JP4267195B2 - Construction method of hardware parts manufacturing factory etc. structure with precast concrete waffle slab layer - Google Patents
Construction method of hardware parts manufacturing factory etc. structure with precast concrete waffle slab layer Download PDFInfo
- Publication number
- JP4267195B2 JP4267195B2 JP2000320731A JP2000320731A JP4267195B2 JP 4267195 B2 JP4267195 B2 JP 4267195B2 JP 2000320731 A JP2000320731 A JP 2000320731A JP 2000320731 A JP2000320731 A JP 2000320731A JP 4267195 B2 JP4267195 B2 JP 4267195B2
- Authority
- JP
- Japan
- Prior art keywords
- precast concrete
- waffle slab
- concrete waffle
- precast
- rectangular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Panels For Use In Building Construction (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は一種のプレキャストコンクリートワッフルスラブ構造に関するものである。特に一種の構造の安全、防火及び耐震性能、輸送の利便性、迅速な施工、及び美観を達成するプレキャストコンクリートワッフルスラブ層を有するハードウエアー部品製造工場等構造物の構築法に係るものである。
【0002】
【従来の技術】
社会構造の急速な変遷に伴い、多くの作業方式において伝統的な考え方は遺棄されつつある。例えば、建築施工法では既に、建築設計の企画時、出来る限り標準化されたプレキャストコンクリート造製品を採用、或いは有効な組合せ工法を運用するまでに至っている。なぜなら、こうすることにより、現場施工の安全、環境の衛生、工期の短縮、技術人員及び材料の同時調達等、多くの問題を改善することが可能であるからである。
しかし、すべての建築、或いは土木作業工程がプレキャストコンクリート工法の採用に適している訳ではない。ひとえに構造の安全、建築コスト、施工の可能性、輸送の利便性等に対するニーズを満たすことができるか否かによるのである。一般の建築設計技術者、或いは建築施工技術者が状況に応じて採用する場所打ち現場コンクリート工法、及びプレキャストコンクリート工法を組み合わせた混合工法は、多くの制約条件を克服する良好な方法である。即ち、多くの建築工事において、プレキャストコンクリート工法はなくてはならない重要な工法の一つである。
【0003】
ここ数年、IT技術が経済の牽引役となっており、それに伴いIT技術の核心である「集積回路等ハードウエアーを構成する」部品の需要は、右肩上がりに直線を描いて上昇している。このような状況であるため、ハードウエアー部品製造工場への投資と工場建設において、欠くべからざる条件は「時間」、とも言えるものである。つまり、部品製造工場の建設原則は、構造、工事の安全等が建築法規規定に合致することはもちろんのこと、完成予定、即ち工期は、利益確保の最良時期を掌握できるか否かの重要な要素となっている。
一般に当該ハードウエアー部品製造工場は機器、加工機等の配備が必要であるため、当該配備に用いるワッフルスラブ層を設置する。当該ワッフルスラブ層は支柱により床を上げたスラブ層で、従来のハードウエアー部品製造工場のスラブ層施工においては、先ず現場において柱体を施工し、次に柱体の完成後、型枠を組み立て、鉄筋を配置する。続いて、コンクリートを打設しスラブ層を完成させるが、この工法は施工期間が長く、しかも現場の他の施工との間で工程進行上の衝突を生み出す。
【0004】
【発明が解決しようとする課題】
上記公知施工法の欠点を解決するため、本発明はハードウエアー部品製造工場のプレキャストコンクリートワッフルスラブ構造の提供を課題とする。
それは、ハードウエアー部品製造工場において機器、加工機等を設置するワッフルスラブ層全体を、プレキャストコンクリート工法により製造、構造の組み立てを行うもので、数本が対応し直立する柱体に、プレキャストコンクリートワッフルスラブ層を組合せ構成する。当該構造は各種機具設置のニーズに適合する他、施工期間を短縮することができ、かつハードウエアー部品製造工場建設における現場施工工数を大幅に減少させることができる。こうして、構造の安全、防火及び耐震性能、輸送の利便性、迅速な施工、及び美観を達成する。
【0005】
【課題を解決するための手段】
上記課題を解決するため、本発明は下記のハードウエアー部品製造工場プレキャストコンクリートワッフルスラブ構造を提供する。
それは主に、数本の共用のプレキャストコンクリート及び、場所打ちコンクリート造柱体を含む。
当該柱体は正方形、円形及び矩形を呈し、当該柱体頭部の大きなサポート部分を形成する。これに、数種の異なる実施例、及び類似相互体であるプレキャストコンクリートワッフルスラブを組合せる。
その組合せ方式は、先ず当該柱体を対応位置において、予め直立、設置させ、各実施例のプレキャストコンクリートワッフルスラブを当該柱体において設置する。続いて、各プレキャストコンクリートワッフルスラブの角を直接接触させ、或いは組合せ部品を用い、当該柱体サポート部分上に設置し、ハードウエアー部品製造工場プレキャストコンクリートワッフルスラブ層を構成する。
【0006】
【発明の実施の形態】
図が示すように、本発明は主に数本の共用のプレキャストコンクリート及び、場所打ちコンクリート造柱体1を含む。当該柱体の形状は正方形、円形及び矩形を呈し、当該柱体頭部の大きなサポート部分11を形成する。これに、数種の異なる実施例、及び類似相互体であるプレキャストコンクリートワッフルスラブ2、3、4、5、6、7、8、9を組合せ、ハードウエアー部品製造工場等構造物のプレキャストコンクリートワッフルスラブを構成する。
当該柱体1は対応位置において、予め直立、設置し、各実施例のプレキャストコンクリートワッフルスラブ2、3、4、5、6、7、8、9を当該各柱体1において設置する。続いて、各プレキャストコンクリートワッフルスラブ2、3、4、5、6、7、8、9の角を直接接触させ、或いは組合せ部品を用い、当該各柱体1サポート部分11上に設置し、ハードウエアー部品製造工場等構造物のプレキャストコンクリートワッフルスラブ層を構成する。
【0007】
図が示すように本発明第一、二、三、四実施例のワッフルスラブ、及び第一、二実施例のワッフルスラブ類似相互体はすべてフルプレキャストコンクリート造に属する。即ち、当該プレキャストコンクリートワッフルスラブ2、3、4、5、7、8、は予め全体をプレキャストコンクリートに成型し、現場に輸送した時には、直接当該各柱体1上に設置、或いは組み立てを経て当該各柱体1上に設置するだけで良く、接合部以外は、現場において別に鉄筋を設置し、コンクリートを打設する作業を必要としない。
また、本発明第五実施例のワッフルスラブ、及び第九実施例のワッフルスラブ類似相互体はハーフプレキャストコンクリート造に属する。即ち、当該プレキャストコンクリートワッフルスラブ6、9は予めハーフプレキャストコンクリートに成型し、当該プレキャストコンクリートワッフルスラブ6、9上に小型円柱体63、及び(或いは)多柱状連結ブロック65を融合し、現場に輸送した時には、さらに鉄筋を配置し、コンクリートを打設し成型作業を完成するものである。
【0008】
図1、2、3、4が示すように、本発明第一実施例の方形プレキャストコンクリートワッフルスラブ2は、その各角に切欠部21を形成し、上面には円形孔22を開設する。下面は貫通格子状23を呈し、十分な強度を具えた中空格子である当該貫通格子状23により重量、及び材料を節約することができる。当該プレキャストコンクリートワッフルスラブ2を各柱体1間に設置することにより、安定した構造で安全性を具えたハードウエアー部品製造工場等構造物のプレキャストコンクリートワッフルスラブ層を構成する。
【0009】
図5、6、7、8が示すように、本発明第二実施例の方形プレキャストコンクリートワッフルスラブ3は、先ず逆T型プレキャストコンクリート梁補助部品31を、当該各柱体1上に二方向に設置し、その上で、対応する当該方形プレキャストコンクリートワッフルスラブ3を各逆T型プレキャストコンクリート梁補助部品31中に嵌入し、設置する。当該逆T型プレキャストコンクリート梁補助部品31上には貫通孔32を設置し、上面には円形孔33を開設する。下面には格子状強化梁34を設置する。
【0010】
図9、10、11、12が示すように、本発明第三実施例の複数本よりなる矩形梁状プレキャストコンクリートワッフルスラブ4は、先ず側辺において錐状凹凸を形成する逆T型プレキャストコンクリート梁補助部品41を、当該各柱体1上に一方向に設置し、その上で、対応する当該矩形梁状プレキャストコンクリートワッフルスラブ4をその両端を利用し各側辺において錐状凹凸を形成する逆T型プレキャストコンクリート梁補助部品41中に嵌入し、設置する。当該梁状プレキャストコンクリートワッフルスラブは、複数の一方向梁構造をなす。
【0011】
図13、14、15、16が示すように、本発明第四実施例の逆U型梁状プレキャストコンクリートワッフルスラブ5は、全体の形状が逆U型を呈し、複数個並べてワッフルスラブを形成する。また、逆T型プレキャストコンクリート梁補助部品51は側辺において突起ブロック52を形成する。先ず逆T型プレキャストコンクリート梁補助部品51を、当該各柱体1上に一方向に設置し、その上で、対応する当該逆U型梁状プレキャストコンクリートワッフルスラブ5を両端を利用し各逆T型プレキャストコンクリート梁補助部品51の突起ブロック52中に嵌入し、設置する。当該逆U型梁状プレキャストコンクリートワッフルスラブ5上面には方形孔53を開設し、下面は二本の一方向矩形状梁54を設置する。
【0012】
図17、18、19、20が示すように、本発明第五実施例のハーフプレキャスト皿型コンクリートワッフルスラブ6は、その上面周囲縁は薄板61を呈し、該薄板61上には円形孔62を設置する。該円形孔62には小型円柱体63(軽量プラスチック製の補助円柱)を嵌入し、当該ハーフプレキャスト皿型コンクリートワッフルスラブ6と結合し一体とする。当該ハーフプレキャスト皿型コンクリートワッフルスラブ6の中央部分には方形槽64を形成し、当該方形槽64中には多柱状連結ブロック65を嵌入し、当該ハーフプレキャスト皿型コンクリートワッフルスラブ6と結合し一体化する。
本ハーフプレキャスト皿型コンクリートワッフルスラブ造式実施例は、成型後は図19が示す形状となり、現場に輸送後、当該各柱体1に固定後、コンクリートを打設し、図3が示すような第一実施例のフルプレキャストコンクリートワッフルスラブ2を成型する。
当該ハーフプレキャスト皿型コンクリートワッフルスラブの特性は、強度が十分で、かつフルプレキャストコンクリートワッフルスラブに比較し軽量である点である。そのため、運送、及び施工共に、フルプレキャストコンクリートワッフルスラブに比較し優れ、かつ当該ハーフプレキャスト皿型コンクリートワッフルスラブ間における鉄筋の接続作業は、フルプレキャストコンクリートワッフルスラブより一層容易である。しかし、その欠点は現場において、別にコンクリート打設等の作業を必要とする点である。
【0013】
次に図21、22、23、24が示すように、本発明第一実施例の方形プレキャストコンクリートワッフルスラブ2は、方形プレキャストコンクリートワッフルスラブ類似相互体7に成型することもできる。当該方形プレキャストコンクリートワッフルスラブ類似相互体7は実芯状で、かつ上には貫通孔71を形成する。
さらに次に図25、26、27、28が示すように、本発明第二実施例の逆T型プレキャストコンクリート梁補助部品および方形プレキャストコンクリートワッフルスラブよりなるプレキャストコンクリートワッフルスラブの方形プレキャストコンクリートワッフルスラブ3は、方形プレキャストコンクリートワッフルスラブ類似相互体8に成型することもできる。この場合も逆T型プレキャストコンクリート梁補助部品31は変わらず、当該方形プレキャストコンクリートワッフルスラブ類似相互体8は実芯状で、かつ上には貫通孔81を形成する。
また、図、29、30、31、32が示すように、本発明第五実施例のハーフプレキャスト皿型コンクリートワッフルスラブ6は、ハーフプレキャスト皿型コンクリートワッフルスラブ類似相互体9に成型することもできる。この場合には、一列に並んだ貫通孔91とし、同様に小型円柱体63を嵌入することができる。これにより、その効果は第五実施例のワッフルスラブ6構造と同様となり、しかも強度は十分でありながら、軽量であると言う長所を具える。加えて、ワッフルスラブ間の接合作業は、フルプレキャストコンクリートワッフルスラブより一層容易である。
【0014】
【発明の効果】
本発明はハードウエアー部品製造工場において機器、加工機等を設置するワッフルスラブ層全体を、プレキャストコンクリート工法により製造、構造の組み立てを行うものである。当該構造は十分な強度を具えるため、各種機具設置のニーズに適合する構造の安全性を達成することができる。
さらに、現場における鉄筋配置、コンクリート打設等の作業を短縮、或いは不要とし、また接合操作が容易であるため現場施工を減少させることができるため、施工期間を大幅に短縮することができる。こうして、ハードウエアー部品製造工場建設における重要な要素である、利益確保の最良時期を的確に掌握可能とする。
加えて、当該構造は軽量であるため輸送の利便性が高く、しかも高い防火及び耐震性能をも具える。
【図面の簡単な説明】
【図1】本発明第一実施例であるワッフルスラブ層の上面図である。
【図2】本発明第一実施例であるワッフルスラブ層の側面図である。
【図3】本発明第一実施例であるワッフルスラブ層の立体図である。
【図4】本発明第一実施例であるワッフルスラブ層の底面立体図である。
【図5】本発明第二実施例であるワッフルスラブ層の上面図である。
【図6】本発明第二実施例であるワッフルスラブ層の側面図である。
【図7】本発明第二実施例であるワッフルスラブ層の立体図である。
【図8】本発明第二実施例であるワッフルスラブ層の底面立体図である。
【図9】本発明第三実施例であるワッフルスラブ層の上面図である。
【図10】本発明第三実施例であるワッフルスラブ層の側面図である。
【図11】本発明第三実施例であるワッフルスラブ層の立体図である。
【図12】本発明第三実施例であるワッフルスラブ層の底面立体図である。
【図13】本発明第四実施例であるワッフルスラブ層の上面図である。
【図14】本発明第四実施例であるワッフルスラブ層の側面図である。
【図15】本発明第四実施例であるワッフルスラブ層の立体図である。
【図16】本発明第実施例であるワッフルスラブ層の底面立体図である。
【図17】本発明第五実施例であるワッフルスラブ層の上面図である。
【図18】本発明第五実施例であるワッフルスラブ層の側面図である。
【図19】本発明第五実施例であるワッフルスラブ層の立体図である。
【図20】本発明第五実施例であるワッフルスラブ層の底面立体図である。
【図21】本発明第一実施例であるワッフルスラブ層類似相互体の上面図である。
【図22】本発明第一実施例であるワッフルスラブ層類似相互体の側面図である。
【図23】本発明第一実施例であるワッフルスラブ層類似相互体の立体図である。
【図24】本発明第一実施例であるワッフルスラブ層類似相互体の底面立体図である。
【図25】本発明第二実施例であるワッフルスラブ層類似相互体の上面図である。
【図26】本発明第二実施例であるワッフルスラブ層類似相互体の側面図である。
【図27】本発明第二実施例であるワッフルスラブ層類似相互体の立体図である。
【図28】本発明第二実施例であるワッフルスラブ層類似相互体の底面立体図である。
【図29】本発明第五実施例であるワッフルスラブ層類似相互体の上面図である。
【図30】本発明第五実施例であるワッフルスラブ層類似相互体の側面図である。
【図31】本発明第五実施例であるワッフルスラブ層類似相互体の立体図である。
【図32】本発明第五実施例であるワッフルスラブ層類似相互体の底面立体図である。
【符号の説明】
1 プレキャストコンクリート及び、場所打ちコンクリート造柱体
11 サポート部分
2 方形プレキャストコンクリートワッフルスラブ
21 切欠部
22 円形孔
23 貫通状
3 方形プレキャストコンクリートワッフルスラブ
31 逆T型プレキャストコンクリート梁補助部品
32 貫通孔
33 円形孔
34 格子状梁
4 矩形梁状プレキャストコンクリートワッフルスラブ
41 逆T型プレキャストコンクリート梁補助部品
42 棒状部品
43 錐型強化梁
5 逆U型梁状プレキャストコンクリートワッフルスラブ
51 逆T型プレキャストコンクリート梁補助部品
52 突起ブロック
53 方形孔
54 一方向矩形梁
6 ハーフプレキャスト皿型コンクリートワッフルスラブ
61 薄板
62 円形孔
63 小型円柱体
64 方形槽
65 多柱状連結ブロック
7 方形プレキャストコンクリートワッフルスラブ類似相互体
71 貫通孔
8 方形プレキャストコンクリートワッフルスラブ類似相互体
81 貫通孔
9 ハーフプレキャスト皿型コンクリートワッフルスラブ類似相互体
91 貫通孔[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a kind of precast concrete waffle slab structure. In particular, the present invention relates to a method for constructing a structure such as a hardware component manufacturing factory having a precast concrete waffle slab layer that achieves a kind of structure safety, fire prevention and seismic performance, transportation convenience, rapid construction, and aesthetics.
[0002]
[Prior art]
With the rapid change of social structure, traditional ways of thinking are being abandoned in many working methods. For example, the building construction method has already come to adopt precast concrete products standardized as much as possible or to use an effective combination method when planning architectural design. This is because, in this way, it is possible to improve many problems such as on-site construction safety, environmental hygiene, shortening the construction period, and simultaneous procurement of technical personnel and materials.
However, not all construction or civil engineering work processes are suitable for adopting a precast concrete method. It depends solely on whether the needs for structural safety, construction costs, construction possibilities, transportation convenience, etc. can be met. A cast-in-place concrete method and a precast concrete method combined by a general building design engineer or a building construction engineer according to the situation are a good method for overcoming many constraints. In other words, the precast concrete method is one of the important methods that must be used in many construction works.
[0003]
In recent years, IT technology has been a driving force in the economy, and as a result, the demand for components that make up hardware such as integrated circuits, which is the core of IT technology, has risen in a straight line. Yes. Because of this situation, the indispensable condition for investing in a hardware parts manufacturing factory and building a factory is “time”. In other words, the construction principle of the parts manufacturing plant is not only that the structure, construction safety, etc. meet the regulations of the building law, but also the planned completion, that is, whether the construction period can grasp the best time to secure profits. It is an element.
Generally, since the hardware component manufacturing factory requires the deployment of equipment, processing machines, etc., a waffle slab layer used for the deployment is installed. The waffle slab layer is a slab layer whose floor is raised by a support column. In the conventional slab layer construction of a hardware parts manufacturing factory, the column body is first constructed on the spot, and then the formwork is assembled after the column body is completed. Place the rebar. Subsequently, concrete is cast to complete the slab layer. This construction method has a long construction period, and also creates a collision in the process progress with other construction on the site.
[0004]
[Problems to be solved by the invention]
In order to solve the drawbacks of the above known construction methods, an object of the present invention is to provide a precast concrete waffle slab structure of a hardware component manufacturing factory.
In the hardware parts manufacturing factory, the entire waffle slab layer where equipment, processing machines, etc. are installed is manufactured by precast concrete construction and the structure is assembled. Precast concrete waffles are supported on several upright columns. Combining slab layers. In addition to meeting the needs of various equipment installations, this structure can shorten the construction period and can greatly reduce the number of on-site construction man-hours in the construction of a hardware component manufacturing factory. In this way, structural safety, fire and seismic performance, transportation convenience, rapid construction and aesthetics are achieved.
[0005]
[Means for Solving the Problems]
In order to solve the above problems, the present invention provides the following hardware component manufacturing factory precast concrete waffle slab structure.
It mainly includes several shared precast concrete and cast-in-place concrete columns.
The column body has a square shape, a circular shape, and a rectangular shape, and forms a large support portion of the column body head. This is combined with several different embodiments and precast concrete waffle slabs which are similar to each other.
In the combination method, the column body is first set upright in advance at the corresponding position, and the precast concrete waffle slab of each embodiment is installed in the column body. Subsequently, the corners of each precast concrete waffle slab are brought into direct contact with each other, or a combination part is used to install the precast concrete waffle slab on the pillar support portion, thereby forming a hardware part manufacturing factory precast concrete waffle slab layer.
[0006]
DETAILED DESCRIPTION OF THE INVENTION
As the figure shows, the present invention mainly includes several common precast concrete and cast-in-
The
[0007]
As shown in the figure, the waffle slabs of the first, second, third, and fourth embodiments of the present invention and the waffle slab-like mutual bodies of the first and second embodiments all belong to a full precast concrete structure. That is, the precast
Moreover, the waffle slab of the fifth embodiment of the present invention and the waffle slab-like mutual body of the ninth embodiment belong to the half precast concrete structure. That is, the precast
[0008]
As shown in FIGS. 1, 2, 3, and 4, the rectangular precast concrete waffle slab 2 according to the first embodiment of the present invention has a
[0009]
As shown in FIGS. 5, 6, 7, and 8, the rectangular precast concrete waffle slab 3 according to the second embodiment of the present invention first has the inverted T-type precast concrete beam
[0010]
As shown in FIGS. 9, 10, 11, and 12, a rectangular beam-shaped precast concrete waffle slab 4 composed of a plurality of pieces according to the third embodiment of the present invention is an inverted T precast concrete beam that first forms conical unevenness on the side. The
[0011]
As shown in FIGS. 13, 14, 15, and 16, the inverted U-shaped precast
[0012]
As shown in FIGS. 17, 18, 19, and 20, the half precast dish-type concrete waffle slab 6 of the fifth embodiment of the present invention has a thin plate 61 at the upper peripheral edge, and a
In this half precast dish type concrete waffle slab modeled embodiment, after molding, the shape shown in FIG. 19 is obtained. After transporting to the site, after fixing to each
The characteristics of the half precast dish-type concrete waffle slab are that it has sufficient strength and is lighter than a full precast concrete waffle slab. Therefore, both transportation and construction are superior to the full precast concrete waffle slab, and the connecting work of the reinforcing bars between the half precast plate type concrete waffle slabs is easier than the full precast concrete waffle slab. However, the disadvantage is that it requires a separate work such as placing concrete on site.
[0013]
Next, as shown in FIGS. 21, 22, 23, and 24, the rectangular precast concrete waffle slab 2 of the first embodiment of the present invention can be molded into a rectangular precast concrete waffle slab-like
Next, as shown in FIGS. 25, 26, 27, and 28, a rectangular precast concrete waffle slab 3 of a precast concrete waffle slab comprising an inverted T-type precast concrete beam auxiliary part and a square precast concrete waffle slab according to the second embodiment of the present invention. Can also be molded into a rectangular precast concrete waffle slab-
Further, as shown in FIGS. 29, 30, 31, and 32, the half precast dish-type concrete waffle slab 6 of the fifth embodiment of the present invention can be molded into a half precast dish-type concrete waffle slab-like
[0014]
【The invention's effect】
This invention manufactures the whole waffle slab layer which installs an apparatus, a processing machine, etc. in a hardware component manufacturing factory by a precast concrete construction method, and assembles a structure. Since the structure has sufficient strength, it is possible to achieve the safety of the structure that meets the needs of various equipment installations.
Furthermore, the construction work can be greatly shortened because the construction work such as the placement of reinforcing bars, concrete placement and the like can be shortened or made unnecessary, and the construction work can be reduced because the joining operation is easy. In this way, it is possible to accurately grasp the best time to secure profits, which is an important factor in the construction of a hardware component manufacturing factory.
In addition, since the structure is lightweight, it is highly convenient for transportation, and also has high fire and earthquake resistance.
[Brief description of the drawings]
FIG. 1 is a top view of a waffle slab layer according to a first embodiment of the present invention.
FIG. 2 is a side view of a waffle slab layer according to the first embodiment of the present invention.
FIG. 3 is a three-dimensional view of a waffle slab layer according to the first embodiment of the present invention.
FIG. 4 is a bottom three-dimensional view of a waffle slab layer according to the first embodiment of the present invention.
FIG. 5 is a top view of a waffle slab layer according to a second embodiment of the present invention.
FIG. 6 is a side view of a waffle slab layer according to a second embodiment of the present invention.
FIG. 7 is a three-dimensional view of a waffle slab layer according to a second embodiment of the present invention.
FIG. 8 is a bottom three-dimensional view of a waffle slab layer according to a second embodiment of the present invention.
FIG. 9 is a top view of a waffle slab layer according to a third embodiment of the present invention.
FIG. 10 is a side view of a waffle slab layer according to a third embodiment of the present invention.
FIG. 11 is a three-dimensional view of a waffle slab layer according to a third embodiment of the present invention.
FIG. 12 is a bottom three-dimensional view of a waffle slab layer according to a third embodiment of the present invention.
FIG. 13 is a top view of a waffle slab layer according to a fourth embodiment of the present invention.
FIG. 14 is a side view of a waffle slab layer according to a fourth embodiment of the present invention.
FIG. 15 is a three-dimensional view of a waffle slab layer according to a fourth embodiment of the present invention.
FIG. 16 is a bottom three-dimensional view of a waffle slab layer according to a first embodiment of the present invention.
FIG. 17 is a top view of a waffle slab layer according to a fifth embodiment of the present invention.
FIG. 18 is a side view of a waffle slab layer according to a fifth embodiment of the present invention.
FIG. 19 is a three-dimensional view of a waffle slab layer according to a fifth embodiment of the present invention.
FIG. 20 is a bottom three-dimensional view of a waffle slab layer according to a fifth embodiment of the present invention.
FIG. 21 is a top view of a waffle slab layer-like mutual body according to the first embodiment of the present invention.
FIG. 22 is a side view of a waffle slab layer-like mutual body according to the first embodiment of the present invention.
FIG. 23 is a three-dimensional view of a waffle slab layer-like mutual body according to the first embodiment of the present invention.
FIG. 24 is a bottom three-dimensional view of a waffle slab layer-like mutual body according to the first embodiment of the present invention.
FIG. 25 is a top view of a waffle slab layer-like mutual body according to a second embodiment of the present invention.
FIG. 26 is a side view of the waffle slab layer-like mutual body according to the second embodiment of the present invention.
FIG. 27 is a three-dimensional view of a waffle slab layer-like mutual body according to a second embodiment of the present invention.
FIG. 28 is a bottom three-dimensional view of a waffle slab layer-like mutual body according to a second embodiment of the present invention.
FIG. 29 is a top view of a waffle slab layer-like mutual body according to a fifth embodiment of the present invention.
FIG. 30 is a side view of a waffle slab layer-like mutual body according to a fifth embodiment of the present invention.
FIG. 31 is a three-dimensional view of a waffle slab layer-like mutual body according to a fifth embodiment of the present invention.
FIG. 32 is a bottom three-dimensional view of a waffle slab layer-like mutual body according to a fifth embodiment of the present invention.
[Explanation of symbols]
DESCRIPTION OF
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000320731A JP4267195B2 (en) | 2000-10-20 | 2000-10-20 | Construction method of hardware parts manufacturing factory etc. structure with precast concrete waffle slab layer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000320731A JP4267195B2 (en) | 2000-10-20 | 2000-10-20 | Construction method of hardware parts manufacturing factory etc. structure with precast concrete waffle slab layer |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002129686A JP2002129686A (en) | 2002-05-09 |
JP4267195B2 true JP4267195B2 (en) | 2009-05-27 |
Family
ID=18798964
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000320731A Expired - Lifetime JP4267195B2 (en) | 2000-10-20 | 2000-10-20 | Construction method of hardware parts manufacturing factory etc. structure with precast concrete waffle slab layer |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4267195B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577358A (en) * | 2018-12-28 | 2019-04-05 | 信息产业电子第十设计研究院科技工程股份有限公司 | A kind of clean room solves the implementation method of micro- vibration using wafer board |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6414686B2 (en) * | 2014-12-26 | 2018-10-31 | 清水建設株式会社 | Bonding structure in precast concrete floorboard |
KR101742538B1 (en) * | 2016-11-25 | 2017-06-01 | 에스케이하이닉스 주식회사 | Frame for clean room using grill beam |
KR101742539B1 (en) * | 2016-11-25 | 2017-06-01 | 에스케이하이닉스 주식회사 | Frame for clean room |
CN108678252A (en) * | 2018-07-06 | 2018-10-19 | 上海天华建筑设计有限公司 | A kind of method of construction of floor |
CN110453943A (en) * | 2019-08-13 | 2019-11-15 | 世源科技工程有限公司 | A kind of microvibration-preventing platform |
KR102326578B1 (en) * | 2020-12-16 | 2021-11-16 | 주식회사 아이엔지니어링 | PC slab with grid groove |
ES2942925B2 (en) * | 2022-12-15 | 2024-01-23 | Univ Madrid Politecnica | Module, system and method of manufacturing and assembly of an integrated modular post-tensioned ultra-high-performance fiber-reinforced concrete (UHPFRC) slab |
-
2000
- 2000-10-20 JP JP2000320731A patent/JP4267195B2/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577358A (en) * | 2018-12-28 | 2019-04-05 | 信息产业电子第十设计研究院科技工程股份有限公司 | A kind of clean room solves the implementation method of micro- vibration using wafer board |
Also Published As
Publication number | Publication date |
---|---|
JP2002129686A (en) | 2002-05-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4267195B2 (en) | Construction method of hardware parts manufacturing factory etc. structure with precast concrete waffle slab layer | |
JP2002339493A (en) | Precast concrete plate, its manufacturing method, and construction method of slab | |
KR20190036995A (en) | Grill beam structure of semiconductor factory and the construction method of it | |
JP6414679B2 (en) | Column beam frame structure, method of building column beam frame structure | |
KR101324884B1 (en) | Hybrid building construction method combining dry type and wet type | |
KR20100121865A (en) | Method for constructing building using prc integrating method | |
CN210529928U (en) | Prefabricated reinforced concrete convex support body for frame structure | |
JP6576204B2 (en) | Slab construction method | |
KR101866559B1 (en) | Construction technique of concrete structures through the Precast Concrete | |
JP2003239435A (en) | Reinforced-concrete void slab structure and its building method | |
JPH0334967Y2 (en) | ||
JP2018131899A (en) | PCa member | |
KR20010091701A (en) | Unit grille beam and construction method thereof | |
TWI769610B (en) | Reinforced structure of reinforced concrete structure by replacing part of steel bars with section steel | |
JPH0375704B2 (en) | ||
JPH0519383Y2 (en) | ||
JPS6043547A (en) | Mold frame and reinforcement iron integral assembling and constructing method | |
JP3358047B2 (en) | Manufacturing method of large slab and construction method of reinforced concrete sloping floor | |
JPS6195136A (en) | Construction of multistoried building skeletal by precast reinforced concrete unit | |
JP3072338B2 (en) | Method of manufacturing orthogonal precast beams | |
JPH08193422A (en) | Construction method for building | |
JPS63261037A (en) | Execution of waffle slab and lower constitution body of waffle slab | |
JP3152134U (en) | Reinforcement structure of cross beam that constitutes pier base | |
JPH068176Y2 (en) | Long precast concrete member | |
JPH0722413Y2 (en) | PC half slab version |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051202 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090203 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090218 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4267195 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120227 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120227 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150227 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: R3D02 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |