JP4669615B2 - Unit building - Google Patents

Unit building Download PDF

Info

Publication number
JP4669615B2
JP4669615B2 JP2001023609A JP2001023609A JP4669615B2 JP 4669615 B2 JP4669615 B2 JP 4669615B2 JP 2001023609 A JP2001023609 A JP 2001023609A JP 2001023609 A JP2001023609 A JP 2001023609A JP 4669615 B2 JP4669615 B2 JP 4669615B2
Authority
JP
Japan
Prior art keywords
building
unit
parallel
ceiling
sub
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001023609A
Other languages
Japanese (ja)
Other versions
JP2002227306A (en
Inventor
健浩 竹中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP2001023609A priority Critical patent/JP4669615B2/en
Publication of JP2002227306A publication Critical patent/JP2002227306A/en
Application granted granted Critical
Publication of JP4669615B2 publication Critical patent/JP4669615B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明はユニット建物に関する。
【0002】
【従来の技術】
ユニット建物として、特開昭55-126638号公報に記載の如く、2個の互いに並列配置されてそれらの辺を同一直線上に揃えた並列置き建物ユニットと、2個の並列置き建物ユニットの同一直線上に揃う2つの辺に沿うように配置された渡り置き建物ユニットとからなるユニット群を有するものがある。
【0003】
【発明が解決しようとする課題】
しかしながら、従来技術では、前記ユニット群の天井補強構造として、2個の並列置き建物ユニットの各天井面の領域と、渡り置き建物ユニットの天井面の領域の全ての領域に水平ブレースを設け、水平力をそれら3個の建物ユニットで均一に負担して水平力に対する変形を防止可能としている。このため、ユニット群の天井部に吹き抜け領域を設けることができず、階段室や吹き抜け室を設けることができない。
【0004】
本発明の課題は、2個の並列置き建物ユニットと渡り置き建物ユニットとからなるユニット群の水平力に対する変形を防止しながら、ユニット群の天井部に吹き抜け領域を設けることにある。
【0005】
【課題を解決するための手段】
請求項1の発明は、2個の互いに並列配置されてそれらの辺を同一直線上に揃えた並列置き建物ユニットと、2個の並列置き建物ユニットの同一直線上に揃う2つの辺に沿うように配置された渡り置き建物ユニットとからなるユニット群を有し、渡り置き建物ユニットの天井又は床部で、両並列置き建物ユニットの境界線の延長線上に位置する部分に補強梁を設け、2個の並列置き建物ユニットの各天井又は床面の領域と、渡り置き建物ユニットの天井又は床面を補強梁で区画した領域とからなる複数の領域のうち、平面視で対角に位置する2つの領域をブレース補強し、残る領域のうち少なくとも1つの領域をブレース補強しない吹き抜け可能な領域とする、ユニット群の補強構造を備えてなるユニット建物において、前記渡り置き建物ユニットが両並列置き建物ユニットの同一直線上に揃う2つの辺の合計長より長尺をなすとき、渡り置き建物ユニットの天井又は床部で、並列置き建物ユニットの外郭線の延長線上に位置する部分にも補強梁を設けるようにしたものである。
【0009】
請求項の発明は、請求項の発明において更に、前記ユニット群を構成する前記2個の並列置き建物ユニットの一方の建物ユニットをサブ渡り置き建物ユニットとし、このサブ渡り置き建物ユニットの辺のうち、前記渡り置き建物ユニットが配置されていない辺に沿って、他の2個のサブ並列置き建物ユニットを並べて配置し、これらのサブ渡り置き建物ユニットと両サブ並列置き建物ユニットによりサブユニット群を構成するとき、サブユニット群についても前記ユニット群におけると同じ補強構造を備えてなるようにしたものである。
【0010】
【作用】
請求項1の発明によれば下記(a)(e)の作用がある。
(a)両並列置き建物ユニットの境界線に沿う水平力を、渡り置き建物ユニットに設けた補強梁の存在により、両並列置き建物ユニットと渡り置き建物ユニットの3個の建物ユニットで負担できる。
【0011】
(b)2個の並列置き建物ユニットの各天井又は床面の領域と、渡り置き建物ユニットの補強梁で区画した領域とからなる複数の領域のうち、平面視で対角に位置する領域をブレース補強した。従って、ブレース補強されない領域の天井又は床面でも、直交するX方向とY方向にて相交差するそれらの天井又は床梁をブレース補強された対角に位置する補強領域に添設されて間接的に補強される。従って、ユニット群に作用するX方向とY方向の水平力を、3個の並列置き建物ユニットと渡り置き建物ユニットの全てによって均一に負担できる。
【0012】
(c)上述(a)(b)により、ユニット群の水平力に対する変形を防止できる。
【0013】
(d)ユニット群の天井又は床部のうち、少なくとも1つの領域をブレース補強しない吹き抜け可能領域とするから、この吹き抜け可能領域に階段室や吹き抜け室を設けることができる。階上部分であれば天窓を設けることもできる。
【0014】
(e)渡り置き建物ユニットが両並列置き建物ユニットの同一直線上に揃う2つの辺の合計長より長尺をなすとき、並列置き建物ユニットの外郭線に沿う水平力を、渡り置き建物ユニットに設けた補強梁の存在により、両並列置き建物ユニットと渡り置き建物ユニットの3個の建物ユニットで負担できる。
【0017】
請求項の発明によれば下記(f)の作用がある。
(f)2個の並列置き建物ユニットと渡り置き建物ユニットからなるユニット群と、2個のサブ並列置き建物ユニットとサブ渡り置き建物ユニットからなるサブユニット群が、ユニット群の1個の並列置き建物ユニットとサブユニット群のサブ渡り置き建物ユニットを同一建物ユニットとする状態で複合化しているときにも、それらユニット群とサブユニット群の両方で、水平力に対する変形を防止しながら、天井部に吹き抜け領域を形成できる。
【0018】
【発明の実施の形態】
図1は第1参考形態のユニット建物のユニット群を示し、(A)は斜視図、(B)は平面図、図2は第1参考形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図、(C)は第3例を示す平面図、図3は本発明実施形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図、図4は第2参考形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図、図5は第3参考形態の天井補給構造を示す平面図、図6は第4参考形態のユニット建物のユニット群とサブユニット群を示す平面図、図7は第4参考形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図である。
【0019】
(第1参考形態)(図1、図2)
ユニット建物1は、図1に示す如く、複数の建物ユニット10を水平方向と鉛直方向に隣接配置して構築され、その一部に図1に示す如くのユニット群20を有する。
【0020】
ユニット群20は、2個の互いに並列配置されてそれらの短辺21A、22Aを同一直線上に設けた並列置き建物ユニット21、22と、2個の並列置き建物ユニット21、22の同一直線上に揃う2つの短辺21A、22Aに沿うように配置された渡り置き建物ユニット23とからなる。尚、建物ユニット21〜23は、各4個の床梁11、柱12、天井梁13を箱型に接合した骨組構造体である。
【0021】
ユニット群20は、下記(1)、(2)の天井補強構造を備える(図2(A))。
(1)渡り置き建物ユニット23の天井部で、両並列置き建物ユニット21、22の境界線の天井梁13、13の延長線上に位置する部分に補給梁23Aを設ける。補強梁23Aは渡り置き建物ユニット23の相対する天井梁13、13の中間部に掛け渡される。
【0022】
(2)2個の並列置き建物ユニット21、22の各天井面の領域A、Bと、渡り置き建物ユニット23の天井面を補強梁23Aで区画した2つの領域C、Dとからなる全4つの領域のうち、平面視で対角に位置する領域A、Cともう1つの領域Dを水平ブレース14でブレース補強し、残る1つの領域Bをブレース補強しない吹き抜け可能領域15とした。
【0023】
参考形態によれば、以下の作用がある。
(a)両並列置き建物ユニット21、22の境界線の天井梁13に沿う水平力を、渡り置き建物ユニット23に設けた補強梁23Aの存在により、両並列置き建物ユニット21、22と渡り置き建物ユニット23の3個の建物ユニットで負担できる。
【0024】
(b)2個の並列置き建物ユニット21、22の各天井面の領域A、Bと、渡り置き建物ユニット23の補強梁23Aで区画した領域C、Dとからなる複数の4つの領域のうち、平面視で対角に位置する領域A、Cをブレース補強した。従って、ブレース補強されない領域Bの天井面でも、直交するX方向とY方向にて相交差するそれらの天井梁13をブレース補強された対角に位置する補強領域A、Cに添設されて間接的に補強される。従って、ユニット群20に作用するX方向とY方向の水平力を、3個の並列置き建物ユニット21、22と渡り置き建物ユニット23の全てによって均一に負担できる。
【0025】
(c)上述(a)(b)により、ユニット群20の水平力に対する変形を防止できる。
【0026】
(d)ユニット群20の天井部のうち、少なくとも1つの領域Bをブレース補強しない吹き抜け可能領域15とするから、この吹き抜け可能領域15に階段室や吹き抜け室を設けることができる。階上部分であれば天窓を設けることもできる。
【0027】
図2(B)はユニット群20の天井補強構造の変形例であり、並列置き建物ユニット21の領域Aを吹き抜け可能領域15とし、並列置き建物ユニット22の領域Bと渡り置き建物ユニット23の領域C、Dを水平ブレース14でブレース補強したものである。
【0028】
図2(C)はユニット群20の天井補強構造の変形例であり、並列置き建物ユニット21の領域Aと渡り置き建物ユニット23の領域Cを水平ブレース14でブレース補強し、並列置き建物ユニット22の領域Bと渡り置き建物ユニット23の領域Dを吹き抜け可能領域15としたものである。即ち、ユニット建物1の階上部分に設けられるユニット群20では、渡り置き建物ユニット23の一方の領域C又はD(図2の*部分)を吹き抜け可能領域15とすることができる。
【0029】
本発明実施形態)(図3)
図3(A)は、2個の並列置き建物ユニット31、32と渡り置き建物ユニット33でユニット群30を構成するものであるが、渡り置き建物ユニット33が両並列置き建物ユニット31、32の同一直線上に揃う2つの短辺31A、32Aの合計長より長尺をなすものである。
【0030】
ユニット群30は、下記(1)、(2)の天井補強構造を備える。
(1)渡り置き建物ユニット33の天井部で、両並列置き建物ユニット31、32の境界線の天井梁13、13の延長線上に位置する部分に補強梁33Aを設けるとともに、狭巾並列置き建物ユニット31の外郭線の天井梁13の延長線上に位置する部分にも補強梁33Bを設ける。補強梁33A、33Bは渡り置き建物ユニット33の相対する天井梁13、13の中間部に掛け渡される。
【0031】
(2)2個の並列置き建物ユニット31、32の各天井面の領域A、Bと、渡り置き建物ユニット33の天井面を補強梁33A、33Bで区画した3つの領域C、D、Eとからなる全5つの領域のうち、平面視で対角に位置する領域A、Cともう2つの領域D、Eを水平ブレース14でブレース補強し、残る1つの領域Bをブレース補強しない吹き抜け可能領域15とした。
【0032】
発明実施形態によれば、渡り置き建物ユニット33が両並列置き建物ユニット31、32の同一直線上に揃う2つの短辺31A、32Aの合計長より長尺をなすとき、狭巾並列置き建物ユニット31の外郭線の天井梁13に沿う水平力を、渡り置き建物ユニット33に設けた補強梁33Bの存在により、両並列置き建物ユニット31、32と渡り置き建物ユニット33の3個の建物ユニットで負担できる。
【0033】
図3(B)はユニット群30の天井補強構造の変形例であり、並列置き建物ユニット31の領域Aを吹き抜け可能領域15とし、並列置き建物ユニット32の領域Bと渡り置き建物ユニット33の領域C、D、Eを水平ブレース14でブレース補強したものである。
【0034】
尚、ユニット建物1の階上部分に設けられるユニット群30では、渡り置き建物ユニット33の領域C又はD(図3の*部分)を吹き抜け可能領域15とすることができる。
【0035】
(第2参考形態)(図4)
図4(A)は、2個の並列置き建物ユニット41、42と渡り置き建物ユニット43でユニット群40を構成するものであるが、両並列置き建物ユニット41、42がそれらの境界線に沿う長辺41A、42Aの長さを互いに異にするものである。
【0036】
ユニット群40は、下記(1)〜(3)の天井補強構造を備える。
(1)渡り置き建物ユニット43の天井部で、両並列置き建物ユニット41、42の境界線の天井梁13、13の延長線上に位置する部分に補強梁43Aを設ける。
【0037】
(2)長尺の並列置き建物ユニット42の天井部で、短尺の並列置き建物ユニット41の外郭線の天井梁13の延長線に位置する部分に補強梁42Bを設ける。
【0038】
(3)2個の並列置き建物ユニット41、42の各天井面の領域A、Bと、渡り置き建物ユニット43の天井面を補強梁43Aで区画した2つの領域C、Dとからなる全4つの領域のうち、平面視で対角に位置する領域A、Cともう1つの領域Dを水平ブレース14でブレース補強し、残る1つの領域Bをブレース補強しない吹き抜け可能領域15とした。
【0039】
参考形態によれば、両並列置き建物ユニット41、42がそれらの境界線に沿う長辺41A、42Aの長さを互いに異にするとき、短尺の並列置き建物ユニット41の外郭線の天井梁13に沿う水平力を、長尺の並列置き建物ユニット42に設けた補強梁42Bの存在により、両並列置き建物ユニット41、42と渡り置き建物ユニット43の3個の建物ユニットで負担できる。
【0040】
図4(B)はユニット群40の天井補強構造の変形例であり、並列置き建物ユニット41の領域Aを吹き抜け可能領域15とし、並列置き建物ユニット42の領域Bと渡り置き建物ユニット43の領域C、Dを水平ブレース14でブレース補強したものである。
【0041】
尚、ユニット建物1の階上部分に設けられるユニット群40では、渡り置き建物ユニット43の領域C又はD(図4の*部分)を吹き抜け可能領域15とすることができる。
【0042】
(第3参考形態)(図5)
図5は、2個の並列置き建物ユニット51、52と渡り置き建物ユニット53でユニット群50を構成するものであるが、渡り置き建物ユニット53が両並列置き建物ユニット51、52の同一直線上に沿う2つの長辺51A、52Aの合計長より短尺をなすものである。
【0043】
ユニット群50は、下記(1)〜(3)の天井補強構造を備える。
(1)渡り置き建物ユニット53の天井部で、両並列置き建物ユニット51、52の境界線の天井梁13、13の延長線上に位置する部分に補強梁53Aを設ける。
【0044】
(2)並列置き建物ユニット51の天井部で、渡り置き建物ユニット53の外郭線の天井梁13の鉛直線上に位置する部分に補強梁51Bを設ける。尚、並列置き建物ユニット51では、相対する天井梁13、13に掛け渡した継ぎ梁51Cに上述の補強梁51BをT字状に突き当て支持する。
【0045】
(3)2個の並列置き建物ユニット51、52の各天井面の領域A、Bと、渡り置き建物ユニット53の天井面を補強梁53Aで区画した2つの領域C、Dとからなる全4つの領域のうち、平面視で対角に位置する領域A、Cともう1つの領域Dを水平ブレース14でブレース補強し、残る1つの領域Bをブレース補強しない吹き抜け可能領域15とした。
【0046】
参考形態によれば、渡り置き建物ユニット53が両並列置き建物ユニット51、52の同一直線上に揃う2つの長辺51A、52Aの合計長より短尺をなすとき、渡り置き建物ユニット53の外郭線の天井梁13に沿う水平力を、並列置き建物ユニット51に設けた補強梁51Bの存在により、両並列置き建物ユニット51、52と渡り置き建物ユニット53の3個の建物ユニットで負担できる。
【0047】
尚、ユニット建物1の階上部分に設けられるユニット群50では、渡り置き建物ユニット53の領域D(図5の*部分)を吹き抜け可能領域15とすることができる。
【0048】
(第4参考形態)(図6、図7)
図6は、図1、図2のユニット群20にサブユニット群60を複合化したものである。即ち、ユニット群20を構成する2個の並列置き建物ユニット21、22の一方の並列置き建物ユニット21をサブ渡り置き建物ユニット63とし、このサブ渡り置き建物ユニット63の辺のうち、渡り置き建物ユニット23が配置されていない長辺63Bに沿って、他の2個のサブ並列置き建物ユニット61、62を並べて配置し、これらの両サブ並列置き建物ユニット61、62とサブ渡り置き建物ユニット63によりサブユニット群60を構成したものである。
【0049】
サブユニット群60についても、ユニット群20におけると同様の天井補強構造を備える。即ち、ユニット群20及びサブユニット群60の天井補強構造は以下の通りになる。
【0050】
(1)ユニット群20を構成する渡り置き建物ユニット23の天井部で、両並列置き建物ユニット21、22の境界線の天井梁13、13の延長線上に位置する部分に補強梁23Aを設ける。同時に、サブユニット群60を構成するサブ渡り置き建物ユニット63(並列置き建物ユニット21)の天井部で、両並列置き建物ユニット61、62の境界線の天井梁13、13の延長線上に位置する部分に補強梁63Aを設ける。
【0051】
(2)ユニット群20において、並列置き建物ユニット21(サブ渡り置き建物ユニット63)の天井面を補強梁63Aで区画した2つの領域A1、A2と、並列置き建物ユニット22の天井面の領域Bと、渡り置き建物ユニット23の天井面を補強梁23Aで区画した2つの領域C、Dとからなる全5つの領域のうち、平面視で対角に位置する領域A1、A2、Cともう1つの領域Dを水平ブレース14でブレース補強し、残る1つの領域Bをブレース補強しない吹き抜け可能領域15とした。
【0052】
(3)サブユニット群60において、2個のサブ並列置き建物ユニット61、62の各天井面の領域E、Fと、サブ渡り置き建物ユニット63の天井面を補強梁63Aで区画した2つの領域A1、A2とからなる全4つの領域のうち、平面視で対角に位置する領域E、A1ともう1つの領域A2を水平ブレース14でブレース補強し、残る1つの領域Fをブレース補強しない吹き抜け可能領域15とした。
【0053】
参考形態によれば、2個の並列置き建物ユニット21、22と渡り置き建物ユニット23からなるユニット群20と、2個のサブ並列置き建物ユニット61、62とサブ渡り置き建物ユニット63からなるサブユニット群60が、ユニット群20の1個の並列置き建物ユニット21とサブユニット群60のサブ渡り置き建物ユニット63を同一建物ユニットとして複合化しているときにも、それらユニット群20とサブユニット群60の両方で、水平力に対する変形を防止しながら、天井部に吹き抜け領域を形成できる。
【0054】
図7(B)はサブユニット群60の天井補強構造の変形例であり、並列置き建物ユニット61の領域Eを吹き抜け可能領域15とし、並列置き建物ユニット62の領域Fと渡り置き建物ユニット63の領域A1、A2を水平ブレース14でブレース補強したものである。
【0055】
以上、本発明の実施の形態を図面により詳述したが、本発明の具体的な構成はこの実施の形態に限られるものではなく、本発明の要旨を逸脱しない範囲の設計の変更等があっても本発明に含まれる。例えば、渡り置き建物ユニットの床部で、両並列置き建物ユニットの境界線の延長線上に位置する部分に補強梁を設け、2個の並列置き建物ユニットの各床面の領域と、渡り置き建物ユニットの床面を補強梁で区画した領域とからなる複数の領域のうち、平面視で対角に位置する2つの領域をブレース補強し、残る領域のうち少なくとも1つの領域をブレース補強しない吹き抜け可能な領域とする、ユニット群の床補強構造を備えてなるものであっても良い。
【0056】
【発明の効果】
以上のように本発明によれば、2個の並列置き建物ユニットと渡り置き建物ユニットとからなるユニット群の水平力に対する変形を防止しながら、ユニット群の天井部に吹き抜け領域を設けることができる。
【図面の簡単な説明】
【図1】 図1は第1参考形態のユニット建物のユニット群を示し、(A)は斜視図、(B)は平面図である。
【図2】 図2は第1参考形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図、(C)は第3例を示す平面図である。
【図3】 図3は本発明実施形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図である。
【図4】 図4は第2参考形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面である。
【図5】 図5は第3参考施形態の天井補給構造を示す平面図である。
【図6】 図6は第4参考形態のユニット建物のユニット群とサブユニット群を示す平面図である。
【図7】 図7は第4参考形態の天井補強構造を示し、(A)は第1例を示す平面図、(B)は第2例を示す平面図である。
【符号の説明】
1 ユニット建物
14 水平ブレース
15 吹き抜け可能領域
30 ユニット群
31、32 並列置き建物ユニット
33 渡り置き建物ユニット
33A、33B 補強梁
60 サブユニット群
61、62 サブ並列置き建物ユニット
63 サブ渡り置き建物ユニット
63A 補強梁
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a unit building.
[0002]
[Prior art]
As a unit building, as described in JP-A-55-126638, two parallel building units arranged in parallel with each other aligned on the same straight line and two parallel building units are the same. There is a unit having a unit group composed of transition building units arranged along two sides aligned on a straight line.
[0003]
[Problems to be solved by the invention]
However, in the prior art, as the ceiling reinforcing structure of the unit group, horizontal braces are provided in all areas of the ceiling surface area of the two parallel building units and the ceiling surface area of the transit building unit. The force is evenly shared by these three building units to prevent deformation due to horizontal force. For this reason, a blow-by area cannot be provided in the ceiling portion of the unit group, and a staircase or a blow-off room cannot be provided.
[0004]
An object of the present invention is to provide a blow-by area in a ceiling portion of a unit group while preventing deformation of the unit group composed of two parallel building units and a crossing building unit against horizontal force.
[0005]
[Means for Solving the Problems]
According to the first aspect of the present invention, two parallel building units that are arranged in parallel with each other and whose sides are aligned on the same straight line and two sides that are aligned on the same straight line of the two parallel placement building units are aligned. placed placed over have a unit group composed of the building unit, in the ceiling or floor of the building units placed over the reinforcing beam disposed in a portion located on the extension of the border line of the two parallel placed building units, 2 2 located diagonally in plan view out of a plurality of regions composed of regions of each ceiling or floor surface of the parallel building units and a region in which the ceiling or floor surface of the transitional building unit is partitioned by reinforcing beams one area was brace reinforcement, at least one region of the blow-possible region not braces reinforce unit building comprising comprising a reinforcing structure of the unit group of the remaining region, the crossover placed building Yoo When the grid is longer than the total length of two sides that are aligned on the same straight line of the two parallel building units, it is located on the ceiling or floor of the cross building unit on the extension of the outline of the parallel building unit Reinforcing beams are also provided on the parts to be used .
[0009]
According to a second aspect of the present invention, in the first aspect of the present invention, one of the two parallel-placed building units constituting the unit group is a sub-crossover building unit, and the side of the sub-crossover building unit The other two sub-parallel building units are arranged side by side along the side where the transition building unit is not arranged, and the sub-unit is constituted by these sub-transition building units and both sub-parallel building units. When configuring a group, the subunit group is also provided with the same reinforcing structure as in the unit group.
[0010]
[Action]
According to the invention of claim 1, the following actions (a) to (e) are obtained.
(a) The horizontal force along the boundary line between the two parallel building units can be borne by the three building units, ie, the two parallel building units and the cross building unit, due to the presence of the reinforcing beam provided in the cross building unit.
[0011]
(b) Of the plurality of areas consisting of the areas of the ceilings or floors of the two parallel building units and the areas partitioned by the reinforcing beams of the transit building units, the areas located diagonally in plan view Reinforced braces. Therefore, even in the ceiling or floor surface of the region where brace reinforcement is not performed, those ceiling or floor beams that intersect each other in the X direction and the Y direction orthogonal to each other are indirectly attached to the reinforcement region located at the diagonally brace reinforcement. To be reinforced. Therefore, the horizontal force in the X direction and the Y direction acting on the unit group can be uniformly borne by all the three parallel building units and the cross building unit.
[0012]
(c) By the above (a) and (b) , the unit group can be prevented from being deformed by the horizontal force.
[0013]
(d) Since at least one area of the ceiling or floor of the unit group is a blowable area without brace reinforcement, a staircase or a blowout room can be provided in this blowable area. A skylight can be provided in the upper part.
[0014]
(e) When the transition building unit is longer than the total length of two sides aligned on the same straight line of both parallel building units, the horizontal force along the outline of the parallel building unit is applied to the transition building unit. Due to the presence of the reinforcing beams provided, it can be borne by three building units, ie, a parallel building unit and a cross building unit.
[0017]
The invention according to claim 2 has the following effect (f) .
(f) A unit group consisting of two parallel building units and a cross building unit, and a sub unit group consisting of two sub parallel building units and a sub cross building unit constitute one parallel unit. Even when the building unit and the sub-spreading building unit of the sub-unit group are combined in the same building unit, both the unit group and the sub-unit group prevent the deformation due to horizontal force, A blow-by region can be formed.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 shows a unit group of a unit building of a first reference form, (A) is a perspective view, (B) is a plan view, FIG. 2 shows a ceiling reinforcing structure of the first reference form, and (A) is a first view. The top view which shows an example, (B) is a top view which shows the 2nd example, (C) is the top view which shows the 3rd example, FIG. 3 shows the ceiling reinforcement structure of this invention embodiment, (A) is the 1st 4B is a plan view showing a second example, FIG. 4 is a plan view showing a ceiling reinforcing structure according to the second embodiment, FIG. 4A is a plan view showing the first example, and FIG. FIG. 5 is a plan view showing the ceiling replenishment structure of the third reference form, FIG. 6 is a plan view showing the unit group and the subunit group of the unit building of the fourth reference form, and FIG. 7 is the fourth reference form. The form of the ceiling reinforcement structure of a form is shown, (A) is a top view showing the 1st example, and (B) is a top view showing the 2nd example.
[0019]
(First Reference Form) (FIGS. 1 and 2)
As shown in FIG. 1, the unit building 1 is constructed by arranging a plurality of building units 10 adjacent to each other in the horizontal direction and the vertical direction, and has a unit group 20 as shown in FIG.
[0020]
The unit group 20 includes two parallel building units 21 and 22 arranged in parallel with each other and their short sides 21A and 22A provided on the same straight line, and the same straight line between the two parallel building units 21 and 22 provided on the same straight line. And the transition building unit 23 arranged along the two short sides 21A and 22A. Each of the building units 21 to 23 is a frame structure in which four floor beams 11, columns 12, and ceiling beams 13 are joined in a box shape.
[0021]
The unit group 20 includes the following ceiling reinforcing structures (1) and (2) (FIG. 2A).
(1) A replenishment beam 23A is provided at a portion of the ceiling portion of the transit building unit 23 located on the extended line of the ceiling beams 13 and 13 at the boundary line between the two parallel building units 21 and 22. The reinforcing beam 23 </ b> A is hung on the intermediate portion between the ceiling beams 13 and 13 of the transit building unit 23.
[0022]
(2) A total of 4 areas consisting of areas A and B on the ceiling surfaces of the two parallel building units 21 and 22 and two areas C and D in which the ceiling surface of the transit building unit 23 is partitioned by reinforcing beams 23A. Of the two regions, regions A and C located diagonally in plan view and another region D are brace reinforced with a horizontal brace 14, and the remaining one region B is a blowable region 15 without brace reinforcement.
[0023]
According to this reference embodiment, there are the following operations.
(a) The horizontal force along the ceiling beam 13 at the boundary line between the two-sided building units 21 and 22 is moved with the two-sided building units 21 and 22 due to the presence of the reinforcing beam 23A provided on the moving-side building unit 23. It can be borne by the three building units of the building unit 23.
[0024]
(b) Among a plurality of four regions consisting of regions A and B on the ceiling surface of the two parallel building units 21 and 22 and regions C and D partitioned by the reinforcing beams 23A of the transition building unit 23 The regions A and C located diagonally in plan view were brace reinforced. Therefore, even on the ceiling surface of the region B where the brace is not reinforced, the ceiling beams 13 intersecting each other in the X direction and the Y direction orthogonal to each other are indirectly attached to the reinforcing regions A and C positioned diagonally with the brace reinforced. Reinforced. Therefore, the horizontal forces in the X and Y directions acting on the unit group 20 can be uniformly borne by all the three parallel building units 21 and 22 and the cross building unit 23.
[0025]
(c) Due to the above (a) and (b) , the unit group 20 can be prevented from being deformed by the horizontal force.
[0026]
(d) Since at least one area B of the ceiling of the unit group 20 is a blowable area 15 without brace reinforcement, a staircase or a blowout room can be provided in the blowable area 15. A skylight can be provided in the upper part.
[0027]
FIG. 2B is a modification of the ceiling reinforcing structure of the unit group 20, where the area A of the parallel-placed building unit 21 is defined as a blowable area 15, and the area B of the parallel-placed building unit 22 and the area of the crossover-building unit 23. C and D are brace reinforced with a horizontal brace 14.
[0028]
FIG. 2C is a modified example of the ceiling reinforcement structure of the unit group 20. The horizontal building 14 is brace reinforced with the horizontal brace 14 in the region A of the parallel building unit 21 and the region C of the cross building unit 23. The area B and the area D of the transit building unit 23 are defined as the area 15 that can be blown through. That is, in the unit group 20 provided in the upper part of the unit building 1, one area C or D (* part in FIG. 2) of the transit building unit 23 can be set as the blowable area 15.
[0029]
(Embodiment of the present invention ) (FIG. 3)
In FIG. 3A, the unit group 30 is composed of two parallel building units 31 and 32 and a cross building unit 33. The cross building unit 33 is composed of two parallel building units 31 and 32. It is longer than the total length of the two short sides 31A and 32A aligned on the same straight line.
[0030]
The unit group 30 includes the following ceiling reinforcing structures (1) and (2).
(1) A reinforcing beam 33A is provided at a portion of the ceiling portion of the transit building unit 33 located on the extended line of the ceiling beams 13 and 13 at the boundary between the two parallel building units 31 and 32, and a narrow-width parallel building Reinforcing beams 33 </ b> B are also provided on portions of the outer lines of the unit 31 located on the extended lines of the ceiling beams 13. The reinforcing beams 33 </ b> A and 33 </ b> B are hung on the intermediate portions of the ceiling beams 13 and 13 of the transit building unit 33.
[0031]
(2) The areas A and B of the ceiling surfaces of the two parallel building units 31 and 32, and the three areas C, D and E obtained by dividing the ceiling surface of the transit building unit 33 by the reinforcing beams 33A and 33B Among the five regions consisting of the regions A and C located diagonally in plan view and the other two regions D and E are braced with the horizontal brace 14 and the remaining one region B is not blown through the braceable region It was set to 15.
[0032]
According to the embodiment of the present invention , when the cross building unit 33 is longer than the total length of the two short sides 31A and 32A aligned on the same straight line of the two parallel building units 31 and 32, the narrow parallel building Due to the presence of the reinforcing beam 33B provided in the crossover building unit 33, the three building units of the parallel building unit 31, 32 and the crossover building unit 33 are subjected to the horizontal force along the ceiling beam 13 of the outer line of the unit 31. Can be borne.
[0033]
FIG. 3B is a modification of the ceiling reinforcing structure of the unit group 30, and the area A of the parallel building unit 31 is defined as a blowable area 15, and the area B of the parallel building unit 32 and the area of the crossover building unit 33 are illustrated. C, D, and E are brace reinforced with a horizontal brace 14.
[0034]
In the unit group 30 provided in the upper part of the unit building 1, the area C or D (the * part in FIG. 3) of the transit building unit 33 can be used as the blowable area 15.
[0035]
( Second reference form) (FIG. 4)
In FIG. 4A, the unit group 40 is composed of two parallel building units 41 and 42 and a cross building unit 43. Both parallel building units 41 and 42 are along the boundary line between them. The long sides 41A and 42A have different lengths.
[0036]
The unit group 40 includes the following ceiling reinforcing structures (1) to (3).
(1) Reinforcement beams 43 </ b> A are provided at portions of the ceiling portion of the transit building unit 43 that are located on the extended lines of the ceiling beams 13 and 13 at the boundary between the two parallel building units 41 and 42.
[0037]
(2) Reinforcing beams 42B are provided at portions of the ceiling portion of the long parallel-placed building unit 42 that are located on the extended line of the ceiling beam 13 of the outline of the short parallel-placed building unit 41.
[0038]
(3) A total of 4 areas consisting of areas A and B on the ceiling surfaces of the two parallel building units 41 and 42, and two areas C and D in which the ceiling surface of the transit building unit 43 is partitioned by reinforcing beams 43A. Of the two regions, regions A and C located diagonally in plan view and another region D are brace reinforced with a horizontal brace 14, and the remaining one region B is a blowable region 15 without brace reinforcement.
[0039]
According to this preferred embodiment, when the building units 41 and 42 placed both parallel to different from the long side 41A along their borders, 42A of the lengths from each other, the ceiling beams of short parallel every contour of the building unit 41 The horizontal force along 13 can be borne by the three building units of the parallel building units 41 and 42 and the cross building unit 43 due to the presence of the reinforcing beam 42B provided on the long parallel building unit 42.
[0040]
FIG. 4B is a modified example of the ceiling reinforcing structure of the unit group 40, and the area A of the parallel building unit 41 is defined as a blowable area 15, and the area B of the parallel building unit 42 and the area of the transition building unit 43 C and D are brace reinforced with a horizontal brace 14.
[0041]
In the unit group 40 provided in the upper part of the unit building 1, the area C or D (the * part in FIG. 4) of the transit building unit 43 can be used as the blowable area 15.
[0042]
( 3rd reference form) (FIG. 5)
In FIG. 5, two parallel building units 51 and 52 and a cross building unit 53 constitute a unit group 50, and the cross building unit 53 is on the same straight line of both the parallel building units 51 and 52. Is shorter than the total length of the two long sides 51A and 52A.
[0043]
The unit group 50 includes the following ceiling reinforcing structures (1) to (3).
(1) Reinforcement beams 53 </ b> A are provided at portions of the ceiling portion of the transit building unit 53 that are located on the extended lines of the ceiling beams 13 and 13 at the boundary between the two parallel building units 51 and 52.
[0044]
(2) Reinforcement beams 51B are provided at portions of the ceiling portion of the parallel building unit 51 located on the vertical line of the ceiling beam 13 of the outline of the transit building unit 53. In the parallel-mounted building unit 51, the reinforcing beam 51B is abutted and supported in a T shape on the joint beam 51C spanning the opposing ceiling beams 13 and 13.
[0045]
(3) A total of 4 areas comprising areas A and B on the ceiling surfaces of the two parallel building units 51 and 52, and two areas C and D obtained by dividing the ceiling surface of the transit building unit 53 by the reinforcing beams 53A. Of the two regions, regions A and C located diagonally in plan view and another region D are braced with a horizontal brace 14, and the remaining one region B is a blowable region 15 that is not braced.
[0046]
According to this reference form, when the transit building unit 53 is shorter than the total length of the two long sides 51A, 52A aligned on the same straight line of the two parallel placement building units 51, 52, the outline of the transit building unit 53 The horizontal force along the line ceiling beam 13 can be borne by the three building units, ie, the two parallel building units 51 and 52 and the cross building unit 53 due to the presence of the reinforcing beam 51B provided in the parallel building unit 51.
[0047]
In the unit group 50 provided in the upper part of the unit building 1, the area D (* part in FIG. 5) of the transit building unit 53 can be set as the blowable area 15.
[0048]
( 4th reference form) (FIG. 6, FIG. 7)
FIG. 6 is a combination of the subunit group 60 and the unit group 20 of FIGS. That is, one parallel building unit 21 of the two parallel building units 21 and 22 constituting the unit group 20 is defined as a sub-overlaying building unit 63, and among the sides of the sub-overlaying building unit 63, The other two sub-parallel placement building units 61 and 62 are arranged side by side along the long side 63B where the unit 23 is not disposed, and both the sub-parallel placement building units 61 and 62 and the sub-crossover building unit 63 are arranged. The subunit group 60 is constituted by the above.
[0049]
The sub unit group 60 also has a ceiling reinforcing structure similar to that in the unit group 20. That is, the ceiling reinforcement structure of the unit group 20 and the subunit group 60 is as follows.
[0050]
(1) Reinforcement beams 23 </ b> A are provided on the ceiling portions of the transit building units 23 constituting the unit group 20 at portions located on the extended lines of the ceiling beams 13 and 13 at the boundary lines of the two parallel mounting building units 21 and 22. At the same time, it is located on the extended part of the ceiling beams 13 and 13 at the boundary line between the two parallel-placed building units 61 and 62 at the ceiling of the sub-crossover building unit 63 (parallel-placed building unit 21) constituting the subunit group 60. A reinforcing beam 63A is provided in the portion.
[0051]
(2) In the unit group 20, two areas A1 and A2 in which the ceiling surface of the parallel building unit 21 (sub-crossover building unit 63) is partitioned by the reinforcing beam 63A, and the area B of the ceiling surface of the parallel building unit 22 Among the five regions consisting of two regions C and D in which the ceiling surface of the transit building unit 23 is partitioned by the reinforcing beams 23A, the regions A1, A2, and C that are diagonally viewed in plan view are the other ones. One region D was brace reinforced with a horizontal brace 14, and the remaining one region B was defined as a blowable region 15 without brace reinforcement.
[0052]
(3) In the subunit group 60, the two areas in which the ceiling surfaces E and F of the two sub-parallel building units 61 and 62 and the ceiling surface of the sub-laying building unit 63 are partitioned by the reinforcing beams 63A. Of all the four regions A1 and A2, the regions E, A1 and another region A2 that are diagonally located in plan view are brace-reinforced with the horizontal brace 14 and the remaining one region F is not brace-reinforced. The possible area 15 was set.
[0053]
According to this preferred embodiment, a unit group 20 consisting of two parallel every building unit 21, 22 and over every other building unit 23, consists of two sub-parallel placed building unit 61, 62 and the sub-cross every building unit 63 Even when the sub unit group 60 combines the single parallel building unit 21 of the unit group 20 and the sub cross building unit 63 of the sub unit group 60 as the same building unit, the unit group 20 and the sub unit In both groups 60, it is possible to form a blow-by area in the ceiling while preventing deformation due to horizontal force.
[0054]
FIG. 7B is a modification of the ceiling reinforcing structure of the subunit group 60, where the area E of the parallel building unit 61 is defined as a blowable area 15, and the area F of the parallel building unit 62 and the cross building unit 63 are arranged. The regions A1 and A2 are brace reinforced by the horizontal brace 14.
[0055]
The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration of the present invention is not limited to this embodiment, and there are design changes and the like without departing from the gist of the present invention. Is included in the present invention. For example, a reinforcing beam is provided on the floor of a transitional building unit that is located on the extension of the boundary line between the two parallel mounting units, and the area of each floor surface of the two parallel building units and the transitional building Of the multiple areas consisting of the area where the floor of the unit is partitioned by reinforcing beams, two areas located diagonally in plan view can be brace reinforced, and at least one of the remaining areas can be blown out without brace reinforcement It may be provided with a floor reinforcement structure of a unit group, which is a simple area.
[0056]
【The invention's effect】
As described above, according to the present invention, it is possible to provide a blow-by area in the ceiling portion of a unit group while preventing deformation of the unit group composed of two parallel building units and a crossing building unit against the horizontal force. .
[Brief description of the drawings]
FIG. 1 shows a unit group of a unit building of a first reference form, (A) is a perspective view, and (B) is a plan view.
2A and 2B show a ceiling reinforcing structure according to a first reference embodiment, wherein FIG. 2A is a plan view showing a first example, FIG. 2B is a plan view showing a second example, and FIG. 2C is a third example. FIG.
3A and 3B show a ceiling reinforcing structure according to an embodiment of the present invention . FIG. 3A is a plan view showing a first example, and FIG. 3B is a plan view showing a second example.
4A and 4B show a ceiling reinforcing structure of a second reference form, in which FIG. 4A is a plan view showing a first example, and FIG. 4B is a plan view showing a second example.
FIG. 5 is a plan view showing a ceiling supply structure of a third reference embodiment.
FIG. 6 is a plan view showing a unit group and a subunit group of a unit building of a fourth reference form.
FIGS. 7A and 7B show a ceiling reinforcing structure according to a fourth reference embodiment. FIG. 7A is a plan view showing a first example, and FIG. 7B is a plan view showing a second example.
[Explanation of symbols]
1 Unit building 14 Horizontal brace 15 Ventable area
30 units
31, 32 parallel building units
33 crossover building unit
33A, 33B Reinforcement beam 60 Sub unit group 61, 62 Sub parallel placement building unit 63 Sub crossover building unit 63A Reinforcement beam

Claims (2)

2個の互いに並列配置されてそれらの辺を同一直線上に揃えた並列置き建物ユニットと、2個の並列置き建物ユニットの同一直線上に揃う2つの辺に沿うように配置された渡り置き建物ユニットとからなるユニット群を有し、
渡り置き建物ユニットの天井又は床部で、両並列置き建物ユニットの境界線の延長線上に位置する部分に補強梁を設け、2個の並列置き建物ユニットの各天井又は床面の領域と、渡り置き建物ユニットの天井又は床面を補強梁で区画した領域とからなる複数の領域のうち、平面視で対角に位置する2つの領域をブレース補強し、残る領域のうち少なくとも1つの領域をブレース補強しない吹き抜け可能な領域とする、ユニット群の補強構造を備えてなるユニット建物において、
前記渡り置き建物ユニットが両並列置き建物ユニットの同一直線上に揃う2つの辺の合計長より長尺をなすとき、渡り置き建物ユニットの天井又は床部で、並列置き建物ユニットの外郭線の延長線上に位置する部分にも補強梁を設けることを特徴とするユニット建物
Two parallel-placed building units arranged in parallel to each other and having their sides aligned on the same straight line, and a transitional building arranged along two sides aligned on the same straight line of the two parallel-placed building units have a unit group consisting of a unit,
Reinforcement beams are provided on the ceiling or floor of the transitional building unit on the extension of the boundary between the two parallel mounting units, and the ceiling or floor area of the two parallel mounting units and the transition Brace reinforcement of two areas located diagonally in plan view, and brace at least one area among the remaining areas among a plurality of areas consisting of areas where the ceiling or floor surface of the building unit is partitioned by reinforcing beams In a unit building with a unit group reinforcement structure, which is an area that can be blown out without reinforcement ,
When the transition building unit is longer than the total length of two sides that are aligned on the same straight line of the parallel building unit, the extension of the outline of the parallel building unit on the ceiling or floor of the transition building unit A unit building characterized in that reinforcing beams are also provided on the part located on the line .
前記ユニット群を構成する前記2個の並列置き建物ユニットの一方の建物ユニットをサブ渡り置き建物ユニットとし、このサブ渡り置き建物ユニットの辺のうち、前記渡り置き建物ユニットが配置されていない辺に沿って、他の2個のサブ並列置き建物ユニットを並べて配置し、これらのサブ渡り置き建物ユニットと両サブ並列置き建物ユニットによりサブユニット群を構成するとき、
サブユニット群についても前記ユニット群におけると同じ補強構造を備えてなる請求項1に記載のユニット建物。
One building unit of the two parallel-placed building units constituting the unit group is set as a sub-crossover building unit, and the side where the cross-over building unit is not arranged among the sides of the sub-crossover building unit. Along the other two sub-parallel placement building units, and when a sub-unit group is constituted by these sub-transition building units and both sub-parallel placement building units,
The unit building according to claim 1, wherein the sub unit group is provided with the same reinforcing structure as in the unit group.
JP2001023609A 2001-01-31 2001-01-31 Unit building Expired - Fee Related JP4669615B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001023609A JP4669615B2 (en) 2001-01-31 2001-01-31 Unit building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001023609A JP4669615B2 (en) 2001-01-31 2001-01-31 Unit building

Publications (2)

Publication Number Publication Date
JP2002227306A JP2002227306A (en) 2002-08-14
JP4669615B2 true JP4669615B2 (en) 2011-04-13

Family

ID=18888876

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001023609A Expired - Fee Related JP4669615B2 (en) 2001-01-31 2001-01-31 Unit building

Country Status (1)

Country Link
JP (1) JP4669615B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5202925B2 (en) * 2007-11-13 2013-06-05 トヨタホーム株式会社 Unit building
JP5836077B2 (en) * 2011-11-17 2015-12-24 積水化学工業株式会社 Attached structures and unit buildings
JP6763653B2 (en) * 2015-09-28 2020-09-30 積水化学工業株式会社 Unit building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS603340A (en) * 1983-06-20 1985-01-09 株式会社クボタ Assembled enclosure of gradient roof hat in unit house
JPH09228484A (en) * 1996-02-26 1997-09-02 Asahi Chem Ind Co Ltd Unit house
JPH10306506A (en) * 1997-05-06 1998-11-17 Misawa Homes Co Ltd Building unit for connection and unit type building
JPH11124914A (en) * 1997-10-22 1999-05-11 Sekisui Chem Co Ltd Arranged structure of building unit
JP2000282581A (en) * 1999-03-31 2000-10-10 Misawa Homes Co Ltd Unit building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS603340A (en) * 1983-06-20 1985-01-09 株式会社クボタ Assembled enclosure of gradient roof hat in unit house
JPH09228484A (en) * 1996-02-26 1997-09-02 Asahi Chem Ind Co Ltd Unit house
JPH10306506A (en) * 1997-05-06 1998-11-17 Misawa Homes Co Ltd Building unit for connection and unit type building
JPH11124914A (en) * 1997-10-22 1999-05-11 Sekisui Chem Co Ltd Arranged structure of building unit
JP2000282581A (en) * 1999-03-31 2000-10-10 Misawa Homes Co Ltd Unit building

Also Published As

Publication number Publication date
JP2002227306A (en) 2002-08-14

Similar Documents

Publication Publication Date Title
CA2408894C (en) Accessory for modular elements for the support and ventilation of crawl spaces, floor structures, floors or similar articles in the building field
JP4669615B2 (en) Unit building
JPH069170Y2 (en) Beam structure
JP3236094B2 (en) Unit building
JP3734310B2 (en) Unit laminated structure
JP3797725B2 (en) Stairwell reinforcement structure
JPH06272317A (en) Building unit and unit type building
JPH10152888A (en) Connecting structure of precast reinforced concrete member
KR102585839B1 (en) Module type ceiling system and construction method thereof
JP7307600B2 (en) building
JP4248349B2 (en) Unit building
JP4338799B2 (en) Plastic pallet
JP4801856B2 (en) Unit building
JP3967998B2 (en) Unit building
JP4163325B2 (en) Unit building
JP3997005B2 (en) Unit building
JP2529611B2 (en) Arrangement structure of tendons
JP6893102B2 (en) building
JPH0634490Y2 (en) Structural floorboards
JP4072278B2 (en) Unit building
JP3330409B2 (en) Unit building
JP3739236B2 (en) Unit building
JP2000001909A (en) Unit type building
JP2978446B2 (en) Middle pillar housing unit
JP2001059274A (en) Unit building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071016

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100629

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100809

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101001

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20101222

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140121

Year of fee payment: 3

R151 Written notification of patent or utility model registration

Ref document number: 4669615

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R151

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140121

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees