JP4726697B2 - Ground excavation method - Google Patents

Ground excavation method Download PDF

Info

Publication number
JP4726697B2
JP4726697B2 JP2006142386A JP2006142386A JP4726697B2 JP 4726697 B2 JP4726697 B2 JP 4726697B2 JP 2006142386 A JP2006142386 A JP 2006142386A JP 2006142386 A JP2006142386 A JP 2006142386A JP 4726697 B2 JP4726697 B2 JP 4726697B2
Authority
JP
Japan
Prior art keywords
shaft
horizontal
cutter head
boring machine
tunnel boring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2006142386A
Other languages
Japanese (ja)
Other versions
JP2007314939A (en
Inventor
信行 松井
範行 伊藤
政昭 佐藤
達也 西野
依早彌 横田
一夫 奥津
禎和 市川
紳一 寺田
享一 森岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Komatsu Ltd
Original Assignee
Kajima Corp
Komatsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Komatsu Ltd filed Critical Kajima Corp
Priority to JP2006142386A priority Critical patent/JP4726697B2/en
Publication of JP2007314939A publication Critical patent/JP2007314939A/en
Application granted granted Critical
Publication of JP4726697B2 publication Critical patent/JP4726697B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、地盤の掘削方法に関するものである。   The present invention relates to a ground excavation method.

従来、高レベル放射性廃棄物等は、地下深層部の岩盤中に形成された分岐坑道内に埋設されてきた。分岐坑道を形成するには、地表から地下深層部まで掘削した立坑を用いて主要坑道(水平坑)を掘削し、主要坑道を用いて分岐坑道を掘削していた。   Conventionally, high-level radioactive wastes and the like have been buried in a branch tunnel formed in the bedrock in the deep underground. In order to form a branch mine, a main shaft (horizontal mine) was excavated using a vertical shaft excavated from the surface to the deep underground, and a branch mine was excavated using the main shaft.

立坑の掘削には、上方から下方または斜め下方への掘削が可能で、掘削ズリを下方から上方に向けてカプセルで輸送するトンネル掘削機(例えば、特許文献1参照)等が用いられてきた。また、分岐坑道の掘削には、主要坑道内で水平回転可能なトンネル掘削機(例えば、特許文献2参照)が用いられてきた。   For excavation of a vertical shaft, a tunnel excavator (for example, see Patent Document 1) that can excavate from below to above or obliquely below, and transports excavation gaps from below to above by capsules has been used. Moreover, for excavation of a branch mine, a tunnel excavator (see, for example, Patent Document 2) that can rotate horizontally in a main mine has been used.

特開2003−328688号公報JP 2003-328688 A 特開2002−106289号公報JP 2002-106289 A

しかしながら、従来の方法では、立坑の掘削と、水平坑の掘削とに、それぞれ異なる掘削機が必要であった。また、上述した立坑用のトンネル掘削機は、掘削機内に大容量の掘削物貯留部が設置されるため、設備が大規模であった。   However, the conventional method requires different excavators for excavating the vertical shaft and for excavating the horizontal shaft. Further, the above-described tunnel excavator for shafts has a large-scale facility because a large-capacity excavation storage unit is installed in the excavator.

前述した目的を達成するための本発明は、第1のトンネルボーリングマシンを用いて立坑を掘削する工程aと、前記立坑の下端部付近から所定の長さの水平坑を掘削する工程bと、前記立坑の上方から前記水平坑内に第2のトンネルボーリングマシンのカッタヘッドを搬入する工程cと、前記第1のトンネルボーリングマシンの前胴の一部およびスラストジャッキを取り外し、取り外した部分を前記立坑と前記水平坑とが分岐する高さまで吊り上げて反転させて前記水平坑内に引き込み、前記カッタヘッドの後方に組み付けて前記第2のトンネルボーリングマシンを組み立てる工程dと、前記第1のトンネルボーリングマシンの後続台車を前記水平坑内に引き込みつつ、前記第2のトンネルボーリングマシンおよび前記後続台車を用いて前記水平坑をさらに掘削する工程eと、を具備することを特徴とする地盤の掘削方法である。 The present invention for achieving the above-mentioned object includes a step a for excavating a shaft using the first tunnel boring machine , a step b for excavating a horizontal shaft having a predetermined length from the vicinity of the lower end of the shaft, A step c for carrying a cutter head of a second tunnel boring machine into the horizontal pit from above the shaft, a part of the front trunk and the thrust jack of the first tunnel boring machine are removed, and the removed part is removed from the shaft and the horizontal mine and is flips lifting to a height that branches draw the horizontal mine, and step d assembling the second tunnel boring machine is assembled in the rear of the cutter head, the first tunnel boring machine while pulling the trailing bogie in the horizontal downhole, using said second tunnel boring machine and the subsequent carriage A drilling method of the ground, characterized by comprising a step e further drilling Hiraana, the.

工程dで第1のトンネルボーリングマシンから取り外される前胴の一部は、例えば、カッタヘッドサポートと、カッタヘッドサポートの後方に設置されたカッタヘッド駆動用モータと、カッタヘッドサポートの外周に設置された第1のフロントサイドサポートとを含む。また、立坑の径が水平坑の径より大きい場合、工程dでは、前胴のうち、第1のフロントサイドサポートの外側に配置された第2のフロントサイドサポートが第1のトンネルボーリングマシンに残置される。 A part of the front cylinder to be removed from the first tunnel boring machine in step d is, for example, installed on the outer periphery of the cutter head support, the cutter head driving motor installed behind the cutter head support, and the cutter head support. And a first front side support. When the diameter of the vertical shaft is larger than the diameter of the horizontal shaft, in step d , the second front side support arranged outside the first front side support in the front trunk is left in the first tunnel boring machine. .

工程dは、前胴の一部を取り外して水平坑内に引き込み、カッタヘッドに接続する工程fと、スラストジャッキを取り外して水平坑内に引き込み、前胴の一部に接続する工程gとからなる。 Step d draws a horizontal downhole remove a portion of the front body consists of a step f to be connected to the cutter head, draw a horizontal downhole remove the thrust jack, a step g of connecting to a portion of the front torso.

後続台車は複数の台車からなり、工程aから工程dの間は、複数の台車を連結して立坑内に吊り下げる。そして、工程eでは、複数の台車を、連結された台車を下降させる作業と、最下段の台車を切り離して水平移動させる作業とを繰り返して水平坑内に引き込む。 The succeeding carriage is composed of a plurality of carriages, and between the steps a to d , the plurality of carriages are connected and suspended in the shaft. In step e , the operation of lowering the connected carts and the operation of horizontally moving the carts by separating the bottom carts are repeatedly drawn into the horizontal pit.

本発明では、まず、第1の掘削機を用いて立坑を掘削した後、立坑の下端部付近から所定の長さの水平坑を掘削する。そして、立坑の上方から水平坑内に第2の掘削機のカッタヘッドを搬入する。次に、第1の掘削機の前胴の一部およびスラストジャッキを取り外して水平坑内に引き込み、第2の掘削機を組み立てる。その後、第1の掘削機の後続台車を水平坑内に引き込みつつ、第2の掘削機および後続台車を用いて水平坑をさらに掘削する。   In the present invention, a shaft is first excavated using the first excavator, and then a horizontal shaft having a predetermined length is excavated from the vicinity of the lower end of the shaft. Then, the cutter head of the second excavator is carried into the horizontal shaft from above the shaft. Next, a part of the front trunk of the first excavator and the thrust jack are removed and pulled into the horizontal pit to assemble the second excavator. Thereafter, the horizontal pit is further excavated using the second excavator and the subsequent carriage while the subsequent carriage of the first excavator is drawn into the horizontal pit.

本発明によれば、最小限の設備を用いて径の異なる立坑と水平坑とを連続して掘削する地盤の掘削方法を提供できる。   According to the present invention, it is possible to provide a ground excavation method for continuously excavating vertical shafts and horizontal shafts having different diameters using a minimum amount of equipment.

以下、図面に基づいて、本発明の実施の形態を詳細に説明する。図1は、トンネルボーリングマシン(以下、TBMとする)を用いて地盤1に立坑3を掘削する工程を示す図、図2は、立坑用TBM5の断面図である。図2の(a)図は、図2の(b)図のB−Bによる断面図、図2の(b)図は、図2の(a)図のA−Aによる断面図を示す。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a diagram showing a process of excavating a shaft 3 in the ground 1 using a tunnel boring machine (hereinafter referred to as TBM), and FIG. 2 is a cross-sectional view of the shaft TBM 5. 2A is a cross-sectional view taken along line BB in FIG. 2B, and FIG. 2B is a cross-sectional view taken along line A-A in FIG.

図1では、立坑用TBM5、後続台車55を用いて、地盤1の上方から下方に向けて立坑3を掘削する。立坑用TBM5は、図2に示すように、カッタヘッド7、前胴13、中胴15、後胴17からなる。   In FIG. 1, the vertical shaft 3 is excavated from above the ground 1 downward using the vertical shaft TBM 5 and the subsequent carriage 55. As shown in FIG. 2, the vertical shaft TBM 5 includes a cutter head 7, a front trunk 13, a middle trunk 15, and a rear trunk 17.

カッタヘッド7は、地盤1を掘削するためのディスクカッタ9、ディスクカッタ11を有する。 The cutter head 7 has a disk cutter 9 and a disk cutter 11 for excavating the ground 1.

前胴13は、スキンプレート31aの内部に、カッタヘッドサポート19、スキンプレート20、オイルパック式フロントサイドサポート21、カッタヘッド駆動用モータ25等を有する。   The front barrel 13 includes a cutter head support 19, a skin plate 20, an oil pack type front side support 21, a cutter head driving motor 25, and the like inside a skin plate 31a.

カッタヘッドサポート19は、カッタヘッド7の後方に配置される。スキンプレート20は、カッタヘッドサポート19の外側に設けられる。スキンプレート20の径は、図5に示す水平坑用TBM53の径に応じて設定される。オイルパック式フロントサイドサポート21は、第1のフロントサイドサポートであり、スキンプレート20に固定される。カッタヘッド駆動用モータ25は、カッタヘッドサポート19の後方に固定される。 The cutter head support 19 is disposed behind the cutter head 7. The skin plate 20 is provided outside the cutter head support 19. The diameter of the skin plate 20 is set according to the diameter of the horizontal shaft TBM 53 shown in FIG. The oil pack type front side support 21 is a first front side support and is fixed to the skin plate 20. The cutter head driving motor 25 is fixed behind the cutter head support 19.

前胴13は、スキンプレート31aに油圧ジャッキ式フロントサイドサポート23を有する。油圧ジャッキ式フロントサイドサポート23は、第2のフロントサイドサポートであり、オイルパック式フロントサイドサポート21の外側に配置される。油圧ジャッキ式フロントサイドサポート23は、スキンプレート31aに固定される。 The front trunk 13 has a hydraulic jack type front side support 23 on a skin plate 31a. The hydraulic jack type front side support 23 is a second front side support and is disposed outside the oil pack type front side support 21. The hydraulic jack type front side support 23 is fixed to the skin plate 31a.

中胴15は、スキンプレート31bの内部にスラストジャッキ27を有する。スラストジャッキ27は、油圧ジャッキ式フロントサイドサポート23の後方に配置される。   The middle barrel 15 has a thrust jack 27 inside the skin plate 31b. The thrust jack 27 is disposed behind the hydraulic jack type front side support 23.

後胴17は、スキンプレート31cにグリッパ29を有する。グリッパ29は、スキンプレート31cに固定される。
スラストジャッキ27は、一端が前胴13に、他端が後胴17に固定される。
The rear trunk 17 has a gripper 29 on the skin plate 31c. The gripper 29 is fixed to the skin plate 31c.
The thrust jack 27 has one end fixed to the front cylinder 13 and the other end fixed to the rear cylinder 17.

立坑用TBM5は、カッタヘッド駆動用モータ25でカッタヘッド7を駆動させて地盤1を掘削する。立坑用TBM5は、スキンプレート31c、スキンプレート31aからそれぞれグリッパ29、油圧ジャッキ式フロントサイドサポート23を外周方向に張り出して立坑3の壁面に押し付けて反力を取る。立坑用TBM5は、前胴13と後胴17とをスラストジャッキ27で互いに接近離間させることで下方へ推進する。   The shaft TBM 5 excavates the ground 1 by driving the cutter head 7 with the cutter head driving motor 25. The vertical shaft TBM 5 overhangs the gripper 29 and the hydraulic jack type front side support 23 from the skin plate 31 c and the skin plate 31 a in the outer circumferential direction and presses them against the wall surface of the vertical shaft 3 to take a reaction force. The shaft TBM 5 is propelled downward by causing the front barrel 13 and the rear barrel 17 to approach and separate from each other by a thrust jack 27.

カッタヘッド7による掘削ズリは、立坑用TBM5の内部に設けられたバケットコンベア(図示せず)により機体後方すなわち上方へ排出され、気送カプセル式揚土設備(図示せず)を用いて地上に搬送される。   The excavation gap by the cutter head 7 is discharged rearward or upward by a bucket conveyor (not shown) provided inside the vertical shaft TBM 5, and is discharged to the ground using a pneumatic capsule type earthing facility (not shown). Be transported.

後続台車55は、複数の台車を上下に連結したものである。後続台車55は、立坑3内に吊り下げられ、立坑3の吹付材料の運搬等に用いられる。   The succeeding carriage 55 is obtained by connecting a plurality of carriages up and down. The trailing carriage 55 is suspended in the shaft 3 and used for transporting the spray material of the shaft 3 and the like.

図3は、所定の長さの水平坑33を掘削する工程を示す図である。図3では、図1に示す工程で掘削した立坑3の下端部付近から、発破等により所定の長さの水平坑33を掘削する。そして、水平坑33内に水平坑用TBM組立発進架台35を設置する。なお、図3に示す工程では、水平坑33は、内部で水平坑用TBMを組み立てられる長さまで掘削される。   FIG. 3 is a diagram illustrating a process of excavating a horizontal pit 33 having a predetermined length. In FIG. 3, a horizontal shaft 33 having a predetermined length is excavated from the vicinity of the lower end of the shaft 3 excavated in the process shown in FIG. Then, the horizontal pit TBM assembly start frame 35 is installed in the horizontal pit 33. In the process shown in FIG. 3, the horizontal pit 33 is excavated to a length in which the horizontal pit TBM can be assembled.

図4は、水平坑TBM用カッタヘッド37を搬入する工程を示す図である。図4では、矢印Cに示すように、地上から立坑3を介して水平坑33内に水平坑TBM用カッタヘッド37を搬入し、水平坑用TBM組立発進架台35上に据え付ける。また、フード部39を地上から立坑3を介して水平坑33内に搬入し、水平坑TBM用のカッタヘッド37に取り付ける。   FIG. 4 is a diagram illustrating a process of carrying in the horizontal well TBM cutter head 37. In FIG. 4, as shown by an arrow C, a horizontal pit TBM cutter head 37 is carried into the horizontal pit 33 from the ground via the vertical shaft 3, and installed on the horizontal pit TBM assembly starter base 35. Moreover, the hood part 39 is carried into the horizontal well 33 from the ground via the vertical shaft 3 and attached to the cutter head 37 for the horizontal well TBM.

図5は、水平坑用TBM53の断面図である。図5の(a)図は、図5の(b)図のH−Hによる断面図、図5の(b)図は、図5の(a)図のG−Gによる断面図を示す。   FIG. 5 is a cross-sectional view of the horizontal shaft TBM 53. 5A is a cross-sectional view taken along line HH in FIG. 5B, and FIG. 5B is a cross-sectional view taken along line GG in FIG. 5A.

水平坑用TBM53は、図5に示すように、カッタヘッド37、フード部39、前胴43、中胴45、後胴47、テール部49からなる。カッタヘッド37は、地盤1を掘削するためのディスクカッタ41を有する。   As shown in FIG. 5, the horizontal shaft TBM 53 includes a cutter head 37, a hood portion 39, a front drum 43, a middle drum 45, a rear drum 47, and a tail portion 49. The cutter head 37 has a disk cutter 41 for excavating the ground 1.

図6は、立坑用TBM5の前胴13の一部を取り外して水平坑33内に引き込む工程を示す図である。図6では、まず、立坑用TBM5の前胴13から、カッタヘッドサポート19、オイルパック式フロントサイドサポート21、カッタヘッド駆動モータ25、スキンプレート20(図2)を一体化した状態で取り外す。   FIG. 6 is a diagram showing a process of removing a part of the front trunk 13 of the vertical shaft TBM 5 and drawing it into the horizontal shaft 33. In FIG. 6, first, the cutter head support 19, the oil pack type front side support 21, the cutter head drive motor 25, and the skin plate 20 (FIG. 2) are removed from the front trunk 13 of the shaft TBM 5 in an integrated state.

次に、取り外した部分を、矢印Dに示すように立坑3と水平坑33とが分岐する高さまで吊り上げ、点線で示す位置で矢印Eに示すように反転させる。そして、矢印Fに示すように水平坑33内に引き込み、カッタヘッド37の後方に組み付ける。立坑用TBM5の第2のフロントサイドサポートである油圧ジャッキ式フロントサイドサポート23は、前胴13に残置される。 Next, the removed portion is lifted up to a height at which the vertical shaft 3 and the horizontal shaft 33 are branched as indicated by an arrow D, and inverted at a position indicated by a dotted line as indicated by an arrow E. Then, as shown by the arrow F, it is drawn into the horizontal pit 33 and assembled behind the cutter head 37. The hydraulic jack type front side support 23 which is the second front side support of the shaft TBM 5 is left in the front trunk 13.

図5の(a)図に示すように、カッタヘッドサポート19、オイルパック式フロントサイドサポート21、カッタヘッド駆動モータ25、スキンプレート20は、水平坑用TBM53の前胴43を形成する。 As shown in FIG. 5A, the cutter head support 19, the oil pack type front side support 21, the cutter head drive motor 25, and the skin plate 20 form a front trunk 43 of the horizontal well TBM 53.

図7は、立坑用TBM5のスラストジャッキ27を取り外して水平坑33内に引き込む工程を示す図である。図7では、立坑用TBM5の中胴15内のスラストジャッキ27を取り外す。そして、矢印Iに示すように、スラストジャッキ27を立坑3内で吊り上げて水平坑33内に引き込み、カッタヘッドサポート19の後方に配置する。   FIG. 7 is a diagram showing a process of removing the thrust jack 27 of the vertical shaft TBM 5 and drawing it into the horizontal shaft 33. In FIG. 7, the thrust jack 27 in the middle trunk 15 of the shaft TBM 5 is removed. Then, as indicated by an arrow I, the thrust jack 27 is lifted in the vertical shaft 3, pulled into the horizontal shaft 33, and disposed behind the cutter head support 19.

図8は、水平坑用TBM53の中胴45、後胴47、テール部49を組み付ける工程を示す図である。図8では、中胴45、後胴47、テール部49を地上から立坑3を介して水平坑33内に搬入し、組み付ける。中胴45、後胴47、テール部49のスキンプレート51(図5)は、上下に2分割して搬入する。
なお、図5の(a)図に示すように、スラストジャッキ27は、一端が前胴43に、他端が後胴47に固定される。
FIG. 8 is a diagram showing a process of assembling the middle drum 45, the rear drum 47, and the tail portion 49 of the horizontal shaft TBM 53. As shown in FIG. In FIG. 8, the middle trunk 45, the rear trunk 47, and the tail portion 49 are carried from the ground through the vertical shaft 3 into the horizontal shaft 33 and assembled. The skin plate 51 (FIG. 5) of the middle drum 45, the rear drum 47, and the tail portion 49 is carried in two divided vertically.
As shown in FIG. 5A, one end of the thrust jack 27 is fixed to the front barrel 43 and the other end is fixed to the rear barrel 47.

図9は、後続台車55および水平坑用TBM53を用いて水平坑33をさらに掘削する工程を示す図である。図9では、立坑3の掘削時に用いた立坑用TBM5の後続台車55を水平坑33内に引き込みつつ、水平坑用TBM53および後続台車55を用いて水平坑33をさらに掘削する。 FIG. 9 is a diagram illustrating a process of further excavating the horizontal well 33 using the trailing carriage 55 and the horizontal well TBM 53. In FIG. 9, the horizontal shaft 33 is further excavated by using the horizontal shaft TBM 53 and the subsequent vehicle 55 while the subsequent vehicle 55 of the vertical shaft TBM 5 used when excavating the shaft 3 is drawn into the horizontal shaft 33.

図1から図8に示す工程で立坑3内に吊り下げられていた後続台車55を水平坑33内に引き込むには、連結された複数の台車を下降させる作業と、最下段の台車55aを切り離して水平移動させる作業とを繰り返す。後続台車55は、水平坑33の吹付材料の運搬等に用いられる。 In order to draw the succeeding carriage 55 suspended in the shaft 3 into the horizontal well 33 in the process shown in FIGS. 1 to 8, the operation of lowering the plurality of connected carriages and the bottom carriage 55a are separated. Repeat the horizontal movement. The trailing carriage 55 is used for transporting the spray material of the horizontal pit 33 and the like.

水平坑用TBM53は、カッタヘッド駆動用モータ25でカッタヘッド7を駆動させて地盤1を掘削する。水平坑用TBM53は、スキンプレート20からオイルパック式フロントサイドサポート21を外周方向に張り出して水平坑33の壁面に押し付けて反力を取る。水平坑用TBM53は、前胴43と後胴47とをスラストジャッキ27で互いに接近離間させることで前方へ推進する。   The horizontal shaft TBM 53 excavates the ground 1 by driving the cutter head 7 with the cutter head driving motor 25. The horizontal well TBM 53 projects the oil pack type front side support 21 from the skin plate 20 in the outer peripheral direction and presses it against the wall surface of the horizontal well 33 to take a reaction force. The horizontal shaft TBM 53 is propelled forward by moving the front trunk 43 and the rear trunk 47 closer to and away from each other by the thrust jack 27.

カッタヘッド37による掘削ズリは、水平坑用TBM53の内部に設けられたベルトコンベア(図示せず)等により機体後方へ排出される。   The excavation gap by the cutter head 37 is discharged to the rear of the machine body by a belt conveyor (not shown) or the like provided inside the horizontal shaft TBM 53.

このように、本実施の形態によれば、立坑用TBM5のカッタヘッドサポート19、オイルパック式フロントサイドサポート21、カッタヘッド駆動モータ25、スキンプレート20、スラストジャッキ27を水平坑用TBM53に転用する。また、掘削ズリの搬出には気送カプセル式揚土設備を用いる。これにより、最小限の設備で径の異なる立坑3と水平坑33とを連続して掘削することができる。   Thus, according to this embodiment, the cutter head support 19, the oil pack type front side support 21, the cutter head drive motor 25, the skin plate 20, and the thrust jack 27 of the vertical shaft TBM 5 are diverted to the horizontal shaft TBM 53. In addition, a pneumatic capsule type earthing facility is used to carry out the excavation sludge. Thereby, the shaft 3 and the horizontal shaft 33 having different diameters can be continuously excavated with the minimum equipment.

以上、添付図面を参照しながら本発明にかかる地盤の掘削方法の好適な実施形態について説明したが、本発明はかかる例に限定されない。当業者であれば、特許請求の範囲に記載された技術的思想の範疇内において各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   The preferred embodiments of the ground excavation method according to the present invention have been described above with reference to the accompanying drawings, but the present invention is not limited to such examples. It is obvious for those skilled in the art that various modifications or modifications can be conceived within the scope of the technical idea described in the claims, and these are naturally within the technical scope of the present invention. It is understood that it belongs.

トンネルボーリングマシンを用いて地盤1に立坑3を掘削する工程を示す図The figure which shows the process of excavating the shaft 3 in the ground 1 using a tunnel boring machine 立坑用TBM5の断面図Cross section of TBM5 for shaft 所定の長さの水平坑33を掘削する工程を示す図The figure which shows the process of excavating the horizontal well 33 of predetermined length 水平坑TBM用カッタヘッド37を搬入する工程を示す図The figure which shows the process of carrying in the cutter head 37 for horizontal well TBM. 水平坑用TBM53の断面図Cross section of horizontal shaft TBM53 立坑用TBM5の前胴13の一部を取り外して水平坑33内に引き込む工程を示す図The figure which shows the process of removing a part of the front trunk | drum 13 of TBM5 for vertical shafts, and drawing in in the horizontal shaft 33 立坑用TBM5のスラストジャッキ27を取り外して水平坑33内に引き込む工程を示す図The figure which shows the process of removing the thrust jack 27 of TBM5 for vertical shafts, and drawing in in the horizontal shaft 33 水平坑用TBM53の中胴45、後胴47、テール部49を組み付ける工程を示す図The figure which shows the process of assembling the center drum 45, the rear drum 47, and the tail part 49 of TBM53 for horizontal shaft 後続台車55および水平坑用TBM53を用いて水平坑33をさらに掘削する工程を示す図The figure which shows the process of further excavating the horizontal well 33 using the succeeding trolley | bogie 55 and TBM53 for horizontal wells.

符号の説明Explanation of symbols

1………地盤
3………立坑
5………立坑用TBM
7、37………カッタヘッド
13、43………前胴
19………カッタヘッドサポート
20、31、51………スキンプレート
21………オイルパック式フロントサイドサポート
23………油圧ジャッキ式フロントサイドサポート
25………カッタヘッド駆動用モータ
27………スラストジャッキ
29………グリッパ
33………水平坑
53………水平坑用TBM
55………後続台車
55a………台車
1 ……… Ground 3 ……… Vertical shaft 5 ……… TBM for vertical shaft
7, 37 ......... Cutter head 13, 43 ......... Front trunk 19 ......... Cutter head support 20, 31, 51 ... …… Skin plate 21 ... …… Oil pack type front side support 23 ... …… Hydraulic jack type front Side support 25 ... …… Cutter head drive motor 27 ……… Thrust jack 29 ……… Gripper 33 ……… Horizontal well 53 ……… Horizontal well TBM
55 ……… Following cart 55a ……… Dolly

Claims (5)

第1のトンネルボーリングマシンを用いて立坑を掘削する工程aと、
前記立坑の下端部付近から所定の長さの水平坑を掘削する工程bと、
前記立坑の上方から前記水平坑内に第2のトンネルボーリングマシンのカッタヘッドを搬入する工程cと、
前記第1のトンネルボーリングマシンの前胴の一部およびスラストジャッキを取り外し、取り外した部分を前記立坑と前記水平坑とが分岐する高さまで吊り上げて反転させて前記水平坑内に引き込み、前記カッタヘッドの後方に組み付けて前記第2のトンネルボーリングマシンを組み立てる工程dと、
前記第1のトンネルボーリングマシンの後続台車を前記水平坑内に引き込みつつ、前記第2のトンネルボーリングマシンおよび前記後続台車を用いて前記水平坑をさらに掘削する工程eと、
を具備することを特徴とする地盤の掘削方法。
A step of excavating a shaft using the first tunnel boring machine ;
A step b of excavating a horizontal shaft having a predetermined length from the vicinity of the lower end of the shaft;
A step c of bringing a cutter head of a second tunnel boring machine into the horizontal shaft from above the vertical shaft;
A part of the front trunk and the thrust jack of the first tunnel boring machine are removed, the removed part is lifted up to a height at which the vertical shaft and the horizontal shaft are branched, inverted , and drawn into the horizontal shaft . a step d assembling the second tunnel boring machine are assembled to the rear,
A step e of further excavating the horizontal pit using the second tunnel boring machine and the subsequent carriage while pulling the subsequent carriage of the first tunnel boring machine into the horizontal pit;
The ground excavation method characterized by comprising.
前記前胴の一部が、
カッタヘッドサポートと、
前記カッタヘッドサポートの後方に設置されたカッタヘッド駆動用モータと、
前記カッタヘッドサポートの外周に設置された第1のフロントサイドサポートと、
を有することを特徴とする請求項1記載の地盤の掘削方法。
A part of the front torso
With cutter head support,
A cutter head driving motor installed behind the cutter head support;
A first front side support installed on the outer periphery of the cutter head support;
The ground excavation method according to claim 1, comprising:
前記工程dで、前記前胴のうち、前記第1のフロントサイドサポートの外側に配置された第2のフロントサイドサポートが前記第1のトンネルボーリングマシンに残置されることを特徴とする請求項2記載の地盤の掘削方法。 The second front side support disposed outside the first front side support in the front trunk is left in the first tunnel boring machine in the step d. How to excavate the ground. 前記工程dが、
前記前胴の一部を取り外して前記水平坑内に引き込み、前記カッタヘッドに接続する工程fと、
前記スラストジャッキを取り外して前記水平坑内に引き込み、前記前胴の一部に接続する工程gと、
からなることを特徴とする請求項1記載の地盤の掘削方法。
Step d is
The pull in a horizontal downhole remove a portion of the front torso, a step f to be connected to the cutter head,
The pull on the horizontal downhole Remove the thrust jacks, a step g of connecting to a portion of the front torso,
The ground excavation method according to claim 1, comprising:
前記後続台車は複数の台車からなり、
前記工程aから前記工程dの間は、前記複数の台車を連結して前記立坑内に吊り下げ、
前記工程eで、前記複数の台車を、連結された前記台車を下降させる作業と、最下段の前記台車を切り離して水平移動させる作業とを繰り返して前記水平坑内に引き込むことを特徴とする請求項1記載の地盤の掘削方法。
The subsequent carriage is composed of a plurality of carriages,
Between the step a to the step d , the plurality of carriages are connected and suspended in the shaft,
The step e is characterized in that in the step e , the operation of lowering the connected carts and the operation of horizontally moving the carts by separating and moving the lowest carts are drawn into the horizontal shaft. The ground excavation method according to 1.
JP2006142386A 2006-05-23 2006-05-23 Ground excavation method Active JP4726697B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006142386A JP4726697B2 (en) 2006-05-23 2006-05-23 Ground excavation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006142386A JP4726697B2 (en) 2006-05-23 2006-05-23 Ground excavation method

Publications (2)

Publication Number Publication Date
JP2007314939A JP2007314939A (en) 2007-12-06
JP4726697B2 true JP4726697B2 (en) 2011-07-20

Family

ID=38849053

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006142386A Active JP4726697B2 (en) 2006-05-23 2006-05-23 Ground excavation method

Country Status (1)

Country Link
JP (1) JP4726697B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201513A (en) * 2015-09-11 2015-12-30 重庆工程职业技术学院 Shaft construction method for rail transit
JP7008539B2 (en) * 2018-03-01 2022-01-25 大成建設株式会社 How to arrange the following equipment of the shield machine
CN110675092B (en) * 2019-10-18 2022-04-05 中铁隧道局集团有限公司 Broken stratum TBM (tunnel boring machine) blocking risk early warning method based on torsion-thrust ratio
CN111911712A (en) * 2020-07-03 2020-11-10 广州市第一市政工程有限公司 Push pipe type trenchless pipeline construction method
CN115822609B (en) * 2023-02-09 2023-06-02 中国建筑西南勘察设计研究院有限公司 Shaft variable diameter construction control method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10252378A (en) * 1997-03-11 1998-09-22 Kawasaki Heavy Ind Ltd Shield driving method and shield machine therefor

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001159293A (en) * 1999-12-03 2001-06-12 Taisei Corp Shield machine and method of digging
JP4576987B2 (en) * 2004-06-16 2010-11-10 株式会社ダイフク Branch equipment

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10252378A (en) * 1997-03-11 1998-09-22 Kawasaki Heavy Ind Ltd Shield driving method and shield machine therefor

Also Published As

Publication number Publication date
JP2007314939A (en) 2007-12-06

Similar Documents

Publication Publication Date Title
CN104564050B (en) Equipment for heading and anchoring parallel operation construction
CN105127707B (en) Method for disassembling earth pressure balance shield machine in tunnel
CN108756909A (en) A kind of construction method of small space shield machine dismantling
JP4726697B2 (en) Ground excavation method
JP2008095293A (en) Method of constructing underground structure
CN103075153B (en) Open-air drilling coal cutter
JP2013028952A (en) Shield type tunnel excavator
JP3471264B2 (en) Tunnel construction method and shield machine used for it
JP4557931B2 (en) Excavator body recovery device in tunnel excavator
JP2008248604A (en) Method of advancing shield machine and shield machine
CN101736764B (en) Impact type excavating device
JP4931635B2 (en) How to reassemble the excavator
JP5528049B2 (en) Tunnel drilling equipment
JP4557930B2 (en) Excavator body recovery device in tunnel excavator
JP3758722B2 (en) Tunnel excavator
CN111764918B (en) Drilling splitting all-in-one machine
JP4599530B2 (en) Dividing structure of excavator and method for retracting excavator
JP3822221B2 (en) Propulsion tunnel removal / backfill equipment
CN112228088A (en) Construction method of vertical shaft starting device for top-down pipe jacking construction in shield tunnel
JP3512012B2 (en) How to excavate
JP4698512B2 (en) Method of collecting excavator body in tunnel excavator
JP2006188907A (en) Segment carrying system
JP6517085B2 (en) Method of constructing secondary tunnel tunnel and branch shield used in the method of construction
JP6012073B2 (en) How to replace excavation members of tunnel excavator
JP5279676B2 (en) Box assembly equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20081226

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101027

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101102

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101228

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110412

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110412

R150 Certificate of patent or registration of utility model

Ref document number: 4726697

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140422

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250