JP5239634B2 - Construction method of underground tank structure - Google Patents

Construction method of underground tank structure Download PDF

Info

Publication number
JP5239634B2
JP5239634B2 JP2008218630A JP2008218630A JP5239634B2 JP 5239634 B2 JP5239634 B2 JP 5239634B2 JP 2008218630 A JP2008218630 A JP 2008218630A JP 2008218630 A JP2008218630 A JP 2008218630A JP 5239634 B2 JP5239634 B2 JP 5239634B2
Authority
JP
Japan
Prior art keywords
roof
underground
underground tank
tank structure
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2008218630A
Other languages
Japanese (ja)
Other versions
JP2010053571A (en
Inventor
峰生 佐藤
滋 菅野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2008218630A priority Critical patent/JP5239634B2/en
Publication of JP2010053571A publication Critical patent/JP2010053571A/en
Application granted granted Critical
Publication of JP5239634B2 publication Critical patent/JP5239634B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

本発明は、液化ガスを貯蔵するための下部が地中に埋設された地下タンク構造の構築方法に関する。   The present invention relates to a construction method of an underground tank structure in which a lower part for storing liquefied gas is buried in the ground.

従来より、LPG,LNGなどの液化ガスの貯蔵タンクとして、底版と、底版の周囲に沿って構築された側壁と、側壁の上部を覆う屋根部とからなり、少なくともその下部が地中に埋設されるように構築された地下タンクが用いられている。このような地下タンクは、地中に筒状の地中連続壁を構築し、地中連続壁内を掘削し、地中連続壁の内部において底版を構築し、地中連続壁の内周に沿うように側壁を構築し、側壁の上部に屋根部を接続することにより構築することができる。   Conventionally, as a storage tank for liquefied gas such as LPG, LNG, etc., it consists of a bottom plate, a side wall constructed along the periphery of the bottom plate, and a roof part covering the upper part of the side wall, and at least the lower part is buried in the ground. An underground tank constructed like this is used. Such underground tanks build a cylindrical underground continuous wall in the ground, excavate the underground continuous wall, build a bottom slab inside the underground continuous wall, and place it on the inner periphery of the underground continuous wall. A side wall can be constructed so as to be along, and a roof portion can be connected to the upper part of the side wall.

また、地下タンクの屋根部を構築する別の方法として、構築が完了した地下タンクの底版上において、鋼材からなるドーム状の仮設屋根を構築し、この仮設屋根をリフトアップして屋根部に相当する高さに保持し、仮設屋根上において仮設屋根と一体となるように鉄筋コンクリート構造を構築して屋根部を構築する方法が知られている。
さらに、例えば、特許文献1には、底版上に屋根部の高さまで支保工を構築し、この支保工上において屋根部の構築作業を行う方法が記載されている。
特開平7―34714号公報
Another method for constructing the roof of the underground tank is to construct a dome-shaped temporary roof made of steel on the bottom plate of the completed underground tank, and lift the temporary roof to correspond to the roof. A method of constructing a roof part by constructing a reinforced concrete structure so as to be integrated with the temporary roof on the temporary roof is known.
Furthermore, for example, Patent Document 1 describes a method of constructing a support work up to the height of the roof part on the bottom plate and performing the construction work of the roof part on the support work.
JP-A-7-34714

しかしながら、鋼材からなる仮設屋根を用いる方法では、仮設屋根をリフトアップするためのリフトアップ装置が必要となりコスト高となるとともに、リフトアップ作業に手間がかかる。また、内部に液化ガスが貯蔵されると仮設屋根は低温状態にさらされるため、仮設屋根には低温状態でも耐えうるように低温靭性を有する特殊鋼材を用いており、材料費が高額になってしまう。
また、特許文献1記載の方法では、非常に大規模な支保工を構築、撤去する必要があるため、コスト高になるとともに工期が長期化してしまう。
However, in the method using a temporary roof made of a steel material, a lift-up device for lifting the temporary roof is required, which increases the cost and requires time and labor for the lift-up operation. In addition, when the liquefied gas is stored inside, the temporary roof is exposed to a low temperature state, and therefore, the temporary roof is made of special steel material having low temperature toughness so that it can withstand even in a low temperature state, resulting in a high material cost. End up.
Moreover, in the method of patent document 1, since it is necessary to construct | assemble and remove a very large support work, it becomes high cost and a construction period will become long.

本発明は、上記の問題に鑑みなされたものであり、地下タンク構造物を構築する際の、手間を削減するとともに、コストを抑えることを目的とする。   This invention is made | formed in view of said problem, and it aims at reducing cost while reducing an effort at the time of constructing an underground tank structure.

本発明の地下タンク構造の構築方法は、筒状に形成された側壁部と、当該側壁部の下部に接続された底版部と、前記側壁部の上部に構築された屋根部とからなる鉄筋コンクリート造の地下タンクを備え、少なくとも側壁部及び底版部が地中に埋設された地下タンク構造の構築方法であって、地上高さにおいて、前記屋根部の周縁部の少なくとも一部を除く屋根中央部を構築する中央部構築ステップと、前記側壁部の外周に相当する位置に筒状の地中壁を構築する地中壁構築ステップと、平面視において前記屋根中央部と前記地中壁の間に開口が形成されるように、かつ、支持部材を介して前記屋根中央部が支持されるように、前記屋根中央部と前記地中壁の頂部とを前記支持部材で連結する連結ステップと、 前記開口を通って内部に進入した、又は、搬入された掘削機により前記地中壁の内部を掘削し、前記開口を通じて外部に掘削土を排出する掘削ステップと、前記掘削した孔の底部に前記底版部を構築する底版部構築ステップと、前記開口を通して資材を揚重しながら前記掘削した地中壁の内部に沿うように前記側壁部を構築する側壁部構築ステップと、前記屋根部の縁部の少なくとも一部を構成する鉄筋コンクリートを構築する縁部構築ステップと、を備えることを特徴とする。   The construction method of the underground tank structure of the present invention is a reinforced concrete structure comprising a cylindrical side wall part, a bottom slab part connected to the lower part of the side wall part, and a roof part constructed on the upper side of the side wall part. Is an underground tank structure in which at least a side wall portion and a bottom plate portion are embedded in the ground, and at a height above the ground, a roof central portion excluding at least a part of a peripheral edge portion of the roof portion. A central construction step for construction, a subterranean wall construction step for constructing a cylindrical underground wall at a position corresponding to the outer periphery of the side wall, and an opening between the roof central portion and the underground wall in plan view And connecting the roof central portion and the top of the underground wall with the support member so that the roof central portion is supported via a support member, and the opening. Through the inside Or, an excavation step of excavating the inside of the underground wall by the carried excavator and discharging the excavated soil to the outside through the opening, and a bottom plate portion construction step of constructing the bottom plate portion at the bottom of the excavated hole And a side wall part construction step for constructing the side wall part so as to follow the inside of the excavated underground wall while lifting the material through the opening, and a reinforced concrete constituting at least a part of the edge part of the roof part. An edge construction step for construction.

上記の地下タンク構造の構築方法において、前記支持部材は鉄筋コンクリートからなり、 前記中央部構築ステップでは、前記屋根中央部と一体に、当該屋根中央部から外周に向かって突出するように前記支持部材を構築し、前記連結ステップでは、前記屋根中央部から突出する前記支持部材の端部が一体となるように、前記地中壁の上部に環状の鉄筋コンクリート部材からなる枠状部を構築することにより、前記屋根中央部と前記地中壁の頂部とを連結してもよい。   In the construction method of the above underground tank structure, the support member is made of reinforced concrete, and in the central part construction step, the support member is integrally projected with the roof central part so as to protrude from the roof central part toward the outer periphery. By constructing, in the connecting step, by constructing a frame-shaped part made of an annular reinforced concrete member at the upper part of the underground wall so that the end part of the support member protruding from the roof center part is integrated, You may connect the said roof center part and the top part of the said underground wall.

また、前記支持部材は鉄骨からなり、前記中央部構築ステップでは、前記屋根中央部から前記鉄骨が外周に向かって突出するように前記屋根中央部を構築し、前記連結ステップでは、前記屋根部から突出する鉄骨の端部が埋設されるように、前記地中壁の上部に環状の鉄筋コンクリート部材からなる枠状部を構築することにより、前記屋根部と前記地中壁の頂部とを連結してもよい。
また、前記枠状部及び前記屋根中央部の周縁部のうち少なくとも一方には、周方向に引張力が加えられた引張部材が埋設されていてもよい。
Further, the support member is made of a steel frame, and in the center part construction step, the roof center part is constructed so that the steel frame protrudes from the roof center part toward the outer periphery, and in the connection step, the roof part is By connecting the roof and the top of the underground wall by constructing a frame-shaped part made of an annular reinforced concrete member on the upper part of the underground wall so that the end of the protruding steel frame is embedded Also good.
In addition, a tensile member to which a tensile force is applied in the circumferential direction may be embedded in at least one of the frame-shaped portion and the peripheral portion of the roof central portion.

また、前記中央部構築ステップと、前記地中壁構築ステップと、を並行して行ってもよい。
また、前記地下タンクの内周面には保冷処理が施されており、前記中央部構築ステップでは、前記屋根中央部を構築した後、前記構築した屋根中央部に吊持されるように吊り足場を設け、前記掘削ステップ、前記底版部構築ステップ、前記側壁部構築ステップ、及び前記縁部構築ステップの少なくとも何れか一つの工程と並行して、前記屋根部の内周面の保冷処理を施してもよい。
Moreover, you may perform the said center part construction step and the said underground wall construction step in parallel.
Further, the inner peripheral surface of the underground tank is subjected to cold insulation processing, and in the center construction step, after constructing the roof center, the suspension scaffold is suspended so as to be suspended on the constructed roof center. In parallel with at least one of the excavation step, the bottom plate portion building step, the side wall portion building step, and the edge portion building step, a cooling process is performed on the inner peripheral surface of the roof portion. Also good.

本発明によれば、地上において屋根部を構築することができるため、従来、屋根部を構築するために必要であった、大掛かりな支保工、リフトアップ装置及び特殊鋼材製の仮設屋根などが不要となるため、コストを削減することができる。また、支保工の構築及び解体作業やリフトアップ作業が不要となり、施工の手間を削減することができる。   According to the present invention, since the roof portion can be constructed on the ground, a large support work, a lift-up device, a temporary roof made of a special steel, and the like, which are conventionally necessary for constructing the roof portion, are unnecessary. Therefore, the cost can be reduced. In addition, support construction, dismantling work, and lift-up work are not required, and the construction work can be reduced.

以下、本発明の地下タンク構造の構築方法の一実施形態を図面を参照しながら、詳細に説明する。
図1は、本実施形態の構築方法により構築された地下タンク構造10を示す鉛直断面図である。同図に示すように、地下タンク構造10は、LPGやLNGなどの液化ガスを貯蔵するためのものであり、地盤に円筒形に形成された地中連続壁30と、地中連続壁30の内部に地中連続壁30と一体となるように構築された地下タンク本体20と、により構成される。
Hereinafter, an embodiment of a construction method of an underground tank structure according to the present invention will be described in detail with reference to the drawings.
FIG. 1 is a vertical sectional view showing an underground tank structure 10 constructed by the construction method of this embodiment. As shown in the figure, the underground tank structure 10 is for storing a liquefied gas such as LPG or LNG. The underground continuous wall 30 formed in a cylindrical shape on the ground, and the underground continuous wall 30 An underground tank body 20 constructed so as to be integrated with the underground continuous wall 30 inside.

地下タンク本体20は、底部に排水砕石層を介して構築された鉄筋コンクリート造の底版22と、底版22の周囲に沿って一体に、かつ、地中連続壁30と一体に構築された鉄筋コンクリート造の側壁部21と、側壁部21の頂部に一体にドーム上に構築された鉄筋コンクリート造の屋根部23とにより構成される。
地下タンク本体20の内周面には、地下タンク本体20の内部に貯蔵される液化ガスの冷熱が外部に伝播しないように、保冷材及びメンブレンが取り付けられている。
The underground tank body 20 is composed of a reinforced concrete bottom slab 22 constructed through a drained crushed stone layer at the bottom, and a reinforced concrete constructed integrally with the underground continuous wall 30 along the periphery of the bottom slab 22. It is comprised by the side wall part 21 and the roof part 23 of the reinforced concrete structure built on the dome integrally with the top part of the side wall part 21. FIG.
A cold insulating material and a membrane are attached to the inner peripheral surface of the underground tank body 20 so that the cold heat of the liquefied gas stored in the underground tank body 20 does not propagate to the outside.

地中連続壁30は、上下方向に延びる筒状の地中壁本体31と、地中壁本体31の頂部の外側に接続された環状の枠状部32とにより構成される。地中連続壁30は、鉄筋コンクリート構造物からなり、枠状部32にはその形状に沿ってPC鋼ケーブルが引張力を加えられた状態で埋設されている。   The underground continuous wall 30 includes a cylindrical underground wall main body 31 extending in the vertical direction and an annular frame-shaped portion 32 connected to the outside of the top of the underground wall main body 31. The underground continuous wall 30 is made of a reinforced concrete structure, and a PC steel cable is embedded in the frame-like portion 32 in a state where a tensile force is applied along the shape.

以下、かかる構成の地下タンク構造の構築方法を図2〜図7を参照しながら説明する。なお、各図において(A)は鉛直断面図、(B)は平面図である。本実施形態の地下タンク構造は、鉛直断面において対称性を有するため、各図(A)には中心軸より左側の鉛直断面を示し、(B)には中心角90度の範囲のみを示す。   Hereinafter, the construction method of the underground tank structure having such a configuration will be described with reference to FIGS. In each figure, (A) is a vertical sectional view, and (B) is a plan view. Since the underground tank structure of this embodiment has symmetry in the vertical section, each figure (A) shows a vertical section on the left side of the central axis, and (B) shows only a range of a central angle of 90 degrees.

まず、図2に示すように、地下タンク本体20の側壁部21の外周に相当する位置に、その上端部が枠状部32の下端高さと等しくなるとともに、その上端から縦筋が突出するように地中壁本体31を構築する。なお、地中壁本体31は、地盤を掘削し、掘削孔内に鉄筋かごを建て込んだ後、掘削孔内にコンクリートを打設することで構築することができる。   First, as shown in FIG. 2, at the position corresponding to the outer periphery of the side wall portion 21 of the underground tank main body 20, the upper end portion is equal to the lower end height of the frame-shaped portion 32, and the vertical streak protrudes from the upper end. The underground wall body 31 is constructed. In addition, the underground wall main body 31 can be constructed by excavating the ground, building a rebar cage in the excavation hole, and then placing concrete in the excavation hole.

また、同図に示すように、地中壁本体31の構築作業と並行して、地下タンク本体20の屋根部23における側壁部21の内周面から幅1〜2m程度の外周部を除いた部分(以下、中央部という)にあたる箇所に支保工40を構築する。そして、支保工40上において、中央部を構成する鉄筋を配筋し、中央部を構成するコンクリートを打設するための型枠41を設置する。   Moreover, as shown in the figure, in parallel with the construction work of the underground wall main body 31, the outer peripheral portion having a width of about 1 to 2 m was removed from the inner peripheral surface of the side wall portion 21 in the roof portion 23 of the underground tank main body 20. The support work 40 is constructed at a location corresponding to a portion (hereinafter referred to as a central portion). And on the support work 40, the reinforcement which comprises a center part is arranged, and the formwork 41 for placing the concrete which comprises a center part is installed.

次に、図3に示すように、中央部の外周に相当する位置に、一端が中央部内に位置し、他端が地中壁本体31の上部(枠状部32に相当する位置)まで到達するように複数の鉄骨50を配置する。なお、これら鉄骨50は、後述するように、その間から掘削用重機が進入することができ、また、掘削土の搬出や、地下タンク本体20を構築するための資材を搬入することができるような間隔に配置する。そして、鉄骨50の中央部23A側の端部が埋設されるように、型枠41内にコンクリートを打設して中央部23Aを構築する。   Next, as shown in FIG. 3, one end is located in the central portion at a position corresponding to the outer periphery of the central portion, and the other end reaches the upper portion of the underground wall body 31 (a position corresponding to the frame-shaped portion 32). A plurality of steel frames 50 are arranged as described above. As will be described later, these steel frames 50 can be used by heavy equipment for excavation between them, and can carry out excavated soil and materials for constructing the underground tank body 20. Place at intervals. Then, concrete is placed in the mold 41 so that the end on the central portion 23A side of the steel frame 50 is buried, thereby constructing the central portion 23A.

また、これと並行して、地中壁本体31の上部に枠状部32を構成する鉄筋及びPC鋼ケーブルを配置し、コンクリートを打設して、鉄骨50の端部が埋設されるとともに、地中壁本体31の上部から突出する鉄筋が埋設されるように枠状部32を構築する。そして、枠状部32を構成するコンクリート内に埋設されたPC鋼ケーブルに引張力を加える。これにより地中連続壁30が構築される。   In parallel with this, the reinforcing bar and the PC steel cable constituting the frame-like portion 32 are arranged on the upper part of the underground wall main body 31, and the concrete is placed, so that the end of the steel frame 50 is embedded, The frame-shaped part 32 is constructed so that the reinforcing bars protruding from the upper part of the underground wall main body 31 are embedded. Then, a tensile force is applied to the PC steel cable embedded in the concrete constituting the frame portion 32. Thereby, the underground continuous wall 30 is constructed.

次に、中央部23Aを構成するコンクリートを打設する際に用いた型枠41を撤去し、支保工40を解体する。ここで、支保工40を解体することにより屋根部23の中央部23Aの荷重は、鉄骨50を介して枠状部32へ伝達されることとなる。地中連続壁30の枠状部32には、中央部23Aの荷重により鉄骨50を介して鉛直方向の荷重及び外周に広がるような水平方向荷重が作用することとなるが、上記のように枠状部32に埋設したPC鋼ケーブルに引張力を加えているため、この水平方向荷重に抵抗することができる。   Next, the formwork 41 used when placing the concrete constituting the central portion 23A is removed, and the support work 40 is dismantled. Here, the load of the central portion 23 </ b> A of the roof portion 23 is transmitted to the frame-shaped portion 32 through the steel frame 50 by disassembling the support work 40. The frame-like portion 32 of the underground continuous wall 30 is subjected to a vertical load and a horizontal load spreading on the outer periphery via the steel frame 50 due to the load of the central portion 23A. Since a tensile force is applied to the PC steel cable embedded in the shaped portion 32, the horizontal load can be resisted.

そして、図4に示すように、中央部23Aの下方において、地盤の掘削作業を行う。なお、地盤の掘削作業は、同図に示すように、掘削孔70内に数台のバックホーなどの掘削用重機71を鉄骨50の間の開口を通して進入させ、又は、搬入し、これらの掘削用重機71により地盤の掘削を行い、土砂バケット72により、鉄骨50の間の開口から掘削土を外部に排出することにより行うことができる。   Then, as shown in FIG. 4, excavation work for the ground is performed below the central portion 23A. In the excavation work of the ground, as shown in the figure, several excavating heavy machines 71 such as backhoes enter the excavation hole 70 through the openings between the steel frames 50 or carry them in for excavation. The ground can be excavated by the heavy machinery 71, and the excavated soil can be discharged from the opening between the steel frames 50 by the earth and sand bucket 72.

また、地盤の掘削作業と並行して、屋根部23の中央部23Aに吊持された吊り足場60上において、屋根部23の下面に保冷材の取付作業及びメンブレンをライニングする作業を行う。なお、この屋根部23の下面における作業は、後述する地下タンクの側壁部21や底版22の構築作業や、地下タンク本体20の側壁部21や底版22における保冷材の取付作業及びメンブレンをライニングする作業と並行して行うこととしてもよい。   In parallel with the excavation work of the ground, on the suspension scaffold 60 suspended by the central part 23A of the roof part 23, the work of attaching the cold insulation material and the work of lining the membrane are performed on the lower surface of the roof part 23. In addition, the work on the lower surface of the roof part 23 is the construction work of the side wall part 21 and the bottom plate 22 of the underground tank, which will be described later, the work of attaching the cold insulation material on the side wall part 21 and the bottom plate 22 of the underground tank body 20, and the membrane lining. It may be performed in parallel with the work.

次に、図5に示すように、地中連続壁30の内部の掘削孔70内の底部に鉄筋コンクリート造の底版22を構築する。この際、底版22を構築するための資材は鉄骨50の間の開口から搬入する。   Next, as shown in FIG. 5, a reinforced concrete bottom slab 22 is constructed at the bottom in the excavation hole 70 inside the underground continuous wall 30. At this time, materials for constructing the bottom plate 22 are carried from the openings between the steel frames 50.

次に、図6に示すように、地中連続壁30の内周に沿うように、地中連続壁30と一体に地下タンク本体20の側壁部21を構築する。   Next, as shown in FIG. 6, the side wall portion 21 of the underground tank body 20 is constructed integrally with the underground continuous wall 30 so as to follow the inner periphery of the underground continuous wall 30.

次に、図7に示すように、側壁部21と屋根部23との接続部に相当する位置に型枠を設置し、型枠内に鉄筋を配筋した後、コンクリートを打設して、側壁部21と中央部23Aとを接続する。これにより、屋根部23と側壁部21とが接続され、地下タンク本体20の構築が完了する。   Next, as shown in FIG. 7, the mold frame is installed at a position corresponding to the connection portion between the side wall portion 21 and the roof portion 23, the reinforcing bars are arranged in the mold frame, and then concrete is placed, The side wall portion 21 and the central portion 23A are connected. Thereby, the roof part 23 and the side wall part 21 are connected, and construction of the underground tank main body 20 is completed.

次に、地下タンク本体20の側壁部21及び底版22の内周面に保冷材の取付作業及びメンブレンをライニングする作業を行う。
そして、屋根部23に吊持された吊り足場60を解体することにより、地下タンク構造10の構築作業が完了する。
Next, the work for attaching the cold insulation material and the work for lining the membrane are performed on the side wall portion 21 of the underground tank body 20 and the inner peripheral surface of the bottom plate 22.
And the construction work of the underground tank structure 10 is completed by dismantling the suspension scaffold 60 suspended by the roof part 23.

本実施形態によれば、地上において地下タンク本体20の屋根部23の中央部23Aを地上で構築することができるため、従来、屋根部23を構築するために必要であった、大掛かりな支保工やリフトアップ装置、特殊鋼材製の仮設屋根などが不要であるため、コストを削減することができる。また、支保工の構築及び解体作業やリフトアップ作業が不要となり、施工の手間を削減することができる。   According to the present embodiment, since the central portion 23A of the roof portion 23 of the underground tank main body 20 can be constructed on the ground, a large support work conventionally required for constructing the roof portion 23 is required. And a lift-up device, a temporary roof made of special steel, and the like are unnecessary, so that the cost can be reduced. In addition, support construction, dismantling work, and lift-up work are not required, and the construction work can be reduced.

また、屋根部23の構築作業と、地中連続壁30の構築作業とを並行して行うことができるため、施工性を向上することができる。   Moreover, since the construction work of the roof part 23 and the construction work of the underground continuous wall 30 can be performed in parallel, workability can be improved.

また、屋根部23に吊り足場60を取り付けておくことで、地中連続壁30の内部の地盤の掘削作業や、地下タンク本体20の側壁部21や底版22の保冷材の取付作業及びメンブレンをライニングする作業と並行して、吊り足場60上において保冷材の取付作業及びメンブレンをライニングする作業を行うことができるため、施工期間を短縮することができる。   In addition, by attaching the suspension scaffold 60 to the roof portion 23, excavation work for the ground inside the underground continuous wall 30, work for attaching the cold insulation material for the side wall portion 21 and the bottom plate 22 of the underground tank body 20, and the membrane can be performed. In parallel with the lining work, the work for attaching the cold insulation material and the work for lining the membrane can be performed on the suspension scaffold 60, so that the construction period can be shortened.

なお、本実施形態では、屋根部23の中央部23Aと、地中連続壁30の枠状部32との間を結ぶように鉄骨を設けることにより、屋根部23の中央部23Aを支持することとしたが、これに限らず、棒状に形成された鉄筋コンクリート部材や鉄骨コンクリート部材により屋根部23の中央部23Aを支持することとしてもよい。   In the present embodiment, the central portion 23A of the roof portion 23 is supported by providing a steel frame so as to connect the central portion 23A of the roof portion 23 and the frame-shaped portion 32 of the underground continuous wall 30. However, the present invention is not limited to this, and the central portion 23A of the roof portion 23 may be supported by a reinforced concrete member or a steel concrete member formed in a rod shape.

なお、鉄筋コンクリート部材や鉄骨コンクリート部材により屋根部23の中央部23Aを支持する構成とする場合には、図3を参照して説明した鉄骨50を配置し、この鉄骨50が埋設されるように中央部23Aを構築する工程に代えて、中央部23Aと一体に中央部23Aから外周に向かって突出するように棒状の鉄筋コンクリート部材又は鉄骨コンクリート部材を構築する工程を行い、鉄骨50の端部が埋設されるように地中構造物本体31の上部に枠状部32を構築する工程に代えて、中央部23Aから外周に向かって突出する棒状の鉄筋コンクリート部材又は鉄骨コンクリート部材が一体となるように、枠状部32を構築する工程を行えばよい。   In addition, when it is set as the structure which supports the center part 23A of the roof part 23 by a reinforced concrete member or a steel concrete member, the steel frame 50 demonstrated with reference to FIG. 3 is arrange | positioned, and the center so that this steel frame 50 may be embedded. Instead of the step of constructing the portion 23A, a step of constructing a rod-shaped reinforced concrete member or a steel concrete member so as to protrude from the central portion 23A toward the outer periphery integrally with the central portion 23A is performed, and the end of the steel frame 50 is embedded Instead of the step of constructing the frame-like part 32 at the upper part of the underground structure main body 31, the rod-shaped reinforced concrete member or the steel concrete member protruding toward the outer periphery from the central part 23A is integrated. What is necessary is just to perform the process of constructing the frame-shaped part 32.

また、本実施形態では、枠状部32に引張力を加えたPC鋼ケーブルを埋設しているが、これに限らず、屋根部23の中央部23Aの周縁部に沿って環状に引張力を加えたPC鋼ケーブルを埋設することとしてもよい。中央部23Aの周縁部に引張力を加えたPC鋼ケーブルを埋設することにより、中央部23Aの自重により、中央部23Aに外周へ向かって広がるような荷重が作用するが、この荷重に抵抗することができる。また、枠状部32及び中央部23Aの周縁部にPC鋼ケーブルを埋設することとしてもよい。   Moreover, in this embodiment, although the PC steel cable which added the tensile force to the frame-shaped part 32 is embed | buried, not only this but a tensile force is cyclically formed along the peripheral part of the center part 23A of the roof part 23. The added PC steel cable may be buried. By embedding a PC steel cable with a tensile force applied to the peripheral edge of the central portion 23A, a load that spreads toward the outer periphery acts on the central portion 23A due to its own weight, but resists this load. be able to. Moreover, it is good also as embedding PC steel cable in the peripheral part of the frame-shaped part 32 and the center part 23A.

さらに、枠状部32にPC鋼ケーブルを埋設するのに代えて、枠状部の対向する位置を引張力を加えたタイロッドにより結ぶこととしてもよい。このような構成であっても、屋根部23の中央部23Aの自重により作用する外周に向かって広がるような荷重に抵抗することができる。これと同様に、中央部23Aの周縁部にPC鋼ケーブルを埋設するのに代えて、中央部23Aの周縁部の対向する位置を結ぶように引張力を加えたタイロッドにより結ぶこととしてもよい。   Further, instead of embedding the PC steel cable in the frame-shaped portion 32, the opposing positions of the frame-shaped portion may be tied by a tie rod to which a tensile force is applied. Even with such a configuration, it is possible to resist a load that spreads toward the outer periphery that acts due to the weight of the central portion 23 </ b> A of the roof portion 23. Similarly, instead of embedding the PC steel cable in the peripheral portion of the central portion 23A, it may be connected by a tie rod to which a tensile force is applied so as to connect the opposing positions of the peripheral portion of the central portion 23A.

また、地下タンク本体20を構築した後、地下タンク本体20の屋根部23の上部に発泡スチロールなどの軽量材料により覆土を行ってもよい。この場合、覆土した軽量材料の上部に防水シートなどを敷設してもよい。   In addition, after the underground tank body 20 is constructed, the upper portion of the roof portion 23 of the underground tank body 20 may be covered with a lightweight material such as polystyrene foam. In this case, a waterproof sheet or the like may be laid on the covered lightweight material.

地下タンク構造を示す鉛直断面図であるIt is a vertical sectional view showing the underground tank structure 地下タンク構造の構築方法を説明するための図(その1)であり、(A)は鉛直断面図、(B)は平面図である。It is the figure (the 1) for demonstrating the construction method of an underground tank structure, (A) is a vertical sectional view, (B) is a top view. 地下タンク構造の構築方法を説明するための図(その2)であり、(A)は鉛直断面図、(B)は平面図である。It is a figure (the 2) for demonstrating the construction method of an underground tank structure, (A) is a vertical sectional view, (B) is a top view. 地下タンク構造の構築方法を説明するための図(その3)であり、(A)は鉛直断面図、(B)は平面図である。It is the figure (the 3) for demonstrating the construction method of an underground tank structure, (A) is a vertical sectional view, (B) is a top view. 地下タンク構造の構築方法を説明するための図(その4)であり、(A)は鉛直断面図、(B)は平面図である。It is a figure (the 4) for demonstrating the construction method of an underground tank structure, (A) is a vertical sectional view, (B) is a top view. 地下タンク構造の構築方法を説明するための図(その5)であり、(A)は鉛直断面図、(B)は平面図である。It is the figure (the 5) for demonstrating the construction method of an underground tank structure, (A) is a vertical sectional view, (B) is a top view. 地下タンク構造の構築方法を説明するための図(その6)であり、(A)は鉛直断面図、(B)は平面図である。It is the figure (the 6) for demonstrating the construction method of an underground tank structure, (A) is a vertical sectional view, (B) is a top view.

符号の説明Explanation of symbols

10 地下タンク構造 20 地下タンク本体
21 側壁部 22 底版
23 屋根部 23A 中央部
30 地中連続壁 31 地中壁本体
32 枠状部 40 支保工
41 型枠 50 鉄骨
60 足場 70 掘削孔
71 掘削用重機 72 土砂バケット
DESCRIPTION OF SYMBOLS 10 Underground tank structure 20 Underground tank main body 21 Side wall part 22 Bottom plate 23 Roof part 23A Central part 30 Underground continuous wall 31 Underground wall main body 32 Frame-like part 40 Supporting work 41 Formwork 50 Steel frame 60 Scaffolding 70 Excavation hole 71 Heavy machine for excavation 72 earth and sand bucket

Claims (6)

筒状に形成された側壁部と、当該側壁部の下部に接続された底版部と、前記側壁部の上部に構築された屋根部とからなる鉄筋コンクリート造の地下タンクを備え、少なくとも側壁部及び底版部が地中に埋設された地下タンク構造の構築方法であって、
地上高さにおいて、前記屋根部の周縁部の少なくとも一部を除く屋根中央部を構築する中央部構築ステップと、
前記側壁部の外周に相当する位置に筒状の地中壁を構築する地中壁構築ステップと、
平面視において前記屋根中央部と前記地中壁の間に開口が形成されるように、かつ、支持部材を介して前記屋根中央部が支持されるように、前記屋根中央部と前記地中壁の頂部とを前記支持部材で連結する連結ステップと、
前記開口を通って内部に進入した、又は、搬入された掘削機により前記地中壁の内部を掘削し、前記開口を通じて外部に掘削土を排出する掘削ステップと、
前記掘削した孔の底部に前記底版部を構築する底版部構築ステップと、
前記開口を通して資材を揚重しながら前記掘削した地中壁の内部に沿うように前記側壁部を構築する側壁部構築ステップと、
前記屋根部の縁部の少なくとも一部を構成する鉄筋コンクリートを構築する縁部構築ステップと、を備えることを特徴とする地下タンク構造の構築方法。
A reinforced concrete underground tank comprising a side wall portion formed in a cylindrical shape, a bottom plate portion connected to a lower portion of the side wall portion, and a roof portion constructed on the upper portion of the side wall portion, and including at least the side wall portion and the bottom plate Is a method of constructing an underground tank structure with a part buried underground,
In the ground height, a center part construction step for constructing a roof center part excluding at least a part of a peripheral part of the roof part, and
An underground wall construction step of constructing a cylindrical underground wall at a position corresponding to the outer periphery of the side wall part,
The roof central portion and the underground wall so that an opening is formed between the roof central portion and the underground wall in a plan view and the roof central portion is supported via a support member. A connecting step of connecting the top of the support member with the support member;
An excavation step for excavating the inside of the underground wall by an excavator that has entered or is carried through the opening and discharging the excavated soil to the outside through the opening;
A bottom plate portion building step for building the bottom plate portion at the bottom of the excavated hole;
A side wall construction step for constructing the side wall so as to follow the inside of the excavated underground wall while lifting the material through the opening;
An edge construction step of constructing reinforced concrete that constitutes at least a part of the edge of the roof, and a construction method for an underground tank structure.
請求項1記載の地下タンク構造の構築方法であって、
前記支持部材は鉄筋コンクリートからなり、
前記中央部構築ステップでは、前記屋根中央部と一体に、当該屋根中央部から外周に向かって突出するように前記支持部材を構築し、
前記連結ステップでは、前記屋根中央部から突出する前記支持部材の端部が一体となるように、前記地中壁の上部に環状の鉄筋コンクリート部材からなる枠状部を構築することにより、前記屋根中央部と前記地中壁の頂部とを連結することを特徴とする地下タンク構造の構築方法。
A construction method of an underground tank structure according to claim 1,
The support member is made of reinforced concrete,
In the center part construction step, the support member is constructed so as to protrude from the roof center part toward the outer periphery, integrally with the roof center part,
In the connecting step, the roof center is constructed by constructing a frame-shaped portion made of an annular reinforced concrete member at the upper part of the underground wall so that ends of the support members protruding from the roof central portion are integrated. The construction method of the underground tank structure characterized by connecting a part and the top part of the underground wall.
請求項1記載の地下タンク構造の構築方法であって、
前記支持部材は鉄骨からなり、
前記中央部構築ステップでは、前記屋根中央部から前記鉄骨が外周に向かって突出するように前記屋根中央部を構築し、
前記連結ステップでは、前記屋根中央部から突出する鉄骨の端部が埋設されるように、前記地中壁の上部に環状の鉄筋コンクリート部材からなる枠状部を構築することにより、前記屋根中央部と前記地中壁の頂部とを連結することを特徴とする地下タンク構造の構築方法。
A construction method of an underground tank structure according to claim 1,
The support member is made of steel,
In the central part construction step, the central part of the roof is constructed so that the steel frame protrudes toward the outer periphery from the central part of the roof,
In the connecting step, by constructing a frame-shaped portion made of an annular reinforced concrete member at the upper part of the underground wall so that an end of a steel frame protruding from the roof central portion is embedded, the roof central portion and A method for constructing an underground tank structure characterized by connecting the top of the underground wall.
請求項2又は3に記載の地下タンク構造の構築方法であって、
前記枠状部及び前記屋根中央部の周縁部のうち少なくとも一方には、周方向に引張力が加えられた引張部材が埋設されていることを特徴とする地下タンク構造の構築方法。
A construction method for an underground tank structure according to claim 2 or 3,
A construction method of an underground tank structure, wherein a tensile member to which a tensile force is applied in a circumferential direction is embedded in at least one of the frame-shaped part and the peripheral part of the roof central part.
請求項1から4のうち何れか1項に記載の地下タンク構造の構築方法であって、
前記中央部構築ステップと、前記地中壁構築ステップと、を並行して行うことを特徴とする地下タンク構造の構築方法。
A construction method of an underground tank structure according to any one of claims 1 to 4,
The construction method of the underground tank structure characterized by performing the said center part construction step and the said underground wall construction step in parallel.
請求項1から4のうち何れか1項に記載の地下タンク構造の構築方法であって、
前記地下タンクの内周面には保冷処理が施されており、
前記中央部構築ステップでは、前記屋根中央部を構築した後、前記構築した屋根中央部に吊持されるように吊り足場を設け、
前記掘削ステップ、前記底版部構築ステップ、前記側壁部構築ステップ、及び前記縁部構築ステップの少なくとも何れか一つの工程と並行して、前記屋根部の内周面の保冷処理を施すことを特徴とする地下タンク構造の構築方法。
A construction method of an underground tank structure according to any one of claims 1 to 4,
The inner peripheral surface of the underground tank is subjected to a cold insulation process,
In the central part construction step, after constructing the roof central part, a suspension scaffold is provided to be suspended in the constructed roof central part,
In parallel with at least any one of the excavation step, the bottom slab portion building step, the side wall portion building step, and the edge portion building step, a cooling process is performed on the inner peripheral surface of the roof portion. To build underground tank structure.
JP2008218630A 2008-08-27 2008-08-27 Construction method of underground tank structure Expired - Fee Related JP5239634B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008218630A JP5239634B2 (en) 2008-08-27 2008-08-27 Construction method of underground tank structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008218630A JP5239634B2 (en) 2008-08-27 2008-08-27 Construction method of underground tank structure

Publications (2)

Publication Number Publication Date
JP2010053571A JP2010053571A (en) 2010-03-11
JP5239634B2 true JP5239634B2 (en) 2013-07-17

Family

ID=42069767

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008218630A Expired - Fee Related JP5239634B2 (en) 2008-08-27 2008-08-27 Construction method of underground tank structure

Country Status (1)

Country Link
JP (1) JP5239634B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763682B (en) * 2019-03-06 2024-03-22 问建建 Underground refrigeration house structure and construction method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5827384B2 (en) * 1979-11-06 1983-06-09 川崎重工業株式会社 Construction method of underground tank
JP3185241B2 (en) * 1991-05-07 2001-07-09 石川島播磨重工業株式会社 How to build an underground cryogenic tank
JP2000087371A (en) * 1998-09-11 2000-03-28 Kumagai Gumi Co Ltd Execution of underground tank

Also Published As

Publication number Publication date
JP2010053571A (en) 2010-03-11

Similar Documents

Publication Publication Date Title
JP4853429B2 (en) Support structure of lining board, method of supporting lining board
KR100926173B1 (en) Piping structure and method for constructing the same
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
JP5356780B2 (en) Structure, construction method and design method of structure
JP2011006849A (en) Method for constructing foundation
KR20060096706A (en) Deck suspension top-down method of sub-structure
JP5239634B2 (en) Construction method of underground tank structure
JP5223701B2 (en) Construction method of side wall of underground tank structure
JP2004027609A (en) Construction method for subterranean structure and subterranean structure
JP6228836B2 (en) Reverse winding method
KR200390421Y1 (en) Top-down substructure by deck suspension
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JP2022176549A (en) flat slab structure
JP6778528B2 (en) How to update the tank
KR100620366B1 (en) Construction method of underground structures comprising composite reinforced concrete girders and beams using FRP
KR101027921B1 (en) Underground constructure form system for preventing concretes of underground slab and girder from crack
JP2021123961A (en) Construction method of pile head part reinforcement structure, and mold
JP2010168806A (en) Method of constructing sidewall of underground tank structure
JP4964032B2 (en) Side wall and method for constructing side wall
JP3208100U (en) Scaffolding device for construction of underground structures
JP4475116B2 (en) Vertical shaft structure and its construction method
JP2016199957A (en) Floor preceding method
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JP4133268B2 (en) caisson
KR101692151B1 (en) A deck support frame

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110801

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120817

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130305

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130318

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160412

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 5239634

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees