JP4686937B2 - System for determining the number of production by production base and specification - Google Patents

System for determining the number of production by production base and specification Download PDF

Info

Publication number
JP4686937B2
JP4686937B2 JP2001256192A JP2001256192A JP4686937B2 JP 4686937 B2 JP4686937 B2 JP 4686937B2 JP 2001256192 A JP2001256192 A JP 2001256192A JP 2001256192 A JP2001256192 A JP 2001256192A JP 4686937 B2 JP4686937 B2 JP 4686937B2
Authority
JP
Japan
Prior art keywords
production
date
factory
file
period
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001256192A
Other languages
Japanese (ja)
Other versions
JP2003067030A (en
Inventor
孝一 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Motor Corp
Original Assignee
Toyota Motor Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Motor Corp filed Critical Toyota Motor Corp
Priority to JP2001256192A priority Critical patent/JP4686937B2/en
Publication of JP2003067030A publication Critical patent/JP2003067030A/en
Application granted granted Critical
Publication of JP4686937B2 publication Critical patent/JP4686937B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Description

【0001】
【発明の属する技術分野】
本発明は、同一種類の製品を複数の生産拠点で分担して生産する生産系のために、各生産拠点で生産する仕様別の生産台数を決定するためのコンピュータシステムに関する。
ここでいう仕様とは同一種類内の細かな種別をいう。例えば、種類1の乗用車と種類2の乗用車があり、種類1の乗用車のなかにルーフウインドウがあるものとないものがある場合、ルーフウインドウの有無に対応して仕様が異なることになる。
【0002】
【従来の技術】
例えば自動車の場合、同一種類の製品を複数の生産拠点で分担して製造するようになっている。この場合、自動車の生産を開始してから発注者に納入されるまでに要する期間は生産拠点毎に相違する。例えば、北海道工場でも九州工場でも製造している自動車を北海道の販売店が発注する場合、九州工場で製造して北海道に運搬する方が北海道工場で製造して北海道の販売店に運搬するよりも長時間を要する。納期までの期間が短いと、九州工場で製造していては間に合わず、北海道工場で製造しなければならなくなってしまう。
同一種類の製品を複数の生産拠点で分担して製造する場合、その分担の割合を合理的に決定することによって、生産拠点群のトータルな生産効率を向上させる必要がある。このためには、できるだけ自由に分担割合を決定できるようにしておく必要がある。
そこで現在では、時間の余裕を持って発注者に需要を予測してもらっている。先の例でいえば、九州工場で分担することになってもまだ間に合う時点で需要予測をしてもらうのである。この時点で需要予測してもらうと、各生産拠点の生産能力や繁忙度等を勘案して最適な分担を決定することができる。
【0003】
【発明が解決しようとする課題】
生産拠点の効率的な運用のためには、生産開始から納入までに要する期間が最長となる生産拠点で生産分担することになっても間に合う時点で需要予測する必要がある。一方、需要予測から納入までの期間が長いと、正確に重要予測することが困難となり、実際の需要に合わない生産をする可能性がある。
特にこの問題は、種類内の仕様別の生産台数を決定するときに大きな問題となる。上記のスケジュールで仕様別の生産台数を決定すると、需要の少ない仕様を多く生産する一方、需要の多い仕様を少なく生産することが起こりえる。
生産拠点毎の分担生産台数は上記のスケジュールで決定することが必要であり、これをその後に変更することは困難であり、また、無理に変更すると生産効率が下がってしまう。しかしながら、仕様別の生産台数は生産開始の直前まで変更可能である。例えば、種類1の乗用車を生産拠点A1でY1台分担生産し、生産拠点A2でY2台分担生産する計画が確定した後で、生産拠点A1で生産するY1台の仕様別の内訳や、生産拠点A2で生産するY2台の仕様別の内訳を決定することが可能である。生産拠点別の分担生産台数を決定する時点でなく、生産拠点で実際に生産するときまでに仕様別の内訳を決めればよいようにしておくと、需要の少ない仕様を多く生産し、需要の多い仕様を少なく生産するといった事態の発生を回避することができる。
【0004】
本発明は、生産拠点別の分担生産台数の決定には期間の制約を受けないようにし(そのためには、生産開始から納入までに要する期間が最長となる生産拠点からでも間にあう時点で生産拠点別の分担生産台数を決定する必要がある)、それでいながら、仕様別の生産台数についてはより後の時点で正確な需要予測に基づいて決定することができるコンピュータシステムを実現することを目的とする。
【0005】
製品の生産から販売までの進捗を管理する技術が、例えば、特開平8−96045号公報や特開平8−137961号公報等に記載されている。
この管理技術では、製品の生産から販売までの過程をいくつかの工程に分割する。顧客から注文を受けると、その受注に応じて製品の生産計画が立案され、その立案された生産計画に基づいて製品の生産が開始される。製品の生産が開始されると、製品が前記した各工程を通過した時刻が順次記憶される。この技術によると、計画上の通過時刻と実際の通過時刻から、生産物流活動の進捗状況を把握することができる。これによって、進捗状況が遅れている製品については、その後の工程での優先順位を上げる等の必要な措置をとることが可能となり、製品を納期内に納入することが可能となる。
【0006】
この他にも、様々な生産物流活動の管理技術が提案されているが、いずれの従来技術によっても、本発明で解決しようとする課題は解決されない。即ち、同一種類の製品を複数の生産拠点で分担して生産する生産系では、生産開始から納入までに要する期間が最長となる生産拠点からでも間にあう時点で生産拠点別の分担生産台数を決定する必要があるところ、その時点では、仕様別の需要予測を正確に行うことが困難であり、その時点で仕様別の生産台数を確定すると、需要の少ない仕様を多く生産して需要の多い仕様を少なく生産することが頻繁に生じるために、仕様毎の生産と需要のミスマッチを低減したいという課題は、いずれの従来技術によっても解決されない。
【0007】
【課題を解決するための手段】
上述した課題を解決するために創作された本願発明のコンピュータシステムは、図1に模式的に示される構成を有する。
このコンピュータシステムは、同一種類の製品を複数の生産拠点A1,A2,A3,A4・・・で分担して生産する生産系のために、各生産拠点A1,A2,A3,A4・・・で生産する仕様D1,D2,D3,D4・・・別の生産台数(図1の場合、生産拠点Aiで製造する仕様Djの生産台数がYijで示されている)を決定するために用いられる。
このコンピュータシステムは、生産開始してから発注者に納入されるまでに要する期間を生産拠点毎に記憶している期間ファイル54を持つ。表56は期間ファイル54の記憶内容を模式的に例示しており、生産拠点Aiで生産開始してから発注者Bjに納入されるまでにXij日を要することが記憶されている。このファイルには、発注者別に最長期間が記憶されている。例えば、Bjの発注者には、生産拠点別にX1jからX4jまでの期間が記憶されており、このうちの最長期間がXjとして記憶されている。
発注者は、発注側コンピュータ42を利用して需要予測台数を入力する。この場合、前記した最長期間Xjよりも先の時点での需要台数を入力する。後記する分担生産台数を決定して生産開始に備える準備工程にC日を要する場合には、最長期間XjにC日を加えた日数だけ先の時点での需要台数を入力する。
発注側コンピュータ42から入力された需要予測台数46は、需要予測ファイル48に記憶される。
このコンピュータシステムは、需要予測ファイル48の記憶内容に基づいて、分担生産する台数Y1,Y2,Y3,Y4・・を生産拠点A1,A2,A3,A4・・・毎に決定する分担生産台数計算手段50を備えており、この計算手段が生産拠点毎の分担生産台数Y1,Y2,Y3,Y4・・を決定する。この計算過程には様々な手法がとりえる。その一例としては、発注者に対して生産拠点に優先順位を付しておき、優先順位の高い順に配分してゆく計算手順が採用できる。この計算では、複数の生産拠点をトータルして評価したときに、最も効率的に生産を分担できる分担割合を決定する。
生産拠点別の分担生産台数Y1,Y2,Y3,Y4・・が計算されると、期間ファイル54を利用して、立案手段60が、生産拠点別の生産物流計画を立案する。このようにして立案される生産拠点別の生産物流計画の一例がスケジュール64に模式的に図式化されている。スケジュール64は、発注者B1が、X日後にY台の需要が予測されると入力したときに立案される生産物流計画を図式化したものであり、図式化されたスケジュールに従って各生産拠点で生産され、図式化されたスケジュールに従って搬送され、X日後に合計Y台が発注者B1に納入される計画が立案されたことを例示している。なお、立案された生産拠点別の生産物流計画は、生産物流計画ファイル62に記憶される。
発注側コンピュータ42には表示装置44が設けられており、この表示装置44には、少なくとも、生産拠点毎の仕様確定最終日66と分担生産台数70が、生産拠点毎に表示される。この他に、生産拠点別の生産物流計画の図式64を合わせて表示することもできる。仕様確定最終日66は、生産物流計画の生産開始日から計算されるものであり、生産開始日の前日までに仕様が確定しなければならなければその前日であり、生産開始日に仕様が確定していればよい場合には生産開始日に等しい。
発注側コンピュータ42には入力装置40が設けられており、発注者は、表示装置44に表示された生産拠点毎の仕様確定最終日66と分担生産台数70を参照して、表示された仕様確定最終日66までに表示された分担生産台数70の仕様別の内訳台数Yijを入力する。
この場合、発注者は日を追って仕様を決定することができ、正確な仕様別の需要台数を生産台数に反映することができる。
図中74は、生産拠点A2のための仕様確定最終日C2に、生産拠点A2の分担生産台数Y2を、仕様別に配分する場合に表示される、表示画面の一例を示す。生産拠点A2のための仕様確定最終日C2は、スケジュール64に示すように、生産拠点A1のための仕様確定最終日C1と生産拠点A3のための仕様確定最終日C3よりも遅く、生産拠点A4のための仕様確定最終日C4よりも早いために、生産拠点A1についての仕様別の生産台数Y11,Y12,Y13,Y14と、生産拠点A3についての仕様別の生産台数Y31,Y32,Y33,Y34は確定しており、生産拠点A4についての仕様別の生産台数はまだ決定する必要がなく、C2日において生産拠点A2についての仕様別の生産台数を決定する必要があることが画面から直ちに理解される。
この場合、X21日後の需要に基づいて仕様別の生産台数を決定することができ、このX21日はX日(需要予測した期間)に比較して短いことから、近い将来の正確にわかっている情報に基づいて生産拠点A2についての仕様別の生産台数を入力することができる。
【0008】
上記の表示装置44に、仕様D1,D2,D3,D4・・・別に、仕様確定台数α1,α2,α3,α4・・・と割当確定台数β1,β2,β3,β4・・・が対照して表示されることが好ましい。
表74の場合、C2日において生産拠点A2についての仕様別の生産台数を決定する際に、生産拠点A1とA3に対してすでに合計α1台の仕様D1の生産を指示し、一方、納入が予定されている製品のうち、仕様D1については既にβ1台が顧客に割当てられていることを例示している。
発注者は、仕様毎に、生産指示済台数αと割当済台数βを比較することによって、これから生産指示することが妥当な仕様別の生産台数を比較的簡単に知ることができる。
なお、発注者は、顧客が確定した段階で生産を指示することもできれば(C2日以前に顧客が確定した場合には、C2日にその仕様の生産指示をすることができる)、あるいは、既に生産指示してまだ割当てられていない製品を顧客に割当てることもできる。顧客の希望する仕様の生産指示済台数αが割当済台数βよりも大きければ、新たに生産指示する代りに、生産指示済のものを割当てることができる。
【0009】
上記の表示装置44に、製品別に、立案された生産物流計画と、実際の進捗状況が対照して表示されることが好ましい。製品の一台一台ごとに、64に図式化して示すように、計画された生産物流スケジュールと実際の進捗状況が対照して表示されることが好ましい。
この場合、製品一台一台についての追跡調査が可能であり、必要な措置をタイムリーに実行することができる。
【0010】
【発明の実施の形態】
以下、本発明の一実施形態について図面を参照して説明する。以下の説明では、製品の一例として自動車の場合について説明する。
自動車は、グレード、色、オプション装備などの相違により多種類の仕様が存在する。顧客の要望する仕様は流行によって大きく変化するため、顧客が要望する仕様を事前に予測することは困難である。
しかるに、近年の生産拠点・販売拠点のグローバル化によって、自動車は世界各地の生産工場で分担して生産され、これらの生産工場から世界中の販売店に運搬されて販売される種類のものが生じてきている。生産拠点・販売拠点のグローバル化は、生産工場と販売店の組合せによっては、生産工場から出荷されてから販売店に納入されるまでの物流期間の長期化を招く。このため、最も物流期間の長い生産工場での生産の開始から所定の準備期間だけ余裕を持って販売店からの需要予測を提示することとすると、その需要予測は実際に販売店に納入される時点からかなり前のタイミングで行うこととなる。例えば、日本国内で生産した自動車を海外の販売店にて販売する場合は、自動車を海上輸送する期間が必要となるため販売店への納入の4〜5ヶ月前に需要予測を行うこととなる。したがって、販売店が予測した需要(特に仕様)と顧客の要望する仕様が異なる場合が生じる可能性が高くなっている。
そこで、以下に説明する本実施形態の生産物流管理システムは、最も物流期間の長い生産拠点での生産開始に間に合うよう余裕を持って需要予測を行いながら、仕様別の生産台数についてはより後の時点で決定することを可能としている。
【0011】
まず、本実施形態に係る生産物流管理システムの管理対象となる自動車(同一種類)を生産する生産工場群と、その生産工場群で生産された自動車を販売する販売店群について説明する。図2は、生産工場群と販売店群との自動車供給関係を示している。なお、実際には、図に示す以外にも多くの生産工場や販売店があるが、ここでは説明の簡略化のためその図示を省略している。
図2に示すように、生産工場Aはフランスに、生産工場Bはトルコに、生産工場Cはタイに、生産工場Dは日本にあり、それぞれの国で同一種類の自動車を生産している。各生産工場で生産された自動車は、複数の販売店群(販売店a,販売店b)に運搬されて納入される。販売店aはフランスの自動車販売店であり、生産工場A(フランス)と生産工場B(トルコ)と生産工場D(日本)で生産された自動車が運搬されて納入される。また、販売店bはタイの自動車販売店であり、生産工場B(トルコ)と生産工場C(タイ)と生産工場D(日本)で生産された自動車が運搬されて納入される。したがって、販売店aと販売店bには、複数の生産工場で生産された自動車が納入されることとなる。
【0012】
上記のように各販売店には、それぞれ複数の生産工場から自動車が納入されるため、生産工場が異なると物流経路が異なり、生産工場の出荷から販売店に納入されるまでに要する時間(物流リードタイム)が異なることとなる。図3は、販売店aと生産工場A,販売店aと生産工場B,販売店aと生産工場Dについて、仕様確定から販売店到着までの概略の流れを示している。
図3に示すように、生産工場D(日本工場)で生産される製品は、生産開始日より所定日だけ前(本実施形態では、全ての生産工場で生産開始日の前日に仕様が確定する)に仕様が確定し生産が開始される。そして、生産工場での生産が終了すると、まず、港まで陸送され通関手続きが行われる。通関手続きが済むと、海上輸送が行われて港(フランス)に到着し、再度通関手続きが行われ陸送されて販売店に到着する。
例えば、生産工場Dの生産に3日、生産工場Dから港までの陸送に1日、日本での通関手続きに2日、海上輸送に52日、フランスでの通関手続きに2日、港から販売店までの陸送に2日を、それぞれ要するものとすると、フランスの販売店aに納入される車両は、納入日の62日前(3+1+2+52+2+2)に生産工場Dで生産が開始されることとなる。したがって、生産工場Dから納入される車両の仕様は、納入日(例えば、4月17日)の63日前(例えば、2月13日)に確定することとなる。
【0013】
生産工場B(トルコ工場)の場合も、上記の生産工場D(日本工場)と同様に、仕様確定→生産→陸送→通関→海上輸送→通関→陸送を経由して販売店aに到着する。ただし、生産工場Bでは、物流経路、特に、出荷港(トルコ)と到着港(フランス)の間の海上距離が短いため、その分だけ物流リードタイムが短くなる。したがって、生産工場D(日本工場)で生産される車両と生産工場B(トルコ工場)で生産される車両では、同日に販売店aに納入される場合であっても生産工場B(トルコ工場)で生産される車両は生産工場D(日本工場)で生産される車両よりも遅い時点で仕様が確定し生産が開始されることとなる。
具体的に説明すると、例えば、生産工場Bでの生産に3日、生産工場Bから港までの陸送に2日、トルコでの通関手続きに2日、海上輸送に34日、フランスでの通関手続きに2日、港から販売店までの陸送に2日、それぞれ要するものとすると、フランスの販売店aに納入される車両は、納入日の45日前(3+2+2+34+2+2)に生産工場Bで生産が開始される。したがって、生産工場Bから納入される車両の仕様は、納入日(例えば、4月17日)の46日前(例えば、3月2日)に確定することとなる。
【0014】
一方、生産工場A(フランス工場)の場合には、同一国内であるため通関手続きや海上輸送が不要となり、生産工場Aで生産された車両は生産が完了すると陸送されて販売店に納入される。例えば、生産工場Aでの生産に3日、生産工場Aからの陸送に3日を要するものとすると、販売店aに納入される車両は納入日の6日前に生産工場Aで生産が開始される。したがって、生産工場Aから納入される車両の仕様は、納入日(例えば、4月17日)の7日前(例えば、4月10日)に確定することとなる。
以上の説明から明らかなように、販売店に同日に納入される車両であっても、生産される生産工場が異なると、その生産開始日や仕様確定日が異なることとなる。したがって、販売店からみると生産工場ごとに仕様変更が可能な時期が異なることとなる。
【0015】
以下、本実施形態の生産物流管理システムを詳細に説明する。図4は本実施形態の生産物流管理システムの概略構成を示す図である。図4に示すように、本実施形態の生産物流管理システムは、本社等に設置される一の受注側コンピュータ10と、各販売店ごとに設置される複数の販売店端末30(発注側コンピュータ)とで構成される。受注側コンピュータ10と各販売店端末30は、データ通信が可能なように接続されている。
【0016】
図5は受注側コンピュータ10と販売店端末30(1台のみを図示)の機能ブロック図を示している。図5に示すように、受注側コンピュータ10は、需要予測ファイル12と期間ファイル14と生産物流計画ファイル16を備える。
需要予測ファイル12は、各販売店端末30から入力される需要予測台数を記憶する。具体的には、図6に示すように、入力された販売店と納入希望日と発注台数が記憶されている。図6の例では、フランス販売店aが納入希望日X1月Y1日にn1台という需要(発注)があり、タイ販売店bが納入希望日X2月Y2日にn2台という需要(発注)がある例を示している。
ここで、販売店端末30から需要予測を入力する時期は、その販売店端末が設置された販売店に自動車を納入する生産工場のうち、最も生産物流期間が長く要する生産工場を基準に決められている。具体的には、納入希望日より最も長くなる生産物流期間を遡り、その遡った日(生産開始日)よりさらに所定の期間〔生産物流計画立案から生産に取掛かるための準備期間(本実施形態では3ヶ月)〕だけ遡った時点で需要予測を入力するようになっている。図3の販売店a(フランス)の場合を例に説明すると、図3から明らかなように、販売店aに自動車を供給する生産工場A(フランス),生産工場B(トルコ),生産工場D(日本)のうち、最も生産物流期間が長い生産工場は生産工場Dである。したがって、販売店aは、生産工場Dの生産から販売店aへの納入に要する生産物流期間(例えば62日)だけ納入希望日を遡り、その遡った日からさらに3ヶ月遡った時点(納入希望日から約5ヶ月前)で需要予測を入力することとなる。例えば、フランス販売店aは、8月中旬の需要予測を3月中旬に入力することとなる。
なお、販売店端末30から需要予測を入力する時期は各販売店ごとに異なる。各販売店には異なる複数の生産工場群から車両が納入され、その最長生産物流期間も販売店によって異なるためである。
【0017】
期間ファイル14は、生産を開始してから販売店に納入されるまでに要する期間を生産拠点毎に記憶する。図7には、図3を用いて説明した生産工場D(日本)と販売店a(フランス)、生産工場B(トルコ)と販売店a(フランス)、生産工場A(フランス)と販売店a(フランス)のそれぞれに関する期間ファイルを示している。
図7から明らかなように、期間ファイル14は、各生産工場における生産開始から販売店に納入されるまでの工程をいくつかの工程に分割し、各工程に要する期間を記憶している。例えば、生産工場D(日本)で生産され販売店a(フランス)に納入される場合は、ホデー・塗装期間,組立期間,陸送期間,通関期間,海上輸送期間,通関期間,陸送期間のそれぞれについて標準通過日数が記憶されている。なお、生産工場A(フランス)で生産され販売店a(フランス)に納入される場合は、通関期間・海上輸送期間等が不要なため、その部分については記憶されていない。
【0018】
生産物流計画ファイル16は、生産工場別に当該生産工場で生産される車両の生産の開始から販売店への納入予定日までを記憶する。図8に生産工場D(日本)についての生産計画ファイルの一例を示している。図8に示すように、生産物流計画ファイル16には、当該生産工場で生産される製品(製品ID)ごとに仕向け先、仕様情報、車両仕様、顧客情報、仕様確定から販売店への納入までの予定時刻と実績時刻が記憶されている。
仕向け先は、当該生産車両がどの販売店向けの車両かを示す情報であり、後述する分担生産台数計算手段20により各生産工場の分担生産台数(仕向け先別生産台数)が決まるときに決定される。例えば、図8に示す例では、製品ID0001,0005の車両はフランスに向けて生産され、製品ID0002,0003の車両は日本に向けて生産され、製品ID0004の車両は米国に向けて生産される。
仕様情報は、仕様が確定している否かを示す情報であり、車両仕様は生産される製品の仕様(グレード・オプション等)を示す情報である。また、顧客情報は、生産される製品に顧客が割当てられているか否かを示す情報である。なお、本実施形態では、基本的には生産開始日(着工日)の前日に仕様が確定するが、顧客が割当てられている製品については顧客の要望する仕様であるため、着工日の前日より前であっても仕様情報として‘確定’が格納される。例えば、図8に示す製品ID0001の車両は、仕様確定日前(他の車両は仕様情報が‘未’となっている)であっても顧客が割当てられ仕様が確定しているため、仕様情報の欄には‘確定’が格納されている。
また、生産物流計画ファイル16には、製品の仕様確定(生産開始)から販売店に納入されるまでの各工程についての通過予定日が格納される。すなわち、製品の仕向け先が決まれば、当該製品の生産開始から販売店への納入までの生産物流過程が決まる。生産物流過程が決まると、期間ファイル14によってその生産物流過程の各工程の標準通過期間が分かるため、各工程の通過予定日が算出され、その算出された通過予定日が生産物流計画ファイル16に格納される。この通過予定期間の算出は後述する生産物流計画立案手段22によって行われる。
さらに、生産物流計画ファイル16には、上述のように各工程について算出された通過予定日に対応して通過実績日が格納される。すなわち、製品が各工程を通過すると、各工程に設置された端末(図示省略)から受注側コンピュータ10にその通過した製品の製品IDが送信され、その送信日が通過実績日として格納される。これにより、製品の生産物流過程の進捗状況が管理される。
【0019】
受注側コンピュータ10は、さらに、需要予測ファイル更新手段18、分担生産台数計算手段20、生産物流計画立案手段22、ファイル検索手段24を有する。
需要予測ファイル更新手段18は、販売店端末30から需要予測(納入希望日と納入台数)が入力されると、その情報を需要予測ファイル12に記憶する。例えば、販売店a(フランス)の販売店端末30から納入希望日X1月Y1日にn1台の注文を受けると、図6に示すように需要予測ファイル12にその注文を記憶する。
【0020】
分担生産台数計算手段20は、需要予測ファイル12に記憶されている各販売店の需要予測(注文)に基づいて、各生産工場における各販売店向けの生産台数(仕向け先別生産台数)を決定する。
具体的には、生産工場から販売店までの物流リードタイム等を考慮して、販売店別に各生産工場に優先順位を付しておき、各販売店の需要予測(発注台数)を優先順位の高い生産工場から順に配分する。例えば、販売店a(フランス)からn台の発注(需要予測)があった場合、そのn台の生産を優先的に物流コストが最も低くなる生産工場A(フランス)に分担させる。そして、生産工場A(フランス)の生産能力では不足する場合に、次に物流コストが低い生産工場B(トルコ)に分担させ、それでも不足する場合に生産工場D(日本)に分担させる。このような手順によって、全ての販売店の需要を満足するよう各生産工場の分担生産台数を決めた後、各生産工場の負荷が平準化するよう生産台数の再調整をすることで、各生産工場の生産効率を最大化する。
上述のようにして決定される仕向け先別生産台数の一例を、生産工場D(日本)と生産工場A(フランス)について図9に示す。図9に示す例では、生産工場D(日本)は一日当りの総生産台数が280台であり、そのうち20台がフランス向け、20台がタイ向け、40台が米国向け、残り200台が国内(日本)向けに生産される。また、生産工場A(フランス)は、生産工場Dと同様に一日当りの総生産台数が280台であり、そのうち100台がイギリス向け、30台が米国向け、150台がフランス向けに生産される。したがって、図9の例では日本工場で生産された自動車がイギリスに出荷されることはなく、また、フランス工場で生産された自動車がタイや日本に出荷されることはない。
上述の説明から明らかなように、各生産工場の分担生産台数(仕向け先別生産台数)は生産工場ごとに異なり、また、各国の需要(各国の好景気・不景気による自動車需要の増減等)によって時期的にも変動することとなる。なお、一部の生産工場によっては、仕向け先別生産台数を設けずに車両(すなわち、全ての販売店向けの車両)を生産するようにしても良い。
【0021】
生産物流計画立案手段22は、上述した分担生産台数計算手段20によって各生産工場の仕向け先別生産台数(すなわち、生産される車両の仕向け先)が決まると、その工場で生産される車両の生産の開始から販売店への納入までの生産物流計画を立案する。
具体的には、仕向け先別生産台数が決まると生産工場で生産される車両の仕向け先を決めることができるため、期間ファイル14の内容から、その車両の工場出荷後の物流工程が特定できる。したがって、その車両の生産開始日が決まれば、期間ファイル14の内容から、その車両の仕様確定日,塗装完了予定日,ラインオフ予定日,・・販売店到着予定日等を算出する。これらの算出された予定日は、生産物流計画ファイル16に記憶される。例えば、2月14日に生産工場D(日本)で販売店a(フランス)向けの車両が生産開始されるものとする。この車両の各工程に要する期間は、期間ファイル14(図7参照)から判明しているため、この期間ファイル14に記憶されている期間を利用して各工程の通過予定日を算出する。すなわち、生産開始日(例えば、2月14日)にボデー・塗装期間を加算することで塗装完了予定日(例えば、2月16日)を算出する。以下順に期間ファイル14に記憶されている各工程の期間を加算することで、各工程の通過予定日を算出し、最終的に販売店aへの到着予定日(例えば、4月17日)を算出する。なお、本実施形態では、生産開始日の前日が仕様確定日であるため、このことから仕様確定日(例えば、2月13日)が算出される。このように算出された各工程の通過予定日は、生産物流計画ファイル16に格納されることとなる(図8参照)。
【0022】
ファイル検索手段24は、後述する販売店端末30より検索条件(例えば販売店到着日等)が入力されたときに、生産物流計画ファイル16から該当する車両を検索する。
【0023】
上述したように構成される受注側コンピュータ10と接続される販売店端末30は、例えば、汎用のコンピュータにより構成される。この販売店端末30は、検索条件等を入力する入力装置32、検索結果を表示する表示装置36、受注側コンピュータ10とデータの送受信を行うデータ処理手段34を備える。
入力装置32は、キーボードやマウス等であり、既に説明した需要予測や生産物流計画ファイル16を検索する際の検索条件等を入力する装置である。表示装置36は、上記のファイル検索手段24によって検索された結果を表示する装置である。また、データ処理手段34は、入力された情報を受注側コンピュータ10に送信したり、受注側コンピュータ10から送信されたデータを受けて表示装置36に画像を表示する処理を行う。
【0024】
次に、上述のように構成される生産物流管理システムの作用について説明する。まず、受注側コンピュータ10により生産物流計画が立案される際の手順を、図10に示すフローチャートを参照して説明する。なお、受注側コンピュータ10による生産物流計画の立案は、所定の期間毎(例えば1週間毎)に行われ、前回の生産物流計画立案後に受注した車両について生産物流計画を立案する。
受注側コンピュータ10は、まず、需要予測ファイル12に記憶されているデータから販売店毎の総需要(総注文台数)を算出する(ステップS1)。すなわち、需要予測ファイル12に記憶されている各販売店からの注文を販売店毎に集計する。例えば、需要予測ファイル12に同一の販売店から複数の注文が記憶されている場合には、その注文台数を集計することで総注文台数を算出する。なお、ステップS1により集計され生産計画に組み込まれたデータはクリアされるため、その後の周期の生産物流計画立案処理において処理されることはない。
ステップS2では、ステップS1の処理により販売店毎に算出された総発注台数に基づいて、分担生産台数計算手段20が各生産工場の仕向け先別の生産台数を算出する。この処理によって、各生産工場には仕向け先別生産枠(図9参照)が設けられ、各生産工場で生産される各車両の仕向け先が決定される。
ステップS3では、ステップS2の処理によって決まる仕向け先別生産台数に基づいて各生産工場で生産される車両の仕向け先を決め、期間ファイル14を参照して生産開始から販売店への納入までにおける各工程の通過予定日が算出される。
生産工場群で生産される全ての車両について、各工程の通過予定日が算出されて生産物流計画が立案されると、その新たに生産物流計画が立案された車両を生産物流計画ファイル16(図8参照)に追加する(ステップS4)。
なお、既に説明したことから明らかなように、上述の処理により新たに生産物流計画が立案された車両は、仕向け先は決まっているものの、具体的な仕様については決められていない。具体的な仕様は、仕様確定日までに販売店端末30から指示されることとなる。
【0025】
次に、販売店端末30を用いて生産物流計画ファイル16に記憶されている車両について仕様を指示する際の手順の一例を、図11に示すフローチャートを参照して説明する。
ステップS10で、販売店は、生産物流計画ファイル16を検索する検索条件として販売店到着日を入力装置32から入力する。
販売店到着日が入力されると、入力された販売店到着日(検索条件)が販売店端末30から受注側コンピュータ10に送信される(ステップS12)。このステップS12の検索条件の送信と同時に販売店のID情報も受注側コンピュータ10に送信される。これにより、受注側コンピュータ10は、いずれの販売店から検索要求を受けたのかを認識する。
【0026】
ステップS14では、受注側コンピュータ10のファイル検索手段24が、生産物流計画ファイル16内に記憶されている当該販売店を仕向け先とする車両の中から、入力された販売店到着日に販売店に到着する予定の車両を検索する。
具体的には、まず、生産物流計画ファイル16に記憶されている車両の中で仕向け先が当該販売店となっているものを抽出し、さらに、その検索された車両の中で、販売店への到着予定日が入力された販売店到着日であるものを抽出する。例えば、販売店a(フランス)に設置された販売店端末30から販売店到着日が4月17日と入力され、図8に示す生産物流計画ファイル16〔生産工場D(日本)の生産物流計画ファイル〕を検索する場合を考える。この場合、生産物流計画ファイル16に記憶されている車両で、販売店aを仕向け先とし、かつ、販売店到着予定日が4月17日のものは製品ID0001,0005・・の車両である。したがって、ファイル検索手段24はこれらの車両を抽出する。なお、実際には販売店aを仕向け先とする車両は、生産工場A(フランス)や生産工場B(トルコ)でも生産される。したがって、これらの生産工場の生産物流計画ファイル16についても検索されると、これらの生産工場で生産される車両についも抽出されることとなる。
【0027】
ステップS14の検索処理が終了すると、その検索結果が受注側コンピュータ10から販売店端末30に出力される(ステップS16)。受注側コンピュータ10から出力された検索結果を販売店端末30が受信すると、その受信した検索結果が表示装置36に表示される(ステップS18)。
例えば、上述の販売店aから販売店到着日として4月17日が入力された場合には、図12に示すような検索結果が表示装置36に表示される。図12では、4月17日に販売店a(フランス)に納入される予定の車両は、生産工場A(フランス)から3台、生産工場B(トルコ)から2台、生産工場D(日本)から2台であることが示されている。また、生産工場A(フランス)で生産される車両の仕様確定日(4月10日)と、生産工場B(トルコ)で生産される車両の仕様確定日(3月2日)と、生産工場D(日本)で生産される車両の仕様確定日(2月13日)が表示される。したがって、販売店aは生産工場D(フランス)で生産される3台の車両については4月11日までに仕様を確定すれば良いことが分かり、生産工場B(トルコ)で生産される2台の車両については3月2日までに仕様を確定すれば良いことが分かり、生産工場D(日本)で生産される2台の車両については2月13日までに仕様を確定すれば良いことが分かる。このため、販売店a(フランス)は、生産工場によって異なる上記の仕様確定日までに順に仕様を決定すれば良いこととなる。この際、表示装置36には、仕様が確定したか否かの仕様情報、顧客が割当てられているか否かの顧客情報が併せて示されるので、仕様を指示することができる車両か否か、顧客を割当てることができる車両か否かを知ることができる。
また、仕様情報と顧客情報から仕様が確定しているが未だ顧客が確定していない車両(すなわち、仕様確定日までに顧客が割当てられなかった車両)については、販売店に到着するまで販売店端末30により顧客を割当てることができる。さらには、図12に示すように、通過予定日と実際の通過日が併せて示されるため、その製品がどの段階まで工程が終了しているか等を知ることができ、商談中の顧客に即座に応答することができる。
なお、該当する車両が検索されなかった場合には、該当車両が検索されなかった旨が表示装置36に表示される。
【0028】
ステップS18で検索結果が表示装置36に表示されるため、販売店a(販売店の販売スタッフ等)は表示画面に表示された車両について、入力装置32を用いて顧客の割当てを行ったり、仕様を指示する(ステップS20)。
ステップS20で顧客割当てや確定した仕様が指示されると、その情報が販売店端末30から受注側コンピュータ10に送信され(ステップS22)、受注側コンピュータ10は、その情報を基に生産物流計画ファイル16を更新する(ステップS24)。
【0029】
なお、上述した図11のフローチャートを用いて説明した販売店端末30を用いた顧客割当て,仕様入力の手順は単なる一例であって、販売店は種々の方法で顧客の割当て,仕様入力を行うことができる。例えば、販売店端末から販売店到着日と仕様確定日(期間として入力することも可能)を入力し、仕様が確定していない車両のみを検索し顧客の割当て・仕様入力を行うようにしても良い。この際には同時に、入力された販売店到着日に販売店に到着する車両の中で仕様が確定している生産台数と、顧客が割当てられている生産台数を仕様別に対照して表示されることが好ましい。このように仕様別に仕様確定台数と顧客割当て台数が表示されると、その時点で余剰となっている仕様の車両が分かるため、販売店はこれらの情報を参照して仕様を指示することができる。
また、顧客が割当てられ仕様が確定している車両についても、当該顧客からの仕様変更の依頼があり、その依頼が仕様確定日前であれば仕様変更を行うことも可能である。
【0030】
上述してきたことから明らかなように、本実施形態の生産物流管理システムは、販売店から提示される需要予測に基づいて製品の仕向け先のみが決定され生産物流計画を立案する。そして、製品の仕様については、生産工場毎に決まる仕様確定日までに販売店が指示することができる。すなわち、販売店が提示する需要予測時点では車両の仕様を決定する必要はなく、生産される製品の仕様は仕様確定日までに行えば良い。したがって、需要予測が実際の販売店への納入よりかなり前の時点で行う場合でも、その仕様は販売店への納入日に近い仕様確定日までに行えば良いことから、生産される車両の仕様を実際の顧客の要望に一致させ易くなる。
また、上記の説明から明らかなように、販売店による顧客の割当てや仕様の指示は、当該販売店を仕向け先としている車両に限られる。このため、生産物流効率を最大化するよう立案された生産物流計画の分担台数が、その後の顧客割当てや仕様変更等によって変更されることはない。
さらには、本実施形態の生産物流管理システムを用いると、製品の生産から販売店への納入までの各工程の通過予定日と実績日が表示されるため、実績日が通過予定日より遅れているものについては、その後の工程での優先度を上げること等により納期の遵守に寄与することができる。
【0031】
以上、本発明の好適な一実施形態について詳細に説明したが、これは例示に過ぎず、本発明は当業者の知識に基づいて種々の変更、改良を施した形態で実施することができる。
例えば、上述の実施形態では、各生産工場・各販売店が世界各国にある例であったが、本発明はこのような場合に限られず、生産工場・販売店が国内各地に複数ある場合にも適用することができる。すなわち、日本各地に同一種類の製品を生産する生産工場があり、これらの生産工場で生産される製品を販売する販売店が日本各地に複数ある場合にも本発明のシステムを適用することができる。この場合であっても、各生産工場から各販売店までの物流過程が考慮されて製品の仕様確定日等が提示されるため、生産工場毎により近い将来の予測に基づいて製品の仕様を指示することができる。
また、上述の実施形態では、受注側コンピュータにより各生産工場の分担生産台数と生産物流計画が立案されたが、本発明はこのような例に限られない。例えば、各生産工場の分担生産台数の決定は一のコンピュータにより行う。そして、このコンピュータにより決定された分担生産台数に基づいて各生産工場に設置された管理コンピュータが、当該生産工場で生産される製品の生産物流計画を立案する(生産物流計画ファイルを作成する)。このような構成の場合、販売店端末は各生産工場の生産物流計画ファイルに個別にアクセスすることで、当該販売店を仕向け先とする車両を検索することとなる。
【0032】
なお、本明細書または図面に説明した技術要素は、単独であるいは各種の組み合わせによって技術的有用性を発揮するものであり、出願時請求項記載の組み合わせに限定されるものではない。また、本明細書または図面に例示した技術は複数の目的を同時に達成するものであり、そのうちの一つの目的を達成すること自体で技術的有用性を持つものである。
【図面の簡単な説明】
【図1】 本発明のコンピュータシステムの概要を示す図である。
【図2】 本実施形態の生産物流管理システムの管理対象となる製品(自動車)を生産する生産工場と、その生産工場で生産された製品を販売する販売店の関係を示す図である。
【図3】 生産工場における仕様の確定から販売店に製品が納入されるまでの概略の流れを示す図である。
【図4】 本実施形態の生産物流管理システムの概略構成を示す図である。
【図5】 本実施形態の生産物流管理システムの機能ブロック図である。
【図6】 需要予測ファイルの内容を示す図である。
【図7】 期間ファイルの内容を示す図である。
【図8】 生産物流計画ファイルの内容を示す図である。
【図9】 生産工場に設定される仕向け先別生産台数の一例を示す図である。
【図10】 受注側コンピュータによる生産物流計画立案処理の手順を示すフローチャートである。
【図11】 販売店端末を用いて顧客割当てを行う一手順を示すフローチャートである。
【図12】 販売店端末に表示される検索結果の一例を示す図である。
【符号の説明】
10・・受注側コンピュータ
12・・需要予測ファイル
14・・期間ファイル
16・・生産物流計画ファイル
18・・需要予測ファイル更新手段
20・・分担生産台数計算手段
22・・生産物流計画立案手段
24・・ファイル検索手段
30・・販売店端末
32・・入力装置
36・・表示装置
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a computer system for determining the number of productions according to specifications produced at each production base in order to produce the same type of product at a plurality of production bases.
The specification here refers to a fine type within the same type. For example, if there are a type 1 passenger car and a type 2 passenger car, and there is a type 1 passenger car with and without a roof window, the specifications differ depending on the presence or absence of the roof window.
[0002]
[Prior art]
For example, in the case of an automobile, the same type of product is shared by a plurality of production bases. In this case, the period required from the start of automobile production to delivery to the orderer varies from production site to production site. For example, if a Hokkaido dealer orders a car that is manufactured at either the Hokkaido factory or the Kyushu factory, the car manufactured at the Kyushu factory and transported to Hokkaido will be manufactured at the Hokkaido factory and transported to the Hokkaido dealer. It takes a long time. If the time to delivery is short, the Kyushu factory will not make it in time, and it will have to be manufactured at the Hokkaido factory.
When manufacturing the same type of product at a plurality of production bases, it is necessary to improve the total production efficiency of the production base group by rationally determining the ratio of the divisions. For this purpose, it is necessary to be able to determine the sharing ratio as freely as possible.
Therefore, at present, the demand is predicted by the orderer with enough time. In the case of the previous example, even if the Kyushu factory is to share the demand, the demand is predicted when it is still in time. If the demand is predicted at this point, it is possible to determine the optimum share in consideration of the production capacity and busyness of each production base.
[0003]
[Problems to be solved by the invention]
For efficient operation of production bases, it is necessary to predict demand at a point in time even if production is shared at the production base that takes the longest time from production start to delivery. On the other hand, if the period from the demand forecast to the delivery is long, it is difficult to make an important forecast accurately, and there is a possibility that the production does not meet the actual demand.
In particular, this problem becomes a big problem when determining the number of production by specification within a type. When the number of production by specification is determined according to the above schedule, it is possible to produce many specifications with low demand while producing few specifications with high demand.
It is necessary to determine the number of shared productions for each production site according to the above schedule, and it is difficult to change this thereafter, and if it is changed forcibly, the production efficiency is lowered. However, the number of production by specification can be changed until just before the start of production. For example, after a plan to produce one type of passenger car Y1 at production base A1 and Y2 production at production base A2 is confirmed, breakdown by specification of Y1 cars produced at production base A1 and production base It is possible to determine the breakdown by specification of the Y2 units produced at A2. If the breakdown by specification is determined by the time of actual production at the production site, not at the time of determining the number of shared production by production site, many specifications with low demand are produced and there is much demand. It is possible to avoid the occurrence of a situation in which the number of specifications is reduced.
[0004]
In the present invention, the determination of the number of shared production by production base is not limited by the period (for that purpose, the production base is separated at the point in time even from the production base where the period from the start of production to delivery is the longest. However, the purpose is to realize a computer system that can determine the number of production by specification based on accurate demand forecast at a later point in time. .
[0005]
Techniques for managing the progress from product production to sales are described, for example, in Japanese Patent Laid-Open Nos. 8-96045 and 8-137961.
This management technology divides the process from product production to sales into several processes. When an order is received from a customer, a production plan for the product is drawn up according to the received order, and production of the product is started based on the planned production plan. When the production of the product is started, the time at which the product has passed through the above-described steps is sequentially stored. According to this technology, it is possible to grasp the progress of production logistics activities from the planned transit time and the actual transit time. As a result, it is possible to take necessary measures such as raising the priority in the subsequent process for products whose progress is delayed, and it is possible to deliver the products within the delivery date.
[0006]
In addition, various management techniques for production logistics activities have been proposed, but none of the conventional techniques can solve the problem to be solved by the present invention. In other words, in production systems that share the same type of product at multiple production bases, the number of shared production by production base is determined at the point in time that the production period from the start of production to delivery is the longest. At that time, it is difficult to accurately forecast demand by specification at that time, and when the number of production by specification is determined at that time, many specifications with low demand are produced and specifications with high demand are produced. Since the production of a small amount frequently occurs, the problem of reducing the mismatch between production and demand for each specification is not solved by any conventional technology.
[0007]
[Means for Solving the Problems]
The computer system of the present invention created to solve the above-described problem has a configuration schematically shown in FIG.
This computer system is a production system in which products of the same type are divided and produced by a plurality of production bases A1, A2, A3, A4..., So that each production base A1, A2, A3, A4. Used to determine specifications D1, D2, D3, D4,..., Another production quantity to be produced (in the case of FIG. 1, the production quantity of the specification Dj produced at the production site Ai is indicated by Yij).
This computer system has a period file 54 in which a period required from the start of production to delivery to an orderer is stored for each production site. Table 56 schematically illustrates the storage contents of the period file 54, and stores that it takes Xij days from the start of production at the production site Ai to delivery to the orderer Bj. This file stores the longest period for each client. For example, the orderer of Bj stores a period from X1j to X4j for each production base, and the longest period among them is stored as Xj.
The orderer uses the ordering computer 42 to input the demand forecast number. In this case, the number of demands at the time before the longest period Xj is input. In the case where C days are required for the preparation process for determining the shared production number to be described later and preparing for the start of production, the number of demands at the previous time point is input by the number of days obtained by adding C days to the longest period Xj.
The demand forecast quantity 46 input from the ordering computer 42 is stored in the demand forecast file 48.
In this computer system, based on the stored contents of the demand forecast file 48, the number of shares to be produced is determined for each production site A1, A2, A3, A4,. Means 50 are provided, and this calculation means determines the number of production units Y1, Y2, Y3, Y4,. Various methods can be used for this calculation process. As an example, a calculation procedure can be adopted in which priority is given to the production base for the orderer and the order is allocated in descending order of priority. In this calculation, when a plurality of production bases are evaluated in total, a share ratio that can share production most efficiently is determined.
When the shared production numbers Y1, Y2, Y3, Y4,... For each production base are calculated, the planning means 60 uses the period file 54 to formulate a production logistics plan for each production base. An example of a production logistics plan for each production site that is planned in this manner is schematically illustrated in a schedule 64. The schedule 64 is a diagram of a production logistics plan that is planned when the orderer B1 inputs that demand for Y units is predicted after X days, and is produced at each production site according to the schematized schedule. It is illustrated that a plan has been made in which a total of Y units are delivered to the orderer B1 after X days after being transported in accordance with the schematized schedule. The planned production logistics plan for each production site is stored in the production logistics plan file 62.
The ordering computer 42 is provided with a display device 44. The display device 44 displays at least the specification finalization date 66 and the shared production quantity 70 for each production site for each production site. In addition to this, it is also possible to display a diagram 64 of the production distribution plan for each production base. The final specification date 66 is calculated from the production start date of the production distribution plan. If the specification has to be finalized by the day before the production start date, it is the day before the specification, and the specification is finalized on the production start date. If it should be, it is equal to the production start date.
The ordering computer 42 is provided with an input device 40, and the orderer confirms the displayed specifications by referring to the specification finalizing date 66 and the shared production quantity 70 for each production base displayed on the display device 44. The breakdown number Yij by specification of the shared production number 70 displayed by the last day 66 is input.
In this case, the orderer can determine the specifications day by day, and can accurately reflect the demand quantity for each specification in the production quantity.
In the figure, 74 shows an example of a display screen that is displayed when the shared production quantity Y2 of the production base A2 is distributed according to the specifications on the final date C2 of specification specification for the production base A2. As shown in the schedule 64, the final specification date C2 for the production site A2 is later than the final specification date C1 for the production site A1 and the final specification date C3 for the production site A3. Therefore, the production number Y11, Y12, Y13, Y14 by specification for the production site A1 and the production number Y31, Y32, Y33, Y34 by specification for the production site A3 From the screen, it is immediately understood that it is not necessary to determine the number of production by specification for the production base A4, and it is necessary to determine the number of production by specification for the production base A2 on the C2 day. The
In this case, the number of production by specification can be determined based on the demand after X21 days, and since this X21 day is shorter than the X day (demand forecast period), it is accurately known in the near future. Based on the information, it is possible to input the number of production by specification for the production base A2.
[0008]
The above-mentioned display device 44 is contrasted with specifications D1, D2, D3, D4,..., Specifications determined number α1, α2, α3, α4... And allocation determined numbers β1, β2, β3, β4. Are preferably displayed.
In the case of Table 74, when determining the number of production by specification for the production base A2 on the C2 day, the production bases A1 and A3 are already instructed to produce a total of α1 specifications D1, while delivery is scheduled. Among the products that have been manufactured, the specification D1 illustrates that β1 units have already been allocated to customers.
The orderer can relatively easily know the number of production by specification that is appropriate to be instructed from now on by comparing the production instructed number α and the assigned number β for each specification.
The orderer can also instruct production at the stage when the customer is confirmed (if the customer is confirmed before C2 day, the production instruction for the specification can be given on C2 day), or already It is also possible to assign a product that has not yet been assigned by the production instruction to the customer. If the production-instructed number α of the specification desired by the customer is larger than the allocated number β, it is possible to assign a production-instructed one instead of instructing a new production.
[0009]
It is preferable that the above-described display device 44 displays the production logistics plan prepared for each product and the actual progress in contrast. For each product, as shown schematically in 64, it is preferable that the planned production distribution schedule and actual progress are displayed in contrast.
In this case, it is possible to carry out a follow-up survey for each product and to perform necessary measures in a timely manner.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In the following description, a case of an automobile will be described as an example of a product.
There are many types of specifications for automobiles due to differences in grades, colors, and optional equipment. Since specifications requested by customers vary greatly depending on the fashion, it is difficult to predict specifications requested by customers in advance.
However, with the recent globalization of production and sales bases, automobiles are produced by sharing production at production plants around the world, and there are some types of vehicles that are transported from these production plants to sales outlets around the world for sale. It is coming. The globalization of production bases and sales bases, depending on the combination of production factories and dealers, may lead to an extended distribution period from shipment from production factories to delivery to dealers. For this reason, if the demand forecast from the dealer is presented with a margin for the predetermined preparation period from the start of production at the production factory with the longest logistics period, the demand forecast is actually delivered to the dealer. It will be performed at a timing considerably before the time. For example, when a car produced in Japan is sold at an overseas dealership, it is necessary to forecast the demand four to five months before delivery to the dealership because a period of ocean transportation is required. . Therefore, there is a high possibility that the demand (especially specifications) predicted by the sales store is different from the specifications requested by the customer.
Therefore, the production logistics management system of the present embodiment described below performs demand forecast with a margin in time for the start of production at the production base with the longest logistics period, and the production volume by specification is later. It is possible to decide at the time.
[0011]
First, a description will be given of a production factory group that produces automobiles (the same type) to be managed by the production logistics management system according to the present embodiment, and a dealer group that sells automobiles produced in the production factory group. FIG. 2 shows the car supply relationship between production factories and dealers. Actually, there are many production factories and sales stores other than those shown in the figure, but the illustration is omitted here for the sake of simplicity.
As shown in FIG. 2, production factory A is in France, production factory B is in Turkey, production factory C is in Thailand, and production factory D is in Japan. The cars produced at each production factory are transported to a plurality of dealer groups (sales shop a, b). The dealer a is a French automobile dealer. Cars produced at the production factory A (France), the production factory B (Turkey), and the production factory D (Japan) are transported and delivered. Further, the dealer b is a Thai automobile dealer, and the cars produced at the production factory B (Turkey), the production factory C (Thailand), and the production factory D (Japan) are transported and delivered. Accordingly, the automobiles produced at a plurality of production factories are delivered to the dealer a and the dealer b.
[0012]
As mentioned above, automobiles are delivered to each dealership from multiple production factories. Therefore, the distribution route differs depending on the production factory, and the time required from delivery of the production factory to delivery to the dealership (distribution Lead time) will be different. FIG. 3 shows an outline flow from specification confirmation to arrival at a dealership a and a production factory A, a dealer a and a production factory B, and a dealer a and a production factory D.
As shown in FIG. 3, the specifications of the products produced at the production factory D (Japan factory) are determined only a predetermined day before the production start date (in this embodiment, the specifications are determined on the day before the production start date at all production plants). ) The specifications are finalized and production begins. When production at the production plant is completed, the cargo is first transported to the port for customs clearance. When customs clearance is completed, sea transportation is carried out and arrives at the port (France), customs clearance is carried out again, land transported, and arrival at the store.
For example, 3 days for production at production factory D, 1 day for land transportation from production factory D to port, 2 days for customs clearance in Japan, 52 days for maritime transportation, 2 days for customs clearance in France, 2 days from port Assuming that two days are required for land transportation to the store, production of the vehicle delivered to the French dealer a starts at the production factory D 62 days before the delivery date (3 + 1 + 2 + 52 + 2 + 2). Therefore, the specification of the vehicle delivered from the production factory D is fixed 63 days before the delivery date (eg, April 17) (eg, February 13).
[0013]
In the case of the production factory B (Turkish factory), as in the case of the production factory D (Japan factory), the specification arrives at the store a via specification confirmation → production → land transportation → customs clearance → sea transportation → customs clearance → land transportation. However, in the production factory B, the logistics lead time, particularly the maritime distance between the shipping port (Turkey) and the arrival port (France) is short, so the logistics lead time is shortened accordingly. Therefore, for vehicles produced at production plant D (Japan plant) and vehicles produced at production plant B (Turkish plant), production plant B (Turkish plant) even if delivered to dealer a on the same day. The specifications of the vehicle produced in the above are determined and production is started at a later time than the vehicle produced in the production factory D (Japan factory).
Specifically, for example, 3 days for production at production plant B, 2 days for land transportation from production plant B to the port, 2 days for customs clearance in Turkey, 34 days for maritime transportation, customs clearance in France 2 days and 2 days for land transportation from the port to the dealership, the vehicles delivered to the French dealership a will be produced at the production plant B 45 days before the delivery date (3 + 2 + 2 + 34 + 2 + 2). The Therefore, the specification of the vehicle delivered from the production factory B is determined 46 days before the delivery date (eg, April 17) (eg, March 2).
[0014]
On the other hand, in the case of the production factory A (French factory), since it is in the same country, customs clearance procedures and maritime transportation are not required, and vehicles produced at the production factory A are transported by land and delivered to the dealers when production is completed. . For example, if it takes 3 days for production at production factory A and 3 days for land transportation from production factory A, the vehicle delivered to dealer a starts production at production factory A six days before the delivery date. The Therefore, the specification of the vehicle delivered from the production factory A is determined 7 days before the delivery date (eg, April 17) (eg, April 10).
As is clear from the above description, even if the vehicle is delivered to the dealer on the same day, the production start date and the specification confirmation date will be different if the production factory to be produced is different. Therefore, from the point of view of the dealer, the time when the specification can be changed differs for each production factory.
[0015]
Hereinafter, the production distribution management system of this embodiment will be described in detail. FIG. 4 is a diagram showing a schematic configuration of the product distribution management system of the present embodiment. As shown in FIG. 4, the production logistics management system of this embodiment includes one order-receiving computer 10 installed at a head office and a plurality of dealer terminals 30 (ordering computers) installed at each dealer. It consists of. The order-receiving computer 10 and each store terminal 30 are connected so that data communication is possible.
[0016]
FIG. 5 shows a functional block diagram of the order-receiving computer 10 and the store terminal 30 (only one is shown). As shown in FIG. 5, the order-receiving computer 10 includes a demand forecast file 12, a period file 14, and a production distribution plan file 16.
The demand prediction file 12 stores the number of demand predictions input from each store terminal 30. Specifically, as shown in FIG. 6, the input store, the desired delivery date, and the number of orders are stored. In the example of FIG. 6, the French store a has a demand (order) of n1 units on the desired delivery date XJan Y1, and the Thai store b has a demand (order) of n2 units on the desired delivery date XFebruary Y2. An example is shown.
Here, the time when the demand forecast is input from the dealer terminal 30 can be determined based on the production factory that takes the longest production logistics period among the production factories that deliver cars to the dealer where the dealer terminal is installed. ing. Specifically, the production logistics period that is the longest from the desired delivery date is traced, and a predetermined period [preparation period for starting production logistics planning to start production (this embodiment) In this case, the demand forecast is input at a time point that goes back only three months). The case of the store a (France) in FIG. 3 will be described as an example. As is clear from FIG. 3, the production plant A (France), the production plant B (Turkey), and the production plant D that supply vehicles to the store a (Japan) The production factory with the longest production distribution period is the production factory D. Therefore, the store a goes back the desired delivery date for the production distribution period (for example, 62 days) required for delivery from the production plant D to the store a, and when it goes back three months from that date (request for delivery) The demand forecast is input about 5 months before the date). For example, a French store a inputs a demand forecast for mid-August in mid-March.
It should be noted that the timing for inputting the demand forecast from the store terminal 30 is different for each store. This is because the vehicles are delivered to each dealer from a plurality of different production factories, and the longest production distribution period varies depending on the dealer.
[0017]
The period file 14 stores, for each production site, the period required from the start of production until it is delivered to the store. 7 shows the production plant D (Japan) and the store a (France), the production plant B (Turkey) and the store a (France), the production plant A (France) and the store a described with reference to FIG. The period file for each of (France) is shown.
As is clear from FIG. 7, the period file 14 divides the process from the start of production in each production factory until it is delivered to the store into several processes, and stores the period required for each process. For example, when the product is produced at the production plant D (Japan) and delivered to the store a (France), it will be the body / painting period, assembly period, land transportation period, customs clearance period, sea transportation period, customs clearance period, and land transportation period. Standard passing days are stored. In addition, when it is produced at the production factory A (France) and delivered to the store a (France), since there is no need for a customs clearance period, a marine transportation period, etc., that part is not stored.
[0018]
The production distribution plan file 16 stores from the start of production of vehicles produced at the production factory to the scheduled delivery date to the dealer for each production factory. FIG. 8 shows an example of a production plan file for the production factory D (Japan). As shown in FIG. 8, the production distribution plan file 16 includes a destination, specification information, vehicle specifications, customer information, specification confirmation, and delivery to a dealer for each product (product ID) produced at the production factory. The scheduled time and the actual time are stored.
The destination is information indicating which dealer the production vehicle is for, and is determined when the shared production number calculation unit 20 (to be described later) determines the shared production number (production number by destination) of each production factory. The For example, in the example shown in FIG. 8, vehicles with product IDs 0001 and 0005 are produced for France, vehicles with product IDs 0002 and 0003 are produced for Japan, and vehicles with product ID 0004 are produced for the United States.
The specification information is information indicating whether or not the specification is fixed, and the vehicle specification is information indicating the specification (grade, option, etc.) of the product to be produced. Customer information is information indicating whether or not a customer is assigned to a product to be produced. In this embodiment, the specifications are basically fixed on the day before the production start date (start date). However, since the product to which the customer is assigned is the specification requested by the customer, from the day before the start date. Even before, “determined” is stored as the specification information. For example, the vehicle with the product ID 0001 shown in FIG. 8 is assigned the customer and the specification is confirmed even before the specification confirmation date (the specification information for other vehicles is “not yet”). “Confirmed” is stored in the column.
In addition, the production distribution plan file 16 stores a scheduled passage date for each process from product specification confirmation (production start) to delivery to a store. In other words, once the destination of a product is determined, the production logistics process from the start of production of the product to delivery to the dealer is determined. When the production logistics process is determined, the standard file passing period of each process of the production logistics process is known from the period file 14, and therefore the scheduled passing date of each process is calculated. Stored. The calculation of the scheduled passage period is performed by the production logistics planning means 22 described later.
Further, the production distribution plan file 16 stores the actual passage date corresponding to the expected passage date calculated for each process as described above. That is, when a product passes through each process, a product ID of the product passed through is transmitted from a terminal (not shown) installed in each process to the order-receiving computer 10, and the transmission date is stored as a passing result date. As a result, the progress of the product distribution process is managed.
[0019]
The order-receiving computer 10 further includes a demand prediction file update unit 18, a shared production number calculation unit 20, a production distribution plan planning unit 22, and a file search unit 24.
The demand prediction file updating means 18 stores the information in the demand prediction file 12 when the demand prediction (desired delivery date and the number of deliveries) is input from the store terminal 30. For example, when n1 orders are received from the dealer terminal 30 of the dealer a (France) on the desired delivery date X1 January Y1, the orders are stored in the demand forecast file 12 as shown in FIG.
[0020]
Based on the demand forecast (order) of each dealer stored in the demand prediction file 12, the shared production quantity calculation means 20 determines the production quantity for each dealer at each production factory (production quantity by destination). To do.
Specifically, in consideration of the distribution lead time from production factories to dealers, priorities are assigned to each production factory by dealer, and the demand forecast (order quantity) of each dealer is given priority. Allocate from the highest production factory. For example, when n orders (demand forecast) are received from the store a (France), the production of the n units is preferentially shared with the production factory A (France) where the distribution cost is lowest. If the production capacity of the production factory A (France) is insufficient, the production factory B (Turkey) with the next lowest distribution cost is assigned to the production factory D (Japan). Through these procedures, after allocating the number of production units at each production plant to satisfy the demands of all dealers, each production plant is readjusted so that the load at each production plant is leveled. Maximize factory production efficiency.
An example of the number of production by destination determined as described above is shown in FIG. 9 for production factory D (Japan) and production factory A (France). In the example shown in FIG. 9, production factory D (Japan) has a total production volume of 280 units per day, of which 20 units are for France, 20 units are for Thailand, 40 units are for the United States, and the remaining 200 units are domestic. Produced for (Japan). Production Factory A (France), like Production Factory D, has a total production of 280 units per day, of which 100 units are produced for the United Kingdom, 30 units for the United States, and 150 units for France. . Accordingly, in the example of FIG. 9, the car produced at the Japanese factory is not shipped to the UK, and the car produced at the French factory is not shipped to Thailand or Japan.
As is clear from the above explanation, the number of units produced by each production factory (production by destination) varies from production factory to production factory, and depends on the demand in each country (increase or decrease in demand for automobiles due to the booming economy or recession in each country). Will also vary. Depending on some production factories, vehicles (that is, vehicles for all dealers) may be produced without providing the number of production by destination.
[0021]
When the production distribution plan planning means 22 determines the production quantity by destination of each production factory (that is, the destination of the vehicle to be produced) by the above-mentioned shared production quantity calculation means 20, the production of vehicles produced at the factory is determined. Develop a production logistics plan from the start of delivery to delivery to dealers.
Specifically, since the destination of the vehicle produced at the production factory can be determined when the number of production by destination is determined, the distribution process after the factory shipment of the vehicle can be specified from the contents of the period file 14. Therefore, when the production start date of the vehicle is determined, the specification confirmation date, the scheduled completion date of painting, the scheduled line-off date,. These calculated scheduled dates are stored in the production distribution plan file 16. For example, it is assumed that production of a vehicle for a store a (France) starts at a production factory D (Japan) on February 14. Since the period required for each process of the vehicle is known from the period file 14 (see FIG. 7), the scheduled passage date of each process is calculated using the period stored in the period file 14. That is, the date of painting completion (for example, February 16) is calculated by adding the body / painting period to the production start date (for example, February 14). By adding the period of each process stored in the period file 14 in the following order, the scheduled passage date of each process is calculated, and finally the scheduled arrival date (for example, April 17) at the store a is calculated. calculate. In this embodiment, since the day before the production start date is the specification confirmation date, the specification confirmation date (for example, February 13) is calculated from this. The estimated passage date of each process calculated in this way is stored in the production distribution plan file 16 (see FIG. 8).
[0022]
The file search means 24 searches the production logistics plan file 16 for a corresponding vehicle when a search condition (for example, a store arrival date) is input from a store terminal 30 described later.
[0023]
The store terminal 30 connected to the order-receiving computer 10 configured as described above is configured by, for example, a general-purpose computer. The dealer terminal 30 includes an input device 32 for inputting search conditions and the like, a display device 36 for displaying search results, and data processing means 34 for transmitting and receiving data to and from the order-receiving computer 10.
The input device 32 is a keyboard, a mouse, or the like, and is a device for inputting a search condition or the like when searching for the demand forecast or the production distribution plan file 16 already described. The display device 36 is a device that displays the results searched by the file search means 24 described above. In addition, the data processing unit 34 transmits the input information to the order-receiving computer 10 and receives the data transmitted from the order-receiving computer 10 to display an image on the display device 36.
[0024]
Next, the operation of the production distribution management system configured as described above will be described. First, a procedure when a production distribution plan is drawn up by the order-receiving computer 10 will be described with reference to a flowchart shown in FIG. The production logistics plan by the order-receiving computer 10 is made every predetermined period (for example, every week), and a production logistics plan is made for the vehicle that has received an order after the last production logistics plan.
The order-receiving computer 10 first calculates the total demand (total number of orders) for each store from the data stored in the demand prediction file 12 (step S1). That is, the orders from each store stored in the demand prediction file 12 are totaled for each store. For example, when a plurality of orders are stored in the demand forecast file 12 from the same store, the total number of orders is calculated by counting the number of orders. In addition, since the data totaled in step S1 and incorporated in the production plan is cleared, it is not processed in the production logistics plan planning process in the subsequent cycle.
In step S2, based on the total order quantity calculated for each store by the processing in step S1, the shared production quantity calculation means 20 calculates the production quantity for each destination in each production factory. Through this process, each production factory is provided with a production frame for each destination (see FIG. 9), and the destination of each vehicle produced at each production factory is determined.
In step S3, the destination of the vehicle to be produced at each production factory is determined based on the number of production by destination determined by the processing in step S2, and each period from the start of production to delivery to the dealer is referred to with reference to the period file 14. The scheduled date for passing the process is calculated.
For all vehicles produced in the production factory group, when the scheduled date of passage of each process is calculated and a production logistics plan is drawn up, the production logistics plan file 16 (see FIG. 8) (step S4).
As is clear from what has already been described, although the destination of a vehicle for which a new production logistics plan has been formulated by the above-described processing has been determined, specific specifications have not been determined. Specific specifications are instructed from the store terminal 30 by the specification confirmation date.
[0025]
Next, an example of a procedure for instructing specifications for a vehicle stored in the production distribution plan file 16 using the store terminal 30 will be described with reference to a flowchart shown in FIG.
In step S <b> 10, the store inputs the store arrival date from the input device 32 as a search condition for searching the production distribution plan file 16.
When the store arrival date is input, the input store arrival date (search condition) is transmitted from the store terminal 30 to the order-receiving computer 10 (step S12). Simultaneously with the transmission of the search condition in step S12, the store ID information is also transmitted to the order-receiving computer 10. Thereby, the order-receiving computer 10 recognizes from which store the search request is received.
[0026]
In step S14, the file search means 24 of the order-receiving computer 10 changes the store that is stored in the production distribution plan file 16 to the store on the date of arrival at the input store. Search for vehicles that will arrive.
Specifically, first, the vehicles stored in the production distribution plan file 16 whose destination is the dealer are extracted, and further, the searched vehicles are sent to the dealer. Are extracted when the estimated arrival date is the arrival date of the store. For example, the store arrival date is input as April 17 from the store terminal 30 installed in the store a (France), and the production distribution plan file 16 [production distribution plan of the production factory D (Japan) shown in FIG. Consider the case of searching for [file]. In this case, the vehicle stored in the production distribution plan file 16 and having the store a as the destination and the planned store arrival date on April 17 is the vehicle having the product ID 0001,0005,. Therefore, the file search means 24 extracts these vehicles. Actually, the vehicle destined for the dealer a is also produced at the production factory A (France) and the production factory B (Turkey). Accordingly, when the production distribution plan files 16 of these production factories are also searched, the vehicles produced at these production factories are also extracted.
[0027]
When the search process in step S14 is completed, the search result is output from the order-receiving computer 10 to the store terminal 30 (step S16). When the store terminal 30 receives the search result output from the order-receiving computer 10, the received search result is displayed on the display device 36 (step S18).
For example, when April 17 is input from the above-mentioned store a as the store arrival date, a search result as shown in FIG. In FIG. 12, the vehicles scheduled to be delivered to the store a (France) on April 17 are three from the production plant A (France), two from the production plant B (Turkey), and the production plant D (Japan). It is shown that there are two units. Also, the specification confirmation date (April 10) for vehicles produced at production plant A (France), the specification confirmation date (March 2) for vehicles produced at production plant B (Turkey), and the production plant The specification confirmation date (February 13) of the vehicle produced in D (Japan) is displayed. Therefore, the dealer a knows that the specifications of the three vehicles produced at the production plant D (France) should be finalized by April 11, and the two vehicles produced at the production plant B (Turkey). It is understood that it is sufficient to finalize the specifications by March 2 for the vehicle of No.2 and that the specifications should be confirmed by February 13 for the two vehicles produced at the production plant D (Japan). I understand. For this reason, the store a (France) has only to determine the specifications in order by the above-mentioned specification determination date that varies depending on the production factory. At this time, the display device 36 also displays specification information as to whether or not the specification has been confirmed and customer information as to whether or not a customer is assigned, so whether or not the vehicle can instruct the specification. It is possible to know whether the vehicle can be assigned a customer.
In addition, for vehicles whose specifications have been determined from the specification information and customer information but whose customers have not yet been determined (that is, vehicles for which no customer has been assigned by the specification determination date), the dealers will arrive until the dealer arrives. Customers can be assigned by the terminal 30. Furthermore, as shown in FIG. 12, since the scheduled passage date and the actual passage date are shown together, it is possible to know to what stage the product has been completed, etc. Can respond to.
In addition, when a corresponding vehicle is not searched, the display device 36 displays that the corresponding vehicle has not been searched.
[0028]
Since the search result is displayed on the display device 36 in step S18, the dealer a (sales staff of the dealer, etc.) assigns a customer to the vehicle displayed on the display screen using the input device 32, and the specification. Is instructed (step S20).
When customer assignment or confirmed specifications are instructed in step S20, the information is transmitted from the dealer terminal 30 to the order receiving computer 10 (step S22), and the order receiving computer 10 generates a production distribution plan file based on the information. 16 is updated (step S24).
[0029]
The procedure of customer assignment and specification input using the store terminal 30 described with reference to the flowchart of FIG. 11 is merely an example, and the store performs customer assignment and specification input by various methods. Can do. For example, the dealer arrival date and the specification confirmation date (which can also be entered as a period) are input from the dealer terminal, and only the vehicles whose specifications are not confirmed are searched, and the customer assignment / specification input is performed. good. At the same time, the number of productions whose specifications are confirmed among the vehicles that arrive at the dealer on the date of arrival at the dealer's arrival date and the number of productions to which the customer is assigned are displayed by specification. It is preferable. Thus, when the number of specifications determined and the number of customers allocated are displayed for each specification, since the vehicle with the specification that is surplus at that time is known, the dealer can instruct the specification by referring to this information .
In addition, for a vehicle to which a customer is assigned and the specification is fixed, a specification change request is received from the customer, and the specification can be changed if the request is before the specification determination date.
[0030]
As is apparent from the above description, the production logistics management system of the present embodiment formulates a production logistics plan in which only the product destination is determined based on the demand forecast presented by the dealer. Then, the dealer can instruct the product specifications by the specification confirmation date determined for each production factory. In other words, it is not necessary to determine vehicle specifications at the time of demand forecast presented by the dealer, and the specifications of the product to be produced may be performed by the specification confirmation date. Therefore, even if the demand forecast is made at a time well before the actual delivery to the dealer, the specifications can be made by the specification confirmation date close to the delivery date to the dealer. It becomes easy to match the actual customer's request.
Further, as is clear from the above description, customer assignment and specification instructions by a dealer are limited to vehicles destined for the dealer. For this reason, the number of shares of the production distribution plan designed to maximize the production distribution efficiency is not changed by the subsequent customer allocation or specification change.
Furthermore, when the production logistics management system of this embodiment is used, the scheduled date and actual date of each process from product production to delivery to the dealer are displayed, so the actual date is delayed from the scheduled date of passage. For those that are, it is possible to contribute to adherence to the delivery date by raising the priority in the subsequent processes.
[0031]
The preferred embodiment of the present invention has been described in detail above, but this is only an example, and the present invention can be implemented in various modifications and improvements based on the knowledge of those skilled in the art.
For example, in the above-described embodiment, each production factory / sales store is an example in each country of the world. However, the present invention is not limited to such a case, and when there are a plurality of production factories / sales stores in various parts of the country. Can also be applied. That is, the system of the present invention can be applied even when there are production factories that produce the same type of product in various parts of Japan, and there are a plurality of dealers that sell products produced in these production factories. . Even in this case, the specification process date of the product will be presented in consideration of the logistics process from each production factory to each dealer, so the product specifications will be instructed based on the forecast in the near future for each production factory. can do.
Further, in the above-described embodiment, the shared production quantity and production distribution plan of each production factory are made by the order-receiving computer, but the present invention is not limited to such an example. For example, determination of the number of shared productions at each production factory is performed by one computer. Then, the management computer installed in each production factory based on the shared production number determined by this computer creates a production logistics plan for the products produced in the production factory (creates a production logistics plan file). In the case of such a configuration, the dealer terminal searches for a vehicle whose destination is the dealer by individually accessing the production distribution plan file of each production factory.
[0032]
It should be noted that the technical elements described in this specification or the drawings exhibit technical usefulness alone or in various combinations, and are not limited to the combinations described in the claims at the time of filing. In addition, the technology exemplified in this specification or the drawings achieves a plurality of objects at the same time, and has technical utility by achieving one of the objects.
[Brief description of the drawings]
FIG. 1 is a diagram showing an outline of a computer system of the present invention.
FIG. 2 is a diagram showing a relationship between a production factory that produces a product (automobile) to be managed by the production distribution management system of the present embodiment and a dealer that sells the product produced at the production factory.
FIG. 3 is a diagram showing a schematic flow from specification confirmation in a production factory to delivery of a product to a store.
FIG. 4 is a diagram showing a schematic configuration of a product distribution management system of the present embodiment.
FIG. 5 is a functional block diagram of the product distribution management system of the present embodiment.
FIG. 6 is a diagram showing the contents of a demand forecast file.
FIG. 7 is a diagram showing the contents of a period file.
FIG. 8 is a diagram showing the contents of a production distribution plan file.
FIG. 9 is a diagram illustrating an example of the number of production by destination set in a production factory.
FIG. 10 is a flowchart showing a procedure of production logistics planning processing by an order-receiving computer.
FIG. 11 is a flowchart showing a procedure for assigning a customer using a store terminal.
FIG. 12 is a diagram showing an example of a search result displayed on a store terminal.
[Explanation of symbols]
10. Order-receiving computer
12. Demand forecast file
14. Period file
16. Production logistics plan file
18. Demand forecast file update means
20 ·· Shared production number calculation means
22. ・ Production logistics planning means
24 .. File search means
30. Dealer terminal
32. Input device
36..Display device

Claims (3)

同一種類の製品を複数の生産拠点で分担して生産する生産系のために、各生産拠点で生産する仕様別の生産台数を決定するためのコンピュータシステムであり、
生産開始してから発注者に納入されるまでに要する期間を生産拠点毎に記憶している期間ファイルと、
期間ファイルに記憶されている最長期間以上先の時点におけるその種類の製品の需要予測台数を入力する需要予測ファイルと、
需要予測ファイルの記憶内容に基づいて、分担生産する台数を生産拠点毎に決定する分担生産台数計算手段と、
計算された生産拠点別の分担生産台数と期間ファイルを利用して、生産拠点別の生産物流計画を立案する手段と、
立案された生産拠点別の生産物流計画から決まる生産拠点毎の仕様確定最終日と分担生産台数を生産拠点毎に表示する表示装置と、
表示された生産拠点毎の仕様確定最終日と分担生産台数を参照して、表示された仕様確定最終日までに表示された分担生産台数の仕様別の内訳台数を入力する手段と、
を備える生産拠点と仕様別の生産台数を決定するためのコンピュータシステム。
It is a computer system for determining the number of production by specification to be produced at each production base for production systems that share the same type of product at multiple production bases.
A period file that stores the time required from the start of production to delivery to the orderer for each production site,
A demand forecast file that inputs the number of demand forecasts for that type of product at a point beyond the longest period stored in the period file;
Based on the stored contents of the demand prediction file, a shared production number calculation means for determining the number of shared production for each production base,
Using the calculated production volume and period file for each production site, creating a production logistics plan for each production site,
A display device that displays the final date of specification specification for each production site determined from the planned production logistics plan for each production site and the number of shared production for each production site;
A means for referring to the final specification confirmation date and the number of production units for each production base displayed, and for inputting the breakdown number by specification of the shared production units displayed up to the displayed final specification date;
A computer system for determining production bases and production quantities by specification.
上記の表示装置に、仕様別に、仕様確定台数と割当確定台数が対照して表示されることを特徴とする請求項1のコンピュータシステム。2. The computer system according to claim 1, wherein the number of specifications determined and the number of determined allocations are displayed on the display device for each specification. 上記の表示装置に、製品別に、立案された生産物流計画と、実際の進捗状況が対照して表示されることを特徴とする請求項1のコンピュータシステム。2. The computer system according to claim 1, wherein the display device displays a product distribution plan designed for each product and an actual progress status.
JP2001256192A 2001-08-27 2001-08-27 System for determining the number of production by production base and specification Expired - Fee Related JP4686937B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001256192A JP4686937B2 (en) 2001-08-27 2001-08-27 System for determining the number of production by production base and specification

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001256192A JP4686937B2 (en) 2001-08-27 2001-08-27 System for determining the number of production by production base and specification

Publications (2)

Publication Number Publication Date
JP2003067030A JP2003067030A (en) 2003-03-07
JP4686937B2 true JP4686937B2 (en) 2011-05-25

Family

ID=19084039

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001256192A Expired - Fee Related JP4686937B2 (en) 2001-08-27 2001-08-27 System for determining the number of production by production base and specification

Country Status (1)

Country Link
JP (1) JP4686937B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4990939B2 (en) * 2009-07-01 2012-08-01 株式会社神戸製鋼所 Production base assignment program, production base assignment apparatus, and production base assignment method
JP6070651B2 (en) 2014-07-22 2017-02-01 トヨタ自動車株式会社 Product production planning method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07175857A (en) * 1993-10-12 1995-07-14 Nec Corp Production planning system
JPH08315018A (en) * 1995-05-16 1996-11-29 Hitachi Ltd Method for calculating parts preparation date by using retrospective date
JP2000288874A (en) * 1999-03-31 2000-10-17 Toyota Motor Corp Method of calculating production planning quantity of commodities
JP2000288875A (en) * 1999-04-01 2000-10-17 Toyota Motor Corp Production and sales programming system
JP2001209711A (en) * 2000-01-28 2001-08-03 Amada Co Ltd Method and system for automatically deciding merchandise manufacture destination and storage medium with program of the same method stored

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07175857A (en) * 1993-10-12 1995-07-14 Nec Corp Production planning system
JPH08315018A (en) * 1995-05-16 1996-11-29 Hitachi Ltd Method for calculating parts preparation date by using retrospective date
JP2000288874A (en) * 1999-03-31 2000-10-17 Toyota Motor Corp Method of calculating production planning quantity of commodities
JP2000288875A (en) * 1999-04-01 2000-10-17 Toyota Motor Corp Production and sales programming system
JP2001209711A (en) * 2000-01-28 2001-08-03 Amada Co Ltd Method and system for automatically deciding merchandise manufacture destination and storage medium with program of the same method stored

Also Published As

Publication number Publication date
JP2003067030A (en) 2003-03-07

Similar Documents

Publication Publication Date Title
US8219503B2 (en) Estimated time of arrival (ETA) systems and methods
Cornillier et al. A heuristic for the multi-period petrol station replenishment problem
US6885902B2 (en) System and method for replenishment by purchase with attribute based planning
US6898472B2 (en) System and method for order group planning with attribute based planning
CN109345161A (en) A kind of delivery assignment method towards monetary value flow
US7991634B2 (en) Vehicle transport load optimization
CN107578202B (en) Commodity dispatching and delivering method based on existing takeout service
US20200364630A1 (en) System and method for managing transportation vessels
KR20100045499A (en) Transportation management system
US20030050818A1 (en) Production managing system
Amer et al. Analysis of quantitative models of horizontal collaboration in supply chain network design: Towards “green collaborative” strategies
US20140214715A1 (en) Scheduling system and method for distribution of perishable loads of pre-mixed concrete to multiple sites
US20130060712A1 (en) Bulk Distribution Method
JP4686937B2 (en) System for determining the number of production by production base and specification
JP2002203158A (en) Work planning method and work planning device
US20160180268A1 (en) System for setting a delivery count rank
Calvete et al. Vehicle routing problems with soft time windows: An optimization based approach
JP7170392B2 (en) Crew Assignment Device, Crew Assignment Method and Crew Assignment Program
JPH1087036A (en) Stock allocating method, and deciding method of distribution mode and stocking position, in physical distribution system
Singer et al. Fleet configuration subject to stochastic demand: An application in the distribution of liquefied petroleum gas
JP2005060108A (en) Physical distribution management system
JP4303449B2 (en) production management system
Kusuma et al. Optimizing Distribution Route of Packed Drinking Water with The Clarke and Wright Savings and Nearest Neighbor Methods (Case Study of PT. GSI)
US11157881B2 (en) Distributed system for test drive conflict rescheduling
JP2019117436A (en) Operation difficulty acquisition apparatus, operation difficulty acquisition method and operation difficulty acquisition program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080506

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101109

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110118

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110131

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140225

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees