合、まずステップS45において、干渉部材の種類を特定する。干渉部材の種類としては、キッチン設備、空調設備、階段等、複数の種類があり、ここでは、建物30の設計データに基づき、干渉部材がいずれの種類であるかを特定する。 Therefore, in step S44, when there is an interference member that interferes with the on-site panel 33X, in steps S45 and S46, a process for calculating the third man-hours generated for the interference member is performed. In this case, first, in step S45, the type of the interference member is specified. There are a plurality of types of interference members such as kitchen equipment, air conditioning equipment, and stairs. Here, it is specified which type of interference member is based on the design data of the building 30.

続くステップS46では、上記特定された干渉部材を建物ユニット20内に組み込む際に要する工数(つまり第3工数)を算出する。この第3工数の算出に際しては、干渉部材の種類ごとに第3工数をあらかじめ規定した第3工数基準を用いる。この場合、上記ステップS45で特定された干渉部材の種類に対応する第3工数を第3工数基準より取得し、その取得した第3工数を現場付けパネル33Xの第3工数K3として算出する。 In the following step S46, the man-hours required for incorporating the specified interference member into the building unit 20 (that is, the third man-hour) are calculated. In calculating the third man-hour, the third man-hour standard in which the third man-hour is defined in advance for each type of the interference member is used. In this case, the third man-hour corresponding to the type of the interference member specified in step S45 is acquired from the third man-hour standard, and the acquired third man-hour is calculated as the third man-hour K3 of the on-site panel 33X.

ステップS46において第3工数K3を算出した後、ステップS47に進む。また、上述したステップS44において、干渉部材が存在しないと判定された場合にも、ステップS47に進む。 After calculating the third man-hour K3 in step S46, the process proceeds to step S47. Further, even if it is determined in step S44 described above that the interference member does not exist, the process proceeds to step S47.

ステップS47では、現場付けパネル33Xについて、上記各ステップS41,S43,S46で算出した各工数の総和をパネル工数K(X)として算出する。具体的には、上記ステップS44で干渉部材が存在すると判定された場合には、ステップS41で算出された第1工数K1と、ステップS43で算出された第2工数K2と、ステップS46で算出された第3工数K3との総和をパネル工数K(X)として算出する(K1+K2+K3=K(X))。また、上記ステップS44で干渉部材が存在しないと判定された場合には、上記ステップS41,S43で算出された第1工数K1及び第2工数K2の総和をパネル工数K(X)として算出する(K1+K2=K(X))。その後、本処理を終了する。 In step S47, the sum of the man-hours calculated in each of the above steps S41, S43, and S46 for the on-site panel 33X is calculated as the panel man-hours K (X). Specifically, when it is determined in step S44 that the interference member exists, the first man-hour K1 calculated in step S41, the second man-hour K2 calculated in step S43, and the second man-hour K2 calculated in step S46 are calculated. The sum of the third man-hours K3 and the third man-hours K3 is calculated as the panel man-hours K (X) (K1 + K2 + K3 = K (X)). If it is determined in step S44 that the interference member does not exist, the sum of the first man-hours K1 and the second man-hours K2 calculated in steps S41 and S43 is calculated as the panel man-hours K (X). K1 + K2 = K (X)). After that, this process ends.

図8の説明に戻って、工数算出処理(ステップS24)の後のステップS25では、全ての現場付けパネル33について工数算出処理が終了したか否かを判定する。全ての現場付けパネル33について工数算出処理が終了していない場合、つまりまだ工数算出処理を終えていない現場付けパネル33がある場合にはステップS23に戻り、工数算出処理を終えていない現場付けパネル33を選択して工数算出処理を行う。このようにして、各現場付けパネル33(33A~33D)について順次工数算出処理を行い、全ての現場付けパネル33について工数算出処理を終了した後、ステップS26に進む。 Returning to the description of FIG. 8, in step S25 after the man-hour calculation process (step S24), it is determined whether or not the man-hour calculation process has been completed for all the on-site panels 33. If the man-hour calculation process has not been completed for all the on-site panels 33, that is, if there is a on-site panel 33 for which the man-hour calculation process has not been completed, the process returns to step S23, and the on-site panel for which the man-hour calculation process has not been completed. Select 33 to perform man-hour calculation processing. In this way, the man-hour calculation processing is sequentially performed for each of the on-site panels 33 (33A to 33D), and after completing the man-hour calculation processing for all the on-site panels 33, the process proceeds to step S26.

ステップS26では、工数算出処理により算出された各現場付けパネル33A~33Dのパネル工数K(X)を積算し、その積算値をそれら現場付けパネル33A~33Dの総工数Ktとして算出する。これにより、ステップS21で選択された仮固定パターンについて、各現場付けパネル33A~33Dの総工数Ktが算出される。 In step S26, the panel man-hours K (X) of the on-site panels 33A to 33D calculated by the man-hour calculation process are integrated, and the integrated value is calculated as the total man-hours Kt of the on-site panels 33A to 33D. As a result, the total man-hours Kt of the on-site panels 33A to 33D are calculated for the temporary fixing pattern selected in step S21.

ステップS27では、全ての仮固定パターンについて、現場付けパネル33A~33Dの総工数Ktの算出が終了したか否かを判定する。全ての仮固定パターンについて、総工数Ktの算出が終了していない場合、すなわち、総工数Ktの算出が終了していない仮固定パターンがまだ残っている場合には、ステップS21に戻り、総工数Ktの算出が終了していない仮固定パターンを選択して再度ステップS22~S26の処理を行う。このように、各仮固定パターンについて順次ステップS22~S26の各処理が行われる。つまり、各仮固定パターンについて順次総工数Ktの算出が行われる。そして、全ての仮固定パターンについて、総工数Ktの算出が終了した後、ステップS28に進む。 In step S27, it is determined whether or not the calculation of the total man-hours Kt of the on-site panels 33A to 33D has been completed for all the temporary fixing patterns. If the calculation of the total man-hours Kt has not been completed for all the temporary fixing patterns, that is, if there are still temporary fixing patterns for which the calculation of the total man-hours Kt has not been completed, the process returns to step S21 and the total man-hours are calculated. A temporary fixing pattern for which the calculation of Kt has not been completed is selected, and the processes of steps S22 to S26 are performed again. In this way, each process of steps S22 to S26 is sequentially performed for each temporary fixing pattern. That is, the total man-hours Kt are sequentially calculated for each temporary fixing pattern. Then, after the calculation of the total man-hours Kt is completed for all the temporary fixing patterns, the process proceeds to step S28.

ステップS28では、上記算出された各仮固定パターンの総工数Ktを比較し、最も総工数Ktが小さかった場合の仮固定パターンを特定する。ここで、図7(a)~(d)に示す各仮固定パターンについて、算出される総工数Ktを比較してみる。図7(a)の仮固定パターンでは、現場付けパネル33Bの仮固定位置がキッチン設備45と干渉する位置に仮設定されているため、キッチン設備45について第3工数が算出される。また、各現場付けパネル33B~33Dについては、仮固定位置から本取付位置までの移動距離が大きくなっているため、第2工数が大きな工数として算出される。したがって、図7(a)の仮固定パターンでは、総工数Ktが大きな工数で算出されることになる。 In step S28, the total man-hours Kt of each of the calculated temporary fixing patterns are compared, and the temporary fixing pattern when the total man-hours Kt is the smallest is specified. Here, the calculated total man-hours Kt will be compared for each temporary fixing pattern shown in FIGS. 7 (a) to 7 (d). In the temporary fixing pattern of FIG. 7A, since the temporary fixing position of the on-site panel 33B is temporarily set at a position where it interferes with the kitchen equipment 45, the third man-hour is calculated for the kitchen equipment 45. Further, for each of the on-site panels 33B to 33D, since the moving distance from the temporarily fixed position to the main mounting position is large, the second man-hour is calculated as a large man-hour. Therefore, in the temporary fixing pattern of FIG. 7A, the total man-hours Kt is calculated with a large man-hour.

図7(b)に示す仮固定パターンでは、各現場付けパネル33A~33Cの仮固定位置が建物ユニット20の隣接側面部26aに仮設定されているため、これら各現場付けパネル33A~33Cについては第1工数が大きな工数(a1)で算出される。また、各現場付けパネル33A~33Dのそれぞれについて仮固定位置から本取付位置までの移動距離が大きくなっているため、各現場付けパネル33A~33Dそれぞれについて第2工数が大きな工数として算出される。したがって、図7(b)の仮固定パターンでは、総工数Ktが大きな工数で算出されることになる。 In the temporary fixing pattern shown in FIG. 7B, since the temporary fixing positions of the on-site panels 33A to 33C are temporarily set on the adjacent side surface portions 26a of the building unit 20, the on-site panels 33A to 33C are temporarily set. The first man-hour is calculated as a large man-hour (a1). Further, since the moving distance from the temporarily fixed position to the main mounting position is large for each of the on-site panels 33A to 33D, the second man-hour is calculated as a large man-hour for each of the on-site panels 33A to 33D. Therefore, in the temporary fixing pattern of FIG. 7B, the total man-hours Kt is calculated with a large man-hour.

図7(c)に示す仮固定パターンでは、各現場付けパネル33A~33Dがそれぞれ建物ユニット20の非隣接側面部26bに仮設定されているため、各現場付けパネル33A~33Dの第1工数がそれぞれ小さな工数(a2)で算出される。ただ、その一方で、各現場付けパネル33A~33Dのそれぞれについて仮固定位置から本取付位置までの移動距離が大きくなっているため、各現場付けパネル33A~33Dそれぞれについて第2工数が大きな工数で算出される。したがって、図7(c)の仮固定パターンでは、総工数Ktが比較的大きな工数で算出されることになる。ただ、この仮固定パターンでは、総工数Ktが、上記図7(a)及び(b)の仮固定パターンよりも小さな工数で算出されることになる。 In the temporary fixing pattern shown in FIG. 7C, since the on-site panels 33A to 33D are temporarily set on the non-adjacent side surface portions 26b of the building unit 20, the first man-hours of the on-site panels 33A to 33D are increased. Each is calculated with a small man-hour (a2). However, on the other hand, since the moving distance from the temporarily fixed position to the main mounting position is large for each of the on-site panels 33A to 33D, the second man-hour is large for each of the on-site panels 33A to 33D. Calculated. Therefore, in the temporary fixing pattern of FIG. 7C, the total man-hours Kt is calculated with a relatively large man-hour. However, in this temporary fixing pattern, the total man-hours Kt is calculated with a smaller man-hour than the temporary fixing patterns of FIGS. 7A and 7B.

図7(d)に示す仮固定パターンでは、図7(c)の仮固定パターンと同様、各現場付けパネル33A~33Dがそれぞれ建物ユニット20の非隣接側面部26bに仮設定されているため、各現場付けパネル33A~33Dの第1工数がそれぞれ小さな工数(a2)として算出される。また、各現場付けパネル33A,33C,33Dについては仮固定位置から本取付位置までの移動距離が小さくなっているため、これら各現場付けパネル33A,33C,33Dについては第2工数が小さな工数として算出される。したがって、図7(d)の仮固定パターンでは、総工数Ktが小さな工数で算出されることになる。 In the temporary fixing pattern shown in FIG. 7 (d), as in the temporary fixing pattern of FIG. 7 (c), the on-site panels 33A to 33D are temporarily set on the non-adjacent side surface portions 26b of the building unit 20, respectively. The first man-hours of the on-site panels 33A to 33D are calculated as small man-hours (a2). Further, since the moving distance from the temporarily fixed position to the main mounting position is small for the on-site panels 33A, 33C, 33D, the second man-hours for each of the on-site panels 33A, 33C, 33D are small. Calculated. Therefore, in the temporary fixing pattern of FIG. 7D, the total man-hours Kt is calculated with a small man-hour.

以上より、図7(a)~(d)の各仮固定パターンのうちで、図7(d)の仮固定パターンにおいて、総工数Ktが最も小さくなる。また、これら図7(a)~(d)の仮固定パターン以外の仮固定パターンについては図示を省略しているが、それら図示を省略した仮固定パターンを含めても、図7(d)の仮固定パターンにおいて総工数Ktが最も小さくなる。したがって、本ステップS28では、図7(d)の仮固定パターンが最も総工数Ktが小さい仮固定パターンとして特定される。 From the above, among the temporary fixing patterns of FIGS. 7A to 7D, the total man-hours Kt is the smallest in the temporary fixing pattern of FIG. 7D. Further, although the temporary fixing patterns other than the temporary fixing patterns shown in FIGS. 7 (a) to 7 (d) are omitted from the illustration, even if the temporary fixing patterns not shown are included, the temporary fixing patterns shown in FIG. 7 (d) are included. The total man-hour Kt is the smallest in the temporary fixing pattern. Therefore, in this step S28, the temporary fixing pattern of FIG. 7D is specified as the temporary fixing pattern having the smallest total man-hours Kt.

ステップS29では、上記ステップS28で特定された仮固定パターンにしたがい仮設定された各現場付けパネル33A~33Dの仮固定位置をそれぞれ各現場付けパネル33A~33Dの仮固定位置として決定(本決定)する。その後、本処理(仮固定位置決定処理)を終了する。 In step S29, the temporary fixing positions of the on-site panels 33A to 33D temporarily set according to the temporary fixing pattern specified in step S28 are determined as the temporary fixing positions of the on-site panels 33A to 33D (final determination). do. After that, the main process (temporary fixed position determination process) is completed.

図5の説明に戻り、仮固定位置決定処理(ステップS17)の後のステップS18では、仮固定位置決定処理による処理の結果を表示部13に出力する出力処理を行う。これにより、表示部13には、上記処理の結果、すなわち仮固定位置決定処理により決定された各現場付けパネル33A~33Dの仮固定位置が表示される。なお、出力処理では、プリンタ等、表示部13以外の出力機器に処理結果を出力するようにしてもよい。その後、本処理を終了する。 Returning to the description of FIG. 5, in step S18 after the temporary fixed position determination process (step S17), an output process is performed in which the result of the process by the temporary fixed position determination process is output to the display unit 13. As a result, the display unit 13 displays the result of the above processing, that is, the temporary fixing positions of the on-site panels 33A to 33D determined by the temporary fixing position determination processing. In the output processing, the processing result may be output to an output device other than the display unit 13, such as a printer. After that, this process ends.

以上が、仮固定位置決定装置10により行われる制御処理についての説明である。 The above is the description of the control process performed by the temporary fixing position determining device 10.

ここで、本仮固定位置決定装置10は、過去に施工されたユニット式建物(詳しくは現場付けパネルを有するユニット式建物)について、施工現場において実際に発生した第1工数、第2工数及び第3工数に関する実績データ(工数実績データ)を蓄積する工数データベース15~17を備えている。これら各工数データベース15~17は上述したように記憶部14により構築されている。各工数データベース15~17のうち、第1工数データベース15には第1工数に関する実績データ(第1工数実績データ)が蓄積され、第2工数データベース16には第2工数に関する実績データ(第2工数実績データ)が蓄積され、第3工数データベース17には第3工数に関する実績データ(第3工数実績データ)が蓄積されている。 Here, the temporary fixing position determining device 10 uses the first man-hours, the second man-hours, and the second man-hours actually generated at the construction site for the unit-type building constructed in the past (specifically, the unit-type building having the on-site panel). It is equipped with man-hour databases 15 to 17 for accumulating actual data (man-hour actual data) related to three man-hours. Each of these man-hour databases 15 to 17 is constructed by the storage unit 14 as described above. Of the man-hour databases 15 to 17, actual data related to the first man-hour (first man-hour actual data) is accumulated in the first man-hour database 15, and actual data related to the second man-hour (second man-hour) is stored in the second man-hour database 16. Actual data) is accumulated, and actual data (third man-hour actual data) related to the third man-hour is accumulated in the third man-hour database 17.

本仮固定位置決定装置10では、第1工数データベース15に蓄積された第1工数実績データに基づき第1工数基準を作成し、第2工数データベース16に蓄積された第2工数実績データに基づき第2工数基準を作成し、第3工数データベース17に蓄積された第3工数実績データに基づき第3工数基準を作成することとしている。この場合、仮固定位置決定装置10は、例えば工数データベース15~17ごとに、その工数データベース15~17に蓄積された工数基準データを深層学習することで、各々の工数基準を作成する。そこで、以下においては、これら各工数基準の作成に関する処理の内容について順に説明する。 In the temporary fixed position determination device 10, the first man-hour standard is created based on the first man-hour actual data accumulated in the first man-hour database 15, and the first man-hour standard is created based on the second man-hour actual data accumulated in the second man-hour database 16. Two man-hour standards are created, and the third man-hour standard is created based on the third man-hour actual data accumulated in the third man-hour database 17. In this case, the temporary fixed position determining device 10 creates each man-hour standard by deep learning the man-hour reference data accumulated in the man-hour database 15 to 17 for each man-hour database 15 to 17, for example. Therefore, in the following, the contents of the processing related to the creation of each of these man-hour standards will be described in order.

まず、第1工数データベース15に蓄積された第1工数実績データに基づき、第1工数基準を作成する際の処理内容について説明する。 First, the processing content when creating the first man-hour standard will be described based on the first man-hour actual data accumulated in the first man-hour database 15.

第1工数データベース15には、過去に施工されたユニット式建物について、その現場付けパネルが仮固定された仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に生じた第1工数の実績データとが対応付けられた状態で第1工数実績データとして記憶されている。図10(a)には、その記憶された第1工数実績データが例示されている。図10(a)に示すように、第1工数実績データでは、仮固定位置に関する情報が、その仮固定位置が建物ユニット20の隣接側面部26a又は非隣接側面部26bのいずれにあるのかに関する情報(隣接側面情報)となっている。したがって、第1工数実績データとしては、仮固定位置が隣接側面部26aにある場合における第1工数の実績データと、仮固定位置が非隣接側面部26bにある場合における第1工数の実績データとがそれぞれ記憶されている。 In the first man-hour database 15, information on the temporary fixing position where the on-site panel was temporarily fixed for the unit type building constructed in the past, and the first that actually occurred due to the temporary fixing at the temporary fixing position. It is stored as the first man-hour actual data in a state of being associated with the actual man-hour data. FIG. 10A exemplifies the stored first man-hour actual data. As shown in FIG. 10A, in the first man-hour actual data, the information regarding the temporary fixing position is information regarding whether the temporary fixing position is on the adjacent side surface portion 26a or the non-adjacent side surface portion 26b of the building unit 20. (Adjacent side information). Therefore, as the first man-hour actual data, the actual data of the first man-hour when the temporary fixing position is on the adjacent side surface portion 26a and the actual data of the first man-hour when the temporary fixing position is on the non-adjacent side surface portion 26b. Are remembered respectively.

第1工数実績データは、ユーザによる操作部12の入力操作等に基づき、第1工数データベース15に記憶されるようになっている。詳しくは、第1工数実績データに含まれる仮固定位置情報(隣接側面情報)については、ユニット式建物の設計データ(詳しくは仮固定位置情報を含む設計データ)に基づき、制御部11により取得される。また、第1工数実績データに含まれる第1工数の実績データについては、ユーザによる操作部12の入力操作に基づき制御部11により取得される。そして、制御部11は、それら取得された仮固定位置情報及び第1工数(実績データ)を対応付けた状態で第1工数実績データとして第1工数データベース15に記憶する。このようにして、第1工数データベース15には第1工数実績データが蓄積されるようになっている。 The first man-hour actual data is stored in the first man-hour database 15 based on an input operation of the operation unit 12 by the user. Specifically, the temporary fixed position information (adjacent side surface information) included in the first man-hour actual data is acquired by the control unit 11 based on the design data of the unit type building (specifically, the design data including the temporary fixed position information). To. Further, the actual data of the first man-hours included in the actual data of the first man-hours is acquired by the control unit 11 based on the input operation of the operation unit 12 by the user. Then, the control unit 11 stores the acquired temporary fixed position information and the first man-hours (actual data) in the first man-hour database 15 as the first man-hours actual data in a state of associating them with each other. In this way, the first man-hour actual data is accumulated in the first man-hour database 15.

制御部11は、第1工数データベース15に蓄積された第1工数実績データに基づき、第1工数基準を作成する。第1工数基準は、上述したように、現場付けパネル33の仮固定位置が建物ユニット20の隣接側面部26aに設定される場合には第1工数をa1とし、現場付けパネル33の仮固定位置が建物ユニット20の非隣接側面部26bに設定される場合には第1工数をa2とする規定となっている(a1>a2)。そこで、制御部11により第1工数基準を作成するに際しては、次のような処理を行う。 The control unit 11 creates the first man-hour standard based on the first man-hour actual data accumulated in the first man-hour database 15. As described above, the first man-hour standard is that when the temporary fixing position of the site-mounted panel 33 is set on the adjacent side surface portion 26a of the building unit 20, the first man-hour is set to a1 and the temporary fixing position of the site-mounted panel 33 is set. Is set to the non-adjacent side surface portion 26b of the building unit 20, and the first man-hour is set to a2 (a1> a2). Therefore, when the control unit 11 creates the first man-hour standard, the following processing is performed.

まず、制御部11は、仮固定位置が隣接側面部26aにある場合における第1工数の実績データに基づき、仮固定位置が隣接側面部26aに設定された場合における第1工数a1(つまり第1工数基準における第1工数a1)を規定する。例えば、仮固定位置が隣接側面部26aにある場合における第1工数の各実績データの平均値を算出し、その算出した平均値を仮固定位置が隣接側面部26aに設定された場合の第1工数a1として規定する。 First, the control unit 11 has the first man-hour a1 (that is, the first man-hour a1) when the temporary fixing position is set to the adjacent side surface portion 26a based on the actual data of the first man-hours when the temporary fixing position is on the adjacent side surface portion 26a. The first man-hour a1) in the man-hour standard is specified. For example, the average value of each actual data of the first man-hours when the temporary fixing position is on the adjacent side surface portion 26a is calculated, and the calculated average value is the first when the temporary fixing position is set on the adjacent side surface portion 26a. It is defined as man-hours a1.

また、制御部11は、仮固定位置が非隣接側面部26bにある場合における第1工数の実績データに基づき、仮固定位置が非隣接側面部26bに設定された場合における第1工数a2(つまり第1工数基準における第1工数a2)を規定する。例えば、仮固定位置が非隣接側面部26bにある場合における第1工数の各実績データの平均値を算出し、その算出した平均値を仮固定位置が非隣接側面部26bに設定された場合の第1工数a2として規定する。 Further, the control unit 11 has the first man-hours a2 (that is, the first man-hours a2) when the temporary fixing position is set to the non-adjacent side surface portion 26b based on the actual data of the first man-hours when the temporary fixing position is on the non-adjacent side surface portion 26b. The first man-hour a2) in the first man-hour standard is specified. For example, when the temporary fixing position is on the non-adjacent side surface portion 26b, the average value of each actual data of the first man-hours is calculated, and the calculated average value is set to the non-adjacent side surface portion 26b. It is defined as the first man-hour a2.

このようにして、制御部11は、第1工数実績データに基づき第1工数基準を作成する。なお、第1工数基準の作成は、例えば、上述した仮固定位置を決定するための制御処理(図5)が開始される際に行うことが考えられる。 In this way, the control unit 11 creates the first man-hour standard based on the first man-hour actual data. It is conceivable that the first man-hour standard is created, for example, when the control process (FIG. 5) for determining the temporary fixing position described above is started.

続いて、第2工数データベース16に蓄積された第2工数実績データに基づき、第2工数基準を作成する際の処理内容について説明する。 Subsequently, the processing content when creating the second man-hour standard based on the second man-hour actual data accumulated in the second man-hour database 16 will be described.

第2工数データベース16には、過去に施工されたユニット式建物について、その現場付けパネルが仮固定された仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に生じた第2工数の実績データとが対応付けられた状態で第2工数実績データとして記憶されている。図10(b)には、その記憶された第2工数実績データが例示されている。図10(b)に示すように、第2工数実績データでは、仮固定位置に関する情報が、その(現場付けパネルの)仮固定位置から当該現場付けパネルの本取付位置までの移動距離に関する情報(移動距離情報)となっている。そのため、第2工数実績データは、その移動距離情報と第2工数の実績データとが対応付けられたデータとなっている。 In the second man-hour database 16, information on the temporary fixing position where the on-site panel was temporarily fixed for the unit type building constructed in the past, and the second that actually occurred due to the temporary fixing at the temporary fixing position. It is stored as the second man-hour actual data in a state of being associated with the actual man-hour data. FIG. 10B exemplifies the stored second man-hour actual data. As shown in FIG. 10B, in the second man-hour actual data, the information regarding the temporary fixing position is the information regarding the moving distance from the temporary fixing position (of the on-site panel) to the main mounting position of the on-site panel ( Travel distance information). Therefore, the second man-hour actual data is data in which the travel distance information and the actual data of the second man-hour are associated with each other.

第2工数実績データは、ユーザによる操作部12の入力操作等に基づき、第2工数データベース16に記憶されるようになっている。詳しくは、第2工数実績データに含まれる仮固定位置情報(移動距離情報)については、ユニット式建物の設計データ(詳しくは仮固定位置情報を含む設計データ)に基づき、制御部11により取得される。この場合、制御部11は、ユニット式建物の設計データに基づき、仮固定位置から本取付位置までの移動距離を算出し、その算出した移動距離を移動距離情報(つまりは仮固定位置情報)として取得する。また、第2工数実績データに含まれる第2工数の実績データについては、第1工数の実績データと同様、ユーザによる操作部12の入力操作に基づき制御部11により取得される。そして、制御部11は、それら取得された仮固定位置情報(移動距離情報)及び第2工数(実績データ)を対応付けた状態で第2工数実績データとして第2工数データベース16に記憶する。このようにして、第2工数データベース16には第2工数実績データが蓄積されるようになっている。 The second man-hour actual data is stored in the second man-hour database 16 based on an input operation of the operation unit 12 by the user. Specifically, the temporary fixed position information (moving distance information) included in the second man-hour actual data is acquired by the control unit 11 based on the design data of the unit type building (specifically, the design data including the temporary fixed position information). To. In this case, the control unit 11 calculates the moving distance from the temporary fixed position to the main mounting position based on the design data of the unit type building, and uses the calculated moving distance as the moving distance information (that is, the temporary fixed position information). get. Further, the actual data of the second man-hours included in the actual data of the second man-hours is acquired by the control unit 11 based on the input operation of the operation unit 12 by the user, similarly to the actual data of the first man-hours. Then, the control unit 11 stores the acquired temporary fixed position information (moving distance information) and the second man-hours (actual data) in the second man-hour database 16 as the second man-hours actual data in association with each other. In this way, the second man-hour actual data is accumulated in the second man-hour database 16.

制御部11は、第2工数データベース16に蓄積された第2工数実績データに基づき、第2工数基準を作成する。第2工数基準は、上述したように、仮固定位置から本取付位置までの移動距離Lと第2工数との関係を規定したものであり、詳しくは第2工数はα×L(αは定数)であると規定したものである。そこで、制御部11により第2工数基準を作成するに際しては、次のような処理を行う。 The control unit 11 creates a second man-hour standard based on the second man-hour actual data accumulated in the second man-hour database 16. As described above, the second man-hour standard defines the relationship between the moving distance L from the temporarily fixed position to the main mounting position and the second man-hour. Specifically, the second man-hour is α × L (α is a constant). ). Therefore, when the control unit 11 creates the second man-hour standard, the following processing is performed.

制御部11は、第2工数データベース16に記憶された各第2工数実績データごとに、第2工数(実績データ)を移動距離で除することにより距離係数を算出する。そして、制御部11は、それら算出した各第2工数実績データの距離係数の平均値を算出し、その算出した平均値を第2工数基準における上記αとして規定する。 The control unit 11 calculates the distance coefficient by dividing the second man-hour (actual data) by the moving distance for each second man-hour actual data stored in the second man-hour database 16. Then, the control unit 11 calculates the average value of the distance coefficients of each of the calculated second man-hour actual data, and defines the calculated average value as the above α in the second man-hour standard.

このようにして、制御部11は、第2工数実績データを基に第2工数基準を作成する。なお、第2工数基準の作成は、例えば、上述した仮固定位置を決定するための制御処理(図5)が開始される際に行うことが考えられる。 In this way, the control unit 11 creates the second man-hour standard based on the second man-hour actual data. It is conceivable that the second man-hour standard is created, for example, when the control process (FIG. 5) for determining the temporary fixing position described above is started.

続いて、第3工数データベース17に蓄積された第3工数実績データに基づき、第3工数基準を作成する際の処理内容について説明する。 Subsequently, the processing content when creating the third man-hour standard will be described based on the third man-hour actual data accumulated in the third man-hour database 17.

第3工数データベース17には、過去に施工されたユニット式建物について、建物ユニット内に設けられた干渉部材の種類に関する情報(干渉部材情報)と、その干渉部材と干渉する位置に現場付けパネルを仮固定したことに伴い生じた第3工数の実績データとが対応付けられた状態で第3工数実績データとして記憶されている。図10(c)には、その記憶された第3工数実績データが例示されている。 In the third man-hour database 17, information on the types of interference members provided in the building unit (interference member information) for unit-type buildings constructed in the past, and on-site panels at positions that interfere with the interference members are provided. It is stored as the third man-hour actual data in a state of being associated with the actual data of the third man-hour generated by the temporary fixing. FIG. 10C exemplifies the stored third man-hour actual data.

第3工数実績データは、ユーザによる操作部12の入力操作等に基づき、第3工数データベース17に記憶されるようになっている。詳しくは、第3工数実績データに含まれる干渉部材情報については、ユニット式建物の設計データ(詳しくは仮固定位置情報を含む設計データ)に基づき、制御部11により取得される。また、第3工数実績データに含まれる第3工数の実績データについては、ユーザによる操作部12の入力操作に基づき制御部11により取得される。そして、制御部11は、それら取得された干渉部材情報及び第3工数(実績データ)を対応付けた状態で第3工数実績データとして第3工数データベース17に記憶する。このようにして、第3工数データベース17には第3工数実績データが蓄積されるようになっている。 The third man-hour actual data is stored in the third man-hour database 17 based on an input operation of the operation unit 12 by the user. Specifically, the interference member information included in the third man-hour actual data is acquired by the control unit 11 based on the design data of the unit type building (specifically, the design data including the temporary fixed position information). Further, the actual data of the third man-hours included in the actual data of the third man-hours is acquired by the control unit 11 based on the input operation of the operation unit 12 by the user. Then, the control unit 11 stores the acquired interference member information and the third man-hours (actual data) in the third man-hour database 17 as the third man-hours actual data in a state of associating them with each other. In this way, the third man-hour actual data is accumulated in the third man-hour database 17.

制御部11は、第3工数データベース17に蓄積された第3工数実績データに基づき、第3工数基準を作成する。第3工数基準は、上述したように、干渉部材の種類ごとに第3工数を規定したものである。そこで、制御部11により第3工数基準を作成するに際しては、次のような処理を行う。 The control unit 11 creates a third man-hour standard based on the third man-hour actual data accumulated in the third man-hour database 17. As described above, the third man-hour standard defines the third man-hour for each type of interference member. Therefore, when the control unit 11 creates the third man-hour standard, the following processing is performed.

制御部11は、干渉部材の種類ごとに、第3工数の実績データの平均値を算出する。そして、制御部11は、干渉部材の種類ごとに、その算出した第3工数(実績データ)の平均値を第3工数基準における第3工数として規定する。例えば、干渉部材の種類がキッチン設備である場合には、キッチン設備における第3工数の各実績データの平均値を算出し、その算出した平均値をキッチン設備の第3工数として規定する。 The control unit 11 calculates the average value of the actual data of the third man-hours for each type of the interference member. Then, the control unit 11 defines the average value of the calculated third man-hours (actual data) for each type of the interference member as the third man-hour in the third man-hour standard. For example, when the type of the interfering member is kitchen equipment, the average value of each actual data of the third man-hours in the kitchen equipment is calculated, and the calculated average value is defined as the third man-hour of the kitchen equipment.

このようにして、制御部11は、第3工数実績データに基づき第3工数基準を作成する。なお、第3工数基準の作成は、例えば、上述した仮固定位置を決定するための制御処理(図5)が開始される際に行うことが考えられる。 In this way, the control unit 11 creates the third man-hour standard based on the third man-hour actual data. It is conceivable that the third man-hour standard is created, for example, when the control process (FIG. 5) for determining the temporary fixing position described above is started.

以上が、工数データベース15~17に蓄積された工数実績データに基づき、工数基準(第1工数基準~第3工数基準)を作成する処理についての説明である。 The above is the description of the process of creating the man-hour standard (first man-hour standard to third man-hour standard) based on the man-hour actual data accumulated in the man-hour databases 15 to 17.

以上、詳述した本実施形態の構成によれば、以下の優れた効果が得られる。 According to the configuration of the present embodiment described in detail above, the following excellent effects can be obtained.

建物30(対象建物に相当)の設計データ上において各現場付けパネル33A~33Dの仮固定位置が複数の配置パターン(仮固定パターン)で仮設定され、そして、各仮固定パターンごとに、その仮固定パターンで仮設定された各現場付けパネル33A~33Dの仮固定位置に基づき、それら各現場付けパネル33A~33Dについて仮固定に伴い生じる第1工数K1及び第2工数K2が算出される。すなわち、現場付けパネル33A~33Dを仮固定位置から取り外す際に要する工数(第1工数K1)と、その取り外した現場付けパネル33A~33Dを仮固定位置から本取付位置まで運ぶのに要する工数(第2工数K2)とがそれぞれ算出される。この場合、第1工数K1の算出に際しては、仮固定位置と第1工数との関係があらかじめ定められた第1工数基準が用いられ、第2工数K2の算出に際しては、仮固定位置と第2工数との関係があらかじめ定められた第2工数基準が用いられる。そして、このように算出された各仮固定パターンごとの各現場付けパネル33A~33Dの第1工数K1及び第2工数K2に基づき、各仮固定パターンのうちいずれかの仮固定パターンで仮設定された各現場付けパネル33A~33Dの仮固定位置がそれら各現場付けパネル33A~33Dの仮固定位置として決定(本決定)される。 Temporary fixing positions of the panels 33A to 33D attached to each site are temporarily set in a plurality of arrangement patterns (temporary fixing patterns) on the design data of the building 30 (corresponding to the target building), and the temporary fixing patterns are temporarily set for each temporary fixing pattern. Based on the temporary fixing positions of the on-site panels 33A to 33D temporarily set by the fixing pattern, the first man-hours K1 and the second man-hours K2 generated by the temporary fixing of the on-site panels 33A to 33D are calculated. That is, the man-hours required to remove the on-site panels 33A to 33D from the temporary fixing position (first man-hour K1) and the man-hours required to carry the removed on-site panels 33A to 33D from the temporary fixing position to the main mounting position (first man-hours K1). The second man-hours K2) and are calculated respectively. In this case, when calculating the first man-hour K1, the first man-hour standard in which the relationship between the temporarily fixed position and the first man-hour is predetermined is used, and when calculating the second man-hour K2, the temporarily fixed position and the second man-hour are calculated. The second man-hour standard, which has a predetermined relationship with man-hours, is used. Then, based on the first man-hours K1 and the second man-hours K2 of the on-site panels 33A to 33D for each temporary fixing pattern calculated in this way, one of the temporary fixing patterns is temporarily set. The temporary fixing positions of the on-site panels 33A to 33D are determined (finally determined) as the temporary fixing positions of the on-site panels 33A to 33D.

具体的には、各仮固定パターンごとに算出される各現場付けパネル33A~33Dの第1工数K1及び第2工数K2に基づき、各仮固定パターンごとに各現場付けパネル33A~33Dの第1工数K1及び第2工数K2を含む各工数(詳しくは、第3工数K3が生じている場合には第3工数K3も含む)が積算され、そして、その積算された積算値が各現場付けパネル33A~33Dの総工数Ktとして算出される。そして、このように各仮固定パターンごとに算出された総工数Ktのうち、総工数Ktが最小となる仮固定パターンが特定され、その特定された仮固定パターンにしたがって仮設定された各現場付けパネル33A~33Dの仮固定位置がそれら各現場付けパネル33A~33Dの仮固定位置として決定(本決定)される。これにより、複数の現場付けパネル33A~33Dを建物ユニット20に仮固定した状態に輸送する場合において、それら各現場付けパネル33A~33Dの仮固定に伴い生じる施工現場での作業について工数低減を大いに図ることが可能な仮固定位置を得ることが可能となる。 Specifically, based on the first man-hours K1 and the second man-hours K2 of the on-site panels 33A to 33D calculated for each temporary fixing pattern, the first of the on-site panels 33A to 33D for each temporary fixing pattern. Each man-hour including man-hour K1 and second man-hour K2 (specifically, including the third man-hour K3 when the third man-hour K3 occurs) is integrated, and the integrated integrated value is the integrated value attached to each site. It is calculated as the total man-hours Kt of 33A to 33D. Then, out of the total man-hours Kt calculated for each temporary fixing pattern in this way, the temporary fixing pattern that minimizes the total man-hours Kt is specified, and each site attachment temporarily set according to the specified temporary fixing pattern. The temporary fixing positions of the panels 33A to 33D are determined (finally determined) as the temporary fixing positions of the panels 33A to 33D attached to each site. As a result, when transporting a plurality of on-site panels 33A to 33D in a state of being temporarily fixed to the building unit 20, the man-hours for the work at the construction site caused by the temporary fixing of each of the on-site panels 33A to 33D are greatly reduced. It is possible to obtain a temporary fixed position that can be planned.

各仮固定パターンごとに、その仮固定パターンで仮設定された各現場付けパネル33A~33Dの仮固定位置に基づき、それら各現場付けパネル33A~33Dの第1工数K1及び第2工数K2が算出されることに加え、仮設定された現場付けパネル33A~33Dの仮固定位置に現場付けパネル33A~33Dと干渉する干渉部材(例えばキッチン設備45)が存在する場合には、その干渉部材を建物ユニット20内に組み込むのに要する第3工数K3が算出される。そして、このように算出された各仮固定パターンごとの各現場付けパネル33A~33Dの第1工数K1及び第2工数K2に加え、第3工数K3を加味して、各現場付けパネル33A~33Dの仮固定位置が決定(本決定)される。 For each temporary fixing pattern, the first man-hours K1 and the second man-hours K2 of the on-site panels 33A to 33D are calculated based on the temporary fixing positions of the on-site panels 33A to 33D temporarily set by the temporary fixing pattern. In addition to this, if there is an interfering member (for example, kitchen equipment 45) that interferes with the on-site panels 33A to 33D at the temporarily fixed position of the temporarily set on-site panels 33A to 33D, the interfering member is installed in the building. The third man-hour K3 required to be incorporated in the unit 20 is calculated. Then, in addition to the first man-hours K1 and the second man-hours K2 of the on-site panels 33A to 33D for each temporary fixing pattern calculated in this way, the third man-hours K3 are taken into consideration, and the on-site panels 33A to 33D are added. Temporary fixing position of is determined (final determination).

具体的には、各仮固定パターンごとに算出される各現場付けパネル33A~33Dの第1工数K1及び第2工数K2に加え、各仮固定パターンごとに干渉部材が存在する場合に算出される第3工数K3に基づき、各現場付けパネル33A~33Dの第1工数K1及び第2工数K2と、干渉部材に伴い生じた第3工数K3とが積算され、そして、その積算された積算値が各現場付けパネル33A~33Dの総工数Ktとして算出される。そして、このように各仮固定パターンごとに算出された総工数Ktのうち、総工数Ktが最小となる仮固定パターンが特定され、その特定された仮固定パターンにしたがって仮設定された各現場付けパネル33A~33Dの仮固定位置がそれら各現場付けパネル33A~33Dの仮固定位置として決定(本決定)される。この場合、第3工数を加味して現場付けパネル33A~33Dの仮固定位置が決定されるため、現場付けパネル33A~33Dの仮固定に伴い発生する施工現場での作業について工数低減を図ることが可能な仮固定位置をより確実に得ることができる。 Specifically, it is calculated when there is an interference member for each temporary fixing pattern in addition to the first man-hours K1 and the second man-hours K2 of the on-site panels 33A to 33D calculated for each temporary fixing pattern. Based on the third man-hour K3, the first man-hours K1 and the second man-hours K2 of the panels 33A to 33D attached to each site and the third man-hour K3 generated by the interfering member are integrated, and the integrated integrated value is calculated. It is calculated as the total man-hours Kt of each on-site panel 33A to 33D. Then, out of the total man-hours Kt calculated for each temporary fixing pattern in this way, the temporary fixing pattern that minimizes the total man-hours Kt is specified, and each site attachment temporarily set according to the specified temporary fixing pattern. The temporary fixing positions of the panels 33A to 33D are determined (finally determined) as the temporary fixing positions of the panels 33A to 33D attached to each site. In this case, since the temporary fixing position of the on-site panels 33A to 33D is determined in consideration of the third man-hours, the man-hours for the work at the construction site caused by the temporary fixing of the on-site panels 33A to 33D should be reduced. It is possible to more reliably obtain a temporary fixing position where the above is possible.

現場付けパネル33が建物ユニットの隣接側面部26aに仮固定される場合には、現場付けパネル33の取り外しの作業が建物ユニット20内で行われることになるため、その取り外しの作業に際しスペースの確保が困難となり、その作業に際し大きな工数(第1工数)を要することが考えられる。その一方、現場付けパネル33が非隣接側面部26bに仮固定される場合には、現場付けパネル33の取り外し作業を屋外で行うことが可能となるため、取り外し作業を行うためのスペースが広く確保され、その作業に際し工数(第1工数)の低減を図ることが可能となる。 When the site-mounted panel 33 is temporarily fixed to the adjacent side surface portion 26a of the building unit, the work of removing the site-mounted panel 33 is performed in the building unit 20, so that a space is secured for the removal work. It is conceivable that a large number of man-hours (first man-hour) will be required for the work. On the other hand, when the on-site panel 33 is temporarily fixed to the non-adjacent side surface portion 26b, the on-site panel 33 can be removed outdoors, so that a large space for removing the on-site panel 33 is secured. Therefore, it is possible to reduce the man-hours (first man-hours) in the work.

そこで、上記の実施形態では、こうした点を鑑み、第1工数の算出に用いる第1工数基準として、仮固定位置が隣接側面部26aにある場合には第1工数をa1とし、仮固定位置が非隣接側面部26bには第1工数をa1よりも小さいa2とする規定のものを用いている(a1>a2)。これにより、第1工数基準を用いて第1工数を算出するに際し、その第1工数を好適に算出することが可能となる。 Therefore, in the above embodiment, in view of these points, as the first man-hour reference used for calculating the first man-hour, when the temporary fixing position is on the adjacent side surface portion 26a, the first man-hour is set to a1 and the temporary fixing position is set. For the non-adjacent side surface portion 26b, the one specified that the first man-hour is a2 smaller than a1 is used (a1> a2). This makes it possible to preferably calculate the first man-hour when calculating the first man-hour using the first man-hour standard.

施工現場にて仮固定位置から取り外した現場付けパネル33をその仮固定位置から本取付位置まで運ぶのに要する作業工数(第2工数)は、仮固定位置から本取付位置までの移動距離に依存することが考えられる。そこで上記の実施形態では、こうした点に着目し、第2工数の算出に用いる第2工数基準として、仮固定位置から本取付位置までの移動距離と第2工数との関係を規定したものを用いている。詳しくは、第2工数基準は移動距離Lが大きいほど第2工数が大きくなる関係を規定したものとなっており、より詳しくは第2工数をα×Lと規定したものとなっている。 The work man-hours (second man-hours) required to carry the on-site panel 33 removed from the temporary fixing position at the construction site from the temporary fixing position to the main mounting position depend on the moving distance from the temporary fixing position to the main mounting position. It is conceivable to do. Therefore, in the above embodiment, paying attention to these points, as the second man-hour standard used for calculating the second man-hour, the one that defines the relationship between the moving distance from the temporarily fixed position to the main mounting position and the second man-hour is used. ing. Specifically, the second man-hour standard stipulates the relationship that the second man-hour increases as the moving distance L increases, and more specifically, the second man-hour is defined as α × L.

第2工数の算出に際しては、仮設定された仮固定位置から本取付位置までの移動距離が算出され、その算出された移動距離に基づき第2工数基準を用いて第2工数が算出される。これにより、第2工数基準を用いて第2工数を算出するにあたって、その第2工数を好適に算出することができる。 In calculating the second man-hour, the moving distance from the temporarily set temporary fixed position to the main mounting position is calculated, and the second man-hour is calculated using the second man-hour standard based on the calculated moving distance. As a result, when calculating the second man-hour using the second man-hour standard, the second man-hour can be preferably calculated.

第1工数データベース15には、過去に施工されたユニット式建物において、現場付けパネルが仮固定された仮固定位置ごとに、その仮固定位置に関する情報(具体的には隣接側面情報)と、その仮固定位置での仮固定に伴い実際に生じた第1工数の実績データとが対応付けられた状態で第1工数実績データとして記憶されている。そして、この第1工数データベース15に記憶された第1工数実績データに基づき、第1工数基準が作成される。この場合、第1工数基準を用いて第1工数を算出するにあたり、現場での実際の作業に即した工数を算出することが可能となる。 The first man-hour database 15 contains information on the temporary fixing position (specifically, adjacent side surface information) for each temporary fixing position where the on-site panel is temporarily fixed in the unit type building constructed in the past. It is stored as the first man-hour actual data in a state in which the actual data of the first man-hour actually generated by the temporary fixing at the temporary fixing position is associated with the actual data. Then, the first man-hour standard is created based on the first man-hour actual data stored in the first man-hour database 15. In this case, when calculating the first man-hour using the first man-hour standard, it is possible to calculate the man-hour according to the actual work at the site.

同様に、第2工数データベース16には、過去に施工されたユニット式建物において、現場付けパネルが仮固定された仮固定位置ごとに、その仮固定位置に関する情報(具体的には移動距離情報)と、その仮固定位置での仮固定に伴い実際に生じた第2工数の実績データとが対応付けられた状態で第2工数実績データとして記憶されている。そして、この第2工数データベース16に記憶された第2工数実績データに基づき、第2工数基準が作成される。この場合、第2工数基準を用いて第2工数を算出するにあたり、現場での実際の作業に即した工数を算出することが可能となる。 Similarly, in the second man-hour database 16, information on the temporary fixing position (specifically, moving distance information) for each temporary fixing position where the on-site panel is temporarily fixed in the unit type building constructed in the past). And the actual data of the second man-hours actually generated by the temporary fixing at the temporary fixing position are stored as the second man-hours actual data in a state of being associated with each other. Then, the second man-hour standard is created based on the second man-hour actual data stored in the second man-hour database 16. In this case, when calculating the second man-hours using the second man-hour standard, it is possible to calculate the man-hours according to the actual work at the site.

第3工数データベース17には、過去に施工されたユニット式建物について、建物ユニット内に設けられた干渉部材の種類に関する情報(干渉部材情報)と、その干渉部材と干渉する位置に現場付けパネルを仮固定したことに伴い生じた第3工数の実績データとが対応付けられた状態で第3工数実績データとして記憶されている。そして、この第3工数データベース17に記憶された第3工数実績データに基づき、第3工数基準が作成される。この場合、第3工数基準を用いて第3工数を算出するにあたり、現場での実際の作業に即した工数を算出することが可能となる。 In the third man-hour database 17, information on the types of interference members provided in the building unit (interference member information) for unit-type buildings constructed in the past, and on-site panels at positions that interfere with the interference members are provided. It is stored as the third man-hour actual data in a state of being associated with the actual data of the third man-hour generated by the temporary fixing. Then, the third man-hour standard is created based on the third man-hour actual data stored in the third man-hour database 17. In this case, when calculating the third man-hour using the third man-hour standard, it is possible to calculate the man-hour according to the actual work at the site.

本発明は上記実施形態に限らず、例えば次のように実施されてもよい。 The present invention is not limited to the above embodiment, and may be implemented as follows, for example.

(1)上記実施形態では、仮固定パターンごとに算出した各現場付けパネル33A~33Dの総工数Ktのうち、総工数Ktが最小となる仮固定パターンにしたがって仮設定された各現場付けパネル33A~33Dの仮固定位置をそれら各現場付けパネル33A~33Dの仮固定位置として決定(本決定)したが、各現場付けパネル33A~33Dの仮固定位置の決定は必ずしもこのように行う必要はない。 (1) In the above embodiment, of the total man-hours Kt of the on-site panels 33A to 33D calculated for each temporary fixing pattern, each on-site panel 33A temporarily set according to the temporary fixing pattern that minimizes the total man-hours Kt. The temporary fixing positions of the on-site panels 33A to 33D are determined as the temporary fixing positions of the on-site panels 33A to 33D (final determination), but the temporary fixing positions of the on-site panels 33A to 33D do not necessarily have to be determined in this way. ..

例えば、仮固定パターンごとに、各現場付けパネル33A~33Dの第1工数K1の総和を総第1工数として算出するとともに、各現場付けパネル33A~33Dの第2工数K2の総和を総第2工数として算出する。そして、それら算出した各仮固定パターンごとの総第1工数及び総第2工数に基づき、各現場付けパネル33A~33Dの仮固定位置を決定することが考えられる。具体的には、総第1工数が予め定められた第1基準値以下となっており、かつ、総第2工数が予め定められた第2基準値以下となっている仮固定パターンを特定し、その特定した仮固定パターンにしたがって仮設定された各現場付けパネル33A~33Dの仮固定位置をそれら各現場付けパネル33A~33Dの仮固定位置として決定(本決定)することが考えられる。この場合にも、現場付けパネル33A~33Dの仮固定に伴い発生する現場での作業について工数低減を図ることが可能な、仮固定位置を得ることができる。 For example, for each temporary fixing pattern, the total of the first man-hours K1 of the on-site panels 33A to 33D is calculated as the total first man-hours, and the total of the second man-hours K2 of the on-site panels 33A to 33D is the total second. Calculated as man-hours. Then, it is conceivable to determine the temporary fixing positions of the on-site panels 33A to 33D based on the total first man-hours and the total second man-hours for each temporary fixing pattern calculated. Specifically, a temporary fixing pattern in which the total first man-hours are equal to or less than the predetermined first reference value and the total second man-hours are equal to or less than the predetermined second reference value is specified. It is conceivable that the temporary fixing positions of the on-site panels 33A to 33D temporarily set according to the specified temporary fixing pattern are determined (finally determined) as the temporary fixing positions of the on-site panels 33A to 33D. Also in this case, it is possible to obtain a temporary fixing position capable of reducing the man-hours for the on-site work generated by the temporary fixing of the on-site panels 33A to 33D.

(2)上記実施形態では、第1工数基準として、現場付けパネル33の仮固定位置が、建物ユニット20の隣接側面部26aに設定される場合には第1工数をa1とし、非隣接側面部26bに設定される場合には第1工数をa2とする規定のものを用いたが(a1>a2)、これを変更してもよい。 (2) In the above embodiment, as the first man-hour reference, when the temporary fixing position of the site-mounted panel 33 is set on the adjacent side surface portion 26a of the building unit 20, the first man-hour is set to a1 and the non-adjacent side surface portion. When set to 26b, the one specified that the first man-hour is a2 was used (a1> a2), but this may be changed.

例えば、現場付けパネル33が建物ユニット20の非隣接側面部26bに仮固定される場合には、施工現場で現場付けパネル33を建物ユニット20から取り外す際、その取り外しの作業を屋外で詳しくは離し置き領域28で行うことが可能となる。ここで、この取り外しの作業は、離し置き領域28のスペースが広いほど作業がし易いと考えられ、ひいては、離し置き領域28のスペースが広いほど当該作業を行う際の工数つまりは第1工数を低減させることができると考えられる。そこで、かかる点に鑑み、第1工数基準として、現場付けパネル33の仮固定位置が、非隣接側面部26bに設定される場合には、第1工数と離し置き領域28の広さ(例えば離し置きの間隔)との関係を定めたものを用いるようにしてもよい。具体的には、第1工数は離し置きの間隔が大きいほど小さくなる旨を規定したものを用いることが考えられ、例えば第1工数はα(定数)/離し置きの間隔であると規定したものを用いることが考えられる。この場合、離し置き領域28の広さを考慮して第1工数を算出することができるため、第1工数の算出をより精度よく行うことができる。 For example, when the site-mounted panel 33 is temporarily fixed to the non-adjacent side surface portion 26b of the building unit 20, when the site-mounted panel 33 is removed from the building unit 20 at the construction site, the removal work is separated in detail outdoors. This can be done in the placement area 28. Here, it is considered that the wider the space of the separated area 28 is, the easier the work of this removal is, and the wider the space of the separated area 28 is, the more man-hours for performing the work, that is, the first man-hour. It is thought that it can be reduced. Therefore, in view of this point, when the temporary fixing position of the on-site panel 33 is set to the non-adjacent side surface portion 26b as the first man-hour standard, the size of the separated area 28 from the first man-hour (for example, separated). It is also possible to use the one that defines the relationship with the placement interval). Specifically, it is conceivable to use the first man-hour that stipulates that the larger the separation interval is, the smaller the first man-hour is, for example, the first man-hour is stipulated to be α (constant) / separation interval. Can be considered. In this case, since the first man-hours can be calculated in consideration of the size of the separated area 28, the first man-hours can be calculated more accurately.

(3)現場付けパネル33を仮固定位置から本取付位置まで運ぶ際に要する第2工数は、仮固定位置から本取付位置までの移動経路が屋内(建物ユニット20内)にあるか屋外にあるかによっても変わってくることが考えられる。例えば、移動経路が屋内にある場合には、現場付けパネル33を運ぶ際に、内装を傷付けないよう配慮しながら運ぶ等する必要が生じ、第2工数が大きくなることが考えられる。そこで、このような点を鑑み、第2工数基準を以下のように変更することが考えられる。 (3) The second man-hour required to transport the on-site panel 33 from the temporary fixing position to the main mounting position is that the movement path from the temporary fixing position to the main mounting position is indoors (inside the building unit 20) or outdoors. It is possible that it will change depending on the situation. For example, when the movement route is indoors, it is necessary to carry the on-site panel 33 while taking care not to damage the interior, which may increase the second man-hours. Therefore, in view of these points, it is conceivable to change the second man-hour standard as follows.

第2工数基準は、第2工数をα×L(Lは移動距離)であると、規定したものである。そこで、第2工数基準におけるαを、仮固定位置から本取付位置までの移動経路が屋内にある場合にはα1とし、屋外にある場合にはα1よりも小さいα2とする規定としてもよい。この場合、移動経路が屋内外のいずれにあるかも加味して第2工数を算出することができるため、第2工数の算出をより精度よく行うことができる。 The second man-hour standard defines that the second man-hour is α × L (L is the moving distance). Therefore, α in the second man-hour standard may be defined as α1 when the movement path from the temporary fixing position to the main mounting position is indoors, and α2 smaller than α1 when it is outdoors. In this case, since the second man-hour can be calculated in consideration of whether the movement route is indoors or outdoors, the calculation of the second man-hour can be performed more accurately.

(4)ところで、現場付けパネル33の仕様には、パネルの大きさ(サイズ)が異なる複数の仕様や、パネルの形状が異なる複数の仕様等がある。現場付けパネル33の仕様が異なれば、施工現場にて、現場付けパネル33を仮固定位置から取り外す際に要する第1工数や、その取り外した現場付けパネル33を本取付位置まで持ち運ぶ際に要する第2工数が変わってくると考えられる。例えば、現場付けパネル33の大きさが大きかったり、現場付けパネル33の形状がL字状をなしていたりする場合(例えば、現場付けパネル33が建物の入隅部や出隅部に配置されるL字のコーナパネルになっている場合)には、第1工数及び第2工数が大きくなることが考えられる。 (4) By the way, the specifications of the on-site panel 33 include a plurality of specifications having different panel sizes (sizes), a plurality of specifications having different panel shapes, and the like. If the specifications of the on-site panel 33 are different, the first man-hour required to remove the on-site panel 33 from the temporary fixing position at the construction site and the first man-hour required to carry the removed on-site panel 33 to the main mounting position are required. 2 Man-hours are expected to change. For example, when the size of the on-site panel 33 is large or the shape of the on-site panel 33 is L-shaped (for example, the on-site panel 33 is arranged at the inside corner or the outside corner of the building). In the case of an L-shaped corner panel), it is conceivable that the first man-hours and the second man-hours will increase.

そこで、上記の点に鑑み、現場付けパネル33の第1工数及び第2工数を算出するにあたり、仮設定された現場付けパネル33の仮固定位置に加え、現場付けパネル33の仕様に基づき、算出を行うようにしてもよい。この場合、現場付けパネル33の仕様ごとに工数の大小を示す係数を定めた係数基準を用いて、上記の算出を行うことが考えられる。この係数基準は、現場付けパネル33の仕様として、第1工数、第2工数が大きくなる仕様(例えばパネルサイズが大きい仕様)では係数が大きく設定されている一方、第1工数、第2工数が小さくなる仕様(例えばパネルサイズが小さい仕様)では係数が小さく設定されている。そして、現場付けパネル33の第1工数の算出に際しては、その現場付けパネル33の仕様に対応する係数を係数基準より取得し、その取得した係数に基づいて第1工数を算出する。例えば、現場付けパネル33の仮固定位置に基づき算出した第1工数(つまり上記実施形態のステップS41で算出される第1工数)に、上記取得した係数を掛け合わせることで第1工数K1を算出することが考えられる。この場合、現場付けパネル33の仕様を考慮して当該現場付けパネル33の第1工数を算出することができるため、第1工数の算出精度を高めることができる。なお、現場付けパネル33の第2工数を算出するに際にも、上記同様の手順で算出を行うことが可能である。 Therefore, in view of the above points, in calculating the first man-hours and the second man-hours of the on-site panel 33, the calculation is based on the specifications of the on-site panel 33 in addition to the temporarily set temporary fixing position of the on-site panel 33. May be done. In this case, it is conceivable to perform the above calculation using a coefficient standard that defines a coefficient indicating the magnitude of man-hours for each specification of the on-site panel 33. In this coefficient standard, as the specifications of the on-site panel 33, the coefficient is set to be large in the specifications in which the first man-hours and the second man-hours are large (for example, the specifications in which the panel size is large), while the first man-hours and the second man-hours are set. The coefficient is set small in the specifications that are small (for example, the specifications that the panel size is small). Then, when calculating the first man-hours of the on-site panel 33, the coefficient corresponding to the specifications of the on-site panel 33 is acquired from the coefficient reference, and the first man-hour is calculated based on the acquired coefficient. For example, the first man-hour K1 is calculated by multiplying the first man-hour calculated based on the temporarily fixed position of the on-site panel 33 (that is, the first man-hour calculated in step S41 of the above embodiment) by the obtained coefficient. It is conceivable to do. In this case, since the first man-hours of the site-mounted panel 33 can be calculated in consideration of the specifications of the site-mounted panel 33, the calculation accuracy of the first man-hours can be improved. When calculating the second man-hours of the on-site panel 33, the calculation can be performed by the same procedure as described above.

(5)上記実施形態では、現場付けパネル33Xの工数算出処理(ステップS24)に際し、第1工数K1及び第2工数K2に加えて、干渉部材が存在する場合には第3工数K3を算出し、それら算出した各工数K1~K3の総和をパネル工数K(X)として算出したが、これを変更して、工数算出処理に際し、第3工数K3については考慮せず、第1工数K1及び第2工数K2の総和をパネル工数K(X)として算出するようにしてもよい。この場合、現場付けパネル33の仮固定位置の決定に際し、第3工数K3が加味されないことになるものの、その場合にも、第1工数K1及び第2工数K2に基づいて、工数低減を図ることが可能な現場付けパネル33の仮固定位置を決定することが可能となる。 (5) In the above embodiment, in the man-hour calculation process (step S24) of the on-site panel 33X, in addition to the first man-hour K1 and the second man-hour K2, the third man-hour K3 is calculated when an interfering member is present. , The sum of each of the calculated man-hours K1 to K3 was calculated as the panel man-hour K (X), but this was changed and the third man-hour K3 was not considered in the man-hour calculation process, and the first man-hour K1 and the first man-hour K1 and the first man-hour K3 were calculated. The sum of the two man-hours K2 may be calculated as the panel man-hours K (X). In this case, the third man-hour K3 is not taken into consideration when determining the temporary fixing position of the on-site panel 33, but even in that case, the man-hours should be reduced based on the first man-hour K1 and the second man-hour K2. It is possible to determine the temporary fixing position of the on-site panel 33 that can be used.

(6)上記実施形態では、第1工数データベース15に蓄積された第1工数実績データに基づき第1工数基準を作成したが、第1工数基準は必ずしも工数実績データに基づき作成する必要はない。例えば、現場付けパネル33の仮固定位置が建物ユニット20の隣接側面部26aに設定される場合と、非隣接側面部26bに設定される場合とでそれぞれ第1工数がどれくらいになるかを予め見積もっておき、それら見積もった第1工数の見積もり値に基づき、第1工数基準を作成するようにしてもよい。この場合、作成した第1工数基準を操作部12の入力に基づき設定するようにすればよい。なお、第2工数基準及び第3工数基準の作成についても同様に、工数の見積もり値に基づき作成するようにしてもよい。 (6) In the above embodiment, the first man-hour standard is created based on the first man-hour actual data accumulated in the first man-hour database 15, but the first man-hour standard does not necessarily have to be created based on the man-hour actual data. For example, it is estimated in advance how much the first man-hours will be when the temporary fixing position of the on-site panel 33 is set on the adjacent side surface portion 26a of the building unit 20 and when it is set on the non-adjacent side surface portion 26b. Then, the first man-hour standard may be created based on the estimated values of the first man-hours estimated. In this case, the created first man-hour standard may be set based on the input of the operation unit 12. Similarly, the second man-hour standard and the third man-hour standard may be created based on the estimated value of the man-hours.

(7)上記実施形態では、建物30に含まれる複数の現場付けパネル33A~33Dの仮固定位置を決定する場合について説明したが、例えば建物が現場付けパネルを1つしか有していない場合には、その一の現場付けパネルが建物ユニット20に仮固定されて輸送されることになる。そこで、そのような場合に、その一の現場付けパネルの仮固定位置を仮固定位置決定装置10を用いて決定するようにしてもよい。この場合、その一の現場付けパネルについて、その仮固定位置を複数箇所に仮設定し、それら仮設定された各仮固定位置ごとに工数算出処理(ステップS24)を実施するようにすることが考えられる。そして、それら各仮固定位置ごとに算出されるパネル工数K(X)を比較して、パネル工数K(X)が最小となる仮固定位置を当該現場付けパネルの仮固定位置として決定(本決定)することが考えられる。この場合にも、上記一の現場付けパネルの仮固定に伴い発生する施工現場での作業について工数低減を図ることが可能な仮固定位置を得ることができる。 (7) In the above embodiment, the case where the temporary fixing positions of the plurality of on-site panels 33A to 33D included in the building 30 are determined has been described. For example, when the building has only one on-site panel. One of the on-site panels will be temporarily fixed to the building unit 20 and transported. Therefore, in such a case, the temporary fixing position of the one on-site panel may be determined by using the temporary fixing position determining device 10. In this case, it is conceivable to temporarily set the temporary fixing positions of the one on-site panel at a plurality of locations and perform the man-hour calculation process (step S24) for each of the temporarily set temporary fixing positions. Be done. Then, the panel man-hours K (X) calculated for each of the temporary fixing positions are compared, and the temporary fixing position where the panel man-hour K (X) is minimized is determined as the temporary fixing position of the on-site panel (final decision). ) Is conceivable. Also in this case, it is possible to obtain a temporary fixing position capable of reducing the man-hours for the work at the construction site that occurs due to the temporary fixing of the above-mentioned one on-site panel.

(8)上記実施形態の建物30では、離し置きされた各建物ユニット20A,20B(20C,20D)の間の離し置き領域28に現場付けパネル33が設けられていたが、現場付けパネル33が離し置き領域28以外に設けられることもある。例えば、建物ユニット20から屋外側に延びる袖壁を備えた建物では、袖壁が建物ユニット20の側面部26とは異なる所定の位置に設けられるため、袖壁を構成する外壁パネルが施工現場において上記所定位置に取り付けられることになる。そのため、この場合にも、施工現場で取り付けられる外壁パネル(つまり現場付けパネル)を製造工場にて建物ユニット20に仮固定して輸送することが考えられる。したがって、かかる場合にも、現場付けパネルの仮固定位置を決定するにあたり仮固定位置決定装置10を用いることができる。 (8) In the building 30 of the above embodiment, the site-mounted panel 33 is provided in the separated area 28 between the separated building units 20A and 20B (20C, 20D), but the site-mounted panel 33 is provided. It may be provided in a region other than the separated area 28. For example, in a building having a sleeve wall extending from the building unit 20 to the outdoor side, the sleeve wall is provided at a predetermined position different from the side surface portion 26 of the building unit 20, so that the outer wall panel constituting the sleeve wall is provided at the construction site. It will be installed in the above-mentioned predetermined position. Therefore, in this case as well, it is conceivable that the outer wall panel (that is, the panel attached to the site) attached at the construction site is temporarily fixed to the building unit 20 at the manufacturing factory and transported. Therefore, even in such a case, the temporary fixing position determining device 10 can be used to determine the temporary fixing position of the on-site panel.

10…仮固定位置決定システムとしての仮固定位置決定装置、11…制御部、14…記憶部、15…第1工数データベース、16…第2工数データベース、17…第3工数データベース、20…建物ユニット、26…側面部、26a…隣接側面部、26b…非隣接側面部、30…対象建物としての建物、33…現場付けパネル、45…干渉部材としてのキッチン設備。 10 ... Temporary fixed position determination device as a temporary fixed position determination system, 11 ... Control unit, 14 ... Storage unit, 15 ... 1st manpower database, 16 ... 2nd manpower database, 17 ... 3rd manpower database, 20 ... Building unit , 26 ... Side surface, 26a ... Adjacent side surface, 26b ... Non-adjacent side surface, 30 ... Building as target building, 33 ... On-site panel, 45 ... Kitchen equipment as interference member.

Claims (7)

製造工場で製造される複数の建物ユニットを備えて構成されるとともに、外壁パネルとして、施工現場において前記建物ユニットとは異なる所定の取付位置に取り付けられる現場付けパネルを有するユニット式建物において、その現場付けパネルを前記製造工場において前記建物ユニットに仮固定しその仮固定状態で前記施工現場へ輸送する場合に用いられるものであって、
前記現場付けパネルを前記各建物ユニットのうちいずれの建物ユニットのどの位置に仮固定するか、その仮固定位置を決定する仮固定位置決定システムであって、
前記施工現場において前記各建物ユニットを所定の設置位置に設置した後、前記現場付けパネルの前記仮固定に伴い発生する作業の工数として、
前記現場付けパネルを前記仮固定位置から取り外すのに要する第1工数と、
前記取り外した前記現場付けパネルを前記仮固定位置から前記所定の取付位置まで運ぶのに要する第2工数と、があり、
前記仮固定位置と前記第1工数との関係を示す第1工数基準が予め定められており、
前記仮固定位置と前記第2工数との関係を示す第2工数基準が予め定められており、
前記ユニット式建物からなる所定の対象建物について、その設計データを取得する取得手段と、
その取得した前記対象建物の設計データに基づき、前記対象建物に含まれる前記現場付けパネルの前記仮固定位置を決定する仮固定位置決定手段と、を備え、
前記仮固定位置決定手段は、
前記対象建物の設計データ上において前記現場付けパネルの前記仮固定位置を複数箇所に仮設定する仮設定手段と、
前記仮設定された前記仮固定位置ごとに、その仮設定された仮固定位置に基づき、当該仮固定位置に前記現場付けパネルが仮固定された場合に生じる前記第1工数及び前記第2工数をそれぞれ前記第1工数基準及び前記第2工数基準を用いて算出する工数算出手段と、を有し、
前記工数算出手段により算出された前記仮設定された各仮固定位置ごとの前記第1工数及び前記第2工数に基づき、前記仮設定された各仮固定位置のうちいずれかを当該現場付けパネルの前記仮固定位置として決定することを特徴とする仮固定位置決定システム。
In a unit-type building having a plurality of building units manufactured in a manufacturing factory and having a site-mounted panel mounted at a predetermined mounting position different from the building unit at a construction site as an outer wall panel, the site. It is used when the attached panel is temporarily fixed to the building unit in the manufacturing factory and transported to the construction site in the temporarily fixed state.
It is a temporary fixing position determination system that determines at which position of which building unit the on-site panel is temporarily fixed, and the temporary fixing position thereof.
After installing each building unit at a predetermined installation position at the construction site, the man-hours for the work generated by the temporary fixing of the on-site panel are as the man-hours.
The first man-hours required to remove the on-site panel from the temporary fixing position, and
There is a second man-hour required to carry the removed on-site panel from the temporary fixing position to the predetermined mounting position.
The first man-hour standard indicating the relationship between the temporary fixing position and the first man-hour is predetermined.
A second man-hour standard indicating the relationship between the temporarily fixed position and the second man-hour is predetermined.
An acquisition means for acquiring design data of a predetermined target building composed of the unit type buildings, and
Based on the acquired design data of the target building, the temporary fixing position determining means for determining the temporary fixing position of the site-mounted panel included in the target building is provided.
The temporary fixing position determining means
Temporary setting means for temporarily setting the temporary fixing positions of the on-site panel at a plurality of locations on the design data of the target building, and
For each of the temporarily set temporary fixing positions, based on the temporarily set temporary fixing position, the first man-hours and the second man-hours that occur when the on-site panel is temporarily fixed at the temporary fixing position are calculated. Each has a man-hour calculation means for calculating using the first man-hour standard and the second man-hour standard.
Based on the first man-hours and the second man-hours for each of the temporarily set temporary fixing positions calculated by the man-hour calculation means, any one of the temporarily set temporary fixing positions is set on the on-site panel. A temporary fixing position determining system, characterized in that the temporary fixing position is determined.
前記仮固定位置決定手段は、前記対象建物に含まれる複数の前記現場付けパネルについて前記仮固定位置を決定するものであり、
前記仮設定手段は、前記各現場付けパネルの前記仮固定位置を複数の配置パターンで仮設定するものであり、
前記工数算出手段は、前記各配置パターンごとに、前記配置パターンで仮設定された前記各現場付けパネルの前記仮固定位置に基づき、それら各現場付けパネルについて前記仮固定に伴い生じる前記第1工数及び前記第2工数をそれぞれ算出し、
前記仮固定位置決定手段は、前記工数算出手段により算出された前記各配置パターンごとの前記各現場付けパネルの前記第1工数及び前記第2工数に基づき、前記各配置パターンのうちいずれかの配置パターンで仮設定された前記各現場付けパネルの前記仮固定位置をそれら各現場付けパネルの前記仮固定位置として決定することを特徴とする請求項1に記載の仮固定位置決定システム。
The temporary fixing position determining means determines the temporary fixing position for a plurality of the on-site panels included in the target building.
The temporary setting means temporarily sets the temporary fixing position of each on-site panel with a plurality of arrangement patterns.
The man-hour calculation means is based on the temporary fixing position of each of the on-site panels temporarily set in the arrangement pattern for each of the arrangement patterns, and the first man-hours generated by the temporary fixing of each of the on-site panels. And the second man-hours are calculated respectively,
The temporary fixing position determining means arranges any one of the arrangement patterns based on the first man-hours and the second man-hours of the on-site panel for each arrangement pattern calculated by the man-hour calculation means. The temporary fixing position determination system according to claim 1, wherein the temporary fixing positions of the on-site mounting panels temporarily set by a pattern are determined as the temporary fixing positions of the on-site mounting panels.
前記施工現場において前記現場付けパネルの前記仮固定に伴い発生する作業の工数として、
前記仮固定位置が設定された前記建物ユニット内に、その仮固定位置に仮固定される前記現場付けパネルと干渉する干渉部材が存在する場合に、当該現場付けパネルを前記仮固定位置から取り外した後、前記干渉部材を前記建物ユニット内に組み込む組み込み作業に要する第3工数があり、
前記工数算出手段は、
前記対象建物の設計データに基づき、前記仮設定された前記仮固定位置に前記現場付けパネルが仮固定された場合に、当該現場付けパネルと干渉する前記干渉部材が当該仮固定位置が仮設定された前記建物ユニット内に存在するか否かを判定する干渉部材判定手段と、
その干渉部材判定手段により前記干渉部材が存在すると判定された場合に、当該干渉部材について生じる前記第3工数を算出する第3工数算出手段と、を備え、
前記仮固定位置決定手段は、前記第3工数算出手段により算出された前記第3工数を加味して、前記現場付けパネルの前記仮固定位置を決定することを特徴とする請求項1又は2に記載の仮固定位置決定システム。
As the number of man-hours required for the temporary fixing of the on-site panel at the construction site.
When there is an interference member that interferes with the on-site panel temporarily fixed at the temporary fixing position in the building unit in which the temporary fixing position is set, the on-site panel is removed from the temporary fixing position. Later, there is a third man-hour required for the assembling work of incorporating the interference member into the building unit.
The man-hour calculation means
When the site-mounted panel is temporarily fixed at the temporarily set temporary fixing position based on the design data of the target building, the temporary fixing position of the interference member that interferes with the site-mounted panel is temporarily set. Interference member determination means for determining whether or not it exists in the building unit,
A third man-hour calculation means for calculating the third man-hours generated for the interference member when the interference member determining means determines that the interference member exists is provided.
The temporary fixing position determining means according to claim 1 or 2, wherein the temporary fixing position of the on-site panel is determined in consideration of the third man-hour calculated by the third man-hour calculation means. The described temporary fixing position determination system.
前記第1工数基準は、前記仮固定位置が、前記建物ユニットの側面部のうち、他の前記建物ユニットと隣接する隣接側面部に設定される場合と、他の前記建物ユニットと隣接しない非隣接側面部に設定される場合とについてそれぞれ前記第1工数をいずれとするのか規定したものであることを特徴とする請求項1乃至3のいずれか一項に記載の仮固定位置決定システム。 The first man-hour standard is that the temporary fixing position is set on the adjacent side surface portion of the side surface portion of the building unit that is adjacent to the other building unit, and the non-adjacent side portion that is not adjacent to the other building unit. The temporary fixing position determination system according to any one of claims 1 to 3, wherein the first man-hours are specified for each of the cases where the side surface portion is set. 前記第2工数基準は、前記各建物ユニットが所定の設置位置に設置された状態における前記仮固定位置から前記所定の取付位置までの移動距離と前記第2工数との関係を規定したものであり、
前記工数算出手段は、
前記対象建物の設計データに基づき、その対象建物において、前記仮設定手段により仮設定された前記仮固定位置から前記所定の取付位置までの前記移動距離を算出する移動距離算出手段と、
その算出された前記移動距離に基づき、当該仮固定位置に前記現場付けパネルが仮固定された場合に生じる前記第2工数を前記第2工数基準を用いて算出する第2工数算出手段と、を有することを特徴とする請求項1乃至4のいずれか一項に記載の仮固定位置決定システム。
The second man-hour standard defines the relationship between the moving distance from the temporary fixing position to the predetermined mounting position and the second man-hour in a state where each building unit is installed at a predetermined installation position. ,
The man-hour calculation means
Based on the design data of the target building, the moving distance calculating means for calculating the moving distance from the temporarily fixed position temporarily set by the temporary setting means to the predetermined mounting position in the target building, and
Based on the calculated movement distance, a second man-hour calculation means for calculating the second man-hour generated when the on-site panel is temporarily fixed at the temporary fixing position using the second man-hour reference. The temporary fixed position determination system according to any one of claims 1 to 4, wherein the system has.
過去に施工された前記ユニット式建物について、前記現場付けパネルが仮固定された前記仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に発生した前記第1工数のデータとが対応付けられた状態で第1工数実績データとして記憶されている第1工数データベースと、
その第1工数データベースに記憶された前記第1工数実績データに基づき、前記第1工数基準を作成する第1工数基準作成手段と、
を備えることを特徴とする請求項1乃至5のいずれか一項に記載の仮固定位置決定システム。
For the unit-type building constructed in the past, the information on the temporary fixing position where the on-site panel was temporarily fixed and the data of the first man-hours actually generated by the temporary fixing at the temporary fixing position are obtained. The first man-hour database stored as the first man-hour actual data in the associated state,
A first man-hour standard creation means for creating the first man-hour standard based on the first man-hour actual data stored in the first man-hour database, and
The temporary fixed position determination system according to any one of claims 1 to 5, wherein the temporary fixing position determination system is provided.
過去に施工された前記ユニット式建物について、前記現場付けパネルが仮固定された前記仮固定位置に関する情報と、その仮固定位置での仮固定に伴い実際に発生した前記第2工数のデータとが対応付けられた状態で第2工数実績データとして記憶されている第2工数データベースと、
その第2工数データベースに記憶された前記第2工数実績データに基づき、前記第2工数基準を作成する第2工数基準作成手段と、
を備えることを特徴とする請求項1乃至6のいずれか一項に記載の仮固定位置決定システム。
For the unit type building constructed in the past, the information on the temporary fixing position where the on-site panel was temporarily fixed and the data of the second man-hour actually generated by the temporary fixing at the temporary fixing position are obtained. The second man-hour database stored as the second man-hour actual data in the associated state,
A second man-hour standard creation means for creating the second man-hour standard based on the second man-hour actual data stored in the second man-hour database, and
The temporary fixed position determination system according to any one of claims 1 to 6, wherein the temporary fixing position determination system is provided.
JP2019002956A 2019-01-10 2019-01-10 Temporary fixing position determination system Active JP7103958B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019002956A JP7103958B2 (en) 2019-01-10 2019-01-10 Temporary fixing position determination system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019002956A JP7103958B2 (en) 2019-01-10 2019-01-10 Temporary fixing position determination system

Publications (2)

Publication Number Publication Date
JP2020111942A JP2020111942A (en) 2020-07-27
JP7103958B2 true JP7103958B2 (en) 2022-07-20

Family

ID=71667621

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019002956A Active JP7103958B2 (en) 2019-01-10 2019-01-10 Temporary fixing position determination system

Country Status (1)

Country Link
JP (1) JP7103958B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114059841B (en) * 2021-11-25 2023-07-21 中化学建设投资集团安徽工程有限公司 Building encloses fender with sound absorbing effect

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299728A (en) 2005-04-25 2006-11-02 Asahi Kasei Homes Kk Construction order determining system of building
JP2011202439A (en) 2010-03-26 2011-10-13 Toyota Home Kk Building unit
JP2015055123A (en) 2013-09-13 2015-03-23 ミサワホーム株式会社 Design method for unit type building, and manufacturing method for building unit
JP2015088175A (en) 2014-08-26 2015-05-07 宮川工機株式会社 Application support system for lumber precut factory
JP2015225350A (en) 2014-05-26 2015-12-14 株式会社ハウスギア Supply control system of joint metal, control program thereof, and record medium

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299728A (en) 2005-04-25 2006-11-02 Asahi Kasei Homes Kk Construction order determining system of building
JP2011202439A (en) 2010-03-26 2011-10-13 Toyota Home Kk Building unit
JP2015055123A (en) 2013-09-13 2015-03-23 ミサワホーム株式会社 Design method for unit type building, and manufacturing method for building unit
JP2015225350A (en) 2014-05-26 2015-12-14 株式会社ハウスギア Supply control system of joint metal, control program thereof, and record medium
JP2015088175A (en) 2014-08-26 2015-05-07 宮川工機株式会社 Application support system for lumber precut factory

Also Published As

Publication number Publication date
JP2020111942A (en) 2020-07-27

Similar Documents

Publication Publication Date Title
CN108763710A (en) A kind of assembled architecture forward direction Deepen Design method based on BIM
WO2010000017A1 (en) System and method for designing a building
KR20150121699A (en) Method and system using standardized structural components
JP7103958B2 (en) Temporary fixing position determination system
CN115879189A (en) Underground garage ventilation system design method based on BIM platform and related equipment
US9342634B2 (en) Dormer calculator
JP5002376B2 (en) Design simulation system, design simulation method, design simulation program, and recording medium
JP4940324B2 (en) Server room floor load resistance diagnosis system
JP4629594B2 (en) Module evaluation method and apparatus
JP4301705B2 (en) Housing structure design method and structure design apparatus
JP7107781B2 (en) Design support system
JP4839246B2 (en) Building structural design support system
JP4653414B2 (en) Structural downdraft creation processing device
JP2007026085A (en) Method for supporting designing of layout of plant
JP4215350B2 (en) Load-bearing wall placement method used for computer-based building structural calculations
JP2002024309A (en) Automatic route searching method for piping
JP7064964B2 (en) Design support system
JP2014070436A (en) Frame determination method and steel construction building
JPH0944555A (en) Scaffolding planning system
JPH11232320A (en) Design support system for steel frame structure
JP5220823B2 (en) Module evaluation method and apparatus
JP4760651B2 (en) Basic building quantity analysis system, building basic quantity analysis method, and computer program
JPH10326296A (en) Cad system for preparing plane drawing of unit type building
JP5160109B2 (en) Arrangement method of shaft assembly
JP2022141269A (en) Design support device and design support program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210728

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220629

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220705

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220707

R150 Certificate of patent or registration of utility model

Ref document number: 7103958

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150