JP5571708B2 - How to replace the main rope of the elevator - Google Patents

How to replace the main rope of the elevator Download PDF

Info

Publication number
JP5571708B2
JP5571708B2 JP2012014167A JP2012014167A JP5571708B2 JP 5571708 B2 JP5571708 B2 JP 5571708B2 JP 2012014167 A JP2012014167 A JP 2012014167A JP 2012014167 A JP2012014167 A JP 2012014167A JP 5571708 B2 JP5571708 B2 JP 5571708B2
Authority
JP
Japan
Prior art keywords
main rope
rope
hoistway
old
bar member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012014167A
Other languages
Japanese (ja)
Other versions
JP2013151365A (en
Inventor
昌仁 佐度
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP2012014167A priority Critical patent/JP5571708B2/en
Priority to CN201310032226.5A priority patent/CN103224180B/en
Publication of JP2013151365A publication Critical patent/JP2013151365A/en
Priority to HK14100914.7A priority patent/HK1187880A1/en
Application granted granted Critical
Publication of JP5571708B2 publication Critical patent/JP5571708B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、交換対象の旧主ロープを新規交換用の新主ロープに交換する主ロープ交換方法に関する。   The present invention relates to a main rope exchanging method for exchanging an old main rope to be exchanged with a new main rope for new exchange.

図6は従来技術のエレベータの主ロープ交換方法を説明する図である。   FIG. 6 is a diagram illustrating a conventional elevator main rope replacement method.

一般的に、エレベータは、図6に示すように昇降路100と、この昇降路100の上部に設けられた機械室101と、この機械室101に設けられたマシンビーム102とを備えている。そして、エレベータは、昇降路100に設けられた乗かご27と、この乗かご27に対して相対的に昇降する釣合い錘20と、これらの乗かご27と釣合い錘20を昇降路100内で懸架する後述の主ロープと、釣合い錘20を案内する一対のガイドレール21a,21bとを備えている。   In general, as shown in FIG. 6, an elevator includes a hoistway 100, a machine room 101 provided on the upper part of the hoistway 100, and a machine beam 102 provided in the machine room 101. The elevator suspends the car 27 provided in the hoistway 100, the counterweight 20 that moves up and down relatively with respect to the car 27, and the car 27 and the counterweight 20 in the hoistway 100. And a pair of guide rails 21 a and 21 b for guiding the counterweight 20.

機械室101は、マシンビーム102に載置されたトラクションマシン(図示せず)と、電力が供給されて回転する巻上機26と、この巻上機26の近傍に配置され、回動可能に設けられたビームプーリ25とを有している。一方、乗かご27は上部に回動可能に設けられたプーリ28を有し、同様に釣合い錘20も上部に回動可能に設けられたプーリ24を有している。そして、主ロープは、釣合い錘20の上部のプーリ24、機械室101のビームプーリ25、巻上機26、及び乗かご27のプーリ28に巻き掛けられると共に、両端がロープソケット23,29にそれぞれ取付けられている。   The machine room 101 is disposed in the vicinity of a traction machine (not shown) placed on the machine beam 102, a hoisting machine 26 that is powered by electric power, and the hoisting machine 26, and is rotatable. And a beam pulley 25 provided. On the other hand, the car 27 has a pulley 28 provided at the upper part so as to be rotatable. Similarly, the counterweight 20 also has a pulley 24 provided at the upper part so as to be rotatable. The main rope is wound around the pulley 24 at the upper part of the counterweight 20, the beam pulley 25 in the machine room 101, the hoist 26 and the pulley 28 of the car 27, and both ends are attached to the rope sockets 23 and 29, respectively. It has been.

このように、乗かご27と釣合い錘20を円滑に昇降させるために昇降路100に布設された主ロープは、長期間に渡って使用されることによって伸びが発生したり、あるいは損傷するので、既設されている交換対象の旧主ロープ4a,4bを新規交換用の新主ロープ1に交換する必要があり、この主ロープの交換作業に多大な労力や時間がかかることが問題となっていた。従って、旧主ロープ4a,4bを新主ロープ1に交換する際には、従来より作業を容易に行えるように種々の装置が昇降路100内に設けられる。   As described above, the main rope laid in the hoistway 100 for smoothly raising and lowering the passenger car 27 and the counterweight 20 may cause elongation or damage due to use over a long period of time. It is necessary to replace the existing old main ropes 4a and 4b to be replaced with the new main rope 1 for new replacement, and it takes a lot of labor and time to replace the main rope. . Accordingly, when the old main ropes 4a and 4b are replaced with the new main rope 1, various devices are provided in the hoistway 100 so that the work can be easily performed.

例えば、昇降路100のピット104に設置された釣合い錘20の上方で機械室101側からU字状に垂下される新主ロープ1の下隅部、すなわちU字状垂下部分1aにこの新主ロープ1を巻き掛けた状態で装着される一対の金車2a,2bと、これらの金車2a,2bからそれぞれ下方へ突設された一対の連結部材(図示せず)と、釣合い錘20用の一対のガイドレール21a,21bの間に介設されて一対の連結部材に連結される横バー部材60と、この横バー部材60の両端部に固設されてガイドレール21a,21bに摺動自在に装着される案内部材7a,7bとを備えた2:1ローピングエレベータの主ロープ交換治具が従来技術の1つとして提案されている(例えば、特許文献1参照)。   For example, the new main rope 1 is provided at the lower corner of the new main rope 1 that is suspended in a U shape from the machine room 101 side above the counterweight 20 installed in the pit 104 of the hoistway 100, that is, at the U-shaped hanging portion 1a. A pair of gold wheels 2a and 2b mounted in a state where 1 is wound, a pair of connecting members (not shown) projecting downward from the gold wheels 2a and 2b, and a counterweight 20 A horizontal bar member 60 interposed between the pair of guide rails 21a and 21b and connected to the pair of connecting members, and fixed to both ends of the horizontal bar member 60 and slidable on the guide rails 21a and 21b. A main rope exchanging jig for a 2: 1 roping elevator provided with guide members 7a and 7b attached to the vehicle has been proposed as one of the prior arts (see, for example, Patent Document 1).

次に、この従来技術の主ロープ交換治具を用いた主ロープ交換方法を図6に基づいて説明する。   Next, a main rope replacement method using the conventional main rope replacement jig will be described with reference to FIG.

まず、図6に示すように釣合い錘20を昇降路100のピット104に配置した釣合い錘20の支持部材105により支持固定すると共に、乗かご27を機械室101のマシンビーム102に設置したチェーンブロック32bの鎖を介して最上階の階床103a付近に懸下して固定した後、既設された旧主ロープ4a,4bを切断除去する。次に、新規交換用の新主ロープ1が巻かれたロープ送出リール37を最上階の階床103aに設置し、このロープ送出リール37から順次繰り出した新主ロープ1を乗かご27のプーリ28、機械室101の巻上機26、及びビームプーリ25に巻き掛けて機械室101内に導入する。   First, as shown in FIG. 6, the counterweight 20 is supported and fixed by the support member 105 of the counterweight 20 disposed in the pit 104 of the hoistway 100, and the cage 27 is installed on the machine beam 102 of the machine room 101. After hanging and fixing near the uppermost floor 103a through the chain 32b, the existing old main ropes 4a and 4b are cut and removed. Next, the rope sending reel 37 around which the new main rope 1 for replacement is wound is installed on the uppermost floor 103a, and the new main rope 1 fed out from the rope sending reel 37 sequentially is pulled by the pulley 28 of the car 27. Then, it is wound around the hoisting machine 26 of the machine room 101 and the beam pulley 25 and introduced into the machine room 101.

そして、機械室101内に導入された新主ロープ1の先端部をロープソケット23,29のうち釣合い錘20側のロープソケット23に固定することにより、新主ロープ1のうち昇降路100の釣合い錘20側の部分が釣合い錘20の上方で機械室101側からU字状に垂下するので、このU字状垂下部分1aの下方に従来技術の主ロープ交換治具50を取付ける。すなわち、新主ロープ1のU字状垂下部分1aの下隅部にそれぞれ金車2a,2bを装着した後、横バー部材60を釣合い錘20側のガイドレール21a,21bの間に案内部材7a,7bを介して設置し、各金車2a,2bと横バー部材60とを一体化する。   Then, by fixing the tip of the new main rope 1 introduced into the machine room 101 to the rope socket 23 on the counterweight 20 side of the rope sockets 23 and 29, the balance of the hoistway 100 of the new main rope 1 is achieved. Since the portion on the weight 20 side hangs down in a U shape from the machine room 101 side above the counterweight 20, the main rope exchanging jig 50 of the prior art is attached below the U-shaped suspending portion 1a. That is, after attaching the gold wheels 2a and 2b to the lower corners of the U-shaped hanging portion 1a of the new main rope 1, the horizontal bar member 60 is placed between the guide rails 21a and 21b on the counterweight 20 side, the guide members 7a, It installs via 7b, and each gold wheel 2a, 2b and the horizontal bar member 60 are integrated.

このようにして、新主ロープ1のU字状垂下部分1aの下方に従来技術の主ロープ交換治具50を取付けると、この主ロープ交換治具50の自重によってU字状垂下部分1aはガイドレール21a,21bに案内されて徐々に下降していくので、U字状垂下部分1aが釣合い錘20のプーリ24の近傍まで下降する。そして、金車2a,2bから新主ロープ1を離脱させ、U字状垂下部分1aを釣合い錘20のプーリ24に巻回させる。   When the conventional main rope replacement jig 50 is attached below the U-shaped hanging portion 1a of the new main rope 1, the U-shaped hanging portion 1a is guided by its own weight. Since it descends gradually as it is guided by the rails 21 a and 21 b, the U-shaped hanging part 1 a descends to the vicinity of the pulley 24 of the counterweight 20. Then, the new main rope 1 is detached from the gold wheels 2 a and 2 b, and the U-shaped hanging portion 1 a is wound around the pulley 24 of the counterweight 20.

次に、新主ロープ1の両端のうち乗かご27側の一端を乗かご27のプーリ28に巻回させた後、この一端をロープソケット23,29のうち乗かご27側のロープソケット29に固定することにより、旧主ロープ4a,4bを取り外して新主ロープ1を布設する主ロープの交換作業が終了する。そして、従来技術の主ロープ交換治具50を分解して釣合い錘20側のガイドレール21a,21bから取外し、この主ロープ交換治具50を最上階の階床103a付近まで移送し、上述した交換作業の手順を既設されている残りの全ての旧主ロープに対して同様に実施する。   Next, after one end of the new main rope 1 on the side of the car 27 is wound around the pulley 28 of the car 27, the one end is connected to the rope socket 29 on the side of the car 27 of the rope sockets 23 and 29. By fixing, the replacement work of the main rope for removing the old main ropes 4a and 4b and laying the new main rope 1 is completed. Then, the main rope exchanging jig 50 of the prior art is disassembled and removed from the guide rails 21a and 21b on the counterweight 20, the main rope exchanging jig 50 is transferred to the vicinity of the uppermost floor 103a, and the above-described exchanging is performed. Repeat the same procedure for all remaining old main ropes.

特開平10−167612号公報Japanese Patent Laid-Open No. 10-167612

このように、上述した特許文献1に開示された従来技術の2:1ローピングエレベータの主ロープ交換治具50を用いた主ロープ交換方法は、既設されている旧主ロープ4a,4bを切断して回収する回収作業を行った後に、新規交換用の新主ロープ1を布設する布設作業を行うようにしているので、これらの旧主ロープ4a,4bの回収作業及び新主ロープ1の布設作業の2つの作業を同時に行うことができず、主ロープの交換作業を開始してから終了するまでに多大な時間がかかることが問題となっている。   Thus, the main rope exchanging method using the main rope exchanging jig 50 of the conventional 2: 1 roping elevator disclosed in Patent Document 1 described above is to cut the existing old main ropes 4a and 4b. After the recovery work to be recovered, the installation work of laying the new main rope 1 for replacement is performed, so the recovery work of these old main ropes 4a and 4b and the installation work of the new main rope 1 are performed. These two operations cannot be performed at the same time, and it takes a long time to start and end the main rope replacement operation.

また、従来技術の2:1ローピングエレベータの主ロープ交換治具50を用いた主ロープ交換方法では、旧主ロープ4a,4bを切断した際に、作業状況によって切断された旧主ロープ4a,4bが昇降路100のピット104上に落下したり、あるいは散逸することにより、旧主ロープ4a,4bが昇降路100内の機器に引っ掛かって絡まる虞がある。この場合、最下階の階床103bにいる作業者36が旧主ロープ4a,4bをロープ回収リール38に回収する際に、上手く回収することができなくなるので、その分余計に時間がかかることが懸念されている。   In the main rope exchanging method using the main rope exchanging jig 50 of the conventional 2: 1 roping elevator, when the old main ropes 4a and 4b are cut, the old main ropes 4a and 4b which are cut depending on the work situation. May fall on the pit 104 of the hoistway 100 or dissipate, the old main ropes 4a and 4b may be caught by the equipment in the hoistway 100 and become entangled. In this case, when the worker 36 on the lowermost floor 103b recovers the old main ropes 4a and 4b to the rope recovery reel 38, it cannot be recovered well, and accordingly, extra time is required. There are concerns.

さらに、従来技術の2:1ローピングエレベータの主ロープ交換治具50を用いた主ロープ交換方法は、昇降路100の上部から釣合い錘20のプーリ24まで下降する際に、新主ロープ1に対してU字状垂下部分1aにねじれやたわみが生じない程度の大きさの張力を与える必要がある。上述した主ロープ交換方法は、自重を重くすることによって新主ロープ1に上記大きさの張力を与えるようにしているので、現場への運搬作業及び設置作業を含む主ロープの交換作業にかかる作業者の負担が増大する虞がある。   Furthermore, the main rope exchanging method using the main rope exchanging jig 50 of the 2: 1 roping elevator of the prior art is such that when the descent from the upper part of the hoistway 100 to the pulley 24 of the counterweight 20, Thus, it is necessary to apply a tension of such a magnitude that the U-shaped hanging portion 1a does not twist or bend. The above-described main rope replacement method applies the above-mentioned tension to the new main rope 1 by increasing its own weight, so that the work related to the main rope replacement work including transportation work and installation work to the site is performed. There is a risk that the burden on the person will increase.

本発明は、このような従来技術の実情からなされたもので、その目的は、主ロープの交換作業を迅速に行うと共に、主ロープの交換作業にかかる作業者の負担を軽減することができるエレベータの主ロープ交換方法を提供することにある。   The present invention has been made based on such a situation of the prior art, and an object of the present invention is to provide an elevator capable of quickly performing a main rope replacement operation and reducing a burden on an operator involved in the main rope replacement operation. The main rope replacement method is to provide.

上記の目的を達成するために、本発明のエレベータの主ロープ交換方法は、昇降路に設けられた乗かごと、この乗かごと主ロープを介して吊り下げられる釣合い錘と、この釣合い錘を案内する一対のガイドレールと、前記昇降路の上部に設けられた機械室とを含むエレベータに適用され、前記一対のガイドレール間に介設されて前記釣合い錘の上方に配置される横バー部材と、この横バー部材の両端部に固設され、前記一対のガイドレールに摺動自在に装着される案内部材と、前記横バー部材に新規交換用の新主ロープを巻き掛けた状態で装着される金車と、前記横バー部材に設けられ、前記昇降路の頂部に位置する部分で分断して前記昇降路の下部の前記釣合い錘側へ垂下される交換対象の旧主ロープの上端を接続するロープ接続手段とを備えたエレベータの主ロープ交換治具を用いて前記旧主ロープを前記新主ロープに交換するエレベータの主ロープ交換方法であって、前記機械室から前記新主ロープを垂下させて前記金車に装着する装着工程と、前記旧主ロープを前記昇降路の頂部に位置する部分で分断し、分断した前記旧主ロープのうち前記昇降路の下部の前記釣合い錘側へ垂下される部分の上端を前記ロープ接続手段に接続する接続工程と、前記横バー部材を下方に移動させる移動工程とを含むことを特徴としている。 In order to achieve the above object, the elevator main rope replacement method according to the present invention includes a car cage provided in a hoistway, a counterweight suspended via the main rope and the carpool, and the counterweight. A horizontal bar member that is applied to an elevator including a pair of guide rails to be guided and a machine room provided at an upper portion of the hoistway, and is disposed between the pair of guide rails and disposed above the counterweight. And a guide member fixed to both ends of the horizontal bar member and slidably mounted on the pair of guide rails, and a new main rope for replacement being wound around the horizontal bar member. And the upper end of the old main rope to be exchanged, which is provided on the horizontal bar member and is divided at the portion located at the top of the hoistway and is suspended to the counterweight side at the lower part of the hoistway. Rope connection means to connect A method of exchanging the old main rope with the new main rope using an elevator main rope exchanging jig, wherein the new main rope is suspended from the machine room and attached to the gold wheel. An attaching step to divide the old main rope at a portion located at the top of the hoistway, and an upper end of a portion of the divided old main rope that hangs down to the counterweight side of the lower part of the hoistway. It includes a connecting step of connecting to the rope connecting means and a moving step of moving the horizontal bar member downward.

このように構成した本発明は、交換対象の旧主ロープを新規交換用の新主ロープに交換するときには、装着工程において新主ロープを金車に巻き掛け、この状態で金車を各ガイドレール間に介設された横バー部材に取付けると共に、接続工程において旧主ロープを昇降路の頂部に位置する部分で分断し、分断した旧主ロープのうち昇降路の下部の釣合い錘側へ垂下される部分の上端を、横バー部材に設けられたロープ接続手段に接続する。そして、移動工程において横バー部材を新主ロープ及び旧主ロープを保持したまま案内部材でガイドレールに沿って下降させることにより、新主ロープを昇降路内に繰り出すと共に、旧主ロープを昇降路の下部から回収することができる。このように、旧主ロープの回収作業及び新主ロープの布設作業の2つの作業を同時に行うことができるので、主ロープの交換作業を効率良く行うことができる。 In the present invention configured as described above, when replacing the old main rope to be replaced with a new main rope for replacement, the new main rope is wound around the gold wheel in the mounting process, and the gold wheel is moved to each guide rail in this state. It is attached to the horizontal bar member interposed between them, and the old main rope is divided at the top part of the hoistway in the connection process, and the divided old main rope is suspended to the counterweight side at the lower part of the hoistway. The upper end of the portion to be connected is connected to the rope connecting means provided on the horizontal bar member. In the moving process, the horizontal bar member is lowered along the guide rail with the guide member while holding the new main rope and the old main rope, so that the new main rope is fed into the hoistway and the old main rope is moved to the hoistway. It can be recovered from the lower part. Thus, since the two operations of collecting the old main rope and laying the new main rope can be performed at the same time, the replacement operation of the main rope can be performed efficiently.

また、上述したように移動工程において、昇降路の頂部に位置する部分で分断して昇降路の下部の釣合い錘側へ垂下される旧主ロープは横バー部材が下降して昇降路の下部に到達するまでこの横バー部材に保持されているので、昇降路の下部で待機する作業者が旧主ロープをロープ接続手段から取り外すことにより、旧主ロープを昇降路内の機器に絡ませることなく容易に回収することができる。これにより、旧主ロープの回収作業を円滑に行うことができるので、主ロープの交換作業に費やす時間を削減することができる。 In addition, as described above, in the moving process, the old main rope that is divided at the portion located at the top of the hoistway and hangs down to the counterweight side of the lower part of the hoistway lowers the horizontal bar member and moves to the lower part of the hoistway. Since it is held by this horizontal bar member until it reaches, the worker waiting at the lower part of the hoistway removes the old main rope from the rope connection means, so that the old main rope is not entangled with the equipment in the hoistway It can be easily recovered. Thereby, since the collection | recovery operation | work of an old main rope can be performed smoothly, the time spent for the replacement | exchange operation | work of a main rope can be reduced.

さらに、本発明は接続工程において旧主ロープを昇降路の頂部に位置する部分で分断し、分断した旧主ロープのうち昇降路の下部の釣合い錘側へ垂下される部分の上端をロープ接続手段に接続することにより、横バー部材にかかる旧主ロープの荷重を利用して新主ロープに張力を与えるようにしているので、その分各部材を軽くすることができる。これにより、作業者は使用される各部材を昇降路内に持ち運び易くなるので、各部材を容易に組立てたり、分解することができる。このように、主ロープの交換作業を迅速に行うと共に、主ロープの交換作業にかかる作業者の負担を軽減することができる。 Furthermore, the present invention divides the old main rope at the portion located at the top of the hoistway in the connecting step, and the upper end of the portion of the divided old main rope that hangs down to the counterweight side at the lower part of the hoistway is rope connecting means. Since the tension is applied to the new main rope using the load of the old main rope applied to the horizontal bar member, each member can be lightened by that amount. Thereby, since it becomes easy for an operator to carry each member used in a hoistway, each member can be easily assembled or disassembled. As described above, the replacement work of the main rope can be quickly performed, and the burden on the operator related to the replacement work of the main rope can be reduced.

また、本発明に係るエレベータの主ロープ交換方法は、前記発明において、前記主ロープ交換治具は、前記昇降路の頂部に設けられ、前記横バー部材を吊り下げるホイストを備え、前記移動工程は、前記主ロープ交換治具の前記ホイストによって前記横バー部材を下降させることを特徴としている。このように構成すると、横バー部材にかかる旧主ロープの荷重をホイストと新主ロープで分担することができるので、ホイストは旧主ロープの全荷重を保持するのに必要な性能を持つ必要がなくなり、ホイストの計量化を図ることができる。   Further, in the elevator main rope replacement method according to the present invention, in the above invention, the main rope replacement jig is provided at the top of the hoistway, and includes a hoist that suspends the horizontal bar member, and the moving step includes The horizontal bar member is lowered by the hoist of the main rope replacement jig. When configured in this way, the load of the old main rope on the horizontal bar member can be shared by the hoist and the new main rope, so the hoist needs to have the performance necessary to hold the entire load of the old main rope. The hoist can be measured.

また、本発明に係るエレベータの主ロープ交換方法は、前記発明において、前記移動工程が行われた後、前記主ロープ交換治具の前記ホイストによって前記横バー部材を上昇させる上昇工程を含むことを特徴としている。このように構成すると、ホイストによって横バー部材の昇降動作を制御できるので、移動工程において昇降路の下部に移動した横バー部材を上昇工程においてホイストで上昇させることにより、横バー部材を昇降路の上部へ再度戻すことができる。これにより、既設されている旧主ロープの残りを回収する際に、主ロープ交換治具を分解して再び組立てる必要がなくなるので、主ロープの交換作業の効率を高めることができる。   In addition, the elevator main rope replacement method according to the present invention includes, in the above invention, an ascending step of raising the horizontal bar member by the hoist of the main rope exchanging jig after the moving step is performed. It is a feature. If comprised in this way, since the raising / lowering operation | movement of a horizontal bar member can be controlled by a hoist, the horizontal bar member which moved to the lower part of the hoistway in the movement process is raised with a hoist in the raising process, and thereby the horizontal bar member is moved to the hoistway. It can be returned to the top again. This eliminates the need for disassembling and reassembling the main rope exchanging jig when collecting the remaining of the existing old main rope, thereby improving the efficiency of exchanging the main rope.

本発明のエレベータの主ロープ交換方法によれば、装着工程において新主ロープを金車で横バー部材に取付けると共に、接続工程において旧主ロープを昇降路の頂部に位置する部分で分断し、分断した旧主ロープのうち昇降路の下部の釣合い錘側へ垂下される部分の上端を、横バー部材に設けられたロープ接続手段に接続し、移動工程において横バー部材を案内部材でガイドレールに沿って下降させることにより、旧主ロープの回収作業と新主ロープの布設作業の2つの作業を同時に行うことができる。特に、移動工程において、昇降路の頂部に位置する部分で分断して昇降路の下部の釣合い錘側へ垂下される旧主ロープは下降中に横バー部材に保持されているので、昇降路の下部で旧主ロープを取外して容易に回収することができる。また、昇降路の頂部に位置する部分で分断して昇降路の下部の釣合い錘側へ垂下される旧主ロープの荷重を利用して横バー部材を下降させることができるので、各部材を軽くすることができる。このように、主ロープの交換作業を迅速に行うと共に、主ロープの交換作業にかかる作業者の負担を軽減することができ、従来よりも高い作業性を確保することができる。 According to the elevator main rope replacement method of the present invention, the new main rope is attached to the horizontal bar member with a gold wheel in the mounting process, and the old main rope is divided at the top portion of the hoistway in the connection process, and divided. The upper end of the part of the old main rope that is suspended to the counterweight side at the lower part of the hoistway is connected to the rope connecting means provided on the horizontal bar member, and the horizontal bar member is used as a guide rail by the guide member in the moving process. By lowering along, it is possible to simultaneously perform two operations of collecting the old main rope and laying the new main rope. In particular, in the moving process, the old main rope that is divided at the portion located at the top of the hoistway and hangs down to the counterweight side at the lower part of the hoistway is held by the horizontal bar member during the descent. It can be easily recovered by removing the old main rope at the bottom. In addition, the horizontal bar member can be lowered using the load of the old main rope that is divided at the top part of the hoistway and hangs down to the counterweight side at the lower part of the hoistway. can do. In this way, the main rope replacement work can be performed quickly, and the burden on the operator involved in the main rope replacement work can be reduced, and higher workability than before can be ensured.

本発明に係るエレベータの主ロープ交換方法の一実施形態の構成を説明するフローチャートである。It is a flowchart explaining the structure of one Embodiment of the main rope replacement | exchange method of the elevator which concerns on this invention. 本発明に係るエレベータの主ロープ交換方法の一実施形態に用いられる主ロープ交換治具の構成を示す図である。It is a figure showing composition of a main rope exchanging jig used for one embodiment of a main rope exchanging method of an elevator concerning the present invention. 本発明に係るエレベータの主ロープ交換方法の一実施形態が適用される2:1ローピングエレベータの構成を示す図である。It is a figure which shows the structure of 2: 1 roping elevator to which one Embodiment of the main rope replacement | exchange method of the elevator which concerns on this invention is applied. 本発明に係るエレベータの主ロープ交換方法の一実施形態を説明する図であり、装着工程及び接続工程を説明する図である。It is a figure explaining one Embodiment of the main rope replacement | exchange method of the elevator which concerns on this invention, and is a figure explaining a mounting process and a connection process. 本発明に係るエレベータの主ロープ交換方法の一実施形態を説明する図であり、移動工程を説明する図である。It is a figure explaining one Embodiment of the main rope replacement | exchange method of the elevator which concerns on this invention, and is a figure explaining a movement process. 従来技術のエレベータの主ロープ交換治具を用いて主ロープを交換する作業を説明する図である。It is a figure explaining the operation | work which replaces | exchanges a main rope using the main rope replacement jig of the elevator of a prior art.

以下、本発明に係るエレベータの主ロープ交換方法を実施するための形態を図に基づいて説明する。なお、上述した従来技術の説明と重複する部分には同一の符号を付している。   EMBODIMENT OF THE INVENTION Hereinafter, the form for implementing the main rope replacement | exchange method of the elevator which concerns on this invention is demonstrated based on figures. In addition, the same code | symbol is attached | subjected to the part which overlaps with description of the prior art mentioned above.

本発明に係るエレベータの主ロープ交換方法の一実施形態が適用されるエレベータは、例えば図3に示すように昇降路100に設けられ、各階床に停止する乗かご27と、この乗かご27と主ロープ4を介して吊り下げられる釣合い錘20と、この釣合い錘20を案内する一対のガイドレール21a,21bとを含んでいる。なお、本実施形態では、このエレベータは2:1ローピングエレベータから成っており、後述するように本実施形態を使用した主ロープ交換作業は各階床のうち最上階の階床103aと最下階の階床103bで主に行われる。また、主ロープ4は複数本布設されている。   An elevator to which one embodiment of the elevator main rope replacement method according to the present invention is applied is provided in a hoistway 100 as shown in FIG. 3, for example, and a car 27 that stops on each floor, A counterweight 20 suspended via the main rope 4 and a pair of guide rails 21a and 21b for guiding the counterweight 20 are included. In this embodiment, this elevator is composed of a 2: 1 roping elevator. As will be described later, main rope replacement work using this embodiment is performed on the upper floor 103a and the lower floor among the floors. It is mainly performed on the floor 103b. A plurality of main ropes 4 are laid.

昇降路100は、上部に設けられた機械室101と、この機械室101に設けられたマシンビーム102と、後述する支持部材105が取付けられるピット104とを備えている。また、機械室101は、マシンビーム102に載置されたトラクションマシン(図示せず)と、電力が供給されて回転する巻上機26と、この巻上機26の近傍に配置され、回動可能に設けられたビームプーリ25と、マシンビーム102に主ロープ4の両端をロープソケット23,29を介して固定するロープエンド22,30とを有している。   The hoistway 100 includes a machine room 101 provided in an upper part, a machine beam 102 provided in the machine room 101, and a pit 104 to which a support member 105 described later is attached. Further, the machine room 101 is disposed near the hoisting machine 26, a traction machine (not shown) placed on the machine beam 102, a hoisting machine 26 that rotates when supplied with electric power, and rotates. A beam pulley 25 is provided, and rope ends 22 and 30 for fixing both ends of the main rope 4 to the machine beam 102 via rope sockets 23 and 29 are provided.

一方、乗かご27は上部に回動可能に設けられたプーリ28を有し、同様に釣合い錘20も上部に回動可能に設けられたプーリ24を有している。そして、主ロープ4は、釣合い錘20の上部のプーリ24、機械室101のビームプーリ25、巻上機26、及び乗かご27のプーリ28に巻き掛けられると共に、両端がロープソケット23,29にそれぞれ取付けられている。   On the other hand, the car 27 has a pulley 28 provided at the upper part so as to be rotatable. Similarly, the counterweight 20 also has a pulley 24 provided at the upper part so as to be rotatable. The main rope 4 is wound around the pulley 24 at the upper part of the counterweight 20, the beam pulley 25 in the machine room 101, the hoisting machine 26, and the pulley 28 of the car 27, and both ends are respectively attached to the rope sockets 23 and 29. Installed.

なお、本実施形態では、図3に示すように旧主ロープ4のうちロープソケット23から釣合い錘20のプーリ24に巻き掛けられた中央までの部分を旧主ロープ4a、旧主ロープ4のうち釣合い錘20のプーリ24に巻き掛けられた中央から昇降路100の頂部までの部分を旧主ロープ4b、旧主ロープ4のうち昇降路100の頂部からロープソケット29までの部分を旧主ロープ4cと便宜的に呼ぶことにする。   In the present embodiment, as shown in FIG. 3, the portion of the old main rope 4 from the rope socket 23 to the center wound around the pulley 24 of the counterweight 20 is the old main rope 4 a and the old main rope 4. The part from the center wound around the pulley 24 of the counterweight 20 to the top of the hoistway 100 is the old main rope 4b, and the part of the old main rope 4 from the top of the hoistway 100 to the rope socket 29 is the old main rope 4c. For convenience.

本実施形態において交換対象の旧主ロープ4を新規交換用の新主ロープ1に交換するのに用いられる主ロープ交換治具11は、図2に示すように一対のガイドレール21a,21b間に介設され、釣合い錘20の上方に配置される横バー部材6と、この横バー部材6の両端部に固設され、一対のガイドレール21a,21bに摺動自在に装着される案内部材7a,7bと、横バー部材6に新主ロープ1を巻き掛けた状態で装着される一対の金車2a,2bと、横バー部材6に設けられ、旧主ロープ4a,4bを接続する後述のロープ接続手段5a,5bとを備えている。   In the present embodiment, the main rope exchanging jig 11 used for exchanging the old main rope 4 to be exchanged with the new main rope 1 for new exchange is formed between a pair of guide rails 21a and 21b as shown in FIG. A horizontal bar member 6 interposed and disposed above the counterweight 20, and a guide member 7a fixed to both ends of the horizontal bar member 6 and slidably mounted on the pair of guide rails 21a and 21b. , 7b, a pair of gold wheels 2a, 2b mounted in a state in which the new main rope 1 is wound around the horizontal bar member 6, and a horizontal bar member 6, which will be described later for connecting the old main ropes 4a, 4b. Rope connection means 5a and 5b are provided.

具体的には、横バー部材6は、例えば断面L字型にそれぞれ形成された一対の単体バー6a,6bから構成され、これらの単体バー6a,6bが相対的にスライド可能に重ね合わせて設けられるようになっている。すなわち、各単体バー6a,6bの一片の両端のうち一端部分には、一対の長穴9a,9bが設けられ、各単体バー6a,6bの他端に案内部材7a,7bが設けられている。   Specifically, the horizontal bar member 6 is composed of, for example, a pair of single bars 6a and 6b each having an L-shaped cross section, and the single bars 6a and 6b are provided so as to be relatively slidable. It is supposed to be. That is, a pair of elongated holes 9a and 9b are provided at one end of one end of each single bar 6a and 6b, and guide members 7a and 7b are provided at the other end of each single bar 6a and 6b. .

そして、単体バー6aが上側、単体バー6bが下側になるように各単体バー6a,6bの片のうち長穴9a,9bが設けられている片同士を重ね合わせ、これらの単体バー6a,6bの長穴9a,9bにボルト8a1,8b1を平座金8a2,8b2を介して挿通し、ボルト8a1,8b1を平座金8a3,8b3及びばね座金8a4,8b4を介してナット8a5,8b5で締結している。   Then, the single bars 6a, 6b are overlapped with each other so that the single bar 6a is on the upper side and the single bar 6b is on the lower side. Bolts 8a1 and 8b1 are inserted into the long holes 9a and 9b of 6b through plain washers 8a2 and 8b2, and the bolts 8a1 and 8b1 are fastened with nuts 8a5 and 8b5 through plain washers 8a3 and 8b3 and spring washers 8a4 and 8b4. ing.

従って、横バー部材6は、各単体バー6a,6bの長穴9a,9bに取付けたボルト8a1,8b1をナット8a5,8b5で完全に締結する前にボルト8a1,8b1を長穴9a,9bに遊挿させた状態で、単体バー6a,6bを長手方向に沿ってスライドさせることにより、全長が調整可能になっている。なお、各単体バー6a,6bに設けられた長穴9aと長穴9bは横バー部材6の中央の垂線Lに対して対称になっている。   Accordingly, the horizontal bar member 6 has the bolts 8a1 and 8b1 attached to the long holes 9a and 9b before the bolts 8a1 and 8b1 attached to the long holes 9a and 9b of the single bars 6a and 6b are completely fastened with the nuts 8a5 and 8b5. The full length can be adjusted by sliding the single bars 6a and 6b along the longitudinal direction in the loosely inserted state. The elongated holes 9 a and the elongated holes 9 b provided in the individual bars 6 a and 6 b are symmetric with respect to the vertical line L at the center of the horizontal bar member 6.

また、横バー部材6は、各単体バー6a,6bの片の上面のうち長穴9a,9bの両側に設けられ、上方へ向けて突起した一対の突起部3a,3bを有しており、これらの突起部3a,3bは中央の垂線Lに対して対称となるように配置されている。上述した一対の金車2a,2bは、機械室101側からU字状に垂下される新主ロープ1の下隅部、すなわちU字状垂下部分1aが摺接した状態でこれらの突起部3a,3bに係合し、側面部を取外すことによって新主ロープ1の着脱が可能になっている。   Further, the horizontal bar member 6 has a pair of projecting portions 3a and 3b provided on both sides of the long holes 9a and 9b on the upper surface of the single bar 6a and 6b, and projecting upward. These protrusions 3a and 3b are arranged so as to be symmetric with respect to the central vertical line L. The pair of gold wheels 2a and 2b described above has the protrusions 3a and 2b in a state in which the lower corner portion of the new main rope 1 suspended in a U shape from the machine room 101 side, that is, the U-shaped hanging portion 1a is in sliding contact. The new main rope 1 can be attached and detached by engaging with 3b and removing the side surface.

ロープ接続手段5a,5bは、各単体バー6a,6bの片のうち突起部3a,3bと案内部材7a,7bとの間に設けられた一対の貫通孔5a1,5b1と、各貫通孔5a1,5b1に挿通され、先端に雄螺子を形成して他端に旧主ロープ4a,4bを連結する一対のロープ接続部、例えばアイボルト5a2,5b2と、各アイボルト5a2,5b2に介装される平座金5a3,5b3及びばね座金5a4,5b4と、各アイボルト5a2,5b2の雄螺子に螺合するナット5a5,5b5とから成っている。なお、貫通孔5a1,5b1は、横バー部材6の中央の垂線Lに対して対称になっている。   The rope connecting means 5a, 5b includes a pair of through-holes 5a1, 5b1 provided between the protrusions 3a, 3b and the guide members 7a, 7b of the single bar 6a, 6b, and the through-holes 5a1, 5b1, respectively. 5b1, a pair of rope connecting portions that form a male screw at the tip and connect the old main ropes 4a and 4b to the other end, for example, eyebolts 5a2 and 5b2, and a plain washer interposed between the eyebolts 5a2 and 5b2. 5a3, 5b3 and spring washers 5a4, 5b4, and nuts 5a5, 5b5 screwed into male screws of the eyebolts 5a2, 5b2. The through holes 5a1 and 5b1 are symmetric with respect to the vertical line L at the center of the horizontal bar member 6.

主ロープ交換治具11は、図4に示すように昇降路100の頂部に設けられ、横バー部材6を吊り下げるホイスト31aを備えており、横バー部材6は、上側の単体バー6aの片のうち長穴9a,9bが設けられていない片にホイスト31aから繰り出されたホイストロープ31bが取付けられる取付穴10が設けられている。この取付穴10は、各単体バー6a,6bが水平に保たれるように横バー部材6の中央に配置されている。   As shown in FIG. 4, the main rope exchanging jig 11 is provided at the top of the hoistway 100 and includes a hoist 31a for suspending the horizontal bar member 6. The horizontal bar member 6 is a piece of the upper single bar 6a. The mounting hole 10 to which the hoist rope 31b drawn out from the hoist 31a is attached is provided in a piece in which the long holes 9a and 9b are not provided. The mounting hole 10 is disposed at the center of the horizontal bar member 6 so that the individual bars 6a and 6b are kept horizontal.

次に、本発明に係る主ロープ交換方法の一実施形態を図1のフローチャートに基づいて図4及び図5を参照しつつ詳細に説明する。   Next, an embodiment of the main rope replacement method according to the present invention will be described in detail with reference to FIGS. 4 and 5 based on the flowchart of FIG.

図1は本発明に係るエレベータの主ロープ交換方法の一実施形態の構成を説明するフローチャート、図4は本発明に係るエレベータの主ロープ交換方法の一実施形態を説明する図であり、装着工程及び接続工程を説明する図、図5は本発明に係るエレベータの主ロープ交換方法の一実施形態を説明する図であり、移動工程を説明する図である。   FIG. 1 is a flowchart for explaining a configuration of an embodiment of an elevator main rope replacement method according to the present invention. FIG. 4 is a diagram for explaining an embodiment of an elevator main rope replacement method according to the present invention. FIG. 5 is a diagram for explaining an embodiment of an elevator main rope replacement method according to the present invention, and is a diagram for explaining a moving process.

本発明に係るエレベータの主ロープ交換方法の一実施形態は、機械室101から新主ロープ1を垂下させて金車2a、2bに装着する装着工程と、旧主ロープ4a,4bをロープ接続手段5a,5bに接続する接続工程と、横バー部材6を下方に移動させる移動工程と、この移動工程が行われた後、主ロープ交換治具11のホイスト31aによって横バー部材6を上昇させる上昇工程とを含んでいる。本実施形態では、移動工程はホイスト31aによって横バー部材6を下降させ、上昇工程はホイスト31aによって横バー部材6を上昇させるようにしている。   One embodiment of the elevator main rope replacement method according to the present invention includes a step of hanging the new main rope 1 from the machine room 101 and mounting it on the gold wheels 2a and 2b, and a rope connecting means for connecting the old main ropes 4a and 4b. 5a, 5b connecting step, moving step for moving the horizontal bar member 6 downward, and raising the horizontal bar member 6 by the hoist 31a of the main rope exchanging jig 11 after this moving step is performed. Process. In this embodiment, the horizontal bar member 6 is lowered by the hoist 31a in the moving process, and the horizontal bar member 6 is raised by the hoist 31a in the moving process.

具体的には、図4に示すように、まず最下階の階床103bの作業者(図示せず)は昇降路100のピット104に釣合い錘20を支持する支持部材105を設置し、乗かご27上の作業者33は乗かご27を上昇運転して釣合い錘20を支持部材105まで下降させ、釣合い錘20を支持部材105に固定する。その後、乗かご27上の作業者33は、機械室101のマシンビーム102のうち乗かご27側に設けられたチェーンブロック32bの鎖で乗かご27をマシンビーム102に固定することにより、乗かご27が最上階の階床103aの近傍に懸架される(ステップ(以下、Sと記す)1)。   Specifically, as shown in FIG. 4, first, an operator (not shown) of the floor 103 b on the lowest floor installs a support member 105 that supports the counterweight 20 in the pit 104 of the hoistway 100, and An operator 33 on the car 27 raises the car 27 to lower the counterweight 20 to the support member 105, and fixes the counterweight 20 to the support member 105. Thereafter, the worker 33 on the car 27 fixes the car 27 to the machine beam 102 with a chain of chain blocks 32b provided on the car 27 side of the machine beam 102 in the machine room 101. 27 is suspended in the vicinity of the top floor 103a (step (hereinafter referred to as S) 1).

乗かご27上の作業者33は、上述した主ロープ交換治具11を釣合い錘20側のガイドレール21a,21b間に介設する。このとき、主ロープ交換治具11の横バー部材6の各単体バー6a,6bを長手方向に沿ってスライドさせることにより、主ロープ交換治具11がガイドレール21a,21b間に収まるように全長を適宜調整し、案内部材7a,7bをガイドレール21a,21bに係合させる。そして、機械室101のマシンビーム102に設置されたホイスト31aのホイストロープ31bを横バー部材6の取付穴10に取付ける(S2)。   The worker 33 on the car 27 interposes the main rope exchanging jig 11 described above between the guide rails 21a and 21b on the counterweight 20 side. At this time, the individual bar 6a, 6b of the horizontal bar member 6 of the main rope exchanging jig 11 is slid along the longitudinal direction so that the main rope exchanging jig 11 is placed between the guide rails 21a, 21b. The guide members 7a and 7b are engaged with the guide rails 21a and 21b. And the hoist rope 31b of the hoist 31a installed in the machine beam 102 of the machine room 101 is attached to the attachment hole 10 of the horizontal bar member 6 (S2).

次に、作業者33は、マシンビーム102のうち釣合い錘20側に設けられたチェーンブロック32aの鎖に旧主ロープ4aを接続し、旧主ロープ4aを釣合い錘20側のロープソケット23から取外す。次に、作業者33は、チェーンブロック32aを操作することにより、取外された旧主ロープ4aをロープ接続手段5aの近傍まで移動させる。   Next, the operator 33 connects the old main rope 4a to the chain of the chain block 32a provided on the counterweight 20 side of the machine beam 102, and removes the old main rope 4a from the rope socket 23 on the counterweight 20 side. . Next, the operator 33 moves the removed old main rope 4a to the vicinity of the rope connection means 5a by operating the chain block 32a.

次に、作業者33は、図2に示すように旧主ロープ4aの上端をアイボルト5a2に連結し、アイボルト5a2の両端のうち雄螺子が形成されている一端を単体バー6aの貫通孔5a1に下方から上方へ向けて挿通する。そして、作業者33は、アイボルト5a2の一端に平座金5a3及びばね座金5a4を介装してアイボルト5a2の雄螺子にナット5a5を螺合する。その後、作業者33は旧主ロープ4aからチェーンブロック32aの鎖を取外す(S3)。   Next, as shown in FIG. 2, the worker 33 connects the upper end of the old main rope 4a to the eyebolt 5a2, and one end of the eyebolt 5a2 on which the male screw is formed is connected to the through hole 5a1 of the single bar 6a. Insert from bottom to top. Then, the operator 33 inserts a flat washer 5a3 and a spring washer 5a4 at one end of the eyebolt 5a2, and screws the nut 5a5 into the male screw of the eyebolt 5a2. Thereafter, the worker 33 removes the chain of the chain block 32a from the old main rope 4a (S3).

次に、作業者33は、旧主ロープ4のうち旧主ロープ4b,4cをチェーンブロック32aの鎖に接続し、旧主ロープ4を昇降路100の頂部に位置する部分で切断することにより、旧主ロープ4bと旧主ロープ4cに分断する。そして、作業者33は、チェーンブロック32aを操作することにより、旧主ロープ4bをロープ接続手段5bの近傍まで移動させる。   Next, the worker 33 connects the old main ropes 4b and 4c of the old main rope 4 to the chain of the chain block 32a, and cuts the old main rope 4 at a portion located at the top of the hoistway 100. Divide into old main rope 4b and old main rope 4c. And the operator 33 moves the old main rope 4b to the vicinity of the rope connection means 5b by operating the chain block 32a.

次に、作業者33は、図2に示すように旧主ロープ4bの上端をアイボルト5b2に連結し、アイボルト5b2の両端のうち雄螺子が形成されている一端を単体バー6bの貫通孔5b1に下方から上方へ向けて挿通する。そして、作業者33は、アイボルト5b2の一端に平座金5b3及びばね座金5b4を介装してアイボルト5b2の雄螺子にナット5b5を螺合する。その後、作業者33は旧主ロープ4bからチェーンブロック32aの鎖を取外す(S4)。   Next, as shown in FIG. 2, the worker 33 connects the upper end of the old main rope 4b to the eyebolt 5b2, and one end of the eyebolt 5b2 where the male screw is formed is connected to the through hole 5b1 of the single bar 6b. Insert from bottom to top. Then, the operator 33 inserts a flat washer 5b3 and a spring washer 5b4 at one end of the eyebolt 5b2, and screws the nut 5b5 into the male screw of the eyebolt 5b2. Thereafter, the worker 33 removes the chain of the chain block 32a from the old main rope 4b (S4).

このとき、旧主ロープ4a,4bに付与されていた張力が解放されるので、各旧ロープ4a,4bは緩む状態になる。従って、最下階の階床103b上の作業者36は、釣合い錘20の高さとほぼ同じ高さに設定された作業台106を昇降路100の下部に設置し、この作業台106に上がって機械室101側からU字状に垂下される旧主ロープ4の下隅部、すなわちU字状垂下部分を釣合い錘20のプーリ24から取外す。そして、作業台106上の作業者36は旧主ロープ4のU字状垂下部分の中央を切断することにより、旧主ロープ4を旧主ロープ4aと旧主ロープ4bに分断する(S5)。   At this time, the tension applied to the old main ropes 4a and 4b is released, so that the old ropes 4a and 4b are loosened. Therefore, the worker 36 on the lowest floor 103b installs the work table 106 set at substantially the same height as the counterweight 20 at the lower part of the hoistway 100 and goes up to the work table 106. The lower corner of the old main rope 4 that hangs in a U shape from the machine room 101 side, that is, the U-shaped suspending portion is removed from the pulley 24 of the counterweight 20. Then, the worker 36 on the work table 106 cuts the center of the U-shaped hanging portion of the old main rope 4 to divide the old main rope 4 into the old main rope 4a and the old main rope 4b (S5).

次に、機械室101内の作業者35は、旧主ロープ4cの両側のうち釣合い錘20側の部分を昇降路100から引き上げ、旧主ロープ4cをビームプーリ25と巻上機26から取外し機械室101に引き上げる。そして、乗かご27上の作業者33は、旧主ロープ4cを乗かご27側のロープソケット29から取外す。このとき、旧主ロープ4cの両端が解放されるので、乗かご27上の作業者33は、旧主ロープ4cを乗かご27上から機械室101内の作業者35に向けて送り出し、機械室101内の作業者35は旧主ロープ4cを受け取って引上げ回収する(S6)。   Next, the worker 35 in the machine room 101 pulls up the portion on the counterweight 20 side of both sides of the old main rope 4c from the hoistway 100, removes the old main rope 4c from the beam pulley 25 and the hoist 26, and the machine room. Pull up to 101. Then, the worker 33 on the car 27 removes the old main rope 4c from the rope socket 29 on the car 27 side. At this time, since both ends of the old main rope 4c are released, the worker 33 on the car 27 sends out the old main rope 4c from the car 27 toward the worker 35 in the machine room 101, and the machine room The worker 35 in 101 receives the old main rope 4c and pulls up and collects it (S6).

次に、機械室101内の作業者35は麻ロープ(図示せず)を昇降路100内に垂下すると、乗かご27上の作業者33がこの麻ロープの一端を受け取って最上階の階床103a上の作業者34に送り出す。そして、階床103a上の作業者は、乗かご27上の作業者33から麻ロープを受け取り、新主ロープ1が巻き掛けられたロープ送出リール37を引き出して麻ロープに接続する(S7)。   Next, when the worker 35 in the machine room 101 hangs a hemp rope (not shown) into the hoistway 100, the worker 33 on the car 27 receives one end of the hemp rope and receives the top floor. It is sent to the worker 34 on 103a. Then, the worker on the floor 103a receives the hemp rope from the worker 33 on the car 27, pulls out the rope delivery reel 37 around which the new main rope 1 is wound, and connects it to the hemp rope (S7).

次に、最上階の階床103a上の作業者34が麻ロープと共に新主ロープ1を乗かご27上の作業者33に送り出すと、乗かご27上の作業者33は麻ロープと新主ロープ1を受け取って乗かご27上に引き出す(S8)。次に、機械室101内の作業者35は、麻ロープと新主ロープ1を乗かご27上の作業者33から受け取って機械室101内に引き上げる。そして、作業者35は新主ロープ1を巻上機26とビームプーリ25に巻き掛けた後、昇降路100内の釣合い錘20側へ送り出す(S9)。   Next, when the worker 34 on the top floor 103a sends the new main rope 1 together with the hemp rope to the worker 33 on the passenger car 27, the worker 33 on the passenger car 27 has the hemp rope and the new main rope. 1 is received and pulled out onto the car 27 (S8). Next, the worker 35 in the machine room 101 receives the hemp rope and the new main rope 1 from the worker 33 on the car 27 and pulls it up into the machine room 101. Then, the operator 35 winds the new main rope 1 around the hoist 26 and the beam pulley 25, and then sends it out to the counterweight 20 side in the hoistway 100 (S9).

次に、乗かご27上の作業者33は、昇降路100内の釣合い錘20側へ送り出された新主ロープ1を主ロープ交換治具11の金車2a,2bにそれぞれ巻掛け、新主ロープ1の先端を釣合い錘20側のロープソケット23に取付ける(S10)。従って、主ロープ交換治具11は、手順S10において取付けられた新主ロープ1、手順S3において接続された旧主ロープ4a、及び手順S4において接続された旧主ロープ4bを保持している。   Next, the worker 33 on the car 27 wraps the new main rope 1 fed to the counterweight 20 side in the hoistway 100 around the gold wheels 2a and 2b of the main rope changing jig 11, respectively. The tip of the rope 1 is attached to the rope socket 23 on the counterweight 20 side (S10). Therefore, the main rope exchanging jig 11 holds the new main rope 1 attached in step S10, the old main rope 4a connected in step S3, and the old main rope 4b connected in step S4.

次に、乗かご27上の作業者33は、図5に示すようにホイスト31aを操作してホイスト31aからホイストロープ31bを送り出すことにより、主ロープ交換治具11を案内部材7a,7bを介してガイドレール21a,21bに沿って下降させる。すなわち、ホイストロープ31bと新主ロープ1によって主ロープ交換治具11の自重と旧主ロープ4a,4bの荷重が支えられており、ホイストロープ31bが送り出されることによって主ロープ交換治具11は自重と旧主ロープ4a,4bの荷重で矢印39の方向へ移動する。   Next, the operator 33 on the car 27 operates the hoist 31a to send out the hoist rope 31b from the hoist 31a as shown in FIG. 5, whereby the main rope replacement jig 11 is moved through the guide members 7a and 7b. Are lowered along the guide rails 21a and 21b. That is, the own weight of the main rope changing jig 11 and the load of the old main ropes 4a and 4b are supported by the hoist rope 31b and the new main rope 1, and the main rope changing jig 11 has its own weight when the hoist rope 31b is sent out. And it moves to the direction of arrow 39 with the load of old main ropes 4a and 4b.

このとき、最上階の階床103aの作業者34は、主ロープ交換治具11の下降に伴ってロープ送出リール37を保持しながら回転させることにより、新主ロープ1を矢印42の方向へ送出し、機械室101の作業者35は、主ロープ交換治具11の下降に伴ってビームプーリ25を押さえながら新主ロープ1を矢印41の方向へ送出する。これにより、新主ロープ1は昇降路100内の釣合い錘20側において矢印40の方向へ送出される(S11)。   At this time, the operator 34 of the uppermost floor 103a sends the new main rope 1 in the direction of the arrow 42 by rotating while holding the rope sending reel 37 as the main rope changing jig 11 descends. Then, the operator 35 in the machine room 101 sends out the new main rope 1 in the direction of the arrow 41 while pressing the beam pulley 25 as the main rope replacement jig 11 is lowered. Thereby, the new main rope 1 is sent out in the direction of the arrow 40 on the counterweight 20 side in the hoistway 100 (S11).

一方、作業台106上の作業者36は、垂れ下がっている旧主ロープ4a,4bを引き出しながら最下階の階床103bに移動し、旧主ロープ4a,4bの下端をロープ回収リール38に接続する(S12)。そして、最下階の階床103b上の作業者36は、旧主ロープ4a,4bをロープ回収リール38に巻き取って回収する(S13)。   On the other hand, the worker 36 on the work table 106 moves to the lowermost floor 103b while pulling down the old main ropes 4a and 4b, and connects the lower ends of the old main ropes 4a and 4b to the rope recovery reel 38. (S12). Then, the worker 36 on the lowest floor 103b winds up and collects the old main ropes 4a and 4b on the rope collection reel 38 (S13).

次に、主ロープ交換治具11が釣合い錘20のプーリ24の近傍まで下降して新主ロープ1がプーリ24に巻き掛けられる長さまで昇降路100内に布設されると、階床103b上の作業者36は、昇降路100内に入って作業台106に上がり、新主ロープ1のU字状垂下部分1を金車2a,2bから取外し、釣合い錘20のプーリ24に巻き掛けると同時に、乗かご27上の作業者33が新主ロープ1の他端を乗かご27側のロープソケット29に取付ける(S14)。   Next, when the main rope exchanging jig 11 is lowered to the vicinity of the pulley 24 of the counterweight 20 and is laid in the hoistway 100 to a length where the new main rope 1 is wound around the pulley 24, the floor 103b The worker 36 enters the hoistway 100 and goes up to the work table 106, removes the U-shaped hanging portion 1 of the new main rope 1 from the gold wheels 2a and 2b, and winds it on the pulley 24 of the counterweight 20, The worker 33 on the car 27 attaches the other end of the new main rope 1 to the rope socket 29 on the car 27 side (S14).

次に、最下階の階床103b上の作業者36は、主ロープ交換治具11のロープ接続手段5a,5bに接続されている旧主ロープ4a,4bの一端をアイボルト5a2,5b2から取外し、旧主ロープ4a,4bの全てをロープ回収リール38に巻き取ることにより、旧主ロープ4a,4bが矢印43,44の方向へ回収される(S15)。次に、乗かご27上の作業者33は、全本数の主ロープの交換作業が完了したかどうかを判断する(S16)。   Next, the worker 36 on the lowest floor 103b removes one end of the old main ropes 4a and 4b connected to the rope connecting means 5a and 5b of the main rope changing jig 11 from the eyebolts 5a2 and 5b2. Then, all the old main ropes 4a and 4b are wound around the rope collection reel 38, whereby the old main ropes 4a and 4b are collected in the directions of the arrows 43 and 44 (S15). Next, the worker 33 on the car 27 determines whether or not the replacement work for all the main ropes has been completed (S16).

このとき、作業者33は、全本数の主ロープの交換作業が完了していないと判断すると、ホイスト31aを操作してホイスト31aのホイストロープ31bを巻き上げることにより、手順S11において釣合い錘20のプーリ24の近傍まで下降した主ロープ交換治具11を昇降路100の最頂部まで上昇させ(S17)、手順S3の動作に戻る。そして、残りの旧主ロープ4のうち次の交換対象の旧主ロープに対して手順S3〜S15の動作を実施する。   At this time, if the operator 33 determines that the replacement work of all the main ropes has not been completed, the operator 33 operates the hoist 31a to wind up the hoist rope 31b of the hoist 31a, whereby the pulley of the counterweight 20 is obtained in step S11. The main rope exchanging jig 11 lowered to the vicinity of 24 is raised to the top of the hoistway 100 (S17), and the process returns to the operation of step S3. And operation | movement of procedure S3-S15 is implemented with respect to the old main rope of the next replacement object among the remaining old main ropes 4. FIG.

一方、手順S16において作業者33は、全本数の主ロープの交換作業が完了したと判断すると、主ロープ交換治具11をガイドレール21a,21bから取外し(S18)、本実施形態を使用した主ロープの交換作業を終了する。   On the other hand, when the operator 33 determines in step S16 that the replacement work of all the main ropes has been completed, the main rope replacement jig 11 is removed from the guide rails 21a and 21b (S18), and the main rope using this embodiment is used. Finish the rope replacement work.

このように構成した本実施形態によれば、交換対象の旧主ロープ4を新規交換用の新主ロープ1に交換する場合に、移動工程において手順S11に示すように主ロープ交換治具11の横バー部材6が新主ロープ1及び旧主ロープ4a,4bを保持した状態で案内部材7a,7bでガイドレール21a,21bに沿って下降するので、新主ロープ1を昇降路100内に繰り出すと共に、旧主ロープ4a,4bを昇降路100の下部から回収することができる。このように、旧主ロープ4a,4bの回収作業及び新主ロープ1の布設作業の2つの作業を同時に行うことができるので、主ロープの交換作業を効率良く行うことができる。   According to the present embodiment configured as described above, when the old main rope 4 to be replaced is replaced with the new main rope 1 for new replacement, the main rope replacement jig 11 is moved as shown in step S11 in the moving process. Since the horizontal bar member 6 is lowered along the guide rails 21a and 21b by the guide members 7a and 7b while holding the new main rope 1 and the old main ropes 4a and 4b, the new main rope 1 is fed into the hoistway 100. At the same time, the old main ropes 4 a and 4 b can be recovered from the lower part of the hoistway 100. Thus, since the two operations of collecting the old main ropes 4a and 4b and laying the new main rope 1 can be performed at the same time, the replacement operation of the main rope can be performed efficiently.

また、移動工程において手順S11に示すように旧主ロープ4a,4bは主ロープ交換治具11が下降して釣合い錘20のプーリ24の近傍に到達するまで横バー部材6に保持されているので、作業台106上の作業者36が旧主ロープ4a,4bをロープ接続手段5a,5bから取り外すことにより、手順S11〜S13において旧主ロープ4a,4bを昇降路100内の機器に絡ませることなく容易に回収することができる。これにより、旧主ロープ4a,4bの回収作業を円滑に行うことができるので、主ロープの交換作業に費やす時間を削減することができる。   Further, as shown in step S11 in the moving process, the old main ropes 4a and 4b are held by the horizontal bar member 6 until the main rope replacement jig 11 descends and reaches the vicinity of the pulley 24 of the counterweight 20. The operator 36 on the work table 106 detaches the old main ropes 4a and 4b from the rope connecting means 5a and 5b, so that the old main ropes 4a and 4b are entangled with the devices in the hoistway 100 in steps S11 to S13. And can be easily recovered. Thereby, since the collection | recovery operation | work of the old main ropes 4a and 4b can be performed smoothly, the time spent for the replacement | exchange operation | work of a main rope can be reduced.

特に、エレベータが設置される建物が高層階である場合には、既設されている旧主ロープ4a,4bの重量が大きくなるが、上述したように主ロープ交換治具11によって旧主ロープ4a,4bを昇降路100の下部へ容易に降ろすことができるので、重量の大きい主ロープを降ろすのに用いられる大容量のロープ降ろし装置を設置する手間を省くことができる。   In particular, when the building where the elevator is installed is a high floor, the weight of the existing old main ropes 4a and 4b is increased, but as described above, the old main rope 4a, Since 4b can be easily lowered to the lower part of the hoistway 100, it is possible to save the trouble of installing a large-capacity rope lowering device used to lower a heavy main rope.

さらに、接続工程において手順S3及びS4に示すように旧主ロープ4a,4bをロープ接続手段5a,5bに接続することにより、横バー部材6にかかる旧主ロープ4a,4bの荷重を利用して新主ロープ1に張力を与えるようにしているので、その分各部材を軽くすることができる。これにより、作業者は使用される各部材を昇降路100内に持ち運び易くなるので、各部材を容易に組立てたり、分解することができる。このように、主ロープの交換作業を迅速に行うと共に、主ロープの交換作業にかかる作業者の負担を軽減することができ、高い作業性を確保することができる。   Furthermore, by connecting the old main ropes 4a and 4b to the rope connecting means 5a and 5b as shown in steps S3 and S4 in the connecting step, the load of the old main ropes 4a and 4b on the horizontal bar member 6 is used. Since the tension is applied to the new main rope 1, each member can be lightened accordingly. Thereby, since it becomes easy for an operator to carry each member used in the hoistway 100, each member can be easily assembled or disassembled. In this way, the main rope replacement work can be quickly performed, and the burden on the operator for the main rope replacement work can be reduced, and high workability can be ensured.

また、本実施形態は、移動工程において主ロープ交換治具11の横バー部材6にかかる旧主ロープ4a,4bの荷重をホイスト31aと新主ロープ1で分担することができるので、ホイスト31aは旧主ロープ4a,4bの全荷重を保持するのに必要な性能を持つ必要がなくなり、ホイスト31aの計量化も図ることができる。これにより、ホイスト31aが持ち運び易くなるので、機械室101内の作業者35はホイスト31aをマシンビーム102に容易に設置することができ、主ロープの交換作業の準備も迅速に行うことができる。   Moreover, since this embodiment can share the load of the old main ropes 4a and 4b applied to the horizontal bar member 6 of the main rope exchanging jig 11 between the hoist 31a and the new main rope 1 in the moving process, the hoist 31a It is not necessary to have the performance necessary to hold the entire load of the old main ropes 4a and 4b, and the hoist 31a can be quantified. Thereby, since the hoist 31a becomes easy to carry, the operator 35 in the machine room 101 can easily install the hoist 31a on the machine beam 102, and can also quickly prepare for the replacement work of the main rope.

また、本実施形態は、昇降路100の頂部にホイスト31aが設けられており、このホイスト31aのホイストロープ31bは主ロープ交換治具11の取付穴10に取付けられているので、ホイスト31aによって主ロープ交換治具11の昇降動作を制御することができる。そのため、移動工程において手順S11に示すように釣合い錘20のプーリ24の近傍まで下降した主ロープ交換治具11を上昇工程においてホイスト31aによって昇降路100の最頂部まで上昇させることにより、主ロープ交換治具11を昇降路100の頂部へ再度戻すことができる。これにより、既設されている旧主ロープ4の残りを回収する際に、ガイドレール21a,21b間に介設された主ロープ交換治具11を分解して再び組立てる必要がなくなるので、主ロープの交換作業の効率を高めることができる。   Further, in this embodiment, a hoist 31a is provided at the top of the hoistway 100, and the hoist rope 31b of the hoist 31a is attached to the attachment hole 10 of the main rope changing jig 11, so that the hoist 31a The lifting / lowering operation of the rope exchanging jig 11 can be controlled. Therefore, as shown in step S11 in the movement process, the main rope replacement jig 11 lowered to the vicinity of the pulley 24 of the counterweight 20 is raised to the top of the hoistway 100 by the hoist 31a in the ascent process, thereby exchanging the main rope. The jig 11 can be returned to the top of the hoistway 100 again. This eliminates the need for disassembling and reassembling the main rope replacement jig 11 interposed between the guide rails 21a and 21b when collecting the remaining of the existing old main rope 4, so that the main rope The efficiency of the exchange work can be increased.

なお、上述した本実施形態では、ロープ接続手段5a,5bのロープ接続部がアイボルト5a2,5b2から成る場合について説明したが、この場合に限らず、ロープ接続部は切断した旧主ロープ4a,4bの荷重を支えることができる部材であれば良く、例えばバイント゛線等のようにロープを締結する部材やロープソケット等のように挟持が可能な部材であっても良い。   In the above-described embodiment, the case where the rope connecting portions of the rope connecting means 5a and 5b are formed of the eye bolts 5a2 and 5b2 is described. However, the present invention is not limited to this case, and the old main ropes 4a and 4b are cut off. Any member can be used as long as it can support the load, and for example, a member that can be clamped, such as a member that fastens the rope, such as a binder wire, or a rope socket may be used.

1 新主ロープ
2a,2b 金車
3a,3b 突起部
4,4a,4b,4c 旧主ロープ
5a,5b ロープ接続手段
5a1,5b1 貫通孔
5a2,5b2 アイボルト(ロープ接続部)
5a3,5b3 平座金
5a4,5b4 ばね座金
5a5,5b5 ナット
6 横バー部材
6a,6b 単体バー
7a,7b 案内部材
8a1,8b1 ボルト
8a2,8b2,8a3,8b3 平座金
8a4,8b4 ばね座金
8a5,8b5 ナット
9a,9b 長穴
10 取付穴
11 主ロープ交換治具
20 釣合い錘
21a,21b ガイドレール
22 ロープエンド
23 ロープソケット
24 プーリ
25 ビームプーリ
26 巻上機
27 乗かご
29 ロープソケット
30 ロープエンド
31a ホイスト
31b ホイストロープ
100 昇降路
101 機械室
102 マシンビーム
103a 最上階の階床
103b 最下階の階床
104 ピット
105 支持部材
106 作業台
DESCRIPTION OF SYMBOLS 1 New main rope 2a, 2b Gold wheel 3a, 3b Protrusion part 4, 4a, 4b, 4c Old main rope 5a, 5b Rope connection means 5a1, 5b1 Through-hole 5a2, 5b2 Eye bolt (rope connection part)
5a3, 5b3 Plain washer 5a4, 5b4 Spring washer 5a5, 5b5 Nut 6 Horizontal bar member 6a, 6b Single bar 7a, 7b Guide member 8a1, 8b1 Bolt 8a2, 8b2, 8a3, 8b3 Plain washer 8a4, 8b4 Spring washer 8a5, 8b5 9a, 9b Long hole 10 Mounting hole 11 Main rope replacement jig 20 Balance weight 21a, 21b Guide rail 22 Rope end 23 Rope socket 24 Pulley 25 Beam pulley 26 Hoisting machine 27 Car 29 29 Rope socket 30 Rope end 31a Hoist 31b Hoist rope DESCRIPTION OF SYMBOLS 100 Hoistway 101 Machine room 102 Machine beam 103a Top floor 103b Bottom floor 104 Pit 105 Support member 106 Work table

Claims (3)

昇降路に設けられた乗かごと、この乗かごと主ロープを介して吊り下げられる釣合い錘と、この釣合い錘を案内する一対のガイドレールと、前記昇降路の上部に設けられた機械室とを含むエレベータに適用され、前記一対のガイドレール間に介設されて前記釣合い錘の上方に配置される横バー部材と、この横バー部材の両端部に固設され、前記一対のガイドレールに摺動自在に装着される案内部材と、前記横バー部材に新規交換用の新主ロープを巻き掛けた状態で装着される金車と、前記横バー部材に設けられ、前記昇降路の頂部に位置する部分で分断して前記昇降路の下部の前記釣合い錘側へ垂下される交換対象の旧主ロープの上端を接続するロープ接続手段とを備えたエレベータの主ロープ交換治具を用いて前記旧主ロープを前記新主ロープに交換するエレベータの主ロープ交換方法であって、
前記機械室から前記新主ロープを垂下させて前記金車に装着する装着工程と、
前記旧主ロープを前記昇降路の頂部に位置する部分で分断し、分断した前記旧主ロープのうち前記昇降路の下部の前記釣合い錘側へ垂下される部分の上端を前記ロープ接続手段に接続する接続工程と、
前記横バー部材を下方に移動させる移動工程とを含むことを特徴とするエレベータの主ロープ交換方法。
A cage provided in the hoistway, a counterweight suspended from the main cage via the main rope, a pair of guide rails for guiding the counterweight, and a machine room provided above the hoistway A horizontal bar member interposed between the pair of guide rails and disposed above the counterweight, and fixed to both ends of the horizontal bar member, A guide member that is slidably mounted, a gold wheel that is mounted in a state in which a new main rope for replacement is wound around the horizontal bar member, and provided on the horizontal bar member, at the top of the hoistway Using an elevator main rope exchanging jig provided with a rope connecting means for connecting an upper end of an old main rope to be exchanged that is divided at a position where it is suspended and hung to the counterweight side at the lower part of the hoistway The old main rope A main rope method of replacing the elevator to replace in-flops,
A mounting step of hanging the new main rope from the machine room and mounting it on the gold wheel;
The old main rope is divided at a portion located at the top of the hoistway, and the upper end of the divided old main rope that is suspended to the counterweight side at the lower part of the hoistway is connected to the rope connecting means. A connecting step,
And a moving step of moving the lateral bar member downward.
請求項1に記載のエレベータの主ロープ交換方法において、
前記主ロープ交換治具は、前記昇降路の頂部に設けられ、前記横バー部材を吊り下げるホイストを備え、
前記移動工程は、前記主ロープ交換治具の前記ホイストによって前記横バー部材を下降させることを特徴とするエレベータの主ロープ交換方法。
In the elevator main rope replacement method according to claim 1,
The main rope replacement jig is provided at the top of the hoistway, and includes a hoist that suspends the horizontal bar member,
In the moving step, the horizontal bar member is lowered by the hoist of the main rope exchanging jig.
請求項2に記載のエレベータの主ロープ交換方法において、
前記移動工程が行われた後、前記主ロープ交換治具の前記ホイストによって前記横バー部材を上昇させる上昇工程を含むことを特徴とするエレベータの主ロープ交換方法。
In the elevator main rope replacement method according to claim 2,
An elevator main rope exchanging method comprising an ascending step of raising the horizontal bar member by the hoist of the main rope exchanging jig after the moving step is performed.
JP2012014167A 2012-01-26 2012-01-26 How to replace the main rope of the elevator Active JP5571708B2 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP2012014167A JP5571708B2 (en) 2012-01-26 2012-01-26 How to replace the main rope of the elevator
CN201310032226.5A CN103224180B (en) 2012-01-26 2013-01-28 The main cable replacing options of elevator
HK14100914.7A HK1187880A1 (en) 2012-01-26 2014-01-29 Main rope replacement method for elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012014167A JP5571708B2 (en) 2012-01-26 2012-01-26 How to replace the main rope of the elevator

Publications (2)

Publication Number Publication Date
JP2013151365A JP2013151365A (en) 2013-08-08
JP5571708B2 true JP5571708B2 (en) 2014-08-13

Family

ID=48834862

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012014167A Active JP5571708B2 (en) 2012-01-26 2012-01-26 How to replace the main rope of the elevator

Country Status (3)

Country Link
JP (1) JP5571708B2 (en)
CN (1) CN103224180B (en)
HK (1) HK1187880A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115285821B (en) * 2022-08-23 2024-01-19 山东里能鲁西矿业有限公司 System and method for quickly separating new and old steel wire ropes from each other and replacing ropes of multi-rope friction type elevator

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0279379U (en) * 1988-12-06 1990-06-19
JP2504212B2 (en) * 1989-08-31 1996-06-05 三菱電機株式会社 Elevator installation method
JPH09240957A (en) * 1996-03-05 1997-09-16 Mitsubishi Denki Bill Techno Service Kk Main rope guide device of elevator
JPH10167612A (en) * 1996-12-05 1998-06-23 Hitachi Building Syst Co Ltd Main rope exchange jig for 2:1 roping elevator
JPH10338437A (en) * 1997-06-04 1998-12-22 Mitsubishi Denki Bill Techno Service Kk Method for replacing main rope of elevator, main rope housing device used in the method and rope fixing device for car
JPH11189377A (en) * 1997-12-25 1999-07-13 Hitachi Building Systems Co Ltd Main rope replacing method for 2:1-roping elevator
JPH11189378A (en) * 1997-12-25 1999-07-13 Hitachi Building Systems Co Ltd Main rope mounting jig for 2:1-roping elevator
JP3841616B2 (en) * 2000-04-04 2006-11-01 株式会社日立ビルシステム Elevator main rope replacement method and apparatus
FI118534B (en) * 2006-05-08 2007-12-14 Kone Corp A method for replacing a lift hoisting rope and a traction device arrangement for changing

Also Published As

Publication number Publication date
JP2013151365A (en) 2013-08-08
CN103224180B (en) 2016-01-06
HK1187880A1 (en) 2014-04-17
CN103224180A (en) 2013-07-31

Similar Documents

Publication Publication Date Title
JP5571707B2 (en) Elevator main rope replacement jig
JP2005138917A (en) Method for changing main rope on carrier, and main rope changing device
JP5571708B2 (en) How to replace the main rope of the elevator
JP4491110B2 (en) Elevator rope hanging method
JP5327835B2 (en) Elevator emergency stop replacement method, mounting adapter, elevator car and elevator counterweight
JP5595292B2 (en) Replacing the main rope of the machine room-less elevator
JP5841929B2 (en) How to change the main rope of the elevator
JP2839970B2 (en) Elevator main cable replacement method
WO2024069711A1 (en) Elevator main cable replacement method and replacement assisting tool
JP3872833B2 (en) Elevator repair method
JP6847319B1 (en) Rope feed support jig for elevator rope replacement work
JP6950458B2 (en) Elevator weight removal device and weight removal method
JP3020325B2 (en) Elevator main cable replacement method
JP2912989B2 (en) Main rope hanging method of elevator
JP2654409B2 (en) Elevator main cable replacement method
WO2010139845A1 (en) Method in replacing the hoisting roping of an elevator and method for manufacturing an elevator
JP2877593B2 (en) Elevator installation method
JP3471257B2 (en) Elevator main cable replacement method
JP4790941B2 (en) Elevator main rope hanging method
JP2003206083A (en) Main rope changing method and device for elevator
JP3035099B2 (en) Elevator main cable replacement method
JPH10218529A (en) Replacement method of elevator main rope
JP6064023B1 (en) Renewal method of elevator hoisting machine
JP2008037624A (en) Method of replacing main rope for machine room-less elevator of 2:1 roping system
JPH11236175A (en) Method for changing main rope of elevator, and main rope connecting apparatus

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130827

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131212

A131 Notification of reasons for refusal

Effective date: 20140107

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140210

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140617

A61 First payment of annual fees (during grant procedure)

Effective date: 20140626

Free format text: JAPANESE INTERMEDIATE CODE: A61

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Country of ref document: JP

Ref document number: 5571708