JP6464535B2 - Mobile work scaffold - Google Patents

Mobile work scaffold Download PDF

Info

Publication number
JP6464535B2
JP6464535B2 JP2017059241A JP2017059241A JP6464535B2 JP 6464535 B2 JP6464535 B2 JP 6464535B2 JP 2017059241 A JP2017059241 A JP 2017059241A JP 2017059241 A JP2017059241 A JP 2017059241A JP 6464535 B2 JP6464535 B2 JP 6464535B2
Authority
JP
Japan
Prior art keywords
rails
formwork
scaffold
rail
mobile work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017059241A
Other languages
Japanese (ja)
Other versions
JP2018162567A (en
Inventor
大 森田
大 森田
元気 吉田
元気 吉田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP2017059241A priority Critical patent/JP6464535B2/en
Publication of JP2018162567A publication Critical patent/JP2018162567A/en
Application granted granted Critical
Publication of JP6464535B2 publication Critical patent/JP6464535B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Description

本発明は、コンクリート用型枠に設置され、主に表面の均し作業を含むコンクリート打設工程において使用される移動式作業足場に関する。   The present invention relates to a mobile work scaffold which is installed in a concrete formwork and used mainly in a concrete placing process including surface leveling work.

従来、コンクリートの打設工程においては、コンクリート用型枠の外周部に足場(以下、外周固定足場という)を設置し、作業員が外周固定足場上でバイブレータを用いた締固め作業や打設されたコンクリートの均し作業を行っていた(例えば、特許文献1を参照)。   Conventionally, in the concrete placing process, a scaffold (hereinafter referred to as an outer periphery fixed scaffold) is installed on the outer periphery of the concrete formwork, and a worker performs compaction work or placement using a vibrator on the outer periphery fixed scaffold. The concrete was leveled (see, for example, Patent Document 1).

特開2005−127079号公報JP 2005-127079 A

しかしながら、コンクリート打設区画の平面積が大きく、外周固定足場からコンクリート打設区画中央部までの距離が大きい場合、作業員が外周固定足場上で作業を行うことが困難であって、作業員が型枠内に入って作業をしなければならない場合があった。   However, if the concrete placement section has a large flat area and the distance from the outer periphery fixed scaffold to the center of the concrete placement section is large, it is difficult for the worker to perform work on the outer periphery fixed scaffold. In some cases, it was necessary to work inside the formwork.

一方、型枠内に鉄筋を配設する鉄筋コンクリート構造物の場合には、作業を行う範囲の鉄筋上に足場板を仮固定し、作業が終了した範囲の足場を随時撤去しつつ作業を行う方法が一般に用いられているが、この方法では、足場板の設置及び撤去に手間がかかるという問題があった。   On the other hand, in the case of a reinforced concrete structure in which reinforcing bars are placed in the formwork, a method of working while temporarily fixing the scaffolding plate on the reinforcing bars in the working range and removing the scaffolding in the finished range as needed However, this method has a problem that it takes time and labor to install and remove the scaffolding board.

また、防波堤上部工等のように無筋コンクリート構造物の場合には、型枠内に鉄筋が配置されておらず、足場板を設置することができないという問題があった。   In addition, in the case of an unreinforced concrete structure such as a breakwater superstructure, there is a problem that the reinforcing bars are not arranged in the formwork and the scaffolding plate cannot be installed.

そこで、本発明は、このような従来の問題に鑑み、コンクリート打設用の型枠上を移動できる移動式作業足場の提供を目的としてなされたものである。   Therefore, in view of such a conventional problem, the present invention has been made for the purpose of providing a mobile work scaffold that can move on a concrete casting formwork.

上述の如き従来の問題を解決するための請求項1に記載の発明の特徴は、対向する堰板を有する型枠上を移動可能な移動式作業足場であって、両端部が型枠に支持され、前記対向する堰板間に跨って架設される互いに平行な複数のレールと、該複数のレール上に移動可能に架設された架台と、隣り合う前記レール間に配置され、前記対向する堰板間に架設されるレール間隔保持材とを備えている移動式作業足場にある。 The feature of the invention according to claim 1 for solving the conventional problems as described above is a movable work scaffold that is movable on a mold having opposing weir plates, and both ends are supported by the mold. And a plurality of parallel rails installed between the opposing weir plates, a pedestal movably installed on the plurality of rails, and the adjacent weirs disposed between the adjacent rails. It is in a mobile work scaffold provided with a rail spacing holding member constructed between plates .

請求項2に記載の発明の特徴は、請求項1の構成に加え、前記架台は、前記レール上を移動する移動体を備え、該移動体は、前記レールの側部に配置される案内ローラーを備えていることにある。   According to a second aspect of the present invention, in addition to the structure of the first aspect, the gantry includes a moving body that moves on the rail, and the moving body is a guide roller disposed on a side portion of the rail. It is in having.

請求項3に記載の発明の特徴は、請求項2の構成に加え、前記案内ローラーは、平行な一対の前記レールの外側のみ又は内側のみに配置されていることにある。   According to a third aspect of the present invention, in addition to the configuration of the second aspect, the guide roller is disposed only on the outer side or the inner side of the pair of parallel rails.

本発明に係る移動式作業足場は、請求項1に記載の構成を具備することによって、無筋コンクリート構造物の場合のように、型枠内に足場を設置する鉄筋等が無い場合であっても、型枠上の所望の位置に足場を設けることができ、型枠の変形を防止し、レール間隔を一定に保持することができ、作業員が架台に搭乗した状態でコンクリートの締固め作業や均し作業等を行うことができ、或いは、打設したコンクリートの上面を歩くことなく型枠内の所望の位置で作業することができる。また、従来の型枠内に配設された鉄筋等に足場板を支持させる構造とは異なり、作業毎に足場板の設置及び撤去する必要がなく、効率よく作業を行うことができる。 The mobile work scaffold according to the present invention is a case where there is no reinforcing bar or the like for installing the scaffold in the formwork as in the case of an unreinforced concrete structure by providing the configuration according to claim 1. In addition, a scaffold can be provided at a desired position on the formwork, deformation of the formwork can be prevented, the distance between the rails can be kept constant, and the concrete can be compacted while the worker is on the mount. It is possible to perform leveling work or the like, or to work at a desired position in the mold without walking on the upper surface of the placed concrete. Further, unlike the structure in which the scaffolding plate is supported by a reinforcing bar or the like disposed in the conventional formwork, it is not necessary to install and remove the scaffolding plate for each work, and the work can be performed efficiently.

また、本発明において、請求項2に記載の構成を具備することによって、架台がレールより脱線することを防止することができる。   Moreover, in this invention, it can prevent that a mount frame derails from a rail by comprising the structure of Claim 2.

さらに、本発明において、請求項3に記載の構成を具備することによって、脱線を防止しつつ、架台が円滑にレール上を移動することができる。   Furthermore, in the present invention, by providing the configuration according to claim 3, the gantry can smoothly move on the rail while preventing derailment.

本発明に係る移動式作業足場の使用態様の一例を示す平面図である。It is a top view which shows an example of the usage condition of the mobile work scaffold which concerns on this invention. 同上のA−A線矢視断面図である。It is an AA arrow directional cross-sectional view same as the above. 図1中の移動体部分を示す部分拡大平面図である。FIG. 2 is a partially enlarged plan view showing a moving body portion in FIG. 同上の側面図である。It is a side view same as the above. 同上のC−C線矢視断面図である。It is a CC sectional view taken on the line. (a)(b)はそれぞれ本発明に係る移動式作業足場の駆動手段の態様を説明するための図1中のB−B線矢視断面図である。(A) and (b) are each a sectional view taken along line BB in FIG. 1 for explaining the mode of the driving means of the mobile work scaffold according to the present invention.

次に、本発明に係る移動式作業足場の実施態様を図1〜図6に示した実施例に基づいて説明する。尚、図中符号1は型枠、符号2はコンクリート、符号3は型枠1上に設置される移動式作業足場である。   Next, an embodiment of the mobile work scaffold according to the present invention will be described based on the embodiment shown in FIGS. In the figure, reference numeral 1 denotes a formwork, reference numeral 2 denotes concrete, and reference numeral 3 denotes a mobile work scaffold installed on the formwork 1.

型枠1は、型枠1の周方向に互いに間隔を置いて設置された複数の支柱(縦バタ材)4a,4a…と、各支柱4a,4a…に跨がる丸鋼管からなる横バタ材4b,4bと、横バタ材4bを介して支柱4a,4a…の内側に保持された型枠パネルによって構成された堰板5,5…を備え、直立した堰板5,5…によって四方が囲まれた矩形枠状を成している。   The mold 1 is composed of a plurality of support columns (vertical butter materials) 4a, 4a,... Installed in the circumferential direction of the mold frame 1 and a horizontal flap made of a round steel pipe straddling the support columns 4a, 4a,. Are provided with form plates that are held on the inside of the columns 4a, 4a ... through the horizontal flap material 4b, and are arranged in four directions by the upright dam plates 5, 5 ... A rectangular frame is enclosed.

支柱4a,4a…は、溝形鋼、H型鋼、角型鋼管等の部材をもって構成され、互いに型枠周方向に間隔を置いて建て込まれ、隣り合う支柱4a,4a間に跨って型枠パネルが保持され、型枠1の一方を塞ぐ堰板5が形成される。   The pillars 4a, 4a ... are composed of members such as channel steel, H-shaped steel, rectangular steel pipes, etc., and are built at intervals in the circumferential direction of the mold, and straddle between the adjacent pillars 4a, 4a. A panel is held, and a dam plate 5 that closes one of the molds 1 is formed.

型枠パネルの態様は、特に限定されないが、メタルフォーム等の鋼製型枠パネルのように、型枠パネル自体の剛性が高いものを使用することが好ましい。   The form of the formwork panel is not particularly limited, but it is preferable to use a formwork panel having a high rigidity such as a steel formwork panel such as metal foam.

また、互いに対向する堰板(型枠パネル)間には、特に図示しないが、セパレータが配設され、コンクリート2打設時に作用する側圧に対抗するようにしている。   In addition, although not particularly illustrated, a separator is disposed between barrier plates (formwork panels) facing each other so as to resist a lateral pressure acting when the concrete 2 is placed.

尚、この型枠1の上部の外周部には、外周固定足場6と、外周固定足場6に支持された手摺7,7…とが設けられている。   In addition, the outer periphery fixed scaffold 6 and the handrails 7,7 ... supported by the outer periphery fixed scaffold 6 are provided in the outer peripheral part of the upper part of this formwork 1. As shown in FIG.

移動式作業足場3は、図1、図2に示すように、対向する堰板間に跨って架設された互いに平行な一対のレール8,8と、レール8,8に移動可能に支持された架台9と、架台9を移動させる駆動手段とを備え、架台9が型枠1の上方をレール8,8に沿って移動できるようになっている。   As shown in FIGS. 1 and 2, the mobile work scaffold 3 is supported by a pair of parallel rails 8, 8 laid across opposing weir plates, and movably supported by the rails 8, 8. A gantry 9 and driving means for moving the gantry 9 are provided, and the gantry 9 can move along the rails 8 and 8 above the mold 1.

また、移動式作業足場3には、レール8,8間にあって、対向する堰板5,5の上端縁中央部間に架設された梁状のレール間隔保持材10を備え、レール間隔保持材10の両端部が対向する堰板5,5の上端縁部にそれぞれ固定されている。   In addition, the mobile work scaffold 3 includes a beam-like rail spacing member 10 which is provided between the rails 8 and 8 and is installed between the center portions of the upper end edges of the opposing weir plates 5 and 5. Are fixed to the upper edge portions of the weir plates 5 and 5 facing each other.

このレール間隔保持材10は、対向する堰板5,5…の上端縁間を互いに支持させ、コンクリート2の打設時に各堰板5,5…に作用する側圧に対抗し、堰板5,5の撓みや歪みを防止することによって、対向する堰板5,5に跨って配置されたレール8,8の間隔を保持するようになっている。尚、このレール間隔保持材10は、型枠用の巾止め材と兼用してもよい。   The rail spacing member 10 supports the upper end edges of the opposing weir plates 5, 5... Against the side pressure acting on each weir plate 5, 5. By preventing the bending and distortion of 5, the distance between the rails 8, 8 disposed across the opposing weir plates 5, 5 is maintained. In addition, you may use this rail space | interval holding | maintenance material 10 also as the width | variety stop material for molds.

レール8,8は、一定の長さを有するH型鋼等をもって構成され、少なくとも架台9が支持される帯状の軌道8aを備えた梁状に形成されている。   The rails 8 and 8 are made of H-shaped steel or the like having a certain length, and are formed in a beam shape including a belt-like track 8a on which at least the gantry 9 is supported.

各レール8,8は、一定の間隔をおいて互いに対向する堰板5,5を跨ぐように配置されるとともに、その両端部が支柱4a,4a…上に架け渡した梁材に載置されている。   The rails 8 and 8 are arranged so as to straddle the mutually facing weir plates 5 and 5 with a certain interval, and both ends thereof are placed on the beam material spanned on the columns 4a, 4a. ing.

架台9は、各レール8上を移動する一対の移動体11,11と、両移動体11,11に支持された架台本体12とを備え、レール8,8に沿って移動できるようになっている。   The gantry 9 includes a pair of moving bodies 11 and 11 that move on the rails 8, and a gantry body 12 that is supported by the both moving bodies 11 and 11, and can move along the rails 8 and 8. Yes.

架台本体12は、一定幅を有する平面視帯状に形成され、前後に手摺13,13を備え、作業員が架台本体12上に乗って移動しつつ、コンクリート打設工程の各作業及びその補助を行えるようになっている。   The gantry body 12 is formed in a planar band shape having a certain width, and is provided with handrails 13 and 13 on the front and rear sides, and an operator moves on the gantry body 12 to perform each work in the concrete placing process and its assistance. It can be done.

各移動体11は、図3〜図5に示すように、架台本体12の両側部に固定された取付フレーム14,14と、取付フレーム14,14の下端に固定されたスカート部15と、スカート部15内に配置された車輪16,16とを備え、車輪16,16を介してレール8,8の軌道8a上を移動できるようになっている。   As shown in FIGS. 3 to 5, each moving body 11 includes mounting frames 14 and 14 fixed to both sides of the gantry body 12, a skirt portion 15 fixed to the lower ends of the mounting frames 14 and 14, and a skirt. Wheels 16 and 16 disposed in the portion 15 are provided, and can be moved on the tracks 8a of the rails 8 and 8 via the wheels 16 and 16.

取付フレーム14は、L型鋼等によって構成され、架台本体12の側面にボルト等によって固定されている。   The mounting frame 14 is made of L-shaped steel or the like, and is fixed to the side surface of the gantry body 12 with bolts or the like.

スカート部15は、溝形鋼等によって構成され、取付フレーム14の下端に溶接等によって固定された天板15aと、天板15aの両側縁より垂下された一対の側板15b,15bとを備え、天板15aの下面に車輪16,16が回転自在に支持されている。   The skirt portion 15 is made of channel steel or the like, and includes a top plate 15a fixed to the lower end of the mounting frame 14 by welding or the like, and a pair of side plates 15b and 15b suspended from both side edges of the top plate 15a. Wheels 16 are rotatably supported on the lower surface of the top plate 15a.

また、各移動体11には、取付フレーム14にレール8と交差する方向に支持されたローラー支持体17と、ローラ支持体17の両端に支持され、レール8,8の側方に配置される案内ローラー18,18…とを備え、案内ローラー18,18…がレール8,8側面に案内された状態で移動し、架台9の脱線が防止されている。   Each moving body 11 is supported by a mounting frame 14 in a direction crossing the rail 8, and is supported by both ends of the roller support 17 and is disposed on the side of the rails 8 and 8. The guide rollers 18 are moved in a state of being guided by the side surfaces of the rails 8 and 8, and the derailment of the gantry 9 is prevented.

案内ローラー18,18…は、取付フレーム14の両端部より垂下された回転軸18aと、回転軸18aに回転自在に支持された円柱状のローラー本体18bとを備え、両ローラー本体18b,18bの外周面がレール8の側面に当接し、案内ローラー18,18によってレール8を把持するようになっている。   The guide rollers 18, 18... Include a rotation shaft 18a suspended from both ends of the mounting frame 14, and a cylindrical roller body 18b rotatably supported by the rotation shaft 18a. The outer peripheral surface is in contact with the side surface of the rail 8, and the rail 8 is gripped by the guide rollers 18 and 18.

尚、案内ローラー18,18…は、互いに隣り合うレール8,8の外側のみ又は内側のみに配置してもよい。その場合、各レール8,8に対し案内ローラー18,18…が一方側のみで案内されるので、脱線を防止しつつ円滑に移動することができる。   In addition, you may arrange | position the guide rollers 18, 18 ... only to the outer side or the inner side of the rails 8 and 8 which mutually adjoin. In that case, since the guide rollers 18, 18... Are guided only on one side with respect to the rails 8, 8, they can move smoothly while preventing derailment.

駆動手段は、例えば、図6(a)に示すように、一端が架台本体12に連結され、他端側が型枠1上端部(本実施例では外周固定足場6の手摺7部分)に支持された滑車19を介して折り返された移動用ロープ20を備え、架台9上の作業員が移動用ロープ20を引っ張ることにより、移動用ロープ20に引っ張られて架台9が移動するようになっている。   For example, as shown in FIG. 6A, one end of the driving means is connected to the gantry body 12, and the other end is supported by the upper end of the mold 1 (in this embodiment, the handrail 7 portion of the outer periphery fixed scaffold 6). The moving rope 20 is folded back via the pulley 19, and the operator on the gantry 9 pulls the moving rope 20, so that the gantry 9 is moved by being pulled by the moving rope 20. .

また、駆動手段は、図6(b)に示すように、架台9上にウインチ21を設置し、ウインチ21より繰り出したワイヤ22の先端を移動方向前方の型枠1上端(本実施例では手摺7)に固定し、ウインチ21の巻取り動作により架台9が移動するようにしてもよい。   Further, as shown in FIG. 6B, the driving means is provided with a winch 21 on the gantry 9 and the tip of the wire 22 fed out from the winch 21 is moved to the upper end of the mold 1 in the moving direction (in this embodiment, a handrail). 7), and the gantry 9 may be moved by the winding operation of the winch 21.

このように構成された移動式作業足場3では、駆動手段によって架台9がレール8,8上を移動し、且つ、作業員が架台9上を移動することができるので、作業員が型枠1内に入らずとも型枠1上の所望の位置で作業することができる。   In the mobile work platform 3 configured as described above, the platform 9 can be moved on the rails 8 and 8 by the driving means, and the worker can move on the platform 9. Even if it does not enter, it can work at a desired position on the mold 1.

よって、作業員は、型枠1上の所望の位置において、架台9に搭乗した状態でコンクリート締固め作業や均し作業等を行うことができ、或いは、打設したコンクリート2上を歩くことなく型枠1内の所望の位置で作業することができる。   Therefore, the worker can perform the concrete compaction work, the leveling work, etc. in a state of being mounted on the mount 9 at a desired position on the mold 1 or without walking on the placed concrete 2. It is possible to work at a desired position in the mold 1.

さらに、この移動式作業足場3は、無筋コンクリート構造物のように型枠内に足場板を設置可能な鉄筋が存在しない場合であっても適用でき、また、型枠内の鉄筋に足場板を設置するような場合と異なり、作業毎に足場板を撤去する必要が無いので効率よく作業を行うことができる。   Furthermore, this mobile work scaffold 3 can be applied even when there is no reinforcing bar capable of installing a scaffolding plate in the formwork, such as an unreinforced concrete structure, and the scaffolding plate can be applied to the reinforcing bars in the formwork. Unlike the case of installing the scaffolding, it is not necessary to remove the scaffolding plate every work, so that the work can be performed efficiently.

尚、上述の実施例では、架台9を一対のレール8,8に支持させた例について説明したが、レールは3本以上の複数であってもよい。   In the above-described embodiment, the example in which the gantry 9 is supported by the pair of rails 8 and 8 has been described, but the number of rails may be three or more.

また、上述の実施例では、レール間隔保持材10をレール8,8と平行に設けた例について説明したが、レール8,8と交差する方向で対向する堰板5,5間にレール間隔保持材10とは別途に型枠用の巾止め材を設置してもよい。   In the above-described embodiment, the example in which the rail spacing member 10 is provided in parallel to the rails 8 and 8 has been described. However, the rail spacing is maintained between the dam plates 5 and 5 facing each other in the direction intersecting with the rails 8 and 8. A width stop material for the mold may be installed separately from the material 10.

尚、上述の実施例では、四方が堰板に囲まれた型枠を例に説明したが、型枠は、少なくとも互いに対向する二面の堰板を備えていればよく、例えば、既設のコンクリート構造物の端面を利用し、当該既設コンクリート構造物と連続してコンクリートを打設する場合には、堰板は対向する二面又は三面を囲むように配置されていればよい。   In the above-described embodiment, the mold frame surrounded on the four sides by the dam plate has been described as an example. However, the mold frame may be provided with at least two dam plates facing each other, for example, existing concrete. When the concrete is placed continuously with the existing concrete structure using the end surface of the structure, the barrier plate may be disposed so as to surround two or three surfaces facing each other.

1 型枠
2 コンクリート
3 移動式作業足場
4 支柱(縦バタ材)
5 型枠パネル
6 外周固定足場
7 手摺
8 レール
9 架台
10 レール間隔保持材
11 移動体
12 架台本体
13 手摺
14 取付フレーム
15 スカート部
16 車輪
17 ローラー支持体
18 案内ローラー
19 滑車
20 移動用ロープ
21 ウインチ
22 ワイヤ
1 Formwork 2 Concrete 3 Mobile work scaffold 4 Strut (vertical material)
5 Formwork panel 6 Peripheral fixed scaffold 7 Handrail 8 Rail 9 Base 10 Rail spacing holding material 11 Moving body 12 Base body 13 Handrail 14 Mounting frame 15 Skirt portion 16 Wheel 17 Roller support 18 Guide roller 19 Pulley 20 Moving rope 21 Winch 22 wires

Claims (3)

対向する堰板を有する型枠上を移動可能な移動式作業足場であって、
両端部が型枠に支持され、前記対向する堰板間に跨って架設される互いに平行な複数のレールと、該複数のレール上に移動可能に架設された架台と、隣り合う前記レール間に配置され、前記対向する堰板間に架設されるレール間隔保持材とを備えていることを特徴とする移動式作業足場。
A mobile work scaffold that is movable on a formwork having opposing weir plates,
Both ends are supported by a formwork, a plurality of parallel rails that are spanned between the opposing weir plates, a platform that is movably constructed on the plurality of rails, and the adjacent rails A movable work scaffold comprising: a rail spacing holding member disposed between the opposing weir plates .
前記架台は、前記レール上を移動する移動体を備え、該移動体は、前記レールの側部に配置される案内ローラーを備えている請求項1に記載の移動式作業足場。   The mobile work scaffold according to claim 1, wherein the gantry includes a moving body that moves on the rail, and the moving body includes a guide roller disposed on a side portion of the rail. 前記案内ローラーは、平行な一対の前記レールの外側のみ又は内側のみに配置されている請求項2に記載の移動式作業足場。   The movable work scaffolding according to claim 2, wherein the guide roller is disposed only on the outside or the inside of the pair of parallel rails.
JP2017059241A 2017-03-24 2017-03-24 Mobile work scaffold Active JP6464535B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017059241A JP6464535B2 (en) 2017-03-24 2017-03-24 Mobile work scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017059241A JP6464535B2 (en) 2017-03-24 2017-03-24 Mobile work scaffold

Publications (2)

Publication Number Publication Date
JP2018162567A JP2018162567A (en) 2018-10-18
JP6464535B2 true JP6464535B2 (en) 2019-02-06

Family

ID=63859185

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017059241A Active JP6464535B2 (en) 2017-03-24 2017-03-24 Mobile work scaffold

Country Status (1)

Country Link
JP (1) JP6464535B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109822736B (en) * 2019-04-18 2020-05-22 山东省滨州市坤合建筑工程有限公司 Production process of assembled wallboard
CN112726445A (en) * 2020-12-30 2021-04-30 中铁六局集团北京铁路建设有限公司 Side wall design steel form supporting construction
CN112726443A (en) * 2020-12-30 2021-04-30 中铁六局集团北京铁路建设有限公司 Construction method of side wall shaping steel formwork supporting structure

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5814189Y2 (en) * 1981-03-10 1983-03-19 ホリ−株式会社 Scaffolding board erection equipment for temporary foundation construction frames
GB8606896D0 (en) * 1986-03-20 1986-04-23 Friday R W Scaffold unit
JPS6343333Y2 (en) * 1986-08-06 1988-11-11
JPH06129105A (en) * 1992-10-20 1994-05-10 Taisei Corp Movable scaffold for placing concrete
JPH0828031A (en) * 1994-07-18 1996-01-30 Shimizu Corp Traversable/movable gondola device
JP3981469B2 (en) * 1998-06-02 2007-09-26 ヤマハ化工建設株式会社 Construction method of concrete structure
CA2600661C (en) * 2007-09-07 2015-05-26 Aluma Systems Inc. Removable work deck system for fabricating a processing module
JP5038964B2 (en) * 2008-04-11 2012-10-03 大成建設株式会社 Box girder construction method, concrete structure construction method and scaffolding structure

Also Published As

Publication number Publication date
JP2018162567A (en) 2018-10-18

Similar Documents

Publication Publication Date Title
JP5056608B2 (en) Retraction removal method and retraction device for mobile work vehicle for cantilever installation
JP6464535B2 (en) Mobile work scaffold
JP4403579B2 (en) Removal method of existing pier of overpass
KR101030053B1 (en) Movement type apparatus for constructing and detaching frame panel of a steel box bridge
JP4329535B2 (en) Mobile work vehicle for overhanging slabs
KR20190122925A (en) Bridges Construction Vents
CN111074893B (en) Construction system and construction method for concrete cushion layer of river dike and dyke
JP4980257B2 (en) Construction method for column head construction, method for constructing mobile work vehicle using part thereof, and method for extending bridge
JP5038964B2 (en) Box girder construction method, concrete structure construction method and scaffolding structure
JP3996818B2 (en) Work truck for tunnel widening work
JP6460682B2 (en) Temporary scaffolding unit and temporary pier
JP5940404B2 (en) Construction method of beam members
JP6449637B2 (en) Building construction method
JP2000087315A (en) Method and device for construction of floor slab
JP2874539B2 (en) Method for constructing concrete structure and weir plate used in this method
JP7139256B2 (en) Mobile work equipment, construction method of arch bridge
JPH0396598A (en) Movable form for tunnel
JP2020002528A (en) Concrete placement system and concrete placement method
JP3105532U (en) Curing frame device
JP7339477B2 (en) Concrete column formwork construction device and concrete column formwork construction method using the same
JP7330411B2 (en) Floor slab moving method and floor slab moving device
JP7068967B2 (en) Formwork system
JP7249910B2 (en) Arch bridge construction method
JPS5894504A (en) Mold frame moving type constructing process of high bridge slab
JPH049903B2 (en)

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181128

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181221

R150 Certificate of patent or registration of utility model

Ref document number: 6464535

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150