JP6016681B2 - Energy saving system - Google Patents

Energy saving system Download PDF

Info

Publication number
JP6016681B2
JP6016681B2 JP2013055469A JP2013055469A JP6016681B2 JP 6016681 B2 JP6016681 B2 JP 6016681B2 JP 2013055469 A JP2013055469 A JP 2013055469A JP 2013055469 A JP2013055469 A JP 2013055469A JP 6016681 B2 JP6016681 B2 JP 6016681B2
Authority
JP
Japan
Prior art keywords
power
facility
load control
time
target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2013055469A
Other languages
Japanese (ja)
Other versions
JP2014183632A (en
Inventor
長谷川 弘
弘 長谷川
長俊 中目
長俊 中目
幹夫 小林
幹夫 小林
見悦 角掛
見悦 角掛
譲 佐々木
譲 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Osaka Denki Co Ltd
Original Assignee
Osaka Denki Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Osaka Denki Co Ltd filed Critical Osaka Denki Co Ltd
Priority to JP2013055469A priority Critical patent/JP6016681B2/en
Publication of JP2014183632A publication Critical patent/JP2014183632A/en
Application granted granted Critical
Publication of JP6016681B2 publication Critical patent/JP6016681B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Description

本発明は、複数施設のデマンド時限内における総和目標電力を超過することなく、各施設に設置する電力抑制装置の目標電力を配分する省エネルギーシステムに関するものである。   The present invention relates to an energy saving system that distributes target power of a power control device installed in each facility without exceeding the total target power within a demand time limit of a plurality of facilities.

従来の省エネルギーシステムでは、電力抑制装置であるデマンドコントロール装置にデマンド時限内(一般的には30分)の目標電力を設定し、個別施設単位にて最大需要電力の抑制を行っている。このようなデマンドコントロール装置としては、例えば、特許文献1に開示された、デマンド制御の追従性および安定性を向上させたデマンドコントロール装置がある。従来、複数施設の最大需要電力を合計した総和最大需要電力を抑制するため、複数施設の総和目標電力値を予め決定し、各施設の目標電力値の総和が決定した総和目標電力値を超過しないように、固定した目標電力値を手動にて各施設のデマンドコントロール装置に配分している。   In a conventional energy saving system, a target power within a demand time limit (generally 30 minutes) is set in a demand control device, which is a power suppression device, and the maximum demand power is suppressed in units of individual facilities. As such a demand control device, for example, there is a demand control device disclosed in Patent Document 1 with improved demand control followability and stability. Conventionally, in order to suppress the total maximum demand power that is the sum of the maximum demand power of multiple facilities, the total target power value of the multiple facilities is determined in advance, and the sum of the target power values of each facility does not exceed the determined total target power value As described above, the fixed target power value is manually distributed to the demand control devices of each facility.

特開平6−78459号公報JP-A-6-78459

上記従来の省エネルギーシステムを利用して複数施設の総和目標電力管理を行った場合、各施設の稼働状況や環境条件、立地条件により、ある施設では目標電力を達成するために負荷制御が頻繁に行われているにも関わらず、他の施設では負荷制御が行われていないなどの状態が発生する。これを是正するため、従来、デマンド時限終了時に、前デマンド時限の負荷制御状態を踏まえ、手動にて目標電力値を再設定する手法がとられてきた。   When the total target power management of multiple facilities is performed using the conventional energy-saving system described above, load control is frequently performed at a facility to achieve the target power depending on the operating status, environmental conditions, and location conditions of each facility. In spite of this, there are situations where load control is not performed at other facilities. In order to correct this, conventionally, a method has been adopted in which the target power value is manually reset at the end of the demand time period based on the load control state of the previous demand time period.

しかしながら、例えば空調を制御対象負荷とした場合、各施設の立地する気象条件が刻々と変化することに加え各設備の稼働状況が変化するなど、頻繁に環境条件が変化するため、目標電力値の再設定に手間がかかり、実際には再設定が頻繁に行われることは少なかった。このため、上記従来の省エネルギーシステムでは、各施設の稼働状況や環境条件、立地条件により、特定の施設に負荷制御が集中してしまい、バランスよく負荷制御が行われなかった。   However, for example, when air-conditioning is the load to be controlled, the environmental conditions change frequently, such as the weather conditions where each facility is located and the operating conditions of each facility change. It took time to reset, and in fact, it was rare that resetting was performed frequently. For this reason, in the conventional energy saving system, load control is concentrated on a specific facility depending on the operation status, environmental conditions, and location conditions of each facility, and load control is not performed in a balanced manner.

本発明はこのような課題を解決するためになされたもので、
節電可能負荷への通電を制御する負荷制御を行うことで任意の単位時間で定義されるデマンド時限内の施設内使用電力を目標電力値以下に抑制制御する、各施設に設置された電力抑制装置と、各施設における最大需要電力の総和に相当する総和最大需要電力が設定された総和目標電力値を超過しないように各施設の目標電力値を算出し、算出した目標電力値を各施設の電力抑制装置に配分する中央制御装置と、電力抑制装置および中央制御装置間の通信を行う通信手段とから構成され、
電力抑制装置は、デマンド時限内で負荷制御を実施した負荷制御実施時間を計測し、
中央制御装置は、電力抑制装置で計測された負荷制御実施時間を各施設から通信手段によって収集し、負荷制御実施時間が短い負荷制御短時間施設に割り当てられた目標電力を負荷制御実施時間が長い負荷制御長時間施設の目標電力に配分することで、総和目標電力値を変えずに各施設における負荷制御の頻度の均衡を図る省エネルギーシステムを構成した。
The present invention has been made to solve such problems,
Power control devices installed in each facility that control the power consumption in the facility within the demand time period defined in an arbitrary unit time by controlling the power supply to the power-saving load. And calculate the target power value of each facility so that the total maximum demand power corresponding to the sum of the maximum demand power at each facility does not exceed the set target power value, and use the calculated target power value for each facility It is composed of a central control device that distributes to the control device, and a communication means that performs communication between the power control device and the central control device,
The power suppression device measures the load control execution time when the load control is performed within the demand time limit,
The central control unit collects the load control execution time measured by the power suppression device from each facility by communication means, and the load control execution time is short. By allocating to the target power of the load control facility for a long time, an energy saving system was constructed to balance the frequency of load control in each facility without changing the total target power value.

この構成によれば、中央制御装置により、各施設の電力抑制装置からデータが収集され、各施設における最大需要電力の総和に相当する総和最大需要電力が、設定された総和目標電力値を超過しないように、各施設の目標電力値が算出される。算出された目標電力値は、中央制御装置により通信手段を介して各施設の電力抑制装置に配分される。このため、中央制御装置により、複数施設でのデマンド時限内の総和最大需要電力が総和目標電力値内に抑制され、複数施設の総和目標電力値を超過することなく、手間を要しないで各施設の負荷制御を行うことが可能になる。また、中央制御装置により、各施設の電力抑制装置から、デマンド時限内で負荷制御を実施した負荷制御実施時間が収集され、負荷制御実施時間が短い負荷制御短時間施設に割り当てられた目標電力が負荷制御実施時間が長い負荷制御長時間施設の目標電力に配分される。このため、総和目標電力値を変えずに各施設における負荷制御の頻度の均衡を図ることが可能になる。   According to this configuration, data is collected from the power suppression device of each facility by the central control device, and the total maximum demand power corresponding to the sum of the maximum demand power in each facility does not exceed the set total target power value. As described above, the target power value of each facility is calculated. The calculated target power value is distributed by the central control device to the power suppression device of each facility via the communication means. For this reason, the central control unit suppresses the total maximum demand power within the demand time limit at multiple facilities within the total target power value, and does not exceed the total target power value of the multiple facilities, so that each facility is not required. It becomes possible to perform load control. In addition, the central control unit collects the load control execution time for load control within the demand time limit from the power control device of each facility, and the target power assigned to the load control short-time facility with short load control execution time is obtained. The load control execution time is distributed to the target power of the load control long-time facility. For this reason, it is possible to balance the frequency of load control in each facility without changing the total target power value.

また、本発明は、中央制御装置が、負荷制御長時間施設に対してはその施設に設定可能な上限の目標電力を設定し、負荷制御短時間施設に対しては、各負荷制御長時間施設における上限の目標電力の総和に相当する総和上限目標電力を総和目標電力値から差し引いた残電力を配分することで、目標電力を再配分することを特徴とする。   In addition, the present invention sets an upper limit target power that can be set in the facility for the load control long-time facility, and each load control long-time facility for the load control short-time facility. The target power is redistributed by allocating the remaining power obtained by subtracting the total upper limit target power corresponding to the sum of the upper limit target powers in FIG.

この構成によれば、負荷制御実施時間が長く、最大需要電力が目標電力にひっ迫する負荷制御長時間施設には、中央制御装置により、その施設に設定可能な上限の目標電力が設定される。このため、負荷制御長時間施設では、目標電力と最大需要電力との間に余裕が生まれ、頻繁に行われていた負荷制御の頻度は減少する。一方、負荷制御実施時間が短く、最大需要電力と目標電力との間に余裕がある負荷制御短時間施設には、中央制御装置により、総和上限目標電力を総和目標電力値から差し引いた残電力が再配分され、目標電力が下げられる。しかし、負荷制御短時間施設では、最大需要電力と目標電力との間に余裕があったため、目標電力が下げられても、負荷制御の頻度に及ぶ影響は小さい。この結果、総和目標電力値を変えずに各施設における負荷制御の頻度の均衡が図られる。   According to this configuration, in the load control long-time facility where the load control execution time is long and the maximum demand power is close to the target power, the upper limit target power that can be set in the facility is set by the central controller. For this reason, in the load control long-time facility, a margin is created between the target power and the maximum demand power, and the frequency of load control that has been frequently performed decreases. On the other hand, the load control execution time is short, and the load control short-time facility with a margin between the maximum demand power and the target power has a remaining power obtained by subtracting the total upper limit target power from the total target power value by the central controller. Redistribution will reduce the target power. However, since the load control short-time facility has a margin between the maximum demand power and the target power, even if the target power is lowered, the influence on the frequency of the load control is small. As a result, the load control frequency in each facility is balanced without changing the total target power value.

また、本発明は、中央制御装置が、デマンド時限終了時における節電可能負荷の消費電力である節電可能電力を各施設から通信手段によって収集し、節電可能負荷の電力容量である節電可能電力容量に対する節電可能電力の比率が1未満である負荷制御短時間施設に対して、節電可能電力容量から節電可能電力を差し引いた余裕電力、および、余裕電力の総和に相当する総和余裕電力に対する余裕電力の比率である余裕率を算出し、余裕率に応じて残電力を配分することを特徴とする。   Further, according to the present invention, the central control device collects power-saving power that is power consumption of the power-saving load at the end of the demand time period from each facility by communication means, and the power consumption power capacity that is the power capacity of the power-saving load is collected. The ratio of the marginal power to the total marginal power equivalent to the total power of the marginal power equivalent to the sum of the marginal power and the marginal power that is obtained by subtracting the power saving potential from the power saving potential power capacity for the load control short-time facility where the ratio of the power saving potential is less than 1 The margin rate is calculated, and the remaining power is distributed according to the margin rate.

この構成によれば、節電可能電力容量に対する節電可能電力の比率が1未満で、節電可能電力に余裕のある負荷制御短時間施設に対して、総和上限目標電力を総和目標電力値から差し引いた残電力の配分が行われる。このため、負荷制御短時間施設であっても、節電可能電力容量に対する節電可能電力の比率が1以上で、節電可能電力に余裕のない負荷制御短時間施設に対しては、残電力の配分が行われない。また、上記比率が1未満の負荷制御短時間施設に対する残電力の配分は、総和余裕電力に対する余裕電力の比率である余裕率に応じて行われ、節電可能電力に余裕のある施設には残電力が少なく配分されることになる。このため、上記比率が1未満の負荷制御短時間施設に対する残電力の配分は、各施設の余裕電力に応じて公平に行われ、負荷制御は、特定の負荷制御短時間施設に集中することなく、各負荷制御短時間施設間でバランスよく行われる。   According to this configuration, for the load control short-time facility in which the ratio of the power-saving power to the power-saving power capacity is less than 1 and there is a margin in the power-saving power, the total upper limit target power is subtracted from the total target power value. Electric power is distributed. For this reason, even if it is a load control short-time facility, the ratio of the power saveable power to the power saveable power capacity is 1 or more, and the remaining power is distributed to the load control short-time facility where there is no margin for the power saveable power. Not done. Also, the remaining power is distributed to the load control short-time facilities whose ratio is less than 1 according to the margin ratio, which is the ratio of the surplus power to the total surplus power. Will be allocated less. For this reason, the remaining power is distributed to the load control short-time facilities whose ratio is less than 1 fairly according to the surplus power of each facility, and load control is not concentrated on a specific load control short-time facility. Each load control is performed in good balance between the facilities for a short time.

本発明によれば、複数施設の総和目標電力値を超過することなく、手間を要しないで各施設の負荷制御を行うことができ、しかも、総和目標電力値を変えずに各施設における負荷制御の頻度の均衡を図ることが可能な省エネルギーシステムが提供される。   According to the present invention, it is possible to perform load control of each facility without exceeding the total target power value of a plurality of facilities, and without load, and load control in each facility without changing the total target power value An energy saving system capable of balancing the frequency of the above is provided.

本発明の一実施の形態による省エネルギーシステムの構成の概略を示すブロック図である。It is a block diagram which shows the outline of a structure of the energy saving system by one embodiment of this invention. 図1に示す省エネルギーシステムの中で用いられるデマンドコントロール装置の内部構成を示すブロック図である。It is a block diagram which shows the internal structure of the demand control apparatus used in the energy saving system shown in FIG. 図1に示す省エネルギーシステムの中で用いられる中央制御装置の内部構成を示すブロック図である。It is a block diagram which shows the internal structure of the central control apparatus used in the energy saving system shown in FIG. 図3に示す中央制御装置において行われる時限単位目標電力演算処理を示すフローチャートである。It is a flowchart which shows the time unit target electric power calculation process performed in the central control apparatus shown in FIG.

次に、本発明による省エネルギーシステムの一実施の形態について説明する。   Next, an embodiment of the energy saving system according to the present invention will be described.

図1は、本実施の形態による省エネルギーシステム1の構成の概略を示すブロック図である。   FIG. 1 is a block diagram showing an outline of the configuration of an energy saving system 1 according to the present embodiment.

各施設2には、空調機等の制御対象負荷3と、施設全体の使用電力を計測するための電力量計4と、最大需要電力を抑制する機能を持つデマンドコントロール装置5とが設置されている。制御対象負荷3は、電力供給を絶って節電することが可能な節電可能負荷であり、単独もしくは複数からなる。デマンドコントロール装置5は、任意の単位時間、本実施の形態では30分間で定義されるデマンド時限内における施設2内の使用電力を、目標電力値以下に抑制制御を行う電力抑制装置を構成し、各施設2に設置されて各施設2の最大需要電力を抑制する。   Each facility 2 is provided with a controlled load 3 such as an air conditioner, a watt-hour meter 4 for measuring the power consumption of the entire facility, and a demand control device 5 having a function of suppressing the maximum demand power. Yes. The control target load 3 is a power-saving load that can save power by stopping power supply, and is composed of a single or a plurality of loads. The demand control device 5 constitutes a power suppression device that performs control to suppress the power used in the facility 2 within the demand time period defined in an arbitrary unit time, 30 minutes in this embodiment, to a target power value or less, Installed in each facility 2 to suppress the maximum demand power of each facility 2.

施設2は複数存在し、図で例示する3施設には限らない。各施設2のデマンドコントロール装置5は中央制御装置6と接続されている。   There are a plurality of facilities 2 and are not limited to the three facilities illustrated in the figure. The demand control device 5 of each facility 2 is connected to the central control device 6.

図2はデマンドコントロール装置5の内部構成を示すブロック図である。デマンドコントロール装置5は、電力量計4から出力される受電電力データを受電電力計測部7にて計測し、演算部9にてデマンド時限終了時の需要電力量を予測する。そして、予め設定された目標電力を超過すると予測される場合に、制御出力部10を介して制御対象負荷3への通電を抑制する負荷制御を実施することにより、デマンド時限終了時の需要電力が目標電力を超えることを防止する。また、節電可能電力計測部8は、電力量計4の出力信号から、または、制御対象負荷3の出力信号から、制御対象負荷3の使用電力を節電可能電力として計測する。演算部9は、デマンド時限内で制御対象負荷3に対して負荷制御を実施した負荷制御実施時間を計測すると共に、節電可能電力計測部8で計測される節電可能電力から、デマンド時限終了時の節電可能電力を予測演算する。なお、デマンド時限終了時の電力予測方法については、デマンド時限途中までの使用電力量とその増加割合い、例えば、単位時間での増加率から算出する方法などがあるが、いずれの方法を利用した場合でも、本発明の本質に関わらないので詳細は説明しない。通信部11は中央制御装置6との間で双方向通信を行う。   FIG. 2 is a block diagram showing an internal configuration of the demand control device 5. The demand control device 5 measures the received power data output from the watt-hour meter 4 by the received power measuring unit 7 and predicts the demand power amount at the end of the demand time limit by the calculating unit 9. Then, when it is predicted that the preset target power will be exceeded, by performing load control that suppresses energization to the control target load 3 via the control output unit 10, the demand power at the end of the demand time limit is obtained. Prevent exceeding the target power. Further, the power saving possible power measurement unit 8 measures the power used by the control target load 3 as the power saving possible power from the output signal of the watt hour meter 4 or from the output signal of the control target load 3. The calculation unit 9 measures the load control execution time in which the load control is performed on the control target load 3 within the demand time limit, and from the power saving possible power measured by the power saving possible power measurement unit 8 at the end of the demand time limit. Predict and calculate power that can be saved. As for the power prediction method at the end of the demand time period, there is a method of calculating from the amount of power used until the middle of the demand time period and the rate of increase, for example, the rate of increase in unit time, but either method was used. Even in this case, the details of the present invention are not described because they are not related to the essence of the present invention. The communication unit 11 performs bidirectional communication with the central control device 6.

図3は中央制御装置6の内部構成を示すブロック図である。中央制御装置6は、各施設2のデマンドコントロール装置5と双方向に通信可能な通信部12を介して、各デマンドコントロール装置5に接続されている。デマンドコントロール装置5内の通信部11および中央制御装置6内の通信部12は、デマンドコントロール装置5および中央制御装置6間の通信を行う通信手段を構成する。省エネルギーシステム1は、デマンドコントロール装置5と中央制御装置6とこの通信手段とから構成されている。   FIG. 3 is a block diagram showing the internal configuration of the central controller 6. The central control device 6 is connected to each demand control device 5 via a communication unit 12 capable of bidirectional communication with the demand control device 5 of each facility 2. The communication unit 11 in the demand control device 5 and the communication unit 12 in the central control device 6 constitute communication means for performing communication between the demand control device 5 and the central control device 6. The energy saving system 1 includes a demand control device 5, a central control device 6, and communication means.

データ蓄積部13は、通信部11および通信部12を介して各施設2のデマンドコントロール装置5から送られてくるデータを蓄積する。また、条件設定部14には、各施設2の節電可能電力容量が予め設定されている。また、条件設定部14には、基準時間および各施設2に設定可能な上限の目標電力も予め設定されている。基準時間は、後述する時限単位目標電力演算処理において、デマンド時限内における負荷制御実施時間の長短を判断する基準にされる。また、設定可能な上限の目標電力とは、個別の各施設2が電力会社と契約している契約電力、または、この契約電力に裕度を持たせた目標電力である。   The data storage unit 13 stores data sent from the demand control device 5 of each facility 2 through the communication unit 11 and the communication unit 12. In the condition setting unit 14, the power saving capacity of each facility 2 is set in advance. In the condition setting unit 14, a reference time and an upper limit target power that can be set for each facility 2 are also set in advance. The reference time is used as a reference for determining the length of the load control execution time within the demand time limit in the time-unit target power calculation process described later. Moreover, the target power of the upper limit that can be set is contract power that each individual facility 2 contracts with an electric power company, or target power that has a margin for this contract power.

中央制御装置6は、データ蓄積部13と条件設定部14内のデータをもとに、時限単位目標電力演算部15および時限内デマンド演算部16において、時限単位目標電力演算処理および時限内デマンド演算処理を後述するように行い、デマンドコントロール装置5に対して設定データおよび指令データを送信する動作を行う。   Based on the data in the data storage unit 13 and the condition setting unit 14, the central controller 6 uses the time-unit target power calculation unit 15 and the intra-time demand calculation unit 16 to perform time-unit target power calculation processing and intra-time demand calculation. The processing is performed as described later, and an operation of transmitting setting data and command data to the demand control device 5 is performed.

中央制御装置6は、上記の時限単位目標電力演算処理において、各施設2のデマンドコントロール装置5からデータを収集して、各施設2における最大需要電力の総和に相当する総和最大需要電力が、設定された総和目標電力値を超過しないように各施設2の目標電力値を算出し、算出した目標電力値を各施設2のデマンドコントロール装置5に配分する。この際、本実施の形態では、中央制御装置6は、デマンドコントロール装置5で計測された制御対象負荷3に対する負荷制御実施時間を各施設2から通信手段によって収集し、負荷制御実施時間が短い負荷制御短時間施設2に割り当てられた目標電力を負荷制御実施時間が長い負荷制御長時間施設2の目標電力に配分することで、総和目標電力値を変えずに各施設2における負荷制御の頻度の均衡を図る。具体的には、中央制御装置6は、負荷制御長時間施設2に対してはその施設2に設定可能な上限の目標電力を設定し、負荷制御短時間施設2に対しては、各負荷制御長時間施設2における上限の目標電力の総和に相当する総和上限目標電力を総和目標電力値から差し引いた残電力を配分することで、目標電力を再配分する。   The central control device 6 collects data from the demand control device 5 of each facility 2 in the above time-unit target power calculation processing, and the total maximum demand power corresponding to the sum of the maximum demand power in each facility 2 is set. The target power value of each facility 2 is calculated so as not to exceed the total target power value thus calculated, and the calculated target power value is distributed to the demand control device 5 of each facility 2. At this time, in this embodiment, the central control device 6 collects the load control execution time for the control target load 3 measured by the demand control device 5 from each facility 2 by communication means, and the load control execution time is short. By distributing the target power allocated to the control short-time facility 2 to the target power of the load control long-time facility 2 having a long load control execution time, the frequency of load control in each facility 2 can be changed without changing the total target power value. Try to balance. Specifically, the central controller 6 sets an upper limit target power that can be set for the facility 2 for the load control long-time facility 2, and each load control for the load control short-time facility 2. The target power is redistributed by allocating the remaining power obtained by subtracting the total upper limit target power corresponding to the total upper limit target power in the long-time facility 2 from the total target power value.

また、中央制御装置6は、上記の時限内デマンド演算処理において、デマンド時限内の任意時間にて、各施設2のデマンドコントロール装置5からデマンド時限の終了時点での予測最大需要電力を通信手段によって収集し、各施設2の予測最大需要電力の総和である総和予測最大需要電力が設定された総和目標電力値を超過する場合に、各施設2のデマンドコントロール装置5に対して制御対象負荷3の切り制御指令を通信手段を介して強制的に発する。この際、本実施の形態では、中央制御装置6は、デマンド時限内の任意時間にて、各施設2のデマンドコントロール装置5からデマンド時限の終了時点での予測節電可能電力を通信手段によって収集し、節電可能電力容量に対する予測節電可能電力の割合が少ない施設2に優先して切り制御指令を発する。   Further, the central control device 6 uses the communication means to calculate the predicted maximum demand power at the end of the demand time period from the demand control device 5 of each facility 2 at any time within the demand time period in the demand calculation within the time period. When the total predicted maximum demand power that is the sum of the predicted maximum demand power of each facility 2 exceeds the set total target power value, the load control device 5 of each facility 2 A cut control command is forcibly issued via the communication means. At this time, in the present embodiment, the central control device 6 collects the predicted power-saving power at the end of the demand time period from the demand control device 5 of each facility 2 by the communication means at an arbitrary time within the demand time period. The cut-off control command is issued in preference to the facility 2 having a small ratio of the predicted power-saving power to the power-saving power capacity.

次に、デマンド時限終了時における最大需要電力の目標すなわち時限単位目標電力を各施設2に配分する手段について、説明する。   Next, means for allocating the target of the maximum demand power at the end of the demand time limit, that is, the time unit target power to each facility 2 will be described.

図4は、中央制御装置6において行われる、時限単位目標電力を各施設2に配分する時限単位目標電力演算処理の動作を示すフローチャートである。   FIG. 4 is a flowchart showing the operation of the time-unit target power calculation process for allocating the time-unit target power to each facility 2 performed in the central controller 6.

中央制御装置6は、S1の手順で、デマンド時限終了後に、各施設2のデマンドコントロール装置5から、受電電力計測部7で計測されたデマンド時限終了時の需要電力、および節電可能電力計測部8で計測された節電可能電力を収集する。引き続いて、S2の手順で、各施設2のデマンドコントロール装置5から、デマンド時限内で演算部9で計測された制御対象負荷3に対する負荷制御実施時間を収集する。そして、収集した各データをデータ蓄積部13に蓄積する。なお、各データの収集タイミングは、現在のデマンド時限に演算結果を反映させる必要があることから、デマンド時限の開始直後に行われる。   The central controller 6 uses the procedure of S1 to measure the demand power at the end of the demand period measured by the received power measuring unit 7 from the demand control apparatus 5 of each facility 2 after the end of the demand period, and the power saving possible power measuring unit 8 Collect power that can be saved in Subsequently, the load control execution time for the control target load 3 measured by the calculation unit 9 within the demand time period is collected from the demand control device 5 of each facility 2 in the procedure of S2. The collected data is stored in the data storage unit 13. The collection timing of each data is performed immediately after the start of the demand time period because the calculation result needs to be reflected in the current demand time period.

次に、S3の手順にて、データ蓄積部13に蓄積された各施設2の負荷制御実施時間を、条件設定部14に設定された基準時間と比較し、負荷制御実施時間の長短を判断する。基準時間は、デマンド時限である30分よりも短い例えば10分などに設定されるが、設定により変更することができる。   Next, in the procedure of S3, the load control execution time of each facility 2 stored in the data storage unit 13 is compared with the reference time set in the condition setting unit 14, and the length of the load control execution time is determined. . The reference time is set to, for example, 10 minutes, which is shorter than the demand time of 30 minutes, but can be changed by setting.

負荷制御実施時間の長短を判断した結果、負荷制御実施時間が基準時間以上(負荷制御実施時間≧基準時間)である、S3の判断がYESの負荷制御長時間施設2に対しては、S4の手順で、条件設定部14にその施設2について設定された上限の目標電力を次回のデマンド時限の目標電力に設定する。この際、中央制御装置6は、負荷制御長時間施設2が複数ある場合には、これら各負荷制御長時間施設2の上限の目標電力の総和を総和上限目標電力として、時限単位目標電力演算部15で算出する。   As a result of determining the length of the load control execution time, the load control execution time is equal to or greater than the reference time (load control execution time ≧ reference time). In the procedure, the upper limit target power set for the facility 2 in the condition setting unit 14 is set as the target power for the next demand time limit. At this time, when there are a plurality of load control long-term facilities 2, the central control device 6 uses the sum of the upper limit target power of each load control long-time facility 2 as the total upper limit target power, and the time-unit target power calculation unit 15 is calculated.

また、負荷制御実施時間の長短を判断した結果、負荷制御実施時間が基準時間未満(負荷制御実施時間<基準時間)である、S3の判断がNOの負荷制御短時間施設2に対しては、S5の手順で、節電可能率を算出する。節電可能率は、節電可能電力容量に対する、データ蓄積部13に蓄積された節電可能電力の割合であり、以下の式(1)により、時限単位目標電力演算部15で算出される。
[節電可能率] = [節電可能電力] ÷ [節電可能電力容量] …(1)
In addition, as a result of determining the length of the load control execution time, the load control execution time is less than the reference time (load control execution time <reference time), and for the load control short-time facility 2 in which the determination of S3 is NO, In step S5, the power saving rate is calculated. The power saving rate is a ratio of the power saving possible power stored in the data storage unit 13 to the power saving possible power capacity, and is calculated by the time-unit target power calculation unit 15 by the following equation (1).
[Power saving rate] = [Power saving potential] ÷ [Power saving capacity] (1)

各負荷制御短時間施設2に対して上記の節電可能率を算出した後、次に、S6の手順にて、各負荷制御短時間施設2に新たに配分する目標電力の算出を行う。この算出は、例えば以下のように行われる。   After calculating the power saving possibility rate for each load control short-time facility 2, next, the target power newly allocated to each load control short-time facility 2 is calculated in the procedure of S6. This calculation is performed as follows, for example.

はじめに、節電可能電力容量に対する節電可能電力の割合が1以上である負荷制御短時間施設2に対して、節電可能率を1とする。節電可能電力容量を前年の最大需要電力とした場合に、節電可能負荷の稼働状況によっては、節電可能電力容量に対する節電可能電力の割合は1以上に成り得る。しかし、この割合は、負荷制御実施時間の短い施設2から長い施設2へ目標電力を配分する際に、配分できる節電可能電力の余裕の有無を判断することに使用される値であり、節電可能率を1以上の数値にしても意味をなさない。このため、節電可能電力容量に対する節電可能電力の割合が1以上である場合、上記のように節電可能率を1とする。そして、節電可能率を1とした負荷制御短時間施設2に対しては、前回のデマンド時限に設定された目標電力を変えずに、その目標電力を次回のデマンド時限の目標電力に設定する。   First, the power saving possible rate is set to 1 for the load control short-time facility 2 in which the ratio of the power saving possible power to the power saving possible power capacity is 1 or more. When the power-saving power capacity is the maximum demand power of the previous year, the ratio of power-saving power to the power-saving power capacity can be 1 or more depending on the operating status of the power-saving load. However, this ratio is a value used to determine whether there is a margin of power that can be allocated when distributing target power from the facility 2 with a short load control execution time to the facility 2 with a long load control time. Even if the rate is 1 or more, it does not make sense. For this reason, when the ratio of the power saving power to the power saving power capacity is 1 or more, the power saving rate is set to 1 as described above. For the load control short-time facility 2 with a power saving rate of 1, the target power is set to the target power for the next demand time period without changing the target power set for the previous demand time period.

また、節電可能電力容量に対する節電可能電力の割合が1未満である負荷制御短時間施設2、つまり、余裕施設に対しては、節電可能電力容量から節電可能電力を差し引いた余裕電力を以下の式(2)によって算出する。
[余裕電力] = [節電可能電力容量] − [節電可能電力] …(2)
Moreover, for the load control short-time facility 2 in which the ratio of the power-saving power capacity to the power-saving power capacity is less than 1, that is, the surplus facilities, the surplus power obtained by subtracting the power-saving power capacity from the power-saving power capacity is expressed as Calculated by (2).
[Reserved power] = [Power saving capacity]-[Power saving power] (2)

また、各負荷制御短時間施設2における余裕電力の総和を総和余裕電力とし、この総和余裕電力に対する余裕電力の割合を余裕率として以下の式(3)のように算出する。
[余裕率] = [余裕電力] ÷ [総和余裕電力] …(3)
Further, the sum of the surplus power in each load control short-time facility 2 is defined as the total surplus power, and the ratio of the surplus power to the total surplus power is calculated as a margin rate as shown in the following equation (3).
[Margin rate] = [Marginal power] ÷ [Total marginal power] (3)

ここで、負荷制御実施時間の長い負荷制御長時間施設2の目標電力は、S4の手順で既に上限値に設定されているため、総和最大需要電力が総和目標電力を超過しないようにさせるために、総和目標電力から総和上限目標電力を差し引いて算出される残電力を、余裕率に応じて負荷制御短時間施設2に分配する。この分配は、例えば、以下の式(4)のように算出される新規目標電力を余裕施設に設定することで、行われる。
[余裕施設の新規目標電力]
= [総和目標電力―総和上限目標電力] × [1−余裕率] …(4)
Here, since the target power of the load control long-time facility 2 having a long load control execution time is already set to the upper limit value in the procedure of S4, in order to prevent the total maximum demand power from exceeding the total target power. The remaining power calculated by subtracting the total upper limit target power from the total target power is distributed to the load control short-time facility 2 according to the margin rate. This distribution is performed, for example, by setting a new target power calculated as shown in the following formula (4) in a margin facility.
[New target power for surplus facilities]
= [Total target power-Total upper limit target power] x [1-margin ratio] (4)

この分配により、余裕のある負荷制御短時間施設2に対しては、その新規目標電力が余裕のある分だけ減少させられる。また、S3の手順で、全施設2の負荷制御実施時間が基準時間より長くまたは短く、全施設2が負荷制御実施時間の長いまたは短い施設2である場合には、特に目標電力を再配分する必要はなく、前回のデマンド時限と同じ目標電力を新規目標電力に設定する。   As a result of this distribution, the new target power is reduced by a margin for the load control short-time facility 2 with a margin. Further, in the procedure of S3, when the load control execution time of all facilities 2 is longer or shorter than the reference time and all the facilities 2 are facilities 2 having a long or short load control execution time, the target power is redistributed particularly. There is no need, and the same target power as the previous demand time limit is set as the new target power.

以上の演算により、各施設2の新規な時限単位デマンド目標電力を算出後、S7の手順にて、各施設2のデマンドコントロール装置5に対し、新規目標電力を送信する。S7の手順を終えると、中央制御装置6は時限単位目標電力演算処理を終了する。   After calculating the new time unit demand target power of each facility 2 by the above calculation, the new target power is transmitted to the demand control device 5 of each facility 2 in the procedure of S7. When the procedure of S7 is completed, the central controller 6 ends the time-unit target power calculation process.

このように本実施の形態の省エネルギーシステム1では、中央制御装置6により、各施設2のデマンドコントロール装置5からデータが収集され、各施設2における最大需要電力の総和に相当する総和最大需要電力が、設定された総和目標電力値を超過しないように、各施設2の目標電力値が算出される。算出された目標電力値は、中央制御装置6により通信部12および通信部11を介して各施設2のデマンドコントロール装置5に配分される。このため、中央制御装置6により、複数施設2でのデマンド時限内の総和最大需要電力が総和目標電力値内に抑制され、複数施設2の総和目標電力値を超過することなく、手間を要しないで各施設2の負荷制御を行うことが可能となる。また、中央制御装置6により、各施設2のデマンドコントロール装置5から、デマンド時限内で負荷制御を実施した負荷制御実施時間が収集され、負荷制御実施時間が短い負荷制御短時間施設2に割り当てられた目標電力が負荷制御実施時間が長い負荷制御長時間施設2の目標電力に配分される。このため、総和目標電力値を変えずに各施設2における負荷制御の頻度の均衡を図ることが可能になる。   As described above, in the energy saving system 1 according to the present embodiment, the central control device 6 collects data from the demand control device 5 of each facility 2, and the total maximum demand power corresponding to the sum of the maximum demand power in each facility 2 is obtained. The target power value of each facility 2 is calculated so as not to exceed the set total target power value. The calculated target power value is distributed to the demand control device 5 of each facility 2 by the central control device 6 via the communication unit 12 and the communication unit 11. For this reason, the central control device 6 suppresses the total maximum demand power within the demand time limit in the plurality of facilities 2 within the total target power value, and does not exceed the total target power value of the plurality of facilities 2, and does not require labor. Thus, the load control of each facility 2 can be performed. Also, the central control device 6 collects the load control execution time during which the load control is performed within the demand time period from the demand control device 5 of each facility 2 and assigns it to the load control short-time facility 2 with a short load control execution time. The target power is distributed to the target power of the load control long-time facility 2 having a long load control execution time. For this reason, it is possible to balance the frequency of load control in each facility 2 without changing the total target power value.

本実施形態では、負荷制御実施時間が長く、最大需要電力が目標電力にひっ迫する負荷制御長時間施設2には、中央制御装置6により、その施設2に設定可能な上限の目標電力が図4、S4の手順で設定される。このため、負荷制御長時間施設2では、目標電力と最大需要電力との間に余裕が生まれ、頻繁に行われていた負荷制御の頻度は減少する。一方、負荷制御実施時間が短く、最大需要電力と目標電力との間に余裕がある負荷制御短時間施設2には、中央制御装置6により、総和上限目標電力を総和目標電力値から差し引いた残電力が式(4)のように算出されて再配分され、目標電力が下げられる。しかし、負荷制御短時間施設2では、最大需要電力と目標電力との間に余裕があったため、目標電力が下げられても、負荷制御の頻度に及ぶ影響は小さい。この結果、総和目標電力値を変えずに各施設2における負荷制御の頻度の均衡が図られる。   In the present embodiment, the load control long-time facility 2 in which the load control execution time is long and the maximum demand power is constrained to the target power, the upper limit target power that can be set in the facility 2 by the central controller 6 is shown in FIG. , S4 is set. For this reason, in the load control long-time facility 2, a margin is created between the target power and the maximum demand power, and the frequency of the load control that has been frequently performed decreases. On the other hand, in the load control short-time facility 2 where the load control execution time is short and there is a margin between the maximum demand power and the target power, the central control device 6 uses the central control device 6 to subtract the total upper limit target power from the total target power value. The power is calculated and redistributed as shown in Equation (4), and the target power is lowered. However, since the load control short-time facility 2 has a margin between the maximum demand power and the target power, even if the target power is lowered, the influence on the frequency of the load control is small. As a result, the frequency of load control in each facility 2 is balanced without changing the total target power value.

また、本実施形態では、図4、S5およびS6の手順で、節電可能電力容量に対する節電可能電力の比率が1未満で、節電可能電力に余裕のある負荷制御短時間施設2に対して、総和上限目標電力を総和目標電力値から差し引いた残電力の配分が行われる。このため、負荷制御短時間施設2であっても、節電可能電力容量に対する節電可能電力の比率が1以上で、節電可能電力に余裕のない負荷制御短時間施設2に対しては、残電力の配分が行われない。また、上記比率が1未満の負荷制御短時間施設2に対する残電力の配分は、総和余裕電力に対する余裕電力の比率である余裕率に応じて式(4)のように行われ、節電可能電力に余裕のある施設2には残電力が少なく配分されることになる。このため、上記比率が1未満の負荷制御短時間施設2に対する残電力の配分は、各施設2の余裕電力に応じて公平に行われ、負荷制御は、特定の負荷制御短時間施設2に集中することなく、各負荷制御短時間施設2間でバランスよく行われる。   Further, in the present embodiment, in the procedure of FIGS. 4, S5 and S6, the ratio of the power saving possible power to the power saving possible power capacity is less than 1, and the sum total is applied to the load control short-time facility 2 having a margin in the power saving possible power. The remaining power is distributed by subtracting the upper limit target power from the total target power value. For this reason, even in the load control short-time facility 2, the ratio of the power-saving power to the power-saving power capacity is 1 or more, and the load control short-time facility 2 having no margin for power-saving power Allocation is not performed. Further, the distribution of the remaining power to the load control short-time facility 2 with the ratio less than 1 is performed according to the margin ratio, which is the ratio of the margin power to the total margin power, as shown in Equation (4), and the power can be saved. The remaining power 2 is allocated to the facility 2 having a margin. For this reason, the distribution of the remaining power to the load control short-time facilities 2 having the ratio of less than 1 is performed fairly according to the surplus power of each facility 2, and the load control is concentrated on the specific load control short-time facilities 2. Without being performed, each load control is performed in a balanced manner between the facilities 2 for a short time.

なお、時限単位目標電力を各施設2にバランスよく配分する時限単位目標電力演算処理として、本実施の形態で説明した図4に示す処理でなく、次のような処理が考えられる。つまり、中央制御装置6が、デマンド時限終了時における制御対象負荷3の消費電力を節電可能電力として各施設2から通信手段によって収集し、各施設2の目標電力値の総和が総和目標電力値以下となるように、節電可能電力容量に対する節電可能電力の割合が小さい施設の目標電力を優先的に減少させて、目標電力を再配分する。この時限単位目標電力演算処理によれば、節電可能電力容量に対する節電可能電力の割合が小さい施設2、つまり、電力供給を絶って消費電力を大きく節減することが出来る制御対象負荷3を有する施設2から、優先して目標電力が下げられ、施設2全体での負荷制御の頻度を低下させることが出来る。   Note that, as the time-unit target power calculation processing for distributing the time-unit target power to each facility 2 in a balanced manner, the following processing can be considered instead of the processing shown in FIG. 4 described in the present embodiment. That is, the central control device 6 collects the power consumption of the control target load 3 at the end of the demand time period as the power saving power from each facility 2 by the communication means, and the sum of the target power value of each facility 2 is less than the total target power value. Thus, the target power of the facility having a small ratio of the power saving power capacity to the power saving power capacity is reduced preferentially, and the target power is redistributed. According to this time-unit target power calculation processing, the facility 2 having a small ratio of the power saving power to the power saving power capacity, that is, the facility 2 having the control target load 3 that can greatly reduce power consumption by cutting off the power supply. Therefore, the target power is reduced with priority, and the frequency of load control in the entire facility 2 can be reduced.

しかしながら、節電可能電力容量は、主に制御対象負荷3となる空調機の設備容量、または前年最大電力などの固定値として設定されることが多く、また、季節・時間帯によって節電等のためにあらかじめ強制的に電力供給を停止することもあるため、条件設定部14に設定した値を頻繁に設定変更する必要が生じることになる。ここで、この節電可能電力容量の設定変更をし忘れた場合、条件設定部14に設定された値よりも実際の節電可能電力容量の値の方が小さくなり、設定された節電可能電力容量に対する節電可能電力の割合が、実際の節電可能電力容量に対する割合よりも小さくなることがある。このような場合、その施設2は、目標電力を再配分する際に常に割合が小さい施設2と誤認識され、デマンド時限を更新した後も頻繁に負荷制御が起動するような、低い目標電力が配分されることになる。このため、上述の、節電可能電力容量に対する節電可能電力の割合が小さい施設の目標電力を優先的に減少させて目標電力を再配分する時限単位目標電力演算処理では、当該省エネシステムの目的である各施設2の負荷制御の頻度をバランスよく保つことが困難となることが、考えられる。   However, the power-saving capacity is often set as a fixed value such as the capacity of the air conditioner that is the load to be controlled 3 or the previous year's maximum power. Since the power supply may be forcibly stopped in advance, the value set in the condition setting unit 14 needs to be frequently changed. Here, when it is forgotten to change the setting of the power-saving power capacity, the actual power-saving power capacity value is smaller than the value set in the condition setting unit 14, and the power-saving power capacity is set with respect to the set power-saving power capacity. The ratio of power that can be saved may be smaller than the ratio of the actual power saving capacity. In such a case, the facility 2 is misrecognized as a facility 2 that always has a small proportion when the target power is redistributed, and the target power is low so that the load control is frequently activated even after the demand time period is updated. Will be allocated. For this reason, the above-mentioned time-unit target power calculation processing that preferentially decreases the target power of the facility having a small ratio of the power saving possible power capacity to the power saving possible power capacity and redistributes the target power is the purpose of the energy saving system. It is conceivable that it is difficult to maintain a balanced load control frequency for each facility 2.

例えば、A施設2の節電可能電力容量が800kW、節電可能電力が200kWである場合、節電可能電力容量に対する節電可能電力の割合は0.25(=200kW/800kW)である。しかし、既に300kW分の負荷が停止してこれを制御対象負荷3にできない場合は、実際の節電可能電力容量は500kW(=800kW−300kW)になり、実際の節電可能電力容量に対する節電可能電力の割合は0.4(=200kW/500kW)となる。一方、B施設2での制御対象負荷3はすべて制御可能であり、その節電可能電力容量が300kW、節電可能電力が100kWの場合、節電可能電力容量に対する節電可能電力の割合は0.33(=100kW/300kW)となる。この場合、中央制御装置6で演算される節電可能電力容量に対する節電可能電力の割合は、A施設2の0.25が最も小さくなるため、A施設2に最も小さな目標電力が再配分されることになる。このため、A施設2では、常に負荷制御を伴う目標電力で稼働する必要が出てくる。   For example, when the power saving power capacity of the facility A 2 is 800 kW and the power saving power capacity is 200 kW, the ratio of the power saving power capacity to the power saving power capacity is 0.25 (= 200 kW / 800 kW). However, when the load of 300 kW has already stopped and cannot be made the load 3 to be controlled, the actual power-saving power capacity is 500 kW (= 800 kW-300 kW), and the power-saving power with respect to the actual power-saving power capacity The ratio is 0.4 (= 200 kW / 500 kW). On the other hand, when all the control target loads 3 in the facility B are controllable and the power-saving power capacity is 300 kW and the power-saving power is 100 kW, the ratio of the power-saving power to the power-saving power capacity is 0.33 (= 100 kW / 300 kW). In this case, the ratio of the power saving possible power to the power saving possible power capacity calculated by the central controller 6 is that 0.25 of the A facility 2 is the smallest, so that the smallest target power is redistributed to the A facility 2. become. For this reason, in the A facility 2, it becomes necessary to always operate with the target power accompanied by load control.

しかし、本実施の形態で説明した図4に示す時限単位目標電力演算処理を行うと、中央処理装置6は、各施設2のデマンドコントロール装置5が、予め設定された目標電力値内に需要電力を抑え込むための自動負荷制御を起動している負荷制御実施時間を把握する。そして、負荷制御実施時間の長い施設2に対しては、負荷制御が起動しにくい高い目標電力を設定し、負荷制御実施時間の短い施設2に対しては、これまでより負荷制御が起動しやすい低い目標電力を設定する。これにより、負荷制御実施時間の長い施設2の目標電力を一旦上げることで、負荷制御長時間施設2でさらなる負荷制御を起動させなくし、一方、負荷制御短時間施設2には目標電力を余裕電力に応じて減じることで、上記の不都合を生じさせずに、バランスよく目標電力を再配分することが可能となる。この結果、複数施設2の総和目標電力を超過することなく、また、節電可能電力容量を頻繁に変更することなく、すでにデマンドコントロール装置5による負荷制御が実施されている施設2にさらなる負荷制御が集中しない、バランスの良い目標電力の配分を行うことを可能とする省エネルギーシステムが提供される。   However, when the timed unit target power calculation process shown in FIG. 4 described in the present embodiment is performed, the central processing unit 6 causes the demand control device 5 of each facility 2 to have a power demand within a preset target power value. To grasp the load control execution time when the automatic load control is started to suppress the load. For facilities 2 with a long load control execution time, a high target power that makes it difficult to start load control is set, and for facilities 2 with a short load control execution time, load control is easier to start than before. Set a lower target power. Thus, once the target power of the facility 2 having a long load control execution time is once increased, the load control long-time facility 2 does not activate further load control. Accordingly, the target power can be redistributed in a well-balanced manner without causing the above-described inconvenience. As a result, further load control is performed on the facility 2 where load control has already been performed by the demand control device 5 without exceeding the total target power of the plurality of facilities 2 and without frequently changing the power saving capacity. Provided is an energy saving system that makes it possible to distribute well-balanced target power without being concentrated.

上記の実施の形態では、本発明による省エネルギーシステムを、各施設における最大需要電力の総和が、設定された総和目標電力値を超過しないように負荷制御する場合について、説明した。しかし、本発明による省エネルギーシステムは、これに限定されることはなく、電力系統の需要電力ひっ迫などの情報にもとづく電力使用制限要求がある場合の負荷制御にも、設定する総和目標電力値を制限要求のある電力値とすることで、同様に適用することが出来、同様な作用効果が奏される。   In the above embodiment, the energy saving system according to the present invention has been described for the case where the load control is performed so that the sum of the maximum demand power in each facility does not exceed the set sum target power value. However, the energy saving system according to the present invention is not limited to this, and the total target power value to be set is also limited for load control when there is a power usage restriction request based on information such as demand power tightness of the power system. By setting the required power value, it can be applied in the same manner, and the same effect can be obtained.

1…省エネルギーシステム
2…施設
3…制御対象負荷(節電可能負荷)
4…電力量計
5…デマンドコントロール装置(電力抑制装置)
6…中央制御装置
7…受電電力計測部
8…節電可能電力計測部
9…演算部
10…制御出力部
11,12…通信部(通信手段)
13…データ蓄積部
14…条件設定部
15…時限単位目標電力演算部
16…時限内デマンド演算部
1 ... Energy-saving system 2 ... Facility 3 ... Control target load (load that can save power)
4 ... Electricity meter 5 ... Demand control device (power suppression device)
6 ... Central control device 7 ... Received power measurement unit 8 ... Power saving possible power measurement unit 9 ... Calculation unit 10 ... Control output unit 11, 12 ... Communication unit (communication means)
DESCRIPTION OF SYMBOLS 13 ... Data storage part 14 ... Condition setting part 15 ... Time-unit target electric power calculation part 16 ... In-time demand calculation part

Claims (3)

節電可能負荷への通電を制御する負荷制御を行うことで任意の単位時間で定義されるデマンド時限内の施設内使用電力を目標電力値以下に抑制制御する、各施設に設置された電力抑制装置と、各施設における最大需要電力の総和に相当する総和最大需要電力が設定された総和目標電力値を超過しないように各施設の目標電力値を算出し、算出した目標電力値を各施設の前記電力抑制装置に配分する中央制御装置と、前記電力抑制装置および前記中央制御装置間の通信を行う通信手段とから構成され、
前記電力抑制装置は、デマンド時限内で前記負荷制御を実施した負荷制御実施時間を計測し、
前記中央制御装置は、前記電力抑制装置で計測された前記負荷制御実施時間を各施設から前記通信手段によって収集し、前記負荷制御実施時間が短い負荷制御短時間施設に割り当てられた目標電力を前記負荷制御実施時間が長い負荷制御長時間施設の目標電力に配分することで、前記総和目標電力値を変えずに各施設における前記負荷制御の頻度の均衡を図る省エネルギーシステム。
Power control devices installed in each facility that control the power consumption in the facility within the demand time period defined in an arbitrary unit time by controlling the power supply to the power-saving load. And calculating the target power value of each facility so that the total maximum demand power corresponding to the sum of the maximum demand power in each facility does not exceed the set total target power value, and the calculated target power value A central control device that distributes power control devices, and communication means that communicates between the power control device and the central control device,
The power suppression device measures a load control execution time in which the load control is performed within a demand time period,
The central control device collects the load control execution time measured by the power suppression device from each facility by the communication means, and sets the target power allocated to the load control short-time facility with the short load control execution time as the target power. An energy saving system that balances the frequency of the load control in each facility without changing the total target power value by allocating to the target power of the load control facility having a long load control execution time.
前記中央制御装置は、前記負荷制御長時間施設に対してはその施設に設定可能な上限の目標電力を設定し、前記負荷制御短時間施設に対しては、各前記負荷制御長時間施設における前記上限の目標電力の総和に相当する総和上限目標電力を前記総和目標電力値から差し引いた残電力を配分することで、目標電力を再配分することを特徴とする請求項1に記載の省エネルギーシステム。   The central control unit sets an upper limit target power that can be set for the load control long-time facility, and for the load control short-time facility, the load control long-time facility 2. The energy saving system according to claim 1, wherein the target power is redistributed by allocating a remaining power obtained by subtracting a total upper limit target power corresponding to a total of the upper limit target power from the total target power value. 前記中央制御装置は、デマンド時限終了時における前記節電可能負荷の消費電力である節電可能電力を各施設から前記通信手段によって収集し、前記節電可能負荷の電力容量である節電可能電力容量に対する前記節電可能電力の比率が1未満である前記負荷制御短時間施設に対して、前記節電可能電力容量から前記節電可能電力を差し引いた余裕電力、および、前記余裕電力の総和に相当する総和余裕電力に対する前記余裕電力の比率である余裕率を算出し、前記余裕率に応じて前記残電力を配分することを特徴とする請求項2に記載の省エネルギーシステム。   The central control device collects power-saving power that is power consumption of the power-saving load at the end of the demand time period from each facility by the communication means, and the power-saving power capacity that is the power capacity of the power-saving load is collected. For the load control short-time facility whose ratio of possible power is less than 1, the margin power obtained by subtracting the power saving potential power from the power saving potential power capacity, and the total margin power corresponding to the sum of the margin power The energy saving system according to claim 2, wherein a margin ratio that is a ratio of margin power is calculated, and the remaining power is distributed according to the margin ratio.
JP2013055469A 2013-03-18 2013-03-18 Energy saving system Active JP6016681B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013055469A JP6016681B2 (en) 2013-03-18 2013-03-18 Energy saving system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013055469A JP6016681B2 (en) 2013-03-18 2013-03-18 Energy saving system

Publications (2)

Publication Number Publication Date
JP2014183632A JP2014183632A (en) 2014-09-29
JP6016681B2 true JP6016681B2 (en) 2016-10-26

Family

ID=51701876

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013055469A Active JP6016681B2 (en) 2013-03-18 2013-03-18 Energy saving system

Country Status (1)

Country Link
JP (1) JP6016681B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6252250B2 (en) * 2014-02-28 2017-12-27 富士電機株式会社 Demand control method and demand control system
JP7268814B2 (en) * 2019-02-13 2023-05-08 株式会社ダイヘン power management system
JP7258648B2 (en) * 2019-05-17 2023-04-17 大崎電気工業株式会社 Power demand forecasting device for the target facility
JP7093034B2 (en) * 2020-09-30 2022-06-29 ダイキン工業株式会社 Power control system and program

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5597144A (en) * 1979-01-16 1980-07-24 Tokyo Electric Power Co Method of shielding load of demand monitor
JPS58222728A (en) * 1982-06-18 1983-12-24 株式会社東芝 Power receiving device
JPH09224331A (en) * 1996-02-15 1997-08-26 Nishikawa Densetsu:Kk Power-receiving device
JPH11215700A (en) * 1998-01-27 1999-08-06 Mitsubishi Electric Corp Demand control method and device thereof
JP4032903B2 (en) * 2002-09-27 2008-01-16 ダイキン工業株式会社 Target power control system
JP3768229B1 (en) * 2005-12-05 2006-04-19 アイ電気通信株式会社 Power control device

Also Published As

Publication number Publication date
JP2014183632A (en) 2014-09-29

Similar Documents

Publication Publication Date Title
US11271400B2 (en) Power control device, operation plan planning method, and recording medium
CN106575883B (en) Managing device and management method
JP6249895B2 (en) Power control system, method, and power control apparatus
US20170159955A1 (en) Air-conditioning controller, air-conditioning control method and air-conditioning control program
US9651975B2 (en) System, method and apparatus for power demand adjustment based on consumer annoyance
JP5789764B1 (en) Storage battery management apparatus and method thereof
JP6016681B2 (en) Energy saving system
US10496060B2 (en) Power management system and method for power management
US10571947B2 (en) Increasing the demand reduction effectiveness of an energy storage system
WO2016002346A1 (en) Power control system, and power control device
WO2016136260A1 (en) Power management device, power management system, and power management method
JP2013078177A (en) Electric power accommodation system, demand control device, demand control method and program
WO2016084313A1 (en) Power demand adjustment system, demand adjustment device, group generation device, and group generation method
JP6108665B2 (en) Energy saving system
JP2016046934A (en) Energy management system, community energy management system, and user energy management system
WO2014185014A1 (en) Management apparatus, device management method, and management system
US20160241033A1 (en) Control device, control method, and program
KR101744576B1 (en) Power dissipation operation system using small and medium distributed ess
JP6778891B2 (en) Power management system, power management method and program
JP2017195752A (en) Electric power control system and power control method
WO2017163934A1 (en) Power control system, control device, control method, and computer program
JP6261755B2 (en) Control device, device control method, and program
JP2018026913A (en) Power management system
JP6454929B2 (en) Storage battery control system, storage battery control method, and program
JP2016127622A (en) Power demand prediction system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160122

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20160921

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160927

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160927

R150 Certificate of patent or registration of utility model

Ref document number: 6016681

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250