JP6176462B2 - Rebar connection method - Google Patents

Rebar connection method Download PDF

Info

Publication number
JP6176462B2
JP6176462B2 JP2015135227A JP2015135227A JP6176462B2 JP 6176462 B2 JP6176462 B2 JP 6176462B2 JP 2015135227 A JP2015135227 A JP 2015135227A JP 2015135227 A JP2015135227 A JP 2015135227A JP 6176462 B2 JP6176462 B2 JP 6176462B2
Authority
JP
Japan
Prior art keywords
reinforcing bar
bar
layer
side plate
recess
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015135227A
Other languages
Japanese (ja)
Other versions
JP2017014858A (en
Inventor
尹衍▲リョウ▼
Original Assignee
潤弘精密工程事業股▲ふん▼有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 潤弘精密工程事業股▲ふん▼有限公司 filed Critical 潤弘精密工程事業股▲ふん▼有限公司
Priority to JP2015135227A priority Critical patent/JP6176462B2/en
Publication of JP2017014858A publication Critical patent/JP2017014858A/en
Application granted granted Critical
Publication of JP6176462B2 publication Critical patent/JP6176462B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

本発明は、基礎版の建設に用いられる鉄筋接続方法に関する。 The present invention relates to a reinforcing bar connecting method used for construction of a foundation plate.

建築施工過程において、構造体の間の連結は構造強度全体に影響を及ぼすキーファクタの一つである。このため、グラウチング作業の前に、補強筋の数量や結束方式等の事項が規範に符合しているかを詳しく確認しなければならない。また、開口部或いは角の箇所の補強措置等も確認しなければならない。 In the construction process, the connection between structures is one of the key factors affecting the overall structural strength. For this reason, before grouting work, it is necessary to confirm in detail whether the number of reinforcing bars, the bundling method, etc. are consistent with the norm. In addition, reinforcement measures for openings or corners must be confirmed.

しかしながら、段階的に構造体の施工を完成させる方式では、一部の構造がグラウチング作業の完成後に、接続部分の構造の施工において、鉄筋の溶接箇所の数量過多のために往々に鉄筋が適切に接続されない状況が発生する。監督者にとっては、これらのミスを探し出すことは時間と労力の浪費になる。逐一確認する場合、施工全体の効率に影響するため、工期が長引くことになる。 However, in the method of completing the construction of the structure step by step, after the grouting work is completed for a part of the structure, the reinforcing bars are often appropriately used in the construction of the connection part due to the excessive number of welding points of the reinforcing bars. There is a situation where you are not connected. For supervisors, finding these mistakes is a waste of time and effort. When checking one by one, the construction period will be prolonged because it affects the efficiency of the entire construction.

そこで、本発明者は上記の欠点が改善可能と考え、鋭意検討を重ねた結果、合理的設計で上記の課題を効果的に改善する本発明の提案に到った。 Therefore, the present inventor considered that the above-mentioned drawbacks can be improved, and as a result of intensive studies, the present inventor has arrived at a proposal of the present invention that effectively improves the above-described problems by rational design.

本発明は、このような従来の問題に鑑みてなされたものである。上記課題解決のため、本発明は、鉄筋接続方法を提供することを主目的とする。 The present invention has been made in view of such conventional problems. In order to solve the above-mentioned problems, the present invention mainly aims to provide a reinforcing bar connecting method.

上述した課題を解決し、目的を達成するために、本発明に係る鉄筋接続方法は、基礎版の建設に用いられ、前記基礎版は第一方向に沿って段階的に進行し、
複数の第一下層鉄筋及び複数の第二下層鉄筋で構成されると共に相互に交錯し、これら前記第二下層鉄筋は前記第一方向に沿って等間隔で並設され、且つこれら前記第一下層鉄筋は前記第一方向に交錯する第二方向に沿って等間隔で並設される、設置面に下層鉄筋が架設される工程(I)と、
複数の第一上層鉄筋及び複数の第二上層鉄筋で構成されると共に相互に交錯し、且つ前記第二方向及び前記第一方向に沿ってそれぞれ等間隔で並設され、これら前記第一上層鉄筋は第一下層鉄筋の端部の外に突出される、前記下層鉄筋の上方に上層鉄筋が架設される工程(II)と、
外側面及び前記外側面に連接される上面を有し、前記外側面には複数の孔部が形成され、これら前記第一下層鉄筋の端部はこれら前記孔部に収納され、且つ上面と設置面との間には横向きのストップバーが設置され、前記横向きのストップバーはそれの外側面に固定される、側板が架設される工程(III)
前記上層鉄筋及び前記下層鉄筋を覆うようにコンクリートを注入して部分基礎版を完成させる工程(IV)と、
前記部分基礎版の前記第一下層鉄筋の端部の接続器に継続される次の部分基礎版の第一下層鉄筋を接続すると共に前記部分基礎版の第一上層鉄筋に前記次の部分基礎版の第一上層鉄筋を重ね継手方式で接続する工程(V)と、
を含むことを特徴とする。
In order to solve the above-described problems and achieve the object, the reinforcing bar connecting method according to the present invention is used for the construction of a foundation plate, and the foundation plate proceeds stepwise along a first direction,
It is composed of a plurality of first lower layer reinforcing bars and a plurality of second lower layer reinforcing bars and crosses each other, and these second lower layer reinforcing bars are juxtaposed at equal intervals along the first direction, and the first The lower layer reinforcing bars are arranged at equal intervals along the second direction intersecting with the first direction, and the step (I) in which the lower layer reinforcing bars are installed on the installation surface,
A plurality of first upper-layer reinforcing bars and a plurality of second upper-layer reinforcing bars are crossed with each other and arranged in parallel at equal intervals along the second direction and the first direction, respectively. and step (II) of the upper layer rebar is laid over the being, the lower reinforcing bars protrude out of the end of the first lower rebar,
The outer surface has an upper surface connected to the outer surface, and a plurality of holes are formed in the outer surface, and ends of the first lower reinforcing bars are accommodated in the holes, and A side stop bar is installed between the installation surface and the side stop bar is fixed to the outer side of the side stop bar, and a side plate is installed (III) ,
Step (IV) of injecting concrete so as to cover the upper layer reinforcing bar and the lower layer reinforcing bar to complete a partial foundation plate,
Connecting the first lower layer reinforcing bar of the next partial foundation plate continued to the connector at the end of the first lower layer reinforcing bar of the partial foundation plate and the next portion to the first upper layer reinforcing bar of the partial foundation plate A step (V) of connecting the first upper layer reinforcing bar of the base plate by a lap joint method; and
It is characterized by including.

本発明によれば、施工全体の効率を高める。 According to the present invention, the efficiency of the entire construction is increased.

下層鉄筋及び上層鉄筋を架設する概念図である。It is a conceptual diagram which constructs a lower layer reinforcement and an upper layer reinforcement. 側板を架設する概念図である。It is a conceptual diagram which constructs a side plate. 横向きのストップバーを設置する概念図である。It is a conceptual diagram which installs a sideways stop bar. 下押しバーを架設する概念図である。It is a conceptual diagram which constructs a downward push bar. 下押しバーを架設する概念図である。It is a conceptual diagram which constructs a downward push bar. 本発明の他の実施形態に係る下押しバー及び側板を架設する概念図である。It is a conceptual diagram which constructs the downward pushing bar and side plate which concern on other embodiment of this invention. 縦向きのストップバーを設置する概念図である。It is a conceptual diagram which installs a vertically oriented stop bar. 斜め支持部材を設置する概念図である。It is a conceptual diagram which installs a diagonal support member. コンクリートを注入する概念図である。It is a conceptual diagram which inject | pours concrete. コンクリートを注入する概念図である。It is a conceptual diagram which inject | pours concrete. 下層鉄筋及び上層鉄筋を架設する鉄筋を接続する概念図である。It is a conceptual diagram which connects the reinforcing bar which constructs a lower layer reinforcing bar and an upper layer reinforcing bar. 下層鉄筋及び上層鉄筋を架設する鉄筋を接続する概念図である。It is a conceptual diagram which connects the reinforcing bar which constructs a lower layer reinforcing bar and an upper layer reinforcing bar. コンクリートを注入し、基礎版を部分完成する概念図である。It is a conceptual diagram in which concrete is poured and a basic version is partially completed. 本発明の鉄筋接続方法のフローチャートである。It is a flowchart of the reinforcing bar connecting method of the present invention.

本発明における好適な実施の形態について、添付図面を参照して説明する。尚、以下に説明する実施の形態は、特許請求の範囲に記載された本発明の内容を限定するものではない。また、以下に説明される構成の全てが、本発明の必須要件であるとは限らない。 Preferred embodiments of the present invention will be described with reference to the accompanying drawings. Note that the embodiments to be described below are not intended to limit the present invention described in the appended claims. In addition, all of the configurations described below are not necessarily essential requirements of the present invention.

以下、本発明の実施形態について、図面を参照しながら説明する。図1に示すように、下層鉄筋100は複数の第一下層鉄筋110及び複数の第二下層鉄筋120で構成されると共に相互に交錯する。第一下層鉄筋110は第一方向aに沿って延伸され、且つ第二方向bに等間隔で交錯して並設される。第二下層鉄筋120は第二方向bに沿って延伸され、且つ第一方向aに等間隔で並設される。下層鉄筋100の結束後に、需要に応じて設置面にマット130を入れて持ち上げることで保護させる。下層鉄筋100の上方には上層鉄筋200が架設される。前記上層鉄筋200は複数の第一上層鉄筋210及び複数の第二上層鉄筋220で構成されると共に相互に交錯する。第一上層鉄筋210は第一方向aに沿って延伸され、且つ第二方向bに沿って等間隔で並設される。第二上層鉄筋220は第二方向bに沿って延伸され、且つ第一方向aに沿って等間隔で並設される。また、各第一下層鉄筋110の端部には保護栓114を有する接続器112が設置され、施工過程で異物が進入するのを防止させる。 Hereinafter, embodiments of the present invention will be described with reference to the drawings. As shown in FIG. 1, the lower layer rebar 100 is crossed with each other with including a plurality of first lower reinforcing bars 110 and a plurality of second lower reinforcing bars 120. The first lower layer reinforcing bars 110 are extended along the first direction a, and are arranged in parallel in the second direction b at equal intervals. The 2nd lower layer reinforcement 120 is extended along the 2nd direction b, and is arranged in parallel at equal intervals in the 1st direction a. After bundling the lower layer reinforcing bars 100, the mat 130 is put on the installation surface according to demand and is protected by lifting. An upper layer reinforcing bar 200 is installed above the lower layer reinforcing bar 100. The upper rebar 200 is composed of a plurality of first upper rebars 210 and a plurality of second upper rebars 220 and crosses each other. The first upper-layer reinforcing bars 210 are extended along the first direction a, and are arranged in parallel along the second direction b at equal intervals. The second upper-layer reinforcing bars 220 are extended along the second direction b, and are arranged in parallel along the first direction a at equal intervals. Moreover, the connector 112 which has the protective stopper 114 is installed in the edge part of each 1st lower layer reinforcement 110, and prevents that a foreign material approachs in the construction process.

また、図2に示すように、前記側板300は外側面302及び上面304を有する。外側面302には複数の孔部306が形成され、且つ第一下層鉄筋110の端部が孔部306に収納される。他の上面304には複数の第一凹部308が形成され、且つ第一上層鉄筋210は上面304に跨設されると共に第一凹部308に収納される。上面304に跨設される第一上層鉄筋210は第一下層鉄筋110の端部の外に突出される。 As shown in FIG. 2, the side plate 300 has an outer surface 302 and an upper surface 304. A plurality of hole portions 306 are formed in the outer side surface 302, and the end portions of the first lower layer reinforcing bars 110 are accommodated in the hole portions 306. A plurality of first concave portions 308 are formed on the other upper surface 304, and the first upper-layer reinforcing bar 210 is straddled over the upper surface 304 and is accommodated in the first concave portion 308. The first upper-layer reinforcing bar 210 straddling the upper surface 304 protrudes outside the end portion of the first lower-layer reinforcing bar 110.

このほか、側板300には補助支持構造が任意で設置され、例えば、横向きのストップバー400、縦向きのストップバー600及び斜め支持部材700が設置され、図3、図5及に図6にそれぞれ図示する。横向きのストップバー400は上面304と設置面との間に設置されると共に側板300の外側面302に固定される。これにより、側板300の構造強度を全体的に高め、側板300がグラウチング後に変形するのを防止させる(図3参照)。 In addition, an auxiliary support structure is optionally installed on the side plate 300. For example, a lateral stop bar 400, a vertical stop bar 600, and an oblique support member 700 are installed, and FIG. 3, FIG. 5 and FIG. Illustrated. The horizontal stop bar 400 is installed between the upper surface 304 and the installation surface and is fixed to the outer surface 302 of the side plate 300. Thereby, the structural strength of the side plate 300 is increased as a whole, and the side plate 300 is prevented from being deformed after grouting (see FIG. 3).

図4Aに示すように、下押しバー500には複数の第二凹部502が形成されると共に側板300の複数の第一凹部308に対応される。各第一凹部308及び第二凹部502は共に第一上層鉄筋210を包囲させる。第一凹部308及び第二凹部502の外形は半円の切欠き等であり、径方向に共に第一上層鉄筋210を収納する空間を構成させる(図4Aの第一上層鉄筋210aの上下の第一凹部及び第二凹部を参照)。 As shown in FIG. 4A, a plurality of second recesses 502 are formed in the lower push bar 500 and correspond to the plurality of first recesses 308 of the side plate 300. Each of the first recess 308 and the second recess 502 surrounds the first upper-layer reinforcing bar 210. The outer shapes of the first concave portion 308 and the second concave portion 502 are semicircular cutouts or the like, and both form a space for accommodating the first upper layer rebar 210 in the radial direction (the first upper and lower rebars 210a in FIG. See one recess and the second recess).

図4Bに示すように、側板300の上面には下押しバー500が設置され、これにより側板300を第一上層鉄筋210の上方の空間に封止させ、第一上層鉄筋210をさらに固定させる。この設計により、グラウチング時に第一上層鉄筋の箇所からの漏れを防ぐ。また、側板300にはU字型の第一凹部308が採用され、U字型の凹部の深さは第一上層鉄筋210の径方向の長さに実質相等し、下押しバー500には凹部が設けられずに平面となる設計になる。これにより、下押しバー500を置く際に下押しバー500を側板300に位置を合わせる時間を節約させる(図4C参照)。 As shown in FIG. 4B, a lower push bar 500 is installed on the upper surface of the side plate 300, thereby sealing the side plate 300 in a space above the first upper layer rebar 210 and further fixing the first upper layer rebar 210. This design prevents leakage from the location of the first upper rebar during grouting. Further, a U-shaped first concave portion 308 is adopted for the side plate 300, the depth of the U-shaped concave portion is substantially equal to the length in the radial direction of the first upper-layer reinforcing bar 210, and the lower push bar 500 has a concave portion. The design is flat without being provided. This saves time for aligning the lower push bar 500 with the side plate 300 when placing the lower push bar 500 (see FIG. 4C).

なお、前記下押しバー500は下押しバー500及び側板300の連結箇所から外側面302に向けて突出される凸縁部504を有し、凸縁部504の突出する長さは側板300の横向きのストップバー400の深さ(外側面に突出されるサイズ)に実質相等し、下押しバー500が外側面302の側板300から離れる方向に横向きのストップバー400の表面に水平になり、縦向きのストップバー600が下押しバー500及び横向きのストップバー400に固定される(図5参照)。縦向きのストップバー600及び横向きのストップバー400により構造強度が全体的に高まり、グラウチング後に変形するのを防止させる。この際、下押しバー500は外側面302に水平になり(即ち、凸縁部504を有しない)、縦向きのストップバー600を側板300及び下押しバー500に直接固定させる。 The lower push bar 500 has a convex edge portion 504 that protrudes from the connecting portion of the lower push bar 500 and the side plate 300 toward the outer surface 302, and the protruding length of the convex edge portion 504 is a lateral stop of the side plate 300. Substantially equal to the depth of the bar 400 (the size protruding from the outer surface), the lower push bar 500 is horizontal to the surface of the lateral stop bar 400 in a direction away from the side plate 300 of the outer surface 302, and the vertical stop bar 600 is fixed to the lower push bar 500 and the lateral stop bar 400 (see FIG. 5). The vertical stop bar 600 and the horizontal stop bar 400 increase the overall structural strength and prevent deformation after grouting. At this time, the lower push bar 500 is horizontal to the outer surface 302 (that is, does not have the convex edge 504), and the vertical stop bar 600 is directly fixed to the side plate 300 and the lower push bar 500.

図6に示すように、外側面302には斜め支持部材700が設置される。斜め支持部材700の端面が外側面302に当接される以外、好ましくは、斜め支持部材700が縦向きのストップバー600の一側に隣接されることで、側板300の構造強度をさらに高める。 As shown in FIG. 6, an oblique support member 700 is installed on the outer surface 302. Except for the end surface of the diagonal support member 700 being in contact with the outer surface 302, preferably, the diagonal support member 700 is adjacent to one side of the vertical stop bar 600 to further increase the structural strength of the side plate 300.

次は、図7に示すように、側板300の内側に上層鉄筋210及び下層鉄筋を覆うようにコンクリートが注入された後、側板300、下押しバー500及び他の補助支持構造が取り払われ、部分基礎版810が完成する(図8参照)。この設計により、下押しバー及び側板が鉄筋に組み合わされるのみならず、両者の組み合わせと取り払いが相当便利になり、施工品質が高まる。 Next, as shown in FIG. 7, after concrete is poured into the side plate 300 so as to cover the upper layer rebar 210 and the lower layer rebar, the side plate 300, the lower push bar 500 and other auxiliary support structures are removed, and the partial foundation A plate 810 is completed (see FIG. 8). With this design, not only is the bottom bar and side plate combined with the reinforcing bar, but the combination and removal of both is considerably convenient and construction quality is enhanced.

部分基礎版810が完成すると、第一方向aに沿って下層鉄筋100及び上層鉄筋200が継続的に設置される(図9及び図10参照)。第一下層鉄筋110は前述の接続器112の位置から部分基礎版810の第一下層鉄筋110まで接続され、第一上層鉄筋210‐2及び部分基礎版810の第一上層鉄筋210‐1は重ね継手方式で接続される。次に、前述のように、側板、下押しバー及び支持部材(例えば、横向きのストップバー、縦向きのストップバー)の架設工程が行われる。 When the partial foundation plate 810 is completed, the lower layer reinforcing bar 100 and the upper layer reinforcing bar 200 are continuously installed along the first direction a (see FIGS. 9 and 10). The first lower layer reinforcement 110 is connected from the position of the connector 112 to the first lower layer reinforcement 110 of the partial foundation plate 810, and the first upper layer reinforcement 210-2 and the first upper layer reinforcement 210-1 of the partial foundation plate 810. Are connected by a lap joint method. Next, as described above, the erection process of the side plate, the lower push bar, and the support member (for example, a horizontal stop bar, a vertical stop bar) is performed.

図11に示すように、コンクリートが注入されることで部分基礎版820が形成される。上述の方式を重複して行い基礎版800を段階的に完成させる。側板の第一凹部及び孔部の設計により、鉄筋の位置合わせの精度が高まり、段階的な施工過程での施工効率が向上する。 As shown in FIG. 11, a partial foundation plate 820 is formed by pouring concrete. The above method is repeated to complete the basic version 800 step by step. The design of the first recess and the hole of the side plate increases the accuracy of rebar alignment and improves the construction efficiency in a stepwise construction process.

図12に示すように、工程S1010では、設置面に下層鉄筋が架設される。下層鉄筋は複数の第一下層鉄筋及び複数の第二下層鉄筋で構成されると共に相互に交錯し、第一下層鉄筋は第二方向に沿って等間隔で並設され、第二下層鉄筋は第一方向に沿って等間隔で並設される。工程S1030では、下層鉄筋の上方に上層鉄筋が架設される。上層鉄筋は複数の第一上層鉄筋及び複数の第二上層鉄筋で構成されると共に相互に交錯し、且つ第二方向及び第一方向に沿ってそれぞれ等間隔で並設される。このほか、各第一下層鉄筋の端部には接続装置を有し、また、好ましくは、保護栓により第一下層鉄筋に接続される反対側から接続装置を封止させる。これにより、施工過程で異物が接続器に進入するのを防止させ、接続効果に影響を与えさせない。 As shown in FIG. 12, in step S1010, a lower layer reinforcing bar is installed on the installation surface. The lower layer reinforcing bars are composed of a plurality of first lower layer reinforcing bars and a plurality of second lower layer reinforcing bars and cross each other, and the first lower layer reinforcing bars are arranged in parallel along the second direction at equal intervals. Are arranged at equal intervals along the first direction. In step S1030, the upper layer reinforcing bar is installed above the lower layer reinforcing bar. The upper-layer reinforcing bars are composed of a plurality of first upper-layer reinforcing bars and a plurality of second upper-layer reinforcing bars, intersect with each other, and are arranged in parallel at equal intervals along the second direction and the first direction. In addition, it has a connection apparatus in the edge part of each 1st lower layer reinforcement, Preferably, a connection apparatus is sealed from the opposite side connected to a 1st lower layer reinforcement with a protective stopper. This prevents foreign matter from entering the connector during the construction process and does not affect the connection effect.

工程S1050では、側板が架設される。側板は外側面及び外側面に連接される上面を有する。外側面には複数の孔部が形成され、且つ上面には第二方向に沿って等間隔で配列される複数の第一凹部が形成される。第一下層鉄筋の端部は孔部に収納され、且つ第一上層鉄筋は上面に跨設されると共に第一凹部に収納される。また、側板の架設工程において、側板の上面と設置面との間に複数の横向きのストップバーが任意で設置されて補助支持構造となる。横向きのストップバーは側板の外側面に固定される。これにより側板の構造強度を全体的に高め、側板がグラウチング後に変形するのを防ぐ。 In step S1050, a side plate is installed. The side plate has an outer surface and an upper surface connected to the outer surface. A plurality of hole portions are formed on the outer side surface, and a plurality of first concave portions arranged at equal intervals along the second direction are formed on the upper surface. The end of the first lower layer reinforcing bar is housed in the hole, and the first upper layer reinforcing bar is straddled on the upper surface and is housed in the first recess. Further, in the side plate laying step, a plurality of lateral stop bars are arbitrarily installed between the upper surface of the side plate and the installation surface to form an auxiliary support structure. The lateral stop bar is fixed to the outer surface of the side plate. This increases the structural strength of the side plate as a whole and prevents the side plate from being deformed after grouting.

工程S1070では、側板の上面に下押しバーが設置される。下押しバーには複数の第二凹部が形成されると共に側板の複数の第一凹部に対応される。各第一凹部及び第二凹部は共に第一上層鉄筋を包囲させる。また、下押しバーの設置工程では、側板及び下押しバーに複数の縦向きのストップバーが任意で設置される。縦向きのストップバーは下押しバー及び側板に連結されて側板支持部材を共に形成させ、斜め支持部材が外側面に設置される。斜め支持部材は、好ましくは、縦向きのストップバーの一側に隣接され、側板の構造強度をさらに高める。工程S1090では、上層鉄筋及び下層鉄筋を覆うようにコンクリートが注入されて部分基礎版が形成される。接続方向(例えば、第一方向)に沿って部分基礎版が継続的に完成され、各部分基礎版が接続されて基礎板の建設が完成する。側板の第一凹部及び孔部の設計により、鉄筋の位置合わせの精度が高まり、施工効率が向上する。 In step S1070, a lower push bar is installed on the upper surface of the side plate. The lower push bar is formed with a plurality of second recesses and corresponds to the plurality of first recesses of the side plate. Both the first recess and the second recess surround the first upper-layer reinforcing bar. In the lower push bar installation step, a plurality of vertical stop bars are optionally installed on the side plate and the lower push bar. The vertical stop bar is connected to the lower push bar and the side plate to form a side plate support member, and the diagonal support member is installed on the outer surface. The oblique support member is preferably adjacent to one side of the vertical stop bar to further enhance the structural strength of the side plate. In step S1090, concrete is poured so as to cover the upper layer reinforcing bar and the lower layer reinforcing bar to form a partial foundation plate. The partial foundation plates are continuously completed along the connection direction (for example, the first direction), and the partial foundation plates are connected to complete the construction of the foundation plate. The design of the first concave portion and the hole portion of the side plate increases the accuracy of rebar alignment and improves the construction efficiency.

従って、本明細書に開示された実施例は、本発明を限定するものではなく、説明するためのものであり、このような実施例によって本発明の思想と範囲が限定されるものではない。本発明の範囲は特許請求の範囲により解釈すべきであり、それと同等の範囲内にある全ての技術は、本発明の権利範囲に含まれるものと解釈すべきである。 Accordingly, the embodiments disclosed herein are for the purpose of explaining, not limiting the present invention, and the spirit and scope of the present invention are not limited by such embodiments. The scope of the present invention should be construed according to the claims, and all technologies within the equivalent scope should be construed as being included in the scope of the present invention.

100 下層鉄筋
110 第一下層鉄筋
112 接続器
114 保護栓
120 第二下層鉄筋
130 マット
200 上層鉄筋
210、210a、210−1、210−2 第一上層鉄筋
220 第二上層鉄筋
300 側板
302 外側面
304 上面
306 孔部
308 第一凹部
400 横向きのストップバー
500 下押しバー
502 第二凹部
600 縦向きのストップバー
700 斜め支持部材
800 基礎版
810、820部分基礎版
a 第一方向
b 第二方向
DESCRIPTION OF SYMBOLS 100 Lower layer reinforcement 110 First lower layer reinforcement 112 connector 114 Protection stopper 120 Second lower layer reinforcement 130 Mat 200 Upper layer reinforcement 210, 210a, 210-1, 210-2 First upper layer reinforcement 220 Second upper layer reinforcement 300 Side plate 302 Outer surface 304 Upper surface 306 Hole 308 First recess 400 Horizontal stop bar 500 Lower push bar 502 Second recess 600 Vertical stop bar 700 Diagonal support member 800 Base plate 810, 820 Partial base plate a First direction b Second direction

Claims (2)

基礎版の建設に用いられ、前記基礎版は第一方向(a)に沿って段階的に進行する鉄筋接続方法であって、
複数の第一下層鉄筋(110)及び複数の第二下層鉄筋(120)で構成されると共に相互に交錯し、これら前記第二下層鉄筋(120)は前記第一方向(a)に沿って等間隔で並設され、且つこれら前記第一下層鉄筋(110)は前記第一方向(a)に交錯する第二方向(b)に沿って等間隔で並設される、設置面に下層鉄筋(100)が架設される工程(I)と、
複数の第一上層鉄筋(210)及び複数の第二上層鉄筋(220)で構成されると共に相互に交錯し、且つ前記第二方向(b)及び前記第一方向(a)に沿ってそれぞれ等間隔で並設され、これら前記第一上層鉄筋(210)は第一下層鉄筋(110)の端部の外に突出される、前記下層鉄筋(100)の上方に上層鉄筋(200)が架設される工程(II)と、
外側面(302)及び前記外側面(302)に連接される上面(304)を有し、前記外側面(302)には複数の孔部(306)が形成され、これら前記第一下層鉄筋(110)の端部はこれら前記孔部(306)に収納され、且つ上面と設置面との間には横向きのストップバー(400)が設置され、前記横向きのストップバー(400)はそれの外側面に固定される、側板(300)が架設される工程(III)
前記上層鉄筋(200)及び前記下層鉄筋(100)を覆うようにコンクリートを注入して部分基礎版(810)を完成させる工程(IV)と、
前記部分基礎版(810)の前記第一下層鉄筋(110)の端部の接続器(112)に継続される次の部分基礎版(820)の第一下層鉄筋(110)を接続すると共に前記部分基礎版(810)の第一上層鉄筋(210-1)に前記次の部分基礎版(820)の第一上層鉄筋(210-2)を重ね継手方式で接続する工程(V)と、
を含むことを特徴とする鉄筋接続方法。
Used for the construction of a base plate, the base plate is a reinforcing bar connection method that progresses stepwise along the first direction (a) ,
It is composed of a plurality of first lower reinforcing bars (110) and a plurality of second lower reinforcing bars (120) and crosses each other, and these second lower reinforcing bars (120) are along the first direction (a). The first lower layer reinforcing bars (110) arranged in parallel at equal intervals, and arranged in parallel in the second direction (b) intersecting with the first direction (a) , the lower layers on the installation surface Step (I) where the reinforcing bar (100) is installed,
It is composed of a plurality of first upper-layer rebars (210) and a plurality of second upper-layer rebars (220) and crosses each other, and each along the second direction (b) and the first direction (a) , etc. are juxtaposed at intervals, these the first upper reinforcement (210) is projected out of the end of the first lower reinforcing bar (110), the upper layer reinforcement (200) above said lower reinforcing bar (100) The process (II) to be installed,
Has a top surface (304) which is connected to the outer surface (302) and said outer surface (302), said outer plurality of holes on the side (302) (306) are formed, these said first lower reinforcing bar The end of (110) is accommodated in these holes (306) , and a lateral stop bar (400) is installed between the upper surface and the installation surface, and the lateral stop bar (400) is A step (III) in which a side plate (300) fixed to the outer surface is installed ; and
Step (IV) of injecting concrete so as to cover the upper layer reinforcing bar (200) and the lower layer reinforcing bar (100) to complete a partial foundation version (810);
The first lower layer reinforcement (110) of the next partial foundation plate (820) is connected to the connector (112) at the end of the first lower layer reinforcement (110) of the partial foundation plate (810). And (V) connecting the first upper layer reinforcing bar (210-2) of the next partial base plate (820) to the first upper layer reinforcing bar (210-1) of the partial base plate (810) by a lap joint method. ,
Reinforcing bar connection method characterized by including.
前記上面(304)には複数の第一凹部(308)が形成されると共に第二方向(b)に沿って等間隔で配列され、これら前記第一上層鉄筋(210)は前記上面(304)に跨設されると共に前記第一凹部(308)に収納され、鉄筋接続方法は、複数の第二凹部(502)が形成されると共にこれら前記第一凹部(308)に対応され、各第一凹部(308)及び第二凹部(502)は共に前記第一上層鉄筋(210)を包囲させる、前記側板(300)の上面に下押しバー(500)が設置される工程(VI)をさらに含むことを特徴とする、請求項1に記載の鉄筋接続方法。 A plurality of first recesses (308) are formed on the upper surface (304) and arranged at equal intervals along the second direction (b) .The first upper-layer reinforcing bars (210) are arranged on the upper surface (304). housed in the first recess (308) while being straddled, the rebar connection method is corresponding to these said first recess (308) with multiple second recess (502) is formed, the first The first recess (308) and the second recess (502) both further include a step (VI) in which a lower push bar (500) is installed on the upper surface of the side plate (300) to surround the first upper-layer reinforcing bar (210). The reinforcing bar connecting method according to claim 1, wherein:
JP2015135227A 2015-07-06 2015-07-06 Rebar connection method Active JP6176462B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015135227A JP6176462B2 (en) 2015-07-06 2015-07-06 Rebar connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015135227A JP6176462B2 (en) 2015-07-06 2015-07-06 Rebar connection method

Publications (2)

Publication Number Publication Date
JP2017014858A JP2017014858A (en) 2017-01-19
JP6176462B2 true JP6176462B2 (en) 2017-08-09

Family

ID=57830065

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015135227A Active JP6176462B2 (en) 2015-07-06 2015-07-06 Rebar connection method

Country Status (1)

Country Link
JP (1) JP6176462B2 (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4569173A (en) * 1984-10-04 1986-02-11 Balboa Construction Co., Inc. Method for constructing buildings and building structures
JPS61106843A (en) * 1984-10-29 1986-05-24 株式会社日立製作所 Anchor structure of nuclear reactor storing vessel
JP4746752B2 (en) * 2001-02-28 2011-08-10 ミサワホーム株式会社 Basic rebar structure
JP2011006849A (en) * 2009-06-23 2011-01-13 Sekisui House Ltd Method for constructing foundation
JP2013189841A (en) * 2012-03-14 2013-09-26 World Room Bliss:Kk Smart foundation system

Also Published As

Publication number Publication date
JP2017014858A (en) 2017-01-19

Similar Documents

Publication Publication Date Title
KR101301081B1 (en) Wall structure and the construction method therefor
KR101584070B1 (en) Loop steel bottom mounted precast bridge deck module
KR101578902B1 (en) The building PC slab structure and the constructing method thereof
KR101933471B1 (en) Double wall comprising inner and outer pannels with connecting member using wave type reinforcing bar
KR20200048596A (en) Precast concrete double wall for constructing shear wall, method for manufacturing the same and method for constructing shear wall using the same
JP6176462B2 (en) Rebar connection method
CN110878609B (en) Construction method of unbonded prestressed waffle slab
JP2016205051A (en) Construction method for structure
CN210439477U (en) Post-cast strip interception structure
JP6177151B2 (en) Independent foundation reinforcement structure and independent foundation
JP2014205972A (en) Method for constructing tank, and outer tank liner plate
KR20170093743A (en) Beam bridge having beam support block and its construction method
KR101628255B1 (en) Heat-insulation deck and method for installing the heat-insulation deck
KR102042090B1 (en) Abutment integrated with H-pile in integral abutment bridge, and Constructing method thereof
JP6224181B1 (en) Underground water storage facility
KR20100033165A (en) Insulation deck plate for slab
JP2016118047A (en) Floor slab concrete plate and floor slab
JP5777060B2 (en) PCa member and PCa method
JP5425957B2 (en) Construction method using concrete placement scaffold
JP5461492B2 (en) Construction method of reinforced concrete frame structure
JP7297229B2 (en) Aperture reinforcement structure and reinforcement bars for reinforced concrete slabs
JP2018090980A (en) Form unit and slope reinforcement method
JP7076101B2 (en) Construction method of synthetic slab
JP2016098479A (en) Precast concrete member used for constructing foundation, and foundation construction method
TW201700842A (en) Bar connecting method

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20161124

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170425

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170509

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170627

R150 Certificate of patent or registration of utility model

Ref document number: 6176462

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: R3D02

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250