JPS58222728A - Power receiving device - Google Patents
Power receiving deviceInfo
- Publication number
- JPS58222728A JPS58222728A JP57103946A JP10394682A JPS58222728A JP S58222728 A JPS58222728 A JP S58222728A JP 57103946 A JP57103946 A JP 57103946A JP 10394682 A JP10394682 A JP 10394682A JP S58222728 A JPS58222728 A JP S58222728A
- Authority
- JP
- Japan
- Prior art keywords
- loads
- load
- demand
- power
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔発明の技術分野〕
本発明は、電力を受電する場合のデマンド制御に関する
。DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to demand control when receiving electric power.
デマンド制御は、単位時間で使用する積算電力量を電力
会社との契約値以内に押えようとする制御を言うが、多
くの場合この制御は負荷をしゃ断する方法がとられてい
る。Demand control refers to control that attempts to keep the cumulative amount of electricity used per unit time within the contracted value with the electric power company, and in many cases this control is performed by cutting off the load.
第1図及び第2図は従来のデマンド制御方法を説明した
ものである。横軸は時間で、縦軸は負荷の種類を7a、
7b〜7nは負荷が−しゃ断されている時間を表わして
いる。FIGS. 1 and 2 illustrate a conventional demand control method. The horizontal axis is time, and the vertical axis is load type 7a,
7b to 7n represent the time during which the load is cut off.
第1図は優先しゃ新方法と言っているもので、しゃ断負
荷に優先順位を付けておき、しゃ断する場合は優先順位
の低いものから、復旧する場合は優先順位の高いものか
ら投入する方法である。Figure 1 shows the new priority method, in which the load to be shut off is prioritized, and when shutting off, the load with the lowest priority is applied, and when restoring, the load with the highest priority is applied. be.
第2図はサイクリック方法と言っているものでしゃ断負
荷に順位はついているが、第1図と違って優先順位では
なく、単なる順番であり、若番からしゃ断して行くが復
旧する場合、しゃ断された順位で投入してゆく方法であ
る。この方法は第1図の方法と違い常に同一の負荷から
しゃ断してゆくという欠点は取りのぞかれている。Figure 2 shows what is called a cyclic method, in which the load to be shut off is ranked, but unlike Figure 1, it is not a priority order, but simply an order, and when the load is restored starting from the lowest number, This is a method of introducing players in the cut-off positions. Unlike the method shown in FIG. 1, this method does not have the disadvantage of always cutting off the same load.
しかしこの2方法とも1つの負荷が長時間しや断されっ
ばなしになるという欠点を持っている。However, both of these methods have the disadvantage that one load is interrupted for a long time.
これは例えば30分デマンドにおいて15分目にレベル
1のみしゃ断すればデマンド超過しないと予測されると
第1図優先しゃ新方法では常にレベル1が15分間しゃ
断されることになり、第2図サイクリック方法では、デ
マンド時間が変化するたびにしゃ断される負荷は変わる
が、単位デマンド時間内では連続15分しゃ断されっば
なしになる。とのように従来の方法では同一負荷が長時
間しゃ断されっばなしになる欠点があり、超過予測量が
変わつ之としてもこの傾向は変わらない。For example, if it is predicted that if only level 1 is cut off in the 15th minute of a 30-minute demand, the demand will not be exceeded, then with the new method that gives priority to Figure 1, level 1 will always be cut off for 15 minutes, and Figure 2 In the click method, the load to be cut off changes every time the demand time changes, but it will not be cut off if the load is cut off for 15 consecutive minutes within a unit demand time. The conventional method has the disadvantage that if the same load is cut off for a long time, it will disappear, and this tendency will not change even if the predicted excess amount changes.
本発明はこのようガ欠点をとや除き、同一負荷のみしゃ
断されることがかいようにしたものである。The present invention is designed to eliminate this drawback and allow only the same load to be cut off.
本発明は受電した電力を配分して使用する複数の負荷と
、これらの負荷を開閉するしゃ断器と、受電した電力の
積算値を計測する発振装置付きの積算電力針とからなる
受配電装置に於て、積算電力計からの出力信号により最
大需要電力量の超過予測量を演算する機能及びこの超過
予測量に応じて負荷を群れ分けする機能並びにこの群れ
分けされた負荷の停電時間が予め定められた時間内で均
等になるようにしゃ断器を開閉制御する機能全有する最
大需要電力制御装置を備えた受配電装置である。即ち本
発明はデマンド超過予測量に応じ負荷をしゃ断する電力
デマンド制御方法において、デマンド超過予測量に応じ
負荷を複数のグループにし、グループの被しゃ断時間が
同一デマント時間内で均等になるように順次グループ単
位でしゃ断することを特徴としたデマンド制御を行う受
配電装置である。The present invention relates to a power receiving and distributing device that includes a plurality of loads that distribute and use received power, a breaker that opens and closes these loads, and an integrated power needle with an oscillator that measures the integrated value of the received power. A function to calculate the predicted excess of the maximum demand power amount based on the output signal from the integrating wattmeter, a function to divide the loads into groups according to this predicted excess amount, and a predetermined power outage time for the divided loads. This is a power receiving and distributing device equipped with a maximum power demand control device that has the full function of controlling the opening and closing of circuit breakers evenly within a specified time. That is, the present invention provides a power demand control method for cutting off a load according to a predicted amount of excess demand, in which the loads are divided into a plurality of groups according to the predicted amount of excess demand, and the loads are sequentially divided into groups so that the cut-off times of the groups are equal within the same demand time. This is a power receiving and distributing device that performs demand control and is characterized by shutting off on a group-by-group basis.
本発明は前記のように構成したのでデマンド制御負荷が
長時間しゃ断されることが々く、又同一負荷のみしゃ断
し、電力供給サービスが低下するということが避けられ
るという効果を生ずる。Since the present invention is configured as described above, the demand control load is often cut off for a long time, and it is possible to avoid the situation where only the same load is cut off and the power supply service deteriorates.
次に本発明の実施例について説明する、第3図はデマン
ド制御装置と、しゃ断負荷の関係を表わした図であり、
1は発振装置付の積算電力量計、2はデマンド制御装置
、3a、3b〜3nはしゃ断器、4a、4b〜4n’は
デマンド制御対象の負荷で、おのおのしゃ断器と対の関
係となっている。Next, an embodiment of the present invention will be explained. FIG. 3 is a diagram showing the relationship between the demand control device and the cutoff load.
1 is an integrated electricity meter with an oscillator, 2 is a demand control device, 3a, 3b to 3n are circuit breakers, and 4a, 4b to 4n' are loads to be controlled by demand, each of which is in a pair with a circuit breaker. There is.
第3図は受電した電力を配分して使用する複数の負荷4
a、4b−4nと、負荷4a、4b−4nを開閉するし
ゃ断器3a、3b〜3nと、受電した電力の積算値を計
測する発振装置付きの積算電力量計1とからなる受配電
装置に於て、積算電力量計1からの出力信号により最大
需要電力量の超過予測量を演算する機能及びこの超過予
測量に応じて負荷4a、4b〜4nを群れ分けする機能
並びにこの群れ分けされた負荷4a、4b〜4nの停電
時間が予め定められた時間内で均等になるようにしゃ断
器3a、3b〜3nを開閉制御する機能を有するデマン
ド制御装置2を備えた受配電装置を示している。Figure 3 shows multiple loads 4 that distribute and use the received power.
a, 4b-4n, circuit breakers 3a, 3b to 3n that open and close loads 4a, 4b-4n, and an integrated power meter 1 with an oscillation device that measures the integrated value of received power. In this case, there is a function to calculate the predicted excess amount of the maximum demand power amount based on the output signal from the integrated power meter 1, a function to group the loads 4a, 4b to 4n according to this predicted excess amount, and a function to group the loads 4a, 4b to 4n, and It shows a power receiving and distributing device equipped with a demand control device 2 that has a function of controlling the opening and closing of circuit breakers 3a, 3b to 3n so that the power outage times of loads 4a, 4b to 4n are equalized within a predetermined time. .
第4図は本発明を説明したタイムチャートである。横軸
は時間、縦軸は負荷の種類、7a〜7nは負荷がしゃ断
されている時間を表わす。この方法はデマンドの超過予
測が行なわれると超過分に相当する電力をn個の負荷で
分配し一負荷当りのしゃ断時間を短かくする方法である
。この方法は建物等である系統の空調機ばかりをしゃ断
するとそとのサービスが悪くなるが少時間であれば空調
条件に余り影響を受けないような負荷をデマンド制御対
象負荷にする場合など有効となる3、第4図はt分目に
デマンド超過予測がされ、それ以後の負荷しゃ断のスケ
ジュールを図示したものである。FIG. 4 is a time chart explaining the present invention. The horizontal axis represents time, the vertical axis represents the type of load, and 7a to 7n represent the time during which the load is cut off. In this method, when an excess demand is predicted, the power corresponding to the excess amount is distributed among n loads to shorten the cut-off time per load. This method is effective when shutting off only the air conditioners in a certain system, such as a building, and the service there deteriorates, but for a short time, loads that are not affected by air conditioning conditions are targeted for demand control. Figure 4 shows the schedule for load shedding after the demand exceedance is predicted at the tth minute.
スケジューリングは次の式に従かい行ガう。Scheduling is performed according to the following formula.
ここでTeはデマンド超過予測時からデマンド時間終了
時までののこり時間
Wdはデマンド超過電力量
W は各しゃ断食荷量であり、はぼ等しくなるように負
荷が設定されている。Here, Te is the remaining time Wd from the time when the demand exceedance is predicted to the end of the demand time, and the excess demand electric energy W is the amount of each shutoff load, and the loads are set so that they are approximately equal.
n はしゃ断負荷のグループ数
nm はすでにしゃ断された負荷の数で、最初に超過
予測された時点では零である。n is the number of groups of interrupted loads, nm is the number of loads that have already been interrupted, and is zero at the time when the excess is first predicted.
残シ時間Teで電力量Wdだけ超過すると予測された場
合
W =” x Wd ことでTDはデマンド周期
(分)T。If it is predicted that the amount of electricity Wd will be exceeded in the remaining time Te, then W = " x Wd. Therefore, TD is the demand period (minutes) T.
Wは減電力
Wだけ現在の瞬時電力をしゃ断すればデマンド超過にな
らないことを示す。W indicates that if the current instantaneous power is cut off by the reduced power W, the demand will not be exceeded.
次にWだけしゃ断するための負′荷を、スケジューリン
グする。Next, the load for cutting off only W is scheduled.
今1つのしゃ所員荷量はWであるから
W ) w
の時複数の負荷を同時にしゃ断しないとデマンド超過に
な、る。Since the load capacity of one shutoff station is W, demand will be exceeded unless multiple loads are shut off at the same time when W ) w .
このため KXw≧W>(K−1)xwとなるよう
に K(同時しゃ所員筒数)を決定する。Therefore, K (the number of cylinders in simultaneous operation) is determined so that KXw≧W>(K-1)xw.
全負荷数がnであるので減電力WK対し、rv’にの値
の整数を今時点でのしゃ断グループ数りとし、残り時間
Toの間でしゃ断グループが均等な時間になるようにし
ゃ断時間Ts f決定しスケジューリングする。Since the total number of loads is n, for the power reduction WK, let the integer value of rv' be the current number of cutoff groups, and set the cutoff time Ts so that the cutoff groups have equal time during the remaining time To. Determine and schedule f.
1グループのしゃ断時間Taは
T8”Te/L
となり、K個の負荷iTa時間だけしゃ断し、T!I時
間経過後しゃ断した負荷を投入し、次のに個の負荷iT
s時間しゃ断しデマンド終了時までこの操作を繰シ返し
デマンドの制御を行なう。The cut-off time Ta of one group is T8”Te/L, and the cut-off time for K loads iTa is turned on. After the T!I time has elapsed, the cut-off loads are turned on, and the next load iT is turned on.
This operation is repeated until the demand is shut off for a time s and the demand is controlled.
又、デマンドの監視は通常1分毎に行なわれるが、順次
1分毎に予測し減電力が
KXw≧KXw+W)(K−1)w
の時、現状維持とし、そうでない時はグループの組替え
もしくはデマンド制御復帰を行なう。In addition, demand monitoring is normally performed every minute, but it is sequentially predicted every minute, and when the power reduction is KXw≧KXw+W) (K-1)w, the status quo is maintained, and if not, the group is rearranged or Perform demand control recovery.
グループの組替えを行なう場合、すでにしゃ断された負
荷を除いた負荷により前記の方式でスケジューリングを
行ない、1分毎に順次デマンド予測を行ない次々とスケ
ジューリングを変更してゆく、デマンド時間が終了し九
時、全負荷を投入し次のデマンド時間でのデマンド制御
にそなえるが次の周期でのグループわけの先頭となる負
荷は前周期でしゃ断されなかった負荷、もしくは前周期
で全負荷がしゃ断された場合は前周期での2番目の負荷
が今周期での先頭負荷となるように調整ヲ一・行ない、
常に同じ負荷がしゃ断対象にならないようにしている。When rearranging groups, scheduling is performed using the above method using the load excluding the load that has already been cut off, and the demand is sequentially predicted every minute and the scheduling is changed one after another.The demand time ends at 9 o'clock. , all loads are turned on to prepare for demand control at the next demand time, but the load that will be the first group to be grouped in the next cycle is a load that was not cut off in the previous cycle, or if all loads were cut off in the previous cycle. Adjust so that the second load in the previous cycle becomes the first load in the current cycle,
This ensures that the same load is not always subject to interruption.
第1図、第2図は従来のデマンド制御方法の説明図、第
3図は本発明の一実施例を示すデマンド制御装置としゃ
所員荷の説明図、第4図は本発明のデマンド制御方法の
説明図である。
1・・・積算電力量計 2・・・デマンド制御装置3
a〜3n・・・しゃ断器
7a〜7n・・・負荷しゃ断器
(7317) 代理人 弁理士 則 近 憲 佑 (
ほか1名)第1図
T
第2図
TFig. 1 and Fig. 2 are explanatory diagrams of a conventional demand control method, Fig. 3 is an explanatory diagram of a demand control device and a staff load showing an embodiment of the present invention, and Fig. 4 is an explanatory diagram of a demand control method of the present invention. FIG. 1... Integral power meter 2... Demand control device 3
a~3n... Breaker 7a~7n... Load breaker (7317) Agent Patent attorney Noriyuki Chika (
1 other person) Figure 1 T Figure 2 T
Claims (1)
の負荷を開閉するしゃ断器と、前記受電した電力の積算
値を計測する発振装置付きの積算電力計とからなる受配
電装置に於て、前記積算電力計からの出力信号により最
大需要電力量の超過予測量を演算する第1の手段とこの
超過予測量に応じて前記負荷を群れ分けする第2の手段
並びにこの群れ分けされた負荷の停電時間が予め定めら
れた時間内で均等になるように前記しゃ断器を開閉制御
する第3の手段を有する最大需要電力制御装置を備えた
受配電装置。In a power receiving and distributing device consisting of a plurality of loads that distribute and use the received power, a breaker that opens and closes these loads, and an integrating wattmeter with an oscillation device that measures the integrated value of the received power. , a first means for calculating a predicted excess of the maximum demand power amount based on an output signal from the integrating wattmeter, a second means for dividing the loads into groups according to the predicted excess amount, and the loads divided into groups. A power receiving and distributing device comprising a maximum demand power control device having a third means for controlling opening/closing of the breaker so that the power outage time is equalized within a predetermined time.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57103946A JPS58222728A (en) | 1982-06-18 | 1982-06-18 | Power receiving device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57103946A JPS58222728A (en) | 1982-06-18 | 1982-06-18 | Power receiving device |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS58222728A true JPS58222728A (en) | 1983-12-24 |
JPH027260B2 JPH027260B2 (en) | 1990-02-16 |
Family
ID=14367600
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP57103946A Granted JPS58222728A (en) | 1982-06-18 | 1982-06-18 | Power receiving device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS58222728A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014183632A (en) * | 2013-03-18 | 2014-09-29 | Osaki Electric Co Ltd | Energy saving system |
-
1982
- 1982-06-18 JP JP57103946A patent/JPS58222728A/en active Granted
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014183632A (en) * | 2013-03-18 | 2014-09-29 | Osaki Electric Co Ltd | Energy saving system |
Also Published As
Publication number | Publication date |
---|---|
JPH027260B2 (en) | 1990-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4848412B2 (en) | Power system protection device | |
JP5818499B2 (en) | Storage battery operation control device, storage battery operation control method, and program thereof | |
JP3768229B1 (en) | Power control device | |
JPS6035920A (en) | Dispersed demand power control system | |
JP5788591B2 (en) | Power monitoring apparatus and power monitoring system | |
JP6722481B2 (en) | Energy demand control device, energy demand control method, energy demand control system, and program | |
JP2008151443A5 (en) | ||
US20170102677A1 (en) | Power management system, power management method, and controller | |
WO2016190271A1 (en) | Power supply control device, power supply system, power supply control method, and program | |
US7424348B2 (en) | System and method for monitoring serially-connected devices | |
WO2019230783A1 (en) | Equipment management server, equipment management system, and equipment management method | |
JPS58222728A (en) | Power receiving device | |
CN110176884A (en) | A kind of the excitation method and relevant apparatus of excitation system | |
JP2017041941A (en) | Power demand controller and power demand control method | |
JP4778211B2 (en) | Annual power consumption management system | |
JP6707646B2 (en) | System and method for dealing with outages in utility systems | |
JP6690420B2 (en) | Vehicle battery management device and vehicle battery management program | |
US10826477B2 (en) | Programmable time-division multiplexed comparator | |
JPH09200963A (en) | Selective load breaker device | |
JP5686078B2 (en) | Electric power demand controller | |
JP2019154109A (en) | Power storage system | |
JP2019154108A (en) | Power storage system | |
US11099220B2 (en) | Intelligent electronic device control using wirelessly transmitted electrical measurements | |
JP3292981B2 (en) | Maximum demand power reduction calculation device by demand control | |
JP7309336B2 (en) | power generation system |