JP4282847B2 - Seat plate installation structure and floor plate installation method - Google Patents
Seat plate installation structure and floor plate installation method Download PDFInfo
- Publication number
- JP4282847B2 JP4282847B2 JP30775799A JP30775799A JP4282847B2 JP 4282847 B2 JP4282847 B2 JP 4282847B2 JP 30775799 A JP30775799 A JP 30775799A JP 30775799 A JP30775799 A JP 30775799A JP 4282847 B2 JP4282847 B2 JP 4282847B2
- Authority
- JP
- Japan
- Prior art keywords
- seat plate
- female screw
- screw hole
- unit seat
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、コンクリートで打設されて形成される機器据付用床面のレベル調整のために床面となる領域に設置される座板の設置構造およびレベル調整用の座板が設けられた座板設置床構造の施工方法に関する。
【0002】
【従来の技術】
機器の据え付け基礎となる床面をコンクリートを打設して形成する場合に、床面の水平度を出すために座板を設置することが行われている。
すなわち、従来における座板が設置される床面では、例えば、図10の(a)(b)に示すように、コンクリート1が打設される前に、アンカーボルト2が床面3となる領域に立設状態に複数配筋され、これらアンカーボルト2の先端に一枚の座板4が水平状態にボルト5で所定高さに設置される。
この後、コンクリート1が座板4の下面まで打設されて床面3が形成される。
【0003】
【発明が解決しようとする課題】
しかしながら、上記従来の座板設置手段には、以下のような課題が残されている。すなわち、立設状態に配筋されたアンカーボルト2がコンクリート1の打設によって傾倒してしまい、その上部に設置された座板4が全体的に傾いてしまって高精度な水平度を得ることができなかった。このため、機器を据え付ける前に、座板4と機器の底面との間に所定厚さのライナーを挟み込んでライナー調整を行う必要があり、据付作業に手間がかかり、作業効率を低下させる要因となっていた。
【0004】
本発明は、前述の課題に鑑みてなされたもので、コンクリートの打設により形成される床面のレベル調整を高精度で行うことができ、機器の据え付け作業の効率を向上させることができる座板の設置構造および座板設置床構造の施工方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
本発明は、前記課題を解決するために以下の構成を採用した。すなわち、請求項1記載の座板の設置構造では、コンクリートが打設されて形成される床面のレベル調整をするために床面となる領域に設置される座板の設置構造であって、先端部に雄螺子部を形成した基礎ボルトが、前記床面となる領域内の複数箇所に垂直に立設され、前記座板は、少なくとも下部に取付用雌螺子孔を形成した複数の単位座板で構成され、前記単位座板は、前記取付用雌螺子孔を前記雄螺子部に螺合させて上下動可能に前記複数の基礎ボルトにそれぞれ取り付けられ、前記単位座板の上部には前記取付用雌螺子と同軸に機器固定用雌螺子孔が形成され、前記取付用雌螺子孔と前記機器固定用雌螺子孔との間は、該両孔を連通させない壁部が形成され、さらに複数の前記単位座板の円筒状本体の上部に形成され該円筒状本体より大径の円板部の上面と打設された前記コンクリートの上面をそれぞれ被膜するライニング板を敷設して前記床面が形成される技術が採用される。
【0006】
また、請求項2記載の座板設置床構造の施工方法では、レベル調整用の座板が設けられた座板設置床構造の施工方法であって、先端部に雄螺子部が形成された基礎ボルトを、所定の複数箇所に垂直に立設するボルト設置工程と、少なくとも下部に取付用雌螺子孔が形成されるとともに上部に該取付用雌螺子孔と同軸に機器固定用雌螺子孔が形成され、前記取付用雌螺子孔と前記機器固定用雌螺子孔との間に、該両雌螺子孔を連通させない壁部が形成された複数の単位座板を、前記雄螺子部に前記取付用雌螺子孔を螺合させて前記基礎ボルトにそれぞれ取り付ける単位座板取付工程と、前記単位座板と前記基礎ボルトとの周囲に、単位座板の上面を露出させた状態でコンクリートを打設するコンクリート打設工程とを備え、該コンクリート打設工程は、前記単位座板の下部近傍までコンクリートを打設する一次打設工程と、一次打設工程の後、前記単位座板を回転させて上下動させ高さ調整を行うレベル調整工程と、該レベル調整工程の後、前記単位座板の周囲までコンクリートを打設する二次打設工程と、複数の前記単位座板の円筒状本体の上部に形成され該円筒状本体より大径の円板部の上面と二次打設工程で打設された前記コンクリートの上面をそれぞれ被膜するライニング板を敷設する工程を備えている技術が採用される。
【0007】
この座板の設置構造および座板設置床構造の施工方法では、前記座板が、少なくとも下部に取付用雌螺子孔を形成した複数の単位座板で構成され、単位座板が、取付用雌螺子孔を基礎ボルトの雄螺子部に螺合させて上下動可能に複数の基礎ボルトにそれぞれ取り付けられているので、各単位座板において個別に高さ調整を行うことができる。そして、コンクリートを打設する際に、一旦、単位座板の下部近傍までコンクリートを打設し、単位座板を回転させて上下動させることにより、全体としての座板のレベルを再調整し、さらにこの後、再び単位座板の周囲までコンクリートを打設することにより、ライナー調整によらずとも基礎ボルトのゆがみによって生じた座板の傾きを矯正することができる。
また、単位座板の上部に機器を取り付けるための機器固定用雌螺子孔が形成され、機器固定用雌螺子孔が、取付用雌螺子孔と同軸に設定されているので、単位座板に機器を直接据え付けることができるとともに、単位座板を回転させて高さ調整した後も機器固定用雌螺子孔の位置が横方向にずれず、正確に機器を据え付けることができる。
さらに、取付用雌螺子孔と機器固定用雌螺子孔との間には、両孔を連通させない壁部が形成されているので、単位座板上の流体が機器固定用雌螺子孔に侵入しても単位座板下部のコンクリートに浸透することがない。
【0009】
また、請求項3記載の座板設置床構造の施工方法では、レベル調整用の座板が設けられた座板設置床構造の施工方法であって、先端部に雄螺子部が形成された基礎ボルトを、所定の複数箇所に垂直に立設するボルト設置工程と、少なくとも下部に取付用雌螺子孔が形成されるとともに上部に該取付用雌螺子孔と同軸に機器固定用雌螺子孔が形成され、前記取付用雌螺子孔と前記機器固定用雌螺子孔との間に、該両雌螺子孔を連通させない壁部が形成された複数の単位座板を、前記雄螺子部に前記取付用雌螺子孔を螺合させて前記基礎ボルトにそれぞれ取り付ける単位座板取付工程と、前記単位座板に、その外周面を覆って、人力で破壊可能な低強度材料で形成された環状のスペーサを取り付けるスペーサ取付工程と、前記スペーサを取り付けた前記単位座板と前記基礎ボルトとの周囲に、前記単位座板の上面を露出させた状態でコンクリートを打設するコンクリート打設工程と、該コンクリート打設工程の後、前記スペーサを破壊するとともに、前記単位座板を回転させて上下動させ高さ調整を行うレベル調整工程と、該レベル調整工程の後に、前記スペーサを破壊し取り除いた空間に前記単位座板の周囲をモルタルにて充填するモルタル充填工程と、該モルタル充填工程の後に、複数の前記単位座板の円筒状本体の上部に形成され該円筒状本体より大径の円板部の上面と打設された前記コンクリートの上面と充填された前記モルタルの上面をそれぞれ被膜するライニング板を敷設する工程とを備えている技術が採用される。
【0010】
この座板設置床構造の施工方法では、人力で破壊可能な低強度材料で形成された環状のスペーサが、単位座板の外周面を覆って取り付けられているので、コンクリートを全て打設した後に、スペーサを破壊することにより単位座板の周囲に空間を形成し、単位座板を回転操作することが可能になり、容易に単位座板を上下させることができる。すなわち、コンクリートを打設する際に、単位座板の下部近傍で一旦打設を中断しなくても、一度に単位座板の上面のレベルまで打設した後に単位座板の高さ調整が可能であり、打設工程を2つに分ける必要がない。
【0015】
【発明の実施の形態】
以下、本発明に係る座板の配置構造および座板配置床構造の施工方法の第1実施形態を図1から図5を参照しながら説明する。
これらの図にあって、符号11はアンカーボルト、12は単位座板を示している。
【0016】
〔アンカーボルト配筋工程〕
まず、図1の(a)(b)に示すように、床面となる領域A内の複数箇所に垂直にアンカーボルト(基礎ボルト)11を立設する。
該アンカーボルト11は、その先端部分に雄螺子部11aが形成されている。
本実施形態では、アンカーボルト11が八角形の領域A内に円周上に並べられる。
【0017】
〔単位座板取付工程〕
この後、図2の(a)(b)に示すように、配筋された各アンカーボルト11の先端部分に単位座板12を取り付ける。これら単位座板12は、全体として一つの座板を構成する。
前記単位座板12は、円筒状本体12aと、その上部に形成され円筒状本体12aより大径な円板部12bとからなり、その下部には、雄螺子部11aに螺合可能な取付用雌螺子孔12cが上下に貫通状態に形成されている。
【0018】
すなわち、円板部12bを上方に向けた状態で単位座板12の取付用雌螺子孔12cを、雄螺子部11aに螺合させ、アンカーボルト11に単位座板12を取り付ける。
このとき、各単位座板12を回転操作することによって上下に動かし、高さ調整を行うことにより、座板全体としてのレベル調整を行う。
【0019】
〔一次打設工程〕
各単位座板12の高さ調整を行った後、図3の(a)(b)に示すように、領域Aに一次コンクリート13を打設する。
このとき、一次コンクリート13は、単位座板12の下部近傍の所定高さ(以下、基準線Bという)まで打設するものとし、単位座板12が上下動可能なスペースを確保しておく。
【0020】
〔レベル調整工程〕
一次コンクリート13の打設後、単位座板12を回すことにより、基準線Bに対して各単位座板12の上面レベルを再調整する。これによって、座板全体としての再レベル調整が行われる。
【0021】
〔二次打設工程〕
さらに、一次コンクリート13の上に、図4の(a)(b)に示すように、二次コンクリート14を打設する。
このとき、二次コンクリート14は、単位座板12の上面が露出した状態で床面15の所定高さ、すなわち単位座板12の周囲まで打設する。
この後、二次コンクリート14の表面に被膜としてライニング板16を敷設して床面15を形成する。
【0022】
〔機器据え付け工程〕
コンクリートの養生期間を経て床面15上に機器17を搬入するとともに、図5に示すように、各単位座板12の取付用雌螺子孔(機器固定用雌螺子孔)12cに上部から機器17の据付用ボルト18を螺合させることにより、当該機器17を単位座板12および床面15に据え付け固定する。
【0023】
この座板の設置構造および座板設置床構造の施工方法では、座板が、下部に取付用雌螺子孔12cを形成した複数の単位座板12で構成され、単位座板12が、取付用雌螺子孔12cをアンカーボルト11の雄螺子部11aに螺合させて上下動可能に複数のアンカーボルト11にそれぞれ取り付けられているので、各単位座板12において個別に高さ調整を行うことができ、座板全体として高精度なレベル調整が可能となる。
【0024】
また、コンクリートを打設する際に、一旦、単位座板12の下部近傍における基準線Bまで一次コンクリート13を打設し、単位座板12を回転させて上下動させることにより、全体としての座板のレベルを再調整し、さらにこの後、再び単位座板12の周囲まで二次コンクリート14を打設することにより、ライナー調整によらずともアンカーボルト11のゆがみによって生じた座板の傾きを矯正することができる。
【0025】
次に、本発明に係る座板の配置構造および座板配置床構造の施工方法の第2実施形態を図6から図9を参照しながら説明する。
これらの図にあって、符号20はスペーサ、21は単位座板を示している。
【0026】
第2実施形態と第1実施形態との異なる点は、第1実施形態では、レベル調整のために一次打設工程と二次打設工程の2度の打設を行うのに対し、第2実施形態では、図6の(a)(b)に示すようなスペーサ20を用いることにより、コンクリートを一度に打設してしまった後にレベル調整を行う点である。
以下に、第1実施形態と同様であるアンカーボルト配筋工程以降の各工程について詳述する。
【0027】
〔スペーサ取付工程〕
アンカーボルト11に取り付ける単位座板21には、その外周面を覆って、人力で破壊可能な低強度材料、例えば発泡スチロールで形成された環状のスペーサ20を予めはめ込んで取り付けておく。
該スペーサ20は、内周面の断面形状が段部状とされ、単位座板21の円板部21bおよび円筒状本体21aの両外周面に当接するような形状とされている。
【0028】
また、前記単位座板21は、円筒状本体21aと円板部21bとから構成され、下部に軸線を同じくした取付用雌螺子孔21cが形成されるとともに、該取付用雌螺子孔21cと同軸に設定された機器固定用雌螺子孔21dが上部に形成され、取付用雌螺子孔21cと機器固定用雌螺子孔21dとの間には、両孔を連通させない壁部21eが形成されている。
【0029】
〔単位座板取付工程〕
第1実施形態と同様な〔アンカーボルト配筋工程〕の後、図6の(a)(b)に示すように、配筋された各アンカーボルト11の先端部分にスペーサ20を取り付けた単位座板21を取り付ける。
すなわち、円板部21bを上方に向けた状態で単位座板21の取付用雌螺子孔21cを、雄螺子部1aに螺合させることにより、アンカーボルト11に単位座板21を取り付ける。
このとき、各単位座板21をスペーサ20とともに回転操作することによって上下に動かし、高さ調整を行うことにより、座板全体としてのレベル調整を行う。
【0030】
〔コンクリート打設工程〕
各単位座板21の高さ調整を行った後、図7の(a)(b)に示すように、領域Aにコンクリート22を打設する。
このとき、コンクリート22は、単位座板21の上面を露出させた状態で床面25の所定高さ、すなわち単位座板21に取り付けられたスペーサ20の周囲まで打設する。
【0031】
〔レベル調整工程〕
コンクリート22の打設後、図8の(a)(b)に示すように、スペーサ20を破壊して取り除くとともに、これによって単位座板21の周囲に空間Kを形成し、単位座板21を回転操作することによって上下させ、単位座板21の上面レベルを再調整する。これによって、座板全体としての再レベル調整が行われる。
なお、このレベル調整後、図9に示すように、空間KをモルタルM(ノンシュリンク)にて充填する。
この後、コンクリート22の表面に被膜としてライニング板6を敷設して床面25を形成する。
【0032】
〔機器据え付け工程〕
コンクリートの養生期間を経て床面25上に機器17を搬入するとともに、図9に示すように、各単位座板21の機器固定用雌螺子孔21dに上部から機器17の据付用ボルト18を螺合させることにより、当該機器17を単位座板21および床面25に据え付け固定する。
【0033】
この座板の設置構造および座板設置床構造の施工方法では、人力で破壊可能な低強度材料で形成された環状のスペーサ20が、単位座板21の外周面を覆って取り付けられているので、コンクリート22を打設した後に、スペーサ20を破壊することにより単位座板21の周囲に空間Kを形成し、単位座板21を回転操作することが可能になり、容易に単位座板21を上下させることができる。
すなわち、第1実施形態のように、コンクリートを打設する際に、単位座板の下部近傍で一旦打設を中断しなくても、一度に単位座板21の上面のレベルまで打設した後に単位座板21の再度の高さ調整が可能であり、打設工程を2つに分ける必要がない。
【0034】
また、この座板の設置構造では、取付用雌螺子孔21cと機器固定用雌螺子孔21dとの間には、両孔を連通させない壁部21eが形成されているので、単位座板21上の流体が機器固定用雌螺子孔21dに侵入しても、壁部21eによって遮断され単位座板21下部のコンクリート22に浸透することがない。
例えば、放射性流体である放射性廃液を取り扱う機器を据え付けた場合でも、たとえ放射性廃液が単位座板21の機器固定用雌螺子孔21dに侵入しても基礎のコンクリート22を汚染することはない。
【0035】
【発明の効果】
本発明によれば、以下の効果を奏する。
(1)請求項1記載の座板の設置構造および請求項2記載の座板設置床構造の施工方法によれば、座板が、少なくとも下部に取付用雌螺子孔を形成した複数の単位座板で構成され、単位座板が、取付用雌螺子孔を基礎ボルトの雄螺子部に螺合させて上下動可能に複数の基礎ボルトにそれぞれ取り付けられているので、各単位座板において個別に高さ調整を行うことができ、座板全体として高精度なレベル調整を行うことができる。そして、コンクリートを打設する際に、一旦、単位座板の下部近傍までコンクリートを打設し、単位座板を回転させてレベルを再調整することにより、ライナー調整によらずとも基礎ボルトのゆがみによって生じた座板の傾きを矯正することができ、高い据付精度をもって機器の据え付け作業の効率を向上させることができる。
また、単位座板の上部に機器を取り付けるための機器固定用雌螺子孔が形成され、機器固定用雌螺子孔が、取付用雌螺子孔と同軸に設定されているので、単位座板に機器を直接据え付けることができるとともに、単位座板を回転させて高さ調整した後も機器固定用雌螺子孔の位置が横方向にずれず、正確に機器を据え付けることができる。
さらに、取付用雌螺子孔と機器固定用雌螺子孔との間には、両孔を連通させない壁部が形成されているので、単位座板上の流体が機器固定用雌螺子孔に侵入しても、単位座板下部のコンクリートへの浸透を防ぐことができる。
【0036】
(2)請求項3記載の座板設置床構造の施工方法によれば、人力で破壊可能な低強度材料で形成された環状のスペーサが、単位座板の外周面を覆って取り付けられているので、コンクリートを全て打設した後でも、スペーサを破壊することにより単位座板を回転操作することが可能になり、コンクリートの打設工程を途中で中断しなくても容易に単位座板を上下動させることができ、工程の短縮化を図ることができる。
【図面の簡単な説明】
【図1】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第1実施形態におけるアンカーボルト配筋工程を示す上面図および要部断面図である。
【図2】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第1実施形態における単位座板取付工程を示す上面図および要部断面図である。
【図3】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第1実施形態における一次打設工程およびレベル調整工程を示す上面図および要部断面図である。
【図4】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第1実施形態における二次打設工程を示す上面図および要部断面図である。
【図5】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第1実施形態における機器据え付け工程を示す要部断面図である。
【図6】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第2実施形態における単位座板取付工程を示す上面図および要部断面図である。
【図7】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第2実施形態におけるコンクリート打設工程を示す上面図および要部断面図である。
【図8】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第2実施形態におけるレベル調整工程を示す上面図および要部断面図である。
【図9】 本発明に係る座板の設置構造および座板設置床構造の施工方法の第2実施形態における機器据え付け工程を示す要部断面図である。
【図10】 本発明に係る座板の設置構造および座板設置床構造の施工方法の従来例を示す上面図および要部断面図である。
【符号の説明】
11 アンカーボルト(基礎ボルト)
11a 雄螺子部
12,21 単位座板
12c 取付用雌螺子孔(機器固定用雌螺子孔)
13 一次コンクリート
14 二次コンクリート
15 床面
20 スペーサ
21c 取付用雌螺子孔
21d 機器固定用雌螺子孔
21e 壁部
22 コンクリート
A 床面となる領域[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an installation structure of a seat plate installed in an area to be a floor surface for level adjustment of a floor surface for equipment installation formed by placing with concrete, and a seat provided with a seat plate for level adjustment. It is related with the construction method of a board installation floor structure.
[0002]
[Prior art]
In the case of forming a floor surface as a foundation for installation of equipment by placing concrete, a seat plate is installed in order to obtain a level of the floor surface.
That is, in the floor surface on which the conventional seat plate is installed, for example, as shown in FIGS. 10A and 10B, the area where the
Thereafter, the
[0003]
[Problems to be solved by the invention]
However, the following problems remain in the conventional seat plate installation means. That is, the
[0004]
The present invention has been made in view of the above-described problems, and can adjust the level of a floor surface formed by placing concrete with high accuracy and improve the efficiency of equipment installation work. It aims at providing the installation method of a board installation structure and a seat board installation floor structure.
[0005]
[Means for Solving the Problems]
The present invention employs the following configuration in order to solve the above problems. That is, in the seat plate installation structure according to
[0006]
Moreover, in the construction method of the seat board installation floor structure of
[0007]
In the construction method of the seat plate installation structure and the seat plate installation floor structure, the seat plate is composed of a plurality of unit seat plates in which female screw holes for attachment are formed at least in the lower part, and the unit seat plate is a female female for attachment. Since the screw hole is screwed to the male screw portion of the foundation bolt and attached to the plurality of foundation bolts so as to be movable up and down, the height of each unit seat plate can be adjusted individually. And when placing concrete, once the concrete is placed near the lower part of the unit seat plate, by rotating the unit seat plate up and down, the level of the seat plate as a whole is readjusted, Furthermore, after that, by placing concrete again around the unit seat plate, the inclination of the seat plate caused by the distortion of the foundation bolt can be corrected without adjusting the liner.
Also, a device fixing female screw hole for mounting the device is formed on the upper part of the unit seat plate, and the device fixing female screw hole is set coaxially with the mounting female screw hole. The device fixing female screw hole does not shift in the lateral direction even after the height of the unit seat plate is adjusted by rotating the unit seat plate, and the device can be installed accurately.
Furthermore, since a wall portion that does not allow the holes to communicate with each other is formed between the mounting female screw hole and the device fixing female screw hole, the fluid on the unit seat plate enters the device fixing female screw hole. However, it does not penetrate into the concrete below the unit seat plate.
[0009]
Moreover, in the construction method of the seat board installation floor structure of
[0010]
In the construction method of this floor structure, the annular spacer made of a low-strength material that can be broken by human power is attached so as to cover the outer peripheral surface of the unit seat board. By breaking the spacer, a space is formed around the unit seat plate, the unit seat plate can be rotated, and the unit seat plate can be easily moved up and down. In other words, when placing concrete, it is possible to adjust the height of the unit seat plate after placing it up to the level of the upper surface of the unit seat plate at once, without interrupting the placement once near the lower part of the unit seat plate. Therefore, it is not necessary to divide the placing process into two.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EMBODIMENTS Hereinafter, a first embodiment of a seating board arrangement structure and a seating board arrangement floor structure construction method according to the present invention will be described with reference to FIGS. 1 to 5.
In these drawings,
[0016]
[Anchor bolt reinforcement process]
First, as shown in FIGS. 1 (a) and 1 (b), anchor bolts (foundation bolts) 11 are erected vertically at a plurality of locations in a region A serving as a floor surface.
The
In the present embodiment, the
[0017]
[Unit seating process]
Thereafter, as shown in FIGS. 2A and 2B, the
The
[0018]
That is, the
At this time, each
[0019]
[Primary placement process]
After adjusting the height of each
At this time, the
[0020]
[Level adjustment process]
After placing the
[0021]
[Secondary placement process]
Further, as shown in FIGS. 4A and 4B, the
At this time, the
Thereafter, a
[0022]
[Equipment installation process]
The
[0023]
In the construction method of the seat plate installation structure and the seat plate installation floor structure, the seat plate is composed of a plurality of
[0024]
Further, when placing concrete, the
[0025]
Next, a second embodiment of the construction method of the seat board arrangement structure and the seat board arrangement floor structure according to the present invention will be described with reference to FIGS.
In these drawings,
[0026]
The difference between the second embodiment and the first embodiment is that, in the first embodiment, the primary placement process and the secondary placement process are performed twice for level adjustment, whereas the second embodiment is different from the second embodiment. In the embodiment, by using the
Below, each process after the anchor bolt arrangement process similar to 1st Embodiment is explained in full detail.
[0027]
[Spacer mounting process]
An
The
[0028]
The
[0029]
[Unit seating process]
After the [anchor bolt arranging step] similar to the first embodiment, as shown in FIGS. 6A and 6B, the unit seat in which the
That is, the
At this time, each
[0030]
[Concrete placing process]
After adjusting the height of each
At this time, the concrete 22 is placed to a predetermined height of the
[0031]
[Level adjustment process]
After placing the concrete 22, as shown in FIGS. 8 (a) and 8 (b), the
After this level adjustment, the space K is filled with mortar M (non-shrink) as shown in FIG.
Thereafter, the lining plate 6 is laid as a coating on the surface of the concrete 22 to form the
[0032]
[Equipment installation process]
The
[0033]
In the construction method of the seat plate installation structure and the seat plate installation floor structure, the
That is, after placing the concrete up to the level of the upper surface of the
[0034]
Further, in this seat plate installation structure, a
For example, even when a device that handles radioactive liquid waste, which is a radioactive fluid, is installed, even if the radioactive liquid waste enters the device fixing female screw hole 21d of the
[0035]
【The invention's effect】
The present invention has the following effects.
(1) According to the installation method of the seat plate installation structure according to
Also, a device fixing female screw hole for mounting the device is formed on the upper part of the unit seat plate, and the device fixing female screw hole is set coaxially with the mounting female screw hole. The device fixing female screw hole does not shift in the lateral direction even after the height of the unit seat plate is adjusted by rotating the unit seat plate, and the device can be installed accurately.
Furthermore, since a wall portion that does not allow the holes to communicate with each other is formed between the mounting female screw hole and the device fixing female screw hole, the fluid on the unit seat plate enters the device fixing female screw hole. However, it is possible to prevent the penetration of the lower part of the unit seat plate into the concrete.
[0036]
(2) According to the construction method of the seat board installation floor structure of the third aspect, the annular spacer formed of a low strength material that can be broken by human power is attached so as to cover the outer peripheral surface of the unit seat board. Therefore, even after all the concrete has been placed, it is possible to rotate the unit seat plate by destroying the spacer, and the unit seat plate can be easily moved up and down without interrupting the concrete placing process. The process can be shortened.
[Brief description of the drawings]
FIGS. 1A and 1B are a top view and a cross-sectional view of an essential part showing an anchor bolt arranging step in a first embodiment of a seat board installation structure and a seat board installation floor structure construction method according to the present invention.
FIGS. 2A and 2B are a top view and a main part sectional view showing a unit seat plate mounting step in the first embodiment of the seat plate installation structure and the seat plate installation floor structure construction method according to the present invention. FIGS.
FIGS. 3A and 3B are a top view and a main part sectional view showing a primary placing process and a level adjusting process in the first embodiment of the construction method of the seat board installation structure and the seat board installation floor structure according to the present invention. FIGS.
FIGS. 4A and 4B are a top view and a cross-sectional view of a main part showing a secondary placing process in the first embodiment of the construction method of the seat board installation structure and the seat board installation floor structure according to the present invention.
FIG. 5 is a cross-sectional view of an essential part showing a device installation step in the first embodiment of the construction method of the seat board installation structure and the seat board installation floor structure according to the present invention.
FIGS. 6A and 6B are a top view and a cross-sectional view of a main part showing a unit seat plate mounting step in a second embodiment of the seat plate installation structure and the seat plate installation floor structure construction method according to the present invention.
FIGS. 7A and 7B are a top view and a cross-sectional view of a main part showing a concrete placing process in a second embodiment of the construction method of the seat board installation structure and the seat board installation floor structure according to the present invention.
FIGS. 8A and 8B are a top view and a main part sectional view showing a level adjusting step in a second embodiment of the construction method of the seat board installation structure and the seat board installation floor structure according to the present invention. FIGS.
FIG. 9 is a cross-sectional view of an essential part showing a device installation process in a second embodiment of the construction method of the seat board installation structure and the seat board installation floor structure according to the present invention.
FIGS. 10A and 10B are a top view and a main part sectional view showing a conventional example of a construction method of a seat board installation structure and a seat board installation floor structure according to the present invention.
[Explanation of symbols]
11 Anchor bolt (foundation bolt)
11a
13
Claims (3)
先端部に雄螺子部を形成した基礎ボルトが、前記床面となる領域内の複数箇所に垂直に立設され、
前記座板は、少なくとも下部に取付用雌螺子孔を形成した複数の単位座板で構成され、
前記単位座板は、前記取付用雌螺子孔を前記雄螺子部に螺合させて上下動可能に前記複数の基礎ボルトにそれぞれ取り付けられ、
前記単位座板の上部には前記取付用雌螺子と同軸に機器固定用雌螺子孔が形成され、前記取付用雌螺子孔と前記機器固定用雌螺子孔との間は、該両孔を連通させない壁部が形成され、
さらに複数の前記単位座板の円筒状本体の上部に形成され該円筒状本体より大径の円板部の上面と打設された前記コンクリートの上面をそれぞれ被膜するライニング板を敷設して前記床面が形成されたことを特徴とする座板の設置構造。It is an installation structure of a seat plate that is installed in an area that becomes a floor surface in order to adjust the level of the floor surface that is formed by placing concrete,
A foundation bolt having a male screw portion formed at the tip is vertically erected at a plurality of locations in the area to be the floor surface,
The seat plate is composed of a plurality of unit seat plates in which a female screw hole for attachment is formed at least in the lower part,
The unit seat plate is respectively attached to the plurality of foundation bolts so as to be vertically movable by screwing the female screw hole for attachment to the male screw part,
A device fixing female screw hole is formed in the upper part of the unit seat plate coaxially with the mounting female screw, and the two holes are communicated between the mounting female screw hole and the device fixing female screw hole. A wall that is not allowed to be formed,
Furthermore, the floor is formed by laying a lining plate formed on the cylindrical main body of the plurality of unit seat plates and covering the upper surface of the disk portion having a diameter larger than that of the cylindrical main body and the upper surface of the placed concrete. An installation structure of a seat plate, characterized in that a surface is formed .
先端部に雄螺子部が形成された基礎ボルトを、所定の複数箇所に垂直に立設するボルト設置工程と、
少なくとも下部に取付用雌螺子孔が形成されるとともに上部に該取付用雌螺子孔と同軸に機器固定用雌螺子孔が形成され、前記取付用雌螺子孔と前記機器固定用雌螺子孔との間に、該両雌螺子孔を連通させない壁部が形成された複数の単位座板を、前記雄螺子部に前記取付用雌螺子孔を螺合させて前記基礎ボルトにそれぞれ取り付ける単位座板取付工程と、
前記単位座板と前記基礎ボルトとの周囲に、単位座板の上面を露出させた状態でコンクリートを打設するコンクリート打設工程とを備え、
該コンクリート打設工程は、前記単位座板の下部近傍までコンクリートを打設する一次打設工程と、
一次打設工程の後、前記単位座板を回転させて上下動させ高さ調整を行うレベル調整工程と、
該レベル調整工程の後、前記単位座板の周囲までコンクリートを打設する二次打設工程と、
複数の前記単位座板の円筒状本体の上部に形成され該円筒状本体より大径の円板部の上面と二次打設工程で打設された前記コンクリートの上面をそれぞれ被膜するライニング板を敷設する工程を備えていることを特徴とする座板設置床構造の施工方法。It is a construction method of a seat plate installation floor structure provided with a seat plate for level adjustment,
A bolt installation step in which a foundation bolt in which a male screw portion is formed at a tip end portion is erected vertically at a predetermined plurality of locations;
An attachment female screw hole is formed at least in the lower part, and an apparatus fixing female screw hole is formed in the upper part coaxially with the attachment female screw hole, and the attachment female screw hole and the apparatus fixing female screw hole are A plurality of unit seat plates each having a wall portion that does not allow the female screw holes to communicate with each other are attached to the base bolts by screwing the female screw holes for attachment to the male screw portions. Process,
A concrete placing step of placing concrete around the unit seat plate and the foundation bolt with the upper surface of the unit seat plate exposed;
The concrete placing step includes a primary placing step of placing concrete to the vicinity of the lower part of the unit seat plate,
After the primary placing step, the unit seat plate is rotated and moved up and down to adjust the height; and
After the level adjustment step, a secondary placement step of placing concrete around the unit seat plate,
A lining plate formed on the cylindrical main body of the unit seat plate and covering the upper surface of the disk portion having a larger diameter than the cylindrical main body and the upper surface of the concrete placed in the secondary placement step. A construction method for a floor structure with a seat plate, characterized by comprising a step of laying .
先端部に雄螺子部が形成された基礎ボルトを、所定の複数箇所に垂直に立設するボルト設置工程と、
少なくとも下部に取付用雌螺子孔が形成されるとともに上部に該取付用雌螺子孔と同軸に機器固定用雌螺子孔が形成され、前記取付用雌螺子孔と前記機器固定用雌螺子孔との間に、該両雌螺子孔を連通させない壁部が形成された複数の単位座板を、前記雄螺子部に前記取付用雌螺子孔を螺合させて前記基礎ボルトにそれぞれ取り付ける単位座板取付工程と、
前記単位座板に、その外周面を覆って、人力で破壊可能な低強度材料で形成された環状のスペーサを取り付けるスペーサ取付工程と、
前記スペーサを取り付けた前記単位座板と前記基礎ボルトとの周囲に、前記単位座板の上面を露出させた状態でコンクリートを打設するコンクリート打設工程と、
該コンクリート打設工程の後、前記スペーサを破壊するとともに、前記単位座板を回転させて上下動させ高さ調整を行うレベル調整工程と、
該レベル調整工程の後に、前記スペーサを破壊し取り除いた空間に前記単位座板の周囲をモルタルにて充填するモルタル充填工程と、
該モルタル充填工程の後に、複数の前記単位座板の円筒状本体の上部に形成され該円筒状本体より大径の円板部の上面と打設された前記コンクリートの上面と充填された前記モルタルの上面をそれぞれ被膜するライニング板を敷設する工程とを備えていることを特徴とする座板設置床構造の施工方法。It is a construction method of a seat plate installation floor structure provided with a seat plate for level adjustment,
A bolt installation step in which a foundation bolt in which a male screw portion is formed at a tip end portion is erected vertically at a predetermined plurality of locations;
An attachment female screw hole is formed at least in the lower part, and an apparatus fixing female screw hole is formed in the upper part coaxially with the attachment female screw hole, and the attachment female screw hole and the apparatus fixing female screw hole are A plurality of unit seat plates each having a wall portion that does not allow the female screw holes to communicate with each other are attached to the base bolts by screwing the mounting female screw holes into the male screw portions. Process,
A spacer mounting step for mounting an annular spacer formed of a low-strength material that can be broken by human power, covering the outer peripheral surface of the unit seat plate,
And concreting step of pouring the concrete in the state around and the unit seat plate fitted with the spacer the foundation bolts, to expose the upper surface of the unit seat plate,
After the concrete placing step, the level adjusting step of breaking the spacer and rotating the unit seat plate to move up and down to adjust the height ;
After the level adjustment step, a mortar filling step of filling the space around the unit seat plate with mortar in the space where the spacer is destroyed and removed,
After the mortar filling step, the mortar filled with the upper surface of the disk portion and the upper surface of the concrete formed on the cylindrical main body of the plurality of unit seat plates and having a larger diameter than the cylindrical main body. And a step of laying a lining plate that coats the upper surface of the base plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30775799A JP4282847B2 (en) | 1999-10-28 | 1999-10-28 | Seat plate installation structure and floor plate installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30775799A JP4282847B2 (en) | 1999-10-28 | 1999-10-28 | Seat plate installation structure and floor plate installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001124290A JP2001124290A (en) | 2001-05-11 |
JP4282847B2 true JP4282847B2 (en) | 2009-06-24 |
Family
ID=17972918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30775799A Expired - Fee Related JP4282847B2 (en) | 1999-10-28 | 1999-10-28 | Seat plate installation structure and floor plate installation method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4282847B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7396763B1 (en) | 2022-12-14 | 2023-12-12 | スエヒロシステム株式会社 | 3-point anchor integrated liner, long anchor integrated liner, equipment installation method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100794617B1 (en) * | 2006-04-03 | 2008-01-15 | 송유섭 | Concrete placing leveler |
-
1999
- 1999-10-28 JP JP30775799A patent/JP4282847B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7396763B1 (en) | 2022-12-14 | 2023-12-12 | スエヒロシステム株式会社 | 3-point anchor integrated liner, long anchor integrated liner, equipment installation method |
Also Published As
Publication number | Publication date |
---|---|
JP2001124290A (en) | 2001-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7921616B2 (en) | Method and apparatus for setting support columns within a foundation | |
US8365485B2 (en) | Method and apparatus for setting support columns within a foundation | |
JP4282847B2 (en) | Seat plate installation structure and floor plate installation method | |
JP3895023B2 (en) | Machine foundation | |
JP2870513B2 (en) | A method of aligning the core of a steel column with the foundation concrete | |
JP3599050B2 (en) | Construction method of precast concrete ring at pile head | |
GB1599341A (en) | Method and a device for mounting points in mounting areas | |
JP3700096B2 (en) | Seismic isolation device installation method | |
AU2010226975A1 (en) | Precast Concrete Foundation Block and Foundation | |
JP2022551760A (en) | Anchor devices, anchors including anchor devices, and methods of manufacturing anchors | |
JP2003113644A (en) | Building method of precast concrete-made vertical member | |
JP2002242213A (en) | Manhole | |
JP3481986B2 (en) | Precast concrete foundation slab and method of constructing concrete foundation floor | |
JPH0219450Y2 (en) | ||
JP5470196B2 (en) | How to install the structure | |
JPH0742164A (en) | Pillar erection execution method and pillar bottom support device | |
KR20120015807A (en) | Concrete structure for bridge and its manufacturing method | |
JPS6015794Y2 (en) | Electrical equipment installation equipment | |
JP2546498Y2 (en) | Supporting equipment such as floorboards | |
CN206554517U (en) | Housing platform for lining for sandy soil geology | |
JPS6035639Y2 (en) | Hardware for installing foundations of tower-like structures | |
JP2008214986A (en) | Base isolator mounting structure at pile head, and its mounting method | |
JP2022096117A (en) | Equipment foundation structure | |
JPH09264030A (en) | Method of construction of fixing pedestal of exposed type and members and washers for level adjustment used therefor | |
KR200249533Y1 (en) | A man hole cover case being able to adjusting its height |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051227 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20061222 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20061222 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20081104 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090105 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20090116 |
|
TRDD | Decision of grant or rejection written | ||
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20090116 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090303 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090318 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4282847 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120327 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130327 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130327 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140327 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |