JP4975051B2 - Scaffold assembly and disassembly method - Google Patents

Scaffold assembly and disassembly method Download PDF

Info

Publication number
JP4975051B2
JP4975051B2 JP2009072776A JP2009072776A JP4975051B2 JP 4975051 B2 JP4975051 B2 JP 4975051B2 JP 2009072776 A JP2009072776 A JP 2009072776A JP 2009072776 A JP2009072776 A JP 2009072776A JP 4975051 B2 JP4975051 B2 JP 4975051B2
Authority
JP
Japan
Prior art keywords
scaffold
unit
pillars
columns
scaffold unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009072776A
Other languages
Japanese (ja)
Other versions
JP2010222884A (en
Inventor
吉弘 佐野
Original Assignee
有限会社佐野仮設興業
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 有限会社佐野仮設興業 filed Critical 有限会社佐野仮設興業
Priority to JP2009072776A priority Critical patent/JP4975051B2/en
Publication of JP2010222884A publication Critical patent/JP2010222884A/en
Application granted granted Critical
Publication of JP4975051B2 publication Critical patent/JP4975051B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は足場の組立及び解体方法に関する。   The present invention relates to a scaffold assembly and disassembly method.

建築現場では、建物の躯体に沿う左右及び上下に複数個の足場ユニットを隣接及び積層してなる足場を用いている。足場ユニットとしては、例えば特許文献1に記載の着脱連結式(楔緊結式等)足場ユニット、特許文献2に記載の枠式足場ユニットがある。   In a construction site, a scaffold formed by adjoining and stacking a plurality of scaffold units on the left and right and top and bottom along a building frame is used. Examples of the scaffold unit include a detachable connection type (wedge tight connection type) scaffold unit described in Patent Document 1, and a frame-type scaffold unit described in Patent Document 2.

着脱連結式足場ユニットは、柱に着脱連結部を介して、横架材と前連結材と後連結材の各材のそれぞれが連結されてなり、各柱の踏板の上方に設けられる前連結材と後連結材を手摺とする。着脱連結式足場ユニットは、柱、横架材、前連結材、後連結材等の各材を別体として取扱うものであり、運搬保管時の嵩張りがないし、各材を軽作業で短時間にユニット化でき、各材の使用経過による変形ひずみも吸収してユニット化できる。また、長尺柱の採用によれば、1個の足場ユニットで2層又は3層分(建物の2階又は3階分)等の足場を構築することもできる。   The removable connecting type scaffolding unit is a front connecting material that is provided above the tread of each column by connecting each of the horizontal member, the front connecting member, and the rear connecting member to the column via an attaching / detaching connecting portion. And the rear connecting material is a handrail. The removable connecting type scaffolding unit handles each material such as pillars, horizontal members, front connecting materials, and rear connecting materials as separate bodies, and there is no bulkiness during transportation and storage, and each material can be handled lightly and in a short time. It can be unitized, and it can also be unitized by absorbing deformation strain due to the use of each material. In addition, by adopting a long pillar, a scaffold such as two or three layers (for the second or third floor of a building) can be constructed with one scaffold unit.

枠式足場ユニットは、前後の相対応する柱同士を横架材により枠をなすように一体に連結し、又は前側の柱同士を前連結材により、後側の柱同士を後連結材によりそれぞれ枠をなすように一体に連結する。枠式足場ユニットは、相対する枠と枠を筋交いによって固定気的に連結することにより高強度のユニットを構築できる。但し、各材を当初から枠として取扱うものであり、運搬保管時の嵩張りが大きいし、ユニット化の作業が重作業になり、その変形ひずみを生じた枠はユニット化に供せなくなる等の不都合がある。   The frame-type scaffolding unit connects the corresponding columns of the front and back to each other so as to form a frame with a horizontal member, or the front columns are connected by the front connecting material, and the rear columns are connected by the rear connecting material, respectively. Connect together to form a frame. The frame type scaffold unit can construct a high-strength unit by connecting the opposing frames to each other in a fixed manner by bracing. However, since each material is handled as a frame from the beginning, the bulk during transportation and storage is large, the unitization work becomes heavy work, and the frame that caused the deformation strain cannot be used for unitization. There is an inconvenience.

特開平6-280382JP-A-6-280382 特開2003-138742JP2003-138742

着脱連結式足場ユニットや枠式足場ユニット等の足場ユニットは、建築現場における足場の組立及び解体の安全性、生産性を向上するため、地上でユニット化した足場ユニットをクレーン等で吊り上げて下層側の設置済の足場ユニットの上に搭載して連結し、又は上層で使用済となった足場ユニットを下層側の足場ユニットから外してクレーン等で地上に吊り下げることとしている。   Scaffolding units such as detachable and connected scaffolding units and frame-type scaffolding units are lifted by a crane unit to lift the scaffolding unit united on the ground and improve the safety and productivity of scaffold assembly and disassembly at the construction site. It is supposed to be mounted on and connected to the already installed scaffolding unit, or the used scaffolding unit in the upper layer is removed from the lower scaffolding unit and suspended on the ground with a crane or the like.

従来技術では、クレーン等に設けた吊りワイヤを足場ユニットに取付けてそれらの吊り上げ、吊り下げを行なうものであり、以下の問題点がある。   In the prior art, a suspension wire provided on a crane or the like is attached to a scaffold unit to lift and suspend them, and has the following problems.

クレーン等に設けた吊りワイヤで、着脱連結式足場ユニットを吊る場合、例えば前後の各複数本の柱を左右方向に多列(3列以上)設けたとき、前後のそれぞれで、左右両側の柱のみを吊りワイヤに取付けて吊ると、左右方向における中間の柱が前後の連結材との楔結合の外れ等により落下したり、中間の柱が楔結合されている前後の連結材が大きく沈み込む如くに垂れ下がって楔の折損等を生ずるおそれがある。これに対し、前後のそれぞれで、左右方向における全ての柱を吊りワイヤに取付けて吊るときには、柱本数分の多数本の吊りワイヤが必要になる。   When suspending and attaching a detachable connection type scaffolding unit with a suspension wire provided on a crane or the like, for example, when multiple front and rear columns are provided in multiple rows (3 or more) in the left and right direction, the columns on both the left and right sides respectively If only the suspension wire is attached to the suspension wire, the middle pillar in the left-right direction will fall due to the wedge connection with the front / rear coupling material falling, or the front / rear coupling material where the middle pillar is wedge-coupled will sink greatly. As a result, it may hang down and cause wedge breakage or the like. On the other hand, when attaching all the pillars in the left-right direction to the suspension wire and suspending them on the front and rear sides, as many suspension wires as the number of columns are required.

尚、基本的に、着脱連結式足場ユニットの柱を吊りワイヤに取付けて吊るには、複数本の吊りワイヤの端に取付具を設け、各吊りワイヤの取付具の個々に柱を取付け、取外しする必要があり、吊りワイヤの取付作業も煩雑になる。   Basically, to attach and detach the pillars of the detachable coupling type scaffolding unit to the suspension wire, install attachments at the ends of multiple suspension wires and attach and remove the pillars individually to each attachment of the suspension wire. It is necessary to do this, and the attachment work of the suspension wire becomes complicated.

クレーン等に設けた吊りワイヤで枠式足場ユニットを吊る場合、例えば前後の各複数本の柱を左右方向に多列(3列以上)設けたとき、前後のそれぞれで、左右両側の柱のみを吊りワイヤに取付けて吊ると、左右方向における中間の枠が大きく沈み込む如くに垂れ下がって変形ひずみを生ずるおそれがある。これに対し、前後のそれぞれで、左右方向における全ての柱を吊りワイヤに取付けて吊るときには、柱本数分の多数本の吊りワイヤが必要になる。   When suspending a frame-type scaffolding unit with a suspension wire provided on a crane or the like, for example, when multiple columns (three or more columns) are provided in the left-right direction, only the columns on both the left and right sides of the front and rear are provided. If it is attached to a suspension wire and suspended, it may hang down so that the intermediate frame in the left-right direction sinks greatly, thereby causing deformation strain. On the other hand, when attaching all the pillars in the left-right direction to the suspension wire and suspending them on the front and rear sides, as many suspension wires as the number of columns are required.

尚、基本的に、枠式足場ユニットの柱を吊りワイヤに取付けて吊るには、複数本の吊りワイヤの端に取付具を設け、各吊りワイヤの取付具の個々に柱を取付け、取外しする必要があり、吊りワイヤの取付作業も煩雑になる。   Basically, in order to attach and suspend the pillars of the frame type scaffolding unit to the suspension wires, attachments are provided at the ends of the plurality of suspension wires, and the attachments are individually attached to and detached from the attachments of the suspension wires. It is necessary and the installation work of the suspension wire becomes complicated.

本発明の課題は、クレーン等に設けた吊りワイヤで足場ユニットを、安全、確実、簡易に吊ることにある。   An object of the present invention is to suspend a scaffold unit safely, reliably, and easily with a suspension wire provided on a crane or the like.

請求項1の発明は、前後の各複数本の柱と、前後の相対応する柱同士を対にして連結する横架材と、前側の柱同士を連結する前連結材と、後側の柱同士を連結する後連結材と、各柱の所定高さ位置に支持される踏板とを有してなる足場ユニットの複数個を、上下方向に積層してなる足場の組立及び解体方法において、足場ユニットの前後の全柱を横切るように配置されて各柱に少なくとも軸方向にて止められた吊りビームを介して、当該足場ユニットを吊り上げ又は吊り下ろす工程を有してなり、前記足場ユニットが、柱に着脱連結部を介して、横架材と前連結材と後連結材の各材のそれぞれが連結され、柱に設けられる楔受と、各材に設けられる楔体の組合せにより該着脱連結部を構成する楔緊結式足場ユニットであり、前記吊りビームが、各柱の楔受の下部に当て止めされるようにしたものである。 The invention of claim 1 includes a plurality of front and rear columns, a horizontal member that connects the front and rear corresponding columns in pairs, a front connecting member that connects the front columns, and a rear column. In a method for assembling and disassembling a scaffold, a plurality of scaffold units each having a rear connecting material for connecting each other and a step board supported at a predetermined height position of each pillar are stacked in the vertical direction. A step of lifting or lowering the scaffold unit via a suspension beam that is arranged so as to cross all the columns before and after the unit and is stopped at least in the axial direction on each column, the scaffold unit comprising: Each of the horizontal member, the front connecting member, and the rear connecting member is connected to the pillar via the attaching / detaching connecting portion, and the attaching / detaching connection is made by a combination of a wedge receiver provided on the pillar and a wedge body provided on each member. Wedge-type scaffolding unit that constitutes the part, the hanging beam It is obtained so as to be fastened against the bottom of the wedge receiving each column.

請求項2の発明は、請求項1の発明において更に、前記吊りビームが、足場ユニットの前側の全柱に止められる前側吊りビームと、後側の全柱に止められる後側吊りビームとからなるようにしたものである。   According to a second aspect of the present invention, in the first aspect of the present invention, the suspension beam further comprises a front suspension beam that is secured to all the pillars on the front side of the scaffold unit and a rear suspension beam that is secured to all the pillars on the rear side. It is what I did.

請求項3の発明は、請求項1又は2の発明において更に、前記足場ユニットが、前後の相対応する柱同士を横架材により枠をなすように一体に連結し、又は前側の柱同士を前連結材により、後側の柱同士を後連結材によりそれぞれ枠をなすように一体に連結してなる枠式足場ユニットであるようにしたものである。 According to a third aspect of the present invention, in the first or second aspect of the present invention, the scaffold unit connects the front and rear columns corresponding to each other so as to form a frame with a horizontal member, or the front columns are connected to each other. It is a frame-type scaffold unit in which the rear columns are integrally connected to each other so as to form a frame by the rear connecting material by the front connecting material .

(請求項1)
(a)足場ユニットの前後の全柱を横切るように配置されて各柱に少なくとも軸方向にて止められた吊りビームを介して、当該足場ユニットを吊り上げ又は吊り下ろす。従って、足場ユニットの前後の柱の本数が多数本であっても、多数の吊りビームを用意することなく、前後の全柱を横切る吊りビームを用意し、この吊りビームを各柱に少なくとも軸方向にて止めることにより、吊りビームを足場ユニットに簡易に取付けて吊ることができる。
(Claim 1)
(a) The scaffold unit is lifted or suspended via a suspension beam that is arranged so as to cross all the columns before and after the scaffold unit and is stopped at each column at least in the axial direction. Therefore, even if there are a large number of pillars before and after the scaffold unit, a suspension beam that crosses all the front and rear pillars is prepared without preparing a large number of suspension beams. By stopping at, the suspension beam can be easily attached to the scaffold unit and suspended.

(b)吊りビームを前後の全ての柱に直に軸方向で止めることにより、中間の柱、連結材等を沈み込ませる如くに垂れ下げることなく、足場ユニットの全体を変形させずに吊ることができ、足場ユニットを安全、確実に吊ることができる。   (b) By hanging the suspension beam directly on all the front and rear columns in the axial direction, the entire scaffold unit is suspended without being deformed so as to sag the intermediate columns and connecting materials. It is possible to suspend the scaffold unit safely and securely.

(c)足場ユニットが、柱に着脱連結部を介して、横架材と前連結材と後連結材の各材のそれぞれが連結されてなる着脱連結式であるものにした。着脱連結式足場ユニットのメリット(柱、横架材、前連結材、後連結材等の各材を別体として取扱うものであり、運搬保管時の嵩張りがないし、各材を軽作業で短時間にユニット化でき、各材の使用経過による変形ひずみも吸収してユニット化できる、長尺柱の採用によれば、1個の足場ユニットで2層又は3層分(建物の2階又は3階分)等の足場を構築することもできる)を享持しながら、それらの各材を地上でユニット化したものを吊り上げ/吊り下げして建築現場における足場の組立及び解体の安全性、生産性を向上できる。 (c) The scaffold unit is of a detachable connection type in which each member of the horizontal member, the front connection member, and the rear connection member is connected to the column via the attachment / detachment connecting portion. Advantages of detachable connection type scaffolding units (pillars, horizontal members, front connection materials, rear connection materials, etc. are handled separately, and there is no bulkiness during transportation and storage, and each material is light and short. By adopting long pillars that can be unitized in time and can absorb deformation strain due to the use of each material, one scaffold unit can be used for 2 or 3 layers (2nd or 3rd floor of a building) While building a scaffold (such as a floor), the assembly and dismantling of scaffolds at the construction site can be performed by lifting / suspending a unit of these materials on the ground. Can be improved.

着脱連結式足場ユニットの前後の柱の本数が多数本であっても、前後の全柱を横切る吊りビームを用意するだけで当該足場ユニットを安全、確実、簡易に吊ることができる。   Even if there are a large number of front and rear columns of the detachable connection type scaffold unit, it is possible to suspend the scaffold unit safely, reliably and simply by preparing a suspension beam that crosses all the front and rear columns.

(d)着脱連結式足場ユニットが、柱に設けられる楔受と、各材に設けられる楔体の組合せにより前記着脱連結部を構成する楔緊結式足場ユニットであり、前記吊りビームが、各柱の楔受の下部に当て止めされる。従って、前後の全柱を横切る吊りビームをそれらの柱に添設し、各柱の楔受の下部に当て止めすることで、吊りビームを当該足場ユニットに簡易に取付けできる。また、着脱連結式足場ユニットの全体を変形させずに吊ることができるから、柱の楔受や各材の楔体等の折損を生ずるおそれもない。 (d) The detachable connection type scaffolding unit is a wedge binding type scaffolding unit that constitutes the detachable connection part by a combination of a wedge receiver provided on the pillar and a wedge body provided on each material, and the suspension beam is provided on each pillar. It is stopped by the lower part of the wedge holder. Therefore, the suspension beam can be easily attached to the scaffold unit by attaching suspension beams crossing all the front and rear pillars to the pillars and holding them to the lower portions of the wedge receivers of the pillars. In addition, since the entire detachable connection type scaffolding unit can be hung without being deformed, there is no possibility of breakage of the column wedge holder, the wedge body of each material, or the like.

(請求項2)
(e)吊りビームが、足場ユニットの前側の全柱に止められる前側吊りビームと、後側の全柱に止められる後側吊りビームとからなる。従って、前側と後側の各吊りビームを用いて、足場ユニットを上述(a)、(b)により安全、確実、簡易に吊ることができる。
(請求項
(f)足場ユニットが、前後の相対応する柱同士を横架材により枠をなすように一体に連結し、又は前側の柱同士を前連結材により、後側の柱同士を後連結材によりそれぞれ枠をなすように一体に連結してなる枠式であるものにした。枠式足場ユニットのメリット(相対する枠と枠を筋交いによって固定気的に連結することにより高強度のユニットを構築できる)を享持しながら、それらの各材を地上でユニット化したものを吊り上げ/吊り下げして建築現場における足場の組立及び解体の安全性、生産性を向上できる。
(Claim 2)
(e) The suspension beam is composed of a front suspension beam that is fixed to all pillars on the front side of the scaffold unit and a rear suspension beam that is secured to all pillars on the rear side. Therefore, it is possible to suspend the scaffold unit safely, surely and simply by the above-described (a) and (b) using the front and rear suspension beams.
(Claim 3 )
(f) The scaffold unit connects the front and rear corresponding pillars integrally with each other so as to form a frame with a horizontal member, or the front pillars are connected by the front connecting member, and the rear pillars are connected by the rear connecting member. Each frame is a frame type that is integrally connected to form a frame. While enjoying the merits of frame type scaffolding units (high strength units can be constructed by connecting the opposing frames to each other in a fixed manner by bracing), those materials are unitized on the ground. / Can be suspended to improve the safety and productivity of assembly and dismantling of scaffolds at construction sites.

枠式足場ユニットの前後の柱の本数が多数本であっても、前後の全柱を横切る吊りビームを用意するだけで当該足場ユニットを安全、確実、簡易に吊ることができる。   Even if the number of pillars before and after the frame-type scaffolding unit is large, it is possible to suspend the scaffolding unit safely, surely, and simply by preparing a suspension beam that crosses all the pillars before and after.

図1は足場ユニットの構築状態を示す全体斜視図である。FIG. 1 is an overall perspective view showing a construction state of the scaffold unit. 図2は足場ユニットの構築過程を示す斜視図である。FIG. 2 is a perspective view showing the construction process of the scaffold unit. 図3は足場ユニットに取付けた吊りビームを示す斜視図である。FIG. 3 is a perspective view showing a suspension beam attached to the scaffold unit. 図4は足場ユニットの柱と吊りビームを示す正面図である。FIG. 4 is a front view showing the pillar and the suspension beam of the scaffold unit. 図5はクレーンによる足場ユニットの吊り状態を示す斜視図である。FIG. 5 is a perspective view showing a suspended state of the scaffold unit by a crane.

図1に示す足場ユニット10は、前側の複数本(本実施例では4本)の柱11Aと、後側の複数本(本実施例では4本)の柱11Bと、前後の相対応する柱11A、11B同士を対にして連結する横架材12と、前側の柱11A同士を連結する前連結材13Aと、後側の柱11B同士を連結する後連結材13Bと、各柱11A、11Bの所定高さ位置に支持される踏板14とを有して構築される。尚、足場ユニット10において、足場ユニット10が使用される建物の躯体から遠い側を前側、躯体に近い側を後側というものとする。   The scaffold unit 10 shown in FIG. 1 includes a plurality of front (four in this embodiment) pillars 11A, a plurality of rear (four in this embodiment) pillars 11B, and corresponding front and rear pillars. 11A, 11B paired with the horizontal member 12, the front connecting member 13A connecting the front pillars 11A, the rear connecting member 13B connecting the rear pillars 11B, and the pillars 11A, 11B And a tread plate 14 supported at a predetermined height position. In the scaffold unit 10, the side far from the housing of the building where the scaffold unit 10 is used is the front side, and the side close to the housing is the rear side.

本実施例の足場ユニット10は、着脱連結式であり、柱11A、11Bに着脱連結部20を介して、横架材12と前連結材13Aと後連結材13Bの各材のそれぞれが連結されてなり、各柱11A、11Bの踏板14の上方に設けられる前連結材13Aと後連結材13Bを作業者の腰高等に対応する手摺15とするものである。踏板14の両端部に設けられている各2個のフック14Aが相隣る横架材12、12に係着されて設けられる。   The scaffold unit 10 of this embodiment is a detachable connection type, and each of the horizontal member 12, the front connection member 13 </ b> A, and the rear connection member 13 </ b> B is connected to the columns 11 </ b> A and 11 </ b> B via the attachment / detachment connection part 20. Thus, the front connecting member 13A and the rear connecting member 13B provided above the treads 14 of the pillars 11A and 11B are used as handrails 15 corresponding to the waist height of the operator. Two hooks 14 </ b> A provided at both end portions of the tread 14 are engaged with the adjacent horizontal members 12, 12.

本実施例の着脱連結式足場ユニット10は、楔緊結式であり、各柱11A、11Bの正背面に設けられる2個の袋状の楔受21、21と、各柱11A、11Bの左右側面に設けられる2個の袋状の楔受22、22と、各材12、13A、13Bの両端部に設けられる楔体23の組合せにより、前記着脱連結部20を構成する。本実施例では、楔受21を楔受22の下側に段差をなすように配置している。横架材12の両端部の楔体23、23を前後の相対応する柱11A、11Bの相対向する楔受21、21に挿入して押下げることにて、楔結合する。前連結材13Aの両端部の楔体23、23を相隣る前側の柱11A、11Aの相対向する楔受22、22に挿入して押下げることにて、楔結合する。後連結材13Bの両端部の楔体23、23を相隣る後側の柱11B、11Bの相対向する楔受22、22に挿入して押下げることにて、楔結合する。   The detachable connection type scaffolding unit 10 of this embodiment is a wedge-tightening type, and includes two bag-shaped wedge receivers 21 and 21 provided on the front and back surfaces of the pillars 11A and 11B, and left and right side surfaces of the pillars 11A and 11B. The detachable connecting portion 20 is constituted by a combination of two bag-shaped wedge receivers 22 and 22 provided on the two sides and wedge bodies 23 provided at both ends of each material 12, 13 </ b> A and 13 </ b> B. In the present embodiment, the wedge receiver 21 is arranged on the lower side of the wedge receiver 22 so as to form a step. The wedge bodies 23, 23 at both ends of the horizontal member 12 are inserted into the opposite wedge receivers 21, 21 of the corresponding pillars 11 </ b> A, 11 </ b> B corresponding to the front and rear, and are pressed down to couple the wedges. The wedge bodies 23, 23 at both ends of the front connecting member 13A are inserted into the opposing wedge receivers 22, 22 of the adjacent front pillars 11A, 11A and pushed down to be wedge-coupled. The wedge bodies 23 and 23 at both ends of the rear connecting member 13B are inserted into the opposing wedge receivers 22 and 22 of the adjacent rear columns 11B and 11B and pushed down, thereby being wedge-coupled.

従って、足場ユニット10は、図2に示す如く、建築現場の地上にて以下の如くに構築される。   Therefore, as shown in FIG. 2, the scaffold unit 10 is constructed as follows on the ground of the construction site.

(1)地面の上にアンダーベース1が設置され、アンダーベース1の上にパイプジャッキ2が着座される。   (1) The underbase 1 is installed on the ground, and the pipe jack 2 is seated on the underbase 1.

(2)各柱11A、11Bの下端中空部がアンダーベース1の上のパイプジャッキ2に挿通されて支持される。前後の相対応する柱11A、11Bの楔受21、21に横架材12の両端部の楔体23を楔結合し、前側の相隣る柱11A、11Aの楔受22に前連結材13Aの両端部の楔体23を楔結合し、後側の相隣る柱11B、11Bの楔受22に後連結材13Bの両端部の楔体23を楔結合し、相隣る横架材12、12に踏板14の両端部のフック14Aを係着する。   (2) The lower end hollow part of each pillar 11A, 11B is inserted and supported by the pipe jack 2 on the underbase 1. The wedge bodies 23 at both ends of the horizontal member 12 are wedge-coupled to the wedge receivers 21 and 21 of the pillars 11A and 11B corresponding to the front and rear, and the front coupling member 13A is connected to the wedge receivers 22 of the adjacent pillars 11A and 11A on the front side. The wedge bodies 23 at both ends of the rear connection member 13B are wedge-coupled, and the wedge bodies 23 at both ends of the rear connecting member 13B are wedge-coupled to the wedge receivers 22 of the adjacent pillars 11B and 11B on the rear side. 12, hooks 14 </ b> A at both ends of the tread plate 14 are engaged.

しかるに、建築現場では、足場ユニット10を上述の如くに地上にて構築し、複数個の足場ユニット10を建物の躯体に沿う上下方向に順に積層して足場を組立て、その後、解体する。即ち、地上でユニット化した足場ユニット10をクレーン100で吊り上げて下層側の設置済の足場ユニット10の上に搭載して連結し、又は上層で使用済となった足場ユニット10を下層側の足場ユニット10から外してクレーン100で地上に吊り下げる。以下、足場ユニット10を用いた足場の組立及び解体方法について説明する。   However, at the construction site, the scaffold unit 10 is constructed on the ground as described above, a plurality of scaffold units 10 are sequentially stacked in the vertical direction along the building frame, and the scaffold is assembled and then disassembled. That is, the scaffold unit 10 unitized on the ground is lifted by the crane 100 and mounted on and connected to the installed scaffold unit 10 on the lower layer side, or the used scaffold unit 10 on the lower layer is connected to the lower layer side scaffold. Remove from unit 10 and hang on the ground with crane 100. Hereinafter, a method for assembling and disassembling a scaffold using the scaffold unit 10 will be described.

即ち、本発明による足場の組立及び解体方法は、図1、図3に示す如く、足場ユニット10の前後の全柱11A、11Bを横切るように左右方向に延在されて配置される吊りビーム30を介して、当該足場ユニット10を吊り上げ又は吊り下ろす工程を有するものとする。このとき、吊りビーム30は、各柱11A、11Bに少なくとも軸方向にて止められ、クレーン100の上向き吊り力が作用する吊りビーム30を各柱11A、11Bと軸方向で係合させ、各柱11A、11Bを介して足場ユニット10の全体にその吊り力を伝達可能にするものである。   That is, according to the scaffold assembly and disassembly method of the present invention, as shown in FIGS. 1 and 3, the suspension beam 30 is arranged extending in the left-right direction so as to cross all the pillars 11A and 11B before and after the scaffold unit 10. It is assumed that the step of lifting or hanging the scaffold unit 10 is provided. At this time, the suspension beam 30 is stopped at least in the axial direction on the pillars 11A and 11B, and the suspension beam 30 on which the upward lifting force acts on the crane 100 is engaged with the pillars 11A and 11B in the axial direction. The suspension force can be transmitted to the entire scaffold unit 10 through 11A and 11B.

本実施例では、吊りビール30は、足場ユニット10の前側の全柱11Aに止められる前側吊りビーム31(具体的には柱11Aの正背面に添設されて一対をなす2本の前側吊りビーム31、31)と、足場ユニット10の後側の全柱11Bに止められる後側吊りビーム32(具体的には柱11Bの正背面に添設されて一対をなす2本の後側吊りビーム32、32)とからなる。2本のL形鋼からなる前側吊りビーム31、31が図1、図3、図4に示す如く、全柱11Aを正背両側から挟み、それらの前側吊りビーム31の一端側(左側2本の柱11Aの間)と他端側(右側2本の柱11Aの間)で、それらの前側吊りビーム31のウエブに挿通したボルト33及びナット34によりそれらの前側吊りビーム31、31の間に全柱11Aを挟持する。また、2本のL形鋼からなる後側吊りビーム32、32が図1、図3、図4に示す如く、全柱11Bを正背両側から挟み、それらの後側吊りビーム32の一端側(左側2本の柱11Bの間)と他端側(右側2本の柱11Bの間)で、それらの後側吊りビーム32のウエブに挿通したボルト33及びナット34によりそれらの後側吊りビーム32、32の間に全柱11Bを挟持する。   In this embodiment, the suspended beer 30 includes a front suspension beam 31 (specifically, two front suspension beams that are attached to the front and rear surfaces of the pillar 11A and are paired with each other). 31, 31) and a rear suspension beam 32 (specifically, two rear suspension beams 32 attached to the front and rear surfaces of the pillar 11B to be paired with the rear pillar 11B on the rear side of the scaffold unit 10). 32). As shown in FIGS. 1, 3, and 4, the front suspension beams 31, 31 made of two L-shaped steels sandwich the entire column 11 </ b> A from both sides of the back, and one end side of the front suspension beams 31 (two on the left side) Between the front suspension beams 31 and 31 by bolts 33 and nuts 34 inserted into the webs of the front suspension beams 31 on the other end side (between the two right pillars 11A). The entire pillar 11A is clamped. Further, as shown in FIGS. 1, 3, and 4, the rear suspension beams 32, 32 made of two L-shaped steels sandwich the entire column 11B from both sides of the back, and one end side of these rear suspension beams 32. At the other end (between the two right pillars 11B) (between the two left pillars 11B) and the bolts 33 and nuts 34 inserted into the webs of the rear suspension beams 32, the rear suspension beams are provided. The entire pillar 11B is sandwiched between 32 and 32.

更に、各前側吊りビーム31は各柱11Aの正背面に設けてある楔受21の下部にそれらのフランジを下から当て止めすることにて、各柱11Aに軸方向にて止められる。また、各後側吊りビーム32は、各柱11Bの正背面に設けてある楔受21の下部にそれらのフランジを下から当て止めすることにて、各柱11Bに軸方向にて止められる。尚、各前側吊りビーム31と各後側吊りビーム32の両端側の2位置には、それらのフランジに設けられたアイボルト35を介して、吊りワイヤ36の吊り輪37が着脱可能に連結されている。   Further, the front suspension beams 31 are stopped by the respective pillars 11A in the axial direction by applying the flanges to the lower portions of the wedge receivers 21 provided on the front and back surfaces of the respective pillars 11A. Further, the rear suspension beams 32 are stopped on the respective pillars 11B in the axial direction by applying their flanges to the lower portions of the wedge receivers 21 provided on the front and rear surfaces of the respective pillars 11B. Note that a suspension ring 37 of a suspension wire 36 is detachably connected to two positions on both ends of each front suspension beam 31 and each rear suspension beam 32 via eyebolts 35 provided on the flanges. Yes.

従って、足場の組立、解体に際し、足場ユニット10はクレーン100により以下の如くに吊られる。   Accordingly, when the scaffold is assembled and disassembled, the scaffold unit 10 is suspended by the crane 100 as follows.

(1)地上で足場ユニット10を構築した後、最上段の踏板14の上に立つ作業者により、前側吊りビーム31、31を足場ユニット10の全柱11Aに横切らせつつ、各柱11Aの楔受21の下部に対し軸方向にて当て止めして取付けるとともに、後側吊りビーム32、32を足場ユニット10の全柱11Bに横切らせつつ、各柱11Bの楔受21の下部に対し軸方向にて当て止めして取付ける。   (1) After constructing the scaffold unit 10 on the ground, an operator standing on the uppermost tread 14 causes the front suspension beams 31 and 31 to traverse all the pillars 11A of the scaffold unit 10 and the wedges of the pillars 11A. Axes are attached to the lower portions of the receivers 21 in the axial direction, and the rear suspension beams 32 and 32 are traversed across all the pillars 11B of the scaffold unit 10 while being axially attached to the lower parts of the wedge receivers 21 of the respective pillars 11B. Attach and fix with.

(2)クレーン100のフック101に、各前側吊りビーム31の吊りワイヤ36、各後側吊りビーム32の吊りワイヤ36を掛ける。クレーン100によりそれらの吊りビーム31、32を介して、足場ユニット10の全体を吊り上げる(図5)。クレーン100で吊り上げた足場ユニット10の柱11A、11Bの下端中空部を足場の下層側で設置済の足場ユニット10の柱11A、11Bの上端ほぞに差し込み、当該足場ユニット10を下層側の足場ユニット10の上に搭載して連結し、足場を組立てる。各吊りビーム31、32は足場ユニット10から取外される。   (2) The suspension wire 36 of each front suspension beam 31 and the suspension wire 36 of each rear suspension beam 32 are hung on the hook 101 of the crane 100. The entire scaffold unit 10 is lifted by the crane 100 via the suspension beams 31 and 32 (FIG. 5). The lower end hollow portions of the pillars 11A and 11B of the scaffold unit 10 lifted by the crane 100 are inserted into the upper end tenons of the pillars 11A and 11B of the scaffold unit 10 already installed on the lower layer side of the scaffold, and the scaffold unit 10 is placed on the lower side scaffold unit. Mount on 10 and connect to assemble scaffolding. Each suspension beam 31, 32 is removed from the scaffold unit 10.

(3)足場の上層で使用済となった足場ユニット10に、上述(1)におけると同様にして、前側吊りビーム31と後側吊りビーム32を取付ける。   (3) The front hanging beam 31 and the rear hanging beam 32 are attached to the used scaffold unit 10 in the upper layer of the scaffold in the same manner as in the above (1).

(4)クレーン100のフック101に各前側吊りビーム31の吊りワイヤ36、各後側吊りビーム32の吊りワイヤ36を掛け、クレーン100によりそれらの吊りビーム31、32を介して、足場ユニット10の全体を下層側の足場ユニット10から吊り上げて外し、当該足場ユニット10を地上に吊り下げ、足場を解体する。各吊りビーム31、32は足場ユニット10から取外される。   (4) The suspension wire 36 of each front suspension beam 31 and the suspension wire 36 of each rear suspension beam 32 are hung on the hook 101 of the crane 100, and the scaffold unit 10 is connected by the crane 100 via the suspension beams 31 and 32. The whole is lifted off from the lower layer side scaffold unit 10, the scaffold unit 10 is suspended on the ground, and the scaffold is disassembled. Each suspension beam 31, 32 is removed from the scaffold unit 10.

本実施例によれば、以下の作用効果を奏する。
(a)足場ユニット10の前後の全柱11A、11Bを横切るように配置されて各柱11A、11Bに少なくとも軸方向にて止められた吊りビーム30(31、32)を介して、当該足場ユニット10を吊り上げ又は吊り下ろす。従って、足場ユニット10の前後の柱11A、11Bの本数が多数本であっても、多数の吊りビーム30(31、32)を用意することなく、前後の全柱11A、11Bを横切る吊りビーム30(31、32)を用意し、この吊りビーム30(31、32)を各柱11A、11Bに少なくとも軸方向にて止めることにより、吊りビーム30(31、32)を足場ユニット10に簡易に取付けて吊ることができる。
According to the present embodiment, the following operational effects can be obtained.
(a) The scaffold unit 10 is arranged via the suspension beam 30 (31, 32) arranged so as to cross all the pillars 11A, 11B before and after the scaffold unit 10 and stopped at least in the axial direction by the pillars 11A, 11B. 10 is lifted or hung. Therefore, even if the number of the pillars 11A and 11B before and after the scaffold unit 10 is large, the suspension beam 30 crossing all the pillars 11A and 11B before and after without preparing a large number of suspension beams 30 (31, 32). (31, 32) is prepared, and the suspension beam 30 (31, 32) is simply attached to the scaffold unit 10 by stopping the suspension beam 30 (31, 32) at least on the pillars 11A, 11B in the axial direction. Can be hung.

(b)吊りビーム30(31、32)を前後の全ての柱11A、11Bに直に軸方向で止めることにより、中間の柱11A、11B、連結材13A、13B等を沈み込ませる如くに垂れ下げることなく、足場ユニット10の全体を変形させずに吊ることができ、足場ユニット10を安全、確実に吊ることができる。   (b) By hanging the suspension beam 30 (31, 32) directly on all the front and rear columns 11A, 11B in the axial direction, the intermediate beams 11A, 11B, the connecting members 13A, 13B and the like are suspended. The entire scaffold unit 10 can be hung without being deformed without being lowered, and the scaffold unit 10 can be hung safely and reliably.

(c)吊りビーム30(31、32)が、足場ユニット10の前側の全柱11Aに止められる前側吊りビーム31と、後側の全柱11Bに止められる後側吊りビーム32とからなる。従って、前側と後側の各吊りビーム31、32を用いて、足場ユニット10を上述(a)、(b)により安全、確実、簡易に吊ることができる。   (c) The suspension beam 30 (31, 32) includes a front suspension beam 31 that is secured to the entire pillar 11A on the front side of the scaffold unit 10 and a rear suspension beam 32 that is secured to the rear pillar 11B. Therefore, the scaffold unit 10 can be safely, reliably, and easily suspended by the above-described (a) and (b) using the front and rear suspension beams 31 and 32.

(d)足場ユニット10が、柱11A、11Bに着脱連結部20を介して、横架材12と前連結材13Aと後連結材13Bの各材のそれぞれが連結されてなり、各柱11A、11Bの踏板14の上方に設けられる前連結材13Aと後連結材13Bを手摺15としてなる着脱連結式であるものにした。着脱連結式足場ユニット10のメリット(柱、横架材12、前連結材13A、後連結材13B等の各材を別体として取扱うものであり、運搬保管時の嵩張りがないし、各材を軽作業で短時間にユニット化でき、各材の使用経過による変形ひずみも吸収してユニット化できる、長尺柱の採用によれば、1個の足場ユニット10で2層又は3層分(建物の2階又は3階分)等の足場を構築することもできる)を享持しながら、それらの各材を地上でユニット化したものを吊り上げ/吊り下げして建築現場における足場の組立及び解体の安全性、生産性を向上できる。   (d) The scaffold unit 10 is formed by connecting the respective members of the horizontal member 12, the front connecting member 13A, and the rear connecting member 13B to the pillars 11A and 11B via the attachment / detachment connecting part 20, and each pillar 11A, The front connecting member 13 </ b> A and the rear connecting member 13 </ b> B provided above the 11 </ b> B tread 14 are made to be a detachable connecting type as a handrail 15. Advantages of the detachable connection type scaffolding unit 10 (the pillar, the horizontal member 12, the front connecting member 13A, the rear connecting member 13B, etc. are handled separately, and there is no bulk at the time of transportation and storage. It can be unitized in a short time with light work, and can absorb the deformation strain due to the use of each material, and can be unitized. By adopting a long column, one scaffold unit 10 can be used for two or three layers (building Assembling and dismantling the scaffolding at the construction site by hoisting / suspending the unitized materials on the ground Safety and productivity can be improved.

着脱連結式足場ユニット10の踏板14の上で、吊りビーム30(31、32)の取付け、取外しを行なう作業者は、その腰高に設けられる手摺15により作業の安全を確保することもできる。   An operator who attaches and detaches the suspension beam 30 (31, 32) on the tread 14 of the detachable coupling type scaffold unit 10 can also ensure safety of work by the handrail 15 provided at the waist height.

着脱連結式足場ユニット10の前後の柱11A、11Bの本数が多数本であっても、前後の全柱11A、11Bを横切る吊りビーム30(31、32)を用意するだけで当該足場ユニット10を安全、確実、簡易に吊ることができる。   Even if the number of the front and rear columns 11A and 11B of the detachable linkage type scaffolding unit 10 is large, the scaffold unit 10 can be mounted only by preparing the suspension beam 30 (31, 32) crossing all the front and rear columns 11A and 11B. It can be hung safely, reliably and easily.

(e)着脱連結式足場ユニット10が、柱11A、11Bに設けられる楔受21、22と、各材に設けられる楔体23の組合せにより前記着脱連結部20を構成する楔緊結式足場ユニット10であり、前記吊りビーム30(31、32)が、各柱11A、11Bの楔受21の下部に当て止めされる。従って、前後の全柱11A、11Bを横切る吊りビーム30(31、32)をそれらの柱に添設し、各柱11A、11Bの楔受21の下部に当て止めすることで、吊りビーム30(31、32)を当該足場ユニット10に簡易に取付けできる。また、着脱連結式足場ユニット10の全体を変形させずに吊ることができるから、柱11A、11Bの楔受21、22や各材の楔体23等の折損を生ずるおそれもない。   (e) A wedge-coupled scaffold unit 10 in which the detachable coupling-type scaffold unit 10 constitutes the detachable coupling part 20 by a combination of wedge receivers 21 and 22 provided on the pillars 11A and 11B and a wedge body 23 provided on each material. The suspension beam 30 (31, 32) is held against the lower portion of the wedge receiver 21 of each column 11A, 11B. Therefore, the suspension beam 30 (31, 32) crossing all the front and rear pillars 11A, 11B is attached to the pillars, and is attached to the lower part of the wedge receiver 21 of each pillar 11A, 11B, so that the suspension beam 30 ( 31, 32) can be easily attached to the scaffold unit 10. In addition, since the entire detachable connection type scaffolding unit 10 can be hung without being deformed, there is no possibility that the wedge receivers 21 and 22 of the pillars 11A and 11B, the wedge bodies 23 of each material, and the like will be broken.

尚、本発明が適用される足場ユニットは、前後の各複数本の柱と、前後の相対応する柱同士を対にして連結する横架材と、前側の柱同士を連結する前連結材と、後側の柱同士を連結する後連結材と、各柱の所定高さ位置に支持される踏板とを有してなる足場ユニットであって、前後の相対応する柱同士を横架材により枠をなすように一体に連結し、又は前側の柱同士を前連結材により、後側の柱同士を後連結材によりそれぞれ枠をなすように一体に連結してなる枠式足場ユニット(例えば特開2003-138742に記載の足場ユニットA)であっても良い。本発明を枠式足場ユニットからなる足場の組立及び解体方法に適用したときには、枠式足場ユニットのメリット(相対する枠と枠を筋交いによって固定気的に連結することにより高強度のユニットを構築できる)を享持しながら、それらの各材を地上でユニット化したものを吊り上げ/吊り下げして建築現場における足場の組立及び解体の安全性、生産性を向上できる。   The scaffold unit to which the present invention is applied includes a plurality of front and rear columns, a horizontal member that connects the front and rear corresponding columns in pairs, and a front connecting member that connects the front columns. A scaffold unit comprising a rear connecting member for connecting the rear pillars and a step board supported at a predetermined height position of each pillar, and the corresponding pillars on the front and rear sides are supported by a horizontal member. A frame-type scaffolding unit (for example, specially connected to form a frame, or by integrally connecting the front columns to each other with a front coupling material and the rear columns to each other with a rear coupling material. It may be a scaffold unit A) described in Kai 2003-138742. When the present invention is applied to a method of assembling and disassembling a scaffold composed of a frame-type scaffold unit, the advantages of the frame-type scaffold unit (a high-strength unit can be constructed by fixedly connecting the opposing frames to each other by struts. ) Can be lifted / suspended by unitizing these materials on the ground to improve the safety and productivity of assembling and dismantling the scaffolding at the construction site.

枠式足場ユニットの前後の柱の本数が多数本であっても、前後の全柱を横切る吊りビームを用意するだけで当該足場ユニットを安全、確実、簡易に吊ることができる。   Even if the number of pillars before and after the frame-type scaffolding unit is large, it is possible to suspend the scaffolding unit safely, surely, and simply by preparing a suspension beam that crosses all the pillars before and after.

以上、本発明の実施例を図面により詳述したが、本発明の具体的な構成はこの実施例に限られるものではなく、本発明の要旨を逸脱しない範囲の設計の変更等があっても本発明に含まれる。例えば、足場ユニット10に設けられる吊りビームは前後の柱11A、11Bに共通して適用される1本物でも良い。また、吊りビーム30を前後の吊りビーム31、32に分割したとき、各吊りビーム31、32は前後の柱11A、11Bの外側面(足場ユニット10の外方に臨む面)に穿設される1本物でも良い。足場ユニット10において、1本物の吊りビーム30、31、32を採用するとき、それらの吊りビーム30、31、32は柱11A、11Bに例えばUボルト等を用いて取付けられる。   The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration of the present invention is not limited to this embodiment, and even if there is a design change or the like without departing from the gist of the present invention. It is included in the present invention. For example, the suspension beam provided in the scaffold unit 10 may be a single beam that is commonly applied to the front and rear columns 11A and 11B. Further, when the suspension beam 30 is divided into the front and rear suspension beams 31 and 32, the suspension beams 31 and 32 are drilled on the outer side surfaces of the front and rear columns 11A and 11B (surfaces facing the outside of the scaffold unit 10). One thing may be sufficient. When the single suspension beam 30, 31, 32 is employed in the scaffold unit 10, these suspension beams 30, 31, 32 are attached to the pillars 11A, 11B using, for example, U bolts.

また、足場ユニット10において、吊りビーム30、31、32を柱11A、11Bに少なくとも軸方向にて止める手段は、楔緊結式足場ユニットにおける楔受に限らず、実質的に吊りビーム30、31、32を柱11A、11Bに少なくとも軸方向にて固定的に止め得るものであれば、いかなるものでも良い。   In the scaffold unit 10, the means for stopping the suspension beams 30, 31, 32 on the pillars 11 </ b> A, 11 </ b> B at least in the axial direction is not limited to the wedge receiver in the wedge-tightened scaffold unit, but substantially the suspension beams 30, 31, Any material can be used as long as it can fix 32 to the pillars 11A and 11B at least in the axial direction.

本発明は、前後の各複数本の柱と、前後の相対応する柱同士を対にして連結する横架材と、前側の柱同士を連結する前連結材と、後側の柱同士を連結する後連結材と、各柱の所定高さ位置に支持される踏板とを有してなる足場ユニットの複数個を、上下方向に積層してなる足場の組立及び解体方法において、足場ユニットの前後の全柱を横切るように配置されて各柱に少なくとも軸方向にて止められた吊りビームを介して、当該足場ユニットを吊り上げ又は吊り下ろす工程を有してなるものにした。本発明によれば、クレーン等で足場ユニットを安全、確実、簡易に吊ることができる。   The present invention connects a plurality of front and rear columns, a horizontal member that connects the front and rear corresponding columns in pairs, a front connecting member that connects the front columns, and a rear column. In a method for assembling and disassembling a scaffold in which a plurality of scaffold units each having a rear connecting member and a step board supported at a predetermined height position of each pillar are stacked in the vertical direction, before and after the scaffold unit The scaffold unit is lifted or suspended via a suspension beam that is arranged so as to cross all of the pillars and is fixed to each pillar at least in the axial direction. According to the present invention, the scaffold unit can be safely, reliably, and easily suspended with a crane or the like.

10 足場ユニット
11A、11B 柱
12 横架材
13A 13B 連結材
14 踏板
15 手摺
20 着脱連結部
21、22 楔受
23 楔体
30 吊りビーム
31 前側吊りビーム
32 後側吊りビーム
DESCRIPTION OF SYMBOLS 10 Scaffolding unit 11A, 11B Pillar 12 Horizontal member 13A 13B Connecting material 14 Tread 15 Handrail 20 Detachable connecting part 21, 22 Wedge holder 23 Wedge body 30 Hanging beam 31 Front hanging beam 32 Rear hanging beam

Claims (3)

前後の各複数本の柱と、前後の相対応する柱同士を対にして連結する横架材と、前側の柱同士を連結する前連結材と、後側の柱同士を連結する後連結材と、各柱の所定高さ位置に支持される踏板とを有してなる足場ユニットの複数個を、上下方向に積層してなる足場の組立及び解体方法において、
足場ユニットの前後の全柱を横切るように配置されて各柱に少なくとも軸方向にて止められた吊りビームを介して、当該足場ユニットを吊り上げ又は吊り下ろす工程を有してなり、
前記足場ユニットが、柱に着脱連結部を介して、横架材と前連結材と後連結材の各材のそれぞれが連結され、柱に設けられる楔受と、各材に設けられる楔体の組合せにより該着脱連結部を構成する楔緊結式足場ユニットであり、
前記吊りビームが、各柱の楔受の下部に当て止めされることを特徴とする足場の組立及び解体方法。
A plurality of front and rear columns, a horizontal member that connects the corresponding front and rear columns in pairs, a front connecting material that connects the front columns, and a rear connecting material that connects the rear columns And a method for assembling and disassembling a scaffold in which a plurality of scaffold units each having a footboard supported at a predetermined height position of each pillar are stacked in the vertical direction,
A step of lifting or lowering the scaffold unit via a suspension beam that is arranged so as to cross all the columns before and after the scaffold unit and is stopped at least in the axial direction on each column ;
The scaffold unit is configured such that each of the horizontal member, the front connecting member, and the rear connecting member is connected to the pillar via an attaching / detaching connecting portion, a wedge receiver provided on the pillar, and a wedge body provided on each member. A wedge-tightening type scaffolding unit that constitutes the detachable connecting portion by a combination;
A method for assembling and disassembling a scaffold, wherein the suspension beam is held against a lower portion of a wedge receiver of each pillar .
前記吊りビームが、足場ユニットの前側の全柱に止められる前側吊りビームと、後側の全柱に止められる後側吊りビームとからなる請求項1に記載の足場の組立及び解体方法。   The method of assembling and disassembling a scaffold according to claim 1, wherein the suspension beam comprises a front suspension beam that is secured to all the pillars on the front side of the scaffold unit and a rear suspension beam that is secured to all the pillars on the rear side. 前記足場ユニットが、前後の相対応する柱同士を横架材により枠をなすように一体に連結し、又は前側の柱同士を前連結材により、後側の柱同士を後連結材によりそれぞれ枠をなすように一体に連結してなる枠式足場ユニットである請求項1又は2に記載の足場の組立及び解体方法。   The scaffold unit integrally connects the front and rear corresponding columns so as to form a frame with a horizontal member, or the front columns are framed by the front coupling material, and the rear columns are framed by the rear coupling material, respectively. The method of assembling and disassembling a scaffold according to claim 1 or 2, wherein the scaffold is a frame-type scaffold unit that is integrally connected so as to form a frame.
JP2009072776A 2009-03-24 2009-03-24 Scaffold assembly and disassembly method Active JP4975051B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009072776A JP4975051B2 (en) 2009-03-24 2009-03-24 Scaffold assembly and disassembly method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009072776A JP4975051B2 (en) 2009-03-24 2009-03-24 Scaffold assembly and disassembly method

Publications (2)

Publication Number Publication Date
JP2010222884A JP2010222884A (en) 2010-10-07
JP4975051B2 true JP4975051B2 (en) 2012-07-11

Family

ID=43040367

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009072776A Active JP4975051B2 (en) 2009-03-24 2009-03-24 Scaffold assembly and disassembly method

Country Status (1)

Country Link
JP (1) JP4975051B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106994589A (en) * 2017-05-10 2017-08-01 新发中建融资租赁有限公司 Vertical rod bowl button demountor

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7158716B2 (en) * 2018-10-23 2022-10-24 有限会社佐野仮設興業 Connectors for assembling and dismantling scaffolding
CN110805262B (en) * 2019-11-16 2021-07-02 江苏优美特工程技术有限公司 Scaffold base with adjustable angle for building

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2775265B2 (en) * 1988-10-28 1998-07-16 日本ビソー株式会社 Wall moving scaffolding device
JPH0525927A (en) * 1991-07-23 1993-02-02 Yuko Nomura Assembling and disassembling of prefabricated scaffolding
JPH0814198B2 (en) * 1992-04-08 1996-02-14 株式会社福田組 Method for assembling frame scaffold and guide metal fitting for assembling frame scaffold
JP3200788B2 (en) * 1993-12-01 2001-08-20 清水建設株式会社 Installation structure of the frame of the external curing coating
JP3868240B2 (en) * 2001-08-10 2007-01-17 信建エンジニアリング株式会社 Connection structure in temporary structure
JP2005188275A (en) * 2003-12-02 2005-07-14 Sugikou:Kk Preceding handrail for temporary scaffold

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106994589A (en) * 2017-05-10 2017-08-01 新发中建融资租赁有限公司 Vertical rod bowl button demountor
CN106994589B (en) * 2017-05-10 2019-04-02 新发中建融资租赁有限公司 Upright bar bowl buckle demountor

Also Published As

Publication number Publication date
JP2010222884A (en) 2010-10-07

Similar Documents

Publication Publication Date Title
KR101654483B1 (en) The building is equipped with safety scaffold equipment
EP2880228B1 (en) Scaffold structure
US9861190B2 (en) Wood gang form and method for constructing concrete building using same
KR101641340B1 (en) Gang form cage having safety upper and lower worktable
JP4975051B2 (en) Scaffold assembly and disassembly method
JP2014009453A (en) Temporary scaffold assembly jig and assembling method
EP1691007B1 (en) Detachable cross-piece for supporting platforms in scaffolds
JP7158716B2 (en) Connectors for assembling and dismantling scaffolding
JP6355264B2 (en) Suspended scaffolding, suspension scaffold installation method and suspension bracket
JP4482738B2 (en) Hanging hangers for scaffold units
KR20130104923A (en) Assembled gang form
JP7240959B2 (en) Hanging jig and steel tower dismantling method
JP4690383B2 (en) Dismantling gondola unit
JP4951056B2 (en) Working frame dismantling method
KR20100084409A (en) Prefabricated gang form assembly
JP5255914B2 (en) Dismantling method of boiler and boiler building
JP6299825B2 (en) Equilibrium balancing weight device, construction tool for balancing weight device, and construction method for balancing weight device
JP2017206859A (en) Assembling method of hanging foothold and a column used therefor
JP4006697B2 (en) Suspended scaffold for structure and fixing method thereof
CN104005547A (en) Suspension scaffold attached to wall
JP4343525B2 (en) Elevator hoistway unit
JP6529874B2 (en) Method of dismantling a concrete column, and articulated rod device
JP5479645B1 (en) Master rope support and support structure of master rope support
JP3892240B2 (en) Working scaffold and assembly method thereof
JP4127395B2 (en) Method for assembling / disassembling frame scaffolds using scaffold base blocks, and method for assembling / disassembling scaffold base blocks

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20111129

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120105

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120301

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120403

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120410

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150420

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250