JP4798381B2 - Shield tunnel and its construction method, backfilling method, building / backfilling method - Google Patents

Shield tunnel and its construction method, backfilling method, building / backfilling method Download PDF

Info

Publication number
JP4798381B2
JP4798381B2 JP2007039287A JP2007039287A JP4798381B2 JP 4798381 B2 JP4798381 B2 JP 4798381B2 JP 2007039287 A JP2007039287 A JP 2007039287A JP 2007039287 A JP2007039287 A JP 2007039287A JP 4798381 B2 JP4798381 B2 JP 4798381B2
Authority
JP
Japan
Prior art keywords
machine
backfilling
shield tunnel
shield
backfill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2007039287A
Other languages
Japanese (ja)
Other versions
JP2008202296A (en
Inventor
利光 阿曽
芳文 上原
克美 門田
広幸 伊藤
芳人 中島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2007039287A priority Critical patent/JP4798381B2/en
Publication of JP2008202296A publication Critical patent/JP2008202296A/en
Application granted granted Critical
Publication of JP4798381B2 publication Critical patent/JP4798381B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、シールドトンネルおよびその築造工法、埋め戻し工法、築造・埋め戻し工法に関する。   The present invention relates to a shield tunnel and its construction method, backfilling method, and building / backfilling method.

シールドトンネルを仮設的に築造するような場合、たとえば大規模な大断面トンネルの築造に際してその周囲に先行トンネルとして小断面のシールドトンネルを仮設的に築造する場合、あるいは、本設トンネルを築造するための発進立坑や到達立坑を本設トンネルから離れた位置に設置してそれらの間を連絡するためのシールドトンネルを仮設的に設けるような場合等においては、仮設的に築造したシールドトンネルを用済み後に埋め戻して用地を現状に復旧しなければならない場合がある。   When constructing a shield tunnel temporarily, for example, when constructing a large-scale tunnel with a small cross-section as a preceding tunnel around it, or to construct a main tunnel In cases such as when installing a shield tunnel for temporarily connecting the start and end shafts at a position away from the main tunnel and establishing a temporary connection between them, the temporarily constructed shield tunnel is used. It may be necessary to backfill later to restore the site to the current state.

その場合、埋め戻すべきシールドトンネルの内周面には覆工体としてのセグメントが全面的に組み付けられているので、埋め戻しに先だってまずそれらのセグメントを解体撤去する必要があり、そのようなセグメントの解体撤去とその後の埋め戻しを一連の作業として効率的に行うための工法としては、たとえば特許文献1〜3に示されているような既設トンネルや既設管渠を解体撤去するための工法が採用可能であると考えられる。
それらの工法は、解体用のシールド機やそれに類する解体機を前進させつつその内側でセグメントや既設管渠を解体撤去するとともに、解体機の後方に埋め戻し材を充填していくことを基本とするものであり、通常のシールド工法によるシールドトンネルの築造工程とは逆の工程によってシールドトンネルを効率的に埋め戻していくことが可能であるとされている。
特許第3087229号公報 特許第3581619号公報 特許第3721488号公報
In that case, since the segments as the lining body are fully assembled on the inner peripheral surface of the shield tunnel to be backfilled, it is necessary to dismantle and remove those segments first before backfilling. As a construction method for efficiently performing the dismantling and subsequent backfilling as a series of operations, for example, there is a construction method for dismantling and removing existing tunnels and existing pipes as shown in Patent Documents 1 to 3 It is considered that it can be adopted.
These methods are based on the fact that while disassembling shield machines and similar demolition machines move forward, the segments and existing pipes are dismantled and removed, and backfill material is filled behind the demolition machine. It is said that the shield tunnel can be efficiently backfilled by a process reverse to the shield tunnel construction process by a normal shield method.
Japanese Patent No. 3087229 Japanese Patent No. 3581619 Japanese Patent No. 3721488

しかし、上記従来の工法は埋め戻しの範囲やその目的によっては必ずしも好適に採用できない場合がある。
すなわち、シールドトンネルを単に全長にわたって埋め戻す場合には、埋め戻すべきシールドトンネルのいずれか一方の坑口(あるいは発進立坑)から解体機を進入させ、他方の坑口(あるいは到達立坑)に向けて前進させていきつつセグメントの解体撤去と埋め戻しを行えば良く、それによりシールドトンネルの全長を支障なく効率的に埋め戻すことが可能である。
However, the above conventional method may not always be suitably employed depending on the range of backfill and its purpose.
In other words, when the shield tunnel is simply refilled over its entire length, the dismantling machine is entered from one of the shield tunnels (or start-up shafts) to be backfilled, and advanced toward the other tunnel (or the reaching shaft). It is only necessary to dismantle and backfill the segments while continuing to efficiently backfill the entire length of the shield tunnel.

ところが、全長にわたる埋め戻しが不要な場合、あるいは不可能な場合等においては、シールドトンネルの途中から埋め戻しを開始したい場合もあり、そのような場合には上記従来の工法はそのまま採用できるものではない。
つまり、シールドトンネルの途中から埋め戻しを開始する場合には、まず埋め戻し開始地点に解体機を配置しなければならないが、そのためには解体機を埋め戻し開始地点に搬入するために地表から開削を行うか、少なくとも立坑を設ける必要がある。
あるいは、解体機を搬入可能な大きさのパーツに分解しておいて、各パーツを個別に搬入して埋め戻し開始地点において解体機を組み立てることも考えられなくはないが、その場合には埋め戻し開始地点におけるセグメントを解体してそこを一時的であるにせよ無覆工状態としなければならないから、それに先だって周囲地盤を凍結工法や薬液注入工法により改良する必要が生じる。
However, in cases where backfilling over the entire length is unnecessary or impossible, it may be desired to start backfilling in the middle of the shield tunnel. In such a case, the above conventional method cannot be used as it is. Absent.
In other words, when refilling is started from the middle of a shield tunnel, the demolition machine must first be placed at the backfill start point, but for that purpose, the demolition machine must be excavated from the ground surface to be carried into the backfill start point. Or at least a shaft is required.
Alternatively, it can be considered that the dismantling machine is disassembled into parts that can be carried in, each part is individually carried in, and the dismantling machine is assembled at the backfill start point. Since the segment at the return start point must be dismantled and put into an uncovered state even if it is temporary, the surrounding ground needs to be improved by a freezing method or a chemical injection method prior to that.

このように、特許文献1〜3に示されるような解体機を使用してシールドトンネルを途中から埋め戻すようなことは、解体機を埋め戻し開始地点に配置するためだけに大がかりな準備工程が必要であって不合理であり、現実的ではないと考えられる。   Thus, backfilling the shield tunnel from the middle using the demolition machine as shown in Patent Documents 1 to 3 is a large preparation process only for placing the demolition machine at the backfill start point. It is necessary, irrational, and not considered realistic.

上記事情に鑑み、本発明は、築造後にはその途中から埋め戻すことを前提とするシールドトンネルと、その築造および埋め戻しを効率的に行い得る有効適切な工法を提供することを目的とする。   In view of the above circumstances, an object of the present invention is to provide a shield tunnel that is assumed to be backfilled after the construction, and an effective and appropriate construction method that can efficiently perform the construction and backfilling.

請求項1記載の発明のシールドトンネルは、シールド機を掘進しつつその後方でセグメントを組み立てることによって築造されるとともに、築造後にその途中の任意の位置を始点としてセグメントが解体されて埋め戻されるシールドトンネルであって、当該シールドトンネルは、築造後に埋め戻し工程を開始するべき埋め戻し開始予定地点に対し、該埋め戻し工程において使用される解体機のスキンプレートとなる筒状の支保部材が、当該シールドトンネルを築造する工程においてセグメントの外側の位置に予め設置されていることを特徴とする。 The shield tunnel according to the first aspect of the present invention is constructed by assembling a segment behind the shield machine while excavating the shield machine, and after the construction, the shield is disassembled and backfilled starting from an arbitrary position in the middle of the shield tunnel a tunnel, the shield tunnel, against the scheduled start point backfill should begin backfill after construction process, the skin plate to become cylindrical支保member demolition machine used in step back Me 該埋, the In the process of building a shield tunnel, the shield tunnel is preliminarily installed at a position outside the segment.

請求項2記載の発明は、請求項1記載の発明のシールドトンネルを築造するに際し、シールド機を掘進しつつその後方でセグメントを組み立てていくとともに、シールド機が埋め戻し開始予定地点を通過する際には解体機のスキンプレートとなる筒状の支保部材をセグメントの外側の位置に設置することを特徴とする。   When the shield tunnel of the invention according to claim 1 is built, the segment is assembled behind the shield machine while digging the shield machine, and the shield machine passes the planned backfill start point. Is characterized in that a cylindrical support member serving as a skin plate for the dismantling machine is installed at a position outside the segment.

請求項3記載の発明は、請求項1記載の発明のシールドトンネルを埋め戻すに際し、埋め戻し開始予定地点に設置されている支保部材をスキンプレートとする解体機を組み立て、該解体機により支保しつつその内側においてセグメントを解体して撤去するとともに、該解体機を移動させていきつつその移動方向後方側に埋め戻し材を充填していくことを特徴とする。   When the shield tunnel of the invention according to claim 1 is backfilled, the invention according to claim 3 assembles the dismantling machine using the support member installed at the planned start point of backfilling as a skin plate, and is supported by the dismantling machine. While disassembling and removing the segment on the inside, the disassembling machine is moved and a backfill material is filled on the rear side in the moving direction.

請求項4記載の発明は、シールド機を掘進しつつその後方でセグメントを組み立てることによって築造されるとともに、任意の位置を始点としてセグメントが解体されて埋め戻されるシールドトンネルを築造し埋め戻すための工法であって、シールドトンネルを築造する工程においては、シールド機が埋め戻し開始予定地点を通過する際に、解体機のスキンプレートとなる筒状の支保部材をセグメントの外側の位置に設置し、築造したシールドトンネルを埋め戻す工程においては、埋め戻し開始予定地点において前記支保部材をスキンプレートとする解体機を組み立て、該解体機により支保しつつその内側においてセグメントを解体して撤去するとともに、該解体機を移動させていきつつその移動方向後方側に埋め戻し材を充填していくことを特徴とする。   The invention according to claim 4 is for constructing and refilling a shield tunnel in which a segment is disassembled and backfilled at an arbitrary position, while being constructed by assembling segments behind the shield machine while excavating the shield machine In the process of building a shield tunnel, when the shield machine passes the planned backfill start point, a cylindrical support member that becomes the skin plate of the demolition machine is installed at a position outside the segment, In the process of backfilling the built shield tunnel, a dismantling machine using the support member as a skin plate is assembled at the planned start point of backfilling, and the segments are dismantled and removed while being supported by the dismantling machine, Filling backfill material on the rear side in the moving direction while moving the demolition machine And features.

請求項5記載の発明は、請求項4記載の発明のシールドトンネルの築造・埋め戻し工法であって、シールドトンネルを築造するためのシールド機には、そのスキンプレートのテール部の内側に予め支保部材を組み付けておき、該シールド機を埋め戻し開始予定地点を通過させる際に、前記支保部材をスキンプレートから切り離して埋め戻し開始予定地点に残置していくことを特徴とする。   The invention according to claim 5 is the shield tunnel construction / backfill method according to claim 4, wherein the shield machine for constructing the shield tunnel is previously supported inside the tail portion of the skin plate. When the member is assembled and the shield machine is passed through the planned backfill start point, the support member is separated from the skin plate and left at the planned backfill start point.

請求項6記載の発明は、請求項4または5記載の発明のシールドトンネルの築造・埋め戻し工法であって、解体機を組み立てるに際しては、該解体機のスキンプレートとなる支保部材の内側に、埋め戻し材の充填用型枠として機能する面板を設け、前記解体機の移動方向後方側に埋め戻し材を充填する際には、前記面板の背面側に埋め戻し材を加圧充填することを特徴とする。   The invention according to claim 6 is the construction and backfilling method of the shield tunnel according to the invention according to claim 4 or 5, and when assembling the dismantling machine, inside the support member that becomes the skin plate of the dismantling machine, A face plate that functions as a mold for filling backfill material is provided, and when filling backfill material on the rear side in the moving direction of the demolition machine, the backfill material is pressure-filled on the back side of the faceplate. Features.

本発明のシールドトンネルによれば、将来的に解体埋め戻しがなされることを想定してその埋め戻し開始予定地点に予め支保部材が設置されているので、埋め戻しが開始されるまではセグメントに代わって支保部材により支保効果と止水効果が支障なく確保し得ることはもとより、埋め戻しを開始する際には支保部材をスキンプレートとする簡易な解体機を容易に組み立てることが可能であり、その解体機によりセグメントの解体撤去と埋め戻しを安全かつ効率的に実施することが可能である。   According to the shield tunnel of the present invention, since a support member is installed in advance at the planned backfill start point assuming that dismantling and backfilling will be performed in the future, until the backfilling is started, Instead, it is possible to easily assemble a simple demolition machine with the support member as a skin plate when starting backfilling, as well as ensuring that the support effect and water stopping effect can be secured without problems by the support member. The dismantling machine can safely and efficiently implement dismantling and backfilling of segments.

本発明の工法によれば、上記のシールドトンネルを築造する際には予め埋め戻し開始予定位置に支保部材を設置しておき、埋め戻しを開始する際にはその支保部材をスキンプレートとする簡易な解体機を組み立てるので、その解体機を使用することによってセグメントの解体撤去と埋め戻しとを一連の作業として効率的にかつ安全確実に実施できることはもとより、従来のように解体機をシールドトンネル内に搬入するための開削や立坑の設置あるいは地盤改良工事を不要とでき、したがって埋め戻し工程を実施するための準備作業を大幅に軽減し格段に合理化することができ、従来工法に比べて工期短縮と工費削減を充分に図ることができる。   According to the construction method of the present invention, when the shield tunnel is constructed, a support member is installed in advance at a position to start backfilling, and when the backfilling is started, the support member is simply used as a skin plate. Since the dismantling machine is assembled, the dismantling and removal of the segments can be efficiently and safely performed as a series of operations by using the dismantling machine. This eliminates the need for excavation, installation of shafts, or ground improvement work for loading into the construction site, thus significantly reducing the preparation work for implementing the backfilling process and greatly streamlining the construction period compared to conventional methods. And the construction cost can be reduced sufficiently.

本発明のシールドトンネルと、それを築造し埋め戻すための工法の一実施形態を図1〜図14に示す。
本実施形態は、用済み後にはその途中から埋め戻すことを前提とするシールドトンネルを仮設的に築造する場合に適用されるものであり、図1〜図9はその築造工程を示し、図10〜図14は埋め戻し工程を示すものである。
なお、以下の説明においては、築造工程におけるシールド機の掘進方向を基準として図示左方を前方、図示右方を後方といい、したがってシールド機の図示左方への移動を前進、解体機の図示右方への移動を後退ということとする。
One Embodiment of the shield tunnel of this invention and the construction method for building and refilling it is shown in FIGS.
This embodiment is applied to the case where a shield tunnel is temporarily built on the premise that it is buried back after use, and FIGS. 1 to 9 show the building process, and FIG. FIG. 14 shows the backfilling process.
In the following description, the left side in the figure is referred to as the front and the right side in the figure is referred to as the rear, based on the direction of the shield machine in the building process, and therefore the movement of the shield machine to the left in the figure is advanced. The movement to the right is called backward.

図1〜図9に示す築造工程は基本的には通常のシールド工法と同様にシールド機による掘進により行うのであるが、そのシールド機には、後段での埋め戻し工程において使用する解体機の主要構成要素である支保部材を予め組み込んでおき、築造工程の際にその支保部材を埋め戻し開始予定地点に残置していくことを主眼とする。   The building process shown in FIG. 1 to FIG. 9 is basically performed by excavation with a shield machine in the same manner as a normal shield method, but the shield machine is mainly used for the demolition machine used in the backfill process at the later stage. The main purpose is to incorporate a support member as a component in advance and leave the support member at a planned start point for backfilling during the building process.

具体的には、図1に示すようにシールド機1のスキンプレート2のテール部の内側にそれ自体がスキンプレートとして機能する筒状の支保部材3を予め組み付けておき、その内側およびスキンプレート2との間にはそれぞれシール部材4を取り付けておく。
そして、図1〜図3に示すように、シールド機1の後方にセグメント5を組み立て、セグメント5から反力をとって推進ジャッキ6によりシールド機1を前進させてはその後方に新たなセグメント5を継ぎ足してさらに前進させていくという通常のシールド工法により、シールドトンネルを築造していく。
Specifically, as shown in FIG. 1, a cylindrical support member 3 that itself functions as a skin plate is assembled in advance inside the tail portion of the skin plate 2 of the shield machine 1, and the inside and the skin plate 2 A seal member 4 is attached between the two.
As shown in FIGS. 1 to 3, the segment 5 is assembled behind the shield machine 1, the reaction force is taken from the segment 5, and the shield machine 1 is advanced by the propulsion jack 6. The shield tunnel will be built by the usual shield construction method, which will be further advanced by adding.

図3に示すようにシールド機1が埋め戻し開始予定地点に到達したら、図4に示すようにスキンプレート2から支保部材3を切り離し、フランジ部3aを有する筒状の延長部材3bをその前部に継ぎ足して支保部材3を前方に延長する。
図5に示すように、延長した支保部材3のフランジ3aと組み立て済みのセグメント5の最前部との間に反力受け部材7を介装し、図6に示すように推進ジャッキ6により支保部材3のフランジ部3a、反力受け部材7を介してセグメント5から反力をとってシールド機1を前進させるとともに、支保部材3はそこに残置する。そして、図7〜図9に示すように、フランジ部3aの前部に新たなセグメント5を組み立てていきつつシールド機1をさらに前進させていく。
そのようにしてシールドトンネルを築造していくことにより、埋め戻し開始地点においてはセグメント5が省略されてそれに代わる反力受け部材7が配置されるとともにその外側には支保部材3が残置され、その支保部材3がセグメントに代わってそこでの支保性能と止水性を支障なく確保するものとなる。
なお、反力受け部材7としては埋め戻し工程において容易に取り外すことができるものである限りにおいて適宜の部材が採用可能であるが、埋め戻すまでは実質的にセグメントと同様に機能するものであることが好ましく、したがって可能であればセグメント5を反力受け部材7として使用して取り外し可能に組み付けておくことも考えられる。
As shown in FIG. 3, when the shield machine 1 reaches the planned backfill start point, the support member 3 is separated from the skin plate 2 as shown in FIG. 4, and the cylindrical extension member 3b having the flange portion 3a is moved to its front portion. And the support member 3 is extended forward.
As shown in FIG. 5, a reaction force receiving member 7 is interposed between the flange 3a of the extended support member 3 and the foremost part of the assembled segment 5, and the support member is supported by the propulsion jack 6 as shown in FIG. The shield machine 1 is moved forward by taking the reaction force from the segment 5 via the flange portion 3a of 3 and the reaction force receiving member 7, and the support member 3 is left there. Then, as shown in FIGS. 7 to 9, the shield machine 1 is further advanced while assembling a new segment 5 at the front portion of the flange portion 3 a.
By constructing the shield tunnel in this way, the segment 5 is omitted at the refill start point, the reaction force receiving member 7 is arranged in place of it, and the supporting member 3 is left outside, The supporting member 3 can secure the supporting performance and water-stopping performance without any trouble in place of the segment.
As the reaction force receiving member 7, an appropriate member can be adopted as long as it can be easily removed in the backfilling process, but it functions substantially the same as the segment until backfilling. Therefore, it is also conceivable that the segment 5 is used as a reaction force receiving member 7 and is detachably assembled if possible.

以上の工程により築造したシールドトンネルを所望用途に使用した後、用済み後には上記の埋め戻し開始予定地点よりも後方(図示右方)を埋め戻すのであるが、そのためには図10〜図14に示すように開始予定地点において解体機8を組み立てて、そこから解体機8を後方に後退させていきつつセグメント5の解体撤去と埋め戻しを行う。   After the shield tunnel built by the above steps is used for a desired application, after use, the rear side (right side in the figure) is backfilled from the planned backfill start point. As shown in FIG. 4, the dismantling machine 8 is assembled at the scheduled start point, and the dismantling removal and backfilling of the segment 5 are performed while the dismantling machine 8 is moved backward from there.

すなわち、図10に示すように、埋め戻し開始予定地点に組み込んでおいた反力受け部材7を取り外し、そこに仕切り板9を設置してシールドトンネル内を残存部と埋め戻し部とに区画したうえで、埋め戻し部側に面板10を配置して支保部材3の内側に固定することにより、それら支保部材3と面板10とによって通常のシールド機の外殻と同様の形態の簡易な解体機8を形成し、面板10には埋め戻し材11の充填口12を取り付けておく。   That is, as shown in FIG. 10, the reaction force receiving member 7 incorporated at the planned backfill start point is removed, and a partition plate 9 is installed there to partition the shield tunnel into a remaining part and a backfill part. In addition, by disposing the face plate 10 on the backfill portion side and fixing the face plate 10 to the inside of the support member 3, the simple dismantling machine having the same form as the outer shell of a normal shield machine by the support member 3 and the face plate 10. 8 and the filling port 12 of the backfill material 11 is attached to the face plate 10.

そこで、その解体機8を埋め戻し開始予定位置から後退させていくことによってセグメント5の解体撤去と埋め戻しとを行う。勿論、その際の解体物の搬出や資機材の搬出入は後方側(図示右側)から行うことになる。
これにより、解体機8を構成している支保部材3は解体時の支保性能や止水性能を確保するためのスキンプレートとして機能し、面板10はその背面側(解体機8の移動方向に対して後方側)に埋め戻し材11を充填するとともに充填圧を維持するための型枠として機能するものとなる。
なお、埋め戻し材11としてはたとえば発泡モルタルが好適に採用可能である。また、埋め戻し部と残存部を区画するための仕切り板9が不要であればそれを省略してそこに簡易な型枠を設けるだけでも良い。
Therefore, the dismantling and refilling of the segment 5 is performed by retracting the dismantling machine 8 from the planned backfill start position. Of course, the dismantled material and materials and equipment are carried out at the rear side (right side in the figure).
Thereby, the supporting member 3 which comprises the demolishing machine 8 functions as a skin plate for ensuring the supporting performance at the time of a demolishing, and a water stop performance, and the face plate 10 is the back side (with respect to the moving direction of the demolishing machine 8). The back side) is filled with the backfill material 11 and functions as a mold for maintaining the filling pressure.
As the backfill material 11, for example, foamed mortar can be suitably used. Further, if the partition plate 9 for partitioning the backfill portion and the remaining portion is not necessary, it may be omitted and a simple formwork may be provided there.

上記の埋め戻し工程において解体機8を後退させるためには、図10に示すようにセグメント5にブラケット13を取り付けてそのブラケット13と面板10との間に押圧ジャッキ14を介装し、反力受け部材7を取り外して押圧ジャッキ14により面板10を支持しつつ面板10の背面側に埋め戻し材11を密に加圧充填し、それに伴い押圧ジャッキ14を縮退させていくことによて、充填圧とバランスをとりつつ充填圧を利用して解体機8を押し出せば良い。   In order to retract the dismantling machine 8 in the above-described backfilling process, as shown in FIG. 10, a bracket 13 is attached to the segment 5 and a pressing jack 14 is interposed between the bracket 13 and the face plate 10. Filling is performed by removing the receiving member 7 and densely filling the backfill material 11 on the back side of the face plate 10 while supporting the face plate 10 with the pressure jack 14, and depressing the pressure jack 14 accordingly. What is necessary is just to extrude the dismantling machine 8 using a filling pressure, balancing pressure.

図11に示すように解体機8が後退して面板10がセグメント5の位置に達したら、図12に示すように最前部のセグメント5を解体撤去するとともに、ブラケット13を後方に盛り替えた後、埋め戻し材11をさらに充填して解体機8をさらに後退させる。   When the dismantling machine 8 moves backward as shown in FIG. 11 and the face plate 10 reaches the position of the segment 5, the frontmost segment 5 is dismantled and the bracket 13 is rearranged rearward as shown in FIG. Then, the backfill material 11 is further filled and the dismantling machine 8 is further retracted.

以上の手順を繰り返して、図13〜図14に示すようにセグメント5を順次解体撤去していきつつ、それに後追いして埋め戻し材11を充填していき、それを埋め戻し部の終点まで繰り返し、最後に解体機8を解体して搬出すれば良い。   The above procedure is repeated, and the segments 5 are sequentially disassembled and removed as shown in FIGS. 13 to 14, and the backfill material 11 is followed up to the end of the backfill unit. Finally, the dismantling machine 8 may be disassembled and carried out.

以上の工法によれば、シールドトンネルを築造する際に予め埋め戻し開始予定位置に支保部材3を残置しておいて、埋め戻しを行う際にはそれをスキンプレートとする簡易な解体機8を組み立てるので、その解体機8を使用することによってセグメント5の解体撤去と埋め戻しとを一連の作業として効率的にかつ安全確実に実施できることはもとより、従来のように解体機8をシールドトンネル内に搬入するための開削や立坑の設置あるいは地盤改良工事を不要とできる。
したがって本工法の採用により、埋め戻し工程を実施するための準備作業を大幅に軽減して格段に合理化することができ、充分な工期短縮と工費削減を実現することができる。
According to the above construction method, when the shield tunnel is constructed, the supporting member 3 is left in advance at the position where the backfilling is scheduled, and when performing backfilling, the simple dismantling machine 8 using the skin plate as the skin plate is used. Since the disassembly machine 8 is used for assembly, the dismantling and refilling of the segment 5 can be efficiently and safely performed as a series of operations, and the disassembly machine 8 can be placed in a shield tunnel as in the past. It is possible to eliminate the need for excavation, installation of shafts, or ground improvement work for carrying in.
Therefore, by adopting this construction method, the preparation work for carrying out the backfilling process can be greatly reduced and greatly rationalized, and a sufficient shortening of the construction period and reduction of the construction cost can be realized.

以上、本発明の一実施形態を説明したが、上記実施形態はあくまで好適な一例に過ぎず、本発明は上記実施形態に限定されることなくたとえば以下に列挙するような様々な設計的変更や応用が可能である。   Although one embodiment of the present invention has been described above, the above embodiment is merely a preferable example, and the present invention is not limited to the above embodiment, and various design changes and the like listed below are possible. Application is possible.

上記実施形態では埋め戻し材11を加圧充填しつつその充填圧を利用して解体機8を移動させるようにしたが、それに代えて、あるいはそれに加えて、解体機8を他の手段により移動させることも考えられる。
たとえば、上記実施形態における押圧ジャッキ14を牽引手段として利用してそれを縮退させることによりセグメント5から反力をとって解体機8を引き寄せて移動させることでも良いし、あるいは特許文献2〜3に開示されているような牽引手段を採用することも考えられる。
In the above embodiment, the demolition machine 8 is moved by using the filling pressure while filling the backfill material 11 under pressure, but instead of or in addition to this, the demolition machine 8 is moved by other means. It is possible to make it.
For example, by using the pressing jack 14 in the above embodiment as a pulling means and retracting it, it is possible to take the reaction force from the segment 5 and pull the dismantling machine 8 to move or to Patent Documents 2-3. It is also conceivable to employ traction means as disclosed.

上記実施形態では解体機8のスキンプレートとしての支保部材3をシールド機1のスキンプレート2のテール部に予め組み付けておき、それを築造工程において埋め戻し開始予定地点において切り離してそこに残置するようにしたが、それに代えて、シールド機1が埋め戻し開始予定位置に達した時点でシールド機1内に支保部材3の構成パーツを搬入し、セグメント5を組み立てるに先立ってそこで支保部材3を組み立ててセグメント5の外側に設置することでも良い。   In the above embodiment, the support member 3 as the skin plate of the dismantling machine 8 is assembled in advance to the tail portion of the skin plate 2 of the shield machine 1 so that it is separated and left at the planned backfill start point in the building process. However, instead, when the shield machine 1 reaches the planned backfill start position, the components of the support member 3 are carried into the shield machine 1 and the support member 3 is assembled there before assembling the segment 5. It may be installed outside the segment 5.

上記実施形態では解体機8を埋め戻し開始地点から後方(築造工程におけるシールド機1の掘進方向とは逆方向)に後退させつつ埋め戻しを行うようにしたが、逆に前方(シールド機1の掘進方向と同方向)に移動させながら埋め戻しを行うことも可能であり、その場合には当然に解体機8を上記実施形態とは逆向きとなるように形成し、解体物の搬出や資機材の搬出入は前方側から行うことになる。   In the above embodiment, the demolition machine 8 is backfilled while being moved backward from the backfill start point (reverse to the direction of the shield machine 1 in the building process). It is also possible to carry out backfilling while moving in the same direction as the excavation direction. In this case, naturally, the dismantling machine 8 is formed in the opposite direction to that of the above-described embodiment, so Equipment will be loaded and unloaded from the front side.

解体機8はセグメント5を解体撤去する際の支保性能を有し、かつ埋め戻し材11を充填できる機能を有するものであれば良く、その限りにおいて解体機8の構成は様々に変更可能である。
勿論、解体機8に各種の付属装置や付属機器類、たとえばセグメント5を解体撤去する際にそれを保持するためのエレクタや、切断するためのカッター、解体したセグメント5を搬出するための移送手段、埋め戻し材11を調製したりその充填量や充填圧を調整し制御するための装置類、等を任意に付設することができるし、それらは在来のシールド機や特許文献2〜3に示される埋め戻し装置に搭載されるものを転用することが可能である。
The dismantling machine 8 only needs to have a supporting performance when dismantling and removing the segment 5 and a function capable of filling the backfilling material 11, and the configuration of the dismantling machine 8 can be variously changed as long as it is limited. .
Of course, various attachment devices and accessories such as an erector for holding the segment 5 when the segment 5 is dismantled and removed, a cutter for cutting, and a transport means for carrying out the disassembled segment 5 to the dismantling machine 8 In addition, devices for preparing the backfilling material 11 and adjusting and controlling the filling amount and the filling pressure can be arbitrarily attached, and those can be attached to conventional shield machines and Patent Documents 2-3. It is possible to divert what is mounted on the backfill device shown.

なお、埋め戻さずに残す残存部はそのまま放置するか、あるいは何らかの用途に利用すれば良く、利用する場合には必要に応じて適宜の改修工事や変更工事を加えれば良い。
また、残存部も埋め戻す必要がある場合にはセグメント5を解体撤去せずにそのまま埋め戻せば良く、その場合には埋め戻し部に対する埋め戻し工程に先行して残存部を埋め戻すことでも良い(残存部についてもセグメント5を解体撤去したうえで埋め戻す必要がある場合には、上記の解体機による埋め戻し工程をそのまま残存部まで拡張して実施すれば良いことはいうまでもない)。
The remaining portion that is left without being backfilled may be left as it is, or may be used for some purpose, and when used, appropriate repair work or change work may be added as necessary.
If the remaining part needs to be backfilled, the segment 5 may be backfilled as it is without dismantling, and in that case, the remaining part may be backfilled prior to the backfilling process for the backfilling part. (It is needless to say that if the remaining part needs to be backfilled after dismantling and removing the segment 5, the above-mentioned backfilling process by the dismantling machine may be extended to the remaining part as it is).

さらに、シールドトンネルを築造してから埋め戻しを開始するまでには数年程度のかなりの時間が経過することが通常であるので、上記実施形態における築造工程と埋め戻し工程とをそれぞれ独立の築造工法および埋め戻し工法として実施することでも良い。   Furthermore, since a considerable time of several years usually passes after the construction of the shield tunnel until the backfilling is started, the construction process and the backfilling process in the above embodiment are independent of each other. It may be carried out as a construction method and a backfilling construction method.

本発明工法の実施形態を示すもので、シールドトンネルの築造工程を示す図である。The embodiment of the present invention construction method is shown, and is a diagram showing a shield tunnel construction process. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、シールドトンネルの築造が進展した状態を示す図である。It is a figure which shows the state which construction of the shield tunnel advanced. 同、築造したシールドトンネルに対する埋め戻し工程を開始する時点の状態を示す図である。It is a figure which shows the state at the time of starting the backfilling process with respect to the shield tunnel built similarly. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、次の工程を示す図である。It is a figure which shows the next process same as the above. 同、埋め戻し工程が進展した状態を示す図である。It is a figure which shows the state which the backfilling process advanced.

符号の説明Explanation of symbols

1 シールド機
2 スキンプレート
3 支保部材(解体機のスキンプレート)
3a フランジ部
3b 延長部材
4 シール部材
5 セグメント
6 推進ジャッキ
7 反力受け部材
8 解体機
9 仕切り板
10 面板(充填用型枠)
11 埋め戻し材
12 充填口
13 ブラケット
14 押圧ジャッキ
1 Shield machine 2 Skin plate 3 Support member (skin plate of dismantling machine)
3a Flange 3b Extension member 4 Seal member 5 Segment 6 Propulsion jack 7 Reaction force receiving member 8 Dismantling machine 9 Partition plate 10 Face plate (filling formwork)
11 Backfilling material 12 Filling port 13 Bracket 14 Pressing jack

Claims (6)

シールド機を掘進しつつその後方でセグメントを組み立てることによって築造されるとともに、築造後にその途中の任意の位置を始点としてセグメントが解体されて埋め戻されるシールドトンネルであって、
当該シールドトンネルは、築造後に埋め戻し工程を開始するべき埋め戻し開始予定地点に対し、該埋め戻し工程において使用される解体機のスキンプレートとなる筒状の支保部材が、当該シールドトンネルを築造する工程においてセグメントの外側の位置に予め設置されていることを特徴とするシールドトンネル。
It is a shield tunnel that is built by assembling the segment behind it while digging the shield machine, and the segment is disassembled and backfilled starting from an arbitrary position in the middle after construction ,
The shield tunnel, against the scheduled start point backfill should begin backfill after construction process, cylindrical支保member comprising a skin plate demolition machine used in step back Me該埋 is, to construction the shield tunnel A shield tunnel that is pre- installed at a position outside the segment in the process .
請求項1記載のシールドトンネルを築造するに際し、
シールド機を掘進しつつその後方でセグメントを組み立てていくとともに、シールド機が埋め戻し開始予定地点を通過する際には、解体機のスキンプレートとなる筒状の支保部材をセグメントの外側の位置に設置することを特徴とするシールドトンネルの築造工法。
In constructing the shield tunnel according to claim 1,
While digging the shield machine and assembling the segment behind it, when the shield machine passes the planned backfill start point, place the cylindrical support member that becomes the skin plate of the demolition machine to the position outside the segment A construction method of shield tunnel characterized by installation.
請求項1記載のシールドトンネルを埋め戻すに際し、
埋め戻し開始予定地点に設置されている支保部材をスキンプレートとする解体機を組み立て、該解体機により支保しつつその内側においてセグメントを解体して撤去するとともに、該解体機を移動させていきつつその移動方向後方側に埋め戻し材を充填していくことを特徴とするシールドトンネルの埋め戻し工法。
In refilling the shield tunnel according to claim 1,
While assembling a dismantling machine using the support member installed at the planned start point of backfilling as a skin plate, dismantling and removing the segments inside while supporting by the dismantling machine, moving the dismantling machine The shield tunnel backfilling method is characterized by filling backfilling material on the rear side in the moving direction.
シールド機を掘進しつつその後方でセグメントを組み立てることによって築造されるとともに、任意の位置を始点としてセグメントが解体されて埋め戻されるシールドトンネルを築造し埋め戻すための工法であって、
シールドトンネルを築造する工程においては、シールド機が埋め戻し開始予定地点を通過する際に、解体機のスキンプレートとなる筒状の支保部材をセグメントの外側の位置に設置し、
築造したシールドトンネルを埋め戻す工程においては、埋め戻し開始予定地点において前記支保部材をスキンプレートとする解体機を組み立て、該解体機により支保しつつその内側においてセグメントを解体して撤去するとともに、該解体機を移動させていきつつその移動方向後方側に埋め戻し材を充填していくことを特徴とするシールドトンネルの築造・埋め戻し工法。
It is a method for building and backfilling a shield tunnel that is built by assembling segments behind the shield machine while digging the shield machine, and the segments are dismantled and backfilled from any position,
In the process of building a shield tunnel, when the shield machine passes through the planned backfill start point, a cylindrical support member that becomes the skin plate of the demolition machine is installed at a position outside the segment,
In the process of backfilling the built shield tunnel, a dismantling machine using the support member as a skin plate is assembled at the planned start point of backfilling, and the segments are dismantled and removed while being supported by the dismantling machine, A shield tunnel construction and backfilling method characterized by filling the backfilling material on the rear side in the moving direction while moving the dismantling machine.
請求項4記載のシールドトンネルの築造・埋め戻し工法であって、
シールドトンネルを築造するためのシールド機には、そのスキンプレートのテール部の内側に予め支保部材を組み付けておき、
該シールド機を埋め戻し開始予定地点を通過させる際に、前記支保部材をスキンプレートから切り離して埋め戻し開始予定地点に残置していくことを特徴とするシールドトンネルの築造・埋め戻し工法。
A method for constructing and backfilling a shield tunnel according to claim 4,
In a shield machine for building a shield tunnel, a support member is assembled in advance inside the tail portion of the skin plate,
A shield tunnel construction / backfilling method characterized in that when the shield machine is passed through a planned backfill start point, the support member is separated from the skin plate and left at the planned backfill start point.
請求項4または5記載のシールドトンネルの築造・埋め戻し工法であって、
解体機を組み立てるに際しては、該解体機のスキンプレートとなる支保部材の内側に、埋め戻し材の充填用型枠として機能する面板を設け、
前記解体機の移動方向後方側に埋め戻し材を充填する際には、前記面板の背面側に埋め戻し材を加圧充填することを特徴とするシールドトンネルの築造・埋め戻し工法。
A method for constructing and backfilling a shield tunnel according to claim 4 or 5,
When assembling the dismantling machine, a face plate that functions as a filling form for the backfill material is provided inside the support member that becomes the skin plate of the dismantling machine,
A construction / backfilling method for a shield tunnel characterized in that when the backfilling material is filled on the rear side in the moving direction of the dismantling machine, the backfilling material is pressurized and filled on the back side of the face plate.
JP2007039287A 2007-02-20 2007-02-20 Shield tunnel and its construction method, backfilling method, building / backfilling method Expired - Fee Related JP4798381B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007039287A JP4798381B2 (en) 2007-02-20 2007-02-20 Shield tunnel and its construction method, backfilling method, building / backfilling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007039287A JP4798381B2 (en) 2007-02-20 2007-02-20 Shield tunnel and its construction method, backfilling method, building / backfilling method

Publications (2)

Publication Number Publication Date
JP2008202296A JP2008202296A (en) 2008-09-04
JP4798381B2 true JP4798381B2 (en) 2011-10-19

Family

ID=39780078

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007039287A Expired - Fee Related JP4798381B2 (en) 2007-02-20 2007-02-20 Shield tunnel and its construction method, backfilling method, building / backfilling method

Country Status (1)

Country Link
JP (1) JP4798381B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837362B (en) * 2017-04-24 2023-02-07 中铁十八局集团有限公司 Shield tunneling machine initial construction device and construction method
CN110359914B (en) * 2019-08-19 2021-01-15 中钢集团马鞍山矿山研究总院股份有限公司 Safe and low-cost combined sublevel mining method for gently inclined medium-thickness ore body

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02157400A (en) * 1988-12-07 1990-06-18 Mitsui Constr Co Ltd Method and device for backfilling of tunnel
JP2876339B2 (en) * 1990-07-27 1999-03-31 三井建設株式会社 Shield backfill device
JPH04231600A (en) * 1990-12-28 1992-08-20 Mitsui Constr Co Ltd Shield backfilling device
JP3137731B2 (en) * 1992-05-25 2001-02-26 大成建設株式会社 Existing tunnel removal shield machine
JP2001234700A (en) * 2000-02-21 2001-08-31 Mitsui Constr Co Ltd Tunnel backfilling device, and tunnel backfilling method

Also Published As

Publication number Publication date
JP2008202296A (en) 2008-09-04

Similar Documents

Publication Publication Date Title
JP5316894B2 (en) Shield roof construction method
JP6611247B2 (en) Shield machine moving system and construction method of large section tunnel
JP4818048B2 (en) Shield machine
JP4798381B2 (en) Shield tunnel and its construction method, backfilling method, building / backfilling method
JP5479989B2 (en) Tunnel construction method and shield machine
JP5230468B2 (en) Ground improvement device and ground improvement method for shield machine
JP5291024B2 (en) Direct cast concrete method
JP5725691B2 (en) Inner formwork and tunnel excavator provided with the inner formwork
JP4752015B2 (en) Tunnel construction method and removal shield used in this method
JP5292246B2 (en) Tunnel excavator with switching lining
JP6619567B2 (en) Start preparation method and start method for shield machine
JP4824633B2 (en) Excavation mechanism
JP4812134B2 (en) Construction method of widening tunnel
JP2001234700A (en) Tunnel backfilling device, and tunnel backfilling method
JP4752017B2 (en) Removal shield and tunnel removal method using the same
JP4334954B2 (en) Method and apparatus for widening underground space
JP2006037595A (en) Excavator for jacking method and jacking method
JP3733796B2 (en) Shield device and shield method
JP2004060233A (en) Shield machine and tail seal replacing method of shield machine
JP3347810B2 (en) Shield tunnel widening method and equipment
JP2016008427A (en) Construction method for large-cross-section tunnel
JP2930576B1 (en) Branch shield excavation method and shield excavator capable of branch excavation
JPH04315698A (en) Disassembling method for existing shield
JP2005290797A (en) Combined method of propulsion and shielding
JP2009013585A (en) Removal shield

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090603

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110322

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110329

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110516

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110628

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20110719

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110719

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20110719

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140812

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4798381

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140812

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140812

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees