JP5799547B2 - Elevator installation method and elevator installation method - Google Patents

Elevator installation method and elevator installation method Download PDF

Info

Publication number
JP5799547B2
JP5799547B2 JP2011075985A JP2011075985A JP5799547B2 JP 5799547 B2 JP5799547 B2 JP 5799547B2 JP 2011075985 A JP2011075985 A JP 2011075985A JP 2011075985 A JP2011075985 A JP 2011075985A JP 5799547 B2 JP5799547 B2 JP 5799547B2
Authority
JP
Japan
Prior art keywords
elevator
frame
rail
building
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2011075985A
Other languages
Japanese (ja)
Other versions
JP2012206857A (en
Inventor
喜蔵 三浦
喜蔵 三浦
肖一 椎名
肖一 椎名
小野 英雄
英雄 小野
平一郎 滝沢
平一郎 滝沢
和也 矢田
和也 矢田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2011075985A priority Critical patent/JP5799547B2/en
Publication of JP2012206857A publication Critical patent/JP2012206857A/en
Application granted granted Critical
Publication of JP5799547B2 publication Critical patent/JP5799547B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Description

本発明は、昇降機又はエレベーターを建築物の屋内に設置する設置方法に関する。 The present invention, set置方law on you installed indoors of the elevator or elevator buildings.

建築物の建設工事において、建築物の屋外に、昇降足場と仮設の昇降機とを上下に並べて設置する場合がある(例えば、非特許文献1参照)。この場合、屋外の仮設の昇降機で資材等を揚重できるのは、昇降足場の最下位よりも下の階までのため、その上の階へ資材等を揚重できるようにするために、仮設の昇降機を建築物の屋内に設置する場合がある。   In the construction work of a building, a lifting scaffold and a temporary lifting machine may be installed side by side up and down outside the building (see, for example, Non-Patent Document 1). In this case, materials can be lifted with an outdoor temporary elevator because the floor is lower than the lowest floor of the lifting scaffold, so that the materials can be lifted to the upper floor. In some cases, the elevator is installed indoors in a building.

クレーン No.9 第47巻 9号 2009(発行人 古川 裕二、発行所 社団法人 日本クレーン協会、平成21年9月1日 発行)の3頁Crane No. 9 Vol. 47, No. 9, 2009 (Publisher: Yuji Furukawa, publisher, Japan Crane Association, issued on September 1, 2009)

ここで、建築物の屋内に設置する資材等の揚重用の昇降機は、仮設であり、後に撤去されるものであることから、製造コストの抑制に対する要求度は高い。また、建設中の建築物の屋内に仮設の昇降機を設置するために、各階のスラブに開口が空けられる場合があり、この場合、開口を塞がなければ各階の内装工事が完了しないことから、昇降機が、内装工事等が進行した階から速やかに撤去されることが望ましい。   Here, an elevator for lifting materials and the like installed indoors in a building is temporary and is removed later, so that there is a high degree of demand for suppressing manufacturing costs. Also, in order to install a temporary elevator inside the building under construction, an opening may be made in the slab on each floor, and in this case, if the opening is not blocked, the interior work on each floor will not be completed. It is desirable that the elevator be removed promptly from the floor where the interior work has progressed.

本発明は、上記事情に鑑みてなされたものであり、建築物の屋内に設置する仮設の昇降機又はエレベーターの製造コストを低減すると共に、昇降機又はエレベーターを工事が進行した階から速やかに撤去することを課題とするものである。 The present invention has been made in view of the above circumstances, and reduces the manufacturing cost of a temporary elevator or elevator installed indoors in a building, and promptly removes the elevator or elevator from the floor where the construction has progressed. Is an issue.

上記課題を解決するために、エレベーターの設置方法は、搬器と、前記搬器の昇降を案内するレールと、前記レールが連結され前記搬器の昇降路に沿って延びるフレームと、前記フレームの底部に設けられた架台とが一体化されてなるエレベーターが建設中の建築物に開けられた開口に通された状態、且つ、前記架台の進退可能な連結部が前記フレームの外周側に突出するとともに前記建築物の躯体に固定されることによって前記架台が前記躯体に連結された状態から、前記連結部を前記フレームの内側に収納することによって前記架台を前記躯体から外す第一工程と、前記第一工程後に、前記搬器、前記レール、前記フレーム及び前記架台が一体化された状態で前記エレベーターを上階側に揚重する第二工程と、前記第二工程後に、前記連結部を前記フレームの外周側に突出させて前記躯体に固定する第三工程と、を有する。 In order to solve the above problems, method of installing elevator, a carriage, a rail for guiding the vertical movement of the carriage, and a frame in which the rail is connected extends along the hoistway of the carriage, provided at the bottom of the frame An elevator that is integrated with the mounted base is passed through an opening opened in the building under construction, and a connecting portion capable of moving back and forth of the base protrudes to the outer peripheral side of the frame and the building A first step of removing the gantry from the housing by housing the connecting portion inside the frame from a state in which the gantry is coupled to the housing by being fixed to a housing of the object; and the first step. A second step of lifting the elevator to the upper floor side in a state where the transporter, the rail, the frame and the frame are integrated; and after the second step, The parts to protrude to the outer periphery of the frame; and a third step of fixing the skeleton.

前記エレベーターの設置方法は、前記第一工程の前に、前記搬器、前記レール、前記フレーム及び前記架台が予め組立てられた状態の前記エレベーターを前記建築物の上方まで揚重する揚重工程と、前記連結部を前記フレームの内周側に収納した状態で前記エレベーターを前記開口通して下降させる下降工程と、前記連結部を前記フレームの外周側に突出させて前記躯体に固定することによって、前記エレベーターを前記建築物の屋内に設置する工程と、を更に有してもよい。 The elevator installation method includes, before the first step, a lifting step of lifting the elevator in a state in which the carrier, the rail, the frame, and the gantry are pre-assembled to the top of the building , and state on the falling step of the elevator Ru is lowered through the opening which accommodates the inner peripheral side of the frame the connecting section, by fixing to the skeleton to protrude the coupling portion on the outer peripheral side of the frame And the step of installing the elevator indoors in the building .

前記エレベーターの設置方法において、前記レールを、複数のレール材を接続することにより構成し、前記フレームに、複数の柱材を接続することにより構成した複数の支柱を設け、前記レール材と前記柱材とを一体化させた複数の機体ユニットを接続することにより、前記レールと前記フレームとを備える機体を構成してもよい。 In the elevator installation method, the rail is configured by connecting a plurality of rail members, and the frame is provided with a plurality of support columns configured by connecting a plurality of column members. You may comprise the airframe provided with the said rail and the said frame by connecting the several airframe unit which integrated the material.

昇降機の設置方法では、搬器と、前記搬器の昇降を案内するレールと、前記レールが連結され前記搬器の昇降路に沿って延びるフレームとが一体化された状態で、建設中の建築物の屋内に設置された昇降機を、揚重して上階側に盛り替え、前記建築物の屋外には、昇降足場と屋外用昇降機とを上下に並べて設置し、前記建築物の屋内の前記昇降機を、少なくとも前記屋外用昇降機より上階側に昇降路が位置するように設置する。In the elevator installation method, a portable device, a rail for guiding the lifting and lowering of the portable device, and a frame connected to the rail and extending along the hoistway of the portable device are integrated into an indoor of a building under construction. The elevator installed in is lifted and rearranged to the upper floor side, and on the outside of the building, an elevator scaffolding and an outdoor elevator are installed side by side, and the elevator in the building indoors, It is installed so that the hoistway is positioned at least on the upper floor side from the outdoor elevator.

前記昇降機の設置方法において、前記搬器、前記レール、及び前記フレームが予め組立てられた状態の前記昇降機を前記建築物の上方まで揚重し、前記建築物に空けられた開口を通して下降させて前記建築物の屋内に設置してもよい。 In the elevator installation method, the elevator in a state where the carrier, the rail, and the frame are pre-assembled is lifted to the upper side of the building, and lowered through an opening vacated in the building. It may be installed indoors.

本発明によれば、建築物の屋内に設置する仮設の昇降機又はエレベーターの製造コストを低減すると共に、昇降機又はエレベーターを工事が進行した階から速やかに撤去することができる。 ADVANTAGE OF THE INVENTION According to this invention, while lowering the manufacturing cost of the temporary elevator / elevator installed indoors of a building, an elevator / elevator can be quickly removed from the floor where construction progressed.

一実施形態に係る建設工事用の昇降機を内部に設置した建設中の高層ビルの高層部を示す立面断面図である。It is an elevational sectional view showing a high-rise part of a high-rise building under construction in which an elevator for construction work according to one embodiment is installed. 屋内の昇降機を示す立面図である。It is an elevational view showing an indoor elevator. 図2の3−3矢視図(立面図)である。FIG. 3 is a view (elevated view) taken along arrow 3-3 in FIG. 2. 昇降機の下部を拡大して示す正面図である。It is a front view which expands and shows the lower part of an elevator. 昇降機の下部を拡大して側面図である。It is a side view which expands the lower part of an elevator. 架台を拡大して示す正面図である。It is a front view which expands and shows a mount frame. 架台を拡大して示す側面図である。It is a side view which expands and shows a mount frame. 架台を拡大して示す平面図である。It is a top view which expands and shows a mount frame. 図4の9−9断面図(平面断面図)である。It is 9-9 sectional drawing (plan sectional drawing) of FIG. 昇降機の天端部周辺を拡大して示す側面図である。It is a side view which expands and shows the top edge part periphery of an elevator. 昇降機の設置方法を説明するための側断面図である。It is a sectional side view for demonstrating the installation method of an elevator. 昇降機の設置方法を説明するための側断面図である。It is a sectional side view for demonstrating the installation method of an elevator. 昇降機の設置方法を説明するための側断面図である。It is a sectional side view for demonstrating the installation method of an elevator. 昇降機の設置方法を説明するための側断面図である。It is a sectional side view for demonstrating the installation method of an elevator. 他の実施形態に係る架台を示す平面図である。It is a top view which shows the mount frame which concerns on other embodiment.

以下、本発明の一実施形態を、図面を参照しながら説明する。図1は、一実施形態に係る建設工事用の昇降機10を屋内に設置した建設中の高層ビル1の高層部を示す立面断面図である。この図に示すように、建設中の高層ビル1の屋外には、建設工事用かつ屋外用の昇降機2と、昇降足場3とが設置されている。   Hereinafter, an embodiment of the present invention will be described with reference to the drawings. FIG. 1 is an elevational sectional view showing a high-rise part of a high-rise building 1 under construction in which an elevator 10 for construction work according to one embodiment is installed indoors. As shown in this figure, an elevator 2 and a lifting scaffold 3 for construction work and outdoors are installed outside the high-rise building 1 under construction.

屋外の昇降機2のレール4は、高層ビル1の外壁面に面して所定階まで延びるように設置されており、昇降機2の搬器5は、1階と前記所定階の2階下との間でレール4に沿って昇降する。この昇降機2は、屋内の昇降機10と比して、大型であり、搬器5の最大積載荷重が大きい。また、昇降足場3は、屋外の昇降機2の上側に、高層ビル1の外壁面に面して設置されており、昇降機2の天端が位置する前記所定階を最下位として昇降する。   The rail 4 of the outdoor elevator 2 is installed so as to face the outer wall surface of the high-rise building 1 and extend to a predetermined floor, and the carrier 5 of the elevator 2 is located between the first floor and the second floor below the predetermined floor. It goes up and down along the rail 4. The elevator 2 is larger than the indoor elevator 10 and has a large maximum load on the transporter 5. The lifting scaffold 3 is installed on the upper side of the outdoor elevator 2 so as to face the outer wall surface of the high-rise building 1 and moves up and down with the predetermined floor where the top of the elevator 2 is located at the lowest position.

また、高層ビル1の高層部の各階のスラブ6には、屋内の昇降機10の設置空間を確保するための矩形状の開口7が空けられており、昇降機10は、各階の開口7に挿通された状態で設置されている。ここで、屋外の昇降機2で資材や人員を揚重できるのは、前記所定階の2階下までであるところ、屋内の昇降機10は、前記所定階の3階下から現段階での最上階の上側まで延びるように設置されており、昇降機10の搬器20は、前記所定階の2階下と前記の最上階との間で昇降する。また、各階の開口7の周囲には手摺8と幅木9とが設置されている。   The slab 6 on each floor of the high-rise building 1 has a rectangular opening 7 for securing an installation space for the indoor elevator 10. The elevator 10 is inserted into the opening 7 on each floor. Installed. Here, the outdoor elevator 2 can lift materials and personnel up to the second floor below the predetermined floor, and the indoor elevator 10 moves from the third floor below the predetermined floor to the uppermost floor at the current stage. The carrying device 20 of the elevator 10 moves up and down between the second floor below the predetermined floor and the top floor. A handrail 8 and a baseboard 9 are installed around the opening 7 on each floor.

図2は、屋内の昇降機10を示す立面図であり、図3は、図2の3−3矢視図(立面図)である。これらの図に示すように、昇降機10は、ラック&ピニオン駆動方式のエレベーターであり、矩形の箱体である搬器20と、搬器20の昇降路を囲う機体13とを備えている。機体13は、搬器20の昇降を案内するレール30と、レール30が複数の壁つなぎ12を介して連結され、搬器20の昇降路を囲うように構成された四角柱状の骨格であるフレーム40と、フレーム40の周側部の矩形の開口を塞ぐように取り付けられた多数の養生パネル50、扉付きの養生パネル52とを備えている。   FIG. 2 is an elevation view showing the indoor elevator 10, and FIG. 3 is a view (elevation view) taken along arrow 3-3 in FIG. 2. As shown in these drawings, the elevator 10 is a rack-and-pinion drive type elevator, and includes a carrying device 20 that is a rectangular box and a vehicle body 13 that surrounds the hoistway of the carrying device 20. The airframe 13 includes a rail 30 that guides the lifting and lowering of the transporter 20, and a frame 40 that is a quadrangular columnar skeleton that is configured so that the rails 30 are connected via the plurality of wall connectors 12 and surround the hoistway of the transporter 20. A plurality of curing panels 50 and a curing panel 52 with a door attached so as to close a rectangular opening on the peripheral side of the frame 40 are provided.

図4は、昇降機10の下部を拡大して示す正面図であり、図5は、昇降機10の下部を拡大して示す側面図である。なお、扉付きの養生パネル52の設置面を昇降機10の正面、この正面の対向面を昇降機10の背面、これらに挟まれた一対の面を昇降機10の側面と称して説明する。
FIG. 4 is an enlarged front view showing the lower part of the elevator 10, and FIG. 5 is an enlarged side view showing the lower part of the elevator 10. In addition, the installation surface of the curing panel 52 with the door is referred to as the front surface of the elevator 10, the opposite surface of the front surface is referred to as the rear surface of the elevator 10, and a pair of surfaces sandwiched between them is referred to as the side surface of the elevator 10.

図4及び図5に示すように、レール30は、梯子状のフレーム32と、フレーム32に取付けられたレール材34とを備えている。フレーム32は、一対の支柱36と、一対の支柱36を連結する多数の梁材38とを備えている。支柱36は、複数の柱材36Aを接続することにより長尺化されている。なお、上下の柱材36Aはボルト接合されることにより接続されている。また、レール材34は、複数の断面L字状の板材34Aを接続することにより長尺されている。板材34Aの上下両端は、柱材36Aの上下両端を結合する梁材38に、ボルトで締結されている。   As shown in FIGS. 4 and 5, the rail 30 includes a ladder-shaped frame 32 and a rail member 34 attached to the frame 32. The frame 32 includes a pair of struts 36 and a number of beam members 38 that connect the pair of struts 36. The support column 36 is elongated by connecting a plurality of column members 36A. Note that the upper and lower column members 36A are connected by bolting. The rail member 34 is elongated by connecting a plurality of L-shaped plate members 34A. The upper and lower ends of the plate member 34A are fastened with bolts to beam members 38 that join the upper and lower ends of the column member 36A.

即ち、レール30は、一対の柱材36Aと、これらの上下両端及びその中間を連結する複数の梁材38と、複数の梁材38に固定された板材34Aとを備える複数のレールユニット31を上下に接続することにより構成されている。   That is, the rail 30 includes a plurality of rail units 31 including a pair of column members 36A, a plurality of beam members 38 that connect the upper and lower ends thereof and the middle thereof, and a plate member 34A fixed to the plurality of beam members 38. It is configured by connecting up and down.

フレーム40は、平面視にて矩形状に配された4本の支柱42と、4本の支柱42を連結する多数の梁材44と、壁つなぎ用の複数の梁材45と、フレーム40の底部に設けられ、フレーム40及びレール30を高層ビル1の躯体に支持する架台46とを備えている。   The frame 40 includes four columns 42 arranged in a rectangular shape in plan view, a number of beam members 44 connecting the four columns 42, a plurality of beam members 45 for connecting walls, A base 46 is provided at the bottom and supports the frame 40 and the rail 30 on the frame of the high-rise building 1.

支柱42は、複数の柱材42Aを接続することにより長尺化されている。柱材42Aの上下両端にはフランジ部42Bが形成されており、上下のフランジ部42B同士がボルトで締結されることにより、上下の柱材42Aが接続される。また、梁材44は、隣り合った一対の柱材42Aの上端、下端及び中央に溶接されており、平面視にて四角形状に配された4本の柱材42Aの上端、下端及び中央が、上下及び中央の各組4本の梁材44により連結されている。また、上下一対の壁つなぎ用の梁材45が、隣り合った一対の柱材42Aに溶接されている。   The support column 42 is elongated by connecting a plurality of column members 42A. Flange portions 42B are formed at both upper and lower ends of the column member 42A, and the upper and lower column members 42A are connected by fastening the upper and lower flange portions 42B with bolts. The beam member 44 is welded to the upper end, the lower end, and the center of a pair of adjacent column members 42A, and the upper end, the lower end, and the center of the four column members 42A arranged in a square shape in a plan view. The upper and lower and the center are connected by four beam members 44 each. Further, a pair of upper and lower wall connecting beam members 45 are welded to a pair of adjacent column members 42A.

また、柱材42Aと梁材44とにより形成される四角形状の開口には、養生パネル50、52が嵌め込まれており、養生パネル50、52の周縁が柱材42A及び梁材44に取付金具(不図示)を介して固定されている。   Curing panels 50 and 52 are fitted into a rectangular opening formed by the column member 42A and the beam member 44, and the periphery of the curing panels 50 and 52 is attached to the column member 42A and the beam member 44. It is fixed via (not shown).

即ち、フレーム40は、4本の柱材42Aと、これらの上下両端及び中央を連結する上下及び中央の各組4本の梁材44と、上下一対の壁つなぎ用の梁材45とを備える複数のフレームユニット41を上下に接続することにより構成されている。   That is, the frame 40 includes four column members 42A, four beam members 44 in each of the upper and lower ends and the center connecting these upper and lower ends and the center, and a pair of upper and lower beam members 45 for connecting the walls. It is configured by connecting a plurality of frame units 41 vertically.

さらに、昇降機10の機体13は、フレームユニット41と、フレームユニット41と一体化された複数のレールユニット31と、フレームユニット41と一体化された複数の養生パネル50、52とを備える機体ユニット11を上下に接続することにより構成されている。ここで、各機体ユニット11の全高は、高層ビル1の高層部2の2階分の高さに設定されている。また、各機体ユニット11の底端の位置は、対応階のスラブ6より僅かに低い位置に設定され、各機体ユニット11の天端の位置は、上記対応階の2階上のスラブ6より僅かに低い位置に設定されている。また、各機体ユニット11には、上下一対の養生パネル52が設けられており、扉付きの養生パネル52が、各階に対応して設けられている。   Further, the machine body 13 of the elevator 10 includes a frame unit 41, a plurality of rail units 31 integrated with the frame unit 41, and a plurality of curing panels 50 and 52 integrated with the frame unit 41. Are connected by connecting them vertically. Here, the total height of each airframe unit 11 is set to the height of the second floor of the high-rise part 2 of the high-rise building 1. In addition, the position of the bottom end of each airframe unit 11 is set slightly lower than the slab 6 on the corresponding floor, and the position of the top end of each airframe unit 11 is slightly lower than the slab 6 on the second floor of the corresponding floor. Is set to a low position. Each body unit 11 is provided with a pair of upper and lower curing panels 52, and a curing panel 52 with a door is provided corresponding to each floor.

図6は、架台46を拡大して示す正面図であり、図7は、架台46を拡大して示す側面図である。また、図8は、架台46を拡大して示す平面図である。これらの図に示すように、架台46は、平行に配された一対の受梁47と、互に平行かつ受梁47と直交するように配された一対の受梁48とを備えている。一対の受梁47は、昇降機10の正面側から背面側へ延びており、その両端に設けられたブラケット47Dがスラブ6にボルトで締結されている。2本の支柱42は、一方の受梁47上に配され、残りの2本の支柱42は、他方の受梁47上に配されており、支柱42の下端のブラケット42Bが受梁47にボルトで締結されている。   6 is an enlarged front view showing the gantry 46, and FIG. 7 is an enlarged side view showing the gantry 46. As shown in FIG. FIG. 8 is an enlarged plan view showing the gantry 46. As shown in these drawings, the gantry 46 includes a pair of receiving beams 47 arranged in parallel and a pair of receiving beams 48 arranged parallel to each other and orthogonal to the receiving beams 47. The pair of receiving beams 47 extend from the front side to the back side of the elevator 10, and brackets 47 </ b> D provided at both ends thereof are fastened to the slab 6 with bolts. The two struts 42 are arranged on one receiving beam 47, and the remaining two struts 42 are arranged on the other receiving beam 47, and the bracket 42 B at the lower end of the supporting column 42 is attached to the receiving beam 47. It is fastened with bolts.

また、一対の受梁48は、開口7の中心に対して対称に配されており、一対の受梁48の両端は、受梁47上にボルトで締結されている。また、一対の受梁48上には、エレベーターベース54がボルトで締結されている。このエレベーターベース54には、レール30の底端が固定されている。従って、搬器20、レール30、及びフレーム40の荷重が、架台46を介して開口7の周縁に設けられた梁14により受けられる。   The pair of receiving beams 48 are arranged symmetrically with respect to the center of the opening 7, and both ends of the pair of receiving beams 48 are fastened on the receiving beam 47 with bolts. An elevator base 54 is fastened with bolts on the pair of receiving beams 48. The bottom end of the rail 30 is fixed to the elevator base 54. Accordingly, the loads of the transporter 20, the rail 30, and the frame 40 are received by the beam 14 provided on the periphery of the opening 7 via the mount 46.

ここで、受梁47は、開口7上に配された基部47Aと、基部47Aの両端に配された一対の折畳部47Bと、折畳部47Bと基部47Aの端部とを連結する一対のヒンジ47Cとを備えている。図8中に鎖線で示すように、折畳部47Bは、スラブ6に非固定の状態では、鉛直なヒンジ軸を支点として開口7の内側に向けて回動可能である。   Here, the receiving beam 47 includes a pair of base portions 47A disposed on the opening 7, a pair of folding portions 47B disposed on both ends of the base portion 47A, and a pair of the folding portions 47B and the end portions of the base portion 47A. Hinge 47C. As indicated by a chain line in FIG. 8, the folding portion 47 </ b> B is rotatable toward the inside of the opening 7 with a vertical hinge shaft as a fulcrum in a state where it is not fixed to the slab 6.

図9は、図4の9−9断面図(平面断面図)である。この図に示すように、昇降機10の正面側かつスラブ6の高さに配された梁材44には、折畳式の通路板56が取り付けられている。昇降機10の正面側には、搬器20の扉22と養生パネル52の扉とが配されており、搬器20に出入りする乗員が、通路板56の上を通過する。   9 is a sectional view (plan sectional view) taken along line 9-9 in FIG. As shown in this figure, a foldable passage plate 56 is attached to the beam member 44 disposed on the front side of the elevator 10 and at the height of the slab 6. On the front side of the elevator 10, the door 22 of the carrying device 20 and the door of the curing panel 52 are arranged, and an occupant entering and leaving the carrying device 20 passes over the passage plate 56.

通路板56は、一対の長方形状の板材56A、56Bがヒンジ56Cにより折畳可能に連結された構成となっている。板材56A、56Bは、正面側の梁材44と平行に配されており、板材56Aが正面側の梁材44上にボルトにより締結され、板材56Bが、正面側の梁材44と平行なヒンジ軸を支点として回動する。ここで、通路板56は、折畳まれた状態では全体が開口7上に位置し、展開された状態では板材56Bの先端側がスラブ6上に位置する。   The passage plate 56 has a configuration in which a pair of rectangular plate members 56A and 56B are foldably connected by a hinge 56C. The plate members 56A and 56B are arranged in parallel with the front beam member 44, the plate member 56A is fastened to the front beam member 44 by bolts, and the plate member 56B is a hinge parallel to the front beam member 44. It rotates with the shaft as a fulcrum. Here, the passage plate 56 is entirely located on the opening 7 in the folded state, and the leading end side of the plate material 56B is located on the slab 6 in the unfolded state.

図10は、昇降機10の天端部周辺を拡大して示す側面図である。この図に示すように、昇降機10の正面側かつ高層ビル1の最上階のスラブ6の高さに配された一対の梁材44には、折畳式の連結板58が取付けられている。連結板58は、一対の長方形状の板材58A、58Bがヒンジ58Cにより折畳可能に連結された構成となっている。板材58A、58Bは、正面側及び背面側の梁44と平行に配されており、板材56Aが正面側又は背面側の梁材44上にボルトで締結され、板材56Bが正面側及び背面側の梁材44と平行なヒンジ軸を支点として回動する。   FIG. 10 is an enlarged side view showing the vicinity of the top end portion of the elevator 10. As shown in this figure, a foldable connection plate 58 is attached to a pair of beam members 44 arranged at the front side of the elevator 10 and at the height of the slab 6 on the uppermost floor of the high-rise building 1. The connecting plate 58 has a configuration in which a pair of rectangular plate members 58A and 58B are connected by a hinge 58C so as to be foldable. The plate members 58A and 58B are arranged in parallel with the beam 44 on the front side and the back side, the plate member 56A is fastened with bolts on the beam member 44 on the front side or the back side, and the plate member 56B is placed on the front side and the back side. The hinge shaft parallel to the beam member 44 is rotated as a fulcrum.

ここで、連結板58は、折畳まれた状態では全体が開口7上に位置し、展開された状態では板材58Bが、前記の最上階のスラブ6上に位置する。この連結板58は、昇降機10の設置後は、前記の最上階のスラブ6にアンカーで固定される。これにより、昇降装置10の振れが防止される。   Here, the entire connecting plate 58 is positioned on the opening 7 in the folded state, and the plate material 58B is positioned on the uppermost slab 6 in the expanded state. The connecting plate 58 is fixed to the uppermost slab 6 with an anchor after the elevator 10 is installed. Thereby, the swing of the raising / lowering apparatus 10 is prevented.

図11から図14までは、昇降機10の設置方法を説明するための側断面図である。図11に示すように、昇降機10を建設中の高層ビル1の高層部に設置する際には、搬器20、レール30、フレーム40、及び養生パネル50、52の組立が完了された状態の昇降機10をタワークレーン16で、高層ビル1の上方まで揚重し、開口7を通して高層ビル1の屋内で下降させる。この際、架台46の受梁47の先端を折畳んで開口7の投影領域内に収まる状態にして、架台46とスラブ6及び梁14との干渉を防止する。また、連結板58を折畳んで開口7内に収まる状態にして、連結板58とスラブ6及び梁14との干渉を防止する。   11 to 14 are side cross-sectional views for explaining the installation method of the elevator 10. As shown in FIG. 11, when installing the elevator 10 in the high-rise part of the high-rise building 1 under construction, the elevator in a state where the assembly of the transporter 20, the rail 30, the frame 40, and the curing panels 50 and 52 is completed. 10 is lifted up above the high-rise building 1 by the tower crane 16 and lowered through the opening 7 in the high-rise building 1 indoors. At this time, the front end of the receiving beam 47 of the gantry 46 is folded so as to be within the projection region of the opening 7 to prevent interference between the gantry 46 and the slab 6 and the beam 14. In addition, the connecting plate 58 is folded and placed in the opening 7 to prevent the connecting plate 58 from interfering with the slab 6 and the beam 14.

そして、図12に示すように、架台46が設置階まで下降すると、受梁47の先端を展開し、受梁47のフランジ部47Dを設置階のスラブ6にボルトで締結する。また、連結板58を展開し、連結板58の板材58Bを現段階での最上階のスラブ6にボルトで締結する。   Then, as shown in FIG. 12, when the gantry 46 is lowered to the installation floor, the tip of the receiving beam 47 is developed, and the flange portion 47D of the receiving beam 47 is fastened to the slab 6 on the installation floor with a bolt. Further, the connecting plate 58 is developed, and the plate material 58B of the connecting plate 58 is fastened with bolts to the uppermost slab 6 at the current stage.

次に、図13及び図14に示すように、高層ビル1の建設工事が進行して躯体の階数が増えると、昇降機10をタワークレーン16で揚重して上階側に盛り替える。その際、まず、図13に示すように、架台46の受梁47のスラブ6への固定を解除し、受梁47の先端を折畳むことにより、架台46をその全体が開口7の内側に収まる状態にする。また、連結板58の板材58Bのスラブ6への固定を解除し、連結板58を折畳むことにより、連結板58をその全体が開口7の内側に収まる状態にする。   Next, as shown in FIGS. 13 and 14, when the construction work of the high-rise building 1 proceeds and the number of floors of the building increases, the elevator 10 is lifted by the tower crane 16 and rearranged to the upper floor side. At that time, first, as shown in FIG. 13, the fixing of the receiving beam 47 of the frame 46 to the slab 6 is released, and the tip of the receiving beam 47 is folded, so that the entire frame 46 is placed inside the opening 7. Make it fit. Further, the connection plate 58 is released from being fixed to the slab 6 and the connection plate 58 is folded, so that the connection plate 58 is entirely accommodated inside the opening 7.

そして、図14に示すように、受梁47、連結板58を折畳んだ状態の昇降機10を、タワークレーン16で複数階分(本実施形態では2階分)だけ揚重して、受梁47の先端を展開し、受梁47のフランジ部47Dを、これまでよりも上階の設置階のスラブ6にボルトで締結する。また、連結板58を展開し、板材58Bを、現段階での最上階のスラブ6にボルトで締結する。   Then, as shown in FIG. 14, the elevator 10 with the receiving beam 47 and the connecting plate 58 folded is lifted by a tower crane 16 for a plurality of floors (in this embodiment, two floors), and the receiving beam The tip of 47 is developed, and the flange portion 47D of the receiving beam 47 is fastened with a bolt to the slab 6 on the installation floor higher than before. Further, the connecting plate 58 is developed, and the plate material 58B is fastened with bolts to the uppermost slab 6 at the current stage.

以上説明したように、本実施形態では、高層ビル1の高層部の屋内に設置した仮設の昇降機10を、躯体の建設中に上階側に盛り替える。即ち、設置当初から昇降路が工事完了時の最上階まで達するような昇降路の寸法の長い昇降機を製造するのではなく、それよりも昇降路の寸法の短い昇降機10を製造する。そして、まずは、昇降機10を、最下階が屋外の昇降機2の最上階と一致するように設置し、工事が進行して躯体の階数が上がるのに合わせて、昇降機10を上階側に揚重して盛り替える。   As described above, in this embodiment, the temporary elevator 10 installed indoors in the high-rise part of the high-rise building 1 is replaced with the upper floor during the construction of the housing. That is, instead of manufacturing an elevator with a long hoistway dimension so that the hoistway reaches the top floor at the time of completion of construction from the beginning of installation, an elevator 10 with a shorter hoistway dimension is manufactured. First, the elevator 10 is installed so that the lowermost floor coincides with the uppermost floor of the outdoor elevator 2, and as the construction progresses and the number of floors of the enclosure increases, the elevator 10 is raised to the upper floor side. Overlap and reorder.

これにより、昇降機10のレール30やフレーム40の長尺化を抑制でき、これらを構成する部材の数を低減できる。従って、工事完了後に撤去する仮設の昇降機10の製造コストを低減できる。   Thereby, lengthening of the rail 30 of the elevator 10 or the flame | frame 40 can be suppressed, and the number of members which comprise these can be reduced. Therefore, it is possible to reduce the manufacturing cost of the temporary elevator 10 that is removed after the construction is completed.

また、昇降機10を、工事の進行に合わせて上階側に揚重することにより、その下部がスラブ6に空けられた開口7から抜き出される。従って、昇降機10を、内装工事等が進行した階から速やかに撤去することができる。   Further, the elevator 10 is lifted to the upper floor side in accordance with the progress of the construction, so that the lower part is extracted from the opening 7 formed in the slab 6. Therefore, the elevator 10 can be promptly removed from the floor where the interior work or the like has progressed.

また、本実施形態では、架台46の受梁47の先端部を折畳可能に構成し、折畳んだ状態では受梁47の全体が開口7の内側に収まり、展開した状態では受梁47の先端が開口7の外周側に突出するように構成した。これにより、架台46を開口7の周りのスラブ6や梁14に干渉させることなく、昇降機10を高層ビル1の屋内で昇降させることができる。また、昇降機10の設置作業として、架台46を設置階のスラブ6に固定するためのブラケットを受梁47の先端に取付ける作業を行うことを不要にでき、以って、昇降機10の設置作業の工数を低減できる。   Further, in the present embodiment, the tip end portion of the receiving beam 47 of the gantry 46 is configured to be foldable. When folded, the entire receiving beam 47 is accommodated inside the opening 7, and in the unfolded state, The tip is configured to protrude to the outer peripheral side of the opening 7. Accordingly, the elevator 10 can be raised and lowered inside the high-rise building 1 without causing the gantry 46 to interfere with the slab 6 and the beam 14 around the opening 7. Further, as the installation work of the elevator 10, it is not necessary to perform the work of attaching a bracket for fixing the gantry 46 to the slab 6 on the installation floor to the tip of the receiving beam 47. Man-hours can be reduced.

また、本実施形態では、連結板58を折畳可能に構成し、折畳んだ状態では全体が開口7の内側に収まり、展開した状態では板材48Bが開口7の外周側に突出するように構成した。これにより、昇降機10の振れを防止するための連結板58を開口7の周りのスラブ6や梁14に干渉させることなく、昇降機10を高層ビル1の屋内で昇降させることができる。昇降機10の設置作業として、連結板58を最上階のスラブ6に固定するためのブラケットを取付ける作業を行うことを不要にでき、以って、昇降機10の設置作業の工数を低減できる。   Further, in the present embodiment, the connecting plate 58 is configured to be foldable, and is configured so that the entirety fits inside the opening 7 in the folded state, and the plate material 48B protrudes to the outer peripheral side of the opening 7 in the expanded state. did. Thereby, the elevator 10 can be lifted and lowered inside the high-rise building 1 without causing the connecting plate 58 for preventing the swing of the elevator 10 to interfere with the slab 6 and the beam 14 around the opening 7. As the installation work of the elevator 10, it is not necessary to perform the work of attaching a bracket for fixing the connecting plate 58 to the slab 6 on the uppermost floor, so that the number of man-hours for the installation work of the elevator 10 can be reduced.

また、本実施形態では、搬器20、レール30、フレーム40、及び養生パネル50、52の組立が完了された状態の昇降機10を、タワークレーン16で、高層ビル1の上方まで揚重し、開口7を通して高層ビル1の屋内で下降させ、そして、架台46及び連結板58を展開させて、架台46を設置階に連結板58をその段階での最上階に固定する。これにより、昇降機10の設置作業として、柱材や梁材や養生パネル50、52等の昇降機10を構成する各部材や機具等を、高層部まで人力で揚重する作業や、揚重した部材を組み立てる作業を不要にでき、以って、昇降機10の設置作業の工数を低減できる。   Moreover, in this embodiment, the elevator 10 in a state in which the assembling of the transporter 20, the rail 30, the frame 40, and the curing panels 50 and 52 is completed is lifted above the high-rise building 1 by the tower crane 16 and opened. 7 is lowered indoors in the high-rise building 1, and the gantry 46 and the connecting plate 58 are expanded to fix the gantry 46 to the installation floor and the connecting plate 58 to the uppermost floor at that stage. Thereby, as installation work of the elevator 10, the work of lifting the members, tools, etc. constituting the elevator 10 such as the pillar material, the beam material, the curing panel 50, 52, etc. manually to the higher floors, or the lifted member As a result, the work of assembling the elevator 10 can be reduced.

また、本実施形態に係る昇降機10は、フレームユニット41と、フレームユニット41と一体化された複数のレールユニット31と、フレームユニット41と一体化された複数の養生パネル50、52とを備える機体ユニット11を上下に接続することにより構成されている。また、各機体ユニット11の全高を、高層ビル1の2階分の高さに設定し、各階に対応して扉付きの養生パネル52を設置している。   The elevator 10 according to the present embodiment includes a frame unit 41, a plurality of rail units 31 integrated with the frame unit 41, and a plurality of curing panels 50 and 52 integrated with the frame unit 41. It is configured by connecting the units 11 up and down. Moreover, the total height of each airframe unit 11 is set to the height of the second floor of the high-rise building 1, and the curing panel 52 with a door is installed corresponding to each floor.

ここで、本実施形態では、高層ビル1の高層部において、各階の天井高さは同じであることから、全高が均一の1種類の機体ユニット11を上下に接続して昇降機10を構成しているところ、天井高さが異なる階が存在する建築物に設置する場合には、全高が異なる複数種類の機体ユニット11を作製して、これらを上下に接続して昇降機10の機体13を構成すればよい。即ち、複数の機体ユニット11を上下に接続することにより昇降機10の機体13を構成することによって、建築物の各階の天井高さに対応して各階に養生パネル52の扉位置を適当に配置することができる。   Here, in this embodiment, since the ceiling height of each floor is the same in the high-rise part of the high-rise building 1, one type of airframe unit 11 having a uniform overall height is connected up and down to constitute the elevator 10. However, when installing in a building where floors with different ceiling heights exist, a plurality of types of airframe units 11 with different overall heights are produced and connected up and down to form the airframe 13 of the elevator 10. That's fine. That is, by constructing the body 13 of the elevator 10 by connecting a plurality of body units 11 up and down, the door position of the curing panel 52 is appropriately arranged on each floor corresponding to the ceiling height of each floor of the building. be able to.

また、本実施形態では、高層ビル1の高層部の外壁に面して連層足場3が設置され、その下に屋外用の昇降機2が設置されており(図1参照)、昇降機2で資材等を揚重できるのは、連層足場3の設置階よりも下の階までであるところ、その上の階には、屋内に設置した昇降機10で資材等を揚重できる。ここで、一般に、建設工事用かつ屋外用の昇降機の積載荷重は、建設工事用かつ屋内用の昇降機のそれよりも大きいことから、資材等を効率よく揚重することができる。また、屋内用の昇降機10を設置するための開口7をスラブ6に空ける階を、上層階のみに留めることができるので、それよりも下の階については内装工事を完了させることができ、工期の短縮に寄与する。   Moreover, in this embodiment, the multi-layer scaffold 3 is installed facing the outer wall of the high-rise part of the high-rise building 1, and the elevator 2 for outdoor use is installed thereunder (refer to FIG. 1). Etc. can be lifted up to a floor below the floor where the multi-layer scaffold 3 is installed, and materials and the like can be lifted on the upper floor by an elevator 10 installed indoors. Here, in general, since the loading load of the elevator for construction work and outdoor is larger than that of the elevator for construction work and indoor, materials and the like can be efficiently lifted. Further, since the floor where the opening 7 for installing the indoor elevator 10 is opened in the slab 6 can be kept only on the upper floor, the interior work can be completed on the floor below it, and the construction period Contributes to shortening.

図15は、架台46の他の実施形態に係る架台60を示す平面図である。この図に示すように、架台60は、一対の受梁48と、互に平行かつ一対の受梁48と直交するように配された一対の受梁62を備えている。一対の受梁62は、昇降機10の正面側から背面側へ延びており、その両端に設けられたブラケット62Dがスラブ6にボルトで締結されている。2本の支柱42は、一方の受梁62上に配され、残りの2本の支柱42は、他方の受梁62上に配されており、支柱42の下端が受梁62にボルトで締結されている。また、一対の受梁48の両端は、受梁62上にボルトで締結されている。従って、搬器20、レール30、及びフレーム40の荷重が、架台60を介して開口7の周縁に設けられた梁14により受けられる。   FIG. 15 is a plan view showing a gantry 60 according to another embodiment of the gantry 46. As shown in this figure, the gantry 60 includes a pair of receiving beams 48 and a pair of receiving beams 62 arranged so as to be parallel to each other and orthogonal to the pair of receiving beams 48. The pair of receiving beams 62 extends from the front side to the back side of the elevator 10, and brackets 62 </ b> D provided at both ends thereof are fastened to the slab 6 with bolts. The two struts 42 are arranged on one receiving beam 62, and the remaining two struts 42 are arranged on the other receiving beam 62, and the lower end of the supporting column 42 is fastened to the receiving beam 62 with bolts. Has been. Further, both ends of the pair of receiving beams 48 are fastened on the receiving beams 62 with bolts. Accordingly, the loads of the transporter 20, the rail 30, and the frame 40 are received by the beam 14 provided on the periphery of the opening 7 via the gantry 60.

ここで、受梁62は、開口7上に配された基部62Aと、基部62Aの両端に配された一対の伸縮部62Bとを備えている。伸縮部62Bは油圧ジャッキであり、基部62Aに固定されたシリンダー部62Cと、フランジ部62Dが先端に設けられたピストン部62Pとを備えている。図中に鎖線で示すように、伸縮部62Bは、スラブ6に対して非固定の状態では、全体が開口7の内側に収まるように収縮したり、フランジ部62Dが開口7の外側に突出するように伸長したりすることが可能である。なお、伸縮部62Bを、基部62Aの内部に納まる程度の鋼材で構成し、手動で伸縮させるように構成してもよい。   Here, the receiving beam 62 includes a base portion 62A disposed on the opening 7 and a pair of extendable portions 62B disposed on both ends of the base portion 62A. The expansion / contraction part 62B is a hydraulic jack, and includes a cylinder part 62C fixed to the base part 62A and a piston part 62P provided with a flange part 62D at the tip. As indicated by a chain line in the drawing, the expansion / contraction part 62B contracts so that the entire part can be accommodated inside the opening 7 or the flange part 62D protrudes outside the opening 7 when not fixed to the slab 6. It is possible to elongate. In addition, you may comprise the expansion-contraction part 62B with the steel material of the grade which fits in the inside of the base 62A, and extending / contracting manually.

以上のように架台60を構成したことにより、架台60を開口7の周りのスラブ6や梁14に干渉させることなく、昇降機10を高層ビル1の屋内で昇降させることができる。また、昇降機10の設置作業として、架台60を設置階のスラブ6に固定するためのブラケットを受梁62の先端に取付ける作業を行うことを不要にでき、以って、昇降機10の設置作業の工数を低減できる。   By configuring the gantry 60 as described above, the elevator 10 can be raised and lowered inside the high-rise building 1 without causing the gantry 60 to interfere with the slab 6 and the beam 14 around the opening 7. Further, as the installation work of the elevator 10, it is not necessary to perform the work of attaching a bracket for fixing the gantry 60 to the slab 6 on the installation floor to the tip of the receiving beam 62. Man-hours can be reduced.

なお、上述の実施形態は、本発明の理解を容易にするためのものであり、本発明を限定するものではない。本発明はその趣旨を逸脱することなく、変更、改良され得ると共に本発明にはその等価物が含まれることは勿論である。例えば、上述の実施形態では、昇降機10を高層ビル1の高層部に設置したが、低層部に設置してもよい。また、昇降機10の設置前に、養生パネル50、52をフレーム40に取付けておくことは必須ではなく、昇降機10の設置後に行ってもよい。   In addition, the above-mentioned embodiment is for making an understanding of this invention easy, and does not limit this invention. It goes without saying that the present invention can be changed and improved without departing from the gist thereof, and that the present invention includes equivalents thereof. For example, in the above-mentioned embodiment, although the elevator 10 was installed in the high-rise part of the high-rise building 1, you may install in a low-rise part. In addition, it is not essential to attach the curing panels 50 and 52 to the frame 40 before the elevator 10 is installed, and may be performed after the elevator 10 is installed.

1 高層ビル(建築物)、2 昇降機(屋外用昇降機)、3 昇降足場、4 レール、5 搬器、6 スラブ、7 開口、8 手摺、9 幅木、10 昇降機(屋内用昇降機)、11 機体ユニット(ユニット)、12 壁つなぎ、13 機体、14 梁、16 タワークレーン、20 搬器、30 レール、31 レールユニット、32 フレーム、34 レール材、34A 板材、36 支柱、36A 柱材、38 梁材、40 フレーム、41 フレームユニット、42 支柱、42A 柱材、44 梁材、46 架台、47 受梁、47A 基部、47B 折畳部(連結部)、47C ヒンジ、48 受梁、50、52 養生パネル、54 エレベーターベース、56 通路板、56A、56B 板材、56C ヒンジ、58 連結板、58A、58B 板材、58C ヒンジ、60 架台、62 受梁、62A 基部、62B 伸縮部(連結部)、62C シリンダー部、62D フランジ部、62P ピストン部 DESCRIPTION OF SYMBOLS 1 High-rise building (building), 2 Elevator (outdoor elevator), 3 Lifting scaffold, 4 Rail, 5 Carriage, 6 Slab, 7 Opening, 8 Handrail, 9 Skirting board, 10 Elevator (indoor elevator), 11 Airframe unit (Unit), 12 Wall connection, 13 Airframe, 14 Beam, 16 Tower crane, 20 Carrier, 30 Rail, 31 Rail unit, 32 Frame, 34 Rail material, 34A Plate material, 36 Post, 36A Column material, 38 Beam material, 40 Frame, 41 Frame unit, 42 Post, 42A Column material, 44 Beam material, 46 Mounting base, 47 Receiving beam, 47A Base, 47B Folding portion (connecting portion), 47C Hinge, 48 Receiving beam, 50, 52 Curing panel, 54 Elevator base, 56 passage plate, 56A, 56B plate material, 56C hinge, 58 connecting plate, 58A, 58B plate material, 5 C hinges 60 gantry, 62 receiving beam, 62A base, 62B stretchable portion (connecting portion), 62C cylinder unit, 62D flange, 62P piston portion

Claims (5)

搬器と、前記搬器の昇降を案内するレールと、前記レールが連結され前記搬器の昇降路に沿って延びるフレームと、前記フレームの底部に設けられた架台とが一体化されてなるエレベーターが建設中の建築物に開けられた開口に通された状態、且つ、前記架台の進退可能な連結部が前記フレームの外周側に突出するとともに前記建築物の躯体に固定されることによって前記架台が前記躯体に連結された状態から、前記連結部を前記フレームの内側に収納することによって前記架台を前記躯体から外す第一工程と、
前記第一工程後に、前記搬器、前記レール、前記フレーム及び前記架台が一体化された状態で前記エレベーターを上階側に揚重する第二工程と、
前記第二工程後に、前記連結部を前記フレームの外周側に突出させて前記躯体に固定する第三工程と、を有するエレベーターの設置方法。
A carriage, a rail for guiding the vertical movement of the carriage, and a frame in which the rail is connected extends along the hoistway of the carriage, elevator and mount provided, which are integrated into the bottom of the frame under construction A state where the frame is passed through an opening opened in the building, and a connecting portion capable of moving back and forth of the frame protrudes to the outer peripheral side of the frame and is fixed to the frame of the building, whereby the frame is fixed to the frame. A first step of removing the mount from the housing by storing the connecting portion inside the frame from a state connected to the frame;
After the first step, the second step of lifting the elevator to the upper floor side in a state where the carrier, the rail, the frame, and the gantry are integrated;
An elevator installation method comprising: a third step of, after the second step, projecting the connecting portion to the outer peripheral side of the frame and fixing it to the housing .
前記第一工程の前に、前記搬器、前記レール、前記フレーム及び前記架台が予め組立てられた状態の前記エレベーターを前記建築物の上方まで揚重する揚重工程と、
前記揚重工程後に、前記連結部を前記フレームの内周側に収納した状態で前記エレベーターを前記開口通して下降させる下降工程と、
前記下降工程後に、前記連結部を前記フレームの外周側に突出させて前記躯体に固定することによって、前記エレベーターを前記建築物の屋内に設置する工程と、を更に有する請求項1に記載のエレベーターの設置方法。
Prior to the first step, a lifting step of lifting the elevator in a state where the carrier, the rail, the frame, and the gantry are pre-assembled to the top of the building ;
After the lifting step, the lowering step in a state where the connecting portion is accommodated in the inner peripheral side of the frame Ru is lowered through the lift opening;
After the downward movement step, lift according to claim 1, wherein by fixing the skeleton of the connecting portion is protruded on the outer peripheral side of the frame, further having the steps of placing the elevator indoors of the building Installation method.
前記レールを、複数のレール材を接続することにより構成し、
前記フレームに、複数の柱材を接続することにより構成した複数の支柱を設け、
前記レール材と前記柱材とを一体化させた複数の機体ユニットを接続することにより、前記レールと前記フレームとを備える機体を構成する請求項1又は2に記載のエレベーターの設置方法。
The rail is configured by connecting a plurality of rail materials,
The frame is provided with a plurality of struts configured by connecting a plurality of column members,
The elevator installation method according to claim 1 or 2, comprising a fuselage including the rail and the frame by connecting a plurality of fuselage units in which the rail material and the pillar material are integrated.
搬器と、前記搬器の昇降を案内するレールと、前記レールが連結され前記搬器の昇降路に沿って延びるフレームとが一体化された状態で、建設中の建築物の屋内に設置された昇降機を、揚重して上階側に盛り替え、
前記建築物の屋外には、昇降足場と屋外用昇降機とを上下に並べて設置し、
前記建築物の屋内の前記昇降機を、少なくとも前記屋外用昇降機より上階側に昇降路が位置するように設置する昇降機の設置方法。
A lift installed inside a building under construction in a state in which a transporter, a rail for guiding the lifting of the transporter, and a frame connected to the rail and extending along the hoistway of the transporter are integrated. , Lift and rearrange to the upper floor,
Outside the building, a lifting scaffold and an outdoor lift are installed side by side,
The elevator installation method which installs the said elevator in the said building indoor so that a hoistway may be located at least on the upper floor side from the said outdoor elevator.
前記搬器、前記レール、及び前記フレームが予め組立てられた状態の前記昇降機を前記建築物の上方まで揚重し、前記建築物に空けられた開口を通して下降させて前記建築物の屋内に設置する請求項4に記載の昇降機の設置方法。The elevator with the carrier, the rail, and the frame pre-assembled is lifted up above the building and lowered through an opening in the building and installed inside the building. Item 5. The elevator installation method according to Item 4.
JP2011075985A 2011-03-30 2011-03-30 Elevator installation method and elevator installation method Expired - Fee Related JP5799547B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011075985A JP5799547B2 (en) 2011-03-30 2011-03-30 Elevator installation method and elevator installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011075985A JP5799547B2 (en) 2011-03-30 2011-03-30 Elevator installation method and elevator installation method

Publications (2)

Publication Number Publication Date
JP2012206857A JP2012206857A (en) 2012-10-25
JP5799547B2 true JP5799547B2 (en) 2015-10-28

Family

ID=47186948

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011075985A Expired - Fee Related JP5799547B2 (en) 2011-03-30 2011-03-30 Elevator installation method and elevator installation method

Country Status (1)

Country Link
JP (1) JP5799547B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2529747B (en) * 2015-06-11 2016-08-17 Ischebeck Titan Ltd Hoisting apparatus and system
WO2020035933A1 (en) * 2018-08-16 2020-02-20 三菱電機株式会社 Method for applying construction elevator lifting height extension technology

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06322993A (en) * 1993-05-10 1994-11-22 Takenaka Komuten Co Ltd Expansion machine beam of mobile machine room type elevator
JP2002038721A (en) * 2000-07-27 2002-02-06 Miyaoka Komuten:Kk Lifting device of building temporary material

Also Published As

Publication number Publication date
JP2012206857A (en) 2012-10-25

Similar Documents

Publication Publication Date Title
EP2394006B1 (en) Construction system and method for multi-floor buildings
JP6503716B2 (en) Demolition system and demolition method
JP2010265727A (en) Method for demolishing building using floor climbing type tower crane
KR100731315B1 (en) Gang form climbing guide and system using the same
JP2009073599A (en) Supporting structure of tower crane and climbing method
JP5799547B2 (en) Elevator installation method and elevator installation method
JP2009057198A (en) Elevator car, assembly method of elevator car, and lifting tool
JP6712501B2 (en) High-rise building demolition system and demolition method
JP5365854B2 (en) Tower crane support structure and climbing method
JP5799546B2 (en) Elevator, its installation method and elevator installation method
JP4898255B2 (en) Mobile scaffolding and powerless descent device
JP5940404B2 (en) Construction method of beam members
JP2012207379A (en) Structure demolition system
JP4952014B2 (en) Building demolition method and maintenance method, curing scaffold descent device
JP5169604B2 (en) Elevator installation work floor apparatus and its assembly method
JP2013100686A (en) Mounting structure and mounting method for spiral staircase
JP2007284179A (en) Lifting device and its climbing method
JP2008214062A (en) Lifting device and structural material mounting method
JP5301508B2 (en) Climbing crane support method and support jig
JP6084936B2 (en) Elevator installation apparatus and method of assembling the installation apparatus
KR200410591Y1 (en) Lift apparatus for construction
JP6984795B1 (en) How to install the elevator installation work floor device and the elevator installation work floor device
KR200445362Y1 (en) Lower support of the safety netting device
JP7278863B2 (en) How to install a lifting scaffold
JP6971178B2 (en) How to replace work scaffolding

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140220

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150127

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150129

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150305

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150728

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150810

R150 Certificate of patent or registration of utility model

Ref document number: 5799547

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees