JP5952600B2 - Connection structure between superstructure and pile - Google Patents

Connection structure between superstructure and pile Download PDF

Info

Publication number
JP5952600B2
JP5952600B2 JP2012055804A JP2012055804A JP5952600B2 JP 5952600 B2 JP5952600 B2 JP 5952600B2 JP 2012055804 A JP2012055804 A JP 2012055804A JP 2012055804 A JP2012055804 A JP 2012055804A JP 5952600 B2 JP5952600 B2 JP 5952600B2
Authority
JP
Japan
Prior art keywords
pile
misalignment
connection structure
fitting
adjusting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012055804A
Other languages
Japanese (ja)
Other versions
JP2013189784A5 (en
JP2013189784A (en
Inventor
耕之 吉田
耕之 吉田
明 大西
明 大西
敏夫 石丸
敏夫 石丸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chiyoda Geotech Co Ltd
Original Assignee
Chiyoda Geotech Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chiyoda Geotech Co Ltd filed Critical Chiyoda Geotech Co Ltd
Priority to JP2012055804A priority Critical patent/JP5952600B2/en
Publication of JP2013189784A publication Critical patent/JP2013189784A/en
Publication of JP2013189784A5 publication Critical patent/JP2013189784A5/ja
Application granted granted Critical
Publication of JP5952600B2 publication Critical patent/JP5952600B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Description

本発明は上部構造物とそれを支持する杭との接続構造に関する。   The present invention relates to a connection structure between a superstructure and a pile that supports the superstructure.

太陽光発電システムに使用される太陽電池モジュール又は太陽電池アレイを設置する場合、例えば設置予定箇所に予めコンクリートを打設してコンクリート土台を構築し、このコンクリート土台に太陽電池モジュール又は太陽電池アレイ用架台(上部構造物)の脚部を固定する基礎構造が一般的に採用されているが、設置予定箇所にコンクリートを打設する基礎工事と、打設したコンクリートの土台に架台(上部構造物)の脚部を固定する工事とが必要で、施工時間かかり、施工コストが高くなる。 When installing a solar cell module or solar cell array to be used in a photovoltaic power generation system, for example, a concrete base is constructed by placing concrete in advance at a planned installation location, and the concrete base is used for the solar cell module or solar cell array. The foundation structure that fixes the legs of the gantry (superstructure) is generally adopted, but the foundation work for placing concrete in the planned installation location and the gantry (superstructure) on the foundation of the cast concrete of the legs is necessary to work and to fix the, it takes a long construction time, construction cost increases.

この解決策の一つとして、コンクリート基礎の代わりに、例えば、鋼管杭を地中に打ち込み、地面から突出した鋼管杭の杭頭に架台(上部構造物)の脚部下端を接続する、基礎施工法が知られている。しかし、鋼管杭の埋設時、鋼管杭が地盤などの影響を受けて、設置予定位置から水平方向にずれを起こすことがあり(芯ずれを起こすことがある)、また地面からの杭頭の高さが設定した高さよりも低く埋設されてしまうことがあるなど、施工誤差が生じることがある。このため、鋼管杭の杭頭に、芯ずれなどの施工誤差を調整して上部構造物を接続する接続構造を配置することが提案されている(特許文献1参照)。   As one of the solutions, instead of concrete foundation, for example, a steel pipe pile is driven into the ground, and the bottom of the leg of the gantry (superstructure) is connected to the pile head of the steel pipe pile protruding from the ground. The law is known. However, when embedding steel pipe piles, the steel pipe piles may be displaced horizontally from the planned installation position due to the influence of the ground, etc. (may cause misalignment), and the pile head height from the ground Construction errors may occur, such as being buried below the set height. For this reason, it has been proposed to arrange a connection structure for connecting an upper structure by adjusting a construction error such as misalignment on the pile head of the steel pipe pile (see Patent Document 1).

特開2011−94474号公報JP 2011-94447 A

上述した接続構造では、軸方向が鋼管杭の杭頭内を横切って配置され鋼管杭に固定された棒部材と、上部構造物と鋼管杭の上端部との間に上部構造物の荷重を鋼管杭に伝達するように配置されて上部構造物の設置傾斜角及び設置高さを調節するくさび形状の調節部材と、棒部材が通る開口部を有して棒部材と連結される第一端部(リング部)と、杭頭から突出して調節部材及び上部構造物をねじ結合によって固定する第二端部とを有し、杭頭内部の可動範囲内で水平方向位置を調節する、棒部材に対してほぼ直交するように配置される固定部材と、を備えて構成される。   In the connection structure described above, the load of the upper structure is placed between the upper structure and the upper end of the steel pipe pile between the rod member fixed in the steel pipe pile with the axial direction arranged across the pile head of the steel pipe pile. A wedge-shaped adjusting member arranged to transmit to the pile and adjusting the installation inclination angle and installation height of the superstructure, and a first end portion having an opening through which the bar member passes and connected to the bar member (Ring part) and a rod member that protrudes from the pile head and has a second end portion that fixes the adjustment member and the upper structure by screw coupling, and adjusts the horizontal position within the movable range inside the pile head. And a fixing member that is arranged so as to be substantially orthogonal thereto.

しかし、上述した接続構造では、施工現場において、鋼管杭の埋設後、鋼管杭の杭頭内で固定部材の第一端部にある開口部に棒部材を通した状態を維持しつつ、棒部材を、杭頭内を横切るようにして杭頭に固定し、次いで、固定部材を棒部材の軸方向において水平方向の芯ずれ量に合わせて移動調整し、次いで、杭頭と上部構造物との間に上部構造物の設置傾斜角及び設置高さに合わせて調整部材を選択して介在させ、この後、これら調整部材及び上部構造物を貫通した固定部材の第二端部に螺合したナットを締め付け、調節部材及び上部構造物を杭頭に固定する、作業が必要となり、非常に手間がかかる。特に、狭い杭頭内部での作業である、固定部材の開口部に棒部材を通した後、棒部材を杭頭に固定し、固定部材を棒部材の軸方向において水平方向の芯ずれ量に合わせて移動調整することは、非常に煩雑である上に時間がかかる。   However, in the connection structure described above, at the construction site, after the steel pipe pile is buried, the rod member is maintained in the state where the rod member is passed through the opening at the first end of the fixed member within the pile head of the steel pipe pile. Is fixed to the pile head so as to cross the inside of the pile head, and then the fixing member is moved and adjusted in accordance with the horizontal misalignment amount in the axial direction of the bar member, and then the pile head and the upper structure are An adjusting member is selected and interposed in accordance with the installation inclination angle and installation height of the upper structure between them, and then the nut screwed into the second end of the fixing member passing through the adjusting member and the upper structure. The work of fixing the adjusting member and the superstructure to the pile head is necessary and is very troublesome. In particular, the work inside the narrow pile head, after passing the rod member through the opening of the fixing member, the rod member is fixed to the pile head, and the fixing member is adjusted to the horizontal misalignment in the axial direction of the rod member. It is very complicated and time-consuming to adjust the movement together.

上部構造物が太陽電池モジュールを複数並列に接続した太陽電池アレイ用架台の場合にあっては、風圧等に耐えられるように打ち込む鋼管杭の本数が多く、鋼管杭と架台(上部構造物)の脚部との接続作業量は膨大で、接続作業の簡素化が要望されている。   When the superstructure is a solar cell array platform in which multiple solar cell modules are connected in parallel, there are many steel pipe piles that are driven to withstand wind pressure, etc., and the number of steel pipe piles and platforms (superstructure) The amount of connection work with the legs is enormous, and simplification of the connection work is desired.

本発明は上部構造物と杭との接続作業が容易で、施工時間の短縮及び施工コストの低廉化を図ることが可能な、上部構造物と杭との接続構造を提供することを目的とする。   It is an object of the present invention to provide a connection structure between an upper structure and a pile, in which the connection work between the upper structure and the pile is easy, and the construction time can be reduced and the construction cost can be reduced. .

本発明の請求項1に記載の接続構造は、上部構造物とそれを支持する杭との接続構造であって、前記杭に接続され、前記杭の中心軸に沿って延びてその頭部が前記杭の杭頭から突出する接続軸と、前記接続軸が挿入される芯ずれ調整用ルーズ穴を設けた水平片部と前記上部構造物の脚部に取り付けられる垂直片部とを有し、前記杭頭上で前記接続軸に対して移動可能な調整金具と、前記芯ずれ調整用ルーズ穴を覆うようにして前記調整金具上に配置され、前記接続軸が挿入される芯ずれ調整用長穴を設け、前記杭頭上で前記接続軸に対して移動可能な押さえ部材と、を備え、前記杭頭内に、杭回転埋設装置から前記杭に回転力を伝達するトルク伝達金具が配置され、前記接続軸は、前記芯ずれ調整用長穴と前記芯ずれ調整用ルーズ穴とを介してその下端部分が前記トルク伝達金具に接続され、前記調整金具は、前記接続軸の前記頭部と前記押さえ部材とで前記杭頭に固定されることを特徴とする。 The connection structure according to claim 1 of the present invention is a connection structure between an upper structure and a pile that supports the upper structure, and is connected to the pile and extends along a central axis of the pile, and a head thereof is A connection shaft protruding from the pile head of the pile, a horizontal piece portion provided with a loose hole for misalignment adjustment into which the connection shaft is inserted, and a vertical piece portion attached to a leg portion of the upper structure, An adjustment fitting that is movable with respect to the connection shaft on the pile head, and a long hole for misalignment adjustment that is disposed on the adjustment fitting so as to cover the loose hole for misalignment adjustment and into which the connection shaft is inserted. A pressing member that is movable with respect to the connection shaft on the pile head, and a torque transmission fitting that transmits a rotational force from the pile rotary embedding device to the pile is disposed in the pile head, The connecting shaft is inserted through the elongated hole for misalignment adjustment and the loose hole for misalignment adjustment. Its lower end portion is connected to said torque transmission fitting, the adjustment fitting, characterized in that it is fixed to the pile head with said pressing member and said head of said connecting shaft.

本発明の接続構造によれば、上部構造物の軸芯(脚部の軸芯)と杭の軸芯との間に芯ずれが存在していても杭頭上で押さえ部材及び調整金具(水平片部)を回転・移動調整するだけで何ら支障なく杭の杭頭と上部構造物(脚部)とを接続することができる上に、上部構造物と杭との接続作業が容易で、さらにトルク伝達金具を利用して接続軸を杭に接続して、接続軸で押さえ部材、調整金具を杭頭に固定するようにしてあるので、接続構造の簡略化を図ることが可能となり、施工時間の短縮及び施工コストの低廉化を図ることが可能である。 According to the connection structure of the present invention, even if there is a misalignment between the axis of the superstructure (the axis of the leg) and the axis of the pile, the holding member and the adjusting bracket (horizontal piece) on the pile head The pile head and the upper structure (legs) can be connected without any trouble just by adjusting the rotation and movement, and the connection work between the upper structure and the pile is easy and torque Since the connection shaft is connected to the pile using the transmission bracket, and the holding member and adjustment bracket are fixed to the pile head with the connection shaft, the connection structure can be simplified and the construction time can be reduced . It is possible to shorten the construction cost and reduce the construction cost.

本発明の接続構造の一実施例を示す要部の一部切り欠いた側面図である。It is the side view where a part of principal part showing one example of the connection structure of the present invention was notched. 図1の接続構造を正面側から見た要部の一部切り欠いた正面図である。FIG. 2 is a partially cutaway front view of the main part of the connection structure of FIG. 1 viewed from the front side. 図1に示すL字状調整金具の斜視図である。It is a perspective view of the L-shaped adjustment metal fitting shown in FIG. 図4(a)は図1に示すL字状調整金具の平面図、図4(b)は図1に示すL字状調整金具の変形例の平面図である。4A is a plan view of the L-shaped adjustment fitting shown in FIG. 1, and FIG. 4B is a plan view of a modification of the L-shaped adjustment fitting shown in FIG. 図5(a)は図1に示す中間金具の平面図、図5(b)は同断面図である。5A is a plan view of the intermediate metal fitting shown in FIG. 1, and FIG. 5B is a cross-sectional view thereof. 図6(a)は図1に示す押さえ部材の平面図、図6(b)は同断面図である。6A is a plan view of the pressing member shown in FIG. 1, and FIG. 6B is a sectional view thereof. 図7(a)は図1に示すトルク伝達金具の斜視図、図7(b)は同トルク伝達金具の変形例を示す斜視図である。7A is a perspective view of the torque transmission fitting shown in FIG. 1, and FIG. 7B is a perspective view showing a modification of the torque transmission fitting. 図1の接続軸を図7(b)に示すトルク伝達金具に固定した、図1の接続構造の変形例を示す要部の一部切り欠いた側面図である。FIG. 8 is a partially cutaway side view showing a modification of the connection structure of FIG. 1 in which the connection shaft of FIG. 1 is fixed to the torque transmission fitting shown in FIG. 図9(a)は図1に示す鋼管杭の平面図、図9(b)は一部省略、一部切り欠いた側面図である。Fig.9 (a) is a top view of the steel pipe pile shown in FIG. 1, FIG.9 (b) is a partially omitted side view. オーガー接続フランジとトルク伝達金具との関係を示す図で、図10(a)は平面図、図10(b)は図10(a)のA−A’線断面図、図10(c)は図10(a)のB−B’線断面図である。FIG. 10A is a plan view, FIG. 10B is a cross-sectional view taken along line AA ′ of FIG. 10A, and FIG. 10C is a diagram illustrating the relationship between the auger connection flange and the torque transmission fitting. It is BB 'sectional view taken on the line of Fig.10 (a). オーガー接続フランジとトルク伝達金具との関係を示す図10とは別の図で、図11(a)は平面図、図11(b)は図11(a)のA−A’線断面図、図11(c)は図11(a)のB−B’線断面図である。FIG. 11A is a plan view different from FIG. 10 showing the relationship between the auger connection flange and the torque transmission fitting, FIG. 11B is a cross-sectional view taken along the line AA ′ in FIG. FIG.11 (c) is the BB 'sectional view taken on the line of Fig.11 (a). 図1の接続構造での芯ずれ調整操作を示す図で、図12(a)は一方向(図面の右方向)に芯ずれした場合の調整操作の説明平面図、図12(b)は他方向(図面の左方向)に芯ずれした場合の調整操作の説明平面図である。FIGS. 12A and 12B are diagrams illustrating the misalignment adjustment operation in the connection structure of FIG. 1. FIG. 12A is a plan view illustrating the adjustment operation when misalignment occurs in one direction (right direction in the drawing), and FIG. It is an explanatory top view of adjustment operation at the time of misalignment in a direction (left direction of a drawing). 図1の接続構造での芯ずれ調整操作を示す図で、図13(a)は斜め方向に芯ずれした場合の調整操作の説明平面図、図13(b)は高さ調整操作を示す一部切り欠いた説明側面図である。FIGS. 13A and 13B are diagrams illustrating the misalignment adjustment operation in the connection structure of FIG. 1, FIG. 13A is an explanatory plan view of the adjustment operation when the misalignment is performed in an oblique direction, and FIG. FIG. 図1の接続構造において、鋼管杭が経年変化などにより沈下した場合に対処するための実施例を示し、図14(a)は要部の一部切り欠いた側面図、図14(b)は図14(a)に使用される高さ調整用シムの平面図である。In the connection structure of FIG. 1, an example for dealing with a case where a steel pipe pile sinks due to secular change, etc. is shown, FIG. 14 (a) is a side view with a part cut away, and FIG. 14 (b) It is a top view of the shim for height adjustment used for Fig.14 (a). 図1の接続構造を使用して上部構造物としての太陽電池モジュール又は太陽電池アレイ用架台を鋼管杭に接続して支持した状態の説明側面図である。It is explanatory side view of the state which connected and supported the solar cell module as an upper structure or the mount for solar cell arrays to the steel pipe pile using the connection structure of FIG.

本発明の接続構造の実施例(図1、図2、図8、図14(a)参照)では、上部構造物としての太陽電池モジュール又太陽電池アレイS(図15参照)を支持する架台10(図15参照)が設置される敷地の設置予定箇所にそれぞれ埋設される杭として、例えば、図9(a)、(b)に示す翼付き鋼管杭20が使用される。この翼付き鋼管杭20は、鋼管製の杭本体21の下端側外周面にほぼ一巻きの螺旋翼22が設けられ、また杭本体21の下端底部の径方向両端に先端掘削刃23がそれぞれ設けられる。なお、杭としては、図9(a)、(b)に示す翼付き鋼管杭20に限定されるものではない。   In the embodiment of the connection structure of the present invention (see FIGS. 1, 2, 8, and 14A), a gantry 10 that supports a solar cell module or a solar cell array S (see FIG. 15) as an upper structure. For example, a winged steel pipe pile 20 shown in FIGS. 9 (a) and 9 (b) is used as a pile embedded in each of the planned installation locations of the site where (see FIG. 15) is installed. This winged steel pipe pile 20 is provided with a substantially one-turn spiral blade 22 on the outer peripheral surface on the lower end side of a pile main body 21 made of steel pipe, and tip excavating blades 23 are provided on both ends in the radial direction of the bottom bottom of the pile main body 21. It is done. In addition, as a pile, it is not limited to the winged steel pipe pile 20 shown to Fig.9 (a), (b).

翼付き鋼管杭(以下鋼管杭と記す)20の杭頭21a内部には埋設施工をする前に杭頭21aの径方向に延びる平面視I字状のトルク伝達金具24(図7(a)参照)を溶接などで固定しておく。そして、杭本体21を地面に起立させた状態で、杭回転埋設装置(オーガー 図示せず)のオーガー接続フランジFに設けた末端が二つに分かれる回転キャップFa(図10(a)参照)又は末端が四つに分かれる回転キャップFb(図11(a)参照)でトルク伝達金具24を挟み込んで、杭回転埋設装置から鋼管杭20に回転力が伝わるようにして、杭回転埋設装置によって杭本体21を回転させ、螺旋翼22を地盤中に食い込ませることにより、螺旋翼22の回転推進で杭本体21が地中に押し込まれる。地中に埋設された鋼管杭20は、荷重や引き抜き力が作用しても螺旋翼22などによって地中に沈下し、地中から引き抜かれることはない。しかし、地中に埋設する過程で地盤などの影響によって杭本体21が螺旋翼22の傾斜方向に回転移動して水平方向に変位すること(芯ずれを起こすこと)がある。すなわち、本来の埋設予定地点から水平方向に変位して埋設されることがある。また、地面からの杭頭の高さが予定していた高さからずれることがある。すなわち、施工誤差が生じることがある。   A torque transmission fitting 24 having an I-shape in a plan view extending in the radial direction of the pile head 21a before being embedded in a pile head 21a of a winged steel pipe pile (hereinafter referred to as a steel pipe pile) 20 (see FIG. 7A). ) Is fixed by welding. And in the state which raised the pile main body 21 on the ground, the rotation cap Fa (refer FIG. 10 (a)) from which the terminal provided in the auger connection flange F of a pile rotation embedding apparatus (auger not shown) is divided into two or The torque transmission bracket 24 is sandwiched by a rotating cap Fb (see FIG. 11 (a)) whose ends are divided into four so that the rotational force is transmitted from the pile rotating embedding device to the steel pipe pile 20, and the pile main body by the pile rotating embedding device. The pile main body 21 is pushed into the ground by the rotational propulsion of the spiral wing 22 by rotating 21 and causing the spiral wing 22 to bite into the ground. The steel pipe pile 20 buried in the ground sinks into the ground by the spiral wing 22 or the like even if a load or a pulling force is applied, and is not pulled out from the ground. However, the pile main body 21 may be rotated in the inclined direction of the spiral blade 22 and displaced in the horizontal direction (causing misalignment) due to the influence of the ground or the like in the process of being buried in the ground. In other words, there is a case where the burial is displaced in the horizontal direction from the original planned burial point. Moreover, the height of the pile head from the ground may deviate from the planned height. That is, construction errors may occur.

芯ずれを起こす方向は一定せず様々であり、芯ずれ量も様々であり、このため鋼管杭20に架台10(図15参照)の脚11を直接接続することが困難である。 The direction in which the misalignment occurs is not constant and varies, and the misalignment amount is also various. For this reason, it is difficult to directly connect the leg portion 11 of the gantry 10 (see FIG. 15) to the steel pipe pile 20.

本発明の接続構造は、多様な芯ずれなどが存在していても何ら支障なく杭頭21aに架台10(上部構造物)の脚11を接続するものであって、面倒な調整操作をせずに接続できるようにしたものである。 Connecting structure of the present invention, which as diverse as misalignment connects the legs 11 of the gantry 10 in without any problem pile head 21a also be present (superstructure) causes a troublesome adjustment operation It can be connected without connecting.

以下、本発明の接続構造の実施例について詳述する。   Hereinafter, examples of the connection structure of the present invention will be described in detail.

図1乃至図11は本発明の接続構造の一実施例を示す。   1 to 11 show an embodiment of the connection structure of the present invention.

本実施例の接続構造Mは、図1、図2に示すように、鋼管杭20(杭本体21)の上端部にある円筒状の杭頭21a内に予め溶接など固定したトルク伝達金具24を利用する。このトルク伝達金具24の上面中央部には、図7(a)に示すように六角ナット25が固定される。なお、この六角ナット25の代わりに図7(b)に示すようにネジ穴25aを設けたトルク伝達金具24aを利用するようにしてもよい。 As shown in FIGS. 1 and 2, the connection structure M of the present embodiment includes a torque transmission fitting 24 that is fixed in advance in a cylindrical pile head 21 a at the upper end of the steel pipe pile 20 (pile main body 21) by welding or the like. Is used. A hexagonal nut 25 is fixed to the center of the upper surface of the torque transmission fitting 24 as shown in FIG. Instead of the hexagon nut 25, a torque transmission fitting 24a provided with a screw hole 25a as shown in FIG. 7B may be used.

接続構造Mは、下端部分を六角ナット25に螺合することにより鋼管杭20(杭本体21)の中心軸に沿って延びて、上端部分(頭部30a)が杭頭21aから突出する、六角ボルトからなる接続軸30と、この接続軸30が挿入される芯ずれ調整用ルーズ穴31を設けた水平片部32と架台10の脚部11に取り付けられる垂直片部34とを有する、断面がL字状の調整金具(以下L字状調整金具と記す)35と、杭頭21aと水平片部32との間に配置され、中央部に接続軸30が貫通する貫通穴36を設けた中間金具37と、芯ずれ調整用ルーズ穴31を覆うようにしてL字状調整金具35上に配置され、接続軸30が挿入される芯ずれ調整用長穴41を設けた押さえ部材40と、を備えて構成される。L字状調整金具35の、架台10の脚部11に取り付けられる、垂直片部34には、脚部11の取り付け位置の調整が行える取り付け調整長穴33(図3参照)が設けられる。 The connection structure M extends along the central axis of the steel pipe pile 20 (pile main body 21) by screwing the lower end portion into the hexagon nut 25, and the upper end portion (head 30a) protrudes from the pile head 21a. The cross section has a connecting shaft 30 made of a bolt, a horizontal piece portion 32 provided with a loose hole 31 for adjusting misalignment into which the connecting shaft 30 is inserted, and a vertical piece portion 34 attached to the leg portion 11 of the gantry 10. An intermediate having an L-shaped adjustment fitting (hereinafter referred to as an L-shaped adjustment fitting) 35 and a through-hole 36 which is disposed between the pile head 21a and the horizontal piece 32 and through which the connecting shaft 30 passes. A metal fitting 37 and a holding member 40 provided on the L-shaped adjustment metal fitting 35 so as to cover the loose adjustment hole 31 for adjusting the misalignment and provided with a misalignment adjusting long hole 41 into which the connecting shaft 30 is inserted. It is prepared for. The vertical piece 34 that is attached to the leg 11 of the gantry 10 of the L-shaped adjustment fitting 35 is provided with an attachment adjustment long hole 33 (see FIG. 3) that can adjust the attachment position of the leg 11.

接続軸30は、埋設された鋼管杭20の杭頭21a上に中間金具37を載せ、この中間金具37上にL字状調整金具35を重ね、さらにL字状調整金具35上に押さえ部材40を重ねてから、その下端部分をワッシャ38、芯ずれ調整用長穴41、芯ずれ調整用ルーズ孔31、貫通穴36を介して杭頭21a内部に挿入し、六角ナット25に螺合して仮締めされる。押さえ部材40を載せた状態でL字状調整金具35を鋼管杭20の芯ずれに合わせて中間金具37上で回転やスライドをして移動調整をした後に、接続軸30を、六角ナット25に締め付けることにより、接続軸30の上端部分である頭部30aがワッシャ38及び押さえ部材40を介してL字状調整金具35と中間金具37を鋼管杭20の杭頭21aに固定する。   The connection shaft 30 has an intermediate fitting 37 mounted on the pile head 21 a of the buried steel pipe pile 20, an L-shaped adjustment fitting 35 is stacked on the intermediate fitting 37, and a pressing member 40 is further placed on the L-shaped adjustment fitting 35. After that, the lower end portion is inserted into the pile head 21a through the washer 38, the misalignment adjusting long hole 41, the misalignment adjusting loose hole 31, and the through hole 36, and screwed into the hexagon nut 25. It is temporarily tightened. After adjusting the movement of the L-shaped adjustment fitting 35 by rotating or sliding on the intermediate fitting 37 in accordance with the misalignment of the steel pipe pile 20 with the holding member 40 placed, the connection shaft 30 is connected to the hexagon nut 25. By tightening, the head 30 a which is the upper end portion of the connection shaft 30 fixes the L-shaped adjustment fitting 35 and the intermediate fitting 37 to the pile head 21 a of the steel pipe pile 20 via the washer 38 and the pressing member 40.

前記L字状調整金具35の水平片部32に設けた芯ずれ調整用ルーズ孔31は、図3及び図4(a)に示すように、杭頭21aの内径よりも若干小さい内径を有する円形穴である。なお、図4(b)に示すように一辺長さが杭頭21aの内径よりも若干短い正方形状の方形穴31aであってもよい。前記L字状調整金具35の垂直片部34に設けた取り付け調整長穴33は、図3に示すように、垂直片部34の短辺方向に沿って設けられたものと、垂直片部34の長辺方向に沿って設けられたものとがある。芯ずれ調整用ルーズ孔31と取り付け調整長穴33は、鋼管杭20がその埋設予定位置から前後左右方向あるいは上下方向に芯ずれを起こして埋設されても、それに対処できるように設定されたものである。 As shown in FIGS. 3 and 4 (a), the misalignment adjusting loose hole 31 provided in the horizontal piece 32 of the L-shaped adjustment fitting 35 is a circular shape having an inner diameter slightly smaller than the inner diameter of the pile head 21a. It is a hole. The length of one side as shown in FIG. 4 (b) may be slightly shorter square rectangular hole 31a than the inner diameter of the pile cap 21a. As shown in FIG. 3, the attachment adjustment long hole 33 provided in the vertical piece portion 34 of the L-shaped adjustment metal fitting 35 is provided along the short side direction of the vertical piece portion 34, and the vertical piece portion 34. Some of them are provided along the long side direction. The misalignment adjusting loose hole 31 and the attachment adjusting long hole 33 are set so that the steel pipe pile 20 can cope with the embedding caused by the misalignment in the front / rear / left / right direction or the up / down direction from the planned embedding position. It is.

前記水平片部32と垂直片部34の間には、図3に示すように、それらの長辺方向両端において略三角形状の支板39がそれぞれ設けられている。垂直片部34にはソーラーパネルSや架台10(図15参照)の荷重の外にソーラーパネルSや架台10が受けた風圧などが作用することから、垂直片部34が水平片部32に対してぐらつかないように前記L字状調整金具35を補強している。   Between the horizontal piece part 32 and the vertical piece part 34, as shown in FIG. 3, substantially triangular support plates 39 are respectively provided at both ends in the long side direction. Since the wind pressure received by the solar panel S and the gantry 10 acts on the vertical piece 34 in addition to the load of the solar panel S and the gantry 10 (see FIG. 15), the vertical piece 34 is in relation to the horizontal piece 32. The L-shaped adjustment fitting 35 is reinforced so as not to wobble.

前記中間金具37は、図5(a)に示すように円盤状に形成され、鋼管杭20の外径よりも大きく且つ前記水平片部32の短辺方向の寸法よりも若干小さい直径を有し(図1、図2参照)、前記L字状調整金具35(前記水平片部32)を補強するものである。   The intermediate fitting 37 is formed in a disk shape as shown in FIG. 5A, and has a diameter that is larger than the outer diameter of the steel pipe pile 20 and slightly smaller than the dimension of the horizontal piece portion 32 in the short side direction. (Refer FIG. 1, FIG. 2) and the said L-shaped adjustment metal fitting 35 (the said horizontal piece part 32) are reinforced.

前記押さえ部材40は、前記芯ずれ調整用ルーズ穴31を覆い、前記接続軸30の頭部30aにより前記L字状調整金具35(前記水平片部32)を杭頭21a側に押さえて固定するもので、図6(a)に示すように、杭頭21aの直径とほぼ等しい長さの短辺とそれより長い長辺とを有する方形板状である。前記芯ずれ調整用長穴41は前記押さえ部材40の中央部でその短辺方向に延びるように設けられる。前記芯ずれ調整用長穴41の幅は前記接続軸30の直径よりも若干大きい寸法に設定され、また長さは前記芯ずれ調整用ルーズ穴31の直径又は一辺の長さと同じ寸法に設定される。すなわち、前記芯ずれ調整用長穴41の幅と長さは、芯ずれを調整する際、接続軸30に対して前記押さえ部材40が前記L字状調整金具35(前記水平片部32)と共に前記中間金具37上でスムーズに回転やスライドが出来るように設定されている。   The pressing member 40 covers the misalignment adjusting loose hole 31 and fixes the L-shaped adjusting fitting 35 (the horizontal piece portion 32) to the pile head 21a side by the head portion 30a of the connecting shaft 30. As shown in FIG. 6 (a), it has a rectangular plate shape having a short side having a length substantially equal to the diameter of the pile head 21a and a long side longer than the short side. The misalignment adjusting long hole 41 is provided at the center of the pressing member 40 so as to extend in the short side direction. The width of the misalignment adjusting long hole 41 is set to a dimension slightly larger than the diameter of the connection shaft 30, and the length is set to the same dimension as the diameter or one side length of the misalignment adjusting loose hole 31. The That is, the width and length of the misalignment adjusting long hole 41 are adjusted so that the pressing member 40 is connected to the connecting shaft 30 together with the L-shaped adjusting bracket 35 (the horizontal piece portion 32) when adjusting the misalignment. It is set so that it can be smoothly rotated and slid on the intermediate fitting 37.

図8は本実施例の接続構造Mの変形例を示している。図8中、図1、図2に示す部分と同一部分には同一符号を付してその説明を省略する。   FIG. 8 shows a modification of the connection structure M of the present embodiment. 8, parts that are the same as the parts shown in FIGS. 1 and 2 are given the same reference numerals, and descriptions thereof are omitted.

本変形例では、鋼管杭20の杭頭21a内部に図7(b)に示すトルク伝達金具24aを固定し、このトルク伝達金具24aの上面中央部に設けたネジ穴25aに接続軸30の下端部分を螺合することにより、接続軸30を鋼管杭20(杭本体21)の中心軸に沿って起立させて、上端部分(頭部)を杭頭21aから突出させている。それ以外は、図1、図2に示す接続構造と同じである。   In this modification, the torque transmission fitting 24a shown in FIG. 7B is fixed inside the pile head 21a of the steel pipe pile 20, and the lower end of the connecting shaft 30 is inserted into the screw hole 25a provided at the center of the upper surface of the torque transmission fitting 24a. By screwing the portions, the connection shaft 30 is erected along the central axis of the steel pipe pile 20 (pile main body 21), and the upper end portion (head) is protruded from the pile head 21a. Other than that, it is the same as the connection structure shown in FIGS.

次に上述した本実施例の接続構造Mの施工手順について説明する。   Next, the construction procedure of the connection structure M of the above-described embodiment will be described.

鋼管杭20を埋設予定位置に埋設した後、杭頭21a上に鋼管杭20の中心軸位置に貫通穴36が位置するようにして中間金具37を載せる。次いで、この中間金具37上にL字状調整金具35の水平片部32を載せて貫通穴36上に芯ずれ調整用ルーズ孔31を位置させ、さらに芯ずれ調整用ルーズ孔31を覆うようにして水平片部32上に押さえ部材40を載せて貫通穴36及び芯ずれ調整用ルーズ孔31上に芯ずれ調整用長穴41を位置させる。   After embedding the steel pipe pile 20 at the planned embedding position, the intermediate fitting 37 is placed on the pile head 21 a so that the through hole 36 is located at the center axis position of the steel pipe pile 20. Next, the horizontal piece 32 of the L-shaped adjustment fitting 35 is placed on the intermediate fitting 37 so that the misalignment adjusting loose hole 31 is positioned on the through hole 36, and further, the misalignment adjusting loose hole 31 is covered. Then, the pressing member 40 is placed on the horizontal piece 32 and the misalignment adjusting elongated hole 41 is positioned on the through hole 36 and the misalignment adjusting loose hole 31.

次いで、接続軸30を、押さえ部材40上からワッシャ38、芯ずれ調整用長穴41、芯ずれ調整用ルーズ孔31及び貫通穴36に通して鋼管杭20の杭頭21a内部に差し込み、接続軸30の下端部分をトルク伝達金具24に設けた六角ナット25に螺合して仮締めし、接続軸30を鋼管杭20の中心軸に沿って起立させて接続軸30の頭部30aを杭頭21aから突出させる。   Next, the connecting shaft 30 is inserted into the pile head 21 a of the steel pipe pile 20 through the washer 38, the misalignment adjusting long hole 41, the misalignment adjusting loose hole 31, and the through hole 36 from above the pressing member 40. The lower end portion of 30 is screwed into a hexagon nut 25 provided on the torque transmission fitting 24 and temporarily tightened, the connection shaft 30 is raised along the central axis of the steel pipe pile 20, and the head portion 30 a of the connection shaft 30 is piled up. It protrudes from 21a.

この後、接続軸30を締め付けるが、鋼管杭20が芯ずれを起こして埋設された場合には、接続軸30を締め付ける前に、接続軸30を芯ずれ調整用長穴41、芯ずれ調整用ルーズ孔31、貫通穴36に挿入した状態で、芯ずれ量、芯ずれ方向に合わせて押さえ部材40を載せた状態でL字状調整金具35の水平片部32を中間金具37上で回転させ、移動(スライド)させて、L字状調整金具35の垂直片部34を架台10の脚部11に押し当てる。   After this, the connecting shaft 30 is tightened. When the steel pipe pile 20 is buried with misalignment, before the connecting shaft 30 is tightened, the connecting shaft 30 is adjusted with a misalignment adjusting long hole 41, for misalignment adjustment. The horizontal piece 32 of the L-shaped adjustment fitting 35 is rotated on the intermediate fitting 37 with the pressing member 40 placed in accordance with the amount of misalignment and the direction of misalignment while being inserted into the loose hole 31 and the through hole 36. The vertical piece 34 of the L-shaped adjustment fitting 35 is pressed against the leg 11 of the gantry 10 by moving (sliding).

例えば、図12(a)に示すように、鋼管杭20が一方向(図面の右方向)に芯ずれを起こして埋設された場合、押さえ部材40を載せた状態でL字状調整金具35の水平片部32を中間金具37上で他方向(図面の左方向)に芯ずれ量に相当する距離、移動調整してL字状調整金具35の垂直片部34を架台10の脚部11に押し当てる。   For example, as shown in FIG. 12 (a), when the steel pipe pile 20 is embedded with a misalignment in one direction (right direction in the drawing), the L-shaped adjustment fitting 35 is placed with the pressing member 40 mounted thereon. The horizontal piece 32 is moved and adjusted on the intermediate fitting 37 in the other direction (left direction in the drawing) by a distance corresponding to the amount of misalignment, so that the vertical piece 34 of the L-shaped adjustment fitting 35 becomes the leg 11 of the gantry 10. Press.

また、図12(b)に示すように、鋼管杭20が他方向(図面の左方向)に芯ずれを起こして埋設された場合、押さえ部材40を載せた状態でL字状調整金具35の水平片部32を中間金具37上で一方向(図面の右方向)に芯ずれ量に相当する距離、移動調整してL字状調整金具35の垂直片部34を架台10の脚部11に押し当てる。   Also, as shown in FIG. 12B, when the steel pipe pile 20 is embedded with the misalignment in the other direction (the left direction in the drawing), the L-shaped adjustment fitting 35 is mounted with the pressing member 40 mounted thereon. The horizontal piece 32 is moved and adjusted on the intermediate fitting 37 in one direction (rightward in the drawing) by a distance corresponding to the amount of misalignment, so that the vertical piece 34 of the L-shaped adjustment fitting 35 becomes the leg 11 of the gantry 10. Press.

また、図13(a)に示すように、鋼管杭20が斜め方向に芯ずれを起こして埋設された場合、押さえ部材40を載せた状態でL字状調整金具35の水平片部32を中間金具37上で接続軸30を支点として矢印A方向に回転させ且つ矢印B方向に芯ずれ量に相当する距離、移動調整してL字状調整金具35の垂直片部34を架台10の脚部11に押し当てる。   Further, as shown in FIG. 13A, when the steel pipe pile 20 is embedded with an eccentricity in the oblique direction, the horizontal piece 32 of the L-shaped adjustment fitting 35 is placed in the middle with the pressing member 40 placed thereon. The metal plate 37 is rotated in the direction of the arrow A with the connecting shaft 30 as a fulcrum, and is moved and adjusted in the direction of the arrow B by a distance corresponding to the misalignment amount. 11 against.

このようにして鋼管杭20の水平方向における芯ずれに合わせ、押さえ部材40を載せた状態でL字状調整金具35の水平片部32を中間金具37上で回転させ、移動(スライド)させてL字状調整金具35の垂直片部34を架台10の脚部11に押し当てた後に、接続軸30を締め付けると、接続軸30の頭部30aがワッシャ38及び押さえ部材40を介してL字状調整金具35と中間金具37を鋼管杭20の杭頭21aに固定する。   In this way, the horizontal piece 32 of the L-shaped adjustment fitting 35 is rotated on the intermediate fitting 37 and moved (slided) in a state where the pressing member 40 is placed in accordance with the misalignment of the steel pipe pile 20 in the horizontal direction. When the connecting shaft 30 is tightened after the vertical piece 34 of the L-shaped adjustment fitting 35 is pressed against the leg 11 of the gantry 10, the head 30 a of the connecting shaft 30 is L-shaped via the washer 38 and the pressing member 40. The shape adjustment fitting 35 and the intermediate fitting 37 are fixed to the pile head 21a of the steel pipe pile 20.

しかる後、架台10の脚部11を、L字状調整金具35の垂直片部34に設けた取り付け調整長穴33の部分に、ボルト・ナットからなる締結部材50によって固定する。この際、図13(b)に示すように、鋼管杭20の杭頭の高さ(地面からの高さ)が予め設定した高さからずれて埋設された場合でも締結部材50により脚部11を垂直片部34の取り付け調整長穴33の部分に固定することができる。   Thereafter, the leg portion 11 of the gantry 10 is fixed to the portion of the attachment adjustment long hole 33 provided in the vertical piece portion 34 of the L-shaped adjustment fitting 35 by a fastening member 50 made of a bolt and a nut. At this time, as shown in FIG. 13 (b), even when the pile head height (height from the ground) of the steel pipe pile 20 is deviated from a preset height, it is embedded by the fastening member 50. Can be fixed to the portion of the attachment adjustment elongated hole 33 of the vertical piece 34.

これにより、鋼管杭20が芯ずれなどを起こして埋設された場合であっても架台10の脚部11を何ら支障なく鋼管杭20の杭頭21aに接続することが出来る。一旦地中に埋設された鋼管杭20は、螺旋翼22(図9参照)などによって荷重や引き抜き力が作用しても地中に沈下し、地中から引き抜かれることはない。そのため、太陽電池モジュール又太陽電池アレイS(図15参照)に風圧などが作用しても架台10(脚部11)が地面から浮き上がるおそれがなく、また太陽電池モジュール又太陽電池アレイSや架台10などの自重で脚11が地面に沈下するおそれがない。 Thereby, even if it is a case where the steel pipe pile 20 raise | generates misalignment etc. and is embed | buried, the leg part 11 of the mount frame 10 can be connected to the pile head 21a of the steel pipe pile 20 without any trouble. The steel pipe pile 20 once buried in the ground sinks into the ground and is not pulled out from the ground even if a load or a pulling force is applied by a spiral blade 22 (see FIG. 9) or the like. Therefore, even if wind pressure or the like acts on the solar cell module or solar cell array S (see FIG. 15), there is no possibility that the gantry 10 (leg 11) will be lifted from the ground, and the solar cell module or solar cell array S or gantry 10 leg 11 by its own weight, such as there is no risk of subsidence in the ground.

本実施例の接続構造Mによれば、埋設された鋼管杭20の芯ずれ量や芯ずれ方向に合わせて押さえ部材40を載せた状態でL字状調整金具35を中間金具37上で回転させ、スライドさせて移動調整するが、芯ずれ調整用ルーズ穴31は杭頭21aの内径よりも若干小さい内径を有し、芯ずれ調整用長穴41も杭頭21aの内径よりも若干短い長さを有しているので、様々な芯ずれ量や芯ずれ方向の芯ずれに対応することが可能である。また、この芯ずれ調整操作は、L字状調整金具35の水平片部32上に芯ずれ調整用ルーズ穴31を覆うように押さえ部材40を載せ、接続軸30を芯ずれ調整用長穴41、芯ずれ調整用ルーズ孔31、貫通穴36に挿入した状態、すなわち接続軸30で仮止めした状態で行うことから、押さえ部材40とL字状調整金具35が中間金具37上から外れるなどのおそれはなく、スムーズに行うことが出来る。また、鋼管杭20を埋設する際に使用するトルク伝達金具24、24aを利用して接続軸30を鋼管杭20に接続し、これにより接続軸30で押さえ部材40、L字状調整金具35、中間金具37を杭頭21aに固定するようにしてあるので、接続構造Mの簡略化を図ることが可能となる。   According to the connection structure M of the present embodiment, the L-shaped adjustment fitting 35 is rotated on the intermediate fitting 37 in a state where the pressing member 40 is placed according to the misalignment amount and misalignment direction of the buried steel pipe pile 20. Although the sliding adjustment is carried out by sliding, the loose hole 31 for misalignment adjustment has an inner diameter slightly smaller than the inner diameter of the pile head 21a, and the elongated hole 41 for misalignment adjustment is also slightly shorter than the inner diameter of the pile head 21a. Therefore, it is possible to cope with various misalignment amounts and misalignment in the misalignment direction. Further, in this misalignment adjustment operation, the pressing member 40 is placed on the horizontal piece portion 32 of the L-shaped adjustment fitting 35 so as to cover the misalignment adjusting loose hole 31, and the connecting shaft 30 is connected to the misalignment adjusting long hole 41. The pressing member 40 and the L-shaped adjustment fitting 35 are detached from the intermediate fitting 37 because the center displacement adjustment loose hole 31 and the through hole 36 are inserted, that is, temporarily fixed by the connecting shaft 30. There is no fear and it can be done smoothly. Further, the connecting shaft 30 is connected to the steel pipe pile 20 by using the torque transmission fittings 24, 24a used when the steel pipe pile 20 is buried, whereby the holding shaft 40, the L-shaped adjusting fitting 35, Since the intermediate fitting 37 is fixed to the pile head 21a, the connection structure M can be simplified.

また、本実施例の接続構造Mによれば、従来技術の如く、芯ずれを調整するために狭い杭頭空間内での部材の移動調整作業が不要であり、この結果、架台10と鋼管杭20の杭頭との接続作業(施工)時間の短縮を図り、施工コストを低減することが可能となる。特に、太陽電池モジュールを複数並列に接続した太陽電池アレイSの架台10の場合にあっては、風圧等に耐えられるように打ち込む鋼管杭20の本数が多く、鋼管杭20と架台10の脚部11との接続作業量は膨大で、施工時間が長時間化し、施工コストが高くなる問題が生じるが、これを解消することが可能となる。   Further, according to the connection structure M of the present embodiment, as in the prior art, it is not necessary to adjust the movement of the member in the narrow pile head space in order to adjust the misalignment. As a result, the gantry 10 and the steel pipe pile The connection work (construction) time with 20 pile heads can be shortened, and the construction cost can be reduced. In particular, in the case of the platform 10 of the solar cell array S in which a plurality of solar cell modules are connected in parallel, the number of steel pipe piles 20 to be driven so as to withstand wind pressure and the like is large. The amount of connection work with 11 is enormous, and there is a problem that the construction time becomes long and the construction cost becomes high, but this can be solved.

図14(a)、(b)は図1に示す接続構造Mにおいて、鋼管杭20が経年変化などにより沈下した場合に対処するための実施例を示している。図14(a)中、図1、図2に示す部分と同一構成部分には同一符号を付してその説明を省略する。   14 (a) and 14 (b) show an embodiment for dealing with the case where the steel pipe pile 20 is sunk due to secular change or the like in the connection structure M shown in FIG. In FIG. 14A, the same components as those shown in FIG. 1 and FIG.

本実施例では、L字状調整金具35と中間金具37との間に、鋼管杭20の沈下量に合わせて高さ調整部材としてのシム60を介在させるようにしている。なお、経年変化による鋼管杭20の沈下に限定されず、例えば鋼管杭20の埋設時、深く埋設し過ぎた場合にも、同様にL字状調整金具35と中間金具37との間にシム60を介在させて、予め設定した架台10の高さになるように高さ調整をする場合にも適用できることは勿論である。シム60を介在させる以外については図1、図2に示す接続構造と同じである。   In the present embodiment, a shim 60 as a height adjustment member is interposed between the L-shaped adjustment fitting 35 and the intermediate fitting 37 in accordance with the amount of settlement of the steel pipe pile 20. In addition, it is not limited to subsidence of the steel pipe pile 20 by secular change, For example, also when the steel pipe pile 20 is embed | buried deeply, when it embeds deeply, shim 60 is similarly between the L-shaped adjustment metal fitting 35 and the intermediate metal fitting 37. Needless to say, the present invention can also be applied to the case where the height is adjusted to the height of the gantry 10 set in advance. The connection structure is the same as that shown in FIGS. 1 and 2 except that a shim 60 is interposed.

シム60は、例えば図14(b)に示すように、ほぼ方形板状で、その一辺で開口するU字状の取り付け溝61を設ける。鋼管杭20の沈下量に合わせてシム60を介在させる場合には、接続軸30を緩めるかあるいは長いものに取り替え、架台10を若干浮き上がらせた状態を維持して、L字状調整金具35と中間金具37との間に、シム60をその一辺側から挿入して、取り付け溝61内に接続軸30を挿入させる。シム60の挿入が完了したら、架台10を降ろし、接続軸30を締め付ける。これにより架台10の高さを維持することが出来る。なお、シム60を薄板から構成し、シム60を複数枚重ねて架台10の高さを微調整するようにしてもよい。経年変化により鋼管杭20の沈下がさらに進行したときには、シム60を追加すればよい。   For example, as shown in FIG. 14B, the shim 60 has a substantially rectangular plate shape and is provided with a U-shaped attachment groove 61 that opens on one side thereof. When the shim 60 is interposed in accordance with the sinking amount of the steel pipe pile 20, the connection shaft 30 is loosened or replaced with a long one, and the state in which the gantry 10 is slightly lifted is maintained. The shim 60 is inserted between the intermediate fitting 37 from one side thereof, and the connecting shaft 30 is inserted into the mounting groove 61. When the insertion of the shim 60 is completed, the gantry 10 is lowered and the connecting shaft 30 is tightened. Thereby, the height of the gantry 10 can be maintained. The shim 60 may be formed of a thin plate, and a plurality of shims 60 may be stacked to finely adjust the height of the gantry 10. When the settlement of the steel pipe pile 20 further progresses due to secular change, the shim 60 may be added.

なお、経年変化によって鋼管杭20が地盤中に沈下した場合など、例えば図2に示すように一対の脚部11が逆ハの字状に構成されているときには、一対の脚部11を互いに接近するように回転調整(傾斜していた脚部11を起こすように回転調整)して対処することは可能である。しかし、このようにするには脚部11の防錆処理を定期的に行うか、あるいは錆びにくい材料から脚部11を構成する必要があり、コストが嵩むおそれがある。これに対し、図14(a)、(b)に示す本実施例の接続構造Mでは、シム60をL字状調整金具35と中間金具37との間に介在させる極めて簡単な構成なので、コストが嵩むおそれはない。   In addition, when the steel pipe pile 20 sinks in the ground due to secular change, for example, as shown in FIG. 2, when the pair of leg portions 11 are configured in a reverse C shape, the pair of leg portions 11 are brought close to each other. Thus, it is possible to cope with the rotation adjustment (rotation adjustment to raise the inclined leg portion 11). However, in order to do this, it is necessary to periodically perform the rust prevention treatment of the leg part 11 or to construct the leg part 11 from a material that does not easily rust, which may increase the cost. On the other hand, in the connection structure M of the present embodiment shown in FIGS. 14A and 14B, the shim 60 is an extremely simple configuration in which the shim 60 is interposed between the L-shaped adjustment fitting 35 and the intermediate fitting 37. There is no risk of increasing.

本発明の接続構造は、上記実施例で示した太陽電池モジュール又は太陽電池アレイの架台10と鋼管杭20との接続に限定されるものではなく、例えば風力発電装置や送電用鉄塔などの上部構造物と杭との接続などにも適用される。   The connection structure of the present invention is not limited to the connection between the solar cell module or the solar cell array base 10 and the steel pipe pile 20 shown in the above-described embodiment. For example, the upper structure such as a wind power generator or a power transmission tower. This also applies to the connection between objects and piles.

本発明の上部構造物と杭との接続構造は、太陽電池モジュール又は太陽電池アレイの架台などの上部構造物が風圧などで浮き上がるのを防止し、また上部構造物台の自重で沈下するのを防止するために適用される。   The connection structure between the upper structure and the pile according to the present invention prevents the upper structure such as the solar cell module or the array of the solar cell array from being lifted by wind pressure or the like, and prevents the upper structure from sinking due to its own weight. Applied to prevent.

10 架台(上部構造物)
11 脚
20 鋼管杭(杭)
21a 杭頭
24 トルク伝達金具
24a トルク伝達金具
25 六角ナット
25a ネジ穴
30 接続軸
30a 頭部
31 芯ずれ調整用ルーズ穴
32 水平片部
33 取り付け調整長穴
34 垂直片部
35 L字状調整金具
36 貫通穴
37 中間金具
40 押さえ部材
41 芯ずれ調整用長穴
60 シム(高さ調整部材)
10 frame (superstructure)
11 leg 20 steel pipe pile (pile)
21a Pile head 24 Torque transmission fitting 24a Torque transmission fitting 25 Hexagon nut 25a Screw hole 30 Connection shaft 30a Head 31 Loose hole for misalignment adjustment 32 Horizontal piece 33 Mounting adjustment slot 34 Vertical piece 35 L-shaped adjustment fitting 36 Through hole 37 Intermediate bracket 40 Holding member 41 Long hole for adjusting misalignment 60 Shim (height adjusting member)

Claims (6)

上部構造物とそれを支持する杭との接続構造であって、
前記杭に接続され、前記杭の中心軸に沿って延びてその頭部が前記杭の杭頭から突出する接続軸と、
前記接続軸が挿入される芯ずれ調整用ルーズ穴を設けた水平片部と前記上部構造物の脚部に取り付けられる垂直片部とを有し、前記杭頭上で前記接続軸に対して移動可能な調整金具と、
前記芯ずれ調整用ルーズ穴を覆うようにして前記調整金具上に配置され、前記接続軸が挿入される芯ずれ調整用長穴を設け、前記杭頭上で前記接続軸に対して移動可能な押さえ部材と、
を備え、
前記杭頭内に、杭回転埋設装置から前記杭に回転力を伝達するトルク伝達金具が配置され、
前記接続軸は、前記芯ずれ調整用長穴と前記芯ずれ調整用ルーズ穴とを介してその下端部分が前記トルク伝達金具に接続され、
前記調整金具は、前記接続軸の前記頭部と前記押さえ部材とで前記杭頭に固定されることを特徴とする、上部構造物と杭との接続構造。
A connection structure between the superstructure and the pile supporting it;
A connection shaft connected to the pile, extending along a central axis of the pile and having a head protruding from the pile head of the pile;
It has a horizontal piece portion provided with a loose hole for adjusting the misalignment into which the connecting shaft is inserted and a vertical piece portion attached to the leg portion of the superstructure, and is movable with respect to the connecting shaft on the pile head Adjustment brackets,
A presser that is disposed on the adjustment fitting so as to cover the loose hole for adjusting the misalignment, is provided with a misalignment adjusting long hole into which the connecting shaft is inserted, and is movable on the pile head with respect to the connecting shaft. Members,
With
In the head of the pile, a torque transmission fitting for transmitting a rotational force from the pile rotary burying device to the pile is arranged,
The connecting shaft has a lower end portion connected to the torque transmission fitting through the misalignment adjusting elongated hole and the misalignment adjusting loose hole,
The connection structure of an upper structure and a pile, wherein the adjustment fitting is fixed to the pile head by the head portion of the connection shaft and the pressing member .
請求項1に記載の上部構造物と杭との接続構造において、
前記トルク伝達金具に、前記接続軸の前記下端部分を接続するためのネジ穴又はナット部材が設けられていることを特徴とする、上部構造物と杭との接続構造。
In the connection structure between the superstructure and the pile according to claim 1,
Connecting structure which the torque transmission fitting, characterized in that the threaded hole or a nut member for connecting the lower end portion of the connecting shaft is provided, the upper structure and piles.
請求項1又は2に記載の上部構造物と杭との接続構造において、
前記芯ずれ調整用ルーズ穴は、その直径が前記杭頭の内径とほぼ同じ寸法の円形穴又はその一辺の長さが前記杭頭の内径とほぼ同じ寸法の方形穴であり、
前記芯ずれ調整用長穴は、その幅が前記接続軸の直径とほぼ同じ寸法で、その長さが前記芯ずれ調整用ルーズ穴の直径又は一辺の長さとほぼ同じ寸法であることを特徴とする、上部構造物と杭との接続構造。
In the connection structure between the superstructure and the pile according to claim 1 or 2 ,
The loose hole for adjusting misalignment is a circular hole whose diameter is approximately the same as the inner diameter of the pile head or a square hole whose one side is approximately the same size as the inner diameter of the pile head,
The slot for adjusting misalignment has a width that is substantially the same as the diameter of the connecting shaft, and the length is approximately the same as the diameter of the loose hole for adjusting misalignment or the length of one side. The connection structure between the superstructure and the pile.
請求項1ないしの何れか一項に記載の上部構造物と杭との接続構造において、
前記杭頭と前記水平片部との間に配置され、前記接続軸が貫通する貫通穴を有する中間金具を備えてなることを特徴とする、上部構造物と杭との接続構造。
In the connection structure between the superstructure and the pile according to any one of claims 1 to 3 ,
A connection structure between an upper structure and a pile, comprising an intermediate fitting disposed between the pile head and the horizontal piece and having a through hole through which the connection shaft passes.
請求項に記載の上部構造物と杭との接続構造において、
前記水平片部と前記中間金具との間に高さ調整部材を配置したことを特徴とする、上部構造物と杭との接続構造。
In the connection structure between the superstructure and the pile according to claim 4 ,
A connection structure between an upper structure and a pile, wherein a height adjusting member is disposed between the horizontal piece and the intermediate fitting.
請求項1乃至の何れか一項に記載の上部構造物と杭との接続構造において、
前記垂直片部は、前記上部構造物の脚部の取り付け位置の調整が行える取り付け調整長穴を設けたことを特徴とする、上部構造物と杭との接続構造。
In the connection structure between the superstructure and the pile according to any one of claims 1 to 5 ,
The connection structure between the upper structure and the pile, wherein the vertical piece is provided with an attachment adjustment long hole that can adjust the attachment position of the leg of the upper structure.
JP2012055804A 2012-03-13 2012-03-13 Connection structure between superstructure and pile Active JP5952600B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012055804A JP5952600B2 (en) 2012-03-13 2012-03-13 Connection structure between superstructure and pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012055804A JP5952600B2 (en) 2012-03-13 2012-03-13 Connection structure between superstructure and pile

Publications (3)

Publication Number Publication Date
JP2013189784A JP2013189784A (en) 2013-09-26
JP2013189784A5 JP2013189784A5 (en) 2015-02-19
JP5952600B2 true JP5952600B2 (en) 2016-07-13

Family

ID=49390308

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012055804A Active JP5952600B2 (en) 2012-03-13 2012-03-13 Connection structure between superstructure and pile

Country Status (1)

Country Link
JP (1) JP5952600B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6363829B2 (en) * 2013-09-28 2018-07-25 奥地建産株式会社 Support stand for a planar article such as a solar panel and its support position adjusting member
JP2015078566A (en) * 2013-10-18 2015-04-23 株式会社郷葉 Solar panel pedestal construction method, and solar panel pedestal
JP6412342B2 (en) * 2014-06-05 2018-10-24 奥地建産株式会社 Method for constructing support frame for planar article
JP6627957B2 (en) * 2018-12-10 2020-01-08 Jfeエンジニアリング株式会社 Tubular and tower structures

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6059372B2 (en) * 1979-10-09 1985-12-25 松下電工株式会社 Foundation fixing device
JPH0233842U (en) * 1988-08-24 1990-03-02
JPH0532442U (en) * 1991-10-08 1993-04-27 ナシヨナル住宅産業株式会社 Base mounting structure
JPH11158867A (en) * 1997-12-01 1999-06-15 Okamoto Kensetsu Yohin Seisakusho:Kk Steel pipe pile and sealing cover thereof
JP2000008483A (en) * 1998-06-24 2000-01-11 Ishikawa Koyo Baseplate fixing device
JP2000192548A (en) * 1998-12-28 2000-07-11 Sumitomo Forestry Co Ltd Steel sill with position adjusting function
JP5467983B2 (en) * 2009-10-02 2014-04-09 新日鉄住金エンジニアリング株式会社 Pile head joint structure
JP2013083074A (en) * 2011-10-07 2013-05-09 Asahi Kasei Construction Materials Co Ltd Connection device

Also Published As

Publication number Publication date
JP2013189784A (en) 2013-09-26

Similar Documents

Publication Publication Date Title
US9091037B2 (en) Adjustable monopole support structure
JP5917707B2 (en) Wind power generator basics
JP5856511B2 (en) Pile foundation structure
JP5952600B2 (en) Connection structure between superstructure and pile
JP5901912B2 (en) Solar panel mount
JP5069171B2 (en) Offshore wind power generation foundation and superstructure joint structure and superstructure installation method
JP5131518B2 (en) Steel pipe pile and steel column joint structure
US9920748B2 (en) Method and tool for assembling tower elements
JP2013159945A (en) Connection structure of superstructure and pile
JP5356482B2 (en) Fundamental structure of solar cell module or solar cell array mount
JP2013044093A (en) Connection device
JP5841851B2 (en) Pile head joint structure assembly jig and pile head joint structure assembly method using the same
JP3194864U (en) Height adjustable pile
KR101696031B1 (en) Substructure for offshore wind power
JP2014077319A (en) Solar panel frame and construction method of solar panel frame
JP3213752U (en) Solar panel mount
JP2013189784A5 (en)
KR101353488B1 (en) Multiple supporting file foundation
JP2013060711A (en) Foundation structure for solar cell module or solar cell array frame
KR102376457B1 (en) Solar Panel Support Structure
KR101797427B1 (en) Substructure for offshore wind power
JP5968667B2 (en) Construction method of lightweight building foundation
KR20210085227A (en) Height adjustable solar structure support device for soft ground
JP5829151B2 (en) Connection structure between workpiece and pile
JP2015132088A (en) Connection member, and structure for connecting foundation pile and support together

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20141226

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20141226

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150914

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20151111

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151209

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160517

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160610

R150 Certificate of patent or registration of utility model

Ref document number: 5952600

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250