JP4401018B2 - Support hardware to support concrete formwork - Google Patents

Support hardware to support concrete formwork Download PDF

Info

Publication number
JP4401018B2
JP4401018B2 JP2000366220A JP2000366220A JP4401018B2 JP 4401018 B2 JP4401018 B2 JP 4401018B2 JP 2000366220 A JP2000366220 A JP 2000366220A JP 2000366220 A JP2000366220 A JP 2000366220A JP 4401018 B2 JP4401018 B2 JP 4401018B2
Authority
JP
Japan
Prior art keywords
concrete
holding
upper chord
separator
holding member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000366220A
Other languages
Japanese (ja)
Other versions
JP2002167964A (en
Inventor
和晴 森
孝博 島袋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa House Industry Co Ltd
Original Assignee
Daiwa House Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa House Industry Co Ltd filed Critical Daiwa House Industry Co Ltd
Priority to JP2000366220A priority Critical patent/JP4401018B2/en
Publication of JP2002167964A publication Critical patent/JP2002167964A/en
Application granted granted Critical
Publication of JP4401018B2 publication Critical patent/JP4401018B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、コンクリート打設現場で組立施工されるコンクリート型枠を支持するための支持金物に関する。
【0002】
【従来の技術】
建築物の基礎として、鉄筋をベースとしたコンクリート基礎が用いられている。このようなコンクリート基礎を施工するときには、先ず、地盤を掘削して根伐を形成し、必要に応じて根伐の底面に砕石、栗石を敷設し、敷き均しコンクリートを打設する。次に、図14に示すように、ベース筋111、主筋112、スターラップ113等の配筋を行う。そして、これら鉄筋の両側にコンクリート型枠を配置固定し、コンクリート型枠間に形成されるコンクリート打設空間にコンクリートを打設し、コンクリート基礎を構築していた。
【0003】
【発明が解決しようとする課題】
コンクリート型枠としては、例えば図15に示すように、対称に相対峙して並設される型枠120が使用される。型枠120は、上部縦枠121と、下部の拡大底部枠122とからなる。型枠120間には、リブ123が設けられ、リブ123の両端部で型枠120の内壁面に接触して、型枠120間にコンクリートを打設するための間隔を形成している。
【0004】
しかし、上記従来の方法では、コンクリート型枠は、根伐底や栗石、または敷き均しコンクリートの上に直接配置されており、安定して設置することができないという問題があった。また、型枠120の間隔をリブ123によって確保しているのみであるため、コンクリート打設時に、コンクリート0の打設圧力により、リブ123が破損したり、移動したりすることがあり、これにより、型枠120間の間隔が一定に保たれなくなるという問題があった。
【0005】
また、上記のように、鉄筋を使用した基礎の場合、フーチングの主鉄筋や、立上り部の主鉄筋等、多量の鉄筋が必要とされていた。また、これらの鉄筋を、精度良く配金するためには熟練が必要とされ、手間がかかるという問題があった。
【0006】
上記施工方法の他、予めフーチングを設け、フーチングに配筋してある基礎筋を中心にして、フーチング上にコンクリート型枠を立設し、この型枠間にコンクリートを打設して基礎を構築する方法が知られている。
【0007】
このように、予め形成されたフーチング上に型枠を立設することにより、型枠を安定して設置することが可能となる。しかし、上記方法によれば、フーチングと立ち上がり部の成型を別々の工程で行うため、フーチングと立ち上がり部の間にコンクリートの打ち継ぎができてしまうという問題があった。また、フーチングの施工と立ち上がり部の施工が別々に行われるため、手間がかかるとともに、二つの施工期間に渡って設備や人員が必要とされるため、コストの低減が図れなくなるという問題があった。
【0008】
近年では、鉄筋を形鋼に代替した鉄骨構造の基礎が採用されている。鉄骨構造の基礎は、例えば、トラス,箱形鋼,H形鋼からなる鉄骨梁をベースとし、これら鉄骨の回りにコンクリート型枠を立設し、コンクリートを打設してコンクリート基礎を構築するものである。このように、鉄骨構造の基礎とすることにより、工数が減少され、効率的に施工を行うことが可能となる。
【0009】
このため、上記のような鉄骨をベースとした基礎を構築するときに、鉄骨に沿わせて、コンクリート型枠を確実に保持することを可能とする型枠の支持構造が望まれている。
【0010】
また、従来では、基礎鉄筋のかぶり厚さや、基礎巾を確保するために、スペーサドーナツや鋼製丸セパレータ或いは樹脂製のピーコンを受け座としたセパレーターを用いていた。
【0011】
スペーサドーナツは、鉄筋構造の基礎に用いられるものであり、次述するような鉄骨構造の基礎には使用できなかった。また、鋼製丸セパレーターを用いた場合、型枠解体後に、基礎側面部分から鋼製丸セパレータの受け座が露出するため、受け座の露出部分について防錆工事を行う必要があった。また、樹脂製のピーコンを受け座とするセパレーターを使用した場合、立ち上がり部の面からピーコンが露出しないように補修工事を行う必要があり、手間がかかっていた。このため、型枠解体後に補修工事等の要らないセパレーターが望まれている。
【0012】
本発明の目的は、鉄骨造の基礎を施工するときに使用されるコンクリート型枠の支持金物を提供することにある。
【0013】
本発明の他の目的は、根伐底の状態にかかわらず、コンクリート型枠を安定して支持することが可能なコンクリート型枠の支持金物を提供することにある。
【0014】
本発明の他の目的は、予めフーチングを構築しなくても、コンクリート型枠を精度良く配設することが可能なコンクリート型枠の支持金物を提供することにある。
【0015】
本発明の他の目的は、鉄骨梁に簡単に取り付けることができるとともに、種々のコンクリート型枠に対応可能なコンクリート型枠の支持金物を提供することにある。
【0016】
本発明の他の目的は、コンクリート型枠の設置状態を微調整することが可能なコンクリート型枠の支持金物を提供することにある。
【0017】
本発明のさらに他の目的は、型枠解体後に、セパレータ部分の防錆工事や補修工事が不要なコンクリート型枠の支持金物を提供することにある。
【0018】
【課題を解決するための手段】
上記課題は、請求項1に係る本発明によれば、上弦材と下弦材をウェブ材で連結して形成された鉄骨梁を二列に並設し、該二列に並設された鉄骨梁を挟んで立設されるコンクリート型枠を支持する支持金物であって、前記二列に並設された鉄骨梁の上方に位置するセパレーターと、前記二列に並設された鉄骨梁の下弦材にそれぞれ取り付けられる保持部材とを備え、前記保持部材には、前記鉄骨梁の下弦材に取り付けられる取付部と、該取付部よりも外側で前記コンクリート型枠を保持する保持部とが設けられ、前記セパレーターには、前記上弦材の一方に係合される係合片と、前記セパレーターの長手方向に移動可能に設けられ、前記上弦材の他方に止着されて係止される係止部とが設けられ、前記保持部材の保持部に前記コンクリート型枠がそれぞれ載置され、該載置されたコンクリート型枠の間に前記セパレーターが位置するように形成されることにより解決される。
【0020】
上記課題は、請求項2に係る発明によれば、上弦材と下弦材をウェブ材で連結して形成された鉄骨梁を二列に並設し、該二列に並設された鉄骨梁を挟んで立設されるコンクリート型枠を支持する支持金物であって、前記二列に並設された鉄骨梁の上方に位置するセパレーターと、前記上弦材に取り付けられる保持部材とを備え、前記保持部材には、前記二列に並設された鉄骨梁の上弦材の間に位置するとともに前記上弦材に取り付けられる取付部と、該取付部に連続した首部と、該首部の両側で前記コンクリート型枠を保持する一対の保持部とが設けられ、前記保持部材の保持部に前記コンクリート型枠がそれぞれ載置され、該載置されたコンクリート型枠の間に前記セパレーターが位置する、ことにより解決される。
【0021】
なお、前記取付部は、より具体的には、前記二列に並設された鉄骨梁の上弦材に掛け渡されるプレートと、前記首部先端に設けられ前記プレートに接合可能な係止片とを備え、前記プレートと前記係止片とが固着部材により固着された構成とされる。
【0022】
上記課題は、請求項5に係る発明によれば、上弦材と下弦材をウェブ材で連結して形成された鉄骨梁を挟んで立設されるコンクリート型枠を支持する支持金物であって、前記上弦材の上方に位置するセパレーターと、前記上弦材に取り付けられる保持部材とを備え、前記保持部材には、前記上弦材に取り付けられる取付部と、該取付部に連続する首部と、該首部の両側で前記コンクリート型枠を保持する一対の保持部とが設けられ、前記保持部材の保持部に前記コンクリート型枠がそれぞれ載置され、該載置されたコンクリート型枠の間に前記セパレーターが位置する、ことにより解決される。
【0023】
なお、鉄骨梁を二列に並べたダブルラチスを挟んでコンクリート型枠を立設させるときに使用されるセパレータは、前記上弦材の一方に係合される係合片と、前記セパレーターの長手方向に移動可能に設けられ、前記上弦材の他方に止着されて係止される係止部とが設けられた構成とすると好適である。上記構成により、並列する上弦材においてセパレータを確実に固定することが可能となり、立設されたコンクリート型枠について、一定の間隔を開けて確実に保持することが可能となる。
【0024】
また、鉄骨梁をシングルで使用したシングルラチスを挟んでコンクリート型枠を立設させるときに使用されるセパレータについて、前記上弦材に係合される一対の係合片が設けられた構成とすると、上弦材において、セパレータを簡単且つ確実に固定することが可能となる。
【0027】
このように、本発明の支持金物は、剛性の高い鉄骨梁に用いられ、コンクリート型枠を鉄骨梁に沿わせて固定するものである。このとき、第1の保持部と第2の保持部と折曲部とで、コンクリート型枠を確実に保持するように構成されているので、コンクリート打設時にコンクリート型枠が動いたりすることなく、かぶり厚を一定に確保することが可能となる。
【0028】
また、コンクリート型枠は鉄骨梁において保持されるが、鉄骨梁は根伐底に水平に設置されるものであるため、鉄骨梁に保持されたコンクリート型枠の高さレベルは一定に保持される。このため、コンクリート型枠の天端に巾止め金物を確実に取り付けることができ、コンクリート打設時の型枠間の広がりを防止し施工精度を向上させることが可能となる。
【0029】
また、本発明の支持金物はセパレーターと保持部材とからなり、保持部材の取付部を鉄骨梁へ取り付けることにより保持部材を鉄骨梁へ装着することができるように構成されているので、支持金物の設置を、時間をかけることなく簡単に行うことが可能となる。
【0030】
また、本発明の支持金物を使用することにより、支持金物へコンクリート型枠を載置するだけで、コンクリート型枠を精度良く配設することが可能となる。このように、熟練を要することなく、また多くの時間をかけることなく、コンクリート型枠を精度良く設置することが可能となる。
【0031】
また、支持金物は鉄骨梁に後付けで取り付けられるものであるため、コンクリート型枠の種類に合わせた支持金物を使用することにより、どのようなコンクリート型枠を使用しても、コンクリート型枠を確実に保持することができる。さらに、支持金物側で、取付部や保持部の位置や角度等を調整するだけで、所望のかぶり厚さ、型枠の傾きとすることが可能となる。
【0032】
また、本発明の支持金物のセパレーターは、長尺部と、該長尺部の両端部に設けられたモルタル製の受け座とを備えた構成とされているので、基礎が構築された後、コンクリート型枠を解体したときに、受け座が、基礎の立ち上がり部側面と一体となる。このため、従来行っていたような防錆工事や補修工事が必要なくなり、施工効率性を向上させることが可能となる。
【0033】
また、前記受け座は前記長尺部の端部において移動可能に取り付けられているので、受け座の位置を変えるだけで、コンクリート型枠間の距離を簡単に調整することが可能となる。
【0034】
なお、前記保持部材の保持部は、前記鉄骨梁側から前記コンクリート型枠を保持する第1の保持部と、前記コンクリート型枠を外側から保持する第2の保持部とを備え、前記第2の保持部には前記コンクリート型枠側に傾倒可能な折曲部が設けられた構成とされているので、折曲部が折れ曲がることにより、折曲部によりコンクリート型枠のフランジ部が保持され、これにより、コンクリート型枠を確実に保持することが可能となる。
【0035】
また、保持部材に貫通孔を設けた構成とすることにより、打設されたコンクリートが保持部材に邪魔されずにスムーズに流通し、コンクリート型枠間にコンクリートを迅速に充填させることが可能となる。また、前記保持部材を縞鋼板から形成することにより、保持部材へのコンクリートの付着を良くすることが可能となる。
【0036】
【発明の実施の形態】
本例の支持金物Sは、上弦材2と下弦材3をウェブ材4で連結して形成された鉄骨梁1を二列に並設し、この二列に並設された鉄骨梁1を挟んで立設されるコンクリート型枠5を支持するものである。支持金物Sは、セパレーター10と保持部材20とから構成されている。
【0037】
保持部材20は、二列に並設された鉄骨梁1の下弦材3にそれぞれ取り付けられる。保持部材20には、鉄骨梁1の下弦材3に取り付けられる取付部21と、この取付部21よりも外側でコンクリート型枠5を保持する保持部22とが設けられている。
【0038】
下弦材3にそれぞれ保持部材20が取り付けられると、保持部材20の保持部22にコンクリート型枠5がそれぞれ載置され、載置されたコンクリート型枠5の間にセパレーター10が位置して、コンクリート型枠5が支持される。
【0039】
本例の支持金物Sは、上弦材2と下弦材3をウェブ材4で連結して形成された鉄骨梁1を挟んで立設されるコンクリート型枠5を支持するものである。支持金物Sは、セパレーター30と保持部材40とから構成されている。
【0040】
保持部材40には、鉄骨梁1の下弦材3に取り付けられる取付部41と、この取付部41の両側でコンクリート型枠5を保持する保持部42とが設けられている。下弦材3に保持部材40が取り付けられると、保持部材40の保持部42にコンクリート型枠5がそれぞれ載置され、載置されたコンクリート型枠5の間にセパレーター30が位置して、コンクリート型枠5が支持される。
【0041】
本例の支持金物Sは、上弦材2と下弦材3をウェブ材4で連結して形成された鉄骨梁1を二列に並設し、この二列に並設された鉄骨梁1を挟んで立設されるコンクリート型枠5を支持するものである。支持金物Sは、セパレーター10と保持部材50とから構成されている。
【0042】
保持部材50には、二列に並設された鉄骨梁1の上弦材2の間に位置するとともに、上弦材2に取り付けられる取付部51と、取付部51に連続する首部53と、首部53の両側でコンクリート型枠5を保持する一対の保持部52とが設けられている。
【0043】
なお、支持金物Sの取付部51は、二列に並設された鉄骨梁1の上弦材2に掛け渡されるプレート51aと、首部53の先端部に設けられ、プレート51aに接合可能な係止片51bとから構成されている。そして、プレート51aと係止片51bとを固着部材51cにより連結することにより、プレート51aと係合片51bの間において上弦材2の周縁部が挟持され、これにより、上弦材2に保持部材50が装着される。
【0044】
このようにして、上弦材2に保持部材50が取り付けられると、保持部材50の保持部52にコンクリート型枠5がそれぞれ載置され、載置されたコンクリート型枠5の間にセパレーター10が位置して、コンクリート型枠5が支持される。
【0045】
支持金物Sを使用することにより、コンクリート型枠5を、鉄骨梁1の高さの中途位置よりも上方において保持することが可能となる。したがって、支持金物Sは、べた基礎の施工等に好適に用いられる。
【0046】
本例の支持金物Sは、上弦材2と下弦材3をウェブ材4で連結して形成された鉄骨梁1を挟んで立設されるコンクリート型枠5を支持するものである。支持金物Sは、セパレーター30と保持部材60とから構成されている。
【0047】
保持部材60には、上弦材2に取り付けられる取付部61と、この取付部61に連続する首部63と、この首部63の両側でコンクリート型枠5を保持する一対の保持部62とが設けられている。
【0048】
支持金物Sは、取付部61を上弦材2に接合させ、固着部材としてのボルト61c及びナット61dにより取付部61と上弦材2とを連結させることにより、上弦材2に取り付けられる。そして、保持部材60の保持部62にコンクリート型枠5がそれぞれ載置され、載置されたコンクリート型枠5の間にセパレーター30が位置するように構成されている。
【0049】
支持金物Sを使用することにより、コンクリート型枠5を、鉄骨梁1の高さの中途位置よりも上方において保持することが可能となる。したがって、支持金物Sは、べた基礎の施工等に好適に用いられる。
【0050】
上記支持金物S、支持金物Sにおいて、セパレータ10は、上弦材2の一方に係合される係合片11と、セパレーター10の長手方向に移動可能に設けられ、上弦材2の他方に止着されて係止される係止部12とが設けられた構成とすると好適である。
【0051】
本例の係止部12は、係止片12aと蝶ねじ12bからなり、蝶ねじ12bを移動させることにより、係止片12aを上弦材2に押しつけて固定させるように構成されている。
【0052】
上記構成により、並列する上弦材2においてセパレータ10を確実に固定することが可能となり、立設されたコンクリート型枠5について、一定の間隔を開けて確実に保持することが可能となる。
【0053】
また、上記支持金物S、支持金物Sにおいて、セパレータ30は、上弦材2に係合される一対の係合片31が設けられた構成とされている。これにより、上弦材2において、セパレータ30を簡単且つ確実に固定することが可能となる。
【0054】
本例の支持金物Sは、支柱1aと、支柱1aの端部にフランジ部1b,1cを備え、H形またはI形に形成された鉄骨梁1を挟んで立設されるコンクリート型枠5を支持するものである。支持金物Sは、セパレーター70と保持部材80とから構成されている。
【0055】
セパレーター70は、鉄骨梁1の上側のフランジ部1bの上方に位置している。セパレーター70には、上側のフランジ部1bに係合される係合片71が設けられている。また、保持部材80は、下側のフランジ部1cにおいて、支柱1aを挟んで対称に取り付けられる。
【0056】
保持部材80には、鉄骨梁6の下側のフランジ部6cに、固着部材により取り付けられる取付部81と、取付部81よりも外側でコンクリート型枠5を保持する保持部82が設けられている。
【0057】
そして、保持部材80の保持部82に、コンクリート型枠5がそれぞれ載置され、このように載置されたコンクリート型枠5の間に、セパレーター70が位置するように構成されている。
【0058】
本例の支持金物S〜Sを使用することにより、コンクリート型枠5を、根伐底に水平に設置された鉄骨梁1において保持することができるので、根伐底の状態に拘らず、また予めフーチングを作成したりすることなく、2枚のコンクリート型枠5を安定して設置し、天端の高さレベルを一定に保つとともに、隣接するコンクリート型枠を整合させて、精度の良い基礎を構築することが可能となる。
【0059】
本例の支持金物S〜Sにおいて、保持部材20,40,50,60,80の保持部22,42,52,62,82は、鉄骨梁1側からコンクリート型枠5を保持する第1の保持部22a,42a,52a,62a,82aと、コンクリート型枠5を外側から保持する第2の保持部22b,42b,52b,62b,82bとを備え、第2の保持部22b,42b,52b,62b,82bには、コンクリート型枠5側に傾倒可能な折曲部22c,42c,52c,62c,82cが設けられている。
【0060】
従って、コンクリート型枠5を保持部22,42,52,62,82に載置したとき、折曲部22c,42c,52c,62c,82cをハンマー等でコンクリート型枠5側に向けてたたくことにより、第2の保持部22bの先端から、折曲部22cがコンクリート型枠5側へ折れ曲がり、折れ曲がった折曲部22cによりコンクリート型枠5のフランジ部5aが押さえ込まれて、コンクリート型枠5を係止することが可能となる。
【0061】
なお、保持部材20,40,50,60,80に、少なくとも一つの貫通孔22d,42d,52d,62d,82dを設けた構成とすることにより、打設されたコンクリートが保持部材に邪魔されずにスムーズに流通し、コンクリート型枠間にコンクリートを迅速に充填させることが可能となり好適である。また、保持部材20,40,50,60,80を縞鋼板から形成すると、保持部材へのコンクリートの付着を良くすることが可能となり好適である。
【0062】
【実施例】
以下、本発明の一実施例を図面に基づいて説明する。なお、以下に説明する部材,配置等は本発明を限定するものでなく、本発明の趣旨の範囲内で種々改変することができるものである。
【0063】
図1乃至図13は本発明の支持金物S〜Sを示すものであり、図1は支持金物Sの使用状態を示す説明図、図2は支持金物Sを構成するセパレーターの拡大図、図3は支持金物Sの保持部材の拡大図、図4は支持金物Sの使用状態を示す説明図、図5は支持金物Sのセパレーターの拡大図、図6は支持金物Sの保持部材の拡大図、図7は支持金物Sの使用状態を示す説明図、図8は支持金物Sの拡大図、図9は支持金物Sの使用状態を示す説明図、図10は支持金物Sの拡大図、図11は支持金物Sの使用状態を示す説明図、図12は支持金物Sの保持部材の拡大図、図13は折曲部でコンクリート型枠のフランジ部を保持した状態を示す説明図である。
【0064】
本発明に係る支持金物S〜Sは、建築物のコンクリート基礎を形成するときに使用されるものであり、より具体的には、コンクリートを打設するためのコンクリート型枠5を支持するための支持金物である。
【0065】
コンクリート型枠5は、基礎を構築するためのコンクリートを固まらせるときに用いられる枠板であり、木材,合板,鋼板から形成されている。コンクリート型枠5には、コンクリート型枠5を安定して立設できるように、図13に示すように、フランジ部5aが設けられている。
【0066】
本例の支持金物S〜Sは、図1に示すように、二列に並設された鉄骨梁1をベースとする基礎の施工に使用される支持金物Sと、図4に示すように、シングルの鉄骨梁1をベースとする基礎の施工に使用される支持金物Sと、図7に示すように、二列に並設された鉄骨梁1をベースとし、主にべた基礎を施工するときに使用される支持金物Sと、図9に示すように、シングルの鉄骨梁1をベースとし、主にべた基礎を施工するときに使用される支持金物Sと、図11に示すように、H形またはI形の鉄骨梁1をベースとする基礎の施工に使用される支持金物Sとがある。
【0067】
先ず、第1の実施例として、上弦材2と下弦材3とをウェブ材4で連結して形成された鉄骨梁1を向かい合わせにして二列に並設し、このように二列に並設された鉄骨梁1をベースとした基礎の施工に用いられる支持金物Sについて説明する。
【0068】
鉄骨梁1として、本例では、断面略L字状の上弦材2と下弦材3とを、ウェブ材としてのラチス4を介して組み立てたラチス形式の梁が使用される。上弦材2と下弦材3は、それぞれ外側に外角部が向くように配設される。これにより、下弦材3は、立設片3aが外側に位置するように配設される。
【0069】
上記鉄骨梁1は、捨てコンクリートに立設され、水平になるように調整されたベースプレート(図示せず)上に配設される。ベースプレート上では、隣接する鉄骨梁1は、ジョイントプレート(図示せず)により連結される。このように配設された鉄骨梁1を挟んでコンクリート型枠5が立設される。なお、図1の符号7は基礎筋である。
【0070】
コンクリート型枠5は、支持金物の保持部材により支持されて立設されるとともに、支持金物のセパレーターによって、対向するコンクリート型枠5の間に一定の距離が確保される。第1の実施例に係る支持金物Sは、図1で示すように、鉄骨梁1の上方に位置し、鉄骨梁1の上弦材2に係合されるセパレーター10と、鉄骨梁1の下弦材3に装着される一対の保持部材20とから構成されている。
【0071】
セパレーター10は、コンクリート型枠5の間隔を正確に保つものであり、長尺部10aと、この長尺部10aの両端部に設けられた受け座10bとから構成されている。
【0072】
本例のセパレーター10の受け座10bは、モルタルから形成されている。従って、基礎が構築された後、コンクリート型枠5を解体したときに、受け座10bが基礎の立ち上がり部側面と一体となり、従来行っていたような防錆工事や補修工事が必要なくなり、施工効率性を向上させることが可能となる。
【0073】
また、受け座10bは、長尺部10aの端部側に設けられたねじ部10dにおいて移動可能とされており、受け座10bを移動させることにより、コンクリート型枠5間の距離を調整することができるように構成されている。
【0074】
また、セパレーター10は、図2に示すように、一方の上弦材2に係合する係合片11と、セパレータ10の長手方向に摺動可能な係止部12とを備えている。係止部12は、係止片12aと、係止片12aを他方の上弦材2に押しつけて固定させる蝶ねじ12bとを備えている。蝶ねじ12bは、長尺部10a上に設けられたねじ部10cに螺合しており、ねじ部10c上を移動可能に構成されている。
【0075】
セパレーター10の係合片11は、セパレーター10の長尺部10aの中央部よりも、一方の端部側に近い位置に設けられており、対向する鉄骨梁1のうち、一方の鉄骨梁1の上弦材2に係合するように構成されている。
【0076】
係合片11が、一方の鉄骨梁1の上弦材2に係合されたら、次いで、他方の鉄骨梁1の上弦材2に係止片12aを係止させる。そして、蝶ねじ12bを回動させて、蝶ねじ12bを長尺部10aの端部側に向けて移動させる。蝶ねじ12bが移動することにより、蝶ねじ12bに押されて、係止片12aが長尺部10aの端部側に向けて移動する。
【0077】
係止片12aが上弦材2に接触したら、蝶ねじ12bをさらに回動させて、係止片12aを上弦材2に圧接させる。このようにして、一対の鉄骨梁1間において、セパレーター10が固定される。
【0078】
保持部材20は、図3に示すように、鉄骨梁1の下弦材3に取り付けられる取付部21と、コンクリート型枠5を保持する保持部22と、を備えている。取付部21と保持部22とは直交するように構成されている。
【0079】
取付部21は、保持部22に直交する面21aと、この面21aを折り曲げることにより形成される引掛部21bとから構成されている。面21aと引掛部21bとの間は、下弦材3の立設片3aの厚さよりも若干広めの幅が確保され、面21aと引掛部21bとの間に、立設片3aが位置することができるように構成されている。
【0080】
上記引掛部21bを下弦材3の立設片3aに引っ掛け、ハンマー等でたたき込むことにより、取付部21が下弦材3に固定される。このようにして、対向する鉄骨梁1の下弦材3に、それぞれ保持部材20が配設される。
【0081】
保持部材20の保持部22は、保持部材20を下弦材3に配設したときに、下弦材3側に位置する第1の保持部22aと、第1の保持部22aよりも外側に位置する第2の保持部22bとから構成されている。
【0082】
第1の保持部22aと第2の保持部22bの間には、コンクリート型枠5を配設可能となるように、コンクリート型枠5の厚さよりも大きめの間隔xが開けられている。また、第2の保持部22bの先端には、コンクリート型枠5側に傾倒可能な折曲部22cが設けられている。
【0083】
折曲部22cは、保持部22に配設されたコンクリート型枠5を、より確実に保持するためのものである。すなわち、保持部22にコンクリート型枠5が配設されたとき、第2の保持部22bの先端をハンマー等でコンクリート型枠5側に向けてたたくことにより、図13に示すように、第2の保持部22bの先端から、折曲部22cがコンクリート型枠5側へ折れ曲がり、折れ曲がった折曲部22cによりコンクリート型枠5のフランジ部5aが押さえ込まれて、コンクリート型枠5が係止される。
【0084】
本例の保持部材20には、コンクリートを流通させるための貫通孔22dが設けられている。貫通孔22dが設けられていることにより、打ち込まれたコンクリートを均等に行き渡らせることが可能となる。
【0085】
なお、保持部材20は、鉄骨梁1に後付で取り付けられる部材であるため、コンクリート型枠5に合わせて、保持部22の間隔xや、第1の保持部22aや第2の保持部22bの高さ,大きさなどを調整することが可能である。
【0086】
或いは、予め異なる複数種類の保持部材20を用意しておき、施工に使用されるコンクリート型枠5に合わせて最も適した保持部材20を選択するようにしても良い。
【0087】
また、保持部材20の保持部22において、コンクリート型枠5と接する部分22eの角度を変えることにより、コンクリート型枠5を支持する角度を自由に変更することが可能となり、所望の形状の基礎を構築することが可能となる。
【0088】
このように、本例の支持金物Sによれば、支持金物側での調整が可能であるため、様々なタイプのコンクリート型枠に対応することができる。また、支持金物側を調整することにより、構築する基礎の形状を所望の形状に簡単に調整することが可能となる。
【0089】
保持部材20は、二列に並設された鉄骨梁1の下弦材3に、それぞれ複数個ずつ取り付けられる。そして、下弦材3に装着された保持部材20にコンクリート型枠5が載架される。このとき、コンクリート型枠5は、保持部材20の第1の保持部22a,第2の保持部22b,折曲部22cによって下端部を保持されており、また、コンクリート型枠5間の間隔は、セパレーター10により一定に保たれる。
【0090】
さらに、上記のように並設されたコンクリート型枠5の天端に、図1に示すように、巾止め金物6を取り付ける。巾止め金物6は、コンクリートの打設によりコンクリート型枠5間が拡がらないように、コンクリート型枠5の天端側に取り付けられ、コンクリート型枠5の間隔を保持するための保持具である。
【0091】
このようにして、コンクリート型枠5が、二列に並設された鉄骨梁1の両側に立設される。コンクリート型枠5は、水平に調整されたベースプレート上に立設された鉄骨梁1において保持されるので、高さレベルが一定に保たれる。
【0092】
また、コンクリート型枠5は、第1の保持部,第2の保持部,折曲部によって保持されているので、コンクリート打設時にぐらつくことなく、精度の良い基礎を構築することが可能となる。
【0093】
コンクリート型枠5間には、コンクリートCが打設され、このように打設されたコンクリートCが硬化することにより、二列に並設された鉄骨梁1をベースとしたコンクリート基礎が完成する。
【0094】
本例では、支持金物Sにより、鉄骨梁1にコンクリート型枠5が保持されるため、従来のように、予めフーチングを構築しなくても、コンクリート型枠5の高さレベルを一定に保ち、また隣接する型枠同士を整合させながら配設することが可能となる。
【0095】
このため、フーチングと立ち上がり部とを同時に構築することができる。このように、本例の支持金物Sを用いることにより、打ち継ぎがなく、しかも精度の良い基礎を、熟練を要することなく簡単に構築することが可能となる。
【0096】
次に、第2の実施例として、上弦材2と下弦材3とをウェブ材4で連結して形成された鉄骨梁1をシングルで使用し、シングルの鉄骨梁1の両側にコンクリート型枠5を立設させるための支持金物Sについて説明する。
【0097】
鉄骨梁1として、本例では、断面略L字状の上弦材2と下弦材3とを、ウェブ材としてのラチス4を介して組み立てたラチス形式の梁が使用される。鉄骨梁1は、捨てコンクリートに立設され、水平になるように調整されたベースプレート(図示せず)上に配設される。ベースプレート上では、隣接する鉄骨梁1は、ジョイントプレート(図示せず)により連結される。このように配設された鉄骨梁1を挟んでコンクリート型枠5が立設される。
【0098】
第2の実施例に係る支持金物Sは、図4で示すように、鉄骨梁1の上方に位置し、鉄骨梁1の上弦材2に係合されるセパレーター30と、鉄骨梁1の下弦材3に装着される保持部材40とから構成されている。
【0099】
セパレーター30は、コンクリート型枠5の間隔を正確に保つものであり、長尺部30aと、この長尺部30aの両端部に設けられた受け座30bとから構成されている。
【0100】
セパレーター30の受け座30bは、モルタルから形成されている。従って、基礎が構築された後、コンクリート型枠5を解体したときに、受け座30bが基礎の立ち上がり部側面と一体となり、従来行っていたような防錆工事や補修工事が必要なくなり、施工効率性を向上させることが可能となる。
【0101】
また、受け座30bは、長尺部30aの端部側に設けられたねじ部30dにおいて移動可能とされており、受け座30bを移動させることにより、コンクリート型枠5間の距離を調整することができるように構成されている。
【0102】
また、セパレーター30には、図5に示すように、上弦材2を挟持する一対の係合片31が設けられている。本例では、断面略コ字形の部材をセパレーター30に取り付けることにより、係合片31が設けられるように構成されている。
【0103】
セパレーター30を上弦材2に取り付けるときは、係合片31の一方を上弦材2へ係合させ、さらに他方の係合片31の上部をハンマー等でたたき込むことにより、係合片31を上弦材2へ嵌合させる。
【0104】
なお、本例では、係合片31の先端に爪部31aが設けられているので、この爪部31aが上弦材2に引っ掛けられることにより、係合片31が上弦材2から脱落するのを防止することが可能となる。
【0105】
本例の保持部材40は、図6に示すように、鉄骨梁1の下弦材3に取り付けられる取付部41と、コンクリート型枠5を保持する保持部42と、を備えている。本例の保持部材40は、一枚の鋼板を折り曲げ、対向する各面に取付部41と保持部42を設けることにより形成されている。
【0106】
本例の保持部材40は、取付部41の部分が二重に形成されており、確実に下弦材3への取り付けが行われるように構成されている。また、取付部41の両側に位置する保持部42の部分は対向する面が重ならないように形成されている。このように、対向する面が重ならない部分を設けることにより、コンクリートを打設したときに、コンクリートを均等に行き渡らせることが可能となる。
【0107】
取付部41は、取付部本体41aと、溝部41bから構成されている。溝部41bは、下弦材3の立設部3aの厚さよりも若干広めの幅が確保され、溝部41bに、立設片3aが位置することができるように構成されている。
【0108】
上記溝部41bに、下弦材3の立設片3aを位置させ、ハンマー等でたたき込むことにより、取付部41が下弦材3に固定される。このようにして、鉄骨梁1の下弦材3に、保持部材40が配設される。
【0109】
なお、本例では、2種類の溝部41bが設けられており、保持部材40を下弦材3に取り付けるとき、どちらの溝部を使用しても良いように構成されている。このとき、溝部の幅をそれぞれ異なるものとしておけば、立設片3aの厚さが異なる場合でも、別の保持部材を使用することなく対応することができ好適である。
【0110】
保持部材40の保持部42は、取付部41の両側に設けられている。保持部42は、保持部材40を下弦材3に配設したときに、下弦材3側に位置する第1の保持部42aと、第1の保持部42aよりも外側に位置する第2の保持部42bとから構成されている。
【0111】
第1の保持部42aと第2の保持部42bの間には、コンクリート型枠5を配設可能となるように、コンクリート型枠5の厚さよりも大きめの間隔xが開けられている。第2の保持部42bの先端には、コンクリート型枠5側に傾倒可能な折曲部42cが設けられている。
【0112】
折曲部42cは、保持部42に配設されたコンクリート型枠5を、より確実に保持するためのものである。すなわち、保持部42にコンクリート型枠5が配設されたとき、第2の保持部42bの先端をハンマー等でコンクリート型枠5側に向けてたたくことにより、図13に示すように、第2の保持部42bの先端から、折曲部42cがコンクリート型枠5側へ折れ曲がり、折れ曲がった折曲部42cによりコンクリート型枠5のフランジ部5aが押さえ込まれて、コンクリート型枠5が係止される。
【0113】
本例の保持部材42には、コンクリートを流通させるための貫通孔42dが設けられている。貫通孔42dが設けられていることにより、打ち込まれたコンクリートを均等に行き渡らせることが可能となる。
【0114】
なお、保持部材40は、鉄骨梁1に後付で取り付けられる部材であるため、コンクリート型枠5に合わせて、保持部42の間隔xや、第1の保持部42aや第2の保持部42bの高さ,大きさなどを調整することが可能である。
【0115】
或いは、予め異なる複数種類の保持部材40を用意しておき、施工に使用されるコンクリート型枠5に合わせて最も適した保持部材40を選択するようにしても良い。
【0116】
また、保持部材40の保持部22において、コンクリート型枠5と接する部分42eの角度を変えることにより、コンクリート型枠5を支持する角度を自由に変更することが可能となり、所望の形状の基礎を構築することが可能となる。
【0117】
このように、本例の支持金物Sによれば、支持金物側での調整が可能であるため、様々なタイプのコンクリート型枠に対応することができる。また、支持金物側を調整することにより、構築する基礎の形状を所望の形状に簡単に調整することが可能となる。
【0118】
保持部材40は、鉄骨梁1の下弦材3に、複数個取り付けられる。そして、下弦材3に装着された保持部材22にコンクリート型枠5が載架される。このとき、コンクリート型枠5は、保持部材40の第1の保持部42a,第2の保持部42b,折曲部42cによって下端部を保持されており、また、コンクリート型枠5間の間隔は、セパレーター30により一定に保たれる。
【0119】
さらに、上記のように並設されたコンクリート型枠5の天端に、図1に示すように、巾止め金物6を取り付ける。巾止め金物6は、コンクリートの打設によりコンクリート型枠5間が拡がらないように、コンクリート型枠5の天端側に取り付けられ、コンクリート型枠5の間隔を保持するための保持具である。
【0120】
このようにして、コンクリート型枠5が、鉄骨梁1の両側に立設される。コンクリート型枠5は、水平に調整されたベースプレート上に立設された鉄骨梁1において保持されるので、高さレベルが一定に保たれる。
【0121】
また、コンクリート型枠5は、第1の保持部,第2の保持部,折曲部によって保持されているので、コンクリート打設時にぐらつくことなく、精度の良い基礎を構築することが可能となる。
【0122】
コンクリート型枠5間には、コンクリートCが打設され、このように打設されたコンクリートCが硬化することにより、二列に並設された鉄骨梁1をベースとしたコンクリート基礎が完成する。
【0123】
本例では、支持金物Sを用いることにより、鉄骨梁1にコンクリート型枠5が保持されるため、従来のように、予めフーチングを構築しなくても、コンクリート型枠5の高さレベルを一定に保ち、また隣接する型枠同士を整合させながら配設することが可能となる。
【0124】
このため、フーチングと立ち上がり部とを同時に構築することができる。このように、本例の支持金物Sを用いることにより、打ち継ぎがなく、しかも精度の良い基礎を、熟練を要することなく簡単に構築することが可能となる。
【0125】
第3の実施例として、上弦材2と下弦材3とをウェブ材4で連結して形成された鉄骨梁1を向かい合わせにして二列に並設し、このように二列に並設された鉄骨梁1をベースとして、べた基礎を施工するときに用いられる支持金物Sについて説明する。
【0126】
上記鉄骨梁1は、断面略L字状の上弦材2と下弦材3とを、ウェブ材としてのラチス4を介して組み立てたラチス形式の梁であり、上弦材2と下弦材3は、それぞれ外側に外角部が向くように配設される。これにより、下弦材3は、立設片3aが外側に位置するように配設される。
【0127】
上記鉄骨梁1は、捨てコンクリートに立設され、水平になるように調整されたベースプレート(図示せず)上に配設される。ベースプレート上では、隣接する鉄骨梁1は、ジョイントプレート(図示せず)により連結される。このように配設された鉄骨梁1を挟んでコンクリート型枠5が立設される。なお、図7の符号7は基礎筋である。
【0128】
第3の実施例に係る支持金物Sは、図7に示すように、鉄骨梁1の高さの中間位置から上方に向けて、コンクリート型枠5を支持することができるように構成されている。
【0129】
第3の実施例に係る支持金物Sは、図7に示すように、鉄骨梁1の上方に位置し、鉄骨梁1の上弦材2に係合されるセパレーター10と、上弦材2に取り付けられる保持部材50とから構成されている。
【0130】
セパレーター10は、コンクリート型枠5の間隔を正確に保つものであり、長尺部10aと、この長尺部10aの両端部に設けられた受け座10bとから構成されている。また、セパレーター10は、一方の上弦材2に係合する係合片11と、セパレータ10の長手方向に摺動可能な係止部12とを備えている。本例では、第1の実施例におけるセパレーター10と同様の構成のものが使用される。
【0131】
保持部材50は、図8に示すように、二列に並設された鉄骨梁1の上弦材2の間に位置し、上弦材2に係止される取付部51と、取付部51に連続して設けられている首部53と、首部53の両側でコンクリート型枠5を保持する一対の保持部52と、を備えている。
【0132】
取付部51は、二列に並設された鉄骨梁1の上弦材2に掛け渡されるプレート51aと、首部53の先端に形成され、プレート51aに接合可能な係止片51bとから構成されている。プレート51aと係止片51bとは、固着部材としてのボルト51c及びナット51dにより連結される。
【0133】
係止片51bは、図8に示すように、上弦材2の間の隙間よりも長めになるように形成され、両端部が上弦材2に接合するように構成されているので、プレート51aと係止片51bとを固着部材で連結させたときに、プレート51aと係止片51bとで上弦材2の縁部が挟持される。これにより、保持部材50は上弦材2において、脱落しないように確実に固定される。
【0134】
なお、係止部51について、上記のように、プレート51a,ボルト51c,ナット51dを使用しない構成としても良い。例えば、首部53の先端に、上弦材2の縁部に嵌合可能な溝部が設けられた係止片を形成した構成とする。
【0135】
上記係止片を上弦材に取り付けるときは、先ず、上弦材2の間において、上弦材に対して保持部材50が斜めになるようにして位置させ、溝部と上弦材2の縁部の位置を合わせた後、保持部材50を回転させながら、溝部へ上弦材2の縁部を嵌入させる。
【0136】
このような構成とすることにより、プレートや固着部材等の部品が必要でなくなり、部品点数が削減されるとともに、保持部材50を隙間で回転させるだけの簡単な動作で、保持部材50を上弦材2へ固定させることが可能となる。
【0137】
保持部材50の保持部52は、保持部材50を上弦材2に配設したときに、首部53の両側に位置するように構成されている。保持部52は、鉄骨梁1側に位置する第1の保持部52aと、第1の保持部52aよりも外側に位置する第2の保持部52bとから構成されている。
【0138】
第1の保持部52aと第2の保持部52bの間には、コンクリート型枠5を配設可能となるように、コンクリート型枠5の厚さよりも大きめの間隔xが開けられている。また、第2の保持部52bの先端には、コンクリート型枠5側に傾倒可能な折曲部52cが設けられている。
【0139】
折曲部52cは、保持部52に配設されたコンクリート型枠5を、より確実に保持するためのものである。すなわち、保持部52にコンクリート型枠5が配設されたとき、第2の保持部52bの先端をハンマー等でコンクリート型枠5側に向けてたたくことにより、図13に示すように、第2の保持部52bの先端から、折曲部52cがコンクリート型枠5側へ折れ曲がり、折れ曲がった折曲部52cによりコンクリート型枠5のフランジ部5aが押さえ込まれて、コンクリート型枠5が係止される。
【0140】
本例の保持部材52には、コンクリートを流通させるための貫通孔52dが設けられている。貫通孔52dが設けられていることにより、打ち込まれたコンクリートを均等に行き渡らせることが可能となる。
【0141】
なお、保持部材50は、鉄骨梁1に後付で取り付けられる部材であるため、コンクリート型枠5に合わせて、保持部52の間隔xや、第1の保持部52aや第2の保持部52bの高さ,大きさなどを調整することが可能である。
【0142】
或いは、予め異なる複数種類の保持部材50を用意しておき、施工に使用されるコンクリート型枠5に合わせて最も適した保持部材50を選択するようにしても良い。
【0143】
また、保持部材50の保持部52において、コンクリート型枠5と接する部分52eの角度を変えることにより、コンクリート型枠5を支持する角度を自由に変更することが可能となり、所望の形状の基礎を構築することが可能となる。
【0144】
このように、本例の支持金物Sによれば、支持金物側での調整が可能であるため、様々なタイプのコンクリート型枠に対応することができる。また、支持金物側を調整することにより、構築する基礎の形状を所望の形状に簡単に調整することが可能となる。
【0145】
保持部材50は、二列に並設された鉄骨梁1の上弦材2に、複数個取り付けられる。そして、上弦材2に装着された保持部材50にコンクリート型枠5が載架される。このとき、コンクリート型枠5は、保持部材50の第1の保持部52a,第2の保持部52b,折曲部52cによって下端部を保持されており、また、コンクリート型枠5間の間隔は、セパレーター10により一定に保たれる。
【0146】
さらに、上記のように並設されたコンクリート型枠5の天端に、図7に示すように、巾止め金物6を取り付ける。巾止め金物6は、コンクリートの打設によりコンクリート型枠5間が拡がらないように、コンクリート型枠5の天端側に取り付けられ、コンクリート型枠5の間隔を保持するための保持具である。
【0147】
このようにして、コンクリート型枠5が、二列に並設された鉄骨梁1の両側に立設される。コンクリート型枠5は、水平に調整されたベースプレート上に立設された鉄骨梁1において保持されるので、高さレベルが一定に保たれる。
【0148】
また、コンクリート型枠5は、第1の保持部,第2の保持部,折曲部によって保持されているので、コンクリート打設時にぐらつくことなく、精度の良い基礎を構築することが可能となる。
【0149】
コンクリート型枠5間には、コンクリートCが打設され、このように打設されたコンクリートCが硬化することにより、鉄骨梁1をベースとしたコンクリート基礎が完成する。
【0150】
次に、第4の実施例として、上弦材2と下弦材3とをウェブ材4で連結して形成された鉄骨梁1をシングルで使用し、シングルの鉄骨梁1をベースとして、べた基礎を施工するときに用いられる支持金物Sについて説明する。
【0151】
鉄骨梁1として、本例では、断面略L字状の上弦材2と下弦材3とを、ウェブ材としてのラチス4を介して組み立てたラチス形式の梁が使用される。鉄骨梁1は、捨てコンクリートに立設され、水平になるように調整されたベースプレート(図示せず)上に配設される。ベースプレート上では、隣接する鉄骨梁1は、ジョイントプレート(図示せず)により連結される。このように配設された鉄骨梁1を挟んでコンクリート型枠5が立設される。なお、図9の符号7は基礎筋である。
【0152】
第4の実施例に係る支持金物Sは、図9に示すように、鉄骨梁1の高さの中間位置から上方に向けて、コンクリート型枠5を支持することができるように構成されている。
【0153】
第4の実施例に係る支持金物Sは、図9に示すように、鉄骨梁1の上方に位置し、鉄骨梁1の上弦材2に係合されるセパレーター30と、上弦材2に取り付けられる保持部材60とから構成されている。
【0154】
セパレーター30は、コンクリート型枠5の間隔を正確に保つものであり、長尺部30aと、この長尺部30aの両端部に設けられた受け座30bとから構成され、上弦材2を挟持する一対の係合片31が設けられている。本例では、第2の実施例におけるセパレーター30と同様の構成のものが使用される。
【0155】
保持部材60は、図10に示すように、鉄骨梁1の上弦材2に取り付けられる取付部61と、係止部61に連続して設けられている首部63と、首部63の両側でコンクリート型枠5を保持する一対の保持部62と、を備えている。
【0156】
取付部61は、首部63の先端に設けられており、上弦材2に接合可能に形成されている。取付部61は固着部材としてのボルト61c及びナット61dにより、上弦材2に連結されるように構成されている。
【0157】
保持部材60の保持部62は、保持部材60を上弦材2に配設したときに、首部63の両側に位置するように構成されている。保持部62は、鉄骨梁1側に位置する第1の保持部62aと、第1の保持部62aよりも外側に位置する第2の保持部62bとから構成されている。
【0158】
第1の保持部62aと第2の保持部62bの間には、コンクリート型枠5を配設可能となるように、コンクリート型枠5の厚さよりも大きめの間隔xが開けられている。また、第2の保持部62bの先端には、コンクリート型枠5側に傾倒可能な折曲部62cが設けられている。
【0159】
折曲部62cは、保持部62に配設されたコンクリート型枠5を、より確実に保持するためのものである。すなわち、保持部62にコンクリート型枠5が配設されたとき、第2の保持部62bの先端をハンマー等でコンクリート型枠5側に向けてたたくことにより、図13に示すように、第2の保持部62bの先端から、折曲部62cがコンクリート型枠5側へ折れ曲がり、折れ曲がった折曲部62cによりコンクリート型枠5のフランジ部5aが押さえ込まれて、コンクリート型枠5が係止される。
【0160】
本例の保持部材62には、コンクリートを流通させるための貫通孔62dが設けられている。貫通孔62dが設けられていることにより、打ち込まれたコンクリートを均等に行き渡らせることが可能となる。
【0161】
なお、保持部材60は、鉄骨梁1に後付で取り付けられる部材であるため、コンクリート型枠5に合わせて、保持部62の間隔xや、第1の保持部62aや第2の保持部62bの高さ,大きさなどを調整することが可能である。
【0162】
或いは、予め異なる複数種類の保持部材60を用意しておき、施工に使用されるコンクリート型枠5に合わせて最も適した保持部材60を選択するようにしても良い。
【0163】
また、保持部材60の保持部62において、コンクリート型枠5と接する部分62eの角度を変えることにより、コンクリート型枠5を支持する角度を自由に変更することが可能となり、所望の形状の基礎を構築することが可能となる。
【0164】
このように、本例の支持金物Sによれば、支持金物側での調整が可能であるため、様々なタイプのコンクリート型枠に対応することができる。また、支持金物側を調整することにより、構築する基礎の形状を所望の形状に簡単に調整することが可能となる。
【0165】
保持部材60は、鉄骨梁1の上弦材2に、複数個取り付けられる。そして、上弦材2に装着された保持部材60にコンクリート型枠5が載架される。このとき、コンクリート型枠5は、保持部材60の第1の保持部62a,第2の保持部62b,折曲部62cによって下端部を保持されており、また、コンクリート型枠5間の間隔は、セパレーター10により一定に保たれる。
【0166】
さらに、上記のように並設されたコンクリート型枠5の天端に、図9に示すように、巾止め金物6を取り付ける。巾止め金物6は、コンクリートの打設によりコンクリート型枠5間が拡がらないように、コンクリート型枠5の天端側に取り付けられ、コンクリート型枠5の間隔を保持するための保持具である。
【0167】
このようにして、コンクリート型枠5が、鉄骨梁1の両側に立設される。コンクリート型枠5は、水平に調整されたベースプレート上に立設された鉄骨梁1において保持されるので、高さレベルが一定に保たれる。
【0168】
また、コンクリート型枠5は、第1の保持部,第2の保持部,折曲部によって保持されているので、コンクリート打設時にぐらつくことなく、精度の良い基礎を構築することが可能となる。
【0169】
コンクリート型枠5間には、コンクリートCが打設され、このように打設されたコンクリートCが硬化することにより、鉄骨梁1をベースとしたコンクリート基礎が完成する。
【0170】
次に、第5の実施例として、支柱1aと、支柱1aの端部にフランジ部1b,1cを備え、I形に形成された鉄骨梁1をベースとした基礎を施工するときに用いられる支持金物Sについて説明する。
【0171】
鉄骨梁1は、捨てコンクリートに立設され、水平になるように調整されたベースプレート(図示せず)上に配設される。ベースプレート上では、隣接する鉄骨梁1は、ジョイントプレート(図示せず)により連結される。このように配設された鉄骨梁1を挟んでコンクリート型枠5が立設される。
【0172】
第5の実施例に係る支持金物Sは、図11で示すように、鉄骨梁1の上方に位置し、鉄骨梁1の上弦材2に係合されるセパレーター70と、鉄骨梁1の下側のフランジ部1cに装着される一対の保持部材80とから構成されている。
【0173】
セパレーター70は、コンクリート型枠5の間隔を正確に保つものであり、長尺部70aと、この長尺部70aの両端部に設けられた受け座70bとから構成されている。
【0174】
本例のセパレーター70の受け座70bは、モルタルから形成されている。従って、基礎が構築された後、コンクリート型枠5を解体したときに、受け座70bが基礎の立ち上がり部側面と一体となり、従来行っていたような防錆工事や補修工事が必要なくなり、施工効率性を向上させることが可能となる。
【0175】
また、受け座70bは、長尺部70aの端部側に設けられたねじ部(図示せず)において移動可能とされており、受け座70bを移動させることにより、コンクリート型枠5間の距離を調整することができるように構成されている。
【0176】
また、セパレーター70には、図11に示すように、鉄骨梁1の上側のフランジ部1bに係合される係合片71が設けられている。係合片71は、本例のように1つだけ設ける構成の他、一対の係合片71を設け、上側のフランジ部1bの両側に係合片71を係合させた構成としても良い。
【0177】
保持部材80は、図12に示すように、鉄骨梁1の下側のフランジ部1cに取り付けられる取付部81と、コンクリート型枠5を保持する保持部82と、を備えている。取付部81と保持部82は連続して形成されている。
【0178】
取付部81は、下側のフランジ部1cの裏面に接合する面81aと、この面81aの端部側に形成され、フランジ部1cの周縁部に係合する係合部81bとから構成されている。取付部81とフランジ部1cとは、ボルト81c及びナット81dにより連結されている。
【0179】
保持部材80の保持部82は、保持部材80をフランジ部1cに配設したときに、鉄骨梁1側に位置する第1の保持部82aと、第1の保持部82aよりも外側に位置する第2の保持部82bとから構成されている。
【0180】
第1の保持部82aと第2の保持部82bの間には、コンクリート型枠5を配設可能となるように、コンクリート型枠5の厚さよりも大きめの間隔xが開けられている。また、第2の保持部82bの先端には、コンクリート型枠5側に傾倒可能な折曲部82cが設けられている。
【0181】
折曲部82cは、保持部82に配設されたコンクリート型枠5を、より確実に保持するためのものである。すなわち、保持部82にコンクリート型枠5が配設されたとき、第2の保持部82bの先端をハンマー等でコンクリート型枠5側に向けてたたくことにより、図13に示すように、第2の保持部82bの先端から、折曲部82cがコンクリート型枠5側へ折れ曲がり、折れ曲がった折曲部82cによりコンクリート型枠5のフランジ部5aが押さえ込まれて、コンクリート型枠5が係止される。
【0182】
本例の保持部材82には、コンクリートを流通させるための貫通孔82dが設けられている。貫通孔82dが設けられていることにより、打ち込まれたコンクリートを均等に行き渡らせることが可能となる。
【0183】
なお、保持部材80は、鉄骨梁1に後付で取り付けられる部材であるため、コンクリート型枠5に合わせて、保持部82の間隔xや、第1の保持部82aや第2の保持部82bの高さ,大きさなどを調整することが可能である。
【0184】
或いは、予め異なる複数種類の保持部材80を用意しておき、施工に使用されるコンクリート型枠5に合わせて最も適した保持部材80を選択するようにしても良い。
【0185】
また、保持部材80の保持部82において、コンクリート型枠5と接する部分82eの角度を変えることにより、コンクリート型枠5を支持する角度を自由に変更することが可能となり、所望の形状の基礎を構築することが可能となる。
【0186】
このように、本例の支持金物Sによれば、支持金物側での調整が可能であるため、様々なタイプのコンクリート型枠に対応することができる。また、支持金物側を調整することにより、構築する基礎の形状を所望の形状に簡単に調整することが可能となる。
【0187】
保持部材80は、下側のフランジ部1cにおいて、鉄骨梁1の支柱1aを挟んで対向して取り付けられる。保持部材80は、フランジ部1cのそれぞれの側において複数個ずつ取り付けられる。そして、フランジ部1cに装着された保持部材82にコンクリート型枠5が載架される。このとき、コンクリート型枠5は、保持部材80の第1の保持部82a,第2の保持部82b,折曲部82cによって下端部を保持されており、また、コンクリート型枠5間の間隔は、セパレーター10により一定に保たれる。
【0188】
さらに、上記のように並設されたコンクリート型枠5の天端に、図11に示すように、巾止め金物6を取り付ける。巾止め金物6は、コンクリートの打設によりコンクリート型枠5間が拡がらないように、コンクリート型枠5の天端側に取り付けられ、コンクリート型枠5の間隔を保持するための保持具である。
【0189】
このようにして、コンクリート型枠5が、I形の鉄骨梁1の両側に立設される。コンクリート型枠5は、水平に調整されたベースプレート上に立設された鉄骨梁1において保持されるので、高さレベルが一定に保たれる。
【0190】
また、コンクリート型枠5は、第1の保持部,第2の保持部,折曲部によって保持されているので、コンクリート打設時にぐらつくことなく、精度の良い基礎を構築することが可能となる。
【0191】
コンクリート型枠5間には、コンクリートCが打設され、このように打設されたコンクリートCが硬化することにより、鉄骨梁1をベースとしたコンクリート基礎が完成する。
【0192】
本例では、支持金物Sにより、鉄骨梁1にコンクリート型枠5が保持されるため、従来のように、予めフーチングを構築しなくても、コンクリート型枠5の高さレベルを一定に保ち、また隣接する型枠同士を整合させながら配設することが可能となる。
【0193】
このため、フーチングと立ち上がり部とを同時に構築することができる。このように、本例の支持金物Sを用いることにより、打ち継ぎがなく、しかも精度の良い基礎を、熟練を要することなく簡単に構築することが可能となる。
【0194】
なお、上記第1の実施例乃至第5の実施例において、保持部材20,40,50,60,80を縞鋼板から形成すると、保持部材へのコンクリートの付きを良くすることが可能となり好適である。
【0195】
【発明の効果】
以上のように、本発明に係る支持金物は、剛性の高い鉄骨梁に用いられ、コンクリート型枠を鉄骨梁に沿わせて固定するものである。このとき、第1の保持部と第2の保持部と折曲部とでコンクリート型枠を確実に保持するように構成されているので、コンクリート打設時にコンクリート型枠が動いたりすることなく、コンクリートのかぶり厚を一定に確保することが可能となる。
【0196】
また、コンクリート型枠は鉄骨梁において保持されるが、鉄骨梁は根伐底に水平に設置されるものであるため、鉄骨梁に保持されたコンクリート型枠の高さレベルは一定に保持される。このため、コンクリート型枠の天端に巾止め金物を確実に取り付けることができ、コンクリート打設時の型枠間の広がりを防止し施工精度を向上させることが可能となる。
【0197】
また、本発明の支持金物はセパレーターと保持部材とからなり、保持部材の取付部を鉄骨梁へ取り付けることにより保持部材を鉄骨梁へ装着することができるように構成されているので、支持金物の設置を、時間をかけることなく簡単に行うことが可能となる。
【0198】
また、本発明の支持金物を使用することにより、支持金物へコンクリート型枠を載置するだけで、コンクリート型枠を精度良く配設することが可能となる。このように、熟練を要することなく、また多くの時間をかけることなく、コンクリート型枠を精度良く設置することが可能となる。
【0199】
また、支持金物は鉄骨梁に後付けで取り付けられるものであるため、コンクリート型枠の種類に合わせた支持金物を使用することにより、どのようなコンクリート型枠を使用しても、コンクリート型枠を確実に保持することができる。さらに、支持金物側で、取付部や保持部の位置や角度等を調整するだけで、所望のかぶり厚さ、型枠の傾きとすることが可能となる。
【0200】
また、本発明のセパレーターの受け座は、モルタルから形成されている。従って、基礎が構築された後、コンクリート型枠を解体したときに、受け座が基礎の立ち上がり部側面と一体となり、従来行っていたような防錆工事や補修工事が必要なくなり、施工効率性を向上させることが可能となる。
【0201】
また、前記受け座は前記長尺部の端部において移動可能に取り付けられているので、受け座の位置を変えるだけで、コンクリート型枠間の距離を簡単に調整することが可能となる。
【図面の簡単な説明】
【図1】支持金物Sの使用状態を示す説明図である。
【図2】支持金物Sのセパレーターの拡大図である。
【図3】支持金物Sの保持部材の拡大図である。
【図4】支持金物Sの使用状態を示す説明図である。
【図5】支持金物Sのセパレーターの拡大図である。
【図6】支持金物Sの保持部材の拡大図である。
【図7】支持金物Sの使用状態を示す説明図である。
【図8】支持金物Sの拡大図である。
【図9】支持金物Sの使用状態を示す説明図である。
【図10】支持金物Sの拡大図である。
【図11】支持金物Sの使用状態を示す説明図である。
【図12】支持金物Sの保持部材の拡大図である。
【図13】折曲部でコンクリート型枠のフランジ部を保持した状態を示す説明図である。
【図14】従来例を示す説明図である。
【図15】従来例を示す説明図である。
【符号の説明】
1 鉄骨梁
2 上弦材
3 下弦材
4 ウェブ材
5 コンクリート型枠
5a フランジ部
6 巾止め金物
7 基礎筋
10,30,70 セパレーター
11,31,71 係合片
12 係止部
12a 係止片
12b 蝶ねじ
20,40,50,60,80 保持部材
21,41,51,61,81 取付部
22,42,52,62,82 保持部
22a,42a,52a,62a,82a 第1の保持部
22b,42b,52b,62b,82b 第2の保持部
22c,42c,52c,62c,82c 折曲部
22d,42d,52d,62d,82d 貫通孔
C コンクリート
,S,S,S,S 支持金物
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a support hardware for supporting a concrete formwork assembled and constructed at a concrete placing site.
[0002]
[Prior art]
A concrete foundation based on steel bars is used as the foundation of the building. When constructing such a concrete foundation, first, the ground is excavated to form root cutting, and if necessary, crushed stones and chestnuts are laid on the bottom surface of the root cutting, and then leveled concrete is placed. Next, as shown in FIG. 14, the reinforcement of the base muscle 111, the main muscle 112, the stirrup 113, and the like is performed. Then, concrete molds are arranged and fixed on both sides of these reinforcing bars, and concrete is placed in a concrete placement space formed between the concrete molds to construct a concrete foundation.
[0003]
[Problems to be solved by the invention]
As the concrete formwork, for example, as shown in FIG. 15, a formwork 120 arranged in parallel symmetrically with respect to each other is used. The mold 120 includes an upper vertical frame 121 and a lower enlarged bottom frame 122. Ribs 123 are provided between the molds 120, and the both ends of the ribs 123 come into contact with the inner wall surface of the mold 120 to form a space for placing concrete between the molds 120.
[0004]
However, the conventional method has a problem that the concrete formwork is disposed directly on the bottom of the root, the chestnut, or the leveling concrete, and cannot be stably installed. Moreover, since the space | interval of the formwork 120 is only ensured by the rib 123, at the time of concrete placement, the rib 123 may be damaged or moved by the placement pressure of the concrete 0. There is a problem that the interval between the molds 120 cannot be kept constant.
[0005]
In addition, as described above, in the case of a foundation using a reinforcing bar, a large amount of reinforcing bars such as a main reinforcing bar for a footing and a main reinforcing bar for a rising portion are required. Moreover, in order to distribute these rebars with high accuracy, skill is required, and there is a problem that it takes time and effort.
[0006]
In addition to the above construction method, a footing is provided in advance, a concrete formwork is erected on the footing, centering on the foundation reinforcement placed in the footing, and the foundation is constructed by placing concrete between the formwork How to do is known.
[0007]
In this way, by standing the mold on the preformed footing, the mold can be stably installed. However, according to the above method, since the footing and the rising portion are molded in separate steps, there is a problem in that the concrete can be joined between the footing and the rising portion. In addition, the construction of the footing and the construction of the rising part are performed separately, which is troublesome and requires equipment and personnel over two construction periods, resulting in a problem that the cost cannot be reduced. .
[0008]
In recent years, the foundation of the steel structure which replaced the reinforcing bar with the shape steel is adopted. The foundation of the steel structure is based on, for example, a steel beam made of truss, box-shaped steel, and H-shaped steel. A concrete form is set up around these steel frames, and concrete is placed to construct a concrete foundation. It is. Thus, by using it as the foundation of a steel structure, man-hours are reduced and it becomes possible to perform construction efficiently.
[0009]
For this reason, when constructing a foundation based on a steel frame as described above, there is a demand for a formwork support structure that can securely hold the concrete formwork along the steel frame.
[0010]
Conventionally, a spacer donut, a steel round separator, or a separator with a resin pearcon as a seat has been used to secure the cover thickness of the foundation rebar and the foundation width.
[0011]
The spacer donut is used for the foundation of a reinforcing bar structure, and cannot be used for the foundation of a steel structure as described below. In addition, when a steel round separator is used, the steel seats of the steel round separator are exposed from the side of the foundation after the mold is dismantled, so that it is necessary to perform rust prevention work on the exposed portions of the seats. Also, when using a separator made of resin-made pearcon, it was necessary to perform repair work so that the peekon was not exposed from the surface of the rising part, which was troublesome. For this reason, a separator that does not require repair work after dismantling the formwork is desired.
[0012]
An object of the present invention is to provide a supporting metal support for a concrete mold used when constructing a steel structure foundation.
[0013]
Another object of the present invention is to provide a support for a concrete mold that can stably support the concrete mold regardless of the state of the bottom of the bottom.
[0014]
Another object of the present invention is to provide a supporting metal support for a concrete mold capable of arranging a concrete mold with high accuracy without constructing a footing in advance.
[0015]
Another object of the present invention is to provide a support metal fixture for a concrete mold that can be easily attached to a steel beam and can be used for various concrete molds.
[0016]
Another object of the present invention is to provide a concrete mold supporting metal capable of finely adjusting the installation state of the concrete mold.
[0017]
Still another object of the present invention is to provide a support for a concrete mold that does not require a rust prevention work or a repair work for the separator after the mold is disassembled.
[0018]
[Means for Solving the Problems]
According to the first aspect of the present invention, the steel beam formed by connecting the upper chord material and the lower chord material with the web material is arranged in two rows in parallel, and the steel beam arranged in parallel in the two rows A support metal that supports a concrete form erected on both sides of the separator, the separator positioned above the steel beams arranged in two rows, and the lower chord material of the steel beams arranged in two rows A holding member attached to each of the lower chord members of the steel beam, and a holding portion for holding the concrete formwork outside the attaching portion. The separator includes an engagement piece that is engaged with one of the upper chord members, and a locking portion that is provided so as to be movable in the longitudinal direction of the separator and is fixed to the other of the upper chord members. Is provided, This is solved by placing the concrete molds on the holding parts of the holding members and forming the separators between the placed concrete molds.
[0020]
The above issues Claim 2 According to the invention, the steel beams formed by connecting the upper chord material and the lower chord material with the web material are arranged in two rows, and the concrete is erected with the steel beams arranged in two rows in between. A metal support for supporting the formwork, comprising a separator positioned above the steel beam arranged in two rows, and a holding member attached to the upper chord material, the holding member having the two rows A pair of holding members that are located between the upper chord members of the steel beam arranged side by side and are attached to the upper chord member, a neck portion that is continuous with the attaching portion, and the concrete formwork that is held on both sides of the neck portion. And the concrete mold is placed on the holding part of the holding member, and the separator is positioned between the placed concrete molds.
[0021]
More specifically, the mounting portion includes a plate that is stretched over the upper chord material of the steel beam arranged in parallel in the two rows, and a locking piece that is provided at the tip of the neck portion and can be joined to the plate. And the plate and the locking piece are fixed by a fixing member.
[0022]
According to the invention according to claim 5, the above-mentioned problem is a support hardware for supporting a concrete mold erected with a steel beam formed by connecting an upper chord material and a lower chord material with a web material, A separator positioned above the upper chord material; and a holding member attached to the upper chord material. The holding member includes an attachment portion attached to the upper chord material, a neck portion continuous to the attachment portion, and the neck portion A pair of holding portions for holding the concrete formwork on both sides thereof, the concrete formwork is respectively placed on the holding portions of the holding member, and the separator is interposed between the placed concrete formwork It is solved by being located.
[0023]
In addition, the separator used when the concrete formwork is erected with the double lattice in which the steel beams are arranged in two rows, the engagement piece engaged with one of the upper chord members, and the longitudinal direction of the separator It is preferable to have a structure provided with a locking portion that is provided so as to be movable and is fixed to the other of the upper chord members. With the above configuration, it is possible to reliably fix the separator on the parallel upper chord material, and it is possible to reliably hold the standing concrete form with a certain interval.
[0024]
In addition, with respect to the separator used when the concrete formwork is erected with a single lattice using a steel beam as a single piece, with a configuration provided with a pair of engagement pieces to be engaged with the upper chord material, In the upper chord material, the separator can be easily and reliably fixed.
[0027]
As described above, the support hardware of the present invention is used for a highly rigid steel beam, and fixes a concrete mold along the steel beam. At this time, the first holding part, the second holding part, and the bent part are configured to securely hold the concrete formwork, so that the concrete formwork does not move when placing concrete. It is possible to ensure a constant cover thickness.
[0028]
In addition, although the concrete formwork is held in the steel beam, the height level of the concrete formwork held in the steel beam is kept constant because the steel beam is installed horizontally on the bottom of the bottom. . For this reason, it is possible to securely attach the width stop hardware to the top end of the concrete mold, and prevent the spread between the molds at the time of placing the concrete and improve the construction accuracy.
[0029]
In addition, the support hardware of the present invention includes a separator and a holding member, and is configured so that the holding member can be attached to the steel beam by attaching the attachment portion of the holding member to the steel beam. Installation can be easily performed without taking time.
[0030]
Further, by using the support metal of the present invention, it is possible to arrange the concrete mold with high accuracy simply by placing the concrete mold on the support metal. In this way, the concrete formwork can be accurately installed without requiring skill and without taking much time.
[0031]
In addition, since the support hardware is attached to the steel beam retrofitting, the concrete formwork can be reliably secured regardless of the concrete formwork used by using the support hardware that matches the type of concrete formwork. Can be held in. Furthermore, it is possible to obtain the desired cover thickness and the inclination of the formwork only by adjusting the position and angle of the mounting portion and the holding portion on the support hardware side.
[0032]
Moreover, since the separator of the support hardware of the present invention is configured to include a long portion and a mortar seat provided at both ends of the long portion, after the foundation is constructed, When the concrete formwork is dismantled, the receiving seat is integrated with the side of the rising portion of the foundation. For this reason, the rust prevention work and repair work which were performed conventionally become unnecessary, and it becomes possible to improve construction efficiency.
[0033]
In addition, since the receiving seat is movably attached at the end of the elongated portion, it is possible to easily adjust the distance between the concrete molds by simply changing the position of the receiving seat.
[0034]
The holding portion of the holding member includes a first holding portion that holds the concrete formwork from the steel beam side, and a second holding portion that holds the concrete formwork from the outside. Since the holding part is configured to be provided with a bendable portion that can be tilted toward the concrete mold side, the bent part is bent, whereby the flange part of the concrete formwork is held by the bent part, Thereby, it becomes possible to hold | maintain a concrete formwork reliably.
[0035]
Further, by adopting a structure in which the through hole is provided in the holding member, the placed concrete can smoothly flow without being disturbed by the holding member, and the concrete can be quickly filled between the concrete molds. . Further, by forming the holding member from a striped steel plate, it is possible to improve the adhesion of concrete to the holding member.
[0036]
DETAILED DESCRIPTION OF THE INVENTION
Supporting hardware S of this example 1 Is a concrete structure in which steel beams 1 formed by connecting the upper chord material 2 and the lower chord material 3 with a web material 4 are arranged in two rows, and the steel beams 1 arranged in two rows are sandwiched between them. The mold 5 is supported. Support hardware S 1 Is composed of a separator 10 and a holding member 20.
[0037]
The holding members 20 are respectively attached to the lower chord members 3 of the steel beam 1 arranged in two rows. The holding member 20 is provided with an attachment portion 21 that is attached to the lower chord member 3 of the steel beam 1 and a holding portion 22 that holds the concrete formwork 5 outside the attachment portion 21.
[0038]
When the holding members 20 are attached to the lower chord members 3, the concrete molds 5 are respectively placed on the holding portions 22 of the holding members 20, and the separator 10 is positioned between the placed concrete molds 5. The formwork 5 is supported.
[0039]
Supporting hardware S of this example 2 Is for supporting a concrete formwork 5 erected with a steel beam 1 formed by connecting an upper chord member 2 and a lower chord member 3 with a web member 4. Support hardware S 2 Consists of a separator 30 and a holding member 40.
[0040]
The holding member 40 is provided with a mounting portion 41 that is attached to the lower chord material 3 of the steel beam 1 and holding portions 42 that hold the concrete formwork 5 on both sides of the mounting portion 41. When the holding member 40 is attached to the lower chord material 3, the concrete mold 5 is placed on the holding portion 42 of the holding member 40, and the separator 30 is positioned between the placed concrete molds 5. The frame 5 is supported.
[0041]
Supporting hardware S of this example 3 Is a concrete structure in which steel beams 1 formed by connecting the upper chord material 2 and the lower chord material 3 with a web material 4 are arranged in two rows, and the steel beams 1 arranged in two rows are sandwiched between them. The mold 5 is supported. Support hardware S 3 Is composed of a separator 10 and a holding member 50.
[0042]
The holding member 50 is located between the upper chord members 2 of the steel beams 1 arranged in two rows, and has a mounting portion 51 attached to the upper chord member 2, a neck portion 53 continuous to the mounting portion 51, and a neck portion 53. A pair of holding portions 52 for holding the concrete mold 5 is provided on both sides of the frame.
[0043]
Supporting hardware S 3 The mounting portion 51 is composed of a plate 51a that is stretched over the upper chord material 2 of the steel beam 1 arranged in two rows, and a locking piece 51b that is provided at the tip of the neck portion 53 and can be joined to the plate 51a. Has been. Then, by connecting the plate 51a and the locking piece 51b by the fixing member 51c, the peripheral edge portion of the upper chord material 2 is sandwiched between the plate 51a and the engaging piece 51b, whereby the holding member 50 is held on the upper chord material 2. Is installed.
[0044]
In this way, when the holding member 50 is attached to the upper chord material 2, the concrete mold 5 is placed on the holding portion 52 of the holding member 50, and the separator 10 is positioned between the placed concrete molds 5. Thus, the concrete mold 5 is supported.
[0045]
Support hardware S 3 It becomes possible to hold | maintain the concrete formwork 5 above the middle position of the height of the steel beam 1 by using. Therefore, the support hardware S 3 Is suitable for construction of solid foundations.
[0046]
Supporting hardware S of this example 4 Is for supporting a concrete formwork 5 erected with a steel beam 1 formed by connecting an upper chord member 2 and a lower chord member 3 with a web member 4. Support hardware S 4 Is composed of a separator 30 and a holding member 60.
[0047]
The holding member 60 is provided with an attachment portion 61 attached to the upper chord material 2, a neck portion 63 continuous with the attachment portion 61, and a pair of holding portions 62 that hold the concrete mold 5 on both sides of the neck portion 63. ing.
[0048]
Support hardware S 4 Is attached to the upper chord material 2 by joining the attachment portion 61 to the upper chord material 2 and connecting the attachment portion 61 and the upper chord material 2 by bolts 61c and nuts 61d as fixing members. And the concrete formwork 5 is each mounted in the holding | maintenance part 62 of the holding member 60, and it is comprised so that the separator 30 may be located between the placed concrete formwork 5. FIG.
[0049]
Support hardware S 4 It becomes possible to hold | maintain the concrete formwork 5 above the middle position of the height of the steel beam 1 by using. Therefore, the support hardware S 4 Is suitable for construction of solid foundations.
[0050]
Supporting hardware S 1 , Support hardware S 3 The separator 10 is provided with an engagement piece 11 that is engaged with one of the upper chord members 2, and is provided so as to be movable in the longitudinal direction of the separator 10. It is preferable that the portion 12 is provided.
[0051]
The locking portion 12 of this example includes a locking piece 12a and a butterfly screw 12b, and is configured to press the locking piece 12a against the upper chord material 2 and fix it by moving the butterfly screw 12b.
[0052]
With the above configuration, the separator 10 can be reliably fixed in the parallel upper chord material 2, and the standing concrete mold 5 can be reliably held at a certain interval.
[0053]
Also, the support hardware S 2 , Support hardware S 4 The separator 30 has a configuration in which a pair of engagement pieces 31 to be engaged with the upper chord material 2 are provided. Thereby, in the upper chord material 2, it becomes possible to fix the separator 30 easily and reliably.
[0054]
Supporting hardware S of this example 5 Is provided with flanges 1b and 1c at the ends of the pillar 1a and the end of the pillar 1a, and supports the concrete form 5 that is erected with the steel beam 1 formed in an H shape or an I shape in between. Support hardware S 5 Is composed of a separator 70 and a holding member 80.
[0055]
The separator 70 is located above the upper flange portion 1 b of the steel beam 1. The separator 70 is provided with an engagement piece 71 that is engaged with the upper flange portion 1b. In addition, the holding member 80 is attached symmetrically with the support column 1a sandwiched in the lower flange portion 1c.
[0056]
The holding member 80 is provided with a mounting portion 81 attached to the lower flange portion 6c of the steel beam 6 by a fixing member and a holding portion 82 for holding the concrete mold 5 outside the mounting portion 81. .
[0057]
The concrete mold 5 is placed on the holding portion 82 of the holding member 80, and the separator 70 is positioned between the concrete mold 5 thus placed.
[0058]
Supporting hardware S of this example 1 ~ S 5 Since the concrete formwork 5 can be held in the steel beam 1 installed horizontally on the bottom of the root cutting, the footing can be created in advance regardless of the state of the root bottom. In addition, it is possible to stably install the two concrete molds 5 to keep the height level at the top constant, and to align the adjacent concrete molds to construct a high-precision foundation. .
[0059]
Supporting hardware S of this example 1 ~ S 5 , The holding portions 22, 42, 52, 62, 82 of the holding members 20, 40, 50, 60, 80 are the first holding portions 22a, 42a, 52a, which hold the concrete formwork 5 from the steel beam 1 side. 62a, 82a and second holding portions 22b, 42b, 52b, 62b, 82b for holding the concrete mold 5 from the outside. The second holding portions 22b, 42b, 52b, 62b, 82b include concrete. Bending portions 22c, 42c, 52c, 62c, and 82c that can be tilted are provided on the mold 5 side.
[0060]
Therefore, when the concrete mold 5 is placed on the holding portions 22, 42, 52, 62, 82, the bent portions 22c, 42c, 52c, 62c, 82c are hit with the hammer or the like toward the concrete mold 5 side. Accordingly, the bent portion 22c is bent toward the concrete mold 5 from the tip of the second holding portion 22b, and the flange portion 5a of the concrete mold 5 is pressed by the bent portion 22c, whereby the concrete mold 5 is It becomes possible to lock.
[0061]
The holding member 20, 40, 50, 60, 80 is provided with at least one through hole 22d, 42d, 52d, 62d, 82d, so that the placed concrete is not obstructed by the holding member. It is possible to smoothly circulate and quickly fill the concrete between the concrete molds. Further, if the holding members 20, 40, 50, 60, 80 are formed of a striped steel plate, it is possible to improve the adhesion of concrete to the holding member.
[0062]
【Example】
Hereinafter, an embodiment of the present invention will be described with reference to the drawings. The members, arrangements, and the like described below are not intended to limit the present invention and can be variously modified within the scope of the gist of the present invention.
[0063]
1 to 13 show the support metal S of the present invention. 1 ~ S 5 FIG. 1 shows the support hardware S. 1 FIG. 2 is an explanatory view showing the usage state of the support metal S 1 FIG. 3 is an enlarged view of the separator constituting the metal support S 1 4 is an enlarged view of the holding member of FIG. 2 FIG. 5 is an explanatory view showing the use state of the support metal S 2 6 is an enlarged view of the separator of FIG. 2 7 is an enlarged view of the holding member of FIG. 3 FIG. 8 is an explanatory view showing the use state of the support metal S 3 Fig. 9 is an enlarged view of the support hardware S 4 FIG. 10 is a diagram illustrating the use state of the support metal S 4 Fig. 11 is an enlarged view of the support hardware S 5 FIG. 12 is an explanatory view showing the use state of the support metal S 5 FIG. 13 is an explanatory view showing a state in which the flange portion of the concrete mold is held at the bent portion.
[0064]
Supporting hardware S according to the present invention 1 ~ S 5 Is used when forming a concrete foundation of a building, and more specifically, is a support hardware for supporting a concrete formwork 5 for placing concrete.
[0065]
The concrete formwork 5 is a frame board used when the concrete for constructing the foundation is hardened, and is formed from wood, plywood, and steel sheet. As shown in FIG. 13, the concrete mold 5 is provided with a flange portion 5a so that the concrete mold 5 can be stably erected.
[0066]
Supporting hardware S of this example 1 ~ S 5 As shown in FIG. 1, the supporting hardware S used for the construction of the foundation based on the steel beam 1 arranged in two rows is arranged. 1 As shown in FIG. 4, the supporting hardware S used for the construction of the foundation based on the single steel beam 1 is used. 2 And, as shown in FIG. 7, the support hardware S used mainly for constructing a solid foundation based on the steel beam 1 arranged in two rows as a base. 3 As shown in FIG. 9, the support metal S used mainly when constructing a solid foundation is based on a single steel beam 1. 4 As shown in FIG. 11, a supporting hardware S used for the construction of a foundation based on an H-shaped or I-shaped steel beam 1 is used. 5 There is.
[0067]
First, as a first embodiment, the steel beam 1 formed by connecting the upper chord member 2 and the lower chord member 3 with the web member 4 is arranged in two rows in parallel, and in this way in two rows. Supporting hardware S used for the foundation construction based on the installed steel beam 1 1 Will be described.
[0068]
In this example, a lattice-type beam in which an upper chord member 2 and a lower chord member 3 having a substantially L-shaped cross section are assembled via a lattice 4 as a web member is used as the steel beam 1. The upper chord member 2 and the lower chord member 3 are arranged so that the outer corners face outward. Thereby, the lower chord material 3 is arrange | positioned so that the standing piece 3a may be located in the outer side.
[0069]
The steel beam 1 is disposed on a base plate (not shown) that is erected on discarded concrete and adjusted to be horizontal. On the base plate, adjacent steel beams 1 are connected by a joint plate (not shown). A concrete mold 5 is erected with the steel beam 1 arranged in this manner interposed therebetween. In addition, the code | symbol 7 of FIG. 1 is a basic streak.
[0070]
The concrete mold 5 is erected while being supported by a support metal holding member, and a certain distance is secured between the opposing concrete molds 5 by the separator of the support metal. Support hardware S according to the first embodiment 1 As shown in FIG. 1, the separator 10 is located above the steel beam 1 and engaged with the upper chord material 2 of the steel beam 1, and the pair of holding members 20 attached to the lower chord material 3 of the steel beam 1. It is composed of.
[0071]
The separator 10 accurately keeps the interval between the concrete molds 5, and includes a long portion 10 a and receiving seats 10 b provided at both ends of the long portion 10 a.
[0072]
The seat 10b of the separator 10 of this example is formed from mortar. Accordingly, when the concrete formwork 5 is disassembled after the foundation is constructed, the receiving seat 10b is integrated with the side of the rising portion of the foundation, so that the conventional rust prevention work and repair work are not required, and the construction efficiency It becomes possible to improve the property.
[0073]
The receiving seat 10b is movable at a screw portion 10d provided on the end side of the long portion 10a, and the distance between the concrete molds 5 is adjusted by moving the receiving seat 10b. It is configured to be able to.
[0074]
Further, as shown in FIG. 2, the separator 10 includes an engaging piece 11 that engages with one upper chord member 2 and an engaging portion 12 that can slide in the longitudinal direction of the separator 10. The locking portion 12 includes a locking piece 12a and a thumbscrew 12b that presses and fixes the locking piece 12a against the other upper chord material 2. The thumbscrew 12b is screwed into a screw portion 10c provided on the long portion 10a, and is configured to be movable on the screw portion 10c.
[0075]
The engagement piece 11 of the separator 10 is provided at a position closer to one end side than the central portion of the long portion 10 a of the separator 10, and one of the steel beams 1 out of the opposing steel beams 1 is provided. It is configured to engage with the upper chord material 2.
[0076]
When the engaging piece 11 is engaged with the upper chord material 2 of one steel beam 1, the locking piece 12 a is then engaged with the upper chord material 2 of the other steel beam 1. Then, the thumbscrew 12b is rotated to move the thumbscrew 12b toward the end of the long portion 10a. When the thumbscrew 12b moves, it is pushed by the thumbscrew 12b, and the locking piece 12a moves toward the end of the long portion 10a.
[0077]
When the locking piece 12 a comes into contact with the upper chord material 2, the thumbscrew 12 b is further rotated to press the locking piece 12 a against the upper chord material 2. In this way, the separator 10 is fixed between the pair of steel beams 1.
[0078]
As shown in FIG. 3, the holding member 20 includes an attachment portion 21 that is attached to the lower chord material 3 of the steel beam 1 and a holding portion 22 that holds the concrete formwork 5. The attachment portion 21 and the holding portion 22 are configured to be orthogonal to each other.
[0079]
The attachment portion 21 includes a surface 21a orthogonal to the holding portion 22 and a hook portion 21b formed by bending the surface 21a. A width slightly wider than the thickness of the standing piece 3a of the lower chord material 3 is secured between the surface 21a and the hooking portion 21b, and the standing piece 3a is positioned between the surface 21a and the hooking portion 21b. It is configured to be able to.
[0080]
The attaching portion 21 is fixed to the lower chord material 3 by hooking the hook portion 21b on the standing piece 3a of the lower chord material 3 and hitting it with a hammer or the like. Thus, the holding member 20 is arrange | positioned at the lower chord material 3 of the steel beam 1 which opposes, respectively.
[0081]
When the holding member 20 is disposed on the lower chord material 3, the holding portion 22 of the holding member 20 is positioned outside the first holding portion 22a located on the lower chord material 3 side and the first holding portion 22a. The second holding portion 22b is configured.
[0082]
A gap x larger than the thickness of the concrete mold 5 is provided between the first holding part 22a and the second holding part 22b so that the concrete mold 5 can be disposed. In addition, a bent portion 22c that can be tilted toward the concrete mold 5 side is provided at the tip of the second holding portion 22b.
[0083]
The bent portion 22c is for holding the concrete mold 5 disposed in the holding portion 22 more reliably. That is, when the concrete mold 5 is disposed in the holding portion 22, the second holding portion 22b is hit with the hammer or the like toward the concrete mold 5 side as shown in FIG. The bent portion 22c is bent toward the concrete mold 5 from the front end of the holding portion 22b, and the flange 5a of the concrete mold 5 is pressed by the bent bent portion 22c, and the concrete mold 5 is locked. .
[0084]
In the holding member 20 of this example, for distributing concrete Through hole 22d is provided. Through hole By providing 22d, it becomes possible to distribute the concrete poured in evenly.
[0085]
In addition, since the holding member 20 is a member attached to the steel beam 1 by retrofitting, according to the concrete formwork 5, the space | interval x of the holding part 22, the 1st holding part 22a, and the 2nd holding part 22b. It is possible to adjust the height, size, etc.
[0086]
Alternatively, a plurality of different types of holding members 20 may be prepared in advance, and the most suitable holding member 20 may be selected according to the concrete mold 5 used for construction.
[0087]
In addition, by changing the angle of the portion 22e in contact with the concrete mold 5 in the holding part 22 of the holding member 20, the angle for supporting the concrete mold 5 can be freely changed, and the foundation of the desired shape can be obtained. It becomes possible to construct.
[0088]
Thus, the support hardware S of this example 1 According to the above, since adjustment on the support hardware side is possible, it is possible to cope with various types of concrete molds. Further, by adjusting the support hardware side, the shape of the foundation to be constructed can be easily adjusted to a desired shape.
[0089]
A plurality of holding members 20 are respectively attached to the lower chord members 3 of the steel beams 1 arranged in two rows. Then, the concrete mold 5 is mounted on the holding member 20 attached to the lower chord material 3. At this time, the concrete mold 5 is held at the lower end by the first holding part 22a, the second holding part 22b, and the bent part 22c of the holding member 20, and the interval between the concrete molds 5 is The separator 10 is kept constant.
[0090]
Further, as shown in FIG. 1, a width stop hardware 6 is attached to the top end of the concrete mold 5 arranged side by side as described above. The width stop hardware 6 is a holder that is attached to the top end side of the concrete mold 5 so as to prevent the space between the concrete molds 5 from being spread by placing concrete, and holds the interval between the concrete molds 5. .
[0091]
In this way, the concrete mold 5 is erected on both sides of the steel beam 1 arranged in two rows. Since the concrete formwork 5 is held by the steel beam 1 erected on the horizontally adjusted base plate, the height level is kept constant.
[0092]
Moreover, since the concrete formwork 5 is held by the first holding part, the second holding part, and the bent part, it is possible to construct an accurate foundation without wobbling at the time of placing concrete. .
[0093]
Concrete C is placed between the concrete molds 5, and the concrete C thus placed is hardened, whereby a concrete foundation based on the steel beams 1 arranged in two rows is completed.
[0094]
In this example, the support hardware S 1 Thus, since the concrete formwork 5 is held on the steel beam 1, the height level of the concrete formwork 5 can be kept constant and the adjacent formwork can be kept apart from each other without constructing a footing in advance. It is possible to arrange them while aligning them.
[0095]
For this reason, a footing and a rising part can be constructed simultaneously. Thus, the support hardware S of this example 1 By using, it is possible to easily construct a foundation having no joints and high accuracy without requiring skill.
[0096]
Next, as a second embodiment, the steel beam 1 formed by connecting the upper chord material 2 and the lower chord material 3 with the web material 4 is used as a single, and the concrete formwork 5 is provided on both sides of the single steel beam 1. Supporting hardware S for standing up 2 Will be described.
[0097]
In this example, a lattice-type beam in which an upper chord member 2 and a lower chord member 3 having a substantially L-shaped cross section are assembled via a lattice 4 as a web member is used as the steel beam 1. The steel beam 1 is disposed on a base plate (not shown) that is erected on discarded concrete and adjusted to be horizontal. On the base plate, adjacent steel beams 1 are connected by a joint plate (not shown). A concrete mold 5 is erected with the steel beam 1 arranged in this manner interposed therebetween.
[0098]
Supporting hardware S according to the second embodiment 2 4, the separator 30 is located above the steel beam 1 and is engaged with the upper chord material 2 of the steel beam 1, and the holding member 40 attached to the lower chord material 3 of the steel beam 1. It is configured.
[0099]
The separator 30 accurately keeps the interval between the concrete molds 5 and includes a long portion 30a and receiving seats 30b provided at both ends of the long portion 30a.
[0100]
The receiving seat 30b of the separator 30 is formed from mortar. Therefore, when the concrete formwork 5 is disassembled after the foundation is constructed, the receiving seat 30b is integrated with the side surface of the rising portion of the foundation, so that rust prevention work and repair work as conventionally performed are not required, and construction efficiency It becomes possible to improve the property.
[0101]
Further, the receiving seat 30b is movable at a screw portion 30d provided on the end side of the long portion 30a, and the distance between the concrete molds 5 is adjusted by moving the receiving seat 30b. It is configured to be able to.
[0102]
Further, as shown in FIG. 5, the separator 30 is provided with a pair of engagement pieces 31 that sandwich the upper chord material 2. In this example, the engagement piece 31 is provided by attaching a member having a substantially U-shaped cross section to the separator 30.
[0103]
When the separator 30 is attached to the upper chord material 2, one of the engagement pieces 31 is engaged with the upper chord material 2, and the upper portion of the other engagement piece 31 is struck with a hammer or the like, so that the engagement piece 31 is moved to the upper chord material. 2 to fit.
[0104]
In this example, since the claw portion 31 a is provided at the tip of the engagement piece 31, the claw portion 31 a is hooked on the upper chord material 2 so that the engagement piece 31 falls off the upper chord material 2. It becomes possible to prevent.
[0105]
As shown in FIG. 6, the holding member 40 of this example includes an attachment portion 41 that is attached to the lower chord material 3 of the steel beam 1 and a holding portion 42 that holds the concrete mold 5. The holding member 40 of this example is formed by bending a single steel plate and providing an attachment portion 41 and a holding portion 42 on each facing surface.
[0106]
The holding member 40 of the present example is configured so that the attachment portion 41 is doubled and is securely attached to the lower chord material 3. Further, the holding portions 42 located on both sides of the attachment portion 41 are formed so that the opposing surfaces do not overlap. Thus, by providing the part where the opposing surfaces do not overlap, it is possible to spread the concrete evenly when the concrete is placed.
[0107]
The attachment portion 41 includes an attachment portion main body 41a and a groove portion 41b. The groove 41b has a width that is slightly wider than the thickness of the standing portion 3a of the lower chord member 3, and is configured such that the standing piece 3a can be positioned in the groove 41b.
[0108]
The mounting portion 41 is fixed to the lower chord material 3 by positioning the standing piece 3a of the lower chord material 3 in the groove portion 41b and hitting it with a hammer or the like. In this way, the holding member 40 is disposed on the lower chord member 3 of the steel beam 1.
[0109]
In this example, two types of groove portions 41 b are provided, and when the holding member 40 is attached to the lower chord material 3, either groove portion may be used. At this time, if the widths of the groove portions are different from each other, even when the thickness of the standing piece 3a is different, it is possible to cope without using a separate holding member.
[0110]
The holding portions 42 of the holding member 40 are provided on both sides of the attachment portion 41. When the holding member 40 is disposed on the lower chord material 3, the holding portion 42 includes a first holding portion 42 a located on the lower chord material 3 side and a second holding located outside the first holding portion 42 a. Part 42b.
[0111]
An interval x larger than the thickness of the concrete mold 5 is provided between the first holding part 42a and the second holding part 42b so that the concrete mold 5 can be disposed. A bent portion 42c that can be tilted toward the concrete mold 5 side is provided at the tip of the second holding portion 42b.
[0112]
The bent part 42c is for holding the concrete mold 5 disposed in the holding part 42 more reliably. That is, when the concrete mold 5 is disposed in the holding portion 42, the second holding portion 42b is hit with the hammer or the like toward the concrete mold 5 side as shown in FIG. The bent portion 42c is bent toward the concrete mold 5 from the front end of the holding portion 42b, and the flange 5a of the concrete mold 5 is pressed by the bent bent portion 42c so that the concrete mold 5 is locked. .
[0113]
The holding member 42 of this example is used for distributing concrete. Through hole 42d is provided. Through hole By providing 42d, it is possible to spread the concrete that has been driven in evenly.
[0114]
In addition, since the holding member 40 is a member attached to the steel beam 1 by retrofitting, according to the concrete formwork 5, the space | interval x of the holding part 42, the 1st holding part 42a, and the 2nd holding part 42b. It is possible to adjust the height, size, etc.
[0115]
Alternatively, a plurality of different types of holding members 40 may be prepared in advance, and the most suitable holding member 40 may be selected according to the concrete mold 5 used for construction.
[0116]
Further, by changing the angle of the portion 42e in contact with the concrete mold 5 in the holding portion 22 of the holding member 40, the angle for supporting the concrete mold 5 can be freely changed, and the foundation of the desired shape can be obtained. It becomes possible to construct.
[0117]
Thus, the support hardware S of this example 2 According to the above, since adjustment on the support hardware side is possible, it is possible to cope with various types of concrete molds. Further, by adjusting the support hardware side, the shape of the foundation to be constructed can be easily adjusted to a desired shape.
[0118]
A plurality of holding members 40 are attached to the lower chord member 3 of the steel beam 1. Then, the concrete mold 5 is mounted on the holding member 22 mounted on the lower chord material 3. At this time, the concrete mold 5 is held at the lower end by the first holding part 42a, the second holding part 42b, and the bent part 42c of the holding member 40, and the interval between the concrete molds 5 is The separator 30 is kept constant.
[0119]
Further, as shown in FIG. 1, a width stop hardware 6 is attached to the top end of the concrete mold 5 arranged side by side as described above. The width stop hardware 6 is a holder that is attached to the top end side of the concrete mold 5 so as to prevent the space between the concrete molds 5 from being spread by placing concrete, and holds the interval between the concrete molds 5. .
[0120]
In this way, the concrete mold 5 is erected on both sides of the steel beam 1. Since the concrete formwork 5 is held by the steel beam 1 erected on the horizontally adjusted base plate, the height level is kept constant.
[0121]
Moreover, since the concrete formwork 5 is held by the first holding part, the second holding part, and the bent part, it is possible to construct an accurate foundation without wobbling at the time of placing concrete. .
[0122]
Concrete C is placed between the concrete molds 5, and the concrete C thus placed is hardened, so that a concrete foundation based on the steel beams 1 arranged in two rows is completed.
[0123]
In this example, the support hardware S 2 Since the concrete formwork 5 is held by the steel beam 1, the height level of the concrete formwork 5 can be kept constant and the adjacent molds can be maintained without constructing a footing in advance as in the prior art. It is possible to arrange the frames while aligning them.
[0124]
For this reason, a footing and a rising part can be constructed simultaneously. Thus, the support hardware S of this example 2 By using, it is possible to easily construct a foundation having no joints and high accuracy without requiring skill.
[0125]
As a third embodiment, the steel beam 1 formed by connecting the upper chord member 2 and the lower chord member 3 by the web member 4 is arranged in parallel in two rows, and thus arranged in two rows in this way. Supporting hardware S used when constructing a solid foundation based on the steel beam 1 3 Will be described.
[0126]
The steel beam 1 is a lattice-type beam in which an upper chord member 2 and a lower chord member 3 having a substantially L-shaped cross section are assembled via a lattice 4 as a web member. The upper chord member 2 and the lower chord member 3 are respectively It arrange | positions so that an outer corner | angular part may face outside. Thereby, the lower chord material 3 is arrange | positioned so that the standing piece 3a may be located in the outer side.
[0127]
The steel beam 1 is disposed on a base plate (not shown) that is erected on discarded concrete and adjusted to be horizontal. On the base plate, adjacent steel beams 1 are connected by a joint plate (not shown). A concrete mold 5 is erected with the steel beam 1 arranged in this manner interposed therebetween. In addition, the code | symbol 7 of FIG. 7 is a basic streak.
[0128]
Supporting hardware S according to the third embodiment 3 As shown in FIG. 7, the concrete formwork 5 can be supported upward from an intermediate position of the height of the steel beam 1.
[0129]
Supporting hardware S according to the third embodiment 3 7 is composed of a separator 10 that is positioned above the steel beam 1 and is engaged with the upper chord material 2 of the steel beam 1, and a holding member 50 that is attached to the upper chord material 2.
[0130]
The separator 10 accurately keeps the interval between the concrete molds 5, and includes a long portion 10 a and receiving seats 10 b provided at both ends of the long portion 10 a. In addition, the separator 10 includes an engagement piece 11 that engages with one upper chord member 2 and an engaging portion 12 that can slide in the longitudinal direction of the separator 10. In this example, the thing of the structure similar to the separator 10 in a 1st Example is used.
[0131]
As shown in FIG. 8, the holding member 50 is positioned between the upper chord members 2 of the steel beams 1 arranged in two rows, and is attached to the upper chord member 2, and is continuous to the attachment portions 51. And a pair of holding portions 52 that hold the concrete mold 5 on both sides of the neck portion 53.
[0132]
The mounting portion 51 is composed of a plate 51a that is stretched over the upper chord material 2 of the steel beam 1 arranged in two rows, and a locking piece 51b that is formed at the tip of the neck portion 53 and can be joined to the plate 51a. Yes. The plate 51a and the locking piece 51b are connected by a bolt 51c and a nut 51d as fixing members.
[0133]
As shown in FIG. 8, the locking piece 51b is formed so as to be longer than the gap between the upper chord members 2, and is configured so that both end portions are joined to the upper chord member 2. When the locking piece 51b is connected by the fixing member, the edge of the upper chord material 2 is clamped by the plate 51a and the locking piece 51b. Accordingly, the holding member 50 is securely fixed to the upper chord member 2 so as not to drop off.
[0134]
In addition, about the latching | locking part 51, it is good also as a structure which does not use the plate 51a, the volt | bolt 51c, and the nut 51d as mentioned above. For example, it is set as the structure which formed in the front-end | tip of the neck part 53 the latching piece in which the groove part which can be fitted to the edge part of the upper chord material 2 was provided.
[0135]
When attaching the locking piece to the upper chord material, first, between the upper chord material 2, the holding member 50 is positioned so as to be inclined with respect to the upper chord material, and the position of the groove and the edge of the upper chord material 2 is set. After the alignment, the edge of the upper chord material 2 is fitted into the groove while rotating the holding member 50.
[0136]
By adopting such a configuration, parts such as a plate and a fixing member are not necessary, the number of parts is reduced, and the holding member 50 is made to be an upper chord member by a simple operation by simply rotating the holding member 50 through a gap. 2 can be fixed.
[0137]
The holding portion 52 of the holding member 50 is configured to be positioned on both sides of the neck portion 53 when the holding member 50 is disposed on the upper chord material 2. The holding part 52 includes a first holding part 52a located on the steel beam 1 side and a second holding part 52b located outside the first holding part 52a.
[0138]
An interval x larger than the thickness of the concrete formwork 5 is provided between the first holding part 52a and the second holding part 52b so that the concrete formwork 5 can be disposed. In addition, a bent portion 52c that can be tilted toward the concrete mold 5 side is provided at the tip of the second holding portion 52b.
[0139]
The bent portion 52c is for holding the concrete mold 5 disposed in the holding portion 52 more reliably. That is, when the concrete mold 5 is disposed in the holding part 52, the second holding part 52b is hit with the hammer or the like toward the concrete mold 5 side as shown in FIG. The bent portion 52c is bent toward the concrete mold 5 from the front end of the holding portion 52b, and the flange 5a of the concrete mold 5 is pressed by the bent portion 52c, and the concrete mold 5 is locked. .
[0140]
The holding member 52 of the present example is used for distributing concrete. Through hole 52d is provided. Through hole By providing 52d, it is possible to distribute the concrete that has been driven in evenly.
[0141]
In addition, since the holding member 50 is a member attached to the steel beam 1 by retrofitting, according to the concrete formwork 5, the space | interval x of the holding part 52, the 1st holding part 52a, and the 2nd holding part 52b. It is possible to adjust the height, size, etc.
[0142]
Alternatively, a plurality of different types of holding members 50 may be prepared in advance, and the most suitable holding member 50 may be selected in accordance with the concrete mold 5 used for construction.
[0143]
In addition, by changing the angle of the portion 52e in contact with the concrete mold 5 in the holding portion 52 of the holding member 50, the angle for supporting the concrete mold 5 can be freely changed, and the foundation of the desired shape can be obtained. It becomes possible to construct.
[0144]
Thus, the support hardware S of this example 3 According to the above, since adjustment on the support hardware side is possible, it is possible to cope with various types of concrete molds. Further, by adjusting the support hardware side, the shape of the foundation to be constructed can be easily adjusted to a desired shape.
[0145]
A plurality of holding members 50 are attached to the upper chord member 2 of the steel beam 1 arranged in two rows. Then, the concrete formwork 5 is placed on the holding member 50 attached to the upper chord material 2. At this time, the concrete mold 5 is held at the lower end by the first holding part 52a, the second holding part 52b, and the bent part 52c of the holding member 50, and the interval between the concrete molds 5 is The separator 10 is kept constant.
[0146]
Furthermore, as shown in FIG. 7, the width stop metal fitting 6 is attached to the top end of the concrete mold 5 arranged side by side as described above. The width stop hardware 6 is a holder that is attached to the top end side of the concrete mold 5 so as to prevent the space between the concrete molds 5 from being spread by placing concrete, and holds the interval between the concrete molds 5. .
[0147]
In this way, the concrete mold 5 is erected on both sides of the steel beam 1 arranged in two rows. Since the concrete formwork 5 is held by the steel beam 1 erected on the horizontally adjusted base plate, the height level is kept constant.
[0148]
Moreover, since the concrete formwork 5 is held by the first holding part, the second holding part, and the bent part, it is possible to construct an accurate foundation without wobbling at the time of placing concrete. .
[0149]
Concrete C is placed between the concrete molds 5, and the concrete C thus placed is hardened, whereby a concrete foundation based on the steel beam 1 is completed.
[0150]
Next, as a fourth embodiment, a single steel beam 1 formed by connecting the upper chord material 2 and the lower chord material 3 with the web material 4 is used as a single, and the solid steel beam 1 is used as a base and a solid foundation is used. Supporting hardware S used for construction 4 Will be described.
[0151]
In this example, a lattice-type beam in which an upper chord member 2 and a lower chord member 3 having a substantially L-shaped cross section are assembled via a lattice 4 as a web member is used as the steel beam 1. The steel beam 1 is disposed on a base plate (not shown) that is erected on discarded concrete and adjusted to be horizontal. On the base plate, adjacent steel beams 1 are connected by a joint plate (not shown). A concrete mold 5 is erected with the steel beam 1 arranged in this manner interposed therebetween. In addition, the code | symbol 7 of FIG. 9 is a basic streak.
[0152]
Support hardware S according to the fourth embodiment 4 As shown in FIG. 9, the concrete formwork 5 can be supported upward from an intermediate position of the height of the steel beam 1.
[0153]
Support hardware S according to the fourth embodiment 4 As shown in FIG. 9, this is composed of a separator 30 positioned above the steel beam 1 and engaged with the upper chord material 2 of the steel beam 1, and a holding member 60 attached to the upper chord material 2.
[0154]
The separator 30 accurately keeps the interval between the concrete molds 5, and includes a long portion 30 a and receiving seats 30 b provided at both ends of the long portion 30 a, and sandwiches the upper chord material 2. A pair of engagement pieces 31 are provided. In this example, the thing of the structure similar to the separator 30 in a 2nd Example is used.
[0155]
As shown in FIG. 10, the holding member 60 includes a mounting part 61 attached to the upper chord material 2 of the steel beam 1, a neck part 63 provided continuously with the locking part 61, and a concrete mold on both sides of the neck part 63. And a pair of holding portions 62 that hold the frame 5.
[0156]
The attachment portion 61 is provided at the tip of the neck portion 63 and is formed so as to be able to be joined to the upper chord material 2. The mounting portion 61 is configured to be connected to the upper chord material 2 by a bolt 61c and a nut 61d as fixing members.
[0157]
The holding portions 62 of the holding member 60 are configured to be positioned on both sides of the neck portion 63 when the holding member 60 is disposed on the upper chord material 2. The holding part 62 includes a first holding part 62a located on the steel beam 1 side and a second holding part 62b located outside the first holding part 62a.
[0158]
An interval x larger than the thickness of the concrete formwork 5 is provided between the first holding part 62a and the second holding part 62b so that the concrete formwork 5 can be disposed. In addition, a bent portion 62c that can be tilted toward the concrete mold 5 side is provided at the tip of the second holding portion 62b.
[0159]
The bent part 62c is for holding the concrete mold 5 disposed in the holding part 62 more reliably. That is, when the concrete mold 5 is disposed in the holding portion 62, the second holding portion 62b is hit with the hammer or the like toward the concrete mold 5 side as shown in FIG. The bent portion 62c is bent toward the concrete mold 5 from the front end of the holding portion 62b, and the flange 5a of the concrete mold 5 is pressed by the bent portion 62c, and the concrete mold 5 is locked. .
[0160]
The holding member 62 of the present example is for distributing concrete. Through hole 62d is provided. Through hole By providing 62d, it is possible to distribute the concrete that has been driven in evenly.
[0161]
In addition, since the holding member 60 is a member attached to the steel beam 1 by retrofitting, according to the concrete formwork 5, the space | interval x of the holding part 62, the 1st holding part 62a, and the 2nd holding part 62b. It is possible to adjust the height, size, etc.
[0162]
Alternatively, a plurality of different types of holding members 60 may be prepared in advance, and the most suitable holding member 60 may be selected in accordance with the concrete mold 5 used for construction.
[0163]
Further, by changing the angle of the portion 62e in contact with the concrete mold 5 in the holding part 62 of the holding member 60, the angle for supporting the concrete mold 5 can be freely changed, and the foundation of the desired shape can be obtained. It becomes possible to construct.
[0164]
Thus, the support hardware S of this example 4 According to the above, since adjustment on the support hardware side is possible, it is possible to cope with various types of concrete molds. Further, by adjusting the support hardware side, the shape of the foundation to be constructed can be easily adjusted to a desired shape.
[0165]
A plurality of holding members 60 are attached to the upper chord member 2 of the steel beam 1. Then, the concrete mold 5 is mounted on the holding member 60 mounted on the upper chord material 2. At this time, the concrete mold 5 is held at its lower end by the first holding part 62a, the second holding part 62b, and the bent part 62c of the holding member 60, and the interval between the concrete molds 5 is The separator 10 is kept constant.
[0166]
Further, as shown in FIG. 9, a width stop metal fitting 6 is attached to the top end of the concrete mold 5 arranged side by side as described above. The width stop hardware 6 is a holder that is attached to the top end side of the concrete mold 5 so as to prevent the space between the concrete molds 5 from being spread by placing concrete, and holds the interval between the concrete molds 5. .
[0167]
In this way, the concrete mold 5 is erected on both sides of the steel beam 1. Since the concrete formwork 5 is held by the steel beam 1 erected on the horizontally adjusted base plate, the height level is kept constant.
[0168]
Moreover, since the concrete formwork 5 is held by the first holding part, the second holding part, and the bent part, it is possible to construct an accurate foundation without wobbling at the time of placing concrete. .
[0169]
Concrete C is placed between the concrete molds 5, and the concrete C thus placed is hardened, whereby a concrete foundation based on the steel beam 1 is completed.
[0170]
Next, as a fifth embodiment, a support 1a and a support provided with flanges 1b and 1c at the end of the support 1a and used to construct a foundation based on a steel beam 1 formed in an I shape. Hardware S 5 Will be described.
[0171]
The steel beam 1 is disposed on a base plate (not shown) that is erected on discarded concrete and adjusted to be horizontal. On the base plate, adjacent steel beams 1 are connected by a joint plate (not shown). A concrete mold 5 is erected with the steel beam 1 arranged in this manner interposed therebetween.
[0172]
Supporting hardware S according to the fifth embodiment 5 As shown in FIG. 11, a pair of separators 70 located above the steel beam 1 and engaged with the upper chord material 2 of the steel beam 1 and a flange portion 1c on the lower side of the steel beam 1 are mounted. And holding member 80.
[0173]
The separator 70 accurately maintains the interval between the concrete molds 5 and includes a long portion 70a and receiving seats 70b provided at both ends of the long portion 70a.
[0174]
The receiving seat 70b of the separator 70 of this example is formed from mortar. Therefore, when the concrete formwork 5 is disassembled after the foundation is constructed, the receiving seat 70b is integrated with the side surface of the rising portion of the foundation, so that rust prevention work and repair work as conventionally performed are not required, and the construction efficiency It becomes possible to improve the property.
[0175]
Further, the receiving seat 70b is movable at a screw portion (not shown) provided on the end side of the long portion 70a, and the distance between the concrete molds 5 is obtained by moving the receiving seat 70b. It is configured to be able to adjust.
[0176]
Further, as shown in FIG. 11, the separator 70 is provided with an engagement piece 71 that is engaged with the upper flange portion 1 b of the steel beam 1. In addition to the configuration in which only one engagement piece 71 is provided as in this example, a pair of engagement pieces 71 may be provided, and the engagement pieces 71 may be engaged with both sides of the upper flange portion 1b.
[0177]
As shown in FIG. 12, the holding member 80 includes an attachment portion 81 attached to the lower flange portion 1 c of the steel beam 1 and a holding portion 82 that holds the concrete mold 5. The attachment part 81 and the holding part 82 are formed continuously.
[0178]
The attachment portion 81 includes a surface 81a that is joined to the back surface of the lower flange portion 1c, and an engagement portion 81b that is formed on the end portion side of the surface 81a and engages with the peripheral edge portion of the flange portion 1c. Yes. The attachment portion 81 and the flange portion 1c are connected by a bolt 81c and a nut 81d.
[0179]
The holding portion 82 of the holding member 80 is located outside the first holding portion 82a located on the steel beam 1 side and the first holding portion 82a when the holding member 80 is disposed on the flange portion 1c. And a second holding part 82b.
[0180]
A gap x larger than the thickness of the concrete formwork 5 is provided between the first holding part 82a and the second holding part 82b so that the concrete formwork 5 can be disposed. In addition, a bent portion 82c that can be tilted toward the concrete mold 5 side is provided at the tip of the second holding portion 82b.
[0181]
The bent part 82c is for holding the concrete mold 5 disposed in the holding part 82 more reliably. That is, when the concrete mold 5 is disposed on the holding portion 82, the second holding portion 82b is hit with the hammer or the like toward the concrete mold 5 side as shown in FIG. The bent portion 82c bends toward the concrete mold 5 from the front end of the holding portion 82b, and the flange portion 5a of the concrete mold 5 is pressed by the bent bent portion 82c so that the concrete mold 5 is locked. .
[0182]
The holding member 82 of this example is used for distributing concrete. Through hole 82d is provided. Through hole By providing 82d, it is possible to distribute the concrete that has been driven in evenly.
[0183]
Since the holding member 80 is a member attached to the steel beam 1 as a retrofit, the interval x between the holding portions 82, the first holding portion 82a, and the second holding portion 82b are matched to the concrete formwork 5. It is possible to adjust the height, size, etc.
[0184]
Alternatively, a plurality of different types of holding members 80 may be prepared in advance, and the most suitable holding member 80 may be selected in accordance with the concrete mold 5 used for construction.
[0185]
In addition, by changing the angle of the portion 82e in contact with the concrete mold 5 in the holding part 82 of the holding member 80, the angle for supporting the concrete mold 5 can be freely changed, and the foundation of the desired shape can be obtained. It becomes possible to construct.
[0186]
Thus, the support hardware S of this example 5 According to the above, since adjustment on the support hardware side is possible, it is possible to cope with various types of concrete molds. Further, by adjusting the support hardware side, the shape of the foundation to be constructed can be easily adjusted to a desired shape.
[0187]
The holding member 80 is attached to the lower flange portion 1c so as to face each other with the column 1a of the steel beam 1 interposed therebetween. A plurality of holding members 80 are attached to each side of the flange portion 1c. Then, the concrete mold 5 is mounted on the holding member 82 attached to the flange portion 1c. At this time, the lower end of the concrete mold 5 is held by the first holding part 82a, the second holding part 82b, and the bent part 82c of the holding member 80, and the interval between the concrete molds 5 is The separator 10 is kept constant.
[0188]
Furthermore, as shown in FIG. 11, the width stop metal fitting 6 is attached to the top end of the concrete mold 5 arranged side by side as described above. The width stop hardware 6 is a holder that is attached to the top end side of the concrete mold 5 so as to prevent the space between the concrete molds 5 from being spread by placing concrete, and holds the interval between the concrete molds 5. .
[0189]
In this way, the concrete mold 5 is erected on both sides of the I-shaped steel beam 1. Since the concrete formwork 5 is held by the steel beam 1 erected on the horizontally adjusted base plate, the height level is kept constant.
[0190]
Moreover, since the concrete formwork 5 is held by the first holding part, the second holding part, and the bent part, it is possible to construct an accurate foundation without wobbling at the time of placing concrete. .
[0191]
Concrete C is placed between the concrete molds 5, and the concrete C thus placed is hardened, whereby a concrete foundation based on the steel beam 1 is completed.
[0192]
In this example, the support hardware S 5 Thus, since the concrete formwork 5 is held on the steel beam 1, the height level of the concrete formwork 5 can be kept constant and the adjacent formwork can be kept apart from each other without constructing a footing in advance. It is possible to arrange them while aligning them.
[0193]
For this reason, a footing and a rising part can be constructed simultaneously. Thus, the support hardware S of this example 5 By using, it is possible to easily construct a foundation having no joints and high accuracy without requiring skill.
[0194]
In addition, in the said 1st Example thru | or 5th Example, if the holding member 20,40,50,60,80 is formed from a striped steel plate, it will become possible to improve the adhesion of the concrete to a holding member, and is suitable. is there.
[0195]
【The invention's effect】
As described above, the support hardware according to the present invention is used for a highly rigid steel beam, and fixes a concrete mold along the steel beam. At this time, because the concrete formwork is configured to be securely held by the first holding part, the second holding part, and the bent part, the concrete formwork does not move at the time of placing the concrete, It becomes possible to ensure a constant cover thickness of the concrete.
[0196]
In addition, although the concrete formwork is held in the steel beam, the height level of the concrete formwork held in the steel beam is kept constant because the steel beam is installed horizontally on the bottom of the bottom. . For this reason, it is possible to securely attach the width stop hardware to the top end of the concrete mold, and prevent the spread between the molds at the time of placing the concrete and improve the construction accuracy.
[0197]
In addition, the support hardware of the present invention includes a separator and a holding member, and is configured so that the holding member can be attached to the steel beam by attaching the attachment portion of the holding member to the steel beam. Installation can be easily performed without taking time.
[0198]
Further, by using the support metal of the present invention, it is possible to arrange the concrete mold with high accuracy simply by placing the concrete mold on the support metal. In this way, the concrete formwork can be accurately installed without requiring skill and without taking much time.
[0199]
In addition, since the support hardware is attached to the steel beam retrofitting, the concrete formwork can be reliably secured regardless of the concrete formwork used by using the support hardware that matches the type of concrete formwork. Can be held in. Furthermore, it is possible to obtain the desired cover thickness and the inclination of the formwork only by adjusting the position and angle of the mounting portion and the holding portion on the support hardware side.
[0200]
Moreover, the receiving seat of the separator of this invention is formed from mortar. Therefore, when the concrete formwork is dismantled after the foundation is constructed, the receiving seat is integrated with the side of the rising part of the foundation, eliminating the need for rust prevention and repair work as was done in the past, and improving construction efficiency. It becomes possible to improve.
[0201]
In addition, since the receiving seat is movably attached at the end of the elongated portion, it is possible to easily adjust the distance between the concrete molds by simply changing the position of the receiving seat.
[Brief description of the drawings]
FIG. 1 Supporting hardware S 1 It is explanatory drawing which shows the use condition of.
[Fig. 2] Supporting hardware S 1 It is an enlarged view of the separator.
[Fig. 3] Supporting hardware S 1 It is an enlarged view of the holding member.
[Fig. 4] Supporting hardware S 2 It is explanatory drawing which shows the use condition of.
[Fig. 5] Supporting hardware S 2 It is an enlarged view of the separator.
[Fig. 6] Supporting hardware S 2 It is an enlarged view of the holding member.
[Fig. 7] Supporting hardware S 3 It is explanatory drawing which shows the use condition of.
[Fig. 8] Supporting hardware S 3 FIG.
[Fig. 9] Supporting hardware S 4 It is explanatory drawing which shows the use condition of.
[Fig. 10] Supporting hardware S 3 FIG.
FIG. 11: Support hardware S 5 It is explanatory drawing which shows the use condition of.
[Fig. 12] Supporting hardware S 4 It is an enlarged view of the holding member.
FIG. 13 is an explanatory view showing a state in which the flange portion of the concrete mold is held at the bent portion.
FIG. 14 is an explanatory diagram showing a conventional example.
FIG. 15 is an explanatory diagram showing a conventional example.
[Explanation of symbols]
1 Steel beam
2 Upper chord material
3 Lower chord material
4 Web material
5 Concrete formwork
5a Flange
6 Stopper hardware
7 Basic muscles
10, 30, 70 Separator
11, 31, 71 engagement piece
12 Locking part
12a Locking piece
12b thumbscrew
20, 40, 50, 60, 80 Holding member
21, 41, 51, 61, 81 Mounting part
22,42,52,62,82 holding part
22a, 42a, 52a, 62a, 82a 1st holding | maintenance part
22b, 42b, 52b, 62b, 82b 2nd holding | maintenance part
22c, 42c, 52c, 62c, 82c
22d, 42d, 52d, 62d, 82d Through hole
C concrete
S 1 , S 2 , S 3 , S 4 , S 5 Support hardware

Claims (11)

上弦材と下弦材をウェブ材で連結して形成された鉄骨梁を二列に並設し、該二列に並設された鉄骨梁を挟んで立設されるコンクリート型枠を支持する支持金物であって、
前記二列に並設された鉄骨梁の上方に位置するセパレーターと、前記二列に並設された鉄骨梁の下弦材にそれぞれ取り付けられる保持部材とを備え、
前記保持部材には、前記鉄骨梁の下弦材に取り付けられる取付部と、該取付部よりも外側で前記コンクリート型枠を保持する保持部とが設けられ、
前記セパレーターには、前記上弦材の一方に係合される係合片と、前記セパレーターの長手方向に移動可能に設けられ、前記上弦材の他方に止着されて係止される係止部とが設けられ、
前記保持部材の保持部に前記コンクリート型枠がそれぞれ載置され、該載置されたコンクリート型枠の間に前記セパレーターが位置することを特徴とするコンクリート型枠を支持する支持金物。
Support metal fittings that support steel molds that are formed by connecting steel beams formed by connecting upper chord material and lower chord material with a web material in two rows, and sandwiching the steel beams arranged in two rows. Because
A separator located above the steel beams arranged in two rows, and holding members respectively attached to lower chord members of the steel beams arranged in two rows,
The holding member is provided with a mounting portion that is attached to the lower chord material of the steel beam, and a holding portion that holds the concrete formwork outside the mounting portion,
The separator includes an engagement piece that is engaged with one of the upper chord members, and a locking portion that is provided so as to be movable in the longitudinal direction of the separator and is fixed to the other of the upper chord members. Is provided,
A supporting metal for supporting a concrete mold, wherein the concrete mold is placed on a holding portion of the holding member, and the separator is positioned between the placed concrete molds.
上弦材と下弦材をウェブ材で連結して形成された鉄骨梁を二列に並設し、該二列に並設された鉄骨梁を挟んで立設されるコンクリート型枠を支持する支持金物であって、
前記二列に並設された鉄骨梁の上方に位置するセパレーターと、前記上弦材に取り付けられる保持部材とを備え、
前記保持部材には、前記二列に並設された鉄骨梁の上弦材の間に位置するとともに前記上弦材に取り付けられる取付部と、該取付部に連続した首部と、該首部の両側で前記コンクリート型枠を保持する一対の保持部とが設けられ、
前記保持部材の保持部に前記コンクリート型枠がそれぞれ載置され、該載置されたコンクリート型枠の間に前記セパレーターが位置することを特徴とするコンクリート型枠を支持する支持金物。
Support metal fittings that support steel molds that are formed by connecting steel beams formed by connecting upper chord material and lower chord material with a web material in two rows, and sandwiching the steel beams arranged in two rows. Because
A separator located above the steel beam arranged in two rows, and a holding member attached to the upper chord material,
The holding member includes an attachment portion that is located between the upper chord members of the steel beams arranged in parallel in the two rows and is attached to the upper chord member, a neck portion that is continuous with the attachment portion, and the both sides of the neck portion. A pair of holding parts for holding the concrete formwork,
A supporting metal for supporting a concrete mold, wherein the concrete mold is placed on a holding portion of the holding member, and the separator is positioned between the placed concrete molds.
前記取付部は、前記二列に並設された鉄骨梁の上弦材に掛け渡されるプレートと、前記首部先端に設けられ、両端部が前記二列に並設された鉄骨梁の上弦材にそれぞれ接合される係止片とを備え、
前記プレートと前記係止片とが固着部材により固着されたことを特徴とする請求項記載のコンクリート型枠を支持する支持金物。
The attachment portion is provided on the upper chord material of the steel beam arranged in the two rows and provided on the upper chord material of the steel beam arranged in the two rows, and at the tip of the neck portion. A locking piece to be joined,
The supporting metal for supporting the concrete formwork according to claim 2, wherein the plate and the locking piece are fixed by a fixing member.
前記セパレーターには、前記上弦材の一方に係合される係合片と、前記セパレーターの長手方向に移動可能に設けられ、前記上弦材の他方に止着されて係止される係止部とが設けられたことを特徴とする請求項2または3記載のコンクリート型枠を支持する支持金物。The separator includes an engagement piece that is engaged with one of the upper chord members, and a locking portion that is provided so as to be movable in the longitudinal direction of the separator and is fixed to the other of the upper chord members. The support metal object which supports the concrete formwork of Claim 2 or 3 characterized by the above-mentioned. 上弦材と下弦材をウェブ材で連結して形成された鉄骨梁を挟んで立設されるコンクリート型枠を支持する支持金物であって、
前記上弦材の上方に位置するセパレーターと、前記上弦材に取り付けられる保持部材とを備え、
前記保持部材には、前記上弦材に取り付けられる取付部と、該取付部に連続する首部と、該首部の両側で前記コンクリート型枠を保持する一対の保持部とが設けられ、
前記保持部材の保持部に前記コンクリート型枠がそれぞれ載置され、該載置されたコンクリート型枠の間に前記セパレーターが位置することを特徴とするコンクリート型枠を支持する支持金物。
A support hardware for supporting a concrete formwork that is erected with a steel beam formed by connecting an upper chord material and a lower chord material with a web material,
A separator located above the upper chord material, and a holding member attached to the upper chord material,
The holding member is provided with an attachment portion attached to the upper chord material, a neck portion continuing to the attachment portion, and a pair of holding portions for holding the concrete formwork on both sides of the neck portion,
A supporting metal for supporting a concrete mold, wherein the concrete mold is placed on a holding portion of the holding member, and the separator is positioned between the placed concrete molds.
前記保持部材の保持部は、前記鉄骨梁側から前記コンクリート型枠を保持する第1の保持部と、前記コンクリート型枠を外側から保持する第2の保持部とを備え、前記第2の保持部には前記コンクリート型枠側に傾倒可能な折曲部が設けられたことを特徴とする請求項1、2、5いずれか一項に記載のコンクリート型枠を支持する支持金物。The holding part of the holding member includes a first holding part that holds the concrete formwork from the steel beam side, and a second holding part that holds the concrete formwork from the outside, and the second holding part. support hardware in part to support the concrete formwork according to any one of claims 1, 2, 5, characterized in that the bent portion tiltable on the concrete form side is provided. 前記保持部材には少なくとも一つの貫通孔が設けられていることを特徴とする請求項1、2、5いずれか一項に記載のコンクリート型枠を支持する支持金物。The supporting metal for supporting the concrete formwork according to any one of claims 1, 2, and 5, wherein the holding member is provided with at least one through hole. 前記保持部材は縞鋼板からなることを特徴とする請求項1、2、5いずれか一項に記載の記載のコンクリート型枠を支持する支持金物。The said holding member consists of a striped steel plate, The support metal object which supports the concrete formwork as described in any one of Claims 1, 2, 5 characterized by the above-mentioned. 前記セパレーターには、前記上弦材に係合される一対の係合片が設けられたことを特徴とする請求項記載のコンクリート型枠を支持する支持金物。6. A support metal object for supporting a concrete mold according to claim 5 , wherein the separator is provided with a pair of engaging pieces to be engaged with the upper chord material. 前記セパレーターは、長尺部と、該長尺部の両端部に設けられたモルタルからなる受け座とを備えたことを特徴とする請求項1、2、4、5、9いずれか一項に記載のコンクリート型枠を支持する支持金物。The separator is an elongated portion, to claim 1,2,4,5,9 any one which is characterized in that a seat made of mortar which is provided at both ends of the long arm member Supporting hardware that supports the concrete formwork described. 前記受け座は前記長尺部の端部において移動可能に取り付けられたことを特徴とする請求項10記載のコンクリート型枠を支持する支持金物。  The support bracket for supporting a concrete mold according to claim 10, wherein the receiving seat is movably attached to an end of the long portion.
JP2000366220A 2000-11-30 2000-11-30 Support hardware to support concrete formwork Expired - Fee Related JP4401018B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000366220A JP4401018B2 (en) 2000-11-30 2000-11-30 Support hardware to support concrete formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000366220A JP4401018B2 (en) 2000-11-30 2000-11-30 Support hardware to support concrete formwork

Publications (2)

Publication Number Publication Date
JP2002167964A JP2002167964A (en) 2002-06-11
JP4401018B2 true JP4401018B2 (en) 2010-01-20

Family

ID=18836875

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000366220A Expired - Fee Related JP4401018B2 (en) 2000-11-30 2000-11-30 Support hardware to support concrete formwork

Country Status (1)

Country Link
JP (1) JP4401018B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101809064B1 (en) * 2017-07-24 2017-12-14 주식회사 아이에스중공업 Non-foundation flooring system for building
JP7349874B2 (en) * 2019-10-10 2023-09-25 鹿島建設株式会社 formwork support structure

Also Published As

Publication number Publication date
JP2002167964A (en) 2002-06-11

Similar Documents

Publication Publication Date Title
US6591574B2 (en) Bracket assembly for installation of concrete forms for building foundations
US6134861A (en) Foundation construction method
US8790109B1 (en) Pre-cast concrete wall system
US20130283724A1 (en) Utility dowel bracket
KR200442545Y1 (en) Height adjusting form
US20070266659A1 (en) Perimeter foundation panel, and method of use
JP4401018B2 (en) Support hardware to support concrete formwork
JP6644600B2 (en) Integrated foundation and integrated foundation method
JP3763575B2 (en) Underground beam construction frame and underground beam construction method using the same
JPH0827818A (en) Vertical wall construction of concrete retaining wall and construction method thereof
KR100778139B1 (en) Frame for length adjustment in horizontal prop of mold
JP2018123537A (en) Method of constructing mat foundation, tubular formwork and mat foundation structure
KR101898158B1 (en) Cast Frame Using Steel production side gutter
KR20180012535A (en) Angle adjustment tie
KR20210068958A (en) Basic column rod fixing system for pricast concrete column
JP2002201798A (en) Support for concrete form, and supporting structure for the same
JPH07292683A (en) Anchor frame and foundation construction method using the frame
JP2000179152A (en) Form assembling structure of concrete foundation, and foundation-form assembling construction method
KR200285372Y1 (en) Horizontal Adjustable Underpinning for Wall Foam Panel
JP3025638B2 (en) Formwork equipment for fabric foundation
JP2003082852A (en) Form holding fixture
KR20090003182U (en) The support of a mold
JP2001032523A (en) Fitting for supporting form
KR200285374Y1 (en) Horizontal Adjustable Underpinning for Wall Foam Panel
KR20070017085A (en) A Aluminum Handrail

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071114

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090528

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090609

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090805

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091020

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091027

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121106

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121106

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151106

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees