JP4568443B2 - Pile construction machine - Google Patents
Pile construction machine Download PDFInfo
- Publication number
- JP4568443B2 JP4568443B2 JP2001083143A JP2001083143A JP4568443B2 JP 4568443 B2 JP4568443 B2 JP 4568443B2 JP 2001083143 A JP2001083143 A JP 2001083143A JP 2001083143 A JP2001083143 A JP 2001083143A JP 4568443 B2 JP4568443 B2 JP 4568443B2
- Authority
- JP
- Japan
- Prior art keywords
- liner
- chuck
- mast
- pile
- press
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、杭の地盤への圧入及び杭の地盤からの引き抜きのうちの少なくとも一方を行う杭施工機に関するものである。
【0002】
【従来の技術】
一般に、杭圧入引き抜き機(杭施工機)としては、既設の鋼矢板(杭)から反力を取った状態で、新たな鋼矢板を把持した昇降部を降下することにより、地盤に圧入するものが知られている。
また、杭圧入引き抜き機は、既設の鋼矢板から反力を取った状態で、他の鋼矢板を把持した昇降部を上昇することにより、地盤から引き抜くことができる。
そして、杭圧入引き抜き機は、既設の鋼矢板を掴んで反力を取るとともに、既設の鋼矢板上を移動する移動体と、移動体に対して、昇降移動し、鋼矢板を把持して地盤に圧入するための機能を有する昇降部とを備えている。
【0003】
【発明が解決しようとする課題】
ところで、移動体と昇降部が嵌合するとともに、摺動する摺動部は、鋼矢板の圧入(引き抜き)の際、昇降部の摺動による摩擦が発生するため、摩耗が顕著な部分である。そのため、昇降部側の摺動部には、交換自在な摺動保護部材が備えられている。
また、移動体側の摺動部は、昇降部の摺動によって、昇降部に摺動保護部材を用いても、やがて摩耗し、加工補修する必要があった。
また、加工補修を行うには、工作機械を有する工場が必要であるため、現場での加工補修は行えなかった。また、移動体側の摺動部に表面焼き入れを行うことにより、寿命を延ばすことはできるが、摩耗を阻止することはできなかった。
【0004】
本発明の課題は、杭の圧入や引き抜きを行う装置で生じる摩耗に対するメンテナンスを容易なものとすることである。
【0005】
【課題を解決するための手段】
以上の課題を解決するため、
請求項1記載の発明は、例えば、図1〜3に示すように、杭(鋼矢板2)の地盤への圧入及び杭の地盤からの引き抜きのうちの少なくとも一方を行う杭施工機(杭圧入引き抜き機1)において、杭を把持するチャック51と、前記チャックの移動を案内するマスト41と、杭の上昇及び下降のうちの少なくとも一方を行う際に、前記チャックとの摺動による磨耗から前記マストを保護するためのマスト用ライナ47と、前記マストとの摺動による磨耗から前記チャックを保護するためのチャック用ライナ57と、を有し、前記マスト用ライナと前記チャック用ライナは、前記マストと前記チャックに各々交換自在に取り付けられ、前記マスト用ライナは、前記チャック用ライナよりも長いことを特徴とする杭施工機である。
【0006】
請求項1記載の発明によれば、本発明の杭施工機は、マスト用ライナとチャック用ライナは、マストとチャックに各々交換自在に取り付けられており、マスト用ライナとチャック用ライナが摺動保護部材として機能している。
マスト用ライナとチャック用ライナが摩耗した場合は、これを交換すればよいので、杭施工機の加工補修や、場合によっては、移動体全体の交換の必要性がなくなり、容易に摺動保護部材を交換できる。
また、加工補修の必要性がなくなったことにより、加工補修をするための工作機械を備えた工場の設備が不要となる。
したがって、加工補修時間の短縮による工期の短縮、コストダウンが図れる。
【0009】
請求項2記載の発明は、例えば、図3〜4に示すように、前記マスト用ライナが、前記チャック用ライナより硬くされていることを特徴とする杭施工機である。
【0010】
請求項2記載の発明によれば、マスト用ライナが、チャック用ライナより硬くされている。
したがって、圧入(引き抜き)を繰り返すと、昇降部側のチャック用ライナが主に摩耗する。そして、昇降部側のチャック用ライナが摩耗すると、昇降部に傾きが生じる可能性がある。しかし、圧入の際に昇降部を案内する移動体側のマスト用ライナが摩耗しなければ、鋼矢板の圧入方向は保つことができるため、圧入精度を保つことができる。
【0011】
【発明の実施の形態】
以下、図1〜4を参照して、本発明の実施の形態の杭施工機について詳細に説明する。
【0012】
まず、図1及び2を参照して、杭施工機である杭圧入引き抜き機1の構成を説明する。
本発明の杭圧入引き抜き機1は、図2に示すように、既設の鋼矢板(杭)2から反力を取るとともに、順次圧入される鋼矢板2の並び方向に沿って移動する機能を有する移動体3と、鋼矢板2を把持し、上下に昇降することによって地盤に鋼矢板2の圧入及び引き抜きを行うための昇降部5とを備えている。該昇降部5は、移動体3の側面の溝に一部を嵌合する状態で昇降自在に配置されている。
【0013】
前記移動体3は、既設の鋼矢板2上に鋼矢板2を掴むための複数のクランプ31、該クランプ31を下部に備えるサドル32、該サドル32上に設けられ、順次圧入される鋼矢板2のうちの次に圧入される鋼矢板2に向かって、スライド移動するためのスライドベース33とスライドベース33上に旋回自在に配置され、昇降部5を取り付けるためのマスト41とを備えている。
【0014】
図1に示すように、前記マスト41には、鋼矢板2を圧入する側に、前記昇降部5の後述するチャック51を上下方向に昇降自在に案内するための上下に延在する溝を有する案内部43が備えられている。
【0015】
前記昇降部5は、鋼矢板2を把持するとともに、地盤に圧入するためのチャック51と該チャック51をマスト41の案内部43に沿って昇降させるための油圧シリンダ52とを備えている。また、チャック51には、マスト41の案内部43に嵌合される被案内部53が備えられている。
【0016】
次に、図3及び図4に示すように、本発明のポイントであるマスト41及びチャック51の摺動部について説明する。
マスト41には、チャック51との摺動による摩耗からマスト41を保護するための摺動保護部材であるマスト用ライナ47と、該マスト用ライナ47をマスト41に取り付けるための取付部材である取付ビス46とが備えられている。
マスト用ライナ47は、耐摩耗性に優れ、かつ、高硬度を有する薄い板状の部材に取付ビス46用の孔が削孔されたものである。該マスト用ライナ47は、前記案内部43の表面を被覆するように、複数の取付ビス46によってマスト41に接合され、マスト41側の摺動部となる。
また、圧入(引き抜き)時の摺動による取付ビス46への剪断力を低減するために、マスト41とマスト用ライナ47との接合部には、ストッパ48(規制部材)が接合部の上下両端部に、マスト41とマスト用ライナ47とに重なり合うように取り付けられる。
なお、マスト41の接合面の数カ所に、キー溝を形成し、該キー溝の深さの約2倍程度の高さをもつキー49(規制部材)を取り付け、突出したキー49の大きさに合わせて備えられたキー溝を有するマスト用ライナ47を嵌合する方法を用いてもよい。
【0017】
チャック51には、マスト41との摺動による摩耗からチャック51を保護するためのチャック用ライナ57と該チャック用ライナ57をチャック51に取り付けるための取付具である取付ビス46とが備えられている。
チャック用ライナ57は、マスト用ライナ47と同様に、薄い板状の部材で形成されており、前記被案内部53の表面を被覆するように、複数の取付ビス46によってチャック51に接合され、チャック51側の摺動部となる。
なお、チャック51の被案内部53がマスト41の案内部43に沿って、昇降移動するので、マスト41の案内部43の方がチャック51の被案内部53より長くなっており、マスト41の案内部43に取り付けられるマスト用ライナ47全体の上下長さの方が、チャック51の被案内部53に備えられているチャック用ライナ57の全体の上下長さより長くされている。
【0018】
また、鋼矢板2の圧入精度を保つために、マスト用ライナ47の材料は、チャック用ライナ57に比べて耐摩耗性に優れるとともに、チャック用ライナ57より硬い材料が用いられる。
なお、マスト用ライナ47及びチャック用ライナ57は、例えば、合金製のもので、用いる合金を変えることにより、マスト用ライナ47とチャック用ライナ57で硬度を変えることができる。
【0019】
次に、上述した機能を有する杭圧入引き抜き機1により、鋼矢板2を地盤に圧入する方法について説明する。
杭圧入引き抜き機1は、既設の鋼矢板2をクランプ31により掴むことにて、圧入の際の反力を取っている。そして、チャック51が圧入しようとしている鋼矢板2を掴んだ状態で、油圧シリンダ52を作動し、チャック51を地盤に向けて降下することにより、鋼矢板2は地盤に圧入される。
また、既に埋設された鋼矢板2を掴んだ状態で、チャック51を上昇させることで、鋼矢板2を地盤から引き抜くことができる。
【0020】
鋼矢板2の圧入や引き抜きが繰り返されることにより、マスト用ライナ47とチャック用ライナ57は、摺れ合い、摩耗する。
また、前記マスト用ライナ47とチャック用ライナ57との耐摩耗性及び硬度の違いから、主にチャック用ライナ57が摩耗する。したがって、鋼矢板2の圧入方向が変化することもなく、高い圧入精度を実現することができる。
摩耗したマスト用ライナ47及びチャック用ライナ57は、どちらも取付ビス46をはずして容易に交換することができる。
なお、本発明は、上記例の杭圧入引き抜き機に限定されるものではなく、杭の圧入、引き抜きにおいて、摺動する部分を有する装置に適用することができる。
【0021】
【発明の効果】
請求項1記載の発明によれば、本発明の杭施工機は、マスト用ライナとチャック用ライナは、マストとチャックに各々交換自在に取り付けられており、マスト用ライナとチャック用ライナが摺動保護部材として機能している。
マスト用ライナとチャック用ライナが摩耗した場合は、これを交換すればよいので、杭施工機の加工補修や、場合によっては、移動体全体の交換の必要性がなくなり、容易に摺動保護部材を交換できる。
また、加工補修の必要性がなくなったことにより、加工補修をするための工作機械を備えた工場の設備が不要となる。
したがって、加工補修時間の短縮による工期の短縮、コストダウンが図れる。
【0023】
請求項2記載の発明によれば、マスト用ライナが、チャック用ライナより硬くされている。
したがって、圧入(引き抜き)を繰り返すと、昇降部側のチャック用ライナが主に摩耗する。そして、昇降部側のチャック用ライナが摩耗すると、昇降部に傾きが生じる可能性がある。しかし、圧入の際に昇降部を案内する移動体側のマスト用ライナが摩耗しなければ、鋼矢板の圧入方向は保つことができるため、圧入精度を保つことができる。
【図面の簡単な説明】
【図1】本発明の実施の形態の杭施工機を示す平面図である。
【図2】上記例の杭施工機を示す側面図である。
【図3】上記例の杭施工機のマスト及びチャックの摺動部を説明するための図である。
【図4】上記例の杭施工機のマスト用ライナの接合を説明するための図である。
【符号の説明】
1 杭圧入引き抜き機(杭施工機)
2 鋼矢板(杭)
3 移動体(杭施工機本体の一部)
41 マスト(杭施工機本体の一部)
46 取付ビス(取付部材)
47 マスト用ライナ(長い方の摺動部)
48 ストッパ(規制部材)
49 キー(規制部材)
5 昇降部(杭施工機本体の一部)
51 チャック(杭施工機本体の一部)
57 チャック用ライナ(短い方の摺動部)[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a pile construction machine that performs at least one of press-fitting of a pile into the ground and drawing of the pile from the ground.
[0002]
[Prior art]
In general, as a pile press-fitting and pulling machine (pile construction machine), with a reaction force taken from an existing steel sheet pile (pile), it is press-fitted into the ground by descending a lifting part that holds a new steel sheet pile It has been known.
In addition, the pile press-fitting and drawing machine can be pulled out from the ground by ascending and descending the part that grips another steel sheet pile in a state where the reaction force is taken from the existing steel sheet pile.
And the pile press-fitting and pulling machine grabs the existing steel sheet pile and takes the reaction force, and also moves up and down the existing steel sheet pile, and moves up and down relative to the movable body, grips the steel sheet pile, And an elevating part having a function for press-fitting into the.
[0003]
[Problems to be solved by the invention]
By the way, while the moving body and the elevating part are fitted, the sliding part that slides is a portion where wear is significant because friction due to sliding of the elevating part occurs when the steel sheet pile is press-fitted (pulled out). . Therefore, the sliding part on the lifting part side is provided with a replaceable sliding protection member.
Further, the sliding part on the moving body side is worn out and needs to be repaired due to sliding of the elevating part even if a sliding protection member is used for the elevating part.
In addition, since a factory having a machine tool is necessary to perform machining repair, machining repair at the site could not be performed. Further, by performing surface quenching on the sliding portion on the moving body side, the life could be extended, but the wear could not be prevented.
[0004]
An object of the present invention is to facilitate maintenance against wear caused by an apparatus for press-fitting and extracting a pile.
[0005]
[Means for Solving the Problems]
To solve the above issues,
The invention according to
[0006]
According to the first aspect of the present invention, in the pile construction machine of the present invention, the mast liner and the chuck liner are attached to the mast and the chuck so as to be exchangeable, and the mast liner and the chuck liner slide. It functions as a protective member.
If the mast liner and chuck liner are worn, they can be replaced, so there is no need to repair the pile construction machine or, in some cases, the entire moving body, and it is easy to protect the slide. Can be replaced.
In addition, since there is no need for machining repair, the facility of a factory equipped with a machine tool for machining repair becomes unnecessary.
Therefore, the work period can be shortened and the cost can be reduced by shortening the machining repair time.
[0009]
Invention of
[0010]
According to the second aspect of the present invention, the mast liner is harder than the chuck liner .
Therefore, when the press-fitting (pulling) is repeated, the chuck liner on the elevating part side is mainly worn. If the chuck liner on the lifting / lowering part side is worn, the lifting / lowering part may be inclined. However, if the mast liner on the side of the moving body that guides the elevating unit during press-fitting does not wear, the press-fitting direction of the steel sheet pile can be maintained, so that press-fitting accuracy can be maintained.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, with reference to FIGS. 1-4, the pile construction machine of embodiment of this invention is demonstrated in detail.
[0012]
First, with reference to FIG. 1 and 2, the structure of the pile press-in
As shown in FIG. 2, the pile press-fitting and drawing
[0013]
The moving
[0014]
As shown in FIG. 1, the
[0015]
The
[0016]
Next, as shown in FIGS. 3 and 4, the sliding portion of the
The
The
In order to reduce the shearing force to the
It should be noted that key grooves are formed in several places on the joint surface of the
[0017]
The
The
Since the guided
[0018]
In order to maintain the press-fit accuracy of the
The
[0019]
Next, a method for press-fitting the
The pile press-fitting and drawing
Moreover, the
[0020]
As the
Further, due to the difference in wear resistance and hardness between the
Both the
In addition, this invention is not limited to the pile press-fit drawing machine of the said example, It can apply to the apparatus which has a part which slides in the press-fit of a pile, and drawing | extracting.
[0021]
【The invention's effect】
According to the first aspect of the present invention, in the pile construction machine of the present invention, the mast liner and the chuck liner are attached to the mast and the chuck so as to be exchangeable, and the mast liner and the chuck liner slide. It functions as a protective member.
If the mast liner and chuck liner are worn, they can be replaced, so there is no need to repair the pile construction machine or, in some cases, the entire moving body, and it is easy to protect the slide. Can be replaced.
In addition, since there is no need for machining repair, the facility of a factory equipped with a machine tool for machining repair becomes unnecessary.
Therefore, the work period can be shortened and the cost can be reduced by shortening the machining repair time.
[0023]
According to the second aspect of the present invention, the mast liner is harder than the chuck liner .
Therefore, when the press-fitting (pulling) is repeated, the chuck liner on the elevating part side is mainly worn. If the chuck liner on the lifting / lowering part side is worn, the lifting / lowering part may be inclined. However, if the mast liner on the side of the moving body that guides the elevating unit during press-fitting does not wear, the press-fitting direction of the steel sheet pile can be maintained, so that press-fitting accuracy can be maintained.
[Brief description of the drawings]
FIG. 1 is a plan view showing a pile construction machine according to an embodiment of the present invention.
FIG. 2 is a side view showing the pile construction machine of the above example.
FIG. 3 is a view for explaining a sliding portion of a mast and a chuck of the pile construction machine of the above example.
FIG. 4 is a view for explaining joining of a mast liner of the pile construction machine of the above example.
[Explanation of symbols]
1 Pile press-fitting and drawing machine (pile construction machine)
2 Steel sheet pile (pile)
3 Mobile body (part of the pile construction machine)
41 Mast (part of the pile construction machine itself)
46 Mounting screw (Mounting member)
47 Mast liner (longer sliding part)
48 Stopper (Regulator)
49 Key (Regulator)
5 Elevator (part of the pile construction machine main body)
51 Chuck (a part of the main body of the pile construction machine)
57 Chuck liner (shorter sliding part)
Claims (2)
杭を把持するチャックと、
前記チャックの移動を案内するマストと、
杭の上昇及び下降のうちの少なくとも一方を行う際に、前記チャックとの摺動による磨耗から前記マストを保護するためのマスト用ライナと、前記マストとの摺動による磨耗から前記チャックを保護するためのチャック用ライナと、を有し、
前記マスト用ライナと前記チャック用ライナは、前記マストと前記チャックに各々交換自在に取り付けられ、
前記マスト用ライナは、前記チャック用ライナよりも長いことを特徴とする杭施工機。In the pile construction machine that performs at least one of press-fitting into the ground of the pile and drawing out of the ground of the pile,
A chuck for gripping the pile,
A mast for guiding the movement of the chuck;
A mast liner for protecting the mast from wear due to sliding with the chuck and at least one of raising and lowering the pile and protecting the chuck from wear due to sliding with the mast A chuck liner for
The mast liner and the chuck liner are attached to the mast and the chuck in a replaceable manner ,
The pile construction machine , wherein the mast liner is longer than the chuck liner .
前記マスト用ライナが、前記チャック用ライナより硬くされていることを特徴とする杭施工機。In the pile construction machine according to claim 1,
The pile construction machine , wherein the mast liner is harder than the chuck liner .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001083143A JP4568443B2 (en) | 2001-03-22 | 2001-03-22 | Pile construction machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001083143A JP4568443B2 (en) | 2001-03-22 | 2001-03-22 | Pile construction machine |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002285553A JP2002285553A (en) | 2002-10-03 |
JP4568443B2 true JP4568443B2 (en) | 2010-10-27 |
Family
ID=18939000
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001083143A Expired - Lifetime JP4568443B2 (en) | 2001-03-22 | 2001-03-22 | Pile construction machine |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4568443B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6132533B2 (en) * | 2012-12-07 | 2017-05-24 | 株式会社技研製作所 | Slider clearance adjustment mechanism |
JP6132534B2 (en) * | 2012-12-07 | 2017-05-24 | 株式会社技研製作所 | Liner plate |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0738294U (en) * | 1993-12-27 | 1995-07-14 | 日本車輌製造株式会社 | Casing guide device for construction machinery |
JPH1181310A (en) * | 1997-09-04 | 1999-03-26 | Sumitomo Constr Mach Co Ltd | Main body supporting construction in leader type pile driver |
-
2001
- 2001-03-22 JP JP2001083143A patent/JP4568443B2/en not_active Expired - Lifetime
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0738294U (en) * | 1993-12-27 | 1995-07-14 | 日本車輌製造株式会社 | Casing guide device for construction machinery |
JPH1181310A (en) * | 1997-09-04 | 1999-03-26 | Sumitomo Constr Mach Co Ltd | Main body supporting construction in leader type pile driver |
Also Published As
Publication number | Publication date |
---|---|
JP2002285553A (en) | 2002-10-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1787051B1 (en) | Underwater pipe-laying apparatus and method | |
CN209006712U (en) | A kind of radial drilling machine | |
WO2009044481A1 (en) | Lifting device for elevator, elevator car frame, and lifting method for elevator | |
GB2345078A (en) | Drilling vessel provided with auxiliary tower or auxiliary mast | |
JP4568443B2 (en) | Pile construction machine | |
JP2017082452A (en) | Underground obstacle removal attachment and underground obstacle removal method | |
CN112207262B (en) | Demoulding system and demoulding method suitable for casting moulds with various shapes | |
JPS6347848B2 (en) | ||
CN211034868U (en) | Steel reinforcement cage hoist device | |
CN202390145U (en) | Fixing tool for assembling jacking frame cylinder of steel ladle of refining furnace | |
JP5628550B2 (en) | Wire jacking equipment | |
KR20170092514A (en) | Pile hammer | |
CN201500747U (en) | Reinforcing steel bar positioning and supporting device for reinforcing steel bar bending machine | |
JP2015169062A (en) | Pile press-in device | |
CN218322749U (en) | Construction pile extractor | |
CN108425644B (en) | Oil pipe transfer device and use method thereof | |
CN206016694U (en) | A kind of piling machinery for following support function with drilling rod | |
CN205436766U (en) | Punching device of pre -buried steel sheet of bridge | |
CN210280733U (en) | Metal processing device | |
JP2020105853A (en) | Pile pressing-in and pulling-out machine | |
CN220283228U (en) | Tower drum lifter | |
JP6525299B1 (en) | Column material withdrawal device | |
KR200368988Y1 (en) | Hydraulic Jack | |
JP6138469B2 (en) | Pile press-fitting device | |
CN213531380U (en) | Welding positioning device for steel pipe and welding part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20080220 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20091203 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20091215 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100215 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100323 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100524 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100727 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100809 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4568443 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130813 Year of fee payment: 3 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |