JP4979736B2 - Power load adjustment system, power load adjustment device, and power load adjustment method - Google Patents

Power load adjustment system, power load adjustment device, and power load adjustment method Download PDF

Info

Publication number
JP4979736B2
JP4979736B2 JP2009129033A JP2009129033A JP4979736B2 JP 4979736 B2 JP4979736 B2 JP 4979736B2 JP 2009129033 A JP2009129033 A JP 2009129033A JP 2009129033 A JP2009129033 A JP 2009129033A JP 4979736 B2 JP4979736 B2 JP 4979736B2
Authority
JP
Japan
Prior art keywords
load
power
amount
power amount
predicted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2009129033A
Other languages
Japanese (ja)
Other versions
JP2010279160A (en
Inventor
泰廣 丸山
浩二 坪根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2009129033A priority Critical patent/JP4979736B2/en
Publication of JP2010279160A publication Critical patent/JP2010279160A/en
Application granted granted Critical
Publication of JP4979736B2 publication Critical patent/JP4979736B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、負荷ごとに投入及び遮断が可能な電力負荷調整システムに関する。   The present invention relates to a power load adjustment system that can be turned on and off for each load.

負荷が使用する電力の平準化を図るため、深夜時間帯の電力を割安で提供する方法がある。一方、電気温水器等の深夜時間帯に稼動する負荷は、タイムスイッチやマイコンを用いることにより、予め設定された時刻に投入するように制御される。特許文献1には、電力供給を停止及び再開するための開閉器ユニットを有する電力量計が開示されている。   In order to level the power used by the load, there is a method of providing cheaper power during the midnight hours. On the other hand, a load such as an electric water heater that operates in the midnight time zone is controlled to be input at a preset time by using a time switch or a microcomputer. Patent Document 1 discloses a watt-hour meter having a switch unit for stopping and restarting power supply.

特開2006−170787号公報JP 2006-170787 A

今後、電気自動車等の普及により深夜時間帯の電力需要が増加すると、配電設備の仕様(変圧器容量・送電容量)により、深夜時間帯の負荷調整を行うことが必要になると予想される。しかしながら、特許文献1の開閉器ユニット付きの電力量計では、特定の負荷のみを遮断する回路がなく、負荷調整を行うことが困難である。   In the future, if the demand for power during the midnight hours increases due to the spread of electric vehicles, it is expected that it will be necessary to adjust the load during the midnight hours according to the specifications of the power distribution equipment (transformer capacity and transmission capacity). However, in the watt-hour meter with a switch unit of Patent Document 1, there is no circuit that cuts off only a specific load, and it is difficult to perform load adjustment.

本発明は、上記課題を鑑みてなされたものであり、その主たる目的は、需要家の負荷ごとに投入及び遮断を可能とすることにある。   This invention is made | formed in view of the said subject, The main objective is to enable insertion and interruption | blocking for every load of a consumer.

上記課題を解決するために、本発明は、電力負荷調整システムであって、配電系統から受けた電力を降圧して下位系統に供給し、当該下位系統で使用される電力量を合計した合計電力量を計測する変圧器と、各需要家宅に設置され、前記変圧器から供給される電力を使用する負荷と、前記負荷の使用する電力量を計測する電力量計と、前記負荷の投入及び遮断を行う遮断器と、前記遮断器に前記負荷の投入及び遮断を指示する電力負荷調整装置と、を備え、前記電力負荷調整装置が、予め各負荷の使用する電力量を予測した予測電力量を記憶する手段と、前記時間帯が経過するごとに、前記電力量計から各負荷の使用する電力量を計測した計測電力量を取得し、当該計測電力量の累計を前記予測電力量で除算することにより各負荷の達成率を算出し、記憶する手段と、前記変圧器から当該時間帯の前記合計電力量のデータを取得する手段と、前記合計電力量が第1の所定値より小さい場合、前記予測電力量の大きい前記負荷又は前記達成率の低い前記負荷の投入を前記遮断器に指示する手段と、前記合計電力量が第2の所定値より大きい場合、前記達成率の高い前記負荷の遮断を前記遮断器に指示する手段と、を備えることを特徴とする。
この構成によれば、遮断器により、負荷ごとに投入及び遮断を行うことができる。次に、時間帯ごとに変圧器の下位系統の負荷の合計電力量と、第1の所定値及び第2の所定値との大小関係に応じて負荷の投入及び遮断を行うことにより、当該時間帯の合計電力量が第1の所定値〜第2の所定値の間になるように各負荷の電力量を平準化することができる。そして、予測電力量や達成率に基づく順序に従うことにより、その時点で遮断及び投入すべき負荷を適切に選択することができる。
In order to solve the above-mentioned problems, the present invention is a power load adjustment system, which reduces the power received from a distribution system and supplies it to a lower system, and sums the total amount of power used in the lower system A transformer that measures the amount, a load that is installed in each customer's house and uses the power supplied from the transformer, a watt-hour meter that measures the amount of power used by the load, and the turning on and off of the load And a power load adjusting device that instructs the circuit breaker to turn on and off the load, and the power load adjusting device calculates a predicted power amount that is predicted in advance for the amount of power used by each load. Each time the time zone elapses, a storage unit obtains a measured power amount obtained by measuring the power amount used by each load from the watt hour meter, and divides the total of the measured power amount by the predicted power amount To achieve the achievement rate of each load Means for obtaining and storing; means for obtaining data of the total power amount for the time period from the transformer; and if the total power amount is smaller than a first predetermined value, Means for instructing the circuit breaker to turn on the load having a low achievement rate, and means for instructing the circuit breaker to interrupt the load having a high achievement rate when the total power amount is greater than a second predetermined value. And.
According to this configuration, the circuit breaker can be turned on and off for each load. Next, by turning on and off the load according to the magnitude relationship between the total power amount of the load of the subordinate system of the transformer and the first predetermined value and the second predetermined value for each time period, the time It is possible to level the power amount of each load so that the total power amount of the band is between the first predetermined value and the second predetermined value. Then, by following the order based on the predicted electric energy and the achievement rate, it is possible to appropriately select the load to be cut off and input at that time.

また、本発明は、電力負荷調整システムであって、前記電力負荷調整装置が、前記時間帯が経過する前には、前記予測電力量の大きい前記負荷の投入を前記遮断器に指示し、前記時間帯が経過した後には、前記達成率の低い前記負荷の投入を前記遮断器に指示することを特徴とする。
この構成によれば、負荷を投入していない当初は、事前に予測した電力量の大きい負荷を優先して投入し、当初から時間が経過した後は、予測した電力量に対する達成率の低い負荷を優先して投入する。これによれば、時間の経過に応じて適切な負荷を投入することができる。
Further, the present invention is a power load adjustment system, wherein the power load adjustment device instructs the circuit breaker to input the load having a large predicted power amount before the time period elapses, After the time zone has elapsed, the circuit breaker is instructed to turn on the load having a low achievement rate.
According to this configuration, when a load is not initially applied, a load with a large amount of power predicted in advance is given priority, and after a lapse of time from the beginning, a load with a low achievement rate with respect to the predicted power amount Is given priority. According to this, it is possible to input an appropriate load as time elapses.

また、本発明は、電力負荷調整システムであって、前記第1の所定値が、前記予測電力量の当該日における単位時間あたりの平均値であり、前記第2の所定値が、過剰と判断される前記合計電力量の下限値であることを特徴とする。
この構成によれば、変圧器の下位系統にある負荷の合計電力量が予測値に達していない場合には負荷を投入し、その合計電力量が過剰と判断される下限値を超えている場合には負荷を遮断する。これによれば、合計電力量が予測値〜過剰の下限値の間になるように各負荷の電力量を平準化することができる。
Moreover, this invention is an electric power load adjustment system, Comprising: The said 1st predetermined value is an average value per unit time on the said day of the said prediction electric energy, and the said 2nd predetermined value is judged to be excess. It is a lower limit value of the total electric energy.
According to this configuration, when the total power amount of the load in the subordinate system of the transformer does not reach the predicted value, the load is turned on, and the total power amount exceeds the lower limit value that is determined to be excessive Shut off the load. According to this, the electric energy of each load can be leveled so that the total electric energy is between the predicted value and the excessive lower limit value.

また、本発明は、電力負荷調整システムであって、前記電力量計が、複数の前記負荷の電力量を計測し、前記遮断器を内蔵することを特徴とする。
この構成によれば、需要家宅に設置される1の電力量計が複数の負荷に対応するので、需要家は、例えば、電気料金の安い深夜時間帯に複数の負荷を稼働させることができる。また、電力量計が遮断器を内蔵するので、需要家宅において電力量計とは別に遮断器を設置する必要がなくなり、また、電力負荷調整装置は遮断器と通信することなく、電力量計及び変圧器と通信すればよいため、便利である。
Moreover, this invention is an electric power load adjustment system, Comprising: The said watt-hour meter measures the electric energy of the said some load, It is characterized by the above-mentioned.
According to this configuration, since one watt-hour meter installed in a customer's house corresponds to a plurality of loads, the consumer can operate a plurality of loads, for example, at midnight hours when the electricity rate is low. In addition, since the watt-hour meter has a built-in circuit breaker, it is not necessary to install a circuit breaker separately from the watt-hour meter at the customer's house, and the power load adjusting device does not communicate with the circuit breaker. This is convenient because it only needs to communicate with the transformer.

なお、本発明は、電力負荷調整装置及び電力負荷調整方法を含む。その他、本願が開示する課題及びその解決方法は、発明を実施するための形態の欄、及び図面により明らかにされる。   The present invention includes a power load adjustment device and a power load adjustment method. In addition, the problems disclosed by the present application and the solutions thereof will be clarified by the description of the mode for carrying out the invention and the drawings.

本発明によれば、需要家の負荷ごとに投入及び遮断を行うことができる。   According to the present invention, it is possible to perform charging and closing for each load of a consumer.

電力負荷調整システムSの構成を示す図である。It is a figure which shows the structure of the electric power load adjustment system. 電力量計2の構成及び原理を示す図であり、(a)は電力量計2の構成を示し、(b)は電子式電力量計の基本構成を示し、(c)は電力量計のブロック図を示す。It is a figure which shows the structure and principle of a watt-hour meter, (a) shows the structure of a watt-hour meter 2, (b) shows the basic composition of an electronic watt-hour meter, (c) is a watt-hour meter. A block diagram is shown. 電力負荷調整装置4のハードウェア構成を示す図である。It is a figure which shows the hardware constitutions of the electric power load adjustment apparatus. 電力負荷調整装置4の記憶部45に記憶されるデータの構成を示す図であり、(a)は予測電力量データ45Aの構成を示し、(b)は計測電力量データ45Bの構成を示し、(c)は投入リスト45Cの構成を示すIt is a figure which shows the structure of the data memorize | stored in the memory | storage part 45 of the electric power load adjusting apparatus 4, (a) shows the structure of the prediction electric energy data 45A, (b) shows the structure of the measurement electric energy data 45B, (C) shows the structure of the input list 45C. 電力負荷調整装置4の処理を示すフローチャートである。4 is a flowchart showing processing of the power load adjustment device 4.

以下、図面を参照しながら、本発明を実施するための形態を説明する。本発明の実施の形態に係る電力負荷調整システムにおいて、一律に電力供給を停止及び開始する開閉装置ではなく、通常の負荷回路とは別に負荷調整が可能な回路を電力量計に設置する。その回路を用いて、例えば、電気温水器等に代表される200Vの負荷だけを随時投入したり、遮断したりする。これによれば、特定の負荷の投入及び遮断を調整することができる。   Hereinafter, embodiments for carrying out the present invention will be described with reference to the drawings. In the power load adjustment system according to the embodiment of the present invention, a circuit capable of load adjustment is installed in the watt-hour meter separately from a normal load circuit, instead of a switching device that uniformly stops and starts power supply. Using that circuit, for example, only a 200 V load represented by an electric water heater or the like is turned on or off at any time. According to this, it is possible to adjust the turning on and off of a specific load.

≪システムの構成と概要≫
図1は、電力負荷調整システムSの構成を示す図である。負荷調整システムSは、配電系統L1、変圧器1、電線L2、電力量計2、負荷3及び電力負荷調整装置4を備える。配電系統L1は、変電所からの電力を送電し、連系点ごとにつながる変圧器1に電力を供給する。変圧器1は、例えば、柱上変圧器であり、配電系統L1に連係し、連係した配電系統L1から受けた電力を降圧して電力を電線L2に供給する。電線L2は、変圧器1ごとに設けられる引込み線であり、当該変圧器1の管轄地域にある需要家宅の各負荷3に電力を配電する。
≪System configuration and overview≫
FIG. 1 is a diagram illustrating a configuration of the power load adjustment system S. The load adjustment system S includes a power distribution system L <b> 1, a transformer 1, an electric wire L <b> 2, a watt hour meter 2, a load 3, and a power load adjustment device 4. The distribution system L1 transmits power from the substation and supplies power to the transformer 1 connected to each interconnection point. The transformer 1 is, for example, a pole transformer, is linked to the power distribution system L1, and steps down the power received from the linked power distribution system L1 to supply the power to the electric wire L2. The electric wire L <b> 2 is a lead-in line provided for each transformer 1, and distributes electric power to each load 3 in a customer's house in the jurisdiction area of the transformer 1.

電力量計2は、各需要家宅に設けられ、電線L2から負荷3に供給され、消費される電力量を計測するとともに、電力負荷調整装置4からの指示に従って、調整可能な負荷3の投入及び遮断を行う。負荷3は、各需要家宅に設けられ、電線L2及び電力量計2を通じて電力の供給を受け、稼働するものであり、照明機器や空調機器等のようにいつ使用されるか分からないので、常時投入状態になっているものと、電気温水器等のように深夜時間帯に稼働することが分かっており、投入や遮断の調整が可能なものとに分けられる。   The watt-hour meter 2 is installed in each customer's house, is supplied to the load 3 from the electric wire L2, and measures the amount of power consumed, and in accordance with an instruction from the power load adjustment device 4 Shut off. Since the load 3 is installed in each customer's house, receives power supply through the electric wire L2 and the watt-hour meter 2, and does not know when it is used like lighting equipment or air conditioning equipment, It is known that it operates in the late-night time period, such as an electric water heater, etc., and can be adjusted to be switched on or off, such as an electric water heater.

電力負荷調整装置4は、電力会社に設置され、変圧器1及び電力量計2とネットワーク(通信回線)を介して通信可能であり、変圧器1の下位系統の電力量及び電力量計2ごとに計測された電力量を取得する。そして、変圧器1の下位系統における各需要家で消費される電力量が平準化するように、各電力量計2に対して、調整可能な負荷3の投入又は遮断を指示する。なお、電力負荷調整装置4は、1の変圧器1及びその下位系統の複数の電力量計2に対して1台設置してもよいし、複数の変圧器1及び各変圧器1の下位系統の電力量計2に対して1台設置してもよい。複数の変圧器1等を対象にする際に、電力負荷調整装置4は、取得するデータ及びその処理を変圧器1ごとに分ける。   The power load adjusting device 4 is installed in an electric power company and can communicate with the transformer 1 and the watt hour meter 2 via a network (communication line). Get the measured power. Then, the watt hour meter 2 is instructed to turn on or off the adjustable load 3 so that the amount of power consumed by each consumer in the subordinate system of the transformer 1 is leveled. One power load adjusting device 4 may be installed for one transformer 1 and a plurality of watt-hour meters 2 of its subordinate system, or a plurality of transformers 1 and a subordinate system of each transformer 1. One power meter 2 may be installed. When targeting a plurality of transformers 1 and the like, the power load adjusting device 4 divides the data to be acquired and the processing thereof for each transformer 1.

≪装置の構成≫
図2は、電力量計2の構成及び原理を示す図である。図2(a)は、電力量計2の構成を示す。電力量計2は、外部に系統側端子11及び負荷側端子12を備え、内部に開閉操作部(遮断器)20及び計量部30を備える。
<< Device configuration >>
FIG. 2 is a diagram showing the configuration and principle of the watt-hour meter 2. FIG. 2A shows the configuration of the watt-hour meter 2. The watt hour meter 2 includes a system side terminal 11 and a load side terminal 12 on the outside, and includes an opening / closing operation unit (breaker) 20 and a metering unit 30 inside.

系統側端子11は、電線L2に接続される系統側端子111、112及び113からなる。負荷側端子12は、負荷3が接続される負荷側端子121、122、123及び124からなる。負荷側端子121、122及び123には、需要家宅の負荷配線を用いる通常の負荷3Aが接続される。端子121−122間及び端子122−123間には100Vの負荷3Aが接続され、端子121−123間には200Vの負荷3Aが接続される。負荷側端子121−124間には、投入や遮断が調整可能な200Vの負荷3Bが接続される。調整可能な負荷3Bとは、例えば、電気温水器等である。   System side terminal 11 consists of system side terminals 111, 112, and 113 connected to electric wire L2. The load side terminal 12 includes load side terminals 121, 122, 123 and 124 to which the load 3 is connected. The load side terminals 121, 122, and 123 are connected to a normal load 3 </ b> A that uses the load wiring of the customer's house. A 100V load 3A is connected between the terminals 121-122 and 122-123, and a 200V load 3A is connected between the terminals 121-123. Between the load side terminals 121-124, a 200V load 3B that can be adjusted to be turned on or off is connected. The adjustable load 3B is, for example, an electric water heater or the like.

開閉操作部20は、開閉スイッチSW1、SW2及びSW3を備え、電力負荷調整装置4からの開閉指示に従って、以下の3つのモードによる負荷調整を行う。すなわち、停止モードにおいては、開閉スイッチSW1、SW2及びSW3を全て遮断する(開とする)。通常使用モードにおいては、開閉スイッチSW1、SW2及びSW3を全て投入する(閉とする)。負荷調整モードにおいては、開閉スイッチSW1及びSW2を投入し、開閉スイッチSW3を遮断する。なお、開閉スイッチSW1、SW2及びSW3の投入及び遮断は、当該開閉スイッチSW1、SW2及びSW3につながる負荷側端子121、123及び124にそれぞれ接続された負荷3を投入及び遮断することを意味する。なお、遮断信号受信部(図示せず)が電力負荷調整装置4から開閉指示(遮断信号)を受信し、その開閉指示に従って開閉スイッチSW1、SW2及びSW3の投入及び遮断が行われる。   The opening / closing operation unit 20 includes opening / closing switches SW 1, SW 2, and SW 3, and performs load adjustment in the following three modes in accordance with an opening / closing instruction from the power load adjustment device 4. That is, in the stop mode, all the open / close switches SW1, SW2, and SW3 are shut off (open). In the normal use mode, all the open / close switches SW1, SW2 and SW3 are turned on (closed). In the load adjustment mode, the on / off switches SW1 and SW2 are turned on and the on / off switch SW3 is shut off. Note that turning on and off the on / off switches SW1, SW2, and SW3 means turning on and off the load 3 connected to the load side terminals 121, 123, and 124 connected to the on / off switches SW1, SW2, and SW3, respectively. A cutoff signal receiving unit (not shown) receives an opening / closing instruction (shutoff signal) from the power load adjusting device 4, and the opening / closing switches SW1, SW2, and SW3 are turned on and off according to the opening / closing instruction.

計量部30は、計量電子回路31、配線W1〜W7及び電流センサCT1〜CT3を備える。計量電子回路31は、配線W1、W2及びW3の間で電圧値を計測し、電流センサCT1、CT2及びCT3から電流値を取得し、計測した電圧値及び取得した電流値から電力量を計算する。配線W1、W2及びW3は、系統側端子111、112及び113をそれぞれ計量電子回路31に接続する。配線W4は、配線W1を開閉スイッチSW2に接続する。配線W5は、配線W2を負荷側端子122に接続する。配線W6は、配線W3を開閉スイッチSW1に接続する。配線W7は、配線W4を開閉スイッチSW3に接続する。電流センサCT1、CT2及びCT3は、交流電流を計測する変流器(CT:Current Transformer)であり、配線W4、W6及びW7の電流をそれぞれ計測する。   The weighing unit 30 includes a weighing electronic circuit 31, wirings W1 to W7, and current sensors CT1 to CT3. The weighing electronic circuit 31 measures a voltage value between the wirings W1, W2, and W3, acquires a current value from the current sensors CT1, CT2, and CT3, and calculates an electric energy from the measured voltage value and the acquired current value. . The wirings W1, W2, and W3 connect the system side terminals 111, 112, and 113 to the weighing electronic circuit 31, respectively. The wiring W4 connects the wiring W1 to the open / close switch SW2. The wiring W5 connects the wiring W2 to the load side terminal 122. The wiring W6 connects the wiring W3 to the open / close switch SW1. The wiring W7 connects the wiring W4 to the open / close switch SW3. The current sensors CT1, CT2, and CT3 are current transformers (CT: Current Transformer) that measure alternating current, and measure the currents of the wirings W4, W6, and W7, respectively.

負荷側端子121、122及び123の間に接続される常時投入状態にある負荷3Aの消費電力量である通常計量P及び負荷側端子121及び124の間に接続される投入や遮断の調整が可能な負荷3Bの消費電力量である負荷調整計量Pは、次の式1及び式2により算出される。

Figure 0004979736
Adjustment of the connected-on or cut off between the load-side terminals 121, 122 and normal weighing P 1 is the power consumption of the load 3A which is always in on state is connected between the 123 and the load-side terminals 121 and 124 a power consumption of the possible load 3B is a load adjusting metering P 2 is calculated by the following formulas 1 and 2.
Figure 0004979736

ここで、電力量計の計量原理について説明する。電力量計は、配電線の負荷電圧の瞬時値v(t)と、消費電流の瞬時値i(t)との積の積分を行う計測器である。図2(b)は、電子式電力量計の基本構成を示す。図2(b)に示すように、瞬時電圧v(t)及び瞬時電流i(t)は、乗算器で乗算されたv(t)×i(t)(瞬時電力)に比例した信号に変換される。次に、この信号は積分され電力量に比例した信号に変換されて、表示器によって電力量が積算表示される。電力量Pを、次の式3で示す。

Figure 0004979736
Here, the measurement principle of the watt-hour meter will be described. The watt-hour meter is a measuring instrument that integrates the product of the instantaneous value v (t) of the load voltage of the distribution line and the instantaneous value i (t) of the current consumption. FIG. 2B shows a basic configuration of the electronic watt-hour meter. As shown in FIG. 2B, the instantaneous voltage v (t) and the instantaneous current i (t) are converted into signals proportional to v (t) × i (t) (instantaneous power) multiplied by the multiplier. Is done. Next, this signal is integrated and converted into a signal proportional to the electric energy, and the electric energy is integrated and displayed on the display. The electric energy P is shown by the following formula 3.
Figure 0004979736

図2(c)は、電力量計のブロック図を示す。負荷電圧に比例した信号をPT(Potential Transformer)によって検出し、他方、消費電流に比例した信号をCT(Current Transformer)によって検出し、これら2つの信号を電力−電圧(電力−電流)変換器に送る。ここで、電圧及び電流の積すなわち電力に比例した電圧(電流)に変換され、次に、電圧−周波数(電流−周波数)変換器によって電力量に比例したパルス周波数に変換される。すなわち、アナログ量である瞬時電力がディジタル量である電力量に比例したパルス数に変換される。この結果、積分器からの出力パルスのパルス定数は、1000pulse/kWsのようにある単位電力量当りのパルス数で表される。すなわち、この場合は、1Ws当り1パルスのパルスが積分器から出力されることになる。このパルスは1パルス当りの電力量の“時間幅”が小さいため(1000pu1se/kWsでは1パルス当り1Ws)、このままのパルスではkWh単位で電力量を記録するレジスタを駆動することができない。そこで、このパルス周波数は、分周器によって適当な周波数に分周され(周波数が下がって1パルスの時間幅が長くなり)、表示装置によって表示される。なお、レジスタにおいて実際の電力量に換算するための乗率は、この分周器の分周数に基づいて設定される。   FIG.2 (c) shows the block diagram of a watt-hour meter. A signal proportional to the load voltage is detected by PT (Potential Transformer), while a signal proportional to the current consumption is detected by CT (Current Transformer), and these two signals are supplied to a power-voltage (power-current) converter. send. Here, it is converted into a voltage (current) proportional to the product of voltage and current, that is, power, and then converted to a pulse frequency proportional to the amount of power by a voltage-frequency (current-frequency) converter. That is, the instantaneous power that is an analog amount is converted into the number of pulses that is proportional to the power amount that is a digital amount. As a result, the pulse constant of the output pulse from the integrator is represented by the number of pulses per unit electric energy, such as 1000 pulses / kWs. That is, in this case, one pulse per 1 Ws is output from the integrator. Since this pulse has a small “time width” of electric energy per pulse (1 Ws per pulse at 1000 pu1se / kWs), it is not possible to drive a register that records the electric energy in units of kWh with this pulse. Therefore, this pulse frequency is divided to an appropriate frequency by the frequency divider (the frequency is lowered and the time width of one pulse is increased), and is displayed by the display device. Note that the multiplication factor for conversion into the actual power amount in the register is set based on the frequency division number of the frequency divider.

図3は、電力負荷調整装置4のハードウェア構成を示す図である。電力負荷調整装置4は、通信部41、表示部42、入力部43、処理部44及び記憶部45を備える。通信部41は、通信線を介して変圧器1及び各電力量計2と通信を行う部分であり、例えば、NIC(Network Interface Card)等によって実現される。表示部42は、処理部44からの指示によりデータを表示する部分であり、例えば、液晶ディスプレイ(LCD:Liquid Crystal Display)等によって実現される。入力部43は、オペレータがデータ(例えば、需要家ごと、時間ごとの使用電力量の予測値のデータ)を入力する部分であり、例えば、キーボードやマウス等によって実現される。処理部44は、各部間のデータの受け渡しを行うととともに、電力負荷調整装置4全体の制御を行うものであり、CPU(Central Processing Unit)が所定のメモリに格納されたプログラムを実行することによって実現される。記憶部45は、処理部44からデータを記憶したり、記憶したデータを読み出したりするものであり、例えば、フラッシュメモリやハードディスク装置等の不揮発性記憶装置によって実現される。   FIG. 3 is a diagram illustrating a hardware configuration of the power load adjusting device 4. The power load adjustment device 4 includes a communication unit 41, a display unit 42, an input unit 43, a processing unit 44, and a storage unit 45. The communication unit 41 is a part that communicates with the transformer 1 and each watt hour meter 2 via a communication line, and is realized by, for example, a NIC (Network Interface Card) or the like. The display unit 42 is a part that displays data according to an instruction from the processing unit 44, and is realized by, for example, a liquid crystal display (LCD). The input unit 43 is a part in which an operator inputs data (for example, data of a predicted value of power consumption for each customer and for each hour), and is realized by, for example, a keyboard or a mouse. The processing unit 44 exchanges data between the units and controls the entire power load adjusting device 4. A CPU (Central Processing Unit) executes a program stored in a predetermined memory. Realized. The storage unit 45 stores data from the processing unit 44 and reads the stored data, and is realized by, for example, a nonvolatile storage device such as a flash memory or a hard disk device.

≪データの構成≫
図4は、電力負荷調整装置4の記憶部45に記憶されるデータの構成を示す図である。図4(a)は、予測電力量データ45Aの構成を示す。予測電力量データ45Aは、深夜時間帯(例えば、23時〜翌日の8時)について、ある変圧器1の下位系統の需要家(電力使用契約の契約者)ごとに予測される、通常の負荷3A及び調整可能な負荷3Bによる使用電力量を示すものであり、需要家ID45A1、予測電力量45A2及び合計値45A3を含む需要家ごとのレコードからなる。需要家ID45A1は、需要家に固有の識別情報であり、電力使用契約の識別情報であってもよいが、需要家宅にある通常の負荷3A及び調整可能な負荷3Bに対応する情報である。従って、需要家ID45A1は、負荷3Bに固有の識別情報で代用してもよい。これは、需要家ID45B1及び45C1も同様である。予測電力量45A2は、23時〜翌日の8時の間の通常の負荷3A及び調整可能な負荷3Bについて予測される電力量を示し、通常の負荷分45A21及び調整可能な負荷分45A22を含む。予測電力量の合計値45A3は、23時〜翌日の8時の間の予測される電力量の合計値を示す。最後の1行前のレコードには、深夜時間帯の予測電力量45A2の合計値が設定され、最後のレコードには、単位時間(30分)あたりの予測電力量の平均値が設定される。
<< Data structure >>
FIG. 4 is a diagram illustrating a configuration of data stored in the storage unit 45 of the power load adjustment device 4. FIG. 4A shows the configuration of the predicted power amount data 45A. The predicted power amount data 45A is a normal load that is predicted for each customer (subcontractor of a power usage contract) of a subordinate system of a certain transformer 1 in the midnight time zone (for example, 23:00 to 8:00 on the next day). It shows the amount of power used by 3A and adjustable load 3B, and consists of a record for each customer including customer ID 45A1, predicted power amount 45A2, and total value 45A3. The consumer ID 45A1 is identification information unique to the consumer and may be identification information of a power usage contract, but is information corresponding to the normal load 3A and the adjustable load 3B in the consumer's house. Therefore, the customer ID 45A1 may be substituted with identification information unique to the load 3B. The same applies to customer IDs 45B1 and 45C1. The predicted power amount 45A2 indicates the power amount predicted for the normal load 3A and the adjustable load 3B between 23:00 and 8:00 on the next day, and includes a normal load component 45A21 and an adjustable load component 45A22. The total value 45A3 of the predicted power amount indicates the total value of the predicted power amount between 23:00 and 8:00 on the next day. In the last previous record, the total value of the predicted power amount 45A2 in the midnight time zone is set, and in the last record, the average value of the predicted power amount per unit time (30 minutes) is set.

なお、変圧器ごとの消費電力量を予測する方法については、例えば、特開2006−352996号公報に、変圧器負荷想定方法として、日負荷計測データを持つ計測需要家と持たない非計測需要家とが混在する配電系統において、非計測需要家と計測需要家の双方の過去の月間消費電力量の年間変動に基づいて、非計測需要家ごとに類似すると想定される計測需要家の日負荷計測データを特定し、非計測需要家については前記特定した日負荷計測データに基づく日負荷を、計測需要家については日負荷計測データに基づく日負荷をそれぞれ求めるとともに、変圧器ごとに電力供給先となる需要家についての日負荷を総合して変圧器別日負荷を求めるという方法が開示されている。   In addition, about the method of estimating the power consumption for every transformer, for example, Unexamined-Japanese-Patent No. 2006-352996 WHEREIN: As a transformer load assumption method, the measurement consumer with daily load measurement data and the non-measurement consumer without In a distribution system that includes both non-measurement consumers and measurement consumers, based on the annual fluctuations in past monthly power consumption, the daily load measurement of measurement consumers that is assumed to be similar to each non-measurement consumer The data is specified, and the daily load based on the specified daily load measurement data is obtained for the non-measurement consumer, and the daily load based on the daily load measurement data is obtained for the measurement consumer, and the power supply destination is determined for each transformer. The method of calculating | requiring the daily load according to a transformer by integrating the daily load about the said consumer is disclosed.

図4(b)は、計測電力量データ45Bの構成を示す。計測電力量データ45Bは、ある変圧器1の下位系統の需要家の時間ごとに計測された、調整可能な負荷3Bによる使用電力量を示すものであり、需要家ID45B1、時間ごとの計測電力量45B2、計測電力量の合計値45B3及び達成率45B4を含む需要家ごとのレコードからなる。需要家ID45B1は、需要家に固有の識別情報である。時間ごとの計測電力量45B2は、所定の30分間の電力量を実際に計測した値である。計測電力量の合計値45B3は、時間ごとの計測電力量45B2を当該日ごとに合計した値である。達成率45B4は、予測電力量45A2のうち、調整可能な負荷分45A22に対する計測電力量の合計値45B3の割合を示す。このとき、合計値45B3及び達成率45B4は、時間ごとの計測電力量45B2が更新される度に更新されるものとする。   FIG. 4B shows the configuration of the measured power amount data 45B. The measured power amount data 45B indicates the amount of power used by the adjustable load 3B, which is measured for each time of the consumers of the subordinate system of a certain transformer 1, and the consumer ID 45B1 and the measured power amount for each hour. It consists of records for each customer including 45B2, total value 45B3 of measured electric energy, and achievement rate 45B4. The customer ID 45B1 is identification information unique to the customer. The measured power amount 45B2 for each hour is a value obtained by actually measuring the power amount for a predetermined 30 minutes. The total value 45B3 of the measured power amount is a value obtained by totaling the measured power amount 45B2 for each hour for each day. The achievement rate 45B4 indicates the ratio of the total value 45B3 of the measured power amount to the adjustable load 45A22 in the predicted power amount 45A2. At this time, the total value 45B3 and the achievement rate 45B4 are updated each time the measured power amount 45B2 for each hour is updated.

図4(c)は、投入リスト45Cの構成を示す。投入リスト45Cは、30分間の時間帯ごとに、ある変圧器1の下位系統の需要家ID45C1の順序を示すものであり、負荷3Bの投入及び遮断を指示するときに参照される。需要家ID45C1は、事前に予測電力量45A2の大きい順にソートされ、当該時間帯が経過した後に達成率45B3の低い順にソートされる。   FIG. 4C shows the configuration of the input list 45C. The input list 45C indicates the order of the customer ID 45C1 of a subordinate system of a certain transformer 1 for each 30-minute time zone, and is referred to when instructing to input and shut off the load 3B. The customer IDs 45C1 are sorted in advance in descending order of the predicted electric energy 45A2, and are sorted in descending order of the achievement rate 45B3 after the time period has elapsed.

≪システムの処理≫
図5は、電力負荷調整装置4の処理を示すフローチャートである。本処理では、深夜時間帯において、調整可能な負荷3Bの投入及び遮断を逐次行う。その処理の考え方としては、深夜時間帯に入った当初は、予測電力量に基づいて、多くの電力を使いそうな負荷3Bから投入する。その後、予測電力量に対する実際の計測電力量の割合である達成率が低い負荷3Bは、予測電力量に達しておらず、もっと電力を使う余地があると考えられるので、投入する。達成率が高い負荷3Bは、予測電力量を超えており、電力を既に十分使っていると考えられるので、遮断する。
≪System processing≫
FIG. 5 is a flowchart showing processing of the power load adjustment device 4. In this process, the adjustable load 3B is sequentially turned on and off in the midnight time zone. As an idea of the processing, at the beginning of the midnight time zone, the load 3B is likely to use a lot of power based on the predicted power amount. Thereafter, the load 3B having a low achievement rate, which is a ratio of the actual measured power amount to the predicted power amount, is not reached the predicted power amount and is considered to have room for using more power. The load 3B having a high achievement rate exceeds the predicted power amount and is considered to be already using the power sufficiently, and therefore is cut off.

まず、電力負荷調整装置4は、事前にバンク単位の電力量を予測する(S501)。バンク単位とは、変圧器1の下位系統の各需要家宅の負荷3を対象とすることを意味し、その負荷3における、通常の負荷3A及び投入・遮断の調整が可能な負荷3Bについて、その電力量を需要家ごとに予測する。その結果として、記憶部45の予測電力量データ45Aのうち、各需要家ID45A1の予測電力量45A2が設定される。なお、予測の方法については、例えば、特開2006−352996号公報を参照のこと。   First, the power load adjustment device 4 predicts the amount of power in bank units in advance (S501). The bank unit means that the load 3 of each customer's house in the subordinate system of the transformer 1 is a target, and the load 3B in the load 3 and the load 3B that can be adjusted to be turned on / off are Predict the amount of electricity for each customer. As a result, the predicted power amount 45A2 of each customer ID 45A1 is set in the predicted power amount data 45A of the storage unit 45. For the prediction method, see, for example, Japanese Patent Application Laid-Open No. 2006-352996.

次に、電力負荷調整装置4は、各需要家ID45A1の予測電力量45A2の合計45A3を計算し、当該合計45A3をもとに単位時間あたりの平均値を計算する(S502)。その結果として、記憶部45の予測電力量データ45Aのうち、予測電力量45A3の平均値(最後のレコード)が設定される。   Next, the power load adjusting device 4 calculates a total 45A3 of the predicted power amounts 45A2 of the respective customer IDs 45A1, and calculates an average value per unit time based on the total 45A3 (S502). As a result, the average value (last record) of the predicted power amount 45A3 is set in the predicted power amount data 45A of the storage unit 45.

そして、電力負荷調整装置4は、記憶部45の投入リスト45Cの初期設定を行う(S503)。すなわち、予測電力量データ45Aの大きい順(つまり、普段から深夜時間帯に電力を多く使用している需要家の順)に需要家ID45C1を並べる。これは、予測電力量データ45Aの大きい負荷3Bを優先して投入するためである。以上により、深夜時間帯に入る前の事前準備ができたことになる。   Then, the power load adjustment device 4 performs initial setting of the input list 45C in the storage unit 45 (S503). That is, the customer IDs 45C1 are arranged in the descending order of the predicted power amount data 45A (that is, the order of the consumers who use a lot of power in the midnight time zone from usual). This is because the load 3B having the large predicted power amount data 45A is given priority. With the above, preparations are made before entering the midnight time zone.

続いて、23時〜翌日の8時の深夜時間帯に入ると、予め設定された30分ごとにS505〜S517の処理を繰り返す(S504〜S518)。   Subsequently, when entering the midnight time zone from 23:00 to 8:00 on the next day, the processing of S505 to S517 is repeated every 30 minutes set in advance (S504 to S518).

まず、電力負荷調整装置4は、経過時間t=0か否かを判定する(S505)。経過時間tは、23時からの経過時間のことであり、最初はt=0なので(S505でYes)、S509の処理を実行する。2回目以降はt>0なので(S505でNo)、通信線を通じて電力量計2から計測データを収集する(S506)。その結果として、記憶部45の計測電力量データ45Bのうち、各需要家ID45B1の計測電力量45B2が設定される。続いて、調整可能な負荷3Bの達成率を計算する(S507)。達成率は、計測電力量の合計値45B3を予測電力量45A2における調整可能な負荷分45A22で除算することにより算出され、達成率45B4に設定される。そして、記憶部45の投入リスト45Cのうち、当該時間帯の需要家ID45C1を、達成率45B4の低い順に並べ替える(S508)。これは、達成率45B4の低い負荷3Bを優先して投入し、達成率45B4の高い調整可能な負荷3Bを優先して遮断するのに適する。   First, the power load adjusting device 4 determines whether or not the elapsed time t = 0 (S505). The elapsed time t is an elapsed time from 23:00. Since t = 0 at first (Yes in S505), the process of S509 is executed. Since t> 0 after the second time (No in S505), the measurement data is collected from the watt-hour meter 2 through the communication line (S506). As a result, the measured power amount 45B2 of each customer ID 45B1 is set in the measured power amount data 45B of the storage unit 45. Subsequently, the achievement rate of the adjustable load 3B is calculated (S507). The achievement rate is calculated by dividing the total value 45B3 of the measured power amount by the adjustable load 45A22 in the predicted power amount 45A2, and is set to the achievement rate 45B4. Then, in the input list 45C of the storage unit 45, the customer IDs 45C1 in the time period are rearranged in ascending order of the achievement rate 45B4 (S508). This is suitable for giving priority to the load 3B having a low achievement rate 45B4 and cutting off the adjustable load 3B having a high achievement rate 45B4.

ここで、電力負荷調整装置4は、バンク電力量(合計電力量)の計測データを取得する(S509)。バンク電力量は、変圧器1で一括して計測される、その下位系統で使用される電力量の合計値である。そして、計測値が平均値×α(第2の所定値)より大きいか否かを判定する(S510)。αは、1より大きい値とし、予測した電力量の尤度分を示す係数であり、平均値×αは、計測値が過剰であると判断される下限値である。計測値が平均値×αより大きい場合(S510のYes)、実際の電力量が予測値から外れて大きい(過剰である)ことを意味するので、電力量を抑える必要がある。そこで、電力負荷調整装置4は、記憶部45の投入リスト45Cから下位の(達成率の高い)負荷3Bを抽出する(S511)。次に、当該負荷3Bの遮断を当該需要家宅の電力量計2に指示する(S512)。そして、当該時刻における当該負荷3Bの再遮断を禁止する(S513)。再遮断禁止の具体的方法には、投入リスト45Cの当該時間帯のデータのうち、遮断した負荷3Bの需要家ID45C1を削除する方法がある。これにより、当該時刻に一度遮断した負荷3Bは、同じ設定時刻の処理において再度遮断されることはない。その後、S509に戻る。   Here, the power load adjusting device 4 acquires measurement data of the bank power amount (total power amount) (S509). The bank power amount is a total value of the power amount used in the lower system, which is collectively measured by the transformer 1. Then, it is determined whether or not the measured value is larger than the average value × α (second predetermined value) (S510). α is a coefficient larger than 1 and indicates the likelihood of the predicted electric energy, and the average value × α is a lower limit value for determining that the measured value is excessive. If the measured value is larger than the average value × α (Yes in S510), it means that the actual power amount is out of the predicted value and is large (excessive), so it is necessary to suppress the power amount. Therefore, the power load adjustment device 4 extracts a lower load (high achievement rate) 3B from the input list 45C of the storage unit 45 (S511). Next, the watt hour meter 2 at the customer's house is instructed to shut off the load 3B (S512). Then, re-blocking of the load 3B at the time is prohibited (S513). As a specific method of prohibiting re-blocking, there is a method of deleting the customer ID 45C1 of the blocked load 3B from the data in the time zone of the input list 45C. Thereby, the load 3B once interrupted at the time is not interrupted again in the process at the same set time. Thereafter, the process returns to S509.

計測値が平均値×αより大きくない場合(S510のNo)、電力負荷調整装置4は、計測値が平均値(第1の所定値)より大きいか否かを判定する(S514)。計測値が平均値より大きくない場合(S514のNo)、実際の電力量が予測値を下回っていることを意味するので、電力量を増やす必要がある。そこで、記憶部45の投入リスト45Cから上位の(達成率の低い)負荷3Bを抽出する(S515)。次に、当該負荷3Bの投入を当該需要家宅の電力量計2に指示する(S516)。そして、当該時刻における当該負荷3Bの再投入を禁止する(S517)。再投入禁止の具体的方法には、投入リスト45Cの当該時間帯のデータのうち、投入した負荷3Bの需要家ID45C1を削除する方法がある。これにより、当該時刻に一度投入した負荷3Bは、同じ設定時刻の処理において再度投入されることはない。その後、S509に戻る。   When the measured value is not larger than the average value × α (No in S510), the power load adjusting device 4 determines whether or not the measured value is larger than the average value (first predetermined value) (S514). If the measured value is not larger than the average value (No in S514), it means that the actual power amount is lower than the predicted value, so the power amount needs to be increased. Therefore, the upper load 3B (low achievement rate) is extracted from the input list 45C of the storage unit 45 (S515). Next, the watt hour meter 2 of the customer's house is instructed to input the load 3B (S516). Then, recharging of the load 3B at the time is prohibited (S517). As a specific method of prohibiting re-input, there is a method of deleting the customer ID 45C1 of the input load 3B from the data in the time zone of the input list 45C. Thereby, the load 3B once input at the time is not input again in the process at the same set time. Thereafter, the process returns to S509.

なお、同じ設定時刻の処理においてS515〜S517の処理が2回以上行われる際には、投入リストの上位から2番目以降の負荷3Bの投入が順次指示されることになる。   When the processes of S515 to S517 are performed twice or more in the process at the same set time, the second and subsequent loads 3B from the top of the input list are sequentially instructed.

計測値が平均値より大きい場合(S514のYes)、S510の判定結果と合わせて、実際の電力量が予測電力量の平均値から平均値×α(α>1)までの間になり、平均値に近くなるので、調整可能な負荷3Bの電力量が平準化していると考えられる。従って、この場合には、電力負荷調整装置4は、当該時刻における負荷3Bの投入又は遮断の指示は終えて、次の設定時刻になるのを待つ。   When the measured value is larger than the average value (Yes in S514), the actual power amount is between the average value of the predicted power amount and the average value × α (α> 1) together with the determination result in S510. Since it is close to the value, it is considered that the electric energy of the adjustable load 3B is leveled. Accordingly, in this case, the power load adjustment device 4 waits for the next set time after the instruction to turn on or off the load 3B at that time is finished.

なお、S505で経過時間t=0の場合(S505のYes)、S509で取得されるバンク電力量の計測値はゼロに近いので、S510及びS514の判定はともにNoとなると考えられる。従って、電力負荷調整装置4は、上位の負荷3Bを抽出し(S515)、その負荷3Bの投入を指示する(S516)。このとき投入リスト45Cは、S503で初期設定した予測電力量の大きい順になっており、深夜時間帯に入った際の最初の設定時刻には、多くの電力量を使うと予測された負荷3Bから投入されることになる。   When the elapsed time t = 0 in S505 (Yes in S505), the measured value of the bank power acquired in S509 is close to zero, so it is considered that the determinations in S510 and S514 are both No. Therefore, the power load adjusting device 4 extracts the higher-order load 3B (S515), and gives an instruction to input the load 3B (S516). At this time, the input list 45C is in the descending order of the predicted power amount initially set in S503, and from the load 3B predicted to use a large amount of power at the first set time when entering the midnight time zone. Will be thrown in.

以上本発明の実施の形態について説明したが、図3に示す電力負荷調整装置4内の各部を機能させるために、処理部44で実行されるプログラムをコンピュータにより読み取り可能な記録媒体に記録し、その記録したプログラムをコンピュータに読み込ませ、実行させることにより、本発明の実施の形態に係る電力負荷調整システムSが実現されるものとする。なお、プログラムをインターネット等のネットワーク経由でコンピュータに提供してもよいし、プログラムが書き込まれた半導体チップ等をコンピュータに組み込んでもよい。   Although the embodiment of the present invention has been described above, in order to make each unit in the power load adjusting device 4 shown in FIG. 3 function, a program executed by the processing unit 44 is recorded on a computer-readable recording medium, It is assumed that the power load adjustment system S according to the embodiment of the present invention is realized by causing the computer to read and execute the recorded program. Note that the program may be provided to the computer via a network such as the Internet, or a semiconductor chip or the like in which the program is written may be incorporated in the computer.

以上説明した本発明の実施の形態によれば、図2(a)の負荷側端子121−124間に接続された調整可能な負荷3Bに対応して、電力量計2の開閉操作部20(端子213−223)を設けるので、調整可能な負荷3Bごとに投入及び遮断を行うことができる。そして、変圧器1の下位系統の調整可能な負荷3Bの合計電力量の大小に応じて、予測電力量や達成率に基づく順序に従って各負荷3Bの遮断及び投入を行うので、各負荷3Bの電力量を平準化することができる。これによれば、変圧器1が過負荷になるというネックを解消することができる。例えば、電気自動車に充電する場合に、供給する電力に余地ができるので、効率的に変圧器1を使うことができる。   According to the embodiment of the present invention described above, the opening / closing operation unit 20 (see FIG. 2A) corresponding to the adjustable load 3B connected between the load side terminals 121-124 of FIG. Since the terminals 213-223) are provided, the load can be turned on and off for each adjustable load 3B. And since each load 3B is interrupted | blocked and turned on according to the order based on prediction electric energy or achievement rate according to the magnitude of the total electric energy of load 3B which can be adjusted of the subordinate system of transformer 1, electric power of each load 3B The amount can be leveled. According to this, the bottleneck that the transformer 1 is overloaded can be eliminated. For example, when charging an electric vehicle, there is room for the power to be supplied, so the transformer 1 can be used efficiently.

以上によれば、変圧器1の下位系統の調整可能な各負荷3Bの電力量を平準化できるので、配電設備の有効活用、低圧配電線の送電ロスの減少及び2重計量の防止を図ることができる。   According to the above, the electric energy of each adjustable load 3B of the subordinate system of the transformer 1 can be leveled, so that effective use of distribution equipment, reduction of transmission loss of low-voltage distribution lines, and prevention of double weighing Can do.

≪その他の実施の形態≫
以上、本発明を実施するための形態について説明したが、上記実施の形態は本発明の理解を容易にするためのものであり、本発明を限定して解釈するためのものではない。本発明はその趣旨を逸脱することなく変更、改良され得るとともに、本発明にはその等価物も含まれる。例えば、以下のような実施の形態が考えられる。
<< Other embodiments >>
As mentioned above, although the form for implementing this invention was demonstrated, the said embodiment is for making an understanding of this invention easy, and is not for limiting and interpreting this invention. The present invention can be changed and improved without departing from the gist thereof, and equivalents thereof are also included in the present invention. For example, the following embodiments can be considered.

(1)上記実施の形態では、調整可能な負荷3Bの投入及び遮断を電力量計2内の開閉操作部20が行うように記載したが、電力量計2内で入切するのに限定されることはない。例えば、電力量計2と、調整可能な負荷3Bとの間に遮断器を設け、その遮断器により入切を行うようにしてもよい。その場合、電力負荷調整装置4は、各遮断器とも通信して、投入及び開放の指示を行うことになる。 (1) In the above embodiment, the opening / closing operation unit 20 in the watt hour meter 2 performs turning on and off of the adjustable load 3 </ b> B, but it is limited to turning on and off in the watt hour meter 2. Never happen. For example, a circuit breaker may be provided between the watt-hour meter 2 and the adjustable load 3B, and the circuit breaker may be turned on and off. In this case, the power load adjusting device 4 communicates with each circuit breaker and gives instructions for turning on and off.

(2)上記実施の形態では、電力量計2の負荷側端子121−124間に調整可能な負荷3Bを接続するように記載したが、1の電力量計2が1の調整可能な負荷3Bを接続するのに限定されることはなく、1の電力量計2が2以上の調整可能な負荷3Bを接続し、それらの負荷3Bの電力量を計測してもよい。その場合、電力量計2に新たな負荷側端子及び電流センサを設け、電力負荷調整装置4の記憶部45の各データに新たな負荷3Bに対応する需要家ID(負荷に固有の識別情報としてもよい)を追加することになる。そして、2以上の調整可能な負荷3Bとして、電気自動車や電気温水器を割り当てるようにしてもよい。 (2) In the above embodiment, the adjustable load 3B is connected between the load-side terminals 121-124 of the watt-hour meter 2, but one watt-hour meter 2 is one adjustable load 3B. The watt-hour meter 2 may connect two or more adjustable loads 3B and measure the electric energy of these loads 3B. In that case, a new load-side terminal and a current sensor are provided in the watt-hour meter 2, and a customer ID corresponding to the new load 3B (as identification information unique to the load) is stored in each data in the storage unit 45 of the power load adjusting device 4. Will be added). And you may make it allocate an electric vehicle and an electric water heater as 2 or more adjustable load 3B.

(3)電力会社は、電力量計2の負荷側端子121−124間の負荷調整部分の電力量を計測し、その電力量に係る電気料金を割引対象にしてもよい。当該需要家は深夜時間帯における負荷調整に協力しているので、そのような特典があってもよいと考えられる。例えば、電気自動車で遠出したいときは多く充電したいので、通常の負荷側端子121〜123ではなく、より安い電気料金の負荷側端子121−124を使用する方法が考えられる。 (3) The electric power company may measure the amount of power in the load adjustment portion between the load-side terminals 121-124 of the watt-hour meter 2, and may discount the electricity rate related to the amount of power. Since the consumer cooperates with load adjustment in the midnight time zone, it is considered that such a privilege may be provided. For example, since it is desired to charge a lot when going out with an electric vehicle, a method of using the load-side terminals 121-124 with lower electric charges instead of the normal load-side terminals 121-123 can be considered.

1 変圧器
2 電力量計
20 開閉操作部(遮断器)
30 計量部
3 負荷
4 電力負荷調整装置
44 処理部
45 記憶部
45A2 予測電力量
45B2 計測電力量
45B3 達成率
L1 配電系統
L2 電線
S 負荷調整システム
DESCRIPTION OF SYMBOLS 1 Transformer 2 Electric energy meter 20 Switching operation part (breaker)
30 Measurement unit 3 Load 4 Power load adjustment device 44 Processing unit 45 Storage unit 45A2 Predicted electric energy 45B2 Measured electric energy 45B3 Achievement rate L1 Distribution system L2 Electric wire S Load adjustment system

Claims (10)

配電系統から受けた電力を降圧して下位系統に供給し、当該下位系統で使用される電力量を合計した合計電力量を計測する変圧器と、
各需要家宅に設置され、前記変圧器から供給される電力を使用する負荷と、
前記負荷の使用する電力量を計測する電力量計と、
前記負荷の投入及び遮断を行う遮断器と、
前記遮断器に前記負荷の投入及び遮断を指示する電力負荷調整装置と、
を備え、
前記電力負荷調整装置は、
予め各負荷の使用する電力量を予測した予測電力量を記憶する手段と、
前記時間帯が経過するごとに、前記電力量計から各負荷の使用する電力量を計測した計測電力量を取得し、当該計測電力量の累計を前記予測電力量で除算することにより各負荷の達成率を算出し、記憶する手段と、
前記変圧器から当該時間帯の前記合計電力量のデータを取得する手段と、
前記合計電力量が第1の所定値より小さい場合、前記予測電力量の大きい前記負荷又は前記達成率の低い前記負荷の投入を前記遮断器に指示する手段と、
前記合計電力量が第2の所定値より大きい場合、前記達成率の高い前記負荷の遮断を前記遮断器に指示する手段と、
を備える
ことを特徴とする電力負荷調整システム。
A transformer that steps down the power received from the power distribution system and supplies it to a subordinate system, and measures the total amount of power that is the sum of the amount of power used in the subordinate system;
A load that is installed in each customer's house and uses the power supplied from the transformer;
A watt-hour meter for measuring the amount of power used by the load;
A circuit breaker for turning on and off the load; and
A power load adjustment device that instructs the circuit breaker to turn on and off the load;
With
The power load adjustment device is:
Means for storing a predicted power amount in which the power amount used by each load is predicted in advance;
Every time the time period elapses, a measured power amount obtained by measuring the power amount used by each load is obtained from the watt hour meter, and the cumulative amount of the measured power amount is divided by the predicted power amount to thereby calculate the load amount of each load. Means for calculating and storing the achievement rate;
Means for obtaining data of the total electric energy in the time period from the transformer;
Means for instructing the circuit breaker to turn on the load having a large predicted power amount or the load having a low achievement rate when the total power amount is smaller than a first predetermined value;
Means for instructing the circuit breaker to shut off the load having a high achievement rate when the total power is greater than a second predetermined value;
An electric power load adjustment system comprising:
請求項1に記載の電力負荷調整システムであって、
前記電力負荷調整装置は、
前記時間帯が経過する前には、前記予測電力量の大きい前記負荷の投入を前記遮断器に指示し、
前記時間帯が経過した後には、前記達成率の低い前記負荷の投入を前記遮断器に指示する
ことを特徴とする電力負荷調整システム。
The power load adjustment system according to claim 1,
The power load adjustment device is:
Before the time period elapses, the circuit breaker is instructed to turn on the load having a large predicted power amount,
After the time period has elapsed, the circuit breaker is instructed to turn on the load having a low achievement rate.
請求項1又は請求項2に記載の電力負荷調整システムであって、
前記第1の所定値は、前記予測電力量の当該日における単位時間あたりの平均値であり、
前記第2の所定値は、過剰と判断される前記合計電力量の下限値である
ことを特徴とする電力負荷調整システム。
The power load adjustment system according to claim 1 or 2,
The first predetermined value is an average value per unit time on the day of the predicted power amount,
The second predetermined value is a lower limit value of the total electric energy that is determined to be excessive.
請求項1ないし請求項3のいずれか一項に記載の電力負荷調整システムであって、
前記電力量計は、複数の前記負荷の電力量を計測し、前記遮断器を内蔵する
ことを特徴とする電力負荷調整システム。
It is an electric power load adjustment system as described in any one of Claims 1 thru | or 3, Comprising:
The electric energy meter measures the electric energy of a plurality of the loads, and incorporates the circuit breaker.
予め各負荷の使用する電力量を予測した予測電力量を記憶する手段と、
前記時間帯が経過するごとに、各負荷の使用する電力量を計測した計測電力量を取得し、当該計測電力量の累計を前記予測電力量で除算することにより各負荷の達成率を算出し、記憶する手段と、
当該時間帯の変圧器の下位系統で使用される電力量を合計した合計電力量のデータを取得する手段と、
前記合計電力量が第1の所定値より小さい場合、前記予測電力量の大きい前記負荷又は前記達成率の低い前記負荷の投入を遮断器に指示する手段と、
前記合計電力量が第2の所定値より大きい場合、前記達成率の高い前記負荷の遮断を前記遮断器に指示する手段と、
を備えることを特徴とする電力負荷調整装置。
Means for storing a predicted power amount in which the power amount used by each load is predicted in advance;
Each time the time period elapses, a measured power amount obtained by measuring the power amount used by each load is obtained, and the achievement rate of each load is calculated by dividing the cumulative amount of the measured power amount by the predicted power amount. Means for memorizing,
Means for obtaining data of total electric energy obtained by summing up electric energy used in the subordinate system of the transformer in the time period;
Means for instructing a circuit breaker to turn on the load having a large predicted power amount or the load having a low achievement rate when the total power amount is smaller than a first predetermined value;
Means for instructing the circuit breaker to shut off the load having a high achievement rate when the total power is greater than a second predetermined value;
A power load adjusting device comprising:
請求項5に記載の電力負荷調整装置であって、
前記時間帯が経過する前には、前記予測電力量の大きい前記負荷の投入を前記遮断器に指示し、
前記時間帯が経過した後には、前記達成率の低い前記負荷の投入を前記遮断器に指示する
ことを特徴とする電力負荷調整装置。
The power load adjustment device according to claim 5,
Before the time period elapses, the circuit breaker is instructed to turn on the load having a large predicted power amount,
After the elapse of the time period, the circuit breaker is instructed to turn on the load having a low achievement rate.
請求項5又は請求項6に記載の電力負荷調整装置であって、
前記第1の所定値は、前記予測電力量の当該日における単位時間あたりの平均値であり、
前記第2の所定値は、過剰と判断される前記合計電力量の下限値である
ことを特徴とする電力負荷調整装置。
The power load adjustment device according to claim 5 or 6,
The first predetermined value is an average value per unit time on the day of the predicted power amount,
The second predetermined value is a lower limit value of the total electric energy that is determined to be excessive.
コンピュータは、
予め時間帯ごとに各負荷の使用する電力量を予測した予測電力量を記憶するステップと、
前記時間帯が経過するごとに、各負荷の使用する電力量を計測した計測電力量を取得し、当該計測電力量を前記予測電力量で除算することにより各負荷の達成率を算出し、記憶するステップと、
当該時間帯の変圧器の下位系統で使用される電力量を合計した合計電力量のデータを取得するステップと、
前記合計電力量が第1の所定値より小さい場合、前記予測電力量の大きい前記負荷又は前記達成率の低い前記負荷の投入を遮断器に指示するステップと、
前記合計電力量が第2の所定値より大きい場合、前記達成率の高い前記負荷の遮断を前記遮断器に指示するステップと、
を実行することを特徴とする電力負荷調整方法。
Computer
Storing a predicted power amount that is predicted in advance for each load for each load;
Every time the time period elapses, a measured power amount obtained by measuring the power amount used by each load is acquired, and the achievement rate of each load is calculated by dividing the measured power amount by the predicted power amount, and stored. And steps to
Obtaining data on the total amount of power that is the sum of the amount of power used in the subordinate system of the transformer during the time period; and
If the total power is less than a first predetermined value, instructing the circuit breaker to turn on the load with a large predicted power or the load with a low achievement rate;
Instructing the circuit breaker to shut off the load having a high achievement rate if the total power is greater than a second predetermined value;
A method for adjusting the power load, characterized in that
請求項に記載の電力負荷調整方法であって、
前記コンピュータは、
前記時間帯が経過する前には、前記予測電力量の大きい前記負荷の投入を前記遮断器に指示し、
前記時間帯が経過した後には、前記達成率の低い前記負荷の投入を前記遮断器に指示する
ことを特徴とする電力負荷調整方法。
The power load adjustment method according to claim 8 ,
The computer
Before the time period elapses, the circuit breaker is instructed to turn on the load having a large predicted power amount,
After the time period has elapsed, the circuit breaker is instructed to turn on the load having a low achievement rate.
請求項又は請求項に記載の電力負荷調整方法であって、
前記第1の所定値は、前記予測電力量の合計値であり、
前記第2の所定値は、過剰と判断される前記合計電力量の下限値である
ことを特徴とする電力負荷調整方法。
The power load adjustment method according to claim 8 or 9 , wherein
The first predetermined value is a total value of the predicted electric energy,
The power load adjustment method, wherein the second predetermined value is a lower limit value of the total power amount determined to be excessive.
JP2009129033A 2009-05-28 2009-05-28 Power load adjustment system, power load adjustment device, and power load adjustment method Expired - Fee Related JP4979736B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009129033A JP4979736B2 (en) 2009-05-28 2009-05-28 Power load adjustment system, power load adjustment device, and power load adjustment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009129033A JP4979736B2 (en) 2009-05-28 2009-05-28 Power load adjustment system, power load adjustment device, and power load adjustment method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2011163136A Division JP2011247901A (en) 2011-07-26 2011-07-26 Watt-hour meter

Publications (2)

Publication Number Publication Date
JP2010279160A JP2010279160A (en) 2010-12-09
JP4979736B2 true JP4979736B2 (en) 2012-07-18

Family

ID=43425594

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009129033A Expired - Fee Related JP4979736B2 (en) 2009-05-28 2009-05-28 Power load adjustment system, power load adjustment device, and power load adjustment method

Country Status (1)

Country Link
JP (1) JP4979736B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107077705A (en) * 2014-10-23 2017-08-18 丰田自动车株式会社 Power supply management system

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012120623A1 (en) 2011-03-07 2012-09-13 株式会社日立製作所 System, method, and computer program for energy consumption management
JP5741813B2 (en) * 2011-03-07 2015-07-01 日本電気株式会社 Power consumption control device, power consumption control method and program
JP5606977B2 (en) * 2011-03-29 2014-10-15 西日本電信電話株式会社 Network-controlled power management system
JP5857471B2 (en) * 2011-06-24 2016-02-10 オムロン株式会社 Demand processing apparatus, control method for demand processing apparatus, control program, and recording medium
KR101135810B1 (en) 2011-11-04 2012-04-20 배재환 Driving method for distribution switchboard with emergency ramp
JP6540082B2 (en) * 2015-02-19 2019-07-10 中国電力株式会社 Control system and control program for an isolated power plant
CN113657755A (en) * 2021-08-17 2021-11-16 国网河北省电力有限公司 Power system load regulation and control system based on big data analysis
CN114154700B (en) * 2021-11-25 2024-05-03 浙江工业大学 User electricity consumption prediction method based on transformer model

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS631325A (en) * 1986-06-19 1988-01-06 沖電気工業株式会社 Monitoring controller of power consumption
JPH09261897A (en) * 1996-03-18 1997-10-03 Ngk Insulators Ltd Power load adjusting system
JPH11150863A (en) * 1997-11-14 1999-06-02 Toshiba Corp Watt-hour meter
JP4019150B2 (en) * 2004-03-17 2007-12-12 独立行政法人産業技術総合研究所 Distribution system information monitoring system
JP4527515B2 (en) * 2004-12-15 2010-08-18 関西電力株式会社 Unit type energy meter

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107077705A (en) * 2014-10-23 2017-08-18 丰田自动车株式会社 Power supply management system
CN107077705B (en) * 2014-10-23 2020-10-23 丰田自动车株式会社 Power supply management system

Also Published As

Publication number Publication date
JP2010279160A (en) 2010-12-09

Similar Documents

Publication Publication Date Title
JP4979736B2 (en) Power load adjustment system, power load adjustment device, and power load adjustment method
US9866020B2 (en) Electric power control method, electric power control device, and electric power control system
WO2015029448A1 (en) Energy management device, energy management method, and energy management system
EP2843785B1 (en) Power monitoring device and power monitoring system
JP2015070744A (en) Power managing device, power managing method and program
JP5938701B2 (en) Power control apparatus, power control method, program, power control system
JP6209951B2 (en) Transformer connection phase determination device, method, and program
CN108604820A (en) Managing device and control method
JP6208614B2 (en) Energy management apparatus, energy management method, and energy management system
WO2017094138A1 (en) Power management device, power management system, evaluation method, and program
CN104285353B (en) Energy management device, energy management method
JP6386595B2 (en) Control device, control system, control method, and program
JP2013110919A (en) Charge control device
JP6148120B2 (en) Energy management apparatus, energy management method, and energy management system
JP2011128953A (en) Electricity bill system
JP2011247901A (en) Watt-hour meter
JP2004164009A (en) Electric power usage optimization proposal system
JP6456183B2 (en) Control device, communication system, and power consumption control method
JP6113030B2 (en) Energy management apparatus, energy management method, and energy management system
CN108872915A (en) Determination method and decision maker
JP2020198696A (en) Power supply system and power management method
JPWO2017163934A1 (en) Power control system, control device, control method, and computer program
JP5984095B2 (en) Action management device, action management method and program
JP5281684B2 (en) Electricity rate calculation apparatus and method
JP2015047041A (en) Energy management apparatus, energy management method, and energy management system

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110526

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110607

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110726

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120410

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120417

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150427

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4979736

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150427

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees