JP4291992B2 - Pressure estimation model construction system - Google Patents

Pressure estimation model construction system Download PDF

Info

Publication number
JP4291992B2
JP4291992B2 JP2002295140A JP2002295140A JP4291992B2 JP 4291992 B2 JP4291992 B2 JP 4291992B2 JP 2002295140 A JP2002295140 A JP 2002295140A JP 2002295140 A JP2002295140 A JP 2002295140A JP 4291992 B2 JP4291992 B2 JP 4291992B2
Authority
JP
Japan
Prior art keywords
data
estimation model
pressure estimation
online
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002295140A
Other languages
Japanese (ja)
Other versions
JP2004131957A (en
Inventor
波 栄 作 難
川 太 黒
木 達 雄 芦
芳 勝 利 久
蔵 義 弘 本
沢 幸 彦 冨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2002295140A priority Critical patent/JP4291992B2/en
Publication of JP2004131957A publication Critical patent/JP2004131957A/en
Application granted granted Critical
Publication of JP4291992B2 publication Critical patent/JP4291992B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Pipeline Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、配水ブロックに張り巡らされた配水管内の圧力の分布に関する推定モデルを構築する圧力推定モデル構築システムに関する。
【0002】
【従来の技術】
飲料水等の水を一般家庭等の需要家へ配水するための配水管網が、都市基盤の一つとして重要な役割を担っている。需要家への安定した水供給を実現するために、配水管網を管理する際、配水管内を常に適切な圧力に保持することが要求されている。
【0003】
一方、配水管内の圧力状態を把握することにより、(1)配水池等の水供給点から配水管内へ適切な水圧で水供給が行われているか、(2)水圧が不足している地域はないか、或いは(3)水圧が過剰となっている地域はないか、等の情報を得ることができるようになる。このため、配水管内を適切な圧力に保持するためには、配水管内の圧力状態を的確に把握することが非常に有効である。
【0004】
配水管内の圧力状態を把握するために様々な手法が考えられており、例えば図7に示されるような管網解析手法が従来より広く用いられている。
【0005】
配水管網は、図7に示すように、配水ブロック1の全域に設置された消火栓等の需要ポイント45への配水が可能となるように張り巡らされており、配水池等の水が配水注入部3を介して供給されるようになっている。そして、圧力計測器10aや流量計測器10bが配水管2の所定箇所に設置されており、この圧力計測器10aや流量計測器10bによって、配水管2内の圧力や水流量についてのデータが時々刻々と計測されるようになっている。計測された圧力データや流量データは、オンラインで各計測器10a、10bからオンラインデータDB(オンラインデータデータベース)21に送られて、オンラインデータとして計測日時とともに記憶されるようになっている。
【0006】
一方、オペレータ等が、特定の日時の配水管2内の圧力状態を知りたい場合には、この特定日時を日時設定手段50に入力する。入力された日時は、日時設定手段50からデータ取得手段51へと送られる。データ取得手段51は、日時設定手段50から送られてきた特定日時に対して計測日時が対応するオンラインデータをオンラインデータDB21から取得し、このオンラインデータを、データ表示手段52に送るとともに解析手段53に送るようになっている。
【0007】
データ表示手段52は、送られてきたオンラインデータを表示して、オペレータ等に当該オンラインデータを提示するようになっている。
【0008】
解析手段53は、管網解析技術によって、データ取得手段51から送られてくるオンラインデータと、別途設けられた物理情報DB(物理情報データベース)54から送られてくる物理情報と、に基づいて、配水管網の各箇所における圧力等を解析するようになっている。
【0009】
なお、物理情報DB54に格納されている物理情報は、配水管網の各箇所の配水管2の口径や管路長等の土木情報であって、解析手段53が配水管網の各箇所における圧力を解析する際に有用な情報を含んでいる。
【0010】
解析手段53で解析された配水管網の各箇所における圧力等は、解析結果表示手段55でオペレータ等に提示されるようになっている。
【0011】
そして、オペレータは、解析結果表示手段55で提示された情報を考慮して、配水管2内の圧力を管理しており、例えば、水圧不足や水圧過剰の地域を生じさせることなく、配水ブロック1の各需要ポイント45へ適切に配水されているか否か、等の管理を行うようになっている。
【0012】
【発明が解決しようとする課題】
上述のような管網解析手法によって配水管網の各箇所における圧力等を解析して、配水管2内の圧力状態を把握することが従来より行われている。
【0013】
しかしながら、上述のような管網解析手法では、配水管網の所定箇所に設置されている圧力計測器10aや流量計測器10bの計測値にのみ基づいて、配水管網の各箇所における圧力等を解析している。このため、配水ブロック1が広かったり、配水管網が複雑に形成されているような場合であって、適切な数の圧力計測器10aや流量計測器10bが適切に配置されていない場合には、精度良く、信頼性の高い解析を行うことが難しい。
【0014】
また、配水管網の各箇所における圧力等の解析結果は、物理情報DB54に格納されている物理情報によって大きく左右されるため、適切な物理情報を用いることが必要とされる。当該物理情報は、配水管網の大きさや構成に応じて決定されるが、物理情報を決定するために必要とされる配水管網の土木構造の把握、土木構造のデータ化、各需要ポイント45に対する需要量の割付、等の作業には多大な労力が必要とされ、多くの解析時間が必要とされる。また、配水管網の各箇所における圧力等の解析を精度良く行うためには、各需要ポイント45に対する需要量の割付、等の作業を正確に行う必要がある。しかしながら、このような作業を正確に行うことは非常に難しい。
【0015】
本発明はこのような点を考慮してなされたものであり、配水ブロックに張り巡らされた配水管内の圧力分布を精度良く求めることができる圧力推定モデル構築システムを提供することを目的とする。
【0016】
【課題を解決するための手段】
本発明は、配水ブロックに張り巡らされた配水管内の圧力分布に関する推定モデルを構築する圧力推定モデル構築システムであって、配水管のうち1以上の箇所に設けられたオンライン計測ポイントにおける配水管内の圧力および水流量のうち少なくともいずれか一方をオンラインデータとして計測し、当該オンラインデータをオンラインで後段に送る機能を有するオンライン計測手段と、配水管のうちオンライン計測ポイントとは異なる1以上の箇所に設けられたオフライン計測ポイントにおいて予め計測された配水管内の圧力をオフラインデータとして記憶し、当該オフラインデータを後段に送る機能を有するオフライン計測データ記憶手段と、オンライン計測手段及びオフライン計測データ記憶手段の後段に設けられ、オンライン計測手段から送られてくるオンラインデータと、オフライン計測データ記憶手段から送られてくるオフラインデータと、をクラスター分析によって各クラスターに分類する機能を有するクラスタリング手段と、クラスタリング手段の後段に設けられ、各オンラインデータと同一クラスターに分類される各オフラインデータについて、同一クラスターに分類される各オンラインデータに基づき、当該各オフラインデータに対応するオフライン計測ポイントにおける配水管内の圧力モデルである第1圧力推定モデルを構築する第1圧力推定モデル構築手段と、クラスタリング手段の後段に設けられ、各オンラインデータと異なるクラスターに分類される各オフラインデータについて、主成分分析を行って、当該各オフラインデータに対応する推定モデル入力値を演算する機能を有する主成分演算手段と、主成分演算手段の後段に設けられ、各オンラインデータと異なるクラスターに分類される各オフラインデータについて、当該各オフライン計測データに対応する推定モデル入力値に基づき、当該各オフラインに対応するオフライン計測ポイントにおける配水管内の圧力モデルである第2圧力推定モデルを構築する第2圧力推定モデル構築手段と、第1圧力推定モデル構築手段及び第2圧力推定モデル構築手段に接続され、第1圧力推定モデル構築手段によって構築される第1圧力推定モデルと、第2圧力推定モデル構築手段によって構築される第2圧力推定モデルと、から構成される圧力推定モデルを記憶する圧力推定モデル記憶手段と、を備えたことを特徴とする圧力推定モデル構築システムである。
【0017】
本発明の圧力推定モデル構築システムによれば、オンライン計測ポイントからオンラインで送られてくるオンラインデータに基づいて、オフライン計測ポイントにおける配水管内の圧力に関する圧力推定モデルが構築される。
【0018】
【発明の実施の形態】
以下、図面を参照して本発明の実施の形態について説明する。
【0019】
第1の実施の形態
図1及び図2は、本発明の第1の実施の形態を示す図である。図1は、圧力推定モデル構築システム全体の構成を示す概略図である。図2は、クラスター分析によって各クラスターに分類されたオンラインデータ及び各オフラインデータを示す。
【0020】
図1に示すように、配水ブロック1における消火栓等の複数の需要ポイント45に水を供給するために、配水管2が配水ブロック1の全域に渡って張り巡らされている。これにより、配水池等から送られてくる水は、配水注入部3を介して配水ブロック1内の配水管2に供給され、各需要ポイント45へ送られるようになっている。
【0021】
このような配水管2の各箇所における圧力推定モデルを構築するための圧力推定モデル構築システム4は、圧力計測器10a及び流量計測器10b(オンライン計測手段)と、当該圧力計測器10aおよび流量計測器10bに接続された圧力推定装置11と、を備えている。
【0022】
圧力計測器10a及び流量計測器10bは、配水管2のうち1以上の箇所(本実施の形態では3箇所)に設けられたオンライン計測ポイント15における配水管2内の圧力、水流量をオンラインデータとして計測する機能を有している。そして、圧力計測器10a及び流量計測器10bは、このようにして計測されたオンラインデータをオンラインで後段に送る機能を有している。
【0023】
圧力推定装置11は、圧力計測器10aおよび流量計測器10bに接続されたオンライン計測データDB21(オンライン計測データ記憶手段)と、オフライン計測データDB22(オフライン計測データ記憶手段)と、圧力計測器10a及び流量計測器10bとオフライン計測データDB22との後段に設けられたクラスタリング手段23と、クラスタリング手段23の後段に設けられた第1圧力推定モデル構築手段24と、クラスタリング手段23の後段に設けられた主成分演算手段25と、主成分演算手段25の後段に設けられた第2圧力推定モデル構築手段26と、第1圧力推定モデル構築手段24及び第2圧力推定モデル構築手段26に接続された推定モデルDB27(圧力推定モデル記憶手段)と、圧力計測器10a及び流量計測器10bとクラスタリング手段23との間に設けられたオンライン計測データDB21(オンライン計測データ記憶手段)と、オンライン計測データDB21及びオフライン計測データDB22とクラスタリング手段23との間に設けられたデータ取得手段29と、データ取得手段29とクラスタリング手段23との間に設けられた統計値演算手段30と、統計値演算手段30とクラスタリング手段23との間に設けられた正規化手段31と、推定モデルDB27に接続されたモデル表示手段32と、を備えている。
【0024】
オフライン計測データDB22は、配水管2のうちオンライン計測ポイント15とは異なる1以上の箇所(本実施の形態では3箇所)に設けられたオフライン計測ポイント16において、オフラインデータ計測手段33によって予め計測された配水管2内の圧力を、オフラインデータとして記憶するようになっている。すなわち、オフライン計測データDB22は、消火栓等のオフライン計測ポイント16において予め計測された配水管2内の圧力を、オフラインデータとしてその計測日時と併せて記憶するようになっている。
【0025】
なお、オフラインデータ計測手段33として、例えばハンディータイプの圧力計器等が用いられうる。そして、当該圧力計器等によって、オフライン計測ポイント16において、予め、数日間、計測された配水管2内の圧力が、オフラインデータとしてオフライン計測データDB22に記憶される。そして、オフライン計測データDB22は、記憶されているオフラインデータを、後段に設けられたデータ取得手段29に送ることができるようになっている。なお、オフライン計測データDB22は、オフライン計測ポイント16のうちの全部或いは一部におけるオフラインデータを、記憶すると共に後段に送ることができるようになっている。
【0026】
オンライン計測データDB21は、圧力計測器10a及び流量計測器10b(オンライン計測手段)による計測値を、その計測日時とともに記憶するようになっている。
【0027】
なお、オンライン計測データDB21に記憶されるオンラインデータの計測日時と、オフライン計測データDB22に記憶されるオフラインデータの計測日時と、は、相互に対応している。
【0028】
データ取得手段29は、オンライン計測データDB21に記憶されているオンラインデータを取得すると共に、オンライン計測データDB21から取得したオンラインデータの計測時刻に対応するオフラインデータをオフライン計測データDB22から取得する機能を有している。そして、データ取得手段29は、取得したオンラインデータ及びオフラインデータを後段に送る機能を有している。
【0029】
統計値演算手段30は、送られてくるオンラインデータ及びオフラインデータを統計化する機能を有している。
【0030】
本実施の形態ではこれらのオンラインデータ及びオフラインデータの「統計化」は、合計値、最小値、最大値、範囲、標準偏差、分散、平均値、中央値、変動係数、歪度、尖度、といった統計化項目が基本とされる。ただし、統計値演算手段30は、他の統計化項目に基づいて、オンラインデータ及びオフラインデータを「統計化」することも可能である。
【0031】
そして、統計値演算手段30は、統計化されたオンラインデータ及びオフラインデータを後段に送る機能を有している。統計値演算手段30から送られくるオンラインデータ及びオフラインデータは、統計値DB28に記憶された後に、正規化手段31へ送られる。
【0032】
正規化手段31は、送られてくるオンラインデータ及びオフラインデータを正規化して後段に送る機能を有している。このため、本実施の形態では、正規化手段31によって正規化されたオンラインデータ及びオフラインデータは、正規化手段31の後段に設けられたクラスタリング手段23に送られるようになっている。
【0033】
本実施の形態における正規化手段31は、統計値DB28に記憶されているオンラインデータ及びオフラインデータを用いて正規化するようになっており、統計値DB28に記憶されている「平均値」および「標準偏差」に基づき、以下の式(1a)(1b)によって、オンラインデータ及びオフラインデータを、平均=0.0、分散=1.0となるように変換して「正規化」するようになっている。
【0034】
【数1】

Figure 0004291992
すなわち、データ取得手段29で取得したオンラインデータおよびオフラインデータの各データ項目のそれぞれが、式(1a)(1b)によって変換されるようになっている。例えば図1 に示すように、オンラインデータとして配水管2内の水流量に関する1 点のデータ、及び、配水管2内の圧力に関する2 点のデータ、が圧力計測器10a及び流量計測器10bによって時々刻々と収集されており、データ取得手段29において、数時間に渡るオンラインデータ(水流量に関するデータが1 点、圧力に関するデータが2 点)を取得した場合について考えてみる。
【0035】
この場合、取得したデータのそれぞれをX1t,X2t,X3t とする(ここでt は時刻を表す)。まず、X1t を式(1a)(1b)のxに代入して標準化データz を得て、次にX2t を式(1a)(1b)のxに代入して標準化データz を得て、最後にX3t を式(1a)(1b)のxにして、標準化データz を得るようになっている。この作業により、オンラインデータ(水流量に関するデータが1 点、圧力に関するデータが2 点)は、平均が0 、標準偏差が1 、に標準化されたオンラインデータ(水流量に関するデータが1 点、圧力に関するデータが2 点)に変換されるようになっている。
【0036】
また、同様にして、オフラインデータは、平均が0 、標準偏差が1 、に標準化されたオフラインデータに変換されるようになっている。なお、このようにして標準化されたオンラインデータ及びオフラインデータを得る際には、統計値演算手段30にて演算した値が、式(1a)(1b)中の基データの平均値と標準偏差として用いられるようになっている。
【0037】
クラスタリング手段23は、オンライン計測データDB21、データ取得手段29、統計値演算手段30、統計値DB28及び正規化手段31を介して、圧力計測器10aおよび流量計測器10bから送られてくるオンラインデータと、データ取得手段29、統計値演算手段30、統計値DB28及び正規化手段31を介して、オフライン計測データDB22から送られてくるオフラインデータと、をクラスター分析によって各クラスターに分類する機能を有している。
【0038】
ここで「クラスター分析」とは、一般には、標本の中から等質なものをグループ化する作業を意味する。当該クラスター分析は、標本がどのようなグループに属するか不明であって、グループ数も分からない状態から始められる。そして、当該クラスター分析の目的は、標本を等質のグループやクラスターに分類することである。
【0039】
本実施の形態のクラスタリング手段23による、オンラインデータおよびオフラインデータについてのクラスター分析は、具体的には以下のようにして行われる。なお、本実施の形態においてクラスター分析の対象は「圧力」に関するデータのみであって、「水流量」に関するデータは対象とはならない。
【0040】
▲1▼ まず、固体間の距離と、クラスター間の距離と、を定義する。ここでいう「固体」とは、オンラインデータ若しくはオフラインデータに含まれる一つの信号のことを指している。そして、この固体間の距離を示す式として、例えば以下の表1に示すような種々の式が提案されており、本実施の形態では、表1に示されている「ユークリッド距離」を用いて固体間の距離を定義する。一方、クラスター間の距離を示す式として、例えば表2に示すような種々の式が提案されており、本実施の形態では、表2に示されているウォード法を用いてクラスター間の距離を定義する。
【0041】
【表1】
Figure 0004291992
【表2】
Figure 0004291992
なお、表1及び表2において、Xa及びXbは、オンラインデータ(圧力)若しくはオフラインデータを表し、d(Xa,Xb)はXaとXbとの距離を表し、dab→cは、あるクラスターABと、オンラインデータ若しくはオフラインデータ若しくはクラスターCと、の距離を表している。
【0042】
▲2▼ 次に、全ての固体間の距離を計算する。
【0043】
▲3▼ 次に、クラスター若しくは固体間の距離が最も近い固体を併合して一つのクラスターとする。
【0044】
▲4▼ 次に、上記の▲3▼で作成したクラスターを新しい固体とみなして、全ての固体間の距離を計算する。
【0045】
▲5▼ そして、上記の▲1▼〜▲4▼を繰り返して、全ての固体が一つのクラスターに含まれたところで終わる。
【0046】
本実施の形態では、上記の▲1▼〜▲5▼に従って、例えば図2に示すようなクラスター分析の結果を得ることができる。図2において、X軸(横軸)は、各オンラインデータ及び各オフラインデータに対応する各オフライン計測ポイント及び各オンライン計測ポイントを示しており、Y軸(縦軸)は、各オンラインデータ及び各オフラインデータに関するクラスター分析における類似度(距離)を示している。また、図2における線は、線が接続されている距離において同一クラスターとして扱うことができるということ表している。
【0047】
第1圧力推定モデル構築手段24は、各オンラインデータと同一クラスターに分類される各オフラインデータについて、同一クラスターに分類される各オンラインデータに基づき、当該各オフラインデータに対応するオフライン計測ポイント16における配水管2内の圧力モデルである第1圧力推定モデルを構築するようになっている。より具体的には、本実施の形態の第1圧力推定モデル構築手段24は、重回帰分析を用いて第1圧力推定モデルを構築するようになっており、各オフラインデータと同一クラスターに分類されるオンラインデータを、重回帰分析の入力値として用いるようになっている。
【0048】
以下、「重回帰分析」について説明する。
【0049】
重回帰分析では、N組の標本に対して、説明変量{xi1,xi2,…xip}と目的変量y(i=1,2,…,N)との間に次のような線形関係が成立すると仮定する。
【0050】
【数2】
Figure 0004291992
なお、β:偏回帰係数、e:残差を意味する。
【0051】
式(2)における各残差eは、「残差eは互いに独立で正規分布N(0,σ)に従う」という条件(残差の条件)を満足すると仮定する。そして、式(2)を行列形式で表現すると以下の式(3)のようになる。
【0052】
y=zβ+e ………………(3)
なお、式(3)中の行列は以下に示すとおりである。
【0053】
【数3】
Figure 0004291992
【数4】
Figure 0004291992
そして、b,b,…,bは、ελの平方和(以下の式(7)参照)が最小となるように決定される。
【0054】
【数5】
Figure 0004291992
式(7)では、未知数はb,b,…bであり、Sはb,b,…,bに関する2次関数であり、関数Sを最小にするb,b,…,bは、Sをb,b,…,bで偏微分し、値を0とおいた連立1次方程式の解として求めることができる。上記を解いて整理すると、以下の式(8)のような連立方程式が得られる。
【0055】
【数6】
Figure 0004291992
ここで、Sjjはxの偏差平方和、Sjkはxとxの偏差積和、Sjyはxとyの偏差積和であって、それぞれ以下の式(9)のように表される。
【0056】
【数7】
Figure 0004291992
従って、以下の式(11)によって偏回帰係数が求められる。
【0057】
b=S−1M ……………(11)
また、定数項は、以下の式(12)によって求められる。
【0058】
【数8】
Figure 0004291992
本実施の形態では、上述の重回帰分析において、説明変量xは、オンラインデータ若しくは主成分分析手段で得られた主成分得点に該当し、目的変量yは、オフラインデータに該当する。ここで、主成分得点とは、各サンプルの主成分の値を示している。
【0059】
そして、上述の重回帰分析を用いて構築された第1圧力推定モデルは、第1圧力推定モデル構築手段24から推定モデルDB27に送られるようになっている。
【0060】
主成分演算手段25は、各オンラインデータと異なるクラスターに分類される各オフラインデータについて、主成分分析を行って、当該各オフラインデータに対応する推定モデル入力値を演算する機能を有している。すなわち、主成分演算手段25は、クラスタリング手段23において各オンラインデータと異なるクラスターに分類される各オフラインデータに対して、最も近接するオンラインデータの属するクラスターについての主成分分析を行って、各オンラインデータと異なるクラスターに分類される各オフラインデータについての推定モデル入力値を演算するようになっている。そして、この演算された推定モデル入力値は、各オンラインデータ及びオフラインデータとともに、主成分演算手段25から第2圧力推定モデル構築手段26に送られるようになっている。
【0061】
ここで「主成分分析(Principal Component Analysis)」とは、一般には、互いに相関のある多種類の特性値をもつ情報を、互いに無相関な小数個の総合特性値に要約する方法である。
【0062】
主成分分析は、一般には、p個の変量x,x,・・・,xの有する情報を、以下の条件(a)、(b)を満足するm個(m≦p)の総合特性値(式(14))z,z,・・・,zに、要約することを意味し、zを第1主成分、zを第2主成分、zを第m主成分と呼ぶ。
【0063】
=l11+l12+・・・+l1p
=l21+l22+・・・+l2p
・・・・・・・・ ……………(14)
=lm1+lm2+・・・+lmp
【数9】
Figure 0004291992
条件(a)とz(kはlではない;k、l=1,2,・・・、m)との相関はすべてゼロである。
【0064】
条件(b)の分散(x,x,・・・,x)は、あらゆる1次式のもつ分散のうち最大である。zの分散は、zの分散と無関係なあらゆる1次式の中で最大である。以下同様にして、zの分散はz,z,・・・,zm−1のすべてと無関係な1次式の中で最大である。
【0065】
上述の条件(b)は、「主成分z,z,・・・zは、もとの特性値x,x,・・・,xのもつ情報の損失が最小になるように要約した結果である」ということを意味する。
【0066】
本実施の形態では、上述の主成分分析におけるx〜xは、クラスタリング手段23によってクラスター分析が行われた圧力に関するオンラインデータとオフラインデータとに該当する。
【0067】
例えば、クラスター分析によって図2に図示される結果が得られた場合、まず、オンライン計測ポイント15Aに対応するオンラインデータ(圧力)と、図2においてオンライン計測ポイント15Aの両隣に位置する各計測ポイント16K、16Lに対応するオフラインデータ(圧力)と、をx〜xとする。そして、当該x〜xについての主成分得点を演算して、圧力推定モデルを生成するようになっている。次に、オンライン計測ポイント15Aに対応するオンラインデータ(圧力)と図2においてオンライン計測ポイント15Aの両隣に位置するオフライン計測ポイントに対応するオフラインデータ(圧力)と、その左の圧力をその両隣の圧力をx〜xとして、当該x〜xについての主成分得点を演算して、圧力推定モデルを演算する。このような演算を繰り返すことにより、各オフラインデータに対応する各オフライン計測ポイントにおける圧力推定モデルが順々に演算され、全部のオフライン計測ポイントにおける圧力推定モデルが得られるようになっている。
【0068】
第2圧力推定モデル構築手段26は、各オンラインデータと異なるクラスターに分類される各オフラインデータについて、当該各オフラインデータに対応する推定モデル入力値に基づき、当該各オフラインに対応するオフライン計測ポイント16における配水管2内の圧力モデルである第2圧力推定モデルを構築するようになっている。より具体的には、第2圧力推定モデル構築手段26は、上述した重回帰分析を用いて第2圧力推定モデルを構築するようになっており、主成分演算手段25で演算された対応する推定モデル入力値を、重回帰分析の入力値として用いるようになっている。これにより、配水ブロック1に張り巡らされた配水管2のうち、各オンラインデータと異なるクラスターに分類された各オフラインデータに対応するオフライン計測ポイント16における、配水管2内の圧力モデルである第2の圧力推定モデルが構築される。そして、構築された第2の圧力推定モデルは、第2圧力推定モデル構築手段26から推定モデルDB27へ送られるようになっている。
【0069】
推定モデルDB27は、第1圧力推定モデル構築手段24によって構築されて送られてくる第1圧力推定モデルと、第2圧力推定モデル構築手段26によって構築されて送られてくる第2圧力推定モデルと、から構成される圧力推定モデルを記憶するようになっている。
【0070】
モデル表示手段32は、圧力推定モデル記憶手段に記憶されている圧力推定モデルを表示することができるようになっている。
【0071】
次に、このような構成からなる本実施の形態の作用について説明する。
【0072】
配水ブロック1の配水管2のうちオンライン計測ポイント15では、圧力計測器10aおよび流量計測器10bによって水圧および水流量が計測される。そして、これらの計測値は、圧力計測器10aおよび流量計測器10bからオンラインでオンライン計測データDB21へ送られて、オンラインデータとして計測日時と併せてオンライン計測データDB21に記憶される。
【0073】
一方、配水ブロック1の配水管2のうちオフライン計測ポイント16では、予め、ハンディータイプの圧力計器等によって水圧が計測されており、この計測された水圧データは、オフライン計測データとして計測日時と併せてオフライン計測データDB22に記憶される。
【0074】
そして、各オフライン計測ポイント16の圧力推定モデルのうちオペレータ等が必要としている所定日時がデータ取得手段29に入力されると、データ取得手段29は、入力された所定日時に対応するオンラインデータをオンライン計測データDB21から取得するとともに、入力された所定日時に対応するオフラインデータをオフライン計測データDB22から取得する。そして、データ取得手段29は、取得したオンラインデータ及びオフラインデータを、入力された当該所定日時とともに統計値演算手段30へ送る。
【0075】
そして、統計値演算手段30は、送られてくるオンラインデータを統計化すると共に、送られてくるオフラインデータを統計化する。なお、本実施の形態の統計値演算手段30によって演算される統計化項目には、正規化手段31によって用いられる「平均値」および「標準偏差」が含まれている。
【0076】
統計値演算手段30によって統計化されたオンラインデータ及びオフラインデータは、統計値DB28に記憶され、正規化手段31に送られる。
【0077】
正規化手段31に送られるオンラインデータ及びオフラインデータは、正規化手段31によって正規化される。この時、正規化手段31は、統計値DB28に記憶されているオンラインデータ及びオフラインデータについての「平均値」及び「標準偏差」と、上記の式(1a)(1b)と、に基づいて、オンラインデータ及びオフラインデータを、平均=0.0、分散=1.0となるように変換して「正規化」する。
【0078】
そして、正規化されたオンラインデータ及びオフラインデータは、正規化手段31から後段に設置されたクラスタリング手段23へ送られる。
【0079】
クラスタリング手段23に送られたオンラインデータ及びオフラインデータは、クラスタリング手段23によってクラスター分析が行われて、いくつかのクラスターに分類される。これにより、例えば図2に示すようなクラスター分析の結果を得ることができ、オンラインデータおよびオフラインデータは、クラスターA、クラスターB、クラスターC、クラスターDに分類される。例えばオフライン計測ポイント16Aに関するオフラインデータはクラスターAに分類され、オフライン計測ポイント16Jに関するオフラインデータはクラスターBに分類され、オフライン計測ポイント16Kに関するオフラインデータ及びオンライン計測ポイント15Aに関するオンラインデータはクラスターCに分類され、オフライン計測ポイント16Nに関するオフラインデータ及びオンライン計測ポイント15Bに関するオンラインデータはクラスターDに分類される。
【0080】
そして、各オンラインデータと同一クラスターに分類された各オフラインデータに対応する各オフライン計測ポイント16における圧力推定モデル(第1圧力推定モデル)が、第1圧力推定モデル構築手段24によって構築される。この時、第1圧力推定モデル構築手段24は、上述の重回帰分析を用いて第1圧力推定モデルを構築する。
【0081】
例えば、クラスター分析によって図2に示す結果が得られている場合には、オンラインデータに対応するオンライン計測ポイント15A及び15Bが属するクラスターC及びDを対象にして、第1圧力推定モデル構築手段は第1圧力推定モデルを構築する。この時、クラスターCでは、オンライン計測ポイント15Aに対応するオンラインデータ(配水管内の圧力及び水流量)が圧力推定モデルを構築する際の入力値とされ、クラスターDでは、オンライン計測ポイント15Bに対応するオンラインデータ(配水管内の圧力及び水流量)が圧力推定モデルを構築する際の入力値とされる。
【0082】
そして、構築されたこれらの第1圧力推定モデルは、推定モデルDB27に送られて、当該推定モデルDB27に記憶される。
【0083】
一方、各オンラインデータと異なるクラスターに分類された各オフラインデータは、主成分演算手段25によって上述の主成分分析が行われて、各オフラインデータに対応する推定モデル入力値が求められる。そして、各オンラインデータと異なるクラスターに分類された各オフラインデータに対応する各オフライン計測ポイント16における圧力推定モデル(第2圧力推定モデル)が、第2圧力推定モデル構築手段26によって構築される。この時、第2圧力推定モデル構築手段26は、上述の重回帰分析と推定モデル入力値とを用いて圧力推定モデルを構築する。
【0084】
例えば、クラスター分析によって図2に示す結果が得られている場合、主成分演算手段25では、各オンラインデータが属していないクラスターA及びBについての推定モデル入力値が求められる。この時、クラスターBに関して、オンラインデータが属している各クラスターのうち距離の近いクラスターを順次検索する。そして、オンラインデータの属するクラスターCがクラスターBに最も近接しているという検索結果が得られた場合には、クラスターCの主成分が、クラスターBに関する圧力推定モデルを構築する際の入力値となる。同様に、クラスターAは、オンラインデータの属するクラスターCが近接している。この時、クラスターAから見るとクラスターB及びクラスターCは同一クラスターと見れるので、クラスターAの圧力推定モデルを構築する際には、クラスターB及びクラスターCの主成分が入力値となる。
【0085】
そして、構築されたこれらの第2圧力推定モデルは、推定モデルDB27に送られて、当該推定モデルDB27に記憶される。
【0086】
そして、推定モデルDB27に記憶されている第1圧力推定モデル及び第2圧力推定モデルによって構成された圧力推定モデルが、モデル表示手段32において表示されて、オペレータ等に知らされる。
【0087】
以上説明したように、本実施の形態の圧力推定モデル構築システム4によれば、オフライン計測ポイント16における所定日時の圧力推定モデルが、オンライン計測ポイント15で計測されているオンラインデータを用いた形式で、統計値演算手段30、正規化手段31、クラスタリング手段23、第1圧力推定モデル構築手段24、主成分演算手段25及び第2圧力推定モデル構築手段26を介して構築される。これにより、オンライン計測ポイントにおける配水管内の圧力分布はオンラインデータとしてオンラインで得ることができ、オフライン計測ポイントにおける配水管内の圧力分布は、オンラインデータと予め計測されていたオフラインデータとに基づいて構築される圧力推定モデルによって得ることができる。これにより、配水ブロックにおけるオンライン計測ポイント及びオフライン計測ポイントにおける配水管内の圧力を精度良く求めることが可能となる。
【0088】
なお、オンライン計測ポイント15における配水管2の圧力は、圧力計測器10aによって計測され、オンラインでオンライン計測データDBに記憶されているので、オンライン計測ポイントにおける圧力推定モデルを構築しなくても、各オンライン計測ポイントにおける配水管2の圧力値を取得することができる。
【0089】
また、本実施の形態では、従来技術では必要とされていた配水ブロック1に張り巡らされた配水管2に関する複雑な物理情報は不要であり、オンラインで計測されたオンラインデータと、オフラインで計測されたオフライン計測ポイント16における過去の圧力データであるオフラインデータと、に基づいてオフライン計測ポイント16における圧力推定モデルが構築される。このように、計測したデータのみに基づいて圧力推定モデルを構築することができるので、圧力推定モデル構築システム4は簡素化され、圧力推定モデル構築時間が大幅に短縮されうる。
【0090】
また、統計値演算手段30や正規化手段31を介して、オンラインデータ及びオフラインデータをクラスター分析することにより、各オンラインデータ及び各オフラインデータを、より安定、正確に各クラスターに分類することができる。
【0091】
なお、オンライン計測ポイント15における配水管2内の圧力及び水流量のうち少なくともいずれか一方をオンラインデータとして扱うことも可能である。この場合であっても、上述の本実施の形態と同様の作用・効果を奏しうる。
【0092】
また、第2圧力推定モデル構築手段26は、主成分演算手段25によって演算された主成分のうち、全てを使用する必要はなく、一部のみを使用することも可能である。
【0093】
次に、本実施の形態の一変形例について説明する。
【0094】
本変形例による圧力推定モデル構築システムは、統計値演算手段30や正規化手段31が設けられていなくてもよい。
【0095】
この場合、データ取得手段29によって取得されたオンラインデータ及びオフラインデータは、直接的にクラスタリング手段23に送られる。クラスタリング手段23は、オンライン計測データDB21及びオフライン計測データDB22からデータ取得手段29を介して送られてくるオンラインデータ及びオフラインデータをクラスター分析するようになっている。
【0096】
これにより、各オンラインデータ及び各オフラインデータが各クラスタに分類されるので、上述の第1の実施の形態と同様にして、第1圧力推定モデル構築手段24、主成分演算手段25及び第2圧力推定モデル構築手段26によって、圧力推定モデルが構築される。
【0097】
従って、本変形例においても、オフライン計測ポイント16における圧力推定モデルを精度良く構築することができる。
【0098】
なお、クラスタリング手段では、様々な方に変換したオンラインデータ及びオフラインデータを用いてクラスタリングを行うことが可能である。すなわち、クラスタリング手段は、上述のように統計化・正規化を加えたデータや計測したままのデータの他に、周波数スペクトル等の他の形に変換したデータを用いて、クラスター分析を行うことができる。
【0099】
第2の実施の形態
図3及び図4は、本発明の第2の実施の形態を示す図である。図3は、ニューラル・ネットワークで用いられる「ユニット」を説明するための図である。図4は、ニューラル・ネットワークで用いられる「入力層」と「中間層」と「出力層」との関係を示す図である。
【0100】
第2の実施の形態では、第1圧力推定モデル構築手段24が、重回帰分析の代わりにニューラル・ネットワーク(Neural Network)を用いて第1圧力推定モデルを構築するようになっている。すなわち、第1圧力推定モデル構築手段24は、ニューラル・ネットワークを用いることにより、各オンラインデータと同一クラスターに分類された各オフラインデータに対応するオフライン計測ポイント16における配水管2内の圧力モデルである第1の圧力推定モデルを構築するようになっている。そして、構築された第1の圧力推定モデルは、第1圧力推定モデル構築手段24から推定モデルDB27へ送られるようになっている。
【0101】
一方、第2圧力推定モデル構築手段26も、重回帰分析の代わりに上述のニューラル・ネットワークを用いて第2の圧力推定モデルを構築するようになっている。すなわち、第2圧力推定モデル構築手段26は、ニューラル・ネットワークを用いることにより、各オンラインデータと異なるクラスターに分類された各オフラインデータに対応するオフライン計測ポイント16における配水管2内の圧力モデルである第2圧力推定モデルを構築するようになっている。そして、構築された第2の圧力推定モデルは、第2圧力推定モデル構築手段26から推定モデルDB27へ送られるようになっている。
【0102】
次に、図3及び図4を用いて、「ニューラル・ネットワーク(Neural Network)」について説明する。
【0103】
「ニューラル・ネットワーク(Neural Network)」とは、一般に、人間の神経細胞(ニューロン)をモデルとする人工的なシステムを指し、多入力1出力の「ユニット」の集合体として表現される。「ユニット」を図3に示す。ユニット間は神経繊維に対応する線で結ばれており、信号は、この線上を一方向にだけ伝わるようになっており、「重み(図3のw)」を付けられてユニットに入力し、応答関数による変換を経て出力するようになっている。つまり、システム全体としての入力信号が、各ユニットへの結合および変換出力を繰り返しながら次々と伝えられていき、最終的な出力信号が形成されることになる。ユニットの結びつき方、すなわち、ネットワークモデルとしては階層型と相互結合型とが提案されている。
【0104】
階層型ネットワークにおける信号は入力層から出力層へ向かう一方通行であり(図4参照)、層内で情報伝達も考えないのが一般的である。
【0105】
相互結合型ネットワークは、ある初期状態から出発し、安定状態になるまでネットワークの状態が変化する特性を有している。
【0106】
需要予測にNeural Networkを用いる場合、入出力が非線形であるため、応答関数にシグモイド関数を用いた3層の階層型ネットワークを採用する。尚、応答関数は中間層のみに用いられ、入力層及び出力層の出力値yは、y=Uとする。
【0107】
階層型ネットワークのシステム同定は、望ましい入出力が数組用意され(これを教示信号と呼ぶ)、Neural Networkがシステムの入出力関係を十分に近似するように重みを修正していくことによって行われる(これを学習と呼ぶ)。主な学習方法としてバックプロパゲーション法とカルマン・ニューロ法とがあるが、本実施の形態ではバックプロパゲーション法が用いられる。アルゴリズムは以下のようになる。
【0108】
〔ステップ1:各層の演算〕
入力層に与えられた信号から、以下の式(16)(17)で表されるニューロンモデルに従って、中間層及び出力層を演算する。
【0109】
すなわち、中間層の第jニューロンの出力Hは、式(16)のニューロンモデルを用いることにより得られる。
【0110】
【数10】
Figure 0004291992
なお、I:入力層第iニューロンの出力、H:中間層第jニューロンの出力、Wji:入力層第iニューロンと中間層第jニューロンの間の重み係数、1:入力層のニューロン数、f0:応答関数(シグモイド関数を使用)、を意味している。
【0111】
一方、出力層第kニューロンの出力Oは、式(17)のニューロンモデルを用いることにより得られる。
【0112】
【数11】
Figure 0004291992
なお、Hj:中間第jニューロンの出力、O:出力層第kニューロンの出力、Wkj:中間層第jニューロンと出力層第kニューロンの間の重み係数、m:中間層のニューロン数、を意味している。
【0113】
〔ステップ2:重みWの演算〕
出力層の第kニューロンの出力Oと出力層の第kニューロンの教示信号yとの自乗誤差の和を最小化するように、ネットワークの重み係数を修正して学習する。中間層と出力層との重み係数の学習は、以下の式(18)を用いてΔWkjを演算し、Wkjを修正するようになっている。
【0114】
Wkj(t+1)=Wkj(t)+ΔWkj(t)
ΔWkj(t)=−ε・dk(t)・Hj(t) …………(18)
dk(t)=Ok(t)−yk(t)
なお、t:学習回数、ε:1回の修正の大きさを決めるパラメータ、d:出力層の誤差、を意味している。
【0115】
一方、入力層と中間層との重み係数の学習は、以下の式(19)を用いてΔwjiを演算し、Wjiを修正するようになっている。
【0116】
【数12】
Figure 0004291992
なお、dj:中間層の逆伝搬誤差、f0:f0の微分、を意味している。
【0117】
更に、振動を減らし、学習の収束を早めるために、以下の式(20)を使う。
【0118】
ΔWkj(t)=−ε・dk(t)・Hj(t)+α・Wkj(t-1)
ΔWji(t)=−ε・dj(t)・Ii(t)+α・Wji(t-1) ………(20)
なお、α:安定のためのパラメータ、ε:1−α、を意味している。
【0119】
この学習の結果として得られる重み係数が、予測モデルとして記憶されるようになっている。
【0120】
また、ニューラルネットワークを用いた時には、過学習によるモデルのオーバーフィッティングが生じてしまうことが考えられるため、特願2000−021074「短気需要予測装置」に記憶されているようなオーバーフィティングを抑制する手段を付加することが好ましい。
【0121】
本実施の形態のニューラル・ネットワークにおいて、式(16)のIiは、上述の第1の実施の形態において説明した重回帰分析を用いて圧力推定モデルを構築した際に使用した入力値(オンラインデータ(圧力、流量)及び一部のオフラインデータ)に該当する。また、式(18)のyk(t)は、圧力推定モデルを構成するオフラインデータ(各オフライン計測ポイントにおける配水管2内の圧力)に対応する。その他の変数は、いわゆる内部変数(入出力以外の変数)に該当する。
【0122】
他の構成は図1及び図2に示す第1の実施の形態と略同一である。
【0123】
本実施の形態において、図1及び図2に示された第1の実施の形態と同一部分には同一符号を付して詳細な説明は省略する。
【0124】
本実施の形態の圧力推定モデル構築システム4においても、上述の第1の実施の形態と同様に、配水ブロック1の配水管2のうちオンライン計測ポイント15において計測されたオンラインデータと、オフライン計測ポイント16において計測されたオフラインデータとは、データ取得手段29、統計値演算手段30、統計値DB28、正規化手段31及びクラスタリング手段23によって、いくつかのクラスターに分類される。
【0125】
そして、各オンラインデータと同一クラスターに分類された各オフラインデータに対応する各オフライン計測ポイント16における圧力推定モデル(第1圧力推定モデル)が、第1圧力推定モデル構築手段24によって構築される。この時、第1圧力推定モデル構築手段24は、ニューラル・ネットワークを用いて第1圧力推定モデルを構築する。そして、構築されたこれらの第1圧力推定モデルは、推定モデルDB27に送られて、当該推定モデルDB27に記憶される。
【0126】
一方、各オンラインデータと異なるクラスターに分類された各オフラインデータは、主成分演算手段25によって上述の主成分分析が行われて、各オフラインデータに対応する推定モデル入力値が求められる。そして、各オンラインデータと異なるクラスターに分類された各オフラインデータに対応する各オフライン計測ポイント16における圧力推定モデル(第2圧力推定モデル)が、第2圧力推定モデル構築手段26によって構築される。この時、第2圧力推定モデル構築手段26は、上述のニューラル・ネットワークと推定モデル入力値とを用いて圧力推定モデルを構築する。そして、構築されたこれらの第2圧力推定モデルは、推定モデルDB27に送られて、当該推定モデルDB27に記憶される。
【0127】
そして、推定モデルDB27に記憶されている第1圧力推定モデル及び第2圧力推定モデルによって構成された圧力推定モデルが、モデル表示手段32において表示されて、オペレータ等に知らされる。
【0128】
以上説明したように、本実施の形態の圧力推定モデル構築システム4においても、オフライン計測ポイント16における所定日時の圧力推定モデルが、オンラインで計測されているオンラインデータを用いた形式で構築される。このため、これにより、オフライン計測ポイント16における配水管2の圧力分布に関する推定モデルを、精度良く構築することができる。特に、本実施の形態においても、従来技術で必要とされていた配水管網に関する複雑な物理情報は不要なので、圧力推定モデル構築システム4を簡素化することができ、圧力推定モデル構築時間を大幅に短縮することができる。
【0129】
また、ニューラル・ネットワークを用いて圧力推定モデルを構築するので、2次以上の高次系の項も考慮して圧力推定モデルを構築することができ、非線形性の高いプロセスに対しても、精度良く圧力推定モデルを構築することができる。
【0130】
なお、本実施の一変形例として、統計値演算手段30や正規化手段31が設けられておらず、データ取得手段29によって取得されたオンラインデータ及びオフラインデータを直接的にクラスタリング手段23に送るような圧力推定モデル構築システム4であっても、上述した第2の実施の形態における場合と同様の作用・効果を奏しうる。
【0131】
第3の実施の形態
図5は、本発明の第3の実施の形態を示す図であり、圧力推定モデル構築システム全体の構成を示す概略図である。
【0132】
第3の実施の形態の圧力推定モデル構築システム4は、圧力推定装置11が支援手段35を更に有しており、当該支援手段35は、正規化手段31に接続される共に推定モデルDB27に接続された消火栓圧力推定手段36と、消火栓圧力推定手段36に接続された推定結果表示手段37と、を有している。
【0133】
消火栓圧力推定手段36は、現在時刻に対応するオンラインデータを正規化手段31から取得すると共に推定モデル記憶手段から圧力推定モデルを取得するようになっている。そして消火栓圧力推定手段36は、取得した現在時刻に対応するオンラインデータと圧力推定モデルとに基づいて、取得した圧力推定モデルに対応するオフライン計測ポイント16の配水管2内における現在時刻の圧力値を演算する機能を有している。
【0134】
推定結果表示手段37は、消火栓圧力推定手段36によって演算された圧力値を表示して、オペレータ等に当該圧力値を知らせることができるようになっている。
【0135】
他の構成は図1及び図2に示す第1の実施の形態と略同一である。
【0136】
図5において、図1及び図2に示された第1の実施の形態と同一部分には同一符号を付して詳細な説明は省略する。
【0137】
本実施の形態の圧力推定モデル構築システム4においても、上述の第1の実施の形態と同様に、配水ブロック1の配水管2のうちオンライン計測ポイント15において計測されたオンラインデータと、オフライン計測ポイント16において計測されたオフラインデータと、データ取得手段29と、統計値演算手段30と、統計値DB28と、正規化手段31と、クラスタリング手段23と、第1モデル構築手段と、主成分演算手段25と、第2モデル構築手段と、に基づいて、オフライン計測ポイント16における所定日時の圧力推定モデルが得られ、当該圧力推定モデルは推定モデルDB27に記憶される。
【0138】
その後、消火栓圧力推定手段36が、現在時刻に対応するオンラインデータを正規化手段31から取得すると共に、取得したオンラインデータに対応する圧力推定モデルを推定モデルDB27から取得する。そして、消火栓圧力推定手段36は、取得した現在時刻に対応するオンラインデータと圧力推定モデルとに基づいて、取得した圧力推定モデルに対応するオフライン計測ポイント16の配水管2内における現在時刻の圧力値を演算する。
【0139】
消火栓圧力推定手段36によって演算された現在時刻に対応する圧力値は、推定結果表示手段37に送られて表示され、オペレータ等に知らせられる。
【0140】
なお、推定結果表示手段37における表示方法はどのようなものであってもよい。例えば、推定した圧力の値そのものを表示したり、2D形式や3D形式の圧力値の等高線で表示したりすることができるようになっている。また、消火栓圧力推定手段36によって推定された圧力が、予め設定されている許容可能な圧力範囲(運用圧力範囲)を逸脱する場合であっても、推定結果表示手段37は当該推定された圧力を表示することができるようになっている。
【0141】
以上説明したように、本実施の形態の圧力推定モデル構築システム4は、オンラインで計測されているオンラインデータを用いた形式で、各オフライン計測ポイント16における圧力推定モデルを構築することができる。
【0142】
更に、本実施の形態によれば、消火栓圧力推定手段36によって各オフライン計測ポイント16における現在時刻に対応する具体的な圧力値を推定することができる。
【0143】
次に、本実施の形態の一変形例について説明する。
【0144】
本発明による力推定モデル構築システムは、統計値演算手段30や正規化手段31が設けられていなくてもよい。
【0145】
この場合、データ取得手段29によって取得されたオンラインデータ及びオフラインデータは、直接的にクラスタリング手段23に送られる。クラスタリング手段23は、オンライン計測データDB21及びオフライン計測データDB22からデータ取得手段29を介して送られてくるオンラインデータ及びオフラインデータをクラスター分析するようになっている。
【0146】
また、消火栓圧力推定手段36は、オンライン計測データDB21に接続され、当該オンライン計測データDB21から現在時刻に対応するオンラインデータを取得するようになっている。
【0147】
他の構成は、上述した図5に示す第3の実施の形態と略同一であり、上述の第3の実施の形態と同一部分には同一符号を付して詳細な説明は省略する。
【0148】
本変形例においても、各オフライン計測ポイント16における圧力推定モデルが、第1圧力推定モデル構築手段24及び第2圧力推定モデル構築手段26によって構築され、推定モデルDB27に記憶される。
【0149】
そして、消火栓圧力推定手段36は、現在時刻に対応するオンラインデータをオンライン計測データDB21から取得すると共に、このオンラインデータに対応する圧力推定モデルを推定モデルDB27から取得する。そして、消火栓圧力推定手段36は、取得したオンラインデータと圧力推定モデルとに基づいて、現在時刻に対応する各オフライン計測ポイント16における配水管2内の具体的な圧力値を演算する。
【0150】
消火栓圧力推定手段36によって演算された圧力値は、推定結果表示手段37に送られて表示される。
【0151】
以上説明したように、本変形例においても、圧力推定モデル構築システム4は、オンラインで計測されているオンラインデータを用いた形式で、各オフライン計測ポイント16における圧力推定モデルを構築することができる。
【0152】
また、消火栓圧力推定手段36によって各オフライン計測ポイント16における現在時刻に対応する具体的な圧力値を推定することができる。このため、例えば、配水ブロック1の全域に張り巡らされた配水管2の各箇所において、配水管内の圧力が、許容範囲(例えば、許容最低圧力以上であって許容最高圧力以下の範囲)となっているか否かを検証したりすることができる。
【0153】
なお、支援手段35の圧力推定手段36において必要とされるデータは、第1圧力推定モデル構築手段24及び第2圧力推定モデル構築手段26で使用した形式のデータである。従って、各モデル構築手段24,26が正規化されたデータを使用している場合には、圧力推定手段36も正規化されたデータを必要とし、各モデル構築手段24,26が計測したそのままのデータを使用している場合には、圧力推定手段36も計測したそのままのデータを必要とする。
【0154】
また、本実施の形態では、圧力推定手段36に入力されるデータは現在時刻に対応するものが想定されており、圧力推定手段36は、全てのオンラインデータを用いて圧力を推定するので、圧力計測器10a及び流量計測器10bから送られてくるオンラインデータは、全て圧力推定手段36に入力されるようになっている。
【0155】
第4の実施の形態
図6は、本発明の第4の実施の形態を示す図であり、圧力推定モデル構築システム全体の構成を示す概略図である。
【0156】
第4の実施の形態の圧力推定モデル構築システム4は、圧力推定装置11が検証手段40を更に備えており、当該検証手段40は、日時設定手段41と、日時設定手段41に接続されると共にオンライン計測データDB21に接続された日時指定データ取得手段42と、を有している。
【0157】
日時設定手段41は、各オフライン計測ポイント16における過去の所定日時の圧力を推定したい場合に、オペレータ等によって当該過去の所定日時が入力されるようになっている。
【0158】
なお、一定の検証期間の各オフライン計測ポイント16における圧力を推定する場合には、検証開始日時と検証終了日時とを設定するという方法が考えられる。検証開始日時と検証開始日時とを同一日とすることにより、特定日時の検証が可能となる。
【0159】
日時指定データ取得手段42は、日時設定手段41に入力された過去の所定日時に対応するオンラインデータをオンライン計測データ記憶手段から取得して、取得したオンラインデータを正規化手段31に送るようになっている。
【0160】
正規化手段31は、日時指定データ取得手段42から送られくるオンラインデータを正規化して、正規化したオンラインデータを消火栓圧力推定手段36に送る機能を更に有している。
【0161】
消火栓圧力推定手段36は、日時指定データ取得手段42から正規化手段31を介して送られくるオンラインデータに対応する圧力推定モデルを圧力推定モデル記憶手段から取得して、日時指定データ取得手段42から正規化手段31を介して送られくるオンラインデータと取得した圧力推定モデルとに基づいて、過去の所定日時における圧力推定値を演算する機能を更に有している。
【0162】
他の構成は図5に示す第3の実施の形態と略同一である。
【0163】
図6において、図5に示された第3の実施の形態と同一部分には同一符号を付して詳細な説明は省略する。
【0164】
本実施の形態の圧力推定モデル構築システム4においても、上述の第1の実施の形態と同様に、配水ブロック1の配水管2のうちオンライン計測ポイント15において計測されたオンラインデータと、オフライン計測ポイント16において計測されたオフラインデータと、データ取得手段29と、統計値演算手段30と、統計値DB28と、正規化手段31と、クラスタリング手段23と、第1モデル構築手段と、主成分演算手段25と、第2モデル構築手段と、に基づいて、オフライン計測ポイント16における所定日時の圧力推定モデルが得られ、当該圧力推定モデルは推定モデルDB27に記憶される。
【0165】
そして、圧力を推定したい過去の所定日時が、オペレータ等によって日時設定手段41に入力される。日時設定手段41に入力された所定日時は、日時指定データ取得手段42に送られる。
【0166】
日時指定データ取得手段42は、日時設定手段41から送られてきた所定日時に対応するオンラインデータを、オンライン計測データDB21から取得する。そして、オンライン計測データDB21取得された当該オンラインデータは、日時指定データ取得手段42から正規化手段31に送られる。
【0167】
正規化手段31は、正規化手段31から送られてくるオンラインデータを正規化する。そして、正規化手段31は、正規化した当該オンラインデータを消火栓圧力推定手段36に送る。
【0168】
消火栓圧力推定手段36は、正規化手段31から送られてくるオンラインデータに対応する圧力推定モデルを推定モデルDB27から取得する。そして、消火栓圧力推定手段36は、正規化手段31から送られくるオンラインデータと、当該オンラインデータに対応する圧力推定モデルと、に基づいて、各オフライン計測ポイント16の配水管2内における過去の所定日時の圧力値を演算する。
【0169】
消火栓圧力推定手段36によって演算された過去の所定日時に対応する圧力値は、推定結果表示手段37に送られて表示され、オペレータ等に知らせられる。
【0170】
なお、推定結果表示手段37は、演算した圧力値を様々な手法で表示することが可能であり、例えば、一定の検証期間における圧力値を連続的に表示したり(連続再生表示)、当該検証期間のうちの任意時刻における圧力値を表示したり(任意時刻表示)、予め定められた指定時間前からの圧力偏差(圧力変動)を表示したりすることができる。なお、ここでいう「予め定められた指定時間」は、例えば、日時設定手段41を介してオペレータ等によって設定可能であるが、これに限定されるものではない。
【0171】
以上説明したように、本実施の形態の圧力推定モデル構築システム4では、オンラインで計測されているオンラインデータを用いた形式で、各オフライン計測ポイント16における圧力推定モデルを構築することができ、更に、消火栓圧力推定手段36によって各オフライン計測ポイント16における過去の所定日時に対応する具体的な圧力値を推定することができる。
【0172】
【発明の効果】
以上説明したように、本発明の圧力推定モデル構築システムよれば、配水ブロックに張り巡らされた配水管のうち、オンライン計測ポイントにおける配水管内の圧力分布はオンラインデータとしてオンラインで得ることができ、オフライン計測ポイントにおける配水管内の圧力分布は、オンラインデータと予め計測されていたオフラインデータとに基づいて構築される圧力推定モデルによって得ることができる。従って、本発明によれば、配水ブロックにおけるオンライン計測ポイント及びオフライン計測ポイントにおける配水管内の圧力を精度良く求めることが可能となる。
【図面の簡単な説明】
【図1】本発明の第1の実施の形態における圧力推定モデル構築システム全体の構成を示す概略図である。
【図2】クラスター分析によって各クラスターに分類されたオンラインデータ及び各オフラインデータを示す。
【図3】ニューラル・ネットワークで用いられる「ユニット」を説明するための図である。
【図4】ニューラル・ネットワークで用いられる「入力層」と「中間層」と「出力層」との関係を示す図である。
【図5】本発明の第3の実施の形態を示す図であり、圧力推定モデル構築システム全体の構成を示す概略図である。
【図6】本発明の第4の実施の形態を示す図であり、圧力推定モデル構築システム全体の構成を示す概略図である。
【図7】従来の圧力推定モデル構築システム全体の構成を示す概略図である。
【符号の説明】
1 配水ブロック
2 配水管
3 配水注入部
4 圧力推定モデル構築システム
10a 圧力計測器
10b 流量計測器(オンライン計測手段)
11 圧力推定装置
15 オンライン計測ポイント
16 オフライン計測ポイント
21 オンライン計測データDB(オンライン計測データ記憶手段)
22 オフライン計測データDB(オフライン計測データ記憶手段)
23 クラスタリング手段
24 第1圧力推定モデル構築手段
25 主成分演算手段
26 第2圧力推定モデル構築手段
27 推定モデルDB(圧力推定モデル記憶手段)
28 オンライン計測データDB(オンライン計測データ記憶手段)
29 データ取得手段
30 統計値演算手段
31 正規化手段
32 モデル表示手段[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a pressure estimation model construction system that constructs an estimation model related to a pressure distribution in a water distribution pipe stretched around a water distribution block.
[0002]
[Prior art]
A distribution pipe network for distributing drinking water to consumers such as ordinary households plays an important role as one of the urban infrastructures. In order to realize a stable water supply to consumers, it is required to always maintain an appropriate pressure in the distribution pipe when managing the distribution pipe network.
[0003]
On the other hand, by grasping the pressure state in the water distribution pipe, (1) whether water is being supplied from the water supply point such as a water reservoir to the water distribution pipe at an appropriate water pressure, or (2) where the water pressure is insufficient It is possible to obtain information such as whether or not there is (3) an area where the water pressure is excessive. For this reason, in order to keep the inside of the water pipe at an appropriate pressure, it is very effective to accurately grasp the pressure state in the water pipe.
[0004]
Various methods have been considered for grasping the pressure state in the water distribution pipe. For example, a pipe network analysis method as shown in FIG. 7 has been widely used.
[0005]
As shown in FIG. 7, the distribution pipe network is stretched so that water can be distributed to the demand point 45 such as a fire hydrant installed in the entire area of the distribution block 1, and water from the distribution reservoir is injected into the distribution pipe. It is supplied via the section 3. And the pressure measuring instrument 10a and the flow measuring instrument 10b are installed in the predetermined location of the water distribution pipe 2, The data about the pressure in the water distributing pipe 2 and the water flow rate are sometimes obtained by this pressure measuring instrument 10a and the flow measuring instrument 10b. It is measured every moment. The measured pressure data and flow rate data are sent online from the measuring instruments 10a and 10b to the online data DB (online data database) 21 and stored as online data together with the measurement date and time.
[0006]
On the other hand, when an operator or the like wants to know the pressure state in the water pipe 2 at a specific date and time, the specific date and time is input to the date and time setting means 50. The input date / time is sent from the date / time setting means 50 to the data acquisition means 51. The data acquisition means 51 acquires from the online data DB 21 online data whose measurement date corresponds to the specific date sent from the date setting means 50, sends this online data to the data display means 52, and also analyzes 53. To send to.
[0007]
The data display means 52 displays the sent online data and presents the online data to an operator or the like.
[0008]
The analysis means 53 is based on online data sent from the data acquisition means 51 and physical information sent from a separately provided physical information DB (physical information database) 54 by pipe network analysis technology. It is designed to analyze the pressure at each location of the water distribution network.
[0009]
The physical information stored in the physical information DB 54 is civil engineering information such as the diameter and pipe length of the water pipe 2 at each location of the water distribution network, and the analysis means 53 determines the pressure at each location of the water distribution network. Contains useful information when analyzing.
[0010]
The pressure and the like at each location of the water distribution pipe network analyzed by the analysis means 53 are presented to the operator or the like by the analysis result display means 55.
[0011]
Then, the operator manages the pressure in the water distribution pipe 2 in consideration of the information presented by the analysis result display means 55. For example, the water distribution block 1 does not cause an area with insufficient water pressure or excessive water pressure. Whether or not water is appropriately distributed to each demand point 45 is managed.
[0012]
[Problems to be solved by the invention]
Conventionally, the pressure state in the water distribution pipe 2 is grasped by analyzing the pressure and the like at each location of the water distribution pipe network by the pipe network analysis method as described above.
[0013]
However, in the pipe network analysis method as described above, the pressure or the like at each location of the water distribution pipe network is determined based only on the measured values of the pressure measuring device 10a or the flow rate measuring device 10b installed at a predetermined location of the water distribution pipe network. Analyzing. For this reason, when the water distribution block 1 is wide or the water distribution pipe network is formed in a complicated manner, and the appropriate number of pressure measuring instruments 10a and flow measuring instruments 10b are not properly arranged. It is difficult to perform an accurate and reliable analysis.
[0014]
Moreover, analysis results such as pressure at each location of the distribution pipe network are greatly influenced by physical information stored in the physical information DB 54, and therefore it is necessary to use appropriate physical information. The physical information is determined according to the size and configuration of the water distribution pipe network. However, it is necessary to grasp the civil engineering structure of the water distribution pipe network necessary for determining the physical information, to convert the civil engineering structure into data, and to obtain each demand point 45. The work such as the allocation of the demand amount for a large amount of labor requires a lot of labor and a lot of analysis time. Further, in order to accurately analyze the pressure and the like at each location of the water distribution pipe network, it is necessary to accurately perform operations such as allocation of the demand amount to each demand point 45. However, it is very difficult to perform such work accurately.
[0015]
The present invention has been made in consideration of such points, and an object of the present invention is to provide a pressure estimation model construction system capable of accurately obtaining a pressure distribution in a distribution pipe stretched around a distribution block.
[0016]
[Means for Solving the Problems]
The present invention is a pressure estimation model construction system for constructing an estimation model relating to a pressure distribution in a water distribution pipe stretched around a water distribution block, and in the water distribution pipe at an online measurement point provided at one or more locations in the water distribution pipe. Online measurement means that measures at least one of pressure and water flow rate as online data, and sends the online data to the subsequent stage, and one or more locations different from the online measurement point in the water distribution pipe The pressure in the distribution pipe measured in advance at the offline measurement point is stored as offline data, and the offline measurement data storage means having a function of sending the offline data to the subsequent stage, and the subsequent stage of the online measurement means and the offline measurement data storage means Online measurement provided Clustering means having a function of classifying online data sent from the stage and offline data sent from the offline measurement data storage means into each cluster by cluster analysis, and provided on the subsequent stage of the clustering means. For each offline data classified into the same cluster as the data, a first pressure estimation model that is a pressure model in the distribution pipe at the offline measurement point corresponding to each offline data is constructed based on each online data classified into the same cluster The first pressure estimation model constructing means and the clustering means are provided at a subsequent stage, and principal component analysis is performed on each offline data classified into a cluster different from each online data, and an estimation model corresponding to each offline data is obtained. A principal component calculation means having a function for calculating an input value and an estimated model input corresponding to each offline measurement data for each offline data provided in the subsequent stage of the principal component calculation means and classified into a cluster different from each online data A second pressure estimation model construction means for constructing a second pressure estimation model that is a pressure model in the distribution pipe at an offline measurement point corresponding to each offline, a first pressure estimation model construction means, and a second pressure estimation. A pressure estimation model connected to the model construction means and configured by a first pressure estimation model constructed by the first pressure estimation model construction means and a second pressure estimation model constructed by the second pressure estimation model construction means And a pressure estimation model storage means for storing the pressure estimation model storage system System.
[0017]
According to the pressure estimation model construction system of the present invention, a pressure estimation model related to the pressure in the distribution pipe at the offline measurement point is constructed based on online data sent online from the online measurement point.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
[0019]
First embodiment
1 and 2 are diagrams showing a first embodiment of the present invention. FIG. 1 is a schematic diagram showing a configuration of the entire pressure estimation model construction system. FIG. 2 shows online data and each offline data classified into each cluster by cluster analysis.
[0020]
As shown in FIG. 1, in order to supply water to a plurality of demand points 45 such as fire hydrants in the water distribution block 1, a water distribution pipe 2 is stretched over the entire area of the water distribution block 1. Thereby, the water sent from the distribution reservoir etc. is supplied to the water distribution pipe 2 in the water distribution block 1 via the water distribution injection | pouring part 3, and is sent to each demand point 45. FIG.
[0021]
A pressure estimation model construction system 4 for constructing a pressure estimation model at each location of such a water pipe 2 includes a pressure measuring instrument 10a and a flow measuring instrument 10b (online measuring means), and the pressure measuring instrument 10a and the flow measuring instrument. And a pressure estimation device 11 connected to the vessel 10b.
[0022]
The pressure measuring instrument 10a and the flow measuring instrument 10b are online data on the pressure and water flow rate in the distribution pipe 2 at the online measurement point 15 provided in one or more places (three places in the present embodiment) of the distribution pipe 2. It has the function to measure as. The pressure measuring device 10a and the flow rate measuring device 10b have a function of sending online data measured in this way to a subsequent stage.
[0023]
The pressure estimation device 11 includes an online measurement data DB 21 (online measurement data storage means), an offline measurement data DB 22 (offline measurement data storage means), a pressure measurement instrument 10a, and an pressure measurement instrument 10a and a flow measurement instrument 10b. Clustering means 23 provided in the subsequent stage of the flow rate measuring device 10b and the offline measurement data DB 22, a first pressure estimation model construction means 24 provided in the subsequent stage of the clustering means 23, and a main part provided in the subsequent stage of the clustering means 23 The component calculation means 25, the second pressure estimation model construction means 26 provided in the subsequent stage of the principal component calculation means 25, the estimation model connected to the first pressure estimation model construction means 24 and the second pressure estimation model construction means 26 DB27 (pressure estimation model storage means), pressure measuring instrument 10a and flow meter Online measurement data DB 21 (online measurement data storage means) provided between the device 10 b and the clustering means 23, and data acquisition means 29 provided between the online measurement data DB 21 and offline measurement data DB 22 and the clustering means 23. The statistical value calculating means 30 provided between the data acquisition means 29 and the clustering means 23, the normalizing means 31 provided between the statistical value calculating means 30 and the clustering means 23, and the estimated model DB 27. Connected model display means 32.
[0024]
The offline measurement data DB 22 is preliminarily measured by the offline data measurement means 33 at the offline measurement points 16 provided at one or more locations (three locations in the present embodiment) different from the online measurement points 15 in the distribution pipe 2. The pressure in the distribution pipe 2 is stored as offline data. That is, the offline measurement data DB 22 stores the pressure in the water distribution pipe 2 measured in advance at the offline measurement point 16 such as a fire hydrant together with the measurement date and time as offline data.
[0025]
As the offline data measuring means 33, for example, a handy type pressure gauge or the like can be used. Then, the pressure in the distribution pipe 2 measured for several days in advance at the offline measurement point 16 by the pressure gauge or the like is stored in the offline measurement data DB 22 as offline data. The offline measurement data DB 22 can send the stored offline data to the data acquisition means 29 provided in the subsequent stage. The offline measurement data DB 22 stores offline data at all or a part of the offline measurement points 16 and can send it to the subsequent stage.
[0026]
The online measurement data DB 21 stores measurement values obtained by the pressure measuring instrument 10a and the flow rate measuring instrument 10b (online measuring means) together with the measurement date and time.
[0027]
Note that the measurement date / time of online data stored in the online measurement data DB 21 and the measurement date / time of offline data stored in the offline measurement data DB 22 correspond to each other.
[0028]
The data acquisition means 29 has a function of acquiring online data stored in the online measurement data DB 21 and acquiring offline data corresponding to the measurement time of the online data acquired from the online measurement data DB 21 from the offline measurement data DB 22. is doing. The data acquisition unit 29 has a function of sending the acquired online data and offline data to the subsequent stage.
[0029]
The statistical value calculation means 30 has a function of statisticalizing the online data and offline data that are sent.
[0030]
In this embodiment, the “statistication” of these online data and offline data is the sum, minimum, maximum, range, standard deviation, variance, average, median, coefficient of variation, skewness, kurtosis, Such statistical items are basically used. However, the statistical value calculation means 30 can also “statistically” the online data and offline data based on other statistical items.
[0031]
The statistical value calculation means 30 has a function of sending statisticalized online data and offline data to the subsequent stage. Online data and offline data sent from the statistical value calculation means 30 are stored in the statistical value DB 28 and then sent to the normalization means 31.
[0032]
The normalizing means 31 has a function of normalizing the sent online data and offline data and sending them to the subsequent stage. For this reason, in the present embodiment, the online data and offline data normalized by the normalizing means 31 are sent to the clustering means 23 provided at the subsequent stage of the normalizing means 31.
[0033]
The normalizing means 31 in the present embodiment normalizes using online data and offline data stored in the statistical value DB 28, and the “average value” and “ Based on the “standard deviation”, the following formulas (1a) and (1b) are used to convert and normalize the online data and offline data so that the average = 0.0 and the variance = 1.0. ing.
[0034]
[Expression 1]
Figure 0004291992
That is, each data item of online data and offline data acquired by the data acquisition means 29 is converted by the equations (1a) and (1b). For example, as shown in FIG. 1, as the online data, one point of data regarding the water flow rate in the distribution pipe 2 and two points of data regarding the pressure in the distribution pipe 2 are sometimes obtained by the pressure measuring instrument 10a and the flow measuring instrument 10b. Consider the case where data is collected every moment and the data acquisition means 29 acquires online data for several hours (one point for water flow rate data and two points for pressure data).
[0035]
In this case, the acquired data is assumed to be X1t, X2t, and X3t (where t represents time). First, X1t is changed to x in the equations (1a) and (1b).iTo obtain standardized data z, and then X2t is replaced by x in equations (1a) and (1b).iTo obtain standardized data z, and finally X3t is replaced with x in equations (1a) and (1b).iThus, the standardized data z is obtained. As a result of this work, online data (water flow data is 1 point, pressure data is 2 points), average data is 0 and standard deviation is 1 standard data (water flow data is 1 point, pressure data is 1 point) Data is converted to 2 points).
[0036]
Similarly, offline data is converted into offline data that is standardized with an average of 0 and a standard deviation of 1. When the online data and the offline data thus standardized are obtained, the values calculated by the statistical value calculation means 30 are the average value and standard deviation of the base data in the equations (1a) and (1b). It has come to be used.
[0037]
The clustering means 23 includes online data sent from the pressure measuring instrument 10a and the flow measuring instrument 10b via the online measuring data DB 21, the data acquiring means 29, the statistical value calculating means 30, the statistical value DB 28, and the normalizing means 31. , Offline data sent from the offline measurement data DB 22 via the data acquisition means 29, the statistical value calculation means 30, the statistical value DB 28, and the normalization means 31, and has a function of classifying each cluster by cluster analysis. ing.
[0038]
Here, “cluster analysis” generally means an operation of grouping homogeneous samples from a sample. The cluster analysis is started from a state in which the sample belongs to an unknown group and the number of groups is unknown. The purpose of the cluster analysis is to classify specimens into homogeneous groups and clusters.
[0039]
Specifically, the cluster analysis of online data and offline data by the clustering means 23 of the present embodiment is performed as follows. In the present embodiment, the target of cluster analysis is only data related to “pressure”, and data related to “water flow rate” is not the target.
[0040]
(1) First, the distance between solids and the distance between clusters are defined. Here, “solid” refers to one signal included in online data or offline data. For example, various formulas as shown in Table 1 below have been proposed as formulas for indicating the distances between the solids. In this embodiment, the “Euclidean distance” shown in Table 1 is used. Define the distance between solids. On the other hand, for example, various formulas as shown in Table 2 have been proposed as formulas for indicating the distance between clusters. In this embodiment, the distance between clusters is calculated using the Ward method shown in Table 2. Define.
[0041]
[Table 1]
Figure 0004291992
[Table 2]
Figure 0004291992
In Tables 1 and 2, Xa and Xb represent online data (pressure) or offline data, d (Xa, Xb) represents the distance between Xa and Xb, and dab → cRepresents a distance between a certain cluster AB and online data or offline data or cluster C.
[0042]
(2) Next, the distance between all the solids is calculated.
[0043]
(3) Next, the clusters or solids having the shortest distance between the solids are merged into one cluster.
[0044]
(4) Next, the clusters created in (3) above are regarded as new solids, and the distances between all the solids are calculated.
[0045]
{Circle around (5)} Then, the above steps {circle around (1)} to {circle around (4)} are repeated to finish when all the solids are included in one cluster.
[0046]
In the present embodiment, according to the above (1) to (5), for example, the result of cluster analysis as shown in FIG. 2 can be obtained. In FIG. 2, the X axis (horizontal axis) indicates each offline measurement point and each online measurement point corresponding to each online data and each offline data, and the Y axis (vertical axis) indicates each online data and each offline data. It shows the similarity (distance) in cluster analysis for data. Also, the lines in FIG. 2 represent that they can be treated as the same cluster at the distance to which the lines are connected.
[0047]
The first pressure estimation model construction means 24 assigns each offline data classified into the same cluster as each online data, based on each online data classified into the same cluster, at the offline measurement point 16 corresponding to each offline data. A first pressure estimation model that is a pressure model in the water pipe 2 is constructed. More specifically, the first pressure estimation model construction means 24 of the present embodiment constructs the first pressure estimation model using multiple regression analysis, and is classified into the same cluster as each offline data. Online data is used as an input value for multiple regression analysis.
[0048]
Hereinafter, “multiple regression analysis” will be described.
[0049]
In the multiple regression analysis, explanatory variables {xi1, Xi2, ... xip} And the objective variable yiIt is assumed that the following linear relationship is established between (i = 1, 2,..., N).
[0050]
[Expression 2]
Figure 0004291992
Βi: Partial regression coefficient, ei: Indicates a residual.
[0051]
Each residual e in equation (2)i"Residual eiAre independent of each other and normal distribution N (0, σ2) ”(Residual condition). Then, when Expression (2) is expressed in matrix form, the following Expression (3) is obtained.
[0052]
y = zβ + e (3)
The matrix in equation (3) is as shown below.
[0053]
[Equation 3]
Figure 0004291992
[Expression 4]
Figure 0004291992
And b0, B1, ..., bMIs ελIs determined so as to minimize the sum of squares (see Expression (7) below).
[0054]
[Equation 5]
Figure 0004291992
In equation (7), the unknown is b0, B1, ... bpAnd S is b0, B1, ..., bpIs a quadratic function for b that minimizes the function S0, B1, ..., bpB S0, B1, ..., bpAnd can be obtained as a solution of simultaneous linear equations with a value of 0. When the above is solved and arranged, simultaneous equations such as the following equation (8) are obtained.
[0055]
[Formula 6]
Figure 0004291992
Where SjjIs xjDeviation sum of squares, SjkIs xjAnd xkDeviation product sum, SjyIs xjAnd the product of the deviations of y and are expressed as in the following equation (9).
[0056]
[Expression 7]
Figure 0004291992
Therefore, the partial regression coefficient is obtained by the following equation (11).
[0057]
b = S-1M …………… (11)
The constant term is obtained by the following equation (12).
[0058]
[Equation 8]
Figure 0004291992
In the present embodiment, in the above-described multiple regression analysis, the explanatory variable x corresponds to the principal component score obtained by online data or principal component analysis means, and the target variable y corresponds to offline data. Here, the main component score indicates the value of the main component of each sample.
[0059]
Then, the first pressure estimation model constructed using the multiple regression analysis described above is sent from the first pressure estimation model construction means 24 to the estimation model DB 27.
[0060]
The principal component calculation means 25 has a function of performing principal component analysis on each offline data classified into a cluster different from each online data, and calculating an estimated model input value corresponding to each offline data. That is, the principal component calculation means 25 performs principal component analysis on the cluster to which the closest online data belongs for each offline data classified into a cluster different from each online data in the clustering means 23, and each online data The estimated model input value for each offline data classified into different clusters is calculated. The calculated estimated model input value is sent from the principal component calculation means 25 to the second pressure estimation model construction means 26 together with each online data and offline data.
[0061]
Here, “principal component analysis” is generally a method of summarizing information having multiple types of characteristic values that are correlated with each other into a small number of general characteristic values that are uncorrelated with each other.
[0062]
Principal component analysis generally involves p variables x1, X2, ..., xpInformation (m) satisfying the following conditions (a) and (b) (m ≦ p) total characteristic value (formula (14)) z1, Z2, ..., zmMeans to summarize, z1Is the first principal component, z2Is the second principal component, zmIs called the m-th principal component.
[0063]
z1= L11x1+ L12x2+ ... + l1pxp
z2= L21x1+ L22x2+ ... + l2pxp
………………………… (14)
zm= Lm1x1+ Lm2x2+ ... + lmpxp
[Equation 9]
Figure 0004291992
Condition (a)  zlAnd zkThe correlation with (k is not l; k, l = 1, 2,..., M) is all zero.
[0064]
Condition (b)  z1Variance (x1, X2, ..., xp) Is the maximum of the variances of any linear expression. z2The variance of is z1It is the largest of all linear equations unrelated to the variance of. Similarly, zmThe variance of z is1, Z2, ..., zm-1It is the largest among the linear equations unrelated to all of the above.
[0065]
The above condition (b) is “main component z1, Z2, ... zmIs the original characteristic value x1, X2, ..., xpIt is the result of summarizing so that the loss of information of is minimized.
[0066]
In the present embodiment, x in the above-described principal component analysis.1~ XpCorresponds to on-line data and off-line data relating to the pressure subjected to cluster analysis by the clustering means 23.
[0067]
For example, when the result shown in FIG. 2 is obtained by the cluster analysis, first, the online data (pressure) corresponding to the online measurement point 15A and the measurement points 16K located on both sides of the online measurement point 15A in FIG. , Off-line data (pressure) corresponding to 16L, and x1~ XpAnd And the x1~ XpA pressure estimation model is generated by calculating a principal component score for. Next, the online data (pressure) corresponding to the online measurement point 15A, the offline data (pressure) corresponding to the offline measurement point located on both sides of the online measurement point 15A in FIG. X1~ XpX1~ XpThe principal component score for is calculated, and the pressure estimation model is calculated. By repeating such calculation, the pressure estimation models at the respective offline measurement points corresponding to the respective offline data are sequentially calculated, and the pressure estimation models at all the offline measurement points are obtained.
[0068]
The second pressure estimation model construction means 26 uses the offline measurement point 16 corresponding to each offline based on the estimated model input value corresponding to each offline data for each offline data classified into a cluster different from each online data. A second pressure estimation model that is a pressure model in the water distribution pipe 2 is constructed. More specifically, the second pressure estimation model construction unit 26 constructs the second pressure estimation model using the multiple regression analysis described above, and the corresponding estimation calculated by the principal component calculation unit 25. Model input values are used as input values for multiple regression analysis. Thereby, the 2nd pressure model in the distribution pipe 2 in the offline measurement point 16 corresponding to each offline data classified into a cluster different from each online data among the distribution pipes 2 stretched around the distribution block 1. A pressure estimation model is constructed. Then, the constructed second pressure estimation model is sent from the second pressure estimation model construction means 26 to the estimation model DB 27.
[0069]
The estimation model DB 27 includes a first pressure estimation model constructed and sent by the first pressure estimation model construction unit 24, and a second pressure estimation model constructed and sent by the second pressure estimation model construction unit 26. Are stored in the pressure estimation model.
[0070]
The model display means 32 can display the pressure estimation model stored in the pressure estimation model storage means.
[0071]
Next, the operation of the present embodiment having such a configuration will be described.
[0072]
At the online measurement point 15 in the water distribution pipe 2 of the water distribution block 1, the water pressure and the water flow rate are measured by the pressure measuring device 10a and the flow rate measuring device 10b. These measured values are sent online from the pressure measuring device 10a and the flow rate measuring device 10b to the online measurement data DB 21 and stored as online data together with the measurement date and time in the online measurement data DB 21.
[0073]
On the other hand, in the offline measurement point 16 of the distribution pipe 2 of the distribution block 1, the water pressure is measured in advance by a handy type pressure gauge or the like, and the measured water pressure data is combined with the measurement date and time as offline measurement data. Stored in the offline measurement data DB 22.
[0074]
When a predetermined date and time required by an operator or the like among the pressure estimation models at each offline measurement point 16 is input to the data acquisition unit 29, the data acquisition unit 29 stores online data corresponding to the input predetermined date and time online. While acquiring from measurement data DB21, the offline data corresponding to the input predetermined date is acquired from offline measurement data DB22. Then, the data acquisition unit 29 sends the acquired online data and offline data to the statistical value calculation unit 30 together with the input predetermined date and time.
[0075]
Then, the statistical value calculation means 30 statisticizes the sent online data and statistics the sent offline data. Note that the statistical items calculated by the statistical value calculation means 30 of the present embodiment include “average value” and “standard deviation” used by the normalization means 31.
[0076]
The online data and offline data statisticalized by the statistical value calculating means 30 are stored in the statistical value DB 28 and sent to the normalizing means 31.
[0077]
The online data and offline data sent to the normalizing means 31 are normalized by the normalizing means 31. At this time, the normalizing means 31 is based on the “average value” and “standard deviation” for the online data and offline data stored in the statistical value DB 28 and the above formulas (1a) and (1b). Online data and offline data are converted and “normalized” so that the average = 0.0 and the variance = 1.0.
[0078]
Then, the normalized online data and offline data are sent from the normalizing means 31 to the clustering means 23 installed at the subsequent stage.
[0079]
The online data and offline data sent to the clustering means 23 are subjected to cluster analysis by the clustering means 23 and classified into several clusters. Thereby, for example, a result of cluster analysis as shown in FIG. 2 can be obtained, and online data and offline data are classified into cluster A, cluster B, cluster C, and cluster D. For example, offline data related to the offline measurement point 16A is classified into cluster A, offline data related to the offline measurement point 16J is classified into cluster B, offline data related to the offline measurement point 16K and online data related to the online measurement point 15A are classified into cluster C. The offline data regarding the offline measurement point 16N and the online data regarding the online measurement point 15B are classified into the cluster D.
[0080]
Then, the first pressure estimation model construction means 24 constructs a pressure estimation model (first pressure estimation model) at each offline measurement point 16 corresponding to each offline data classified into the same cluster as each online data. At this time, the first pressure estimation model construction means 24 constructs the first pressure estimation model using the above-described multiple regression analysis.
[0081]
For example, when the result shown in FIG. 2 is obtained by the cluster analysis, the first pressure estimation model construction means applies to the clusters C and D to which the online measurement points 15A and 15B corresponding to the online data belong. 1 Build a pressure estimation model. At this time, in the cluster C, online data (pressure and water flow rate in the distribution pipe) corresponding to the online measurement point 15A is used as an input value when constructing the pressure estimation model, and in the cluster D, it corresponds to the online measurement point 15B. Online data (pressure in the distribution pipe and water flow rate) are used as input values when constructing the pressure estimation model.
[0082]
Then, these constructed first pressure estimation models are sent to the estimation model DB 27 and stored in the estimation model DB 27.
[0083]
On the other hand, each offline data classified into a cluster different from each online data is subjected to the above-described principal component analysis by the principal component calculation means 25, and an estimated model input value corresponding to each offline data is obtained. Then, a pressure estimation model (second pressure estimation model) at each offline measurement point 16 corresponding to each offline data classified into a cluster different from each online data is constructed by the second pressure estimation model construction means 26. At this time, the second pressure estimation model construction means 26 constructs a pressure estimation model using the above-described multiple regression analysis and the estimated model input value.
[0084]
For example, when the result shown in FIG. 2 is obtained by cluster analysis, the principal component calculation means 25 obtains estimated model input values for clusters A and B to which each online data does not belong. At this time, with respect to the cluster B, a cluster having a short distance among the clusters to which the online data belongs is sequentially searched. When a search result indicating that the cluster C to which the online data belongs is closest to the cluster B is obtained, the principal component of the cluster C becomes an input value when the pressure estimation model for the cluster B is constructed. . Similarly, cluster A is close to cluster C to which online data belongs. At this time, when viewed from the cluster A, the cluster B and the cluster C can be seen as the same cluster. Therefore, when the pressure estimation model of the cluster A is constructed, the main components of the cluster B and the cluster C are input values.
[0085]
And these constructed | assembled 2nd pressure estimation models are sent to estimation model DB27, and are memorize | stored in the said estimation model DB27.
[0086]
And the pressure estimation model comprised by the 1st pressure estimation model and the 2nd pressure estimation model memorize | stored in estimation model DB27 is displayed in the model display means 32, and an operator etc. are notified.
[0087]
As described above, according to the pressure estimation model construction system 4 of the present embodiment, the pressure estimation model at a predetermined date and time at the offline measurement point 16 is in a format using online data measured at the online measurement point 15. The statistical value calculation means 30, normalization means 31, clustering means 23, first pressure estimation model construction means 24, principal component calculation means 25, and second pressure estimation model construction means 26 are constructed. As a result, the pressure distribution in the distribution pipe at the online measurement point can be obtained online as online data, and the pressure distribution in the distribution pipe at the offline measurement point is constructed based on the online data and the offline data measured in advance. Can be obtained by a pressure estimation model. Thereby, it becomes possible to obtain | require accurately the pressure in the water distribution pipe in the online measurement point in a water distribution block, and an offline measurement point.
[0088]
In addition, since the pressure of the water distribution pipe 2 at the online measurement point 15 is measured by the pressure measuring instrument 10a and stored online in the online measurement data DB, each pressure measurement model at the online measurement point is not constructed. The pressure value of the water distribution pipe 2 at the online measurement point can be acquired.
[0089]
Further, in the present embodiment, complicated physical information about the water pipe 2 laid around the water distribution block 1 that is required in the prior art is unnecessary, and online data measured online and offline measured. The pressure estimation model at the offline measurement point 16 is constructed based on the offline data that is past pressure data at the offline measurement point 16. As described above, since the pressure estimation model can be constructed based only on the measured data, the pressure estimation model construction system 4 can be simplified, and the pressure estimation model construction time can be greatly shortened.
[0090]
In addition, by performing cluster analysis of online data and offline data via the statistical value calculation means 30 and normalization means 31, it is possible to classify each online data and each offline data into each cluster more stably and accurately. .
[0091]
In addition, it is also possible to handle at least one of the pressure and water flow rate in the water distribution pipe 2 at the online measurement point 15 as online data. Even in this case, the same operation and effect as the above-described embodiment can be obtained.
[0092]
Further, the second pressure estimation model construction unit 26 does not need to use all of the principal components calculated by the principal component calculation unit 25, and may use only a part.
[0093]
Next, a modification of the present embodiment will be described.
[0094]
In the pressure estimation model construction system according to this modification, the statistical value calculation means 30 and the normalization means 31 may not be provided.
[0095]
In this case, the online data and offline data acquired by the data acquisition unit 29 are sent directly to the clustering unit 23. The clustering means 23 performs cluster analysis on online data and offline data sent from the online measurement data DB 21 and offline measurement data DB 22 via the data acquisition means 29.
[0096]
As a result, each online data and each offline data is classified into each cluster, so that the first pressure estimation model construction means 24, the principal component calculation means 25, and the second pressure are the same as in the first embodiment described above. A pressure estimation model is constructed by the estimation model construction means 26.
[0097]
Therefore, also in this modification, the pressure estimation model at the off-line measurement point 16 can be constructed with high accuracy.
[0098]
Note that the clustering means can perform clustering using online data and offline data converted into various ways. In other words, the clustering means can perform cluster analysis using data converted into other forms such as a frequency spectrum in addition to data that has been statistically and normalized as described above and data that has been measured. it can.
[0099]
Second embodiment
3 and 4 are diagrams showing a second embodiment of the present invention. FIG. 3 is a diagram for explaining “units” used in the neural network. FIG. 4 is a diagram showing the relationship among the “input layer”, “intermediate layer”, and “output layer” used in the neural network.
[0100]
In the second embodiment, the first pressure estimation model construction means 24 constructs a first pressure estimation model using a neural network instead of multiple regression analysis. That is, the first pressure estimation model construction means 24 is a pressure model in the distribution pipe 2 at the offline measurement point 16 corresponding to each offline data classified into the same cluster as each online data by using a neural network. A first pressure estimation model is constructed. Then, the constructed first pressure estimation model is sent from the first pressure estimation model construction means 24 to the estimation model DB 27.
[0101]
On the other hand, the second pressure estimation model construction means 26 constructs the second pressure estimation model using the above-described neural network instead of the multiple regression analysis. That is, the second pressure estimation model construction means 26 is a pressure model in the distribution pipe 2 at the offline measurement point 16 corresponding to each offline data classified into a cluster different from each online data by using a neural network. A second pressure estimation model is constructed. The constructed second pressure estimation model is sent from the second pressure estimation model construction means 26 to the estimation model DB 27.
[0102]
Next, a “neural network” will be described with reference to FIGS. 3 and 4.
[0103]
A “neural network” generally refers to an artificial system that models a human nerve cell (neuron), and is expressed as an aggregate of “units” having multiple inputs and one output. The “unit” is shown in FIG. The units are connected by a line corresponding to the nerve fiber, and the signal is transmitted only in one direction on this line.*) ”Is input to the unit, and output after being converted by the response function. That is, the input signal as a whole system is successively transmitted while repeating the coupling and conversion output to each unit, and a final output signal is formed. Hierarchical and interconnected types have been proposed as unit connections, that is, network models.
[0104]
Signals in a hierarchical network are one-way traffic from the input layer to the output layer (see FIG. 4), and in general, information transmission is not considered within the layer.
[0105]
The interconnected network has a characteristic that the state of the network changes from an initial state to a stable state.
[0106]
When Neural Network is used for demand forecasting, input / output is nonlinear, so a three-layer hierarchical network using a sigmoid function as the response function is adopted. The response function is used only for the intermediate layer, and the output value y of the input layer and the output layer is y = U.
[0107]
Hierarchical network system identification is performed by modifying the weights so that Neural Network sufficiently approximates the input / output relationship of the system, and several sets of desirable input / outputs are prepared (called teaching signals). (This is called learning). As main learning methods, there are a back-propagation method and a Kalman-neuro method. In this embodiment, the back-propagation method is used. The algorithm is as follows.
[0108]
[Step 1: Calculation of each layer]
From the signal given to the input layer, the intermediate layer and the output layer are calculated according to the neuron model expressed by the following equations (16) and (17).
[0109]
That is, the output H of the j-th neuron in the intermediate layerjIs obtained by using the neuron model of equation (16).
[0110]
[Expression 10]
Figure 0004291992
Ii: Output of input layer i-th neuron, Hj: Output of the middle layer jth neuron, Wji: Weighting factor between input layer i-th neuron and intermediate layer j-th neuron, 1: number of neurons in input layer, f0: response function (using sigmoid function).
[0111]
On the other hand, the output O of the output layer kth neuronkIs obtained by using the neuron model of equation (17).
[0112]
## EQU11 ##
Figure 0004291992
Hj: output of intermediate jth neuron, Ok: An output of the output layer k-th neuron, Wkj: a weighting coefficient between the intermediate layer j-th neuron and the output layer k-th neuron, m: the number of neurons in the intermediate layer.
[0113]
[Step 2: Calculation of weight W]
Output O of the kth neuron in the output layerkAnd the teaching signal y of the k-th neuron in the output layerkIn order to minimize the sum of the square errors with, the weighting factor of the network is corrected and learning is performed. The weighting coefficient learning between the intermediate layer and the output layer is performed using ΔW using the following equation (18).kjAnd WkjHas been fixed.
[0114]
Wkj (t + 1) = Wkj (t) + ΔWkj (t)
ΔWkj (t) =-ε ・ dk (t) ・ Hj (t) (18)
dk (t) = Ok (t) −yk (t)
T: number of learning times, ε: parameter for determining the magnitude of correction once, dk: Indicates an error in the output layer.
[0115]
On the other hand, learning of the weighting coefficient between the input layer and the intermediate layer is performed by using the following equation (19) and ΔwjiAnd WjiHas been fixed.
[0116]
[Expression 12]
Figure 0004291992
Note that dj: intermediate layer back-propagation error, f0: differentiation of f0.
[0117]
Furthermore, in order to reduce vibration and speed up learning convergence, the following equation (20) is used.
[0118]
ΔWkj (t) =-ε ・ dk (t) ・ Hj (t) + α ・ Wkj (t-1)
ΔWji (t) = − ε · dj (t) · Ii (t) + α · Wji (t-1) ……… (20)
Note that α: a parameter for stability, ε: 1-α.
[0119]
The weighting coefficient obtained as a result of this learning is stored as a prediction model.
[0120]
In addition, when a neural network is used, overfitting of the model due to over-learning may occur. Therefore, overfitting as stored in Japanese Patent Application No. 2000-021074 “Short Demand Forecasting Device” is suppressed. It is preferable to add means.
[0121]
In the neural network of this embodiment, Ii in Expression (16) is an input value (online data) used when the pressure estimation model is constructed using the multiple regression analysis described in the first embodiment. (Pressure, flow rate) and some offline data). Moreover, yk (t) in Expression (18) corresponds to offline data (pressure in the distribution pipe 2 at each offline measurement point) constituting the pressure estimation model. Other variables correspond to so-called internal variables (variables other than input / output).
[0122]
Other configurations are substantially the same as those of the first embodiment shown in FIGS.
[0123]
In the present embodiment, the same parts as those in the first embodiment shown in FIGS. 1 and 2 are denoted by the same reference numerals, and detailed description thereof is omitted.
[0124]
Also in the pressure estimation model construction system 4 of the present embodiment, the online data measured at the online measurement point 15 in the distribution pipe 2 of the distribution block 1 and the offline measurement point, as in the first embodiment described above. The offline data measured in 16 is classified into several clusters by the data acquisition unit 29, the statistical value calculation unit 30, the statistical value DB 28, the normalization unit 31, and the clustering unit 23.
[0125]
Then, the first pressure estimation model construction means 24 constructs a pressure estimation model (first pressure estimation model) at each offline measurement point 16 corresponding to each offline data classified into the same cluster as each online data. At this time, the first pressure estimation model construction means 24 constructs a first pressure estimation model using a neural network. Then, these constructed first pressure estimation models are sent to the estimation model DB 27 and stored in the estimation model DB 27.
[0126]
On the other hand, each offline data classified into a cluster different from each online data is subjected to the above-described principal component analysis by the principal component calculation means 25, and an estimated model input value corresponding to each offline data is obtained. Then, a pressure estimation model (second pressure estimation model) at each offline measurement point 16 corresponding to each offline data classified into a cluster different from each online data is constructed by the second pressure estimation model construction means 26. At this time, the second pressure estimation model construction means 26 constructs a pressure estimation model using the above-described neural network and the estimated model input value. And these constructed | assembled 2nd pressure estimation models are sent to estimation model DB27, and are memorize | stored in the said estimation model DB27.
[0127]
And the pressure estimation model comprised by the 1st pressure estimation model and the 2nd pressure estimation model memorize | stored in estimation model DB27 is displayed in the model display means 32, and an operator etc. are notified.
[0128]
As described above, also in the pressure estimation model construction system 4 of the present embodiment, the pressure estimation model at the predetermined date and time at the offline measurement point 16 is constructed in a format using online data measured online. For this reason, the estimation model regarding the pressure distribution of the water distribution pipe 2 at the offline measurement point 16 can thereby be constructed with high accuracy. In particular, in this embodiment, the complicated physical information related to the water distribution pipe network that is required in the prior art is unnecessary, so the pressure estimation model construction system 4 can be simplified and the pressure estimation model construction time can be greatly increased. Can be shortened.
[0129]
In addition, since a pressure estimation model is constructed using a neural network, it is possible to construct a pressure estimation model in consideration of terms of second and higher order systems. A pressure estimation model can be constructed well.
[0130]
As a modification of the present embodiment, the statistical value calculation means 30 and the normalization means 31 are not provided, and the online data and offline data acquired by the data acquisition means 29 are sent directly to the clustering means 23. Even the pressure estimation model construction system 4 can provide the same operations and effects as in the second embodiment described above.
[0131]
Third embodiment
FIG. 5 is a diagram showing a third embodiment of the present invention, and is a schematic diagram showing a configuration of the entire pressure estimation model construction system.
[0132]
In the pressure estimation model construction system 4 according to the third embodiment, the pressure estimation device 11 further includes support means 35, which is connected to the normalization means 31 and connected to the estimation model DB 27. The fire hydrant pressure estimating means 36 and the estimation result display means 37 connected to the fire hydrant pressure estimating means 36 are provided.
[0133]
The fire hydrant pressure estimation means 36 acquires online data corresponding to the current time from the normalization means 31 and acquires a pressure estimation model from the estimation model storage means. And the fire hydrant pressure estimation means 36 calculates the pressure value of the present time in the distribution pipe 2 of the offline measurement point 16 corresponding to the acquired pressure estimation model based on the online data and pressure estimation model corresponding to the acquired current time. It has a function to calculate.
[0134]
The estimation result display means 37 can display the pressure value calculated by the fire hydrant pressure estimation means 36 and inform the operator or the like of the pressure value.
[0135]
Other configurations are substantially the same as those of the first embodiment shown in FIGS.
[0136]
In FIG. 5, the same parts as those of the first embodiment shown in FIGS. 1 and 2 are denoted by the same reference numerals, and detailed description thereof is omitted.
[0137]
Also in the pressure estimation model construction system 4 of the present embodiment, the online data measured at the online measurement point 15 in the distribution pipe 2 of the distribution block 1 and the offline measurement point, as in the first embodiment described above. 16, offline data measured in 16, data acquisition means 29, statistical value calculation means 30, statistical value DB 28, normalization means 31, clustering means 23, first model construction means, and principal component calculation means 25. Based on the second model construction means, a pressure estimation model at a predetermined date and time at the offline measurement point 16 is obtained, and the pressure estimation model is stored in the estimation model DB 27.
[0138]
Thereafter, the fire hydrant pressure estimating means 36 obtains online data corresponding to the current time from the normalizing means 31 and obtains a pressure estimation model corresponding to the obtained online data from the estimation model DB 27. And the fire hydrant pressure estimation means 36 is the pressure value of the present time in the distribution pipe 2 of the offline measurement point 16 corresponding to the acquired pressure estimation model based on the online data and pressure estimation model corresponding to the acquired current time. Is calculated.
[0139]
The pressure value corresponding to the current time calculated by the fire hydrant pressure estimating means 36 is sent to and displayed on the estimation result display means 37 to notify the operator or the like.
[0140]
Note that any display method may be used in the estimation result display unit 37. For example, the estimated pressure value itself can be displayed, or can be displayed by a contour line of the pressure value in 2D format or 3D format. Even if the pressure estimated by the fire hydrant pressure estimating means 36 deviates from a preset allowable pressure range (operating pressure range), the estimation result display means 37 indicates the estimated pressure. It can be displayed.
[0141]
As described above, the pressure estimation model construction system 4 according to the present embodiment can construct a pressure estimation model at each offline measurement point 16 in a format using online data measured online.
[0142]
Furthermore, according to the present embodiment, a specific pressure value corresponding to the current time at each offline measurement point 16 can be estimated by the fire hydrant pressure estimating means 36.
[0143]
Next, a modification of the present embodiment will be described.
[0144]
In the force estimation model construction system according to the present invention, the statistical value calculation means 30 and the normalization means 31 may not be provided.
[0145]
In this case, the online data and offline data acquired by the data acquisition unit 29 are sent directly to the clustering unit 23. The clustering means 23 performs cluster analysis on online data and offline data sent from the online measurement data DB 21 and offline measurement data DB 22 via the data acquisition means 29.
[0146]
The hydrant pressure estimating means 36 is connected to the online measurement data DB 21 and acquires online data corresponding to the current time from the online measurement data DB 21.
[0147]
Other configurations are substantially the same as those of the third embodiment shown in FIG. 5 described above, and the same parts as those of the third embodiment are denoted by the same reference numerals and detailed description thereof is omitted.
[0148]
Also in this modification, the pressure estimation model at each offline measurement point 16 is constructed by the first pressure estimation model construction unit 24 and the second pressure estimation model construction unit 26 and is stored in the estimation model DB 27.
[0149]
The fire hydrant pressure estimating means 36 acquires online data corresponding to the current time from the online measurement data DB 21 and acquires a pressure estimation model corresponding to the online data from the estimation model DB 27. And the fire hydrant pressure estimation means 36 calculates the specific pressure value in the distribution pipe 2 in each offline measurement point 16 corresponding to the present time based on the acquired online data and the pressure estimation model.
[0150]
The pressure value calculated by the fire hydrant pressure estimating means 36 is sent to the estimation result display means 37 and displayed.
[0151]
As described above, also in this modification, the pressure estimation model construction system 4 can construct a pressure estimation model at each offline measurement point 16 in a format using online data measured online.
[0152]
In addition, a specific pressure value corresponding to the current time at each offline measurement point 16 can be estimated by the fire hydrant pressure estimating means 36. For this reason, for example, in each location of the water distribution pipe 2 stretched over the entire area of the water distribution block 1, the pressure in the water distribution pipe becomes an allowable range (for example, a range that is equal to or higher than the allowable minimum pressure and equal to or lower than the allowable maximum pressure). It can be verified whether or not.
[0153]
The data required in the pressure estimation means 36 of the support means 35 is data in the format used by the first pressure estimation model construction means 24 and the second pressure estimation model construction means 26. Therefore, when each model construction means 24, 26 uses normalized data, the pressure estimation means 36 also requires normalized data, and the model construction means 24, 26 measured as it is. When data is used, the data as measured by the pressure estimation means 36 is required.
[0154]
Further, in the present embodiment, it is assumed that the data input to the pressure estimation unit 36 corresponds to the current time, and the pressure estimation unit 36 estimates the pressure using all online data. All the online data sent from the measuring instrument 10a and the flow rate measuring instrument 10b are inputted to the pressure estimating means 36.
[0155]
Fourth embodiment
FIG. 6 is a diagram showing a fourth embodiment of the present invention, and is a schematic diagram showing a configuration of the entire pressure estimation model construction system.
[0156]
In the pressure estimation model construction system 4 of the fourth embodiment, the pressure estimation device 11 further includes a verification unit 40, and the verification unit 40 is connected to the date / time setting unit 41 and the date / time setting unit 41. And date / time designation data acquisition means 42 connected to the online measurement data DB 21.
[0157]
The date and time setting means 41 is configured to input the past predetermined date and time by an operator or the like when it is desired to estimate the pressure of the past predetermined date and time at each offline measurement point 16.
[0158]
Note that when estimating the pressure at each offline measurement point 16 in a certain verification period, a method of setting a verification start date and a verification end date and time can be considered. By setting the verification start date and time and the verification start date and time to the same date, the specific date and time can be verified.
[0159]
The date designation data acquisition unit 42 acquires online data corresponding to the past predetermined date and time input to the date setting unit 41 from the online measurement data storage unit, and sends the acquired online data to the normalization unit 31. ing.
[0160]
The normalizing means 31 further has a function of normalizing the online data sent from the date / time designation data acquiring means 42 and sending the normalized online data to the fire hydrant pressure estimating means 36.
[0161]
The fire hydrant pressure estimating means 36 acquires a pressure estimation model corresponding to the online data sent from the date / time designation data acquisition means 42 via the normalization means 31 from the pressure estimation model storage means, and from the date / time designation data acquisition means 42. Based on the online data sent via the normalization means 31 and the acquired pressure estimation model, it further has a function of calculating a pressure estimation value at a predetermined date and time in the past.
[0162]
Other configurations are substantially the same as those of the third embodiment shown in FIG.
[0163]
In FIG. 6, the same parts as those of the third embodiment shown in FIG.
[0164]
Also in the pressure estimation model construction system 4 of the present embodiment, the online data measured at the online measurement point 15 in the distribution pipe 2 of the distribution block 1 and the offline measurement point, as in the first embodiment described above. 16, offline data measured in 16, data acquisition means 29, statistical value calculation means 30, statistical value DB 28, normalization means 31, clustering means 23, first model construction means, and principal component calculation means 25. Based on the second model construction means, a pressure estimation model at a predetermined date and time at the offline measurement point 16 is obtained, and the pressure estimation model is stored in the estimation model DB 27.
[0165]
Then, a past predetermined date and time for which pressure is to be estimated is input to the date and time setting means 41 by an operator or the like. The predetermined date and time input to the date and time setting means 41 is sent to the date and time designation data acquisition means 42.
[0166]
The date / time designation data acquisition unit 42 acquires online data corresponding to the predetermined date / time sent from the date / time setting unit 41 from the online measurement data DB 21. Then, the online data acquired by the online measurement data DB 21 is sent from the date / time designation data acquisition means 42 to the normalization means 31.
[0167]
The normalizing unit 31 normalizes the online data sent from the normalizing unit 31. Then, the normalizing means 31 sends the normalized online data to the fire hydrant pressure estimating means 36.
[0168]
The fire hydrant pressure estimation means 36 acquires a pressure estimation model corresponding to the online data sent from the normalization means 31 from the estimation model DB 27. And the fire hydrant pressure estimation means 36 is based on the online data sent from the normalization means 31 and the pressure estimation model corresponding to the online data. Calculate the pressure value of date and time.
[0169]
The pressure value corresponding to the past predetermined date and time calculated by the fire hydrant pressure estimating means 36 is sent to and displayed on the estimation result display means 37 to notify the operator or the like.
[0170]
The estimation result display unit 37 can display the calculated pressure value by various methods. For example, the estimation result display unit 37 can continuously display the pressure value in a certain verification period (continuous reproduction display), or perform the verification. A pressure value at an arbitrary time in the period can be displayed (arbitrary time display), or a pressure deviation (pressure fluctuation) from a predetermined time before can be displayed. Here, the “predetermined designated time” can be set by an operator or the like via the date and time setting means 41, but is not limited to this.
[0171]
As described above, in the pressure estimation model construction system 4 according to the present embodiment, it is possible to construct a pressure estimation model at each offline measurement point 16 in a format using online data measured online. The fire hydrant pressure estimating means 36 can estimate a specific pressure value corresponding to the past predetermined date and time at each offline measurement point 16.
[0172]
【The invention's effect】
As described above, according to the pressure estimation model construction system of the present invention, among the distribution pipes stretched around the distribution block, the pressure distribution in the distribution pipe at the online measurement point can be obtained online as online data, and offline. The pressure distribution in the distribution pipe at the measurement point can be obtained by a pressure estimation model constructed based on online data and offline data that has been measured in advance. Therefore, according to this invention, it becomes possible to obtain | require accurately the pressure in the water distribution pipe in the online measurement point in a water distribution block, and an offline measurement point.
[Brief description of the drawings]
FIG. 1 is a schematic diagram showing the overall configuration of a pressure estimation model construction system according to a first embodiment of the present invention.
FIG. 2 shows online data and offline data classified into clusters by cluster analysis.
FIG. 3 is a diagram for explaining “units” used in a neural network;
FIG. 4 is a diagram illustrating a relationship between an “input layer”, an “intermediate layer”, and an “output layer” used in a neural network.
FIG. 5 is a diagram showing a third embodiment of the present invention, and is a schematic diagram showing a configuration of the entire pressure estimation model construction system.
FIG. 6 is a diagram showing a fourth embodiment of the present invention, and is a schematic diagram showing a configuration of an entire pressure estimation model construction system.
FIG. 7 is a schematic diagram showing the overall configuration of a conventional pressure estimation model construction system.
[Explanation of symbols]
1 Water distribution block
2 Water distribution pipe
3 Water distribution injection parts
4 Pressure estimation model construction system
10a Pressure measuring instrument
10b Flow rate measuring device (online measuring means)
11 Pressure estimation device
15 Online measurement points
16 Offline measurement points
21 Online measurement data DB (Online measurement data storage means)
22 Offline measurement data DB (offline measurement data storage means)
23 Clustering means
24 First pressure estimation model construction means
25 Principal component calculation means
26 Second pressure estimation model construction means
27 Estimation model DB (pressure estimation model storage means)
28 Online measurement data DB (Online measurement data storage means)
29 Data acquisition means
30 Statistical value calculation means
31 Normalization means
32 Model display means

Claims (12)

配水ブロックに張り巡らされた配水管内の圧力分布に関する推定モデルを構築する圧力推定モデル構築システムであって、
配水管のうち1以上の箇所に設けられたオンライン計測ポイントにおける配水管内の圧力をオンラインデータとして計測し、当該オンラインデータをオンラインで後段に送る機能を有するオンライン計測手段と、
配水管のうちオンライン計測ポイントとは異なる1以上の箇所に設けられたオフライン計測ポイントにおいて予め計測された配水管内の圧力をオフラインデータとして記憶し、当該オフラインデータを後段に送る機能を有するオフライン計測データ記憶手段と、
オンライン計測手段及びオフライン計測データ記憶手段の後段に設けられ、オンライン計測手段から送られてくるオンラインデータと、オフライン計測データ記憶手段から送られてくるオフラインデータと、をクラスター分析によって各クラスターに分類する機能を有するクラスタリング手段と、
クラスタリング手段の後段に設けられ、各オンラインデータと同一クラスターに分類される各オフラインデータについて、同一クラスターに分類される各オンラインデータに基づき、当該各オフラインデータに対応するオフライン計測ポイントにおける配水管内の圧力モデルである第1圧力推定モデルを構築する第1圧力推定モデル構築手段と、
クラスタリング手段の後段に設けられ、各オンラインデータと異なるクラスターに分類される各オフラインデータについて、主成分分析を行って、当該各オフラインデータに対応する推定モデル入力値を演算する機能を有する主成分演算手段と、
主成分演算手段の後段に設けられ、各オンラインデータと異なるクラスターに分類される各オフラインデータについて、当該各オフライン計測データに対応する推定モデル入力値に基づき、当該各オフラインに対応するオフライン計測ポイントにおける配水管内の圧力モデルである第2圧力推定モデルを構築する第2圧力推定モデル構築手段と、
第1圧力推定モデル構築手段及び第2圧力推定モデル構築手段に接続され、第1圧力推定モデル構築手段によって構築される第1圧力推定モデルと、第2圧力推定モデル構築手段によって構築される第2圧力推定モデルと、から構成される圧力推定モデルを記憶する圧力推定モデル記憶手段と、
を備えたことを特徴とする圧力推定モデル構築システム。
A pressure estimation model construction system for constructing an estimation model for pressure distribution in a distribution pipe stretched around a distribution block,
Online measuring means having a function of measuring the pressure in the distribution pipe at an online measurement point provided at one or more locations in the distribution pipe as online data and sending the online data to the subsequent stage;
Offline measurement data that has the function of storing the pressure in the distribution pipe measured in advance at offline measurement points provided at one or more places different from the online measurement point in the distribution pipe as offline data and sending the offline data to the subsequent stage Storage means;
Provided after the online measurement means and the offline measurement data storage means, the online data sent from the online measurement means and the offline data sent from the offline measurement data storage means are classified into clusters by cluster analysis. A clustering means having a function;
For each offline data that is provided after the clustering means and is classified into the same cluster as each online data, the pressure in the distribution pipe at the offline measurement point corresponding to each offline data based on each online data classified into the same cluster First pressure estimation model construction means for constructing a first pressure estimation model as a model;
Principal component calculation that is provided after the clustering means and has the function of performing principal component analysis on each offline data classified into a cluster different from each online data and calculating the estimated model input value corresponding to each offline data Means,
Based on the estimated model input value corresponding to each offline measurement data, the offline measurement points corresponding to each offline data are provided for each offline data that is provided in the subsequent stage of the principal component calculation means and is classified into a cluster different from each online data. A second pressure estimation model construction means for constructing a second pressure estimation model that is a pressure model in the water pipe;
The first pressure estimation model construction unit and the second pressure estimation model construction unit are connected to the first pressure estimation model construction unit and the second pressure estimation model construction unit, and the second pressure estimation model construction unit constructs the second pressure estimation model construction unit. A pressure estimation model storage means for storing a pressure estimation model composed of a pressure estimation model;
A pressure estimation model construction system characterized by comprising:
第1圧力推定モデル構築手段は、重回帰分析を用いて第1圧力推定モデルを構築し、
第2圧力推定モデル構築手段は、重回帰分析を用いて第2圧力推定モデルを構築する
ことを特徴とする請求項1に記載の圧力推定モデル構築システム。
The first pressure estimation model construction means constructs a first pressure estimation model using multiple regression analysis,
The pressure estimation model construction system according to claim 1, wherein the second pressure estimation model construction means constructs a second pressure estimation model using multiple regression analysis.
第1圧力推定モデル構築手段は、ニューラル・ネットワークを用いて第1圧力推定モデルを構築し、
第2圧力推定モデル構築手段は、ニューラル・ネットワークを用いて第2圧力推定モデルを構築する
ことを特徴とする請求項1に記載の圧力推定モデル構築システム。
The first pressure estimation model construction means constructs a first pressure estimation model using a neural network,
The pressure estimation model construction system according to claim 1, wherein the second pressure estimation model construction means constructs a second pressure estimation model using a neural network.
オンライン計測手段とクラスタリング手段との間に設けられ、オンライン計測手段による計測値を記憶するオンライン計測データ記憶手段と、
オンライン計測データ記憶手段及びオフライン計測データ記憶手段とクラスタリング手段との間に設けられ、オンライン計測データ記憶手段に記憶されているオンラインデータを取得すると共に、オンライン計測データ記憶手段から取得したオンラインデータの計測時刻に対応するオフラインデータをオフライン計測データ記憶手段から取得して、取得したオンラインデータ及びオフラインデータを後段に送る機能を有するデータ取得手段と、
を更に備えたことを特徴とする請求項1乃至3のいずれかに記載の圧力推定モデル構築システム。
Online measurement data storage means that is provided between the online measurement means and the clustering means, and stores the measurement values by the online measurement means;
Online measurement data storage means, offline measurement data storage means, and clustering means are provided between the online measurement data storage means and the online measurement data storage means and the online measurement data storage means Data acquisition means having a function of acquiring offline data corresponding to time from the offline measurement data storage means, and sending the acquired online data and offline data to the subsequent stage;
The pressure estimation model construction system according to any one of claims 1 to 3, further comprising:
データ取得手段とクラスタリング手段との間に設けられ、送られてくるオンラインデータ及びオフラインデータを統計化し、統計化されたオンラインデータ及びオフラインデータを後段に送る機能を有する統計値演算手段を更に備えた
ことを特徴とする請求項4に記載の圧力推定モデル構築システム。
A statistical value calculation means provided between the data acquisition means and the clustering means, further comprising a statistical value calculation means having a function of statistically transmitting the sent online data and offline data and sending the statistical online data and offline data to the subsequent stage. The pressure estimation model construction system according to claim 4 characterized by things.
データ取得手段とクラスタリング手段との間に設けられ、送られてくるオンラインデータ及びオフラインデータを正規化して後段へ送る機能を有する正規化手段を更に備えた
ことを特徴とする請求項4に記載の圧力推定モデル構築システム。
5. The normalization means provided between the data acquisition means and the clustering means, further comprising a normalization means having a function of normalizing the sent online data and offline data and sending it to a subsequent stage. Pressure estimation model construction system.
統計値演算手段とクラスタリング手段との間に設けられ、送られてくるオンラインデータ及びオフラインデータを正規化して後段へ送る機能を有する正規化手段を更に備えた
ことを特徴とする請求項5に記載の圧力推定モデル構築システム。
6. The normalization means provided between the statistical value calculation means and the clustering means, further comprising normalization means having a function of normalizing the sent online data and offline data and sending them to the subsequent stage. Pressure estimation model construction system.
オフライン計測ポイントにおける現在時刻の圧力値を推定するオフライン計測ポイント圧力推定手段であって、
オンライン計測データ記憶手段に接続されると共に推定モデル記憶手段に接続され、現在時刻に対応するオンラインデータをオンライン計測データ記憶手段から取得すると共に当該オンラインデータに対応する圧力推定モデルを推定モデル記憶手段から取得し、取得した現在時刻に対応するオンラインデータと圧力推定モデルとに基づいて、取得した圧力推定モデルに対応するオフライン計測ポイントの配水管内における現在時刻の圧力値を演算する機能を有するオフライン計測ポイント圧力推定手段を更に備えた
ことを特徴とする請求項4乃至7のいずれかに記載の圧力推定モデル構築システム。
An offline measurement point pressure estimating means for estimating a pressure value at a current time at an offline measurement point,
Connected to the online measurement data storage means and connected to the estimation model storage means, obtains online data corresponding to the current time from the online measurement data storage means, and obtains a pressure estimation model corresponding to the online data from the estimation model storage means An offline measurement point that has the function of calculating the pressure value at the current time in the distribution pipe of the offline measurement point corresponding to the acquired pressure estimation model based on the acquired online data and the pressure estimation model corresponding to the acquired current time The pressure estimation model construction system according to any one of claims 4 to 7, further comprising pressure estimation means.
正規化手段に接続されると共に推定モデル記憶手段に接続され、現在時刻に対応するオンラインデータを正規化手段から取得すると共に推定モデル記憶手段から圧力推定モデルを取得し、取得した現在時刻に対応するオンラインデータと圧力推定モデルとに基づいて、取得した圧力推定モデルに対応するオフライン計測ポイントの配水管内における現在時刻の圧力値を演算する機能を有するオフライン計測ポイント圧力推定手段
を更に備えたことを特徴とする請求項6又は7のいずれかに記載の圧力推定モデル構築システム。
Connected to the normalizing means and connected to the estimated model storage means, obtains online data corresponding to the current time from the normalizing means, obtains a pressure estimation model from the estimated model storage means, and corresponds to the obtained current time An offline measurement point pressure estimating means having a function of calculating a pressure value at the current time in the distribution pipe of the offline measurement point corresponding to the acquired pressure estimation model based on the online data and the pressure estimation model is further provided. The pressure estimation model construction system according to claim 6 or 7.
過去の所定日時が入力される日時設定手段と、
日時設定手段に接続されると共にオンライン計測データ記憶手段に接続され、日時設定手段に入力された過去の所定日時に対応するオンラインデータをオンライン計測データ記憶手段から取得して、取得したオンラインデータを正規化手段に送る日時指定データ取得手段と、を更に備え、
正規化手段は、日時指定データ取得手段から送られてくるオンラインデータを正規化して、正規化したオンラインデータをオフライン計測ポイント圧力推定手段に送る機能を更に有し、
オフライン計測ポイント圧力推定手段は、日時指定データ取得手段から正規化手段を介して送られてくるオンラインデータに対応する圧力推定モデルを圧力推定モデル記憶手段から取得して、日時指定データ取得手段から正規化手段を介して送られてくるオンラインデータと取得した圧力推定モデルとに基づいて、過去の所定日時における圧力推定値を演算する機能を更に有する
ことを特徴とする請求項9に記載の圧力推定モデル構築システム。
A date and time setting means for inputting a predetermined date and time in the past;
Connected to the date and time setting means and connected to the online measurement data storage means, acquires online data corresponding to the past predetermined date and time input to the date and time setting means from the online measurement data storage means, and normalizes the acquired online data A date and time designation data acquisition means to be sent to the conversion means,
The normalization means further has a function of normalizing the online data sent from the date and time designation data acquisition means, and sending the normalized online data to the offline measurement point pressure estimation means,
The off-line measurement point pressure estimation means acquires a pressure estimation model corresponding to the online data sent from the date / time designation data acquisition means via the normalization means from the pressure estimation model storage means, and The pressure estimation according to claim 9, further comprising a function of calculating a pressure estimation value at a predetermined past date and time based on online data sent via the conversion means and the acquired pressure estimation model. Model building system.
オフライン計測ポイント圧力推定手段に接続され、オフライン計測ポイント圧力推定手段によって演算された圧力値を表示する推定結果表示手段を更に備えたことを特徴とする請求項8乃至10のいずれかに記載の圧力推定モデル構築システム。  11. The pressure according to claim 8, further comprising an estimation result display unit connected to the offline measurement point pressure estimation unit and displaying a pressure value calculated by the offline measurement point pressure estimation unit. Estimated model construction system. 圧力推定モデル記憶手段に接続され、圧力推定モデル記憶手段に記憶されている圧力推定モデルを表示するモデル表示手段を更に備えたことを特徴とする請求項1乃至11のいずれかに記載の圧力推定モデル構築システム。  12. The pressure estimation according to claim 1, further comprising model display means connected to the pressure estimation model storage means and displaying a pressure estimation model stored in the pressure estimation model storage means. Model building system.
JP2002295140A 2002-10-08 2002-10-08 Pressure estimation model construction system Expired - Lifetime JP4291992B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002295140A JP4291992B2 (en) 2002-10-08 2002-10-08 Pressure estimation model construction system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002295140A JP4291992B2 (en) 2002-10-08 2002-10-08 Pressure estimation model construction system

Publications (2)

Publication Number Publication Date
JP2004131957A JP2004131957A (en) 2004-04-30
JP4291992B2 true JP4291992B2 (en) 2009-07-08

Family

ID=32285487

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002295140A Expired - Lifetime JP4291992B2 (en) 2002-10-08 2002-10-08 Pressure estimation model construction system

Country Status (1)

Country Link
JP (1) JP4291992B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4799168B2 (en) * 2005-12-21 2011-10-26 株式会社東芝 Water distribution and pipeline information analysis system
JP5032445B2 (en) * 2008-11-17 2012-09-26 株式会社東芝 Unknown water amount prediction device and unknown water prediction system
JP7067895B2 (en) * 2017-10-25 2022-05-16 株式会社東芝 End pressure control support device, end pressure control support method and computer program
JP7182961B2 (en) * 2018-09-03 2022-12-05 株式会社東芝 Terminal pressure control support device, terminal pressure control support method and computer program
CN111270728B (en) * 2020-01-21 2021-03-23 重庆垫江水务有限公司 Gravity type constant pressure water supply method
CN112594553A (en) * 2020-12-07 2021-04-02 熊猫智慧水务有限公司 Pipe network pressure regulation and control method based on pressure target curve

Also Published As

Publication number Publication date
JP2004131957A (en) 2004-04-30

Similar Documents

Publication Publication Date Title
CN107153874B (en) Water quality prediction method and system
JP4914457B2 (en) Automatic virtual measurement system and method
CN106338406B (en) The on-line monitoring of train traction electric drive system and fault early warning system and method
CN107992968B (en) Electric energy meter metering error prediction method based on integrated time series analysis technology
CN107230113A (en) A kind of house property appraisal procedure of multi-model fusion
CN106644162B (en) Ring main unit wire core temperature soft measurement method based on neighborhood preserving embedding regression algorithm
CN110555230B (en) Rotary machine residual life prediction method based on integrated GMDH framework
CN109377034A (en) Risk profiles appraisal procedure based on smart grid information communication system
CN106707221A (en) Fault diagnosis method and system for sensor in electric energy metering device
JP4291992B2 (en) Pressure estimation model construction system
CN113469470A (en) Energy consumption data and carbon emission correlation analysis method based on electric brain center
CN109559042A (en) A kind of fund manager's scoring algorithm based on multidimensional index regression analysis
CN109408773A (en) A kind of index automatically screening method of environmental health diagnosis
CN116663419A (en) Sensorless equipment fault prediction method based on optimized Elman neural network
CN110516890B (en) Crop yield monitoring system based on gray combined model
CN110533109A (en) A kind of storage spraying production monitoring data and characteristic analysis method and its device
CN109920489A (en) It is a kind of that model and method for building up are hydrocracked based on Lasso-CCF-CNN
CN109886316B (en) Transformer state parameter combination prediction method based on cloud system similarity weight distribution
CN112446168A (en) Effluent BOD concentration soft measurement method based on MIC and RBFNN
CN115359197A (en) Geological curved surface reconstruction method based on spatial autocorrelation neural network
CN112836275B (en) Stadium emergency evacuation sign readability evaluation system based on fuzzy theory and control method thereof
Nelsia Priya Dharsini et al. Probabilistic model development for estimating construction labor productivity optimization integrating with fuzzy logic approach systems
CN109165740A (en) The fault time calculation method of product subsystem based on section step analysis
CN111695634A (en) Data abnormal mutation point detection algorithm based on limited accompanying censoring mechanism
Yanto et al. Hybrid Method Air Quality Classification Analysis Model.

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050805

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080214

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080422

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080618

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090106

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090220

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090313

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090406

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120410

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130410

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140410

Year of fee payment: 5