JP4423115B2 - An improved method for reducing land subsidence directly under existing embankments - Google Patents
An improved method for reducing land subsidence directly under existing embankments Download PDFInfo
- Publication number
- JP4423115B2 JP4423115B2 JP2004166803A JP2004166803A JP4423115B2 JP 4423115 B2 JP4423115 B2 JP 4423115B2 JP 2004166803 A JP2004166803 A JP 2004166803A JP 2004166803 A JP2004166803 A JP 2004166803A JP 4423115 B2 JP4423115 B2 JP 4423115B2
- Authority
- JP
- Japan
- Prior art keywords
- embankment
- layer
- subsidence
- existing
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
この発明は、上部に盛土層が造成されて基礎地盤を構成する沈下発生層が盛土層の盛土荷重により圧密沈下するのを低減若しくは抑止するための既設盛土直下の地盤沈下低減改良工法に関する。 The present invention relates to an improved method for reducing ground subsidence directly under an existing embankment for reducing or suppressing the settlement subsidence layer that forms the foundation ground with the embankment layer formed on the upper part due to the embankment load of the embankment layer.
粘性土層である沈下発生層の上部に盛土層を造成することは古くからよく行われており、例えば、ケーソン、矢板、L型ブロック等を用いた岸壁等の護岸の際にその背後に形成される裏込めの埋土層や、臨港道路橋梁等の橋台の背面に形成される橋台背面盛土等の近接工事の盛土層等(これら埋土層や盛土層を単に「盛土層」と総称する。)の造成が頻繁に施工されており、また、これまでも頻繁に行われてきた。 The embankment layer has been often built on top of the subsidence generation layer, which is a cohesive soil layer. For example, it forms behind the revetment of a quay using caisson, sheet pile, L-type block, etc. Such as the backfilled buried layer, and the embankment layer of the adjacent construction such as the abutment backfill formed on the back of the abutment such as the harborside bridge, etc. (These buried layers and the embankment layer are simply referred to as “filled layer”) )) Has been constructed frequently, and has been carried out frequently.
ところで、このような既設の盛土層を有する地盤においては、沈下発生層がその上に設けられた盛土層の盛土荷重に起因して徐々に圧密沈下し、周辺地盤との間に段差ができたり、所定の地盤高さを確保できなくなる等の問題を引き起こすことが観察されている。このため、新たに盛土層を造成する際には、通常は予め土質調査を行い、その下部の沈下発生層で圧密沈下が予測される場合には、この沈下発生層での圧密沈下(地盤沈下)を未然に防止するための様々な対策が採られている。 By the way, in the ground having such an existing embankment layer, the settlement generation layer gradually subsides due to the embankment load of the embankment layer provided thereon, and there is a step between the surrounding ground. It has been observed that it causes problems such as failure to secure a predetermined ground height. For this reason, when creating a new embankment layer, a soil survey is usually conducted in advance, and when consolidation settlement is predicted in the settlement generation layer below it, consolidation settlement (ground settlement) in this settlement generation layer is expected. Various measures are taken to prevent).
このような目的で行われる地盤改良施工法としては、例えば、改良対象地盤の一部をスパイラルスクリューオーガを用いて特定の軽量地盤改良材で置換する方法(特開平05-255,924号公報)や、改良対象地盤を掘削して所定長の孔を形成し、この孔内には比重の小さい材料又は気泡の少なくとも一方、土砂、セメント、ベントナイト及び水を地上で混合して得られたソイルセメントを充填し、改良対象地盤にソイルセメントコラムを形成する置換型深層改良工法(特開2001-241,035号公報)が提案されている。 As a ground improvement construction method performed for such a purpose, for example, a method of replacing a part of the ground to be improved with a specific lightweight ground improvement material using a spiral screw auger (Japanese Patent Laid-Open No. 05-255,924), Drilling the ground to be improved to form a hole with a predetermined length, and filling this hole with soil cement obtained by mixing at least one of a material with low specific gravity or bubbles, earth and sand, cement, bentonite and water on the ground However, a substitution type deep layer improvement method (Japanese Patent Laid-Open No. 2001-241,035) for forming a soil cement column on the ground to be improved has been proposed.
また、軟弱地盤に複数本の柱状体を支持層に達しない長さでかつ10〜50%の改良率で構築し、複数本の柱状体の上に補強用網状体を敷設し、あるいは、敷設することなく、浅層改良土層(土砂と固化材とに添加材及び/又は添加剤を混合して固化させた層)を敷設し、この浅層改良土層の上に道路舗装を施す道路の構築方法(特開平10-317,307号公報、特開2003-239,276号公報)や、軟弱地盤上に良質土砂の盛土を敷設し、この盛土と軟弱地盤とに既製杭を打設し、盛土と既製杭との上に固化層を形成し、固化層の上に舗装を構築して既製杭と盛土と固化層と舗装とを一体化させ、軟弱地盤にかかる盛土、固化層、舗装、その他車両等の荷重を既製杭の周面と先端部とから軟弱地盤の深部の地盤に伝達させると共に盛土を介して直接軟弱地盤面に伝達させる方法(特開2003-268,790号公報)も提案されている。 In addition, a plurality of columnar bodies are constructed on soft ground with a length that does not reach the support layer and with an improvement rate of 10 to 50%, and a reinforcing net is laid on the plurality of columnar bodies or installed. A road where a shallow improved soil layer (a layer obtained by mixing an additive and / or an additive in the earth and solidified material and solidified) is laid, and road pavement is applied on the shallow improved soil layer. Construction method (Japanese Patent Laid-Open No. 10-317,307, Japanese Patent Laid-Open No. 2003-239,276), and laying a bank of high quality earth and sand on soft ground, placing ready-made piles on this bank and soft ground, A solidified layer is formed on the ready-made pile, a pavement is built on the solidified layer, and the ready-made pile, embankment, solidified layer, and pavement are integrated, and the embankment, solidified layer, pavement, and other vehicles on the soft ground. And so on to the ground of the deep part of the soft ground and directly to the soft ground through the embankment. Reached method for (JP 2003-268,790) have also been proposed.
更には、盛土地盤の盛り立て造成過程で、盛土撒出層内に予め中空の膨張部材を平面方向適当な間隔で多数埋設しておき、造成が完了した後、盛土地盤上の構築物が盛土地盤の不同沈下によって傾倒した場合には、沈下箇所の真下の膨張部材中にスラリー状固化剤を圧入して選択的に膨張させ、その上の盛土層を隆起させて不同沈下を矯正する方法(特開平08-170,336号公報)も提案されている。 Furthermore, in the embankment creation process of the embankment, a large number of hollow expansion members are embedded in the embankment deposit layer at appropriate intervals in the plane direction, and after the construction is completed, the structure on the embankment is transferred to the embankment In the case of tilting due to uneven settlement, a slurry-like solidifying agent is press-fitted into the expansion member directly below the settlement site and selectively expanded, and the embankment layer above it is raised to correct the uneven settlement. Kaihei 08-170,336) has also been proposed.
しかしながら、これらの方法は、そのいずれも新たに盛土層を造成する際に採用される施工法であり、これまでに既に造成された既設の盛土層を有する場合にはそのまま適用することはできない。
しかるに、これまでに沈下発生層の上部に盛土層を設けて造成された地盤はいたるところに存在し、近年、その沈下発生層の圧密沈下による地盤沈下の問題が顕在化しつつある。
However, any of these methods is a construction method that is adopted when a new embankment layer is created, and cannot be applied as it is when an existing embankment layer that has already been constructed is used.
However, the ground that has been formed with the embankment layer on the subsidence generation layer has existed everywhere, and in recent years, the problem of subsidence due to the consolidation subsidence of the subsidence generation layer is becoming apparent.
このような既設の盛土層を有する地盤で発生する地盤沈下を改善するための方法としては、例えば護岸の背面埋土として造成された盛土層を例にして説明すると、図5に示すように、盛土層aの上方から盛土層aの下部に存在する沈下発生層(粘性土層)bに達する多数の孔cを穿設し、これら各孔c内の沈下発生層bの部分に鉛直方向支持力を増強するための地盤改良杭dを打ち込み、これらの地盤改良杭dによって盛土層aの盛土荷重を支持する沈下発生層bの支持力を補強する地盤改良杭による補強方法や、図6に示すように、護岸壁eの背面埋土として造成されている既設の盛土層aについて、護岸壁eの背面側の盛土層aを掘削しながら気泡混合土等の軽量土fと順次置換する置換方法等が考えられる。 As a method for improving the ground subsidence that occurs in the ground having such an existing embankment layer, for example, an embankment layer created as a backfill of the revetment will be described as shown in FIG. A number of holes c reaching from the upper part of the embankment layer a to the subsidence generation layer (viscous earth layer) b existing at the lower part of the embankment layer a are drilled and vertically supported by the subsidence generation layer b in each hole c Fig. 6 shows a method of reinforcing the ground improvement pile d for driving in the ground improvement piles d. The ground improvement piles d to reinforce the supporting force of the subsidence generation layer b which supports the embankment load of the embankment layer a by these ground improvement piles d. As shown in the figure, the existing embankment layer a created as the backfill of the revetment wall e is sequentially replaced with a light soil f such as bubble mixed soil while excavating the backfill layer a on the backside of the revetment wall e. A method etc. can be considered.
しかしながら、前者の地盤改良杭による補強方法においては、沈下発生層bが盛土層aの天端から深いところに存在し、その施工深度が深くなると、必然的に大型施工機が必要になり、このような大型施工機を搬入できない現場では施工が困難になるほか、盛土層aに孔cを穿設する際に形成された空打ち部gについても盛土材の埋め戻し作業が必要になり、結果として施工コストが嵩むという問題がある。 However, in the former method of reinforcing with ground improvement piles, the subsidence generation layer b exists deep from the top of the embankment layer a, and when the construction depth becomes deep, a large construction machine is inevitably required. As a result, the construction work is difficult at the site where such a large construction machine cannot be carried in, and the backfilling work of the embankment material is also required for the blanking portion g formed when the hole c is drilled in the embankment layer a. There is a problem that the construction cost increases.
また、後者の軽量土fによる置換方法においては、護岸壁eの背面側の盛土層aを掘削しながら軽量土fと順次置換するので比較的工期が長くなるが、この置換された軽量土fが安定するまでの間は護岸壁e自体の強度等が低下し、台風や大雨等の異常気象が発生し易い時期には施工することが難しく、工期の選択に制限が生じるほか、いつ何時に台風や大雨等の異常気象が起こるかもしれないという近年の気象状況では、実際にはこの方法を採用するのが困難な場合が多々ある。
そこで、本発明者らは、上部に盛土層が造成されて基礎地盤を構成する沈下発生層が盛土層の盛土荷重により圧密沈下するのを容易にかつ確実に低減若しくは抑止することができる既設盛土直下の地盤沈下低減改良工法について鋭意検討した結果、沈下発生層及び盛土層の土質調査結果から沈下発生層を正規圧密状態又は過圧密状態にするのに必要な盛土層の最大盛土荷重を求め、この最大盛土荷重と使用する軽量土置換杭の比重とから盛土層を形成する既存盛土材を軽量土置換杭に置換する割合を求め、その結果に基づいて盛土層を形成する既存盛土材の一部を軽量土置換杭で置換することにより、目的を達成できることを見い出し、本発明を完成した。 Therefore, the inventors of the present invention can easily and reliably reduce or suppress the settlement generation layer that forms the foundation ground by forming the embankment layer on the upper part and the consolidation subsidence due to the embankment load of the embankment layer. As a result of earnestly examining the method for reducing and improving the subsidence directly under the ground, the maximum embankment load of the embankment layer required to make the subsidence generation layer normal or overconsolidated from the soil investigation results of the subsidence generation layer and the embankment layer, Based on the maximum embankment load and the specific gravity of the lightweight soil replacement pile to be used, the ratio of replacing the existing embankment material forming the embankment layer with the lightweight soil replacement pile is obtained, and based on the result, one of the existing embankment materials forming the embankment layer is determined. It was found that the purpose could be achieved by replacing the part with a lightweight soil replacement pile, and the present invention was completed.
従って、本発明の目的は、上部に盛土層が造成されて基礎地盤を構成する沈下発生層が盛土層の盛土荷重により圧密沈下するのを容易にかつ確実に低減若しくは抑止することができる既設盛土直下の地盤沈下低減改良工法を提供することにある。 Accordingly, an object of the present invention is to provide an existing embankment that can easily and surely reduce or inhibit the settlement generation layer that forms the foundation ground by forming the embankment layer in the upper part and the consolidation settlement due to the embankment load of the embankment layer. The purpose is to provide an improved method of reducing land subsidence.
すなわち、本発明は、上部に盛土層が造成されて基礎地盤を構成する沈下発生層が盛土層の盛土荷重により圧密沈下するのを低減若しくは抑止するための地盤沈下低減改良工法であり、沈下発生層及び盛土層の土質調査結果から沈下発生層を正規圧密状態又は過圧密状態にするのに必要な盛土層の最大盛土荷重を求め、この最大盛土荷重と使用する軽量土置換杭の比重とから盛土層を形成する既存盛土材を軽量土置換杭に置換する割合を求め、求められた盛土層の既存盛土材を軽量土置換杭に置換する割合に基づいて、盛土層に所定数の孔を穿設して置換すべき既存盛土材を除去すると共にこの所定数の孔内に軽量土置換杭を設けることを特徴とする既設盛土直下の地盤沈下低減改良工法である。 That is, the present invention is a subsidence reduction improved method for subsidence generating layer embankment layer is Construction at the top to constitute the foundation ground is reduced or suppressed to consolidation settlement by embankment load of embankment layers, subsidence occurs The maximum embankment load of the embankment layer necessary to bring the settlement generation layer into the normal consolidation state or overconsolidation state is obtained from the soil survey results of the layer and the embankment layer, and from this maximum embankment load and the specific gravity of the lightweight soil replacement pile to be used The ratio of replacing the existing embankment material forming the embankment layer with the lightweight soil replacement pile is obtained, and a predetermined number of holes are formed in the embankment layer based on the ratio of replacing the existing embankment material of the found embankment layer with the light soil replacement pile. This is an improved construction method for reducing ground subsidence directly under the existing embankment, characterized in that the existing embankment material to be drilled and removed is removed and a light soil replacement pile is provided in the predetermined number of holes .
本発明において、盛土層を形成する既存盛土材の一部を置換するために用いられる軽量土置換杭は、少なくとも上記既存盛土材よりも比重が小さいことが必要であり、既存盛土材の一部がこの軽量土置換杭と置換された後には、盛土層の下部の沈下発生層が所定の沈下量以下に低減され、必要により正規圧密状態、好ましくは過圧密状態になって地盤沈下が完全に抑止されるように置換するのがよい。 In the present invention, the lightweight soil replacement pile used to replace a part of the existing embankment material forming the embankment layer needs to have a specific gravity at least smaller than that of the above existing embankment material, and a part of the existing embankment material However, after substituting this lightweight soil replacement pile, the subsidence generation layer below the embankment layer is reduced below the predetermined subsidence amount, and if necessary, it becomes a normal consolidated state, preferably an overconsolidated state, and the ground subsidence is completely completed. It is better to replace it so that it is suppressed.
この盛土層における既存盛土材と軽量土置換杭との置換は、先ず、改良対象となる施工現場(沈下発生層の上部に盛土層が造成されて地盤沈下が始まっているような場所)の沈下発生層及び盛土層の土質調査を行い、この土質調査の結果に基づいて沈下発生層を少なくとも正規圧密状態に維持するのに必要な、好ましくは過圧密状態にするのに必要な盛土層の最大盛土荷重を求め、また、盛土層を形成する既存盛土材よりも比重が小さく、この既存盛土材と置換するために使用する軽量土置換杭を選定し、ここで求められた最大盛土荷重と選定された軽量土置換杭の比重とから、盛土層を形成する既存盛土材のうちのどれくらいの割合をこの選定された軽量土置換杭に置換すればよいかを算出し、その結果(置換割合)に基づいて、盛土層の所定の位置にその天端から沈下発生層に向けて延びる所定数の孔を穿設することにより置換すべき既存盛土材を除去し、次いで穿設された所定数の孔内に軽量土置換杭を設けることによって、沈下発生層上部の盛土層の盛土荷重が調整される。そして、この際の盛土荷重の調整は、例えば下水管等のようにその機能から多少の地盤沈下が許容されて地盤沈下抑止(沈下量零)に精度が求められない場合には、圧密度100%未満の範囲で許容される沈下量まで低減されればよい場合があるほか、例えば多少の地盤沈下も許されない状態に至っている場合等のように地盤沈下を完全に抑止する必要がある場合には、沈下発生層を正規圧密状態に、好ましくは過圧密状態に調整される。そして、この盛土荷重の調整に際しては、置換される軽量土置換杭全体の重量、杭長及び置換率から選ばれたいずれか1つ又は2つ以上の要素により制御するのがよい。 The replacement of the existing embankment material and lightweight soil replacement piles in this embankment layer begins with the settlement of the construction site to be improved (a place where the embankment layer has been created on the upper part of the settlement subsidence layer and ground subsidence has begun). Conduct a soil survey of the generation layer and the embankment layer, and based on the results of this soil survey, the maximum of the embankment layer necessary to maintain the subsidence generation layer at least in a normal consolidated state, and preferably in an overconsolidated state Determine the fill load, and the specific gravity is smaller than the existing fill material that forms the fill layer, select the lightweight soil replacement pile to be used to replace this existing fill material, and select the maximum fill load determined here. Calculate the ratio of the existing embankment material that forms the embankment layer to the selected light soil replacement pile, and the result (replacement ratio). Based on the fill layer The existing embankment material to be replaced is removed by drilling a predetermined number of holes extending from the top of the ceiling toward the settlement generation layer at a fixed position, and then a lightweight soil replacement pile in the predetermined number of drilled holes By providing the , the embankment load of the embankment layer above the settlement generation layer is adjusted. The embankment load at this time is adjusted to a pressure density of 100, for example, when a certain amount of ground subsidence is allowed due to its function, such as a sewer pipe, and accuracy is not required to suppress land subsidence (zero subsidence). In some cases, it may be necessary to reduce the subsidence to an allowable level within a range of less than%, and when it is necessary to completely suppress subsidence, for example, when some subsidence is not permitted. Is adjusted to a normal consolidation state, preferably an overconsolidation state. And in adjusting this embankment load, it is good to control by any one or two or more elements chosen from the weight of the whole lightweight soil substitution pile to be replaced, pile length, and substitution rate.
また、改良対象となる施工現場において不同沈下が問題となるような場合には、盛土層を縦断及び/又は横断する複数の測定ポイントで複数の土質調査を行い、その結果に基づいて最大盛土荷重を断面方向の分布として求め、この盛土層における最大盛土荷重分布に基づいて盛土層における既存盛土材を軽量土置換杭と置換するようにしてもよく、これによって盛土層縦断及び/又は横断する方向において不同沈下の現象が発生するのを事前に防止することができる。そして、この最大盛土荷重分布を求めて不同沈下が発生しないように既存盛土材を軽量土置換杭と置換する場合においても、盛土層における盛土荷重の調整は、好ましくは、置換される軽量土置換杭全体の重量、杭長及び置換率から選ばれたいずれか1つ又は2つ以上の要素により制御するのがよい。 In addition, when uneven settlement becomes a problem at the construction site to be improved, multiple soil surveys are conducted at multiple measurement points that traverse and / or cross the embankment layer, and the maximum embankment load is based on the results. As a distribution in the cross-sectional direction, and based on the maximum embankment load distribution in this embankment layer, the existing embankment material in the embankment layer may be replaced with lightweight soil replacement piles, whereby the embankment layer longitudinal and / or transverse direction It is possible to prevent the occurrence of the phenomenon of uneven settlement in advance. And even when replacing the existing embankment material with a lightweight soil replacement pile so as not to cause uneven settlement by obtaining this maximum embankment load distribution, the adjustment of the embankment load in the embankment layer is preferably a light soil replacement to be replaced It is good to control by any 1 or 2 or more elements chosen from the weight of the whole pile, the pile length, and the substitution rate.
このような目的で用いられる軽量土置換杭については、特に制限はなく、例えば特開平05-255,924号公報に開示されているようなセメント、セメントミルク、石灰類等の地盤固化材と、粘土、砂、シルト又はこれらが混在した粘性土と、ポリエチレン、ポリスチレン、プロピレン、エチレン共重合体等からなるビーズ状合成樹脂発泡体とを水の存在下に混合してなる軽量地盤改良材や、特開2001-241,035号公報に開示されているような比重の小さい材料又は気泡の少なくとも一方、土砂、セメント、ベントナイト及び水を地上で混合して得られたソイルセメント等の硬化性軽量土を用いて形成されるものを挙げることができる。 The lightweight soil replacement pile used for such purposes is not particularly limited, for example, cement solids such as cement, cement milk, limes and the like as disclosed in JP 05-255,924 A, clay, A lightweight ground improvement material obtained by mixing sand, silt or a viscous soil mixed with these and a bead-like synthetic resin foam made of polyethylene, polystyrene, propylene, ethylene copolymer, etc. in the presence of water, Formed by using curable lightweight soil such as soil cement obtained by mixing at least one of low specific gravity material or bubbles, earth and sand, cement, bentonite and water as disclosed in 2001-241,035 gazette Can be mentioned.
そして、この軽量土置換杭は、改良対象となる施工現場の状況等に応じて、少なくとも盛土層を形成する既存盛土材よりも小さい比重の硬化性軽量土が調製され、また、盛土層には、既存盛土材の軽量土置換杭への置換割合に応じて、その所定の位置に、その天端から沈下発生層に向けて延びる所定の長さ(杭長に対応)及び/又は所定の数の孔を穿設し、この孔内に上記の如き硬化性軽量土を充填し、孔内で硬化させて形成される。 Then, the lightweight soil substitution piles, depending on the situation of the construction site to be improved target, curable lightweight soil specific gravity less than the existing embankment material forming at least the fill layer is prepared, also the fill layer Depending on the replacement ratio of the existing embankment material to the lightweight soil replacement pile, a predetermined length (corresponding to the pile length) and / or a predetermined number extending from the top to the subsidence generation layer in the predetermined position Are formed by filling the hole with the curable lightweight soil as described above and curing it in the hole.
また、このような軽量土置換杭については、好ましくはその杭長方向に沿って単位体積重量の異なる複数の領域を有するものであるのがよく、より好ましくはその全体の平均単位体積重量が5kN/m3以上13kN/m3以下であって、盛土層に置換された際に水位面以浅の単位体積重量が5kN/m3以上10kN/m3以下で水位面以深の単位体積重量が10kN/m3超となるように形成されているのがよい。軽量土置換杭をこのように構成することにより、盛土層に穿設した孔内に水が溜まっても、効率良く施工できるほか、確実に効率良く盛土層の盛土荷重の調整を行うことができる。 Further, such a lightweight soil replacement pile preferably has a plurality of regions having different unit volume weights along the pile length direction, and more preferably has a total average unit volume weight of 5 kN. / m 3 or more 13 kN / m 3 equal to or less than the unit volume weight of the water level surface or deeper in the specific weight of the water level surface shallower than the 5 kN / m 3 or more 10 kN / m 3 or less when it is substituted in the embankment layer is 10 kN / m 3 greater good that is formed such that. By constructing the lightweight soil replacement pile in this way, even if water accumulates in the hole drilled in the embankment layer, it can be constructed efficiently and the embankment load of the embankment layer can be adjusted efficiently and reliably. .
本発明の方法によれば、既設盛土直下の沈下発生層における圧密沈下を防止するために、この沈下発生層の上部の盛土層に対してその一部の既存盛土材を軽量土置換杭に置換すればよいので、例えば既設の堤防等の防護壁等をそのままに残した状態で部分的に(かつ必要により飛び飛びに)地盤沈下低減改良の工事を進めることができ、沈下発生層自体の地盤改良に比べて施工深度が顕著に浅くなり、大型施工機の使用が必要なくなるほか、地盤改良される盛土層についても既存盛土材の埋め戻し作業等が必要なくなり、結果として施工コストの低減化を図ることができ、更に、護岸壁の背面側の盛土層を大幅に掘削する必要もなくなることから、護岸壁自体の強度等に対する影響もなく、工期が制限されることもない。 According to the method of the present invention, in order to prevent consolidation subsidence in the subsidence generation layer directly under the existing embankment, a part of the existing embankment material is replaced with a lightweight soil replacement pile for the upper embankment layer of the subsidence generation layer. For example, it is possible to proceed with partial subsidence improvement work while leaving existing protective walls such as embankments as they are, and to improve the ground subsidence layer itself. The depth of construction will be significantly shallower than that of large-scale construction machines, and it will not be necessary to use large construction machines. In addition, it will not be necessary to backfill existing embankment materials for the embankment layer to be improved, resulting in a reduction in construction costs. In addition, since it is not necessary to excavate the embankment layer on the back side of the revetment wall, there is no influence on the strength of the revetment wall itself, and the construction period is not limited.
以下、添付図面に示す実施例に基づいて、本発明の既設盛土直下の地盤沈下低減改良工法の好適な実施の形態を具体的に説明する。 Hereinafter, based on the Example shown to an accompanying drawing, suitable embodiment of the ground subsidence reduction improvement method directly under the existing embankment of this invention is described concretely.
図1に、L型ブロックによる護岸の裏込めとしての盛土層を有する既設盛土直下の沈下発生層に対して、本発明の実施例1に係る地盤沈下低減改良工法が適用された例が示されている。 FIG. 1 shows an example in which the ground subsidence reduction improvement method according to Example 1 of the present invention is applied to a subsidence generation layer directly under an existing embankment having an embankment layer as a backfill for a revetment by an L-shaped block. ing.
この実施例1においては、先ず、粘性土層からなる沈下発生層1とその上部の盛土層2との土質調査を行い、この土質調査の結果に基づいて沈下発生層1が正規圧密状態になるために必要な盛土層2の最大盛土荷重を算出し、この算出された盛土層2の最大盛土荷重と、盛土層2の土質調査の結果と、使用する軽量土置換杭3の比重とから、沈下発生層1を正規圧密状態(好ましくは、過圧密状態)にするために盛土層2を形成している既存盛土材をどれだけの割合で軽量土置換杭3と置換すればよいか(置換情報)を求め、この置換情報に基づいて、スパイラルスクリューオーガ等の手段を用い、盛土層2にその天端から沈下発生層1に向けて延びる所定数の孔4を穿設し、この穿設された孔4内には所定の硬化性軽量土を流し込み、孔4内でこの硬化性軽量土を硬化させて軽量土置換杭3とすることにより施工される。なお、図1において、L型ブロックで構成された護岸壁5は沈下発生層1の下方の岩盤に達する支持杭6によって支持されている。
In Example 1, first, a soil investigation is performed on the settlement generation layer 1 made of a cohesive soil layer and the
この実施例1の地盤沈下低減改良工法において、スパイラルスクリューオーガ等の手段で穿設された孔4内に充填された硬化性軽量土は、この孔4内で硬化して軽量土置換杭3となり、既設の盛土層2の一部となって既設盛土材をこの軽量土置換杭3に置換した割合に応じて盛土層2の盛土荷重が軽減され、沈下発生層1における沈下量が軽減され、若しくは、抑止される。
In the land subsidence reduction improvement method of the first embodiment, the curable lightweight soil filled in the
なお、この実施例1において、既設の盛土層2に穿設される多数の孔4が水位面を超えて深い場合には、例えば2台のミキサーを用意し、これらのミキサーで単位堆積重量の異なる2種類(例えば、単位体積重量0.7kN/m3のものと単位体積重量1.1kN/m3のもの等)の硬化性軽量土を調製し、孔4内の水位面以深には単位体積重量1.1kN/m3の硬化性軽量土を充填し、また、水位面以浅には単位体積重量0.7kN/m3の硬化性軽量土を充填し、好ましくはその全体の平均単位体積重量が5kN/m3以上13kN/m3以下となるように調整することにより、効率良く施工できるほか、盛土層の盛土荷重の調整を確実にかつ効率良く行うことができる。
In Example 1, when a large number of
図2及び図3に、上記実施例1と同様の既設盛土直下の沈下発生層1に対して、本発明の実施例2に係る地盤沈下低減改良工法が適用された例が示されている。
この実施例2においては、上記実施例1の場合とは異なり、護岸壁5からその背面側の盛土層2を略直角に横切る方向(横断面方向)に沿って複数の測定ポイント7a,7b,7c,……で沈下発生層1とその上部の盛土層2との複数の土質調査を行い、この複数の土質調査の結果に基づいて沈下発生層1が正規圧密状態になるために必要な盛土層2の最大盛土荷重分布を求め、この求められた盛土層2の最大盛土荷重分布と、盛土層2の土質調査の結果と、使用する軽量土置換杭3の比重とから、沈下発生層1を正規圧密状態(好ましくは、過圧密状態)にするために盛土層2を形成している既存盛土材をどの部分においてどれだけの割合で軽量土置換杭3と置換すればよいか(置換情報)を求める。ここで求められた盛土層2の最大盛土荷重分布は、護岸壁5から略直角に離れる方向に沿って発生する不同沈下の沈下曲線8aとして得られる。
2 and 3 show an example in which the ground subsidence reduction improvement method according to Example 2 of the present invention is applied to the subsidence generation layer 1 just under the existing embankment similar to Example 1 described above.
In the second embodiment, unlike the first embodiment, a plurality of
次に、上で求められた沈下発生層1を正規圧密状態(好ましくは、過圧密状態)にするための置換情報に基づいて、スパイラルスクリューオーガ等の手段を用い、盛土層2にその天端から所定の間隔及び所定の深さで沈下発生層1に向けて延びる所定数の孔4a,4b,4c,……を順次穿設し、これら各孔4a,4b,4c,……内に硬化性軽量土を充填し、各孔4a,4b,4c,……内で硬化させて必要な数及び長さの軽量土置換杭3a,3b,3c,……を形成し、これによって盛土層2の既設盛土材の一部を軽量土置換杭3a,3b,3c,……と置換する。
Next, based on the replacement information for bringing the settlement generation layer 1 obtained above into a normal consolidated state (preferably an overconsolidated state), a means such as a spiral screw auger is used, and the top of the
この実施例2においては、盛土層2の既設盛土材と置換される軽量土置換杭3a,3b,3c,……全体の重量、杭長及び置換率(盛土層2の横断面方向に沿って置換される軽量土置換杭3a,3b,3c,……の間隔)とによって改良後の盛土層2の盛土荷重が調整され、これによって必要最小限の既設盛土材を軽量土置換杭3a,3b,3c,……に置換することにより沈下発生層1を正規圧密状態にすることができ、また、図2に示す不同沈下の沈下曲線8aは図3に示すように等沈下の沈下曲線8bに矯正され、不同沈下の現象を未然に防止することができる。
In this Example 2, lightweight
図4に、上記実施例1及び2と同様の既設盛土直下の沈下発生層1に対して、本発明の実施例3に係る地盤沈下低減改良工法が適用された例が示されている。
この実施例3においては、上記実施例1及び2とは異なり、盛土層2の表面部分の既設盛土材を取り除き、盛土層2の残り部分について上記実施例1又は2と同様に地盤改良を行うと共に、この地盤改良された盛土層2の残り部分の上部に、取り除いた既設盛土材に対応する軽量土9を敷設してもよく、これによって盛土層2を形成している既設盛土材の全てを取り除くことなく盛土層2直下の地盤沈下低減改良を行うことができる。
FIG. 4 shows an example in which the ground subsidence reduction improvement method according to Example 3 of the present invention is applied to the subsidence generation layer 1 just below the existing embankment similar to Examples 1 and 2.
In this Example 3, unlike the said Example 1 and 2, the existing embankment material of the surface part of the
本発明の地盤沈下低減改良工法によれば、上部に盛土層が造成されてこの既設の盛土層の盛土荷重により圧密沈下が始まり、あるいは、懸念される沈下発生層について、その沈下発生層の圧密沈下を容易にかつ確実に防止することができ、特に大型施工機を搬入して使用することが難しい既設盛土であっても容易に施工できるほか、護岸壁背面側の盛土層を大幅に掘削する必要がなくて工期も制限されず、産業上極めて有用なものである。 According to the ground subsidence reduction improvement method of the present invention, the embankment layer is formed in the upper part, and consolidation settlement begins due to the embankment load of this existing embankment layer, or, for the subsidence generation layer concerned, the consolidation of the subsidence generation layer Settlement can be prevented easily and reliably, and it can be easily constructed even on existing embankments that are difficult to use with large construction machines, and the excavation layer on the back side of the revetment wall is greatly excavated. It is not necessary and the construction period is not limited, and it is extremely useful industrially.
1…沈下発生層(粘性土層)、2…盛土層、3,3a,3b,3c,…軽量土置換杭、4,4a,4b,4c,…孔、5…護岸壁、6…支持杭、7a,7b,7c,…測定ポイント、8a…沈下曲線(不同沈下)、8b…沈下曲線(等沈下)、9…軽量土。
DESCRIPTION OF SYMBOLS 1 ... Subsidence generation layer (viscous soil layer), 2 ... Embankment layer, 3,3a, 3b, 3c, Lightweight soil substitution pile, 4,4a, 4b, 4c, ... Hole, 5 ... Revetment wall, 6 ...
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004166803A JP4423115B2 (en) | 2004-06-04 | 2004-06-04 | An improved method for reducing land subsidence directly under existing embankments |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004166803A JP4423115B2 (en) | 2004-06-04 | 2004-06-04 | An improved method for reducing land subsidence directly under existing embankments |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005344412A JP2005344412A (en) | 2005-12-15 |
JP4423115B2 true JP4423115B2 (en) | 2010-03-03 |
Family
ID=35497048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004166803A Expired - Fee Related JP4423115B2 (en) | 2004-06-04 | 2004-06-04 | An improved method for reducing land subsidence directly under existing embankments |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4423115B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5692840B2 (en) * | 2010-03-26 | 2015-04-01 | 公益財団法人鉄道総合技術研究所 | Pile slab embankment and its construction method |
CN102116028B (en) * | 2011-01-13 | 2012-05-23 | 中建四局第三建筑工程有限公司 | Method and structure for excavating soil in core tube region based on raft pile supporting |
CN111395312A (en) * | 2020-03-23 | 2020-07-10 | 中铁二院工程集团有限责任公司 | Composite light pile structure, manufacturing method, construction method and pile splicing method |
CN113944167B (en) * | 2021-11-23 | 2022-11-18 | 武汉大学 | Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence |
-
2004
- 2004-06-04 JP JP2004166803A patent/JP4423115B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2005344412A (en) | 2005-12-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6166264B2 (en) | How to build a retaining wall | |
CN104264688A (en) | Manual hole digging non-uniform pile support construction technology | |
JP2006225926A (en) | Banking construction method utilizing backfilling material such as fluidized soil, pit sand, local soil and crushed stone | |
CN105714833A (en) | Construction method of steel plate pile open caisson support | |
CN109750571B (en) | Road collapse emergency and permanent retaining integrated structure and construction method | |
CN113174958A (en) | Construction method for foundation pit of adjacent road under poor ground condition | |
JP4423115B2 (en) | An improved method for reducing land subsidence directly under existing embankments | |
JP4987652B2 (en) | Reinforcement structure and method of embankment and linear embankment | |
JP5204063B2 (en) | Box foundation construction method in open shield method | |
CN101748735A (en) | Foundation ditch excavation method for reducing pile deflection in soft soil area | |
JP4982631B2 (en) | Liquefaction countermeasure method under breakwater by underground wall construction | |
JP2005016196A (en) | Construction method for embankment on backside of substructure | |
JPH09100524A (en) | Development method of fill dam | |
KR100948060B1 (en) | Constructing method for arranging river bank using steel casing retaining wall | |
CN213625433U (en) | A link up transition structure that is used for gravity type and sheet pile formula combination pier | |
KR100602839B1 (en) | Method for constructing basement land-side protection wall in civil engineering | |
CN109338909B (en) | Integral pier reinforcing structure and construction method thereof | |
JP6259271B2 (en) | Caisson installation method and underground column body group | |
KR20130015032A (en) | The buoyancy protection device of a steel pipe piles and thereof construction method | |
JP2020159006A (en) | Retaining wall and its construction method | |
KR102690511B1 (en) | Construction method of pile foundation structure and crushed stone column foundation structure | |
JP6298255B2 (en) | Method and jig for preventing floating of underground structure | |
CN108252303A (en) | A kind of tier building basic engineering method based on anchor jacked pile technology | |
KR102625776B1 (en) | Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function | |
CN219992075U (en) | Soft soil roadbed reinforcing structure suitable for highway |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A712 Effective date: 20061110 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070517 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090325 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090714 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090901 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20091201 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20091207 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121211 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4423115 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121211 Year of fee payment: 3 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121211 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20151211 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |