JP6136575B2 - Pile head structure and construction method of pile head structure - Google Patents

Pile head structure and construction method of pile head structure Download PDF

Info

Publication number
JP6136575B2
JP6136575B2 JP2013111600A JP2013111600A JP6136575B2 JP 6136575 B2 JP6136575 B2 JP 6136575B2 JP 2013111600 A JP2013111600 A JP 2013111600A JP 2013111600 A JP2013111600 A JP 2013111600A JP 6136575 B2 JP6136575 B2 JP 6136575B2
Authority
JP
Japan
Prior art keywords
pile head
pile
backing metal
reinforcing
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2013111600A
Other languages
Japanese (ja)
Other versions
JP2014231673A (en
Inventor
佐藤 光一
光一 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP2013111600A priority Critical patent/JP6136575B2/en
Publication of JP2014231673A publication Critical patent/JP2014231673A/en
Application granted granted Critical
Publication of JP6136575B2 publication Critical patent/JP6136575B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Description

本発明は、港湾鋼構造物等の水域構造物、擁壁、土留壁、フーチング等の陸域構造物等を上部構造物として、これらの上部構造物の基礎杭に用いられる杭頭構造及び杭頭構造の構築方法に関する。   The present invention relates to a pile head structure and a pile used for foundation piles of water structures such as harbor steel structures, land structures such as retaining walls, retaining walls, and footings as upper structures. The present invention relates to a method for constructing a head structure.

従来より、基礎杭に設けられる杭頭補強筋と、上部構造物に設けられる基礎梁主筋との干渉を回避することを目的として、特許文献1に開示される杭頭補強構造が提案されている。   Conventionally, a pile head reinforcing structure disclosed in Patent Document 1 has been proposed for the purpose of avoiding interference between a pile head reinforcing bar provided in a foundation pile and a foundation beam main reinforcing bar provided in an upper structure. .

特許文献1に開示された杭頭補強構造は、鋼板からなる杭天板を杭頭部に有する杭の杭頭部に、基礎梁主筋と交差した状態で多数の杭頭補強筋が配筋されるものである。特許文献1に開示された杭頭補強構造は、鋼製のリングプレートが杭天板の上面に溶接され、リングプレートの上面に多数の杭頭補強筋の下端が溶接される。ここで、多数の杭頭補強筋は、基礎梁主筋と干渉しないように配筋されて、杭頭部の外形輪郭に沿った仮想の正八角形状に配列される。   In the pile head reinforcement structure disclosed in Patent Document 1, a large number of pile head reinforcement bars are arranged on the pile head of a pile having a pile top plate made of steel plate at the pile head in a state of crossing the foundation beam main reinforcement. Is. In the pile head reinforcing structure disclosed in Patent Document 1, a steel ring plate is welded to the upper surface of the pile top plate, and the lower ends of many pile head reinforcing bars are welded to the upper surface of the ring plate. Here, a large number of pile head reinforcing bars are arranged so as not to interfere with the foundation beam main bars, and are arranged in a virtual regular octagonal shape along the outline of the pile head.

特開2006−144355号公報JP 2006-144355 A

しかし、特許文献1に開示された杭頭補強構造は、杭頭部に杭天板とリングプレートとを備えるものであり、リングプレートの上面に多数の杭頭補強筋の下端が溶接されるため、杭頭部の構造が複雑なものとなることから、杭頭部の構築に必要となる施工コストが増大するという問題点があった。   However, the pile head reinforcement structure disclosed in Patent Document 1 is provided with a pile top plate and a ring plate on the pile head, and the lower ends of many pile head reinforcement bars are welded to the upper surface of the ring plate. Since the structure of the pile head is complicated, there is a problem that the construction cost required for the construction of the pile head increases.

また、特許文献1に開示された杭頭補強構造は、リングプレートの上面に溶接された多数の杭頭補強筋が上部構造物の内部に設けられるものであり、杭頭部そのものが上部構造物の内部まで延びて設けられるものでないことから、基礎杭と上部構造物とを強固に接合させることが困難なものとなるという問題点があった。   Moreover, the pile head reinforcement structure disclosed by patent document 1 is provided with many pile head reinforcements welded to the upper surface of the ring plate inside the upper structure, and the pile head itself is the upper structure. Therefore, there is a problem that it is difficult to firmly bond the foundation pile and the upper structure.

さらに、従来の杭頭補強構造90は、図21に示すように、上部構造物97の内部まで基礎杭の杭頭部91が延びて設けられ、基礎梁主筋95が溶接された鋼板92を基礎杭の杭頭部91に溶接させた場合に、特に、鋼板92の端部96で不完全溶け込み溶接に近い状態となり、この溶接部分93が隅肉溶接と同等の強度しか発揮することができないものとなる。また、従来の杭頭補強構造90は、鋼板92の裏側94が海水面に近接していることから、鋼板92の裏側94から溶接することも困難であり、鋼板92の端部96で十分な溶接強度を得ることができないものとなる。   Furthermore, as shown in FIG. 21, the conventional pile head reinforcing structure 90 is based on a steel plate 92 in which a pile head 91 of a foundation pile is extended to the inside of the upper structure 97 and a foundation beam main bar 95 is welded. When welded to the pile head 91 of the pile, in particular, the end portion 96 of the steel plate 92 is in a state close to incomplete penetration welding, and the welded portion 93 can exhibit only the same strength as fillet welding. It becomes. Moreover, since the back side 94 of the steel plate 92 is close to the sea surface, the conventional pile head reinforcing structure 90 is difficult to weld from the back side 94 of the steel plate 92, and the end portion 96 of the steel plate 92 is sufficient. The welding strength cannot be obtained.

このとき、従来の杭頭補強構造90は、上部構造物97の荷重等で基礎梁主筋95から作用する引張力によって、鋼板92の端部96が基礎杭の杭頭部91から脱離されることになり、基礎杭の杭頭部91と上部構造物97との接合強度が不十分なものとなるため、上部構造物97が倒壊するおそれがあるという問題点があった。   At this time, in the conventional pile head reinforcing structure 90, the end portion 96 of the steel plate 92 is detached from the pile head 91 of the foundation pile by the tensile force acting from the foundation beam main reinforcement 95 due to the load of the upper structure 97 or the like. Therefore, since the joint strength between the pile head 91 of the foundation pile and the upper structure 97 becomes insufficient, there is a problem that the upper structure 97 may collapse.

そこで、本発明は、上述した問題点に鑑みて案出されたものであり、その目的とするところは、補強鋼材と基礎杭の杭頭部の外側面及び裏当金とを溶込溶接によって溶け込ませて一体化させ、補強鋼材と基礎杭の杭頭部とを十分な溶接強度で接合させることが可能となる杭頭構造及び杭頭構造の構築方法を提供することにある。   Therefore, the present invention has been devised in view of the above-described problems, and the object of the present invention is to insert the reinforcing steel material, the outer side surface of the pile head of the foundation pile and the backing metal by penetration welding. An object of the present invention is to provide a pile head structure and a construction method of the pile head structure that can be integrated by melting and joining the reinforcing steel material and the pile head of the foundation pile with sufficient welding strength.

第1発明の杭頭構造は、上部構造物の基礎杭に用いられる杭頭構造であって、杭頭部に取り付けられる補強鋼材と、前記補強鋼材の下方に設けられる裏当金とを備え、前記裏当金は、杭頭部の外周を取り囲むようにして、杭頭部に設けられて、前記補強鋼材は、前記補強鋼材の下面に前記裏当金が当接されて前記裏当金に載置された状態で、前記裏当金及び杭頭部の外側面に溶接されることを特徴とする。 The pile head structure of the first invention is a pile head structure used for a foundation pile of an upper structure, and includes a reinforcing steel material attached to the pile head and a backing metal provided below the reinforcing steel material, The backing metal is provided on the pile head so as to surround the outer periphery of the pile head, and the reinforcing steel material is brought into contact with the lower surface of the reinforcing steel material so that the backing metal comes into contact with the backing metal. It is welded to the outer surface of the backing metal and the pile head in the mounted state.

発明の杭頭構造は、第1発明において、前記裏当金は、杭頭部の外周を取り囲むようにして、帯状鋼板を巻き付けることによって、杭頭部に設けられることを特徴とする。 Pile Head structure of the second invention, Oite the first shot bright, the backing metal is characterized in that so as to surround the outer periphery of the pile head, by winding the steel strip, it is provided in the pile head And

発明の杭頭構造は、第発明において、前記裏当金は、締め金具付きの帯状鋼板に設けられた締め金具で締め付けられることによって、杭頭部に設けられることを特徴とする。 The pile head structure of the third invention is characterized in that, in the second invention, the backing metal is provided on the pile head by being tightened with a fastener provided on a belt-like steel plate with a fastener.

発明の杭頭構造は、第1発明において、前記裏当金は、杭頭部の外周を取り囲むようにして、L形断面鋼を巻き付けることによって、杭頭部に設けられることを特徴とする。 Pile Head structure of the fourth invention, Oite the first shot bright, the backing metal is that so as to surround the outer periphery of the pile head, by winding an L-shaped cross-section steel, provided pile head It is characterized by.

発明の杭頭構造は、第発明において、前記裏当金は、締め金具付きのL形断面鋼に設けられた締め金具で締め付けられることによって、杭頭部に設けられることを特徴とする。 The pile head structure of the fifth invention is characterized in that, in the fourth invention, the backing metal is provided at the pile head by being tightened with a fastener provided in an L-shaped cross-section steel with a fastener. To do.

発明の杭頭構造は、第1発明において、前記裏当金は、杭頭部の外周を取り囲むようにして、鉄筋を巻き付けることによって、杭頭部に設けられることを特徴とする。 Pile Head structure of the sixth invention, Oite the first shot bright, the backing metal has a characteristic so as to surround the outer periphery of the pile head, by winding the reinforcing bars, that provided in the pile head To do.

発明の杭頭構造は、第1発明〜第発明の何れかにおいて、前記裏当金は、杭頭部の外周を取り囲むようにして、複数に分割された分割裏当金が用いられて、杭頭部に設けられることを特徴とする。 The pile head structure of the seventh invention is the pile head structure according to any one of the first to sixth inventions, wherein the backing metal is divided into a plurality of divided backing metal so as to surround the outer periphery of the pile head. And provided on the pile head.

発明の杭頭構造は、第1発明〜第発明の何れかにおいて、前記裏当金は、基礎杭に形成された重防食層の上端部と重ならないようにして、杭頭部に設けられることを特徴とする。 The pile head structure according to an eighth aspect of the present invention is the pile head structure according to any one of the first to seventh aspects of the invention, wherein the backing metal is not overlapped with the upper end portion of the heavy anticorrosion layer formed on the foundation pile. It is provided.

発明の杭頭構造は、第1発明〜第発明の何れかにおいて、前記裏当金は、基礎杭に形成された重防食層の上端部と重なるようにして、杭頭部に設けられることを特徴とする。 The pile head structure of the ninth invention is the pile head structure according to any one of the first to seventh inventions, wherein the backing metal is provided on a pile head so as to overlap an upper end portion of a heavy anticorrosion layer formed on the foundation pile. It is characterized by being able to.

第1発明の杭頭構造は、第1発明〜第発明の何れかにおいて、前記裏当金は、基礎杭に形成された重防食層の上端部を、締め金具付きの帯状鋼板に設けられた締め金具で締め付けるようにして、杭頭部に設けられることを特徴とする。 Pile Head structure of the first 0 invention, in any one of the first invention to seventh invention, wherein the backing metal is a top end portion of the heavy duty layer formed on the foundation pile, provided in the steel strip with a fastener It is characterized in that it is provided on the pile head so as to be tightened with a tightened fastener .

第1発明の杭頭構造は、第1発明〜第1発明の何れかにおいて、前記補強鋼材は、上部構造物の補強鉄筋が取り付けられる鉄筋定着鋼板が用いられることを特徴とする。 Pile Head structure of the first 1 invention, in any one of the first invention to third 1 0 invention, the reinforcing steel is characterized in that reinforcing bars fixing steel reinforcement rebar of the superstructure is mounted is used.

第1発明の杭頭構造は、第1発明において、前記補強鋼材は、複数に分割された前記鉄筋定着鋼板が用いられることを特徴とする。 Pile Head structure of the first second invention, in the first first invention, the reinforcing steel, characterized in that the reinforcing bar fixing steel sheet which is divided into a plurality are used.

第1発明の杭頭構造は、第1発明において、前記補強鋼材は、一体化された前記鉄筋定着鋼板が用いられることを特徴とする。 Pile Head structure of the first third invention, in the first first invention, the reinforcing steel is characterized in that it integrated the reinforcing bar fixing steel sheet is used.

第1発明の杭頭構造の構築方法は、上部構造物の基礎杭に用いられる杭頭構造の構築方法であって、杭頭部の外周を取り囲むようにして、杭頭部に裏当金を設ける第1工程と、前記裏当金に補強鋼材の端部を載置した状態で、前記補強鋼材の端部を溶接によって杭頭部の外側面に取り付ける第2工程とを備えることを特徴とする。 Method for constructing a pile head structure of the first 4 invention is a method for constructing a pile structure used in the foundation pile the upper structure, so as to surround the outer periphery of the pile head, the backing metal to pile head And a second step of attaching the end of the reinforcing steel to the outer surface of the pile head by welding in a state where the end of the reinforcing steel is placed on the backing metal. Features.

第1発明の杭頭構造の構築方法は、第1発明において、前記第1工程では、杭頭部の外周を取り囲むようにして、帯状鋼板を巻き付けることによって、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the first 5 invention is the first fourth invention, in the first step, so as to surround the outer periphery of the pile head, by winding the steel strip, said the pile head Urato It is characterized by providing gold.

第1発明の杭頭構造の構築方法は、第1発明において、前記第1工程では、締め金具付きの前記帯状鋼板に設けられた締め金具で締め付けることによって、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the first to sixth aspects, in the first 5 invention, wherein in the first step, by tightening with fastener provided on said steel strip with a fastener, wherein the pile head Urato It is characterized by providing gold.

第1発明の杭頭構造の構築方法は、第1発明において、前記第1工程では、杭頭部の外周を取り囲むようにして、L形断面鋼を巻き付けることによって、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the first seventh invention, in the first 4 invention, in the first step, so as to surround the outer periphery of the pile head, by winding an L-shaped cross-section steel, the the pile head A backing metal is provided.

第1発明の杭頭構造の構築方法は、第1発明において、前記第1工程では、締め金具付きの前記L形断面鋼に設けられた締め金具で締め付けることによって、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the first eighth invention, in the first 7 invention, in the first step, by tightening with fastener provided on the L-section steel with a fastener, wherein the pile head A backing metal is provided.

19発明の杭頭構造の構築方法は、第1発明において、前記第1工程では、杭頭部の外周を取り囲むようにして、鉄筋を巻き付けることによって、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the nineteenth invention, in the first 4 invention, in the first step, so as to surround the outer periphery of the pile head, by winding the reinforcing bars, the backing metal to pile head It is characterized by providing.

第2発明の杭頭構造の構築方法は、第1発明〜第19発明の何れかにおいて、前記第1工程では、複数に分割された分割裏当金を用いて、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the second 0 invention, in any one of the first 4 invention to nineteenth invention, wherein in the first step, by using a divided backing metal which is divided into a plurality, the the pile head A backing metal is provided.

第2発明の杭頭構造の構築方法は、第1発明〜第2発明の何れかにおいて、前記第1工程では、基礎杭に形成された重防食層の上端部と重ならないようにして、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the second 1 invention, in any one of the first 4 invention - second 0 invention, in the first step, so as not to overlap with the upper portion of the heavy duty layer formed on the foundation pile And the backing metal is provided on the pile head.

第2発明の杭頭構造の構築方法は、第1発明〜第2発明の何れかにおいて、前記第1工程では、基礎杭に形成された重防食層の上端部と重なるようにして、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the second second invention, in any of the first 4 invention - second 0 invention, in the first step, so as to overlap with the upper portion of the heavy duty layer formed on the foundation pile The above-mentioned backing metal is provided on the pile head.

第2発明の杭頭構造の構築方法は、第1発明〜第2発明の何れかにおいて、前記第1工程では、基礎杭に形成された重防食層の上端部を、締め金具付きの帯状鋼板に設けられた締め金具で締め付けるようにして、杭頭部に前記裏当金を設けることを特徴とする。 Method for constructing a pile head structure of the second third invention, in any of the first 4 invention - second 0 invention, in the first step, the upper end portion of the heavy duty layer formed on the foundation pile, with fastener The backing metal is provided on the pile head so as to be tightened with a fastener provided on the belt-shaped steel plate .

第2発明の杭頭構造の構築方法は、第1発明〜第2発明の何れかにおいて、前記第2工程では、上部構造物の補強鉄筋が取り付けられる鉄筋定着鋼板を前記補強鋼材として用いることを特徴とする。 Method for constructing a pile head structure of the second fourth invention, in any of the first 4 invention - second third invention, in the second step, the reinforcing bar fixing steel reinforcement rebar of the superstructure is mounted as the reinforcing steel It is characterized by using.

第2発明の杭頭構造の構築方法は、第2発明において、前記第2工程では、複数に分割された前記鉄筋定着鋼板を前記補強鋼材として用いることを特徴とする。 The construction method of a pile head structure according to a twenty- fifth aspect of the invention is characterized in that, in the twenty- fourth aspect , in the second step, the reinforcing steel sheet divided into a plurality of reinforcing bars is used as the reinforcing steel material.

第26発明の杭頭構造の構築方法は、第2発明において、前記第2工程では、一体化された前記鉄筋定着鋼板を前記補強鋼材として用いることを特徴とする。 The construction method of a pile head structure according to a twenty-sixth aspect of the invention is characterized in that, in the twenty- fourth aspect , in the second step, the integrated reinforcing steel plate is used as the reinforcing steel material.

第1発明〜第1発明によれば、補強鋼材の下面に裏当金が当接された状態で、補強鋼材が基礎杭の杭頭部の外側面及び裏当金に溶接されるため、補強鋼材と基礎杭の杭頭部の外側面及び裏当金とが溶け込んで一体化されるものとなり、溶込溶接によって補強鋼材と基礎杭の杭頭部とを十分な溶接強度で接合させることが可能となる。 According to the first aspect of the invention - the first first invention, since the backing metal to the lower surface of the reinforcing steel is in a state of being contact, the reinforcing steel is welded to the outer surface and the backing metal of the pile head of the foundation pile, Reinforced steel and the outer surface of the pile head of the foundation pile and the backing metal are fused and integrated, and the reinforcement steel and the pile head of the foundation pile are joined with sufficient welding strength by penetration welding. Is possible.

第1発明〜第1発明によれば、補強鋼材に取り付けられた補強鉄筋から引張力が作用した場合であっても、補強鋼材が基礎杭の杭頭部から脱離することを防止することが可能となり、基礎杭と上部構造物との接合強度を十分なものとして、上部構造物が倒壊することを防止することが可能となる。 According to 1st invention-11th invention, even if it is a case where a tensile force acts from the reinforcement reinforcement attached to the reinforcement steel material, it prevents that a reinforcement steel material detaches | leaves from the pile head of a foundation pile. It becomes possible, and it becomes possible to prevent the upper structure from collapsing by making the joint strength between the foundation pile and the upper structure sufficient.

第1発明〜第発明によれば、基礎杭の杭頭部の外周を取り囲むようにして設けられた裏当金に、補強鋼材の端部が載置されるため、基礎杭の杭頭部の外周で複数の補強鋼材の高さを容易に合わせることができ、複数の補強鋼材の取付作業を容易にすることが可能となる。 According to 1st invention- 7th invention, since the edge part of a reinforcement steel material is mounted in the backing metal provided so that the outer periphery of the pile head of a foundation pile may be surrounded, the pile head of a foundation pile It is possible to easily match the heights of the plurality of reinforcing steel materials on the outer periphery, and to facilitate the mounting work of the plurality of reinforcing steel materials.

特に、第発明、第1発明によれば、裏当金が重防食層の上端部と重なるようにして設けられるため、重防食層の上端部と基礎杭の杭頭部の外側面との隙間に、海水等が浸入することを防止することができ、海水等の浸入によって基礎杭が腐食することを防止することが可能となる。 Particularly, according to the ninth invention and the tenth invention, since the backing metal is provided so as to overlap the upper end portion of the heavy-duty protection layer, the upper end portion of the heavy-duty protection layer and the outer side surface of the pile head of the foundation pile, It is possible to prevent seawater and the like from entering the gap, and it is possible to prevent the foundation pile from being corroded by the intrusion of seawater and the like.

第1発明〜第2発明によれば、補強鋼材に取り付けられた補強鉄筋から引張力が作用した場合であっても、補強鋼材が基礎杭の杭頭部から脱離することを防止することが可能となり、基礎杭と上部構造物との接合強度を十分なものとして、上部構造物が倒壊することを防止することが可能となる。 According to the first 4 invention - second 6 invention, even tensile force from the reinforcing reinforcement attached to the reinforcing steel is a case where the action, to prevent the steel reinforced material is desorbed from the pile head of the foundation pile Therefore, it is possible to prevent the upper structure from collapsing with sufficient bonding strength between the foundation pile and the upper structure.

特に、第1発明〜第2発明によれば、基礎杭の杭頭部の外周を取り囲むようにして設けられた裏当金に、補強鋼材の端部が載置されるため、基礎杭の杭頭部の外周で複数の補強鋼材の高さを容易に合わせることができ、複数の補強鋼材の取付作業を容易にすることが可能となる。 In particular, according to the first 5 invention - second 0 invention, since the backing metal provided so as to surround the outer periphery of the pile head of the foundation pile, the ends of the reinforcement steel is placed, the foundation pile It is possible to easily match the heights of the plurality of reinforcing steel materials on the outer periphery of the pile head and to facilitate the mounting work of the plurality of reinforcing steel materials.

特に、第2発明、第2発明によれば、裏当金が重防食層の上端部と重なるようにして設けられるため、重防食層の上端部と基礎杭の杭頭部の外側面との隙間に、海水等が浸入することを防止することができ、海水等の浸入によって基礎杭が腐食することを防止することが可能となる。 In particular, the second second invention, according to the second third invention, since the backing gold is provided so as to overlap with the upper portion of the heavy duty layer, the outer surface of the pile head of the upper and foundation pile heavy anticorrosion layer It is possible to prevent seawater and the like from entering the gap, and it is possible to prevent the foundation pile from being corroded by the intrusion of seawater and the like.

本発明を適用した杭頭構造が設けられた上部構造物を示す斜視図である。It is a perspective view which shows the upper structure in which the pile head structure to which this invention was applied was provided. 本発明を適用した杭頭構造を示す斜視図である。It is a perspective view which shows the pile head structure to which this invention is applied. (a)は、本発明を適用した杭頭構造が用いられる基礎杭を示す正面図であり、(b)は、その平面図である。(A) is a front view which shows the foundation pile in which the pile head structure to which this invention is applied is used, (b) is the top view. 本発明を適用した杭頭構造の第1実施形態を示す平面図である。It is a top view which shows 1st Embodiment of the pile head structure to which this invention is applied. 本発明を適用した杭頭構造の第1実施形態の変形例を示す平面図である。It is a top view which shows the modification of 1st Embodiment of the pile head structure to which this invention is applied. 本発明を適用した杭頭構造の第1実施形態を示す断面図である。It is sectional drawing which shows 1st Embodiment of the pile head structure to which this invention is applied. (a)は、本発明を適用した杭頭構造の帯状鋼板を示す平面図であり、(b)は、ヒンジと締め金具とが設けられた帯状鋼板を示す平面図である。(A) is a top view which shows the strip | belt-shaped steel plate of the pile head structure to which this invention is applied, (b) is a top view which shows the strip | belt-shaped steel plate provided with the hinge and the fastener. (a)は、本発明を適用した杭頭構造の2分割された分割裏当金を示す平面図であり、(b)は、4分割された分割裏当金を示す平面図である。(A) is a top view which shows the split backing metal divided into 2 of the pile head structure to which this invention is applied, (b) is a top view which shows the split backing metal divided into 4 parts. (a)は、本発明を適用した杭頭構造の裏当金を示す拡大断面図であり、(b)は、その第1変形例を示す拡大断面図である。(A) is an expanded sectional view which shows the backing metal of the pile head structure to which this invention is applied, (b) is an expanded sectional view which shows the 1st modification. (a)は、本発明を適用した杭頭構造の裏当金の第2変形例を示す拡大断面図であり、(b)は、その第3変形例を示す拡大断面図である。(A) is an expanded sectional view which shows the 2nd modification of the backing metal of the pile head structure to which this invention is applied, (b) is an expanded sectional view which shows the 3rd modification. (a)は、本発明を適用した杭頭構造の裏当金の第4変形例を示す拡大断面図であり、(b)は、その第5変形例を示す拡大断面図である。(A) is an expanded sectional view which shows the 4th modification of the backing metal of the pile head structure to which this invention is applied, (b) is an expanded sectional view which shows the 5th modification. (a)は、本発明を適用した杭頭構造の裏当金の第6変形例を示す拡大断面図であり、(b)は、その第7変形例を示す拡大断面図である。(A) is an expanded sectional view which shows the 6th modification of the backing metal of the pile head structure to which this invention is applied, (b) is an expanded sectional view which shows the 7th modification. (a)は、本発明を適用した杭頭構造の裏当金に鉄筋が用いられた態様を示す断面図であり、(b)は、その平面図である。(A) is sectional drawing which shows the aspect by which the reinforcing bar was used for the backing metal of the pile head structure to which this invention is applied, (b) is the top view. (a)は、本発明を適用した杭頭構造の構築方法における第1工程を説明する正面図であり、(b)は、その平面図である。(A) is a front view explaining the 1st process in the construction method of the pile head structure to which the present invention is applied, and (b) is the top view. (a)は、本発明を適用した杭頭構造の構築方法における第2工程を説明する正面図であり、(b)は、その平面図である。(A) is a front view explaining the 2nd process in the construction method of the pile head structure to which the present invention is applied, and (b) is the top view. 本発明を適用した杭頭構造の補強鋼材と裏当金及び基礎杭の杭頭部の外側面との溶接箇所を示す拡大断面図である。It is an expanded sectional view which shows the welding location with the reinforcement steel material of the pile head structure to which this invention is applied, backing metal, and the outer surface of the pile head of a foundation pile. 本発明を適用した杭頭構造の第1実施形態を示す正面図である。It is a front view which shows 1st Embodiment of the pile head structure to which this invention is applied. 本発明を適用した杭頭構造の裏当金によって重防食層の上端部と基礎杭の杭頭部の外側面との隙間に海水等が浸入することを防止した状態を示す拡大断面図である。It is an expanded sectional view which shows the state which prevented the seawater etc. invading into the clearance gap between the upper end part of a heavy-duty protection layer, and the outer side of the pile head of a foundation pile by the backing metal of the pile head structure to which the present invention is applied. . 本発明を適用した杭頭構造の第2実施形態を示す平面図である。It is a top view which shows 2nd Embodiment of the pile head structure to which this invention is applied. 本発明を適用した杭頭構造の第2実施形態を示す正面図である。It is a front view which shows 2nd Embodiment of the pile head structure to which this invention is applied. 従来の杭頭補強構造を示す拡大断面図である。It is an expanded sectional view showing the conventional pile head reinforcement structure.

以下、本発明を適用した杭頭構造1を実施するための形態について、図面を参照しながら詳細に説明する。   Hereinafter, the form for carrying out pile head structure 1 to which the present invention is applied is explained in detail, referring to drawings.

本発明を適用した杭頭構造1は、図1に示すように、主に、港湾鋼構造物等の水域構造物、擁壁、土留壁、フーチング等の陸域構造物等を上部構造物7として、これらの上部構造物7の基礎杭10となる鋼管杭等の杭頭部11に設けられるものである。   As shown in FIG. 1, the pile head structure 1 to which the present invention is applied mainly includes water structures such as harbor steel structures, land structures such as retaining walls, retaining walls, footings, and the like as upper structures 7. As mentioned above, the pile heads 11 such as steel pipe piles to be the foundation piles 10 of these superstructures 7 are provided.

本発明を適用した杭頭構造1は、図2に示すように、基礎杭10の杭頭部11に取り付けられる補強鋼材2と、補強鋼材2の下方に設けられる裏当金3とを備え、基礎杭10の杭頭部11が上部構造物7に埋め込まれることによって、基礎杭10と上部構造物7とが接合される。   As shown in FIG. 2, the pile head structure 1 to which the present invention is applied includes a reinforcing steel material 2 attached to the pile head 11 of the foundation pile 10 and a backing metal 3 provided below the reinforcing steel material 2. The pile head 11 of the foundation pile 10 is embedded in the upper structure 7, whereby the foundation pile 10 and the upper structure 7 are joined.

上部構造物7は、複数の補強鉄筋5が内部に配設された鉄筋コンクリート等を、現場打ちのコンクリート等で構築するものであり、複数の基礎杭10で下方から支持されるものである。上部構造物7は、現場打ちのコンクリート等で構築された鉄筋コンクリートの下面7aの近傍に、略水平方向に延びる複数の補強鉄筋5が設けられる。   The upper structure 7 is constructed by constructing reinforced concrete or the like in which a plurality of reinforcing reinforcing bars 5 are arranged with concrete made in the field, and is supported by a plurality of foundation piles 10 from below. The upper structure 7 is provided with a plurality of reinforcing reinforcing bars 5 extending in a substantially horizontal direction in the vicinity of the lower surface 7a of the reinforced concrete constructed of concrete cast on the spot.

複数の補強鉄筋5は、略水平方向に延びる複数の補強鉄筋5の一部が略矩形状に切り欠かれる。このとき、複数の補強鉄筋5は、鉄筋コンクリート等の上部構造物7の下面7aの近傍で、基礎杭10の杭頭部11と干渉することのないように設けられて、上部構造物7に作用する引張力に対して、複数の補強鉄筋5で対抗するものとなる。   In the plurality of reinforcing bars 5, a part of the plurality of reinforcing bars 5 extending in a substantially horizontal direction is cut out in a substantially rectangular shape. At this time, the plurality of reinforcing reinforcing bars 5 are provided in the vicinity of the lower surface 7 a of the upper structure 7 such as reinforced concrete so as not to interfere with the pile head 11 of the foundation pile 10 and act on the upper structure 7. A plurality of reinforcing reinforcing bars 5 counteract the tensile force to be applied.

基礎杭10は、断面略円形状の鋼管杭や、鋼管矢板等が用いられる。基礎杭10は、図3(a)に示すように、下端部10aから中間部10bまで地盤80に打ち込まれ、地盤80から支持力を得るものとなる。基礎杭10は、下端部10a又は中間部10bから上端部10cまでの間に、上端部10cから所定の間隔を空けた状態で、重防食層12が形成される。   As the foundation pile 10, a steel pipe pile having a substantially circular cross section, a steel pipe sheet pile, or the like is used. As shown in FIG. 3A, the foundation pile 10 is driven into the ground 80 from the lower end portion 10 a to the intermediate portion 10 b, and obtains support force from the ground 80. In the foundation pile 10, the heavy anticorrosion layer 12 is formed between the lower end portion 10 a or the intermediate portion 10 b and the upper end portion 10 c with a predetermined distance from the upper end portion 10 c.

重防食層12は、上部構造物7の下面7aから3cm〜5cm程度の高さで離間した位置で、基礎杭10の杭頭部11の外周を取り囲むようにして、上端部12aが形成される。重防食層12は、基礎杭10が海中81に設けられる範囲等で、図3(b)に示すように、鋼管杭や鋼管矢板等の基礎杭10の外周が、エポキシ樹脂等で被覆されることによって形成される。   The heavy-duty anticorrosion layer 12 is formed at the position separated from the lower surface 7a of the upper structure 7 at a height of about 3 cm to 5 cm so as to surround the outer periphery of the pile head 11 of the foundation pile 10 and the upper end portion 12a is formed. . As shown in FIG. 3 (b), the heavy-duty anticorrosion layer 12 is an area where the foundation pile 10 is provided in the sea 81, and the outer periphery of the foundation pile 10 such as a steel pipe pile or a steel pipe sheet pile is covered with an epoxy resin or the like. Formed by.

本発明を適用した杭頭構造1は、図4に示すように、第1実施形態において、基礎杭10として鋼管杭が用いられ、補強鋼材2として4枚等の複数に分割された略平板状の鉄筋定着鋼板4が用いられる。本発明を適用した杭頭構造1は、第1実施形態において、これに限らず、図5に示すように、補強鋼材2として一体化された略平板状の鉄筋定着鋼板4が変形例として用いられてもよい。   As shown in FIG. 4, the pile head structure 1 to which the present invention is applied has a substantially flat plate shape in which a steel pipe pile is used as the foundation pile 10 and the reinforcing steel material 2 is divided into a plurality of pieces such as four pieces as shown in FIG. 4. Reinforcing steel plate 4 is used. The pile head structure 1 to which the present invention is applied is not limited to this in the first embodiment. As shown in FIG. 5, a substantially flat reinforcing bar fixing steel plate 4 integrated as a reinforcing steel material 2 is used as a modification. May be.

鉄筋定着鋼板4は、図4に示すように、杭頭部11の外側面11aに溶接で取り付けられる側端部41と、複数の補強鉄筋5が溶接で取り付けられる取付部42とを備える。4枚の鉄筋定着鋼板4は、基礎杭10の杭頭部11の外周を取り囲むようにして、略水平方向に並べて設けられる。   As shown in FIG. 4, the reinforcing steel plate 4 includes a side end 41 that is attached to the outer surface 11 a of the pile head 11 by welding, and an attachment portion 42 to which the plurality of reinforcing reinforcing bars 5 are attached by welding. The four reinforcing steel plates 4 are arranged side by side in a substantially horizontal direction so as to surround the outer periphery of the pile head 11 of the foundation pile 10.

鉄筋定着鋼板4は、杭頭部11の外側面11aに沿うように、側端部41が略円弧状に形成されるとともに、図6に示すように、鉄筋定着鋼板4の下面4aから上面4bに向けて、拡径するように傾斜した開先面41aが側端部41に形成される。鉄筋定着鋼板4は、上面4bに複数の補強鉄筋5を並べて載置できるように、取付部42が略平板状に形成される。   Reinforcing bar fixing steel plate 4 has side end portion 41 formed in a substantially arc shape along outer side surface 11a of pile head 11 and, as shown in FIG. A groove surface 41a that is inclined so as to expand in diameter is formed on the side end portion 41. The reinforcing member fixing steel sheet 4 has a mounting portion 42 formed in a substantially flat plate shape so that a plurality of reinforcing reinforcing bars 5 can be placed side by side on the upper surface 4b.

裏当金3は、図7(a)に示すように、杭頭部11の外側面11aに沿うように、略円形状に形成された帯状鋼板30が用いられる。裏当金3は、これに限らず、如何なる材質のものが用いられてもよく、例えば、銅を材質とした帯状銅板が用いられてもよい。裏当金3は、杭頭部11の外側面11aに、溶接等で仮止めされて固定される。裏当金3は、図7(b)に示すように、帯状鋼板30にヒンジ32が設けられて、締め金具33で固定されてもよい。なお、裏当金3は、これに限らず、図示しないL形断面鋼34にヒンジ32が設けられて、締め金具33で固定されてもよい。   As the backing metal 3, as shown in FIG. 7A, a strip-shaped steel plate 30 formed in a substantially circular shape so as to follow the outer surface 11 a of the pile head 11 is used. The backing metal 3 is not limited to this, and any material may be used. For example, a strip-shaped copper plate made of copper may be used. The backing metal 3 is temporarily fixed to the outer side surface 11a of the pile head 11 by welding or the like. As shown in FIG. 7B, the backing metal 3 may be provided with a hinge 32 on the belt-shaped steel plate 30 and fixed with a fastener 33. The backing metal 3 is not limited to this, and a hinge 32 may be provided on an L-shaped steel 34 (not shown), and the backing metal 3 may be fixed by a fastener 33.

裏当金3は、例えば、図8(a)に示すように、杭頭部11の外周を取り囲むようにして、2分割された分割裏当金31が杭頭部11に巻き付けられて、杭頭部11に設けられる。裏当金3は、これに限らず、如何なる数量によって複数に分割された分割裏当金31が杭頭部11に巻き付けられてもよく、例えば、図8(b)に示すように、4分割された分割裏当金31が杭頭部11に巻き付けられて、杭頭部11に設けられてもよい。   For example, as shown in FIG. 8A, the backing metal 3 surrounds the outer periphery of the pile head 11, and the divided backing metal 31 divided into two is wound around the pile head 11. Provided on the head 11. The backing metal 3 is not limited to this, and the divided backing metal 31 divided into a plurality of pieces by any quantity may be wound around the pile head 11. For example, as shown in FIG. The divided split backing 31 may be wound around the pile head 11 and provided on the pile head 11.

裏当金3は、図9(a)に示すように、基礎杭10に形成された重防食層12の上端部12aと重なるようにして、帯状鋼板30が杭頭部11に設けられる。裏当金3は、帯状鋼板30が断面略矩形状に形成されて、重防食層12の上端部12aと重なる部分で、帯状鋼板30の中間部30bから下端部30aに向けて、拡径するように傾斜したテーパ部38が形成される。裏当金3は、図9(b)に示すように、第1変形例において、図7(b)に示す締め金具33で締め付けられることで、重防食層12の上端部12aをテーパ部38で押圧してもよい。   As shown in FIG. 9A, the strip steel plate 30 is provided on the pile head 11 such that the backing metal 3 overlaps the upper end portion 12 a of the heavy anticorrosion layer 12 formed on the foundation pile 10. The backing metal 3 is a portion in which the strip-shaped steel plate 30 is formed in a substantially rectangular shape and overlaps with the upper end portion 12a of the heavy anticorrosion layer 12, and the diameter is increased from the intermediate portion 30b of the strip-shaped steel plate 30 toward the lower end portion 30a. Thus, the inclined taper portion 38 is formed. As shown in FIG. 9 (b), the backing metal 3 is tightened with the fastener 33 shown in FIG. 7 (b) in the first modification, so that the upper end portion 12a of the heavy anticorrosion layer 12 is tapered. You may press with.

裏当金3は、例えば、管軸直交方向Xの板厚tが0.6〜1.2cm程度で、管軸方向Yの高さhが1〜10cm程度の帯状鋼板30が用いられ、特に、管軸方向Yの高さhを5cm程度とすることが望ましい。これにより、裏当金3は、帯状鋼板30の形態安定性を向上させることができ、帯状鋼板30の運搬や、杭頭部11への設置を容易にすることが可能となる。   The backing metal 3 is, for example, a strip steel plate 30 having a thickness t in the tube axis orthogonal direction X of about 0.6 to 1.2 cm and a height h in the tube axis direction Y of about 1 to 10 cm. The height h in the tube axis direction Y is preferably about 5 cm. Thereby, the backing metal 3 can improve the form stability of the strip-shaped steel plate 30, and can facilitate the transportation of the strip-shaped steel plate 30 and the installation to the pile head 11.

裏当金3は、図10(a)に示すように、第2変形例において、重防食層12の上端部12aと重ならないようにして、杭頭部11に設けられる。また、裏当金3は、図10(b)に示すように、第3変形例において、重防食層12の上端部12aと重なるようにして、杭頭部11に設けられ、重防食層12の上端部12aと重なる部分で、帯状鋼板30の中間部30bから下端部30aにかけて、切欠部39が形成されてもよい。   As shown in FIG. 10A, the backing metal 3 is provided on the pile head 11 so as not to overlap the upper end portion 12a of the heavy anticorrosion layer 12 in the second modification. Further, as shown in FIG. 10 (b), the backing metal 3 is provided on the pile head 11 so as to overlap the upper end portion 12 a of the heavy anticorrosion layer 12 in the third modification, and the heavy anticorrosion layer 12. A cutout portion 39 may be formed from the middle portion 30b of the strip steel plate 30 to the lower end portion 30a at a portion overlapping the upper end portion 12a.

裏当金3は、図11(a)に示すように、第4変形例において、重防食層12の上端部12aと重なるようにして、帯状鋼板30の上端部30cから下端部30aにかけて、テーパ部38や切欠部39を形成させることなく、帯状鋼板30を傾斜させて設けられる。また、裏当金3は、図11(b)に示すように、第5変形例において、重防食層12の上端部12aと重なるようにして、帯状鋼板30の上端部30cから下端部30aにかけて、帯状鋼板30を湾曲させて設けられる。   As shown in FIG. 11A, the backing metal 3 is tapered from the upper end 30c to the lower end 30a of the strip steel plate 30 so as to overlap the upper end 12a of the heavy anticorrosion layer 12 in the fourth modification. The belt-shaped steel plate 30 is provided to be inclined without forming the portion 38 and the notch 39. Further, as shown in FIG. 11 (b), the backing metal 3 extends from the upper end 30c to the lower end 30a of the strip steel plate 30 so as to overlap the upper end 12a of the heavy anticorrosion layer 12 in the fifth modification. The belt-shaped steel plate 30 is provided by being bent.

裏当金3は、図12(a)に示すように、第6変形例において、重防食層12の上端部12aと重なるようにして、L形断面鋼34の上端部30cから下端部30aにかけて、テーパ部38や切欠部39を形成させることなく、L形断面鋼34を傾斜させて設けられる。また、裏当金3は、図12(b)に示すように、第7変形例において、重防食層12の上端部12aと重なるようにして、L形断面鋼34の上端部30cから下端部30aにかけて、L形断面鋼34を湾曲させて設けられる。   As shown in FIG. 12A, the backing metal 3 extends from the upper end 30c to the lower end 30a of the L-shaped cross-section steel 34 so as to overlap the upper end 12a of the heavy anticorrosion layer 12 in the sixth modification. The L-shaped cross-section steel 34 is provided to be inclined without forming the tapered portion 38 or the cutout portion 39. Further, as shown in FIG. 12B, the backing metal 3 is overlapped with the upper end portion 12a of the heavy anticorrosion layer 12 so as to overlap with the lower end portion from the upper end portion 30c of the L-shaped cross section steel 34 in the seventh modification. The L-shaped cross-section steel 34 is bent over 30a.

なお、裏当金3は、図13(a)に示すように、断面略円形状に形成された鉄筋35が用いられ、重防食層12の上端部12aが締め付けられることで、鉄筋35が杭頭部11に設けられてもよい。このとき、裏当金3は、図13(b)に示すように、鉄筋35が杭頭部11に巻き付けられることによって、杭頭部11に設けられる。裏当金3は、これに限らず、重防食層12の上端部12aと重ならないようにして、鉄筋35が杭頭部11に設けられてもよい。   As shown in FIG. 13A, the backing metal 3 uses a reinforcing bar 35 having a substantially circular cross section, and the upper end portion 12a of the heavy anticorrosion layer 12 is tightened so that the reinforcing bar 35 is piled up. The head 11 may be provided. At this time, the backing metal 3 is provided on the pile head 11 by winding the reinforcing bar 35 around the pile head 11 as shown in FIG. The backing metal 3 is not limited to this, and the reinforcing bar 35 may be provided on the pile head 11 so as not to overlap the upper end portion 12 a of the heavy anticorrosion layer 12.

本発明を適用した杭頭構造1は、図4、図6に示すように、4枚の略平板状の鉄筋定着鋼板4の側端部41が、杭頭部11の外周を取り囲むようにして、杭頭部11の外側面11aに取り付けられる。本発明を適用した杭頭構造1は、鉄筋定着鋼板4の下面4aが裏当金3の上面3aに当接された状態で、裏当金3の上面3a及び杭頭部11の外側面11aに、鉄筋定着鋼板4の側端部41が溶接によって取り付けられる。   As shown in FIGS. 4 and 6, the pile head structure 1 to which the present invention is applied is such that the side end portions 41 of the four substantially flat reinforcing steel plates 4 surround the outer periphery of the pile head 11. It is attached to the outer surface 11a of the pile head 11. The pile head structure 1 to which the present invention is applied has the upper surface 3a of the backing metal 3 and the outer surface 11a of the pile head 11 in a state where the lower surface 4a of the reinforcing steel plate 4 is in contact with the upper surface 3a of the backing metal 3. Moreover, the side edge part 41 of the reinforcing steel plate 4 is attached by welding.

本発明を適用した杭頭構造1の構築方法は、第1実施形態において、基礎杭10の杭頭部11に裏当金3を設ける第1工程と、補強鋼材2の端部を溶接によって杭頭部11の外側面11a取り付ける第2工程とを備える。   The construction method of the pile head structure 1 to which the present invention is applied is the first embodiment in which the backing metal 3 is provided on the pile head 11 of the foundation pile 10 and the end of the reinforcing steel material 2 is piled by welding. And a second step of attaching the outer surface 11a of the head 11.

本発明を適用した杭頭構造1の構築方法は、第1工程において、図14に示すように、杭頭部11の外周を取り囲むようにして、裏当金3となる帯状鋼板30を杭頭部11に巻き付けて、基礎杭10の杭頭部11に裏当金3を設けるものである。このとき、帯状鋼板30は、締め金具33付きのものが用いられて、重防食層12の上端部12aと重なるようにして設けられ、締め金具33で締め付けられてもよく、また、重防食層12の上端部12aと重ならないようにして設けられてもよい。なお、裏当金3は、これに限らず、締め金具33付きのL形断面鋼34や、鉄筋35等が用いられてもよい。   In the first step, the construction method of the pile head structure 1 to which the present invention is applied is as follows. As shown in FIG. 14, the strip steel plate 30 to be the backing metal 3 is surrounded by the pile head 11 so as to surround the outer periphery of the pile head 11. The backing metal 3 is provided on the pile head 11 of the foundation pile 10 by being wound around the portion 11. At this time, the strip-shaped steel plate 30 is provided with a fastener 33 and is provided so as to overlap the upper end portion 12a of the heavy anticorrosion layer 12, and may be tightened with the fastener 33, or the heavy anticorrosion layer. 12 may be provided so as not to overlap with the upper end portion 12a. The backing metal 3 is not limited to this, and an L-shaped cross-section steel 34 with a fastener 33, a reinforcing bar 35, or the like may be used.

本発明を適用した杭頭構造1の構築方法は、第2工程において、図15に示すように、複数の補強鉄筋5が略水平方向に並べられて、鉄筋定着鋼板4の略平板状に形成された取付部42に、複数の補強鉄筋5の先端が溶接によって取り付けられる。このとき、鉄筋定着鋼板4は、基礎杭10の杭頭部11の外側面11aに、補強鋼材2の端部となる鉄筋定着鋼板4の側端部41が溶接によって取り付けられる。   In the second step, the construction method of the pile head structure 1 to which the present invention is applied has a plurality of reinforcing bars 5 arranged in a substantially horizontal direction and formed in a substantially flat plate shape of the reinforcing steel sheet 4 as shown in FIG. The tips of the plurality of reinforcing reinforcing bars 5 are attached to the attached mounting portion 42 by welding. At this time, the side end 41 of the reinforcing steel plate 4 that is the end of the reinforcing steel material 2 is attached to the outer surface 11a of the pile head 11 of the foundation pile 10 by welding.

本発明を適用した杭頭構造1の構築方法は、詳述すると、第2工程において、図16に示すように、第1工程で基礎杭10の杭頭部11に設けられた裏当金3の上面3aに、補強鋼材2の端部となる鉄筋定着鋼板4の側端部41を載置して、開先面41aを溶接することによって、基礎杭10の杭頭部11の外側面11a及び裏当金3の上面3aに、鉄筋定着鋼板4の側端部41を取り付けるものとなる。   The construction method of the pile head structure 1 to which the present invention is applied will be described in detail. In the second step, as shown in FIG. 16, the backing metal 3 provided on the pile head 11 of the foundation pile 10 in the first step. By placing the side end 41 of the reinforcing steel plate 4 serving as the end of the reinforcing steel material 2 on the upper surface 3a of the steel plate and welding the groove surface 41a, the outer side surface 11a of the pile head 11 of the foundation pile 10 is obtained. And the side edge part 41 of the reinforcing bar fixing steel plate 4 is attached to the upper surface 3 a of the backing metal 3.

本発明を適用した杭頭構造1は、補強鋼材2として用いられる鉄筋定着鋼板4の下面4aに、裏当金3の上面3aが当接された状態で、鉄筋定着鋼板4の側端部41が開先面41aで溶接されるため、鉄筋定着鋼板4の側端部41と、基礎杭10の杭頭部11の外側面11a及び裏当金3の上面3aとが十分に溶け込んで一体化されるものとなる。   The pile head structure 1 to which the present invention is applied has a side end 41 of the reinforcing bar fixing steel plate 4 in a state where the upper surface 3a of the backing metal 3 is in contact with the lower surface 4a of the reinforcing steel plate 4 used as the reinforcing steel material 2. Is welded at the groove surface 41a, the side end 41 of the reinforcing steel plate 4 and the outer surface 11a of the pile head 11 of the foundation pile 10 and the upper surface 3a of the backing metal 3 are sufficiently melted and integrated. Will be.

このとき、本発明を適用した杭頭構造1は、補強鋼材2として用いられる鉄筋定着鋼板4の側端部41を基礎杭10の杭頭部11の外側面11aに溶込溶接させて、鉄筋定着鋼板4と基礎杭10の杭頭部11とを十分な溶接強度で接合させることができる。   At this time, the pile head structure 1 to which the present invention is applied is such that the side end portion 41 of the reinforcing steel plate 4 used as the reinforcing steel material 2 is welded and welded to the outer surface 11a of the pile head 11 of the foundation pile 10. The fixing steel plate 4 and the pile head 11 of the foundation pile 10 can be joined with sufficient welding strength.

これにより、本発明を適用した杭頭構造1は、補強鋼材2として用いられる鉄筋定着鋼板4に取り付けられた複数の補強鉄筋5から引張力が作用した場合であっても、鉄筋定着鋼板4が基礎杭10の杭頭部11から脱離することを防止することが可能となる。   Thereby, the pile head structure 1 to which the present invention is applied is such that the reinforcing steel sheet 4 is provided even when tensile force is applied from a plurality of reinforcing steel bars 5 attached to the reinforcing steel sheet 4 used as the reinforcing steel material 2. It becomes possible to prevent detachment from the pile head 11 of the foundation pile 10.

本発明を適用した杭頭構造1は、上部構造物7の荷重等で複数の補強鉄筋5から引張力が作用した場合であっても、鉄筋定着鋼板4の側端部41が基礎杭10の杭頭部11の外側面11aから脱離することを防止して、基礎杭10と上部構造物7との接合強度を十分なものとすることができ、上部構造物7が倒壊することを防止することが可能となる。   In the pile head structure 1 to which the present invention is applied, even when a tensile force acts from a plurality of reinforcing reinforcing bars 5 due to the load of the upper structure 7 or the like, the side end 41 of the reinforcing steel plate 4 is the base pile 10. It is possible to prevent detachment from the outer surface 11a of the pile head 11 and to make the joint strength between the foundation pile 10 and the upper structure 7 sufficient, and to prevent the upper structure 7 from collapsing. It becomes possible to do.

また、本発明を適用した杭頭構造1は、杭頭部11の外周を取り囲むようにして巻き付けられた裏当金3に、補強鋼材2として用いられる4枚の鉄筋定着鋼板4の側端部41が載置されるため、杭頭部11の外周で各々の鉄筋定着鋼板4の高さを容易に合わせることができ、補強鋼材2として用いられる4枚の鉄筋定着鋼板4の取付作業を容易にすることが可能となる。   Moreover, the pile head structure 1 to which this invention is applied is the side edge part of the four reinforcing bar fixing steel plates 4 used as the reinforcement steel material 2 to the backing metal 3 wound so that the outer periphery of the pile head 11 might be surrounded. Since 41 is mounted, the height of each reinforcing steel plate 4 can be easily adjusted on the outer periphery of the pile head 11, and the mounting work of the four reinforcing steel plates 4 used as the reinforcing steel material 2 is easy. It becomes possible to.

ここで、本発明を適用した杭頭構造1は、図17に示すように、海面から所定の高さで離間させて上部構造物7が設けられ、上部構造物7の下面7aから3cm〜5cm程度の高さで離間した位置で、重防食層12の上端部12aが基礎杭10の杭頭部11に形成される。   Here, as shown in FIG. 17, the pile head structure 1 to which the present invention is applied is provided with an upper structure 7 separated from the sea surface at a predetermined height, and 3 cm to 5 cm from the lower surface 7 a of the upper structure 7. The upper end portion 12 a of the heavy anticorrosion layer 12 is formed on the pile head portion 11 of the foundation pile 10 at a position separated by a certain height.

上部構造物7は、基礎杭10の杭頭部11を取り囲むようにして、現場打ちのコンクリート等で構築されるため、底型枠と基礎杭10との間の隙間処理が不適切に行われると、コンクリートが十分に充填されないものとなり、図18に示すように、基礎杭10の杭頭部11の周囲で、コンクリートの被りが浅くなるおそれがある。このとき、上部構造物7は、重防食層12の上端部12aを上部構造物7の下面7aから3cm〜5cm程度の高さで離間させることができず、重防食層12の上端部12aが外部に露出するおそれがある。   Since the superstructure 7 is constructed of concrete cast on the ground so as to surround the pile head 11 of the foundation pile 10, the clearance between the bottom formwork and the foundation pile 10 is improperly performed. Then, the concrete is not sufficiently filled, and as shown in FIG. 18, there is a possibility that the concrete covering becomes shallow around the pile head 11 of the foundation pile 10. At this time, the upper structure 7 cannot separate the upper end portion 12a of the heavy anticorrosion layer 12 from the lower surface 7a of the upper structure 7 at a height of about 3 cm to 5 cm. There is a risk of exposure to the outside.

本発明を適用した杭頭構造1は、重防食層12の上端部12aが露出する場合であっても、裏当金3が重防食層12の上端部12aと重なるようにして設けられるため、重防食層12の上端部12aと基礎杭10の杭頭部11の外側面11aとの隙間が裏当金3で塞がれて、この隙間に海水等が浸入することを防止することができる。   The pile head structure 1 to which the present invention is applied is provided so that the backing metal 3 overlaps the upper end portion 12a of the heavy anticorrosion layer 12 even when the upper end portion 12a of the heavy anticorrosion layer 12 is exposed. The gap between the upper end portion 12a of the heavy-duty protection layer 12 and the outer side surface 11a of the pile head 11 of the foundation pile 10 is blocked by the backing metal 3, and seawater or the like can be prevented from entering the gap. .

これにより、本発明を適用した杭頭構造1は、重防食層12の上端部12aと基礎杭10の杭頭部11の外側面11aとの隙間への海水等の浸入を防止することができ、さらに、裏当金3で重防食層12の上端部12aが締め付けられることで、この隙間への海水等の浸入を強固に防止することができ、海水等の浸入による基礎杭10の腐食を防止することが可能となる。   Thereby, the pile head structure 1 to which the present invention is applied can prevent intrusion of seawater or the like into the gap between the upper end portion 12a of the heavy-duty protection layer 12 and the outer surface 11a of the pile head portion 11 of the foundation pile 10. Furthermore, by tightening the upper end portion 12a of the heavy anticorrosion layer 12 with the backing metal 3, it is possible to strongly prevent the intrusion of seawater into the gap, and the corrosion of the foundation pile 10 due to the intrusion of seawater etc. It becomes possible to prevent.

次に、本発明を適用した杭頭構造1の第2実施形態について説明する。なお、上述した構成要素と同一の構成要素については、同一の符号を付すことにより以下での説明を省略する。   Next, 2nd Embodiment of the pile head structure 1 to which this invention is applied is described. In addition, about the component same as the component mentioned above, the description below is abbreviate | omitted by attaching | subjecting the same code | symbol.

本発明を適用した杭頭構造1は、図19に示すように、第2実施形態において、基礎杭10として鋼管矢板が用いられ、鋼管矢板の継手部13と干渉しないように、補強鋼材2として2枚の略平板状の鉄筋定着鋼板4が用いられる。   As shown in FIG. 19, the pile head structure 1 to which the present invention is applied is a steel pipe sheet pile as the foundation pile 10 in the second embodiment, and as a reinforcing steel material 2 so as not to interfere with the joint portion 13 of the steel pipe sheet pile. Two substantially flat reinforcing steel plates 4 having a flat plate shape are used.

裏当金3は、図20に示すように、杭頭部11の外側面11aに沿うように、略円弧状に形成された帯状鋼板30や、帯状銅板、L形断面鋼34、鉄筋35等が用いられ、杭頭部11の外側面11aで、鋼管矢板の継手部13と干渉しないように、溶接等で仮止めされて固定される。   As shown in FIG. 20, the backing metal 3 includes a strip-shaped steel plate 30, a strip-shaped copper plate, an L-shaped cross-section steel 34, a reinforcing bar 35, and the like that are formed in a substantially arc shape along the outer surface 11a of the pile head 11. Is used, and is temporarily fixed by welding or the like so as not to interfere with the joint portion 13 of the steel pipe sheet pile at the outer surface 11a of the pile head 11.

裏当金3は、基礎杭10に形成された重防食層12の上端部12aと重なるようにして、帯状鋼板30や、帯状銅板、L形断面鋼34、鉄筋35等が杭頭部11に設けられ、さらに、これらの帯状鋼板30等で重防食層12の上端部12aが締め付けられてもよい。裏当金3は、これに限らず、重防食層12の上端部12aと重ならないようにして、帯状鋼板30等が杭頭部11に設けられてもよい。   The backing metal 3 is overlapped with the upper end portion 12a of the heavy anticorrosion layer 12 formed on the foundation pile 10, and the strip steel plate 30, the strip copper plate, the L-shaped cross section steel 34, the reinforcing bar 35, etc. are attached to the pile head 11. Further, the upper end portion 12a of the heavy anticorrosion layer 12 may be tightened by these strip-shaped steel plates 30 or the like. The backing metal 3 is not limited to this, and the strip steel plate 30 or the like may be provided on the pile head 11 so as not to overlap the upper end portion 12 a of the heavy anticorrosion layer 12.

本発明を適用した杭頭構造1は、図19、図20に示すように、2枚の略平板状の鉄筋定着鋼板4の側端部41が、杭頭部11の外側面11aに取り付けられる。本発明を適用した杭頭構造1は、鉄筋定着鋼板4の下面4aが裏当金3の上面3aに当接された状態で、裏当金3の上面3a及び杭頭部11の外側面11aに、鉄筋定着鋼板4の側端部41が溶接によって取り付けられる。   In the pile head structure 1 to which the present invention is applied, as shown in FIGS. 19 and 20, the side end portions 41 of the two substantially flat reinforcing steel plates 4 are attached to the outer surface 11 a of the pile head 11. . The pile head structure 1 to which the present invention is applied has the upper surface 3a of the backing metal 3 and the outer surface 11a of the pile head 11 in a state where the lower surface 4a of the reinforcing steel plate 4 is in contact with the upper surface 3a of the backing metal 3. Moreover, the side edge part 41 of the reinforcing steel plate 4 is attached by welding.

本発明を適用した杭頭構造1の構築方法は、第2実施形態においても、基礎杭10の杭頭部11に裏当金3を設ける第1工程と、補強鋼材2の端部を溶接によって杭頭部11の外側面11a取り付ける第2工程とを備える。本発明を適用した杭頭構造1の構築方法は、第2工程において、基礎杭10の杭頭部11に設けられた裏当金3の上面3aに、2枚の鉄筋定着鋼板4の側端部41を載置して、開先面41aを溶接することによって、基礎杭10の杭頭部11の外側面11a及び裏当金3の上面3aに、鉄筋定着鋼板4の側端部41が取り付けられる。   In the construction method of the pile head structure 1 to which the present invention is applied, also in the second embodiment, the first step of providing the backing metal 3 on the pile head 11 of the foundation pile 10 and the end of the reinforcing steel material 2 are welded. And a second step of attaching the outer surface 11a of the pile head 11. In the second step, the construction method of the pile head structure 1 to which the present invention is applied is the side end of the two reinforcing steel sheets 4 on the upper surface 3a of the backing metal 3 provided on the pile head 11 of the foundation pile 10. By placing the portion 41 and welding the groove surface 41a, the side end 41 of the reinforcing steel plate 4 is placed on the outer surface 11a of the pile head 11 of the foundation pile 10 and the upper surface 3a of the backing metal 3. It is attached.

本発明を適用した杭頭構造1は、鉄筋定着鋼板4の側端部41と、基礎杭10の杭頭部11の外側面11a及び裏当金3の上面3aとが十分に溶け込んで一体化されるものとなり、鉄筋定着鋼板4に取り付けられた複数の補強鉄筋5から引張力が作用した場合であっても、各々の鉄筋定着鋼板4が基礎杭10の杭頭部11から脱離することを防止することが可能となる。   In the pile head structure 1 to which the present invention is applied, the side end 41 of the reinforcing steel plate 4 and the outer surface 11a of the pile head 11 of the foundation pile 10 and the upper surface 3a of the backing metal 3 are sufficiently melted and integrated. Even when a tensile force is applied from a plurality of reinforcing reinforcing bars 5 attached to the reinforcing steel plate 4, each reinforcing steel plate 4 is detached from the pile head 11 of the foundation pile 10. Can be prevented.

また、本発明を適用した杭頭構造1は、杭頭部11の外周を取り囲むようにして巻き付けられた裏当金3に、2枚の鉄筋定着鋼板4の側端部41が載置されるため、杭頭部11の外周で各々の鉄筋定着鋼板4の高さを容易に合わせることができ、2枚の鉄筋定着鋼板4の取付作業を容易にすることが可能となる。   In the pile head structure 1 to which the present invention is applied, the side end portions 41 of the two reinforcing steel sheets 4 are placed on the backing metal 3 wound so as to surround the outer periphery of the pile head 11. Therefore, it is possible to easily adjust the heights of the respective reinforcing steel plates 4 on the outer periphery of the pile head 11 and to facilitate the mounting work of the two reinforcing steel plates 4.

さらに、本発明を適用した杭頭構造1は、重防食層12の上端部12aが露出する場合であっても、裏当金3が重防食層12の上端部12aと重なるようにして設けられるため、重防食層12の上端部12aと基礎杭10の杭頭部11の外側面11aとの隙間に、海水等が浸入することを防止することができ、海水等の浸入によって基礎杭10が腐食することを防止することが可能となる。   Furthermore, the pile head structure 1 to which the present invention is applied is provided so that the backing metal 3 overlaps the upper end portion 12 a of the heavy anticorrosion layer 12 even when the upper end portion 12 a of the heavy anticorrosion layer 12 is exposed. Therefore, it is possible to prevent seawater and the like from entering the gap between the upper end portion 12a of the heavy-duty protection layer 12 and the outer side surface 11a of the pile head 11 of the foundation pile 10, and the foundation pile 10 is intruded by the penetration of seawater and the like. It becomes possible to prevent corrosion.

以上、本発明の実施形態の例について詳細に説明したが、上述した実施形態は、何れも本発明を実施するにあたっての具体化の例を示したものに過ぎず、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。   As mentioned above, although the example of embodiment of this invention was demonstrated in detail, all the embodiment mentioned above showed only the example of actualization in implementing this invention, and these are the technical aspects of this invention. The range should not be construed as limiting.

例えば、本発明を適用した杭頭構造1は、補強鋼材2として補強鉄筋5が用いられ、裏当金3の上面3aに補強鉄筋5の端部が直接に載置され、補強鉄筋5が裏当金3の上面3aに当接された状態で、裏当金3の上面3a及び杭頭部11の外側面11aに、補強鉄筋5の端部が溶接によって取り付けられてもよい。   For example, in the pile head structure 1 to which the present invention is applied, a reinforcing bar 5 is used as the reinforcing steel material 2, the end of the reinforcing bar 5 is directly placed on the upper surface 3 a of the backing metal 3, and the reinforcing bar 5 is The end of the reinforcing reinforcing bar 5 may be attached to the upper surface 3a of the backing metal 3 and the outer surface 11a of the pile head 11 by welding while being in contact with the upper surface 3a of the metal 3.

1 :杭頭構造
10 :基礎杭
10a :下端部(基礎杭)
10b :中間部(基礎杭)
10c :上端部(基礎杭)
11 :杭頭部
11a :外側面
12 :重防食層
12a :上端部(重防食層)
13 :継手部
2 :補強鋼材
3 :裏当金
3a :上面(裏当金)
30 :帯状鋼板
30a :下端部
30b :中間部
30c :上端部
31 :分割裏当金
32 :ヒンジ
33 :締め金具
34 :L形断面鋼
35 :鉄筋
38 :テーパ部
39 :切欠部
4 :鉄筋定着鋼板
4a :下面(鉄筋定着鋼板)
4b :上面(鉄筋定着鋼板)
41 :側端部
41a :開先面
42 :取付部
5 :補強鉄筋
7 :上部構造物
7a :下面(上部構造物)
80 :地盤
81 :海中
X :管軸直交方向
Y :管軸方向
1: Pile head structure 10: Foundation pile 10a: Lower end (foundation pile)
10b: Intermediate part (foundation pile)
10c: Upper end (foundation pile)
11: Pile head 11a: Outer surface 12: Heavy anticorrosion layer 12a: Upper end (heavy anticorrosion layer)
13: Joint part 2: Reinforced steel 3: Back metal 3a: Upper surface (back metal)
30: Strip steel plate 30a: Lower end portion 30b: Intermediate portion 30c: Upper end portion 31: Split backing metal 32: Hinge 33: Fastener 34: L-shaped cross section steel 35: Reinforcing bar 38: Tapered portion 39: Notch portion 4: Reinforcing bar fixing Steel plate 4a: bottom surface (rebar fixing steel plate)
4b: Upper surface (reinforcing steel plate)
41: Side end portion 41a: Groove surface 42: Mounting portion 5: Reinforcing bar 7: Upper structure 7a: Lower surface (upper structure)
80: Ground 81: Underwater X: Pipe axis orthogonal direction Y: Pipe axis direction

Claims (26)

上部構造物の基礎杭に用いられる杭頭構造であって、
杭頭部に取り付けられる補強鋼材と、前記補強鋼材の下方に設けられる裏当金とを備え、
前記裏当金は、杭頭部の外周を取り囲むようにして、杭頭部に設けられて、
前記補強鋼材は、前記補強鋼材の下面に前記裏当金が当接されて前記裏当金に載置された状態で、前記裏当金及び杭頭部の外側面に溶接されること
を特徴とする杭頭構造。
Pile head structure used for the foundation pile of superstructure,
A reinforcing steel material attached to the pile head and a backing metal provided below the reinforcing steel material,
The backing metal is provided on the pile head so as to surround the outer periphery of the pile head,
The reinforcing steel material is welded to the outer surface of the backing metal and the pile head in a state where the backing metal is in contact with the lower surface of the reinforcing steel material and placed on the backing metal. Pile head structure.
前記裏当金は、杭頭部の外周を取り囲むようにして、帯状鋼板を巻き付けることによって、杭頭部に設けられること
を特徴とする請求項1に記載の杭頭構造。
The pile head structure according to claim 1, wherein the backing metal is provided on the pile head by winding a strip-shaped steel plate so as to surround an outer periphery of the pile head.
前記裏当金は、締め金具付きの帯状鋼板に設けられた締め金具で締め付けられることによって、杭頭部に設けられること
を特徴とする請求項に記載の杭頭構造。
The pile head structure according to claim 2 , wherein the backing metal is provided on the pile head by being tightened with a fastener provided on a belt-shaped steel plate with a fastener.
前記裏当金は、杭頭部の外周を取り囲むようにして、L形断面鋼を巻き付けることによって、杭頭部に設けられること
を特徴とする請求項1に記載の杭頭構造。
The pile head structure according to claim 1, wherein the backing metal is provided on the pile head by winding L-shaped cross-section steel so as to surround the outer periphery of the pile head.
前記裏当金は、締め金具付きのL形断面鋼に設けられた締め金具で締め付けられることによって、杭頭部に設けられること
を特徴とする請求項に記載の杭頭構造。
The pile head structure according to claim 4 , wherein the backing metal is provided on the pile head by being tightened with a fastener provided on an L-shaped cross-section steel with a fastener.
前記裏当金は、杭頭部の外周を取り囲むようにして、鉄筋を巻き付けることによって、杭頭部に設けられること
を特徴とする請求項1に記載の杭頭構造。
The pile head structure according to claim 1, wherein the backing metal is provided on the pile head by winding a reinforcing bar so as to surround an outer periphery of the pile head.
前記裏当金は、杭頭部の外周を取り囲むようにして、複数に分割された分割裏当金が用いられて、杭頭部に設けられること
を特徴とする請求項1〜の何れか1項に記載の杭頭構造。
The backing metal is to surround the outer periphery of the pile head, used is divided backing metal which is divided into a plurality, claim 1-6, characterized in that provided in the pile head The pile head structure according to item 1.
前記裏当金は、基礎杭に形成された重防食層の上端部と重ならないようにして、杭頭部に設けられること
を特徴とする請求項1〜の何れか1項に記載の杭頭構造。
The pile according to any one of claims 1 to 7 , wherein the backing metal is provided on a pile head so as not to overlap an upper end portion of a heavy anticorrosion layer formed on a foundation pile. Head structure.
前記裏当金は、基礎杭に形成された重防食層の上端部と重なるようにして、杭頭部に設けられること
を特徴とする請求項1〜の何れか1項に記載の杭頭構造。
The pile head according to any one of claims 1 to 7 , wherein the backing metal is provided on a pile head so as to overlap an upper end portion of a heavy anticorrosion layer formed on a foundation pile. Construction.
前記裏当金は、基礎杭に形成された重防食層の上端部を、締め金具付きの帯状鋼板に設けられた締め金具で締め付けるようにして、杭頭部に設けられること
を特徴とする請求項1〜の何れか1項に記載の杭頭構造。
The backing metal is provided at a pile head such that an upper end portion of a heavy anticorrosion layer formed on a foundation pile is fastened with a fastener provided on a belt-like steel plate with a fastener. Item 8. The pile head structure according to any one of Items 1 to 7 .
前記補強鋼材は、上部構造物の補強鉄筋が取り付けられる鉄筋定着鋼板が用いられること を特徴とする請求項1〜1の何れか1項に記載の杭頭構造。 The pile head structure according to any one of claims 1 to 10 , wherein the reinforcing steel material is a reinforcing steel plate to which a reinforcing steel reinforcing bar of an upper structure is attached. 前記補強鋼材は、複数に分割された前記鉄筋定着鋼板が用いられること
を特徴とする請求項1に記載の杭頭構造。
The reinforcing steel, pile head structure according to claim 1 1, characterized in that the reinforcing bar fixing steel sheet which is divided into a plurality are used.
前記補強鋼材は、一体化された前記鉄筋定着鋼板が用いられること
を特徴とする請求項1に記載の杭頭構造。
The reinforcing steel, pile head structure according to claim 1 1, characterized in that integrated the reinforcing bar fixing steel sheet is used.
上部構造物の基礎杭に用いられる杭頭構造の構築方法であって、
杭頭部の外周を取り囲むようにして、杭頭部に裏当金を設ける第1工程と、
前記裏当金に補強鋼材の端部を載置した状態で、前記補強鋼材の端部を溶接によって杭頭部の外側面に取り付ける第2工程とを備えること
を特徴とする杭頭構造の構築方法。
A construction method of a pile head structure used for a foundation pile of an upper structure,
A first step of providing a backing metal to the pile head so as to surround the outer periphery of the pile head;
A second step of attaching the end of the reinforcing steel material to the outer surface of the pile head by welding in a state where the end of the reinforcing steel material is placed on the backing metal. Construction method.
前記第1工程では、杭頭部の外周を取り囲むようにして、帯状鋼板を巻き付けることによって、杭頭部に前記裏当金を設けること
を特徴とする請求項1に記載の杭頭構造の構築方法。
In the first step, so as to surround the outer periphery of the pile head, by winding the steel strip, the pile head structure according to claim 1 4, characterized in that providing the backing metal to pile head Construction method.
前記第1工程では、締め金具付きの前記帯状鋼板に設けられた締め金具で締め付けることによって、杭頭部に前記裏当金を設けること
を特徴とする請求項1に記載の杭頭構造の構築方法。
The pile head structure according to claim 15 , wherein, in the first step, the backing metal is provided on a pile head by fastening with a fastener provided on the belt-shaped steel plate with a fastener. Construction method.
前記第1工程では、杭頭部の外周を取り囲むようにして、L形断面鋼を巻き付けることによって、杭頭部に前記裏当金を設けること
を特徴とする請求項1に記載の杭頭構造の構築方法。
In the first step, so as to surround the outer periphery of the pile head, by winding an L-shaped cross-section steel, as claimed in claim 1 4, characterized in that providing the backing metal to pile head pile How to build the structure.
前記第1工程では、締め金具付きの前記L形断面鋼に設けられた締め金具で締め付けることによって、杭頭部に前記裏当金を設けること
を特徴とする請求項1に記載の杭頭構造の構築方法。
The pile head according to claim 17 , wherein, in the first step, the backing metal is provided on the pile head by fastening with a fastener provided on the L-shaped cross-section steel with a fastener. How to build the structure.
前記第1工程では、杭頭部の外周を取り囲むようにして、鉄筋を巻き付けることによって、杭頭部に前記裏当金を設けること
を特徴とする請求項1に記載の杭頭構造の構築方法。
Building in the first step, so as to surround the outer periphery of the pile head, by winding the reinforcing bars, pile head structure according to claim 1 4, characterized in that providing the backing metal to pile head Method.
前記第1工程では、複数に分割された分割裏当金を用いて、杭頭部に前記裏当金を設けること
を特徴とする請求項119の何れか1項に記載の杭頭構造の構築方法。
In the first step, by using a divided backing metal which is divided into a plurality, according to any one of claims 1 4-19, characterized in that providing the backing metal to pile head pile How to build the structure.
前記第1工程では、基礎杭に形成された重防食層の上端部と重ならないようにして、杭頭部に前記裏当金を設けること
を特徴とする請求項1〜2の何れか1項に記載の杭頭構造の構築方法。
In the first step, so as not to overlap with the upper portion of the heavy duty layer formed on the foundation pile, claim 1 4-2 0, characterized in that providing the backing metal to pile head A method for constructing a pile head structure according to item 1.
前記第1工程では、基礎杭に形成された重防食層の上端部と重なるようにして、杭頭部に前記裏当金を設けること
を特徴とする請求項1〜2の何れか1項に記載の杭頭構造の構築方法。
In the first step, so as to overlap with the upper portion of the heavy duty layer formed on the foundation pile, claim 1 4-2 0, characterized in that providing the backing metal to pile head 1 The construction method of the pile head structure as described in a term.
前記第1工程では、基礎杭に形成された重防食層の上端部を、締め金具付きの帯状鋼板に設けられた締め金具で締め付けるようにして、杭頭部に前記裏当金を設けること
を特徴とする請求項1〜2の何れか1項に記載の杭頭構造の構築方法。
In the first step, the backing metal is provided on the pile head so that the upper end of the heavy anticorrosion layer formed on the foundation pile is tightened with a fastener provided on a belt-like steel plate with a fastener. method for constructing a pile structure according to any one of claims 1 4-2 0, wherein.
前記第2工程では、上部構造物の補強鉄筋が取り付けられる鉄筋定着鋼板を前記補強鋼材として用いること
を特徴とする請求項1〜2の何れか1項に記載の杭頭構造の構築方法。
In the second step, method for constructing a pile structure according to any one of claims 1 to 4, ~ 2, which comprises using a reinforcing bar fixing steel reinforcement rebar of the superstructure is mounted as the reinforcing steel .
前記第2工程では、複数に分割された前記鉄筋定着鋼板を前記補強鋼材として用いること
を特徴とする請求項2に記載の杭頭構造の構築方法。
In the second step, method for constructing a pile structure according to claim 2 4, characterized by using the reinforcing bar fixing steel sheet which is divided into a plurality as the reinforcing steel.
前記第2工程では、一体化された前記鉄筋定着鋼板を前記補強鋼材として用いること
を特徴とする請求項2に記載の杭頭構造の構築方法。
In the second step, method for constructing a pile structure according to claim 2 4, characterized by using an integrated said reinforcing bar fixing steel plate as the steel reinforced material.
JP2013111600A 2013-05-28 2013-05-28 Pile head structure and construction method of pile head structure Active JP6136575B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013111600A JP6136575B2 (en) 2013-05-28 2013-05-28 Pile head structure and construction method of pile head structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013111600A JP6136575B2 (en) 2013-05-28 2013-05-28 Pile head structure and construction method of pile head structure

Publications (2)

Publication Number Publication Date
JP2014231673A JP2014231673A (en) 2014-12-11
JP6136575B2 true JP6136575B2 (en) 2017-05-31

Family

ID=52125237

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013111600A Active JP6136575B2 (en) 2013-05-28 2013-05-28 Pile head structure and construction method of pile head structure

Country Status (1)

Country Link
JP (1) JP6136575B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6541255B2 (en) * 2015-04-27 2019-07-10 パイルフォーラム株式会社 Pile design method and structure support structure
JP7146476B2 (en) * 2018-06-21 2022-10-04 五洋建設株式会社 Method of anchoring steel pipe piles and reinforcing bars

Family Cites Families (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5017428B2 (en) * 1971-10-30 1975-06-20
JPS55114498A (en) * 1979-02-28 1980-09-03 Nippon Steel Corp Mounting method of backing strip
JPS56137896U (en) * 1980-03-11 1981-10-19
JPS57128900A (en) * 1981-02-04 1982-08-10 Hitachi Ltd Lining container
JPS5847392U (en) * 1981-09-21 1983-03-30 株式会社長谷工コーポレーション Backing material
JPS58156746U (en) * 1982-04-13 1983-10-19 日本国有鉄道 Connection structure between foundation pile and foundation structure
JPS6076137U (en) * 1983-10-31 1985-05-28 三菱鉱業セメント株式会社 Joint structure of steel pipe concrete composite pile
JPH0497937U (en) * 1991-01-09 1992-08-25
JPH11107294A (en) * 1997-10-07 1999-04-20 Taisei Corp Treating method for reinforcing bar at head portion of steel pipe pile
JP2000237896A (en) * 1999-02-19 2000-09-05 Maeda Corp Backing for hollow steel tube
JP2001303604A (en) * 2000-04-25 2001-10-31 Nippon Steel Corp Joining structure of steel pipe pile and upper structure
JP2004107875A (en) * 2002-09-13 2004-04-08 Nippon Corrosion Engineering Co Ltd Protective cover mounting structure of columnar body
JP4130393B2 (en) * 2003-09-02 2008-08-06 株式会社奥村組 Pile-column connection structure
JP4648959B2 (en) * 2008-03-10 2011-03-09 株式会社エムオーテック Steel pipe support and method of connecting steel pipes
JP2010120037A (en) * 2008-11-18 2010-06-03 Ihi Corp Backing member and welding method

Also Published As

Publication number Publication date
JP2014231673A (en) 2014-12-11

Similar Documents

Publication Publication Date Title
JP6703307B2 (en) Steel pipe joining method and joining structure
JP7041588B2 (en) Slavic support structure
JP5380084B2 (en) Steel pipe and pile for pile
JP4548311B2 (en) Abutment structure of composite ramen bridge
CN110424763B (en) Steel-clad structure of stand column and using method thereof
KR102268071B1 (en) Apparatus for reinforcing the pile head
JP6136575B2 (en) Pile head structure and construction method of pile head structure
JP2017106307A (en) Segments
JP5596638B2 (en) Winding rebar
JP5757510B1 (en) Steel column reinforcement structure
JP6780063B2 (en) Pile head reinforcement structure
CN210368944U (en) Bored concrete pile owner muscle and strengthening rib connection structure and bored concrete pile steel reinforcement cage
JP6012398B2 (en) Steel tower reinforcement structure
JP3981688B2 (en) Joint structure and composite structure of steel beam and reinforced concrete column
JP5165220B2 (en) Reinforced concrete structure and method for manufacturing reinforced concrete structure
JP2019056231A (en) Quay wall structure
JP5873704B2 (en) Joining jig and joining method
JP2000220152A (en) Pile head construction for steel pipe pile
JP6871493B2 (en) Pile head reinforcement structure
KR101378663B1 (en) Satgat type reinforcement member for preventing punching shear
JP5159942B1 (en) Column base of building
KR101304501B1 (en) Steel Pipe Pile head reinforcement device
JP5540451B2 (en) Concrete pile with outer shell steel pipe and manufacturing method thereof
JP5344702B2 (en) Column and slab joint structure
JP6155845B2 (en) Anticorrosion steel, standing structure and sacrificial steel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160107

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20161031

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20161115

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20161122

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170404

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170417

R151 Written notification of patent or utility model registration

Ref document number: 6136575

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R151

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350